Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 14
CASE NO.:
Appeal (civil) 1940 of 2008
PETITIONER:
Gujarat Urja Vikash Nigam Ltd
RESPONDENT:
Essar Power Ltd
DATE OF JUDGMENT: 13/03/2008
BENCH:
H.K. Sema & Markandey Katju
JUDGMENT:
J U D G M E N T
CIVIL APPEAL NO 1940 OF 2008
[Arising out of S.L.P(C) No.2700 of 2007]
WITH
CIVIL APPEAL NO. 1941 OF 2008
[Arising out of S.L.P(C) No.675 of 2007]
MARKANDEY KATJU, J.
1. Leave granted.
2. This appeal by special leave has been filed against the judgment of the
learned Single Judge of the Gujarat High Court dated 15.6.2006 which was
passed on a petition under Section 11(5) and (6) of The Arbitration and
Conciliation Act, 1996 (hereinafter in short "the 1996 Act"). By that
judgment the High Court has appointed Hon’ble Mr. Justice A.M. Ahmadi,
retired Chief Justice of India, as the sole arbitrator for deciding certain
disputes between the parties.
3. Heard learned counsel for the parties and perused the record.
4. The appellant-company is engaged in the business of generation of
electrical energy. The appellant-company has its generation station at
Hazira, Surat. On 30th May, 1996 the appellant-company entered into a
power purchase agreement (hereinafter in short "the aforesaid agreement")
with the Gujarat Electricity Board. Under the aforesaid agreement the
parties agreed, inter alia, that out of the total generating capacity of 515MW
electricity the appellant-company would allocate 300MW electricity to the
Board and 215MW electricity to the Essar Group of Companies. Under
Clause 11 of the agreement the parties agreed that in the event any dispute
arose the same may be resolved by the parties by mutual agreement as
envisaged by Clause 11(1) of the aforesaid agreement. In the event of
failure to resolve the dispute by amicable settlement, the parties agreed that
such dispute be submitted to arbitration vide Clause 11(2).
5. In the meantime, under the Gujarat Electricity Industry
(Reorganization and Regulation) Act, 2003 published in the Gujarat
Government Gazette on 12th May, 2003 the assets and liabilities of the Board
were transferred to the appellant Nigam.
6. It appears that certain disputes had arisen between the parties mainly
in connection with the allocation of power to the Essar Group of Companies.
It is not in dispute that the respondent-company did not utilize its total
generating capacity to generate 515MW electricity. It also did not supply
300MW electricity to the Board as agreed. According to the Board, in the
event of the respondent-company generating less than its total generating
capacity of 515MW electricity under the aforesaid agreement, the
respondent-company was required to maintain a ratio of 300MW:215MW in
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 14
allocation of electrical energy to the Board and the Essar Group of
Companies respectively. The respondent-company, allegedly, did not
maintain the said ratio, and supplied more electricity to the Essar Group than
in accordance with the ratio of 300MW:215MW.
7. The respondent-company and the Board tried to settle the above
dispute amicably. The State Government also intervened in the matter but to
no avail. After protracted correspondence, on 14th November, 2005 the
respondent-company called upon the appellant-Nigam to refer the disputes
arising from the aforesaid agreement to the arbitrator Mr. Justice A.M.
Ahmadi, retired Chief Justice of India. On the other hand, the Nigam
approached the Gujarat Electricity Regulatory Commission, Ahmedabad
(hereinafter in short "the Commission") by Application No.873 of 2005
made under Section 86(1)(f) of the Electricity Act, 2003 (hereinafter in short
"the Act of 2003").
8. Since the Nigam did not send its approval for appointment of Mr.
Justice A.M. Ahmadi as arbitrator, the respondent-company approached the
Gujarat High Court by filing an application under Section 11(5) and (6) of
the 1996 Act, and by the impugned judgment dated 15.6.2006 the learned
Single Judge, Gujarat High Court, has appointed Mr. Justice A.M. Ahmadi,
retired Chief Justice of India, as the sole arbitrator for resolving the disputes.
Aggrieved, this appeal by special leave has been filed by the Nigam before
us.
9. Mr. K.K. Venugopal, learned senior counsel for the appellant, has
relied on Section 174 of the Act of 2003 which states :
"174. Act to have overriding effect \026 Save as
otherwise provided in section 173, the provisions of this
Act shall have effect notwithstanding anything
inconsistent therewith contained in any other law for the
time being in force or in any instrument having effect by
virtue of any law other than this Act."
10. He has also invited our attention to Section 173 of the Act of 2003
which states :
"173. Inconsistency in laws \026 Nothing contained
in this Act or any rule or regulation made thereunder or
any instrument having effect by virtue of this Act, rule or
regulation shall have effect in so far as it is inconsistent
with any other provisions of the Consumer Protection
Act, 1986 (68 of 1986) or the Atomic Energy Act, 1962
(33 of 1962) or the Railways Act, 1989 (24 of 1989)."
11. Mr. K.K. Venugopal submitted that a joint reading of these provisions
indicates that ordinarily the Act of 2003 will prevail over all other laws or
instruments, but the said Act will have to give way only to the Consumer
Protection Act, the Atomic Energy Act, or the Railways Act. In other
words, except for the aforementioned three Acts, the Act of 2003 will
prevail over all other laws and instruments.
12. Mr. K.K. Venugopal then invited our attention to Section 86(1) of the
Act of 2003 which states :
"86. Functions of State Commission (1) The
State Commission shall discharge the following function,
namely \026
(a) determine the tariff for generation, supply,
transmission and wheeling of electricity,
wholesale, bulk or retail, as the case may be,
within the State:
Provided that where open access has been
permitted to a category of consumers under section
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 14
42, the State Commission shall determine only the
wheeling charges and surcharge thereon, if any, for
the said category of consumers;
(b) regulate electricity purchase and
procurement process of distribution licensees
including the price at which electricity shall be
procured from the generating companies or
licensees or from other sources through
agreements for purchase of power for distribution
and supply within the State;
(c) facilitate intra-State transmission and
wheeling of electricity;
(d) issue licences to persons seeking to act as
transmission licensees, distribution licensees and
electricity traders with respect to their operations
within the State;
(e) promote cogeneration and generation of
electricity from renewable sources of energy by
providing suitable measures for connectivity with
the grid and sale of electricity to any person, and
also specify, for purchase of electricity from such
sources, a percentage of the total consumption of
electricity in the area of a distribution licensee;
(f) adjudicate upon the disputes between the
licensees and generating companies and to refer
any dispute for arbitration;
(g) levy fee for the purposes of this Act;
(h) specify State Grid Code consistent with the
Grid Code specified under clause (h) of sub-
section (1) of section 79;
(i) specify or enforce standards with respect to
quality, continuity and reliability of service by
licensees;
(j) fix the trading margin in the intra-
State trading of electricity, if considered,
necessary;
(k) discharge such other functions as may be
assigned to it under this Act."
13. Learned counsel for the appellant submitted that Section 86(1)(f) of
the Act of 2003 clearly indicates that the disputes between the licensees and
generating companies can only be adjudicated upon by the State
Commission, either itself or by an arbitrator to whom the Commission refers
the dispute. Hence he submitted that the High Court cannot refer disputes
between licensees and generating companies to an arbitrator since such
power of adjudication or reference to an arbitrator has been specifically
given to the State Commission.
14. Shri K.K. Venugopal also relied on Section 158 of the Act of 2003
which states :
"158. Arbitration \026 Where any matter is, by or
under this Act, directed to be determined by arbitration,
the matter shall, unless it is otherwise expressly provided
in the licence of a licensee, be determined by such person
or persons as the Appropriate Commission may nominate
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 14
in that behalf on the application of either party; but in all
other respects the arbitration shall be subject to the
provisions of the Arbitration and Conciliation Act, 1996
(26 of 1996)."
15. Shri K.K. Venugopal also relied on Section 2(3) of the 1996 Act
which states :
"2(3) \026 This part shall not affect any other law for
the time being in force by virtue of which certain
disputes may not be submitted to arbitration."
16. Shri Venugopal submitted that Section 11 of the 1996 Act has no
application because the Act of 2003 has provided for arbitration of
disputes between licensees and generating companies by the Commission or
its nominated arbitrator. Since the Electricity Act is a special law dealing
with arbitrations of disputes between licensees and the generating
companies, he submitted that the general provision in Section 11 of the
Arbitration and Conciliation Act, 1996 will not apply for appointing an
arbitrator for such disputes in view of the maxim Generalia specialibus non
derogant (vide G.P. Singh’s ‘Principles of Statutory Interpretation’, 9th
Edition, 2004 page 133).
17. Shri K.K. Venugopal submitted that in view of Section 86(1)(f) of the
Act of 2003 it is only the State Commission or its nominee which can
adjudicate upon disputes between licensees and generating companies.
Hence he submitted that the impugned judgment of the High Court referring
the dispute to an arbitrator was illegal, since the High Court has no such
power.
18. On the other hand Shri F.S. Nariman, learned senior counsel for the
respondent, has invited our attention to the agreement between the parties
dated 30.5.1996. The relevant part of the agreement is Article 11 which
states:
"ARTICLE 11
ARBITRATION
11.1 RESOLUTION OF DISPUTES :
Except as otherwise provided in this Agreement, any
disagreement dispute controversy or claim (the
"Dispute") between the Board and the Company in
connection with or arising out of this Agreement, the
Parties shall attempt to settle such Dispute in the first
instance within thirty days by discussion between the
Com[any and the Board in the following manner :
(a) Each Party shall designate in writing to the other
Party a representative who shall be authorized to
resolve any dispute arising under this Agreement
in an equitable manner.
(b) If the designated representatives are unable to
resolve the dispute under this Agreement within 15
days, such dispute shall be referred by such
representatives to a senior officer designated by
the Company and a senior officer designated by
the Board respectively, who shall attempt to
resolve the Dispute within a further period of 15
days.
(c) The Parties hereto agree to use their best efforts to
attempt to resolve all Disputes arising hereunder
promptly equitably and in good faith and further
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 14
agree to, provide each other with reasonable access
during normal business hours to any records,
information and data pertaining to any such
Dispute.
11.2 ARBITRATION
In the event that any Dispute is not resolved between the
Parties pursuant to Article 11.1 then such Dispute shall
be settled exclusively and finally by Arbitration. It is
specifically understood and agreed that any Dispute that
cannot be resolved between the Parties, including any
matter relating to the interpretation of this Agreement,
shall be submitted to Arbitration irrespective of the
magnitude thereof and the amount in dispute or whether
such Dispute would otherwise be considered justifiable
or ripe for resolution by any Court. This Agreement and
the rights and obligations of the Parties hereunder shall
remain in full force and effect pending the award in such
Arbitration proceedings. The award shall determine
whether and when Termination of this Agreement, if
relevant, shall become effective.
The Arbitration shall be in accordance with the Indian
Arbitration and Conciliation Ordinance, 1996 or such
modifications or re-enactment thereof.
11.3 NUMBER OF ARBITRATORS
The arbitral tribunal shall consist either (a) of sole
Arbitrator mutually agreed upon or (b) of three (3)
(Arbitrators \026 One each to be chosen by each Party and
third person to be selected by two Arbitrators so chosen
before commencement of arbitration proceedings to act
as an Umpire/third Arbitrator.
11.4 PLACE OF ARBITRATION
The arbitration shall be conducted at Baroda.
11.5 FINALITY AND ENFORCEMENT OF
AWARD
The arbitral tribunal shall give reasoned decision or
award which shall be final and binding upon the Parties.
The Parties hereto agree that the arbitral award may be
enforced against the Parties to the arbitration proceeding
or their assets wherever they may be found and that a
judgment upon the arbitral award may be entered in any
Court which shall have jurisdiction over the matter."
19. Shri F.S. Nariman invited our attention to Section 175 of the Act of
2003 which states :
"175. Provisions of this Act to be in addition to
and not in derogation of other laws \026 The provisions of
this Act are in addition to and not in derogation of any
other law for the time being in force."
20. In view of the above provision, Shri Nariman submitted that the Act
of 2003 does not prohibit the application of the provisions of the Act of 1996
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 6 of 14
including Section 11 thereof. Hence he submitted that a reference can be
made by the Court under Section 11(5) and (6) of the said Act of disputes
between licensees and generating companies. Accordingly he submitted, the
High Court order was valid.
21. It appears that the respondent Essar Power limited was obliged under
its agreement with the Gujarat Electricity Board to supply power to the
Board and the Essar Steel Limited in the ratio of 300MW:215MW. The
grievance of the Board (now the Nigam) was that the Essar Power Limited
has diverted energy which was to be supplied to the Board to the Essar Steel
Limited. Hence the Board vide its letter dated 29.10.2003 raised a demand
of Rs.537 crores upon Essar Power Limited for diverting the said energy.
On the other hand, Essar Power Limited disputed the said claim by its reply
dated 1.11.2003 and stated that the Board had not honoured its commitment
under the agreement regarding payment to it. The Board, thereafter, raised
further claims against Essar Power Limited.
22. The appellant company then approached the Gujarat Electricity
Regulatory Commission under Section 86(1)(f) of the Electricity Act, 2003
whereas Essar Power Limited filed a petition in the Gujarat High Court
under Section 11(5) and (6) of the Arbitration and Conciliation Act, 1996 in
which the impugned order was passed.
23. It may be mentioned that before filing the petition in the High Court
the respondent Essar Power Limited sent a notice dated 14.11.2005 invoking
the arbitration clause and nominating Mr. Justice A.M. Ahmadi as the sole
Arbitrator in terms of Article 11 of the agreement, and called upon the
Nigam to concur to the said nomination or suggest its own nominee within
thirty days. Instead of concurring to the nominee suggested by the company
or suggesting its own nominee, the Nigam vide its letter dated 5.12.2005
denied that the dispute can be resolved by appointing an Arbitrator under
Section 11 of the Act of 1996. The Nigam contended that only the State
Commission can adjudicate the dispute under Section 86(1)(f) of the Act of
2003, or refer the matter to an arbitrator.
24. The main question before us is whether the application under Section
11 of the Act of 1996 is maintainable in view of the statutory specific
provisions contained in the Electricity Act of 2003 providing for
adjudication of disputes between the licensee and the generating companies.
25. In our opinion, the submission of Mr. K.K. Venugopal has to be
accepted.
26. It may be noted that Section 86(1)(f) of the Act of 2003 is a special
provision for adjudication of disputes between the licensee and the
generating companies. Such disputes can be adjudicated upon either by the
State Commission or the person or persons to whom it is referred for
arbitration. In our opinion the word ‘and’ in Section 86(1)(f) between the
words ’generating companies’ and ‘to refer any dispute for arbitration’
means ‘or’. It is well settled that sometimes ‘and’ can mean ‘or’ and
sometimes ‘or’ can mean ‘and’ (vide G.P. Singh’s ‘Principle of Statutory
Interpretation’ 9th Edition, 2004 page 404.)
27. In our opinion in Section 86(1)(f) of the Electricity Act, 2003 the
word ‘and’ between the words ‘generating companies’ and the words ‘refer
any dispute’ means ‘or’, otherwise it will lead to an anomalous situation
because obviously the State Commission cannot both decide a dispute itself
and also refer it to some Arbitrator. Hence the word ‘and’ in Section
86(1)(f) means ‘or’.
28. Section 86(1)(f) is a special provision and hence will override the
general provision in Section 11 of the Arbitration and Conciliation Act, 1996
for arbitration of disputes between the licensee and generating companies. It
is well settled that the special law overrides the general law. Hence, in our
opinion, Section 11 of the Arbitration and Conciliation Act, 1996 has no
application to the question who can adjudicate/arbitrate disputes between
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 7 of 14
licensees and generating companies, and only Section 86(1)(f) shall apply in
such a situation.
29. This is also evident from Section 158 of the Electricity Act, 2003
which has been quoted above. We may clarify that the agreement dated
30.5.1996 is not a part of the licence of the licensee. An agreement is
something prior to the issuance of a licence. Hence any provision for
arbitration in the agreement cannot be deemed to be a provision for
arbitration in the licence. Hence also it is the State Commission which alone
has power to arbitrate/adjudicate the dispute either itself or by appointing an
arbitrator.
30. Shri Jayant Bhushan, learned counsel for one of the parties in the
connected case submitted that Section 86(1)(f) is violative of Article 14 of
the Constitution of India because it does not specify when the State
Commission shall itself decide a dispute and when it will refer the matter to
arbitration by some arbitrator. In our opinion there is no violation of Article
14 at all. It is in the discretion of the State Commission whether the dispute
should be decided itself or it should be referred to an arbitrator. Some
leeway has to be given to the legislature in such matters and there has to be
judicial restraint in the matter of judicial review of constitutionality of a
statute vide Government of Andhra Pradesh & Ors. vs. Smt. P. Laxmi
Devi JT 2008(2) 8 SC 639. There are various reasons why the State
Commission may not decide the dispute itself and may refer it for arbitration
by an arbitrator appointed by it. For example, the State Commission may be
overburdened and may not have the time to decide certain disputes itself,
and hence such cases can be referred to an arbitrator. Alternatively, the
dispute may involve some highly technical point which even the State
Commission may not have the expertise to decide, and such dispute in such
a situation can be referred to an expert arbitrator. There may be various
other considerations for which the State Commission may refer the dispute
to an arbitrator instead of deciding it itself. Hence there is no violation of
Article 14 of the Constitution of India.
31. We may now deal with the submission of Mr. Fali S. Nariman that in
view of Section 175 of the Electricity Act, 2003, Section 11 of the
Arbitration and Conciliation Act, 1996 is also available for arbitrating
disputes between licensees and generating companies.
32. Section 175 of the Electricity Act, 2003 states that the provisions of
the Act are in addition to and not in derogation of any other law. This would
apparently imply that the Arbitration and Conciliation Act, 1996 will also
apply to disputes such as the one with which we are concerned. However, in
our opinion Section 175 has to be read along with Section 174 and not in
isolation.
33. Section 174 provides that the Electricity Act, 2003 will prevail over
anything inconsistent in any other law. In our opinion the inconsistency may
be express or implied. Since Section 86(1)(f) is a special provision for
adjudicating disputes between licensees and generating companies, in our
opinion by implication Section 11 of the Arbitration and Conciliation Act,
1996 will not apply to such disputes i.e. disputes between licensees and
generating companies. This is because of the principle that the special law
overrides the general law. For adjudication of disputes between the
licensees and generating companies there is a special law namely 86(1)(f) of
the Electricity Act, 2003. Hence the general law in Section 11 of the
Arbitration and Conciliation Act, 1996 will not apply to such disputes.
34. It is well settled that where a statute provides for a thing to be done in
a particular manner, then it has to be done in that manner, and in no other
manner, vide Chandra Kishore Jha vs. Mahavir Prasad, AIR 1999 SC
3558 (para 12), Dhananjaya Reddy vs. State of Karnataka, AIR 2001
SC 1512 (para 22), etc. Section 86(1)(f) provides a special manner of
making references to an arbitrator in disputes between a licensee and a
generating company. Hence by implication all other methods are barred.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 8 of 14
35. At first glance there is an apparent inconsistency between Section 175
and Section 174 of the Electricity Act, 2003. While Section 174 says that
the said Act will prevail over other laws, Section 175 says that the said Act
is in addition and not in derogation of any other law (which would include
Section 11 of the Arbitration and Conciliation Act, 1996.)
36. In our opinion to resolve this conflict the Mimansa principles of
Interpretation would of great utility.
37. It is deeply regrettable that in our Courts of law, lawyers quote
Maxwell and Craies but nobody refers to the Mimansa Principles of
Interpretation. Today many of our educated people are largely unaware
about the great intellectual achievements of our ancestors and the intellectual
treasury they have bequeathed us. The Mimansa Principles of Interpretation
is part of that intellectual treasury but it is distressing to note that apart from
a reference to these principles in the judgment of Sir John Edge, the then
Chief Justice of Allahabad High Court in Beni Prasad vs. Hardai Devi,
(1892) ILR 14 All 67 (FB), and some judgments by one of us (M. Katju, J.)
there has been almost no utilization of these principles even in our own
country.
38. It may be mentioned that the Mimansa Rules of Interpretation were
our traditional principles of interpretation laid down by Jaimini, whose
Sutras were explained by Shabar, Kumarila Bhatta, Prabhakar, etc. These
Mimansa Principles were regularly used by our great jurists like
Vijnaneshwara (author of Mitakshara), Jimutvahana (author of Dayabhaga),
Nanda Pandit, etc. whenever they found any conflict between the various
Smritis or any ambiguity, incongruity, or casus omissus therein. There is no
reason why we cannot use these principles on appropriate occasions.
However, it is a matter of deep regret that these principles have rarely been
used in our law Courts. It is nowhere mentioned in our Constitution or any
other law that only Maxwell’s Principles of Interpretation can be used by the
Court. We can use any system of interpretation which helps us resolve a
difficulty. In certain situations Maxwell’s principles would be more
appropriate, while in other situations the Mimansa principles may be more
suitable.
39. The Mimansa principles of interpretation were created for resolving
the practical difficulties in performing the yagyas. The rules for performing
the various yagyas were given in books called the Brahmanas (all inSanskrit)
e.g. Shatapath Brahmana, Aitareya Brahmana, Taitareya Brahmana, etc.
There were many ambiguities, obscurities, conflicts etc. in the Brahmana
texts, and hence the Mimansa Principles of Interpretation were created for
resolving these difficulties.
40. Although the Mimansa principles were created for religious purpose,
they were so rational and logical that they subsequently began to be used in
law, grammar, logic, philosophy, etc. i.e. they became of universal
application. The books on Mimansa are all in Sanskrit, but there is a good
book in English by Prof. Kishori Lal Sarkar called ‘The Mimansa Rules of
Interpretation’ published in the Tagore Law Lecture Series, which may be
seen by anyone who wishes to go deeper into the subject.
41. In the Mimansa system there are three ways of dealing with conflicts
which have been fully discussed by Shabar Swami in his commentary on
Sutra 14, Chapter III, Book III of Jaimini.
(1) Where two texts which are apparently conflicting are capable of being
reconciled, then by the Principle of Harmonious Construction (which is
called the Samanjasya Principle in Mimansa) they should be reconciled.
The Samanjasya Principle has been laid down by Jaimini in Chapter II, Sutra
9 which states :
"The inconsistencies asserted are not actually
found. The conflicts consist in difference of application.
The real intention is not affected by application.
Therefore, there is consistency."
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 9 of 14
42. The Samanjasya axiom is illustrated in the Dayabhag. Jimutvahana
found that there were two apparently conflicting texts of Manu and
Yajnavalkya. The first stated "a son born after a division shall alone take the
paternal wealth". The second text stated "sons, with whom the father has
made a partition, should give a share to the son born after the distribution".
Jimutvahana, utilizing the Samanjasya principle of Mimansa, reconciled
these two texts by holding that the former applies to the case of property
which is the self-acquired property of the father, and the latter applies to the
property descended from the grand-father.
43. One of the illustrations of the Samanjasya principle is the maxim of
lost horses and burnt chariot (Nashtashvadaghda Ratha Nyaya). This is
based on the story of two men traveling in their respective chariots and one
of them losing his horses and the other having his chariot burnt through the
outbreak of fire in the village in which they were putting up for the night.
The horses that were left were harnessed to the remaining chariot and the
two men pursued their journey together. Its teaching is union for mutual
advantage, which has been quoted in the 16th Vartika to Panini, and is
explained by Patanjali. It is referred to in Kumarila Bhatta’s Tantra Vartika.
(2) The second situation is a conflict where it is impossible to reconcile
the two conflicting texts despite all efforts. In this situation the Vikalpa
principle applies, which says that whichever law is more in consonance with
reason and justice should be preferred. However, conflict should not be
readily assumed and every effort should be made to reconcile conflicting
texts. It is only when all efforts of reconciliation fail that the Vikalpa
principle is to be resorted to.
(3) There is a third situation of a conflict and this is where there are two
conflicting irreconciliable texts but one overrides the other because of its
greater force. This is called a Badha in the Mimansa system (similar to the
doctrine of ultra vires). The great Mimansa scholar Sree Bhatta Sankara in
his book ‘Mimansa Valaprakasha’ has given several illustrations of Badha as
follows :
"A Shruti of a doubtful character is barred by a
Shruti which is free from doubt. A Linga which is more
cogent bars that which is less cogent. Similarly a Shruti
bars a Smriti. A Shruti bars Achara (custom) also. An
absolute Smriti without reference to any popular reason
bars one that is based upon a popular reason. An
approved Achara bars an unapproved Achara. An
unobjectionable Achara bars an objectionable Achara. A
Smriti of the character of a Vidhi bars one of the
character of an Arthavada. A Smriti of a doubtful
character is barred by one free from doubts. That which
serves a purpose immediately bars that which is of a
remote service. That which is multifarious in meaning is
barred by that which has a single meaning. The
application of a general text is barred by a special text. A
rule of procedure is barred by a mandatory rule. A
manifest sense bars a sense by context. A primary sense
bars a secondary sense. That which has a single
indication is preferable to what has many indications. An
indication of an inherent nature bars one which is not so.
That which indicates an action is to be preferred to what
merely indicates a capacity. If you can fill up an ellipse
by an expression which occurs in a passage, you cannot
go beyond it."
(emphasis supplied)
44. The principle of Badha is discussed by Jaimini in the tenth chapter of
his work. Badha primarily means barring a thing owing to inconsistency.
Jaimini uses the principle of Badha mainly with reference to cases where
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 10 of 14
Angas or sub-ceremonies are to be introduced from the Prakriti Yagya (i.e. a
yagya whose rules for performance are given in detail in the Brahmanas)
into a Vikriti (i.e. a yagya whose rules of performance are not mentioned
anywhere, or are incompletely mentioned). In such a case, though the Angas
or the sub-ceremonies are to be borrowed from the Prakriti Yagya, those of
the sub-ceremonies which prove themselves to be inconsistent with or out of
place in the Vikriti Yagya, are to be omitted.
45. For example, in the Rajsuya Yagya, certain homas are prescribed, for
the proper performance of which one must borrow details from the
Darshapaurnamasi Yagya. In the Rajsuya Yagya, plain ground is directed to
be selected as the Vedi for the homas, while in the case of the
Darshapaurnamasi, the Vedi should be erected by digging the ground with
spade etc. Such an act would be out of place in constructing the Vedi for the
homas in the Rajsuya Yagya. Here, there is a Badha (bar) of the particular
rule regarding the erection of the Vedi in the Darshapaurnamasi Yagya,
being extended to the Rajsuya Yagya. This is the case of Badha by reason
of express text.
46. There are other instances in which the inconsistency arises
incidentally. For example, in the Sadyaska there is no need of cutting the
peg with which the animal is to be tied. But, in the Agni-Somiya Yagya
which is the Prakriti of the Sadyaska Yagya, reciting of certain Mantras is
prescribed in connection with the cutting of the peg. This recital being out
of place in the former Yagya is barred in carrying the Atidesha process.
Numerous other illustrations can be given. For example, in the Satra Yagya
the selection of Rittik is out of place and so omitted, though this is done in
the Soma Yagya of which the Satra is the Vikriti. The Krishnala Nyaya
(black bean maxim) is another instance. In cases where Atidesha is to be
made by implication, it is altogether barred, if there is an express text against
making the implication.
47. When there is a negative ordinance prohibiting a thing, it is to prevail
notwithstanding that there is an Atidesha which by implication enjoins the
thing. For instance, there is a rule that all sacrifices partake of the character
of Darsha and Paurnamasi Yagyas. The result is that all the rules of Darsha
and Paurnamasi Yagyas are applicable to the Pasu Yagya also. But there is a
text which says that the Aghara and the Ajyabhaga homas need not be made
in the Pasu Yagya. Therefore, these homas need not be made in the Pasu
Yagya, though in the absence of the prohibitory text they would have to be
made on account of the rule which lays down that all Yagyas must partake
of the character of Darsha and paurnamasi.
48. One of the Mimansa principles is the Gunapradhan Axiom, and since
we are utilizing it in this judgment (apart from the badha and samanjasya
principles) we may describe it in some detail.
49. ‘Guna’ means subordinate or accessory, while ‘Pradhan’ means
principal. The Gunapradhan Axiom states :
"If a word or sentence purporting to express a
subordinate idea clashes with the principal idea, the
former must be adjusted to the latter or must be
disregarded altogether."
This principle is also expressed by the popular
maxim known as matsya nyaya i.e. ‘the bigger fish eats
the smaller fish’.
According to Jaimini, acts are of two kind,
principal and subordinate (see Jaimini 2 : 1 : 6).
In Sutra 3 : 3 : 9 Jaimini states :
xq.keq[;O;frdzes rnFkZRokr
eq[;su osn la;ksx%
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 11 of 14
Kumarila Bhatta, in his Tantravartika (See
Ganganath Jha’s English Translation Vol.3, page 1141)
explains this Sutra as follows :
"When the Primary and the Accessory
belong to two different Vedas, the Vedic
characteristic of the Accessory is determined
by the Primary, as the Accessory is
subservient to the purpose of the primary."
It is necessary to explain this Sutra in some detail.
The peculiar quality of the Rigveda and Samaveda is that
the mantras belonging to them are read aloud, whereas
the mantras in the Yajurveda are read in a low voice.
Now the difficulty arose about certain ceremonies, e.g.
Agnyadhana, which belong to the Yajurveda but in which
verses of the Samveda are to be recited. Are these
Samaveda verses to be recited in a low voice or loud
voice? The answer, as given in the above Sutra, is that
they are to be recited in low voice, for although they are
Samavedi verses, yet since they are being recited in a
Yajurveda ceremony their attribute must be altered to
make it in accordance with the Yajurveda.
Commenting on Jaimini 3 : 3 : 9 Kumarila Bhatta
says :
"The Siddhanta (principle) laid down
by this Sutra is that in a case where there is
one qualification pertaining to the Accessory
by itself and another pertaining to it through
the Primary, the former qualification is
always to be taken as set aside by the latter.
This is because the proper fulfillment of the
Primary is the business of the Accessory
also as the latter operates solely for the sake
of the former. Consequently if, in
consideration of its own qualification it were
to deprive the Primary of its natural
accomplishment then there would be a
disruption of that action (the Primary) for
the sake of which it was meant to operate.
Though in such a case the proper fulfillment
of the Primary with all its accompaniments
would mean the deprival of the Accessory of
its own natural accompaniment, yet, as the
fact of the Accessory being equipped with
all its accompaniments is not so very
necessary (as that of the primary), there
would be nothing incongruous in the said
deprival". See Ganganath Jha’s English
translation of the Tantravartika, Vol.3 page
1141.
50. In our opinion the gunapradhan axiom applies to this case. Section
174 is the pradhan whereas Section 175 is the guna (or subordinate). If we
read Section 175 in isolation then of course we would have to agree to Mr.
Nariman’s submission that Section 11 of the Arbitration and Conciliation
Act, 1996 applies. But we cannot read Section 175 in isolation, we have to
read it along with Section 174, and reading them together, we have to adjust
Section 175 (the guna or subordinate) to make it in accordance with Section
174 (the pradhan or principal). For doing so we will have to add the
following words at the end of Section 175 "except where there is a conflict,
express or implied, between a provision in this Act and any other law, in
which case the former will prevail".
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 12 of 14
51. No doubt ordinarily the literal rule of interpretation should be
followed, and hence the Court should neither add nor delete words in a
statute. However, in exceptional cases this can be done where not doing so
would deprive certain existing words in a statute of all meaning, or some
part of the statute may become absurd.
52. In the chapter on ‘Exceptional Construction’ in his book on
‘Interpretation of Statutes’ Maxwell writes :
"Where the language of a statute, in its ordinary
meaning and grammatical construction leads to a
manifest contradiction of the apparent purpose of the
enactment, or to some inconvenience or absurdity,
hardship or injustice, presumably not intended, a
construction may be put upon it which modifies the
meaning of the words, and even the structure of the
sentence. This may be done by departing from the rules
of grammar, by giving an unusual meaning to particular
words, by altering their collocation, by rejecting them
altogether, or by interpolating other words, under the
influence, no doubt, of an irresistible conviction that the
legislature could not possibly have intended what the
words signify, and that the modifications thus made are
mere corrections of careless language and really give the
true intention."
53. Thus, in S.S. Kalra vs. Union of India 1991(2) SCC 87, this Court
has observed that sometimes courts can supply words which have been
accidentally omitted.
54. In G.P. Singh’s ‘Principles of Statutory Interpretation’ Ninth Edition,
2004 at pages 71-74 several decisions of this Court and foreign Courts have
been referred to where the Court has added words to a statute (though
cautioning that normally this should not be done).
55. Hence we have to add the aforementioned words at the end of Section
175 otherwise there will be an irreconciliable conflict between Section 174
and Section 175.
56. In our opinion the principle laid down in Section 174 of the Electricity
Act, 2003 is the principal or primary whereas the principle laid down in
Section 175 is the accessory or subordinate to the principal. Hence Section
174 will prevail over Section 175 in matters where there is any conflict (but
no further).
57. In our opinion Section 174 and Section 175 of the Electricity Act,
2003 can be read harmoniously by utilizing the Samanjasya, Badha and
Gunapradhana principles of Mimansa. This can be done by holding that
when there is any express or implied conflict between the provisions of the
Electricity Act, 2003 and any other Act then the provisions of the Electricity
Act, 2003 will prevail, but when there is no conflict, express or implied, both
the Acts are to be read together.
58. In the present case we have already noted that there an implied
conflict between Section 86(1)(f) of the Electricity Act, 2003 and Section 11
of the Arbitration and Conciliation Act, 1996 since under Section 86(1)(f)
the dispute between licensees and generating companies is to be decided by
the State Commission or the arbitrator nominated by it, whereas under
Section 11 of the Arbitrary and Conciliation Act, 1996, the Court can refer
such disputes to an arbitrator appointed by it. Hence on harmonious
construction of the provisions of the Electricity Act, 2003 and the
Arbitration and Conciliation Act, 1996 we are of the opinion that whenever
there is a dispute between a licensee and the generating companies only the
State Commission or Central Commission (as the case may be) or arbitrator
(or arbitrators) nominated by it can resolve such a dispute, whereas all other
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 13 of 14
disputes (unless there is some other provision in the Electricity Act, 2003)
would be decided in accordance with Section 11 of the Arbitration and
Conciliation Act, 1996. This is also evident from Section 158 of the
Electricity Act, 2003. However, except for Section 11 all other provisions of
the Arbitration and Conciliation Act, 1996 will apply to arbitrations under
Section 86(1)(f) of the Electricity Act, 2003 (unless there is a conflicting
provision in the Electricity Act, 2003, in which case such provision will
prevail.)
59. In the present case, it is true that there is a provision for arbitration in
the agreement between the parties dtd. 30.5.1996. Had the Electricity Act,
2003 not been enacted, there could be no doubt that the arbitration would
have to be done in accordance with the Arbitration and Conciliation Act,
1996. However, since the Electricity Act, 2003 has come into force w.e.f.
10.6.2003, after this date all adjudication of disputes between licensees and
generating companies can only be done by the State Commission or the
arbitrator (or arbitrators) appointed by it. After 10.6.2003 there can be no
adjudication of dispute between licensees and generating companies by
anyone other than the State Commission or the arbitrator (or arbitrators)
nominated by it. We further clarify that all disputes, and not merely those
pertaining to matters referred to in clauses (a) to (e) and (g) to (k) in Section
86(1), between the licensee and generating companies can only be resolved
by the Commission or an arbitrator appointed by it. This is because there is
no restriction in Section 86(1)(f) about the nature of the dispute.
60. We make it clear that it is only with regard to the authority which can
adjudicate or arbitrate disputes that the Electricity Act, 2003 will prevail
over Section 11 of the Arbitration and Conciliation Act, 1996. However, as
regards, the procedure to be followed by the State Commission (or the
arbitrator nominated by it) and other matters related to arbitration (other than
appointment of the arbitrator) the Arbitration and Conciliation Act, 1996
will apply (except if there is a conflicting provision in the Act of 2003). In
other words, Section 86(1)(f) is only restricted to the authority which is to
adjudicate or arbitrate between licensees and generating companies.
Procedural and other matters relating to such proceedings will of course be
governed by Arbitration and Conciliation Act, 1996, unless there is a
conflicting provision in the Act of 2003.
61. Since the High Court has appointed an arbitrator for deciding the
dispute between the licensee and the generating company, in our opinion, the
judgment of the High Court has to be set aside. Only the State Commission
or the arbitrator (or arbitrators) appointed by it could resolve such a dispute.
We, therefore, set aside the impugned judgment of the High Court but leave
it open to the State Commission or the Arbitrator (or Arbitrators) nominated
by it to adjudicate/arbitrate the dispute between the parties expeditiously.
Appeal allowed. The impugned judgment set aside.
62. Case No.873 of 2005 filed by the appellant under Section 86(1)(f) of
the Electricity Act, 2003 before the Gujarat Electricity Regulatory
Commission, is still pending. Since the matter is pending from 2005, we
direct the Gujarat Electricity Regulatory Commission to dispose of the
petition as expeditiously as possible preferably within six months.
C.A. No........../2008 [Arising out of S.L.P(C) No.675/2007]
63. This appeal is filed regarding the deduction of Rs.5 crores. The
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 14 of 14
appellant may file application under Section 94(2) of the Electricity Act,
2003 before the appropriate Commission, to pass such an interim order, as
may consider appropriate. This appeal is, accordingly, dismissed.