Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 5
PETITIONER:
RAM NATH INTERNATIONAL CONSTRUCTION PVT. LTD.
Vs.
RESPONDENT:
STATE OF U.P.
DATE OF JUDGMENT: 21/10/1997
BENCH:
SUJATA V. MANOHAR, D.P. WADHWA
ACT:
HEADNOTE:
JUDGMENT:
[with Civil Appeal No 7375 of 1997 [arising out of SLP[c)
No. 20055 of 1997 (cc 6248/97}]
J U D G M E N T
Mrs. Sujata V. Manohar, J.
Delay in filing S.L.P.(c) No. 20055 /97 (cc 6248) is
condoned.
Leave in both the petitions is granted.
These cross appeals arise from a common judgment of the
Allahabad High Court. For the sake of convenience, the
appellant, M/s. Ram Nath International Construction Pvt.
Ltd., in the appeal arising from S.L.P.(C) No. 4328 of 1997
is referred to as the appellant while the State of U.P. is
referred to as the respondent.
The appellant entered into an agreement with the
respondent dated 17.2.1989 for the work o lining of the
Upper Ganga Canal from kilometres 189.50 to 197.00 at
Gesupur in Bulandshahr. The total amount payable to the
appellant under the agreement was Rs. 4,81,4,312. Clause 32
of the tender which related to "Extra Items" stated, "Extra
terms of work shall not vitiate the contract. The
contractor shall be bound to execute extra items of work as
directed by the Engineer Incharge. The rates of extra items
are to be mutually agreed". Clause 51 which provides for
arbitration is as follows:
"ARBITRATION:
All the disputes in respect of
which the decision has not been
final and conclusive shall be
referred for arbitration to a sole
arbitrator appointed as follows.
The arbitration shall be conducted
in accordance with the provisions
of the Indian Arbitration Act, 1940
or any statutory modification
thereof. The decision of the
arbitrator shall be final and
binding on the parties thereto.
The arbitrator shall determine the
amount of costs of arbitration to
be awarded to either parties.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 5
Performance under the contract
shall continue during the
arbitration proceedings and
payments due to the contractor by
the owner shall not be withheld
unless they are the subject matter
of the arbitration proceedings.
All award shall be in writing and
in case of awards amounting to Rs.
100 lakhs above, such awards shall
state reasons for the amounts
awarded.
Neither party is entitled to bring
a claim to arbitration if the
arbitrator has not been appointed
before the expiration of thirty
days after defect liability
period."
Disputes arose between the appellant and the respondent
in connection with the execution of the work specified in
the tender as also in relation to payment for extra items of
work. Ultimately by an Office Memorandum dated October 4,
1992 disputes between the parties were referred to the sole
arbitration of Shri Thakur Das, Chief Engineer, Design and
Research, I.D.U.P., Lucknow. The terms of reference as
recorded in the Office Memorandum are as follows:-
"as such Shri Thakur Das, Chief
Engineer, Design and Research,
I.D., U.P., Lucknow is hereby
appointed as Arbitrator for the
following claims as raised by the
contractor vide his letter dated
13.12.1991 against the agreement
No.B2-02A-033 dated 17.2.1989
according to para 51 of the
Agreement.
i) Rate for extra item of earth
work beyond lip cutting in reach
km. 189.50 to km.190.70.
ii) Bailing out of standing water.
iii) Earth work beyond lip cutting
in reach km.190.70 to km. 197.00.
iv) Claims of idle labour due to
non supply of cement."
The arbitrator has given a detailed speaking award
dated 23.5.1994 under which, inter alia, in respect of the
extra item of earth work beyond lip cutting in reach km
189.50 to km.190.70. the arbitrator has awarded a sum of Rs.
72.22.740/. The arbitrator has also awarded to the appellant
interest at the rate of 18% per annum on the total amount of
claim (Rs. 1,71,11,208/-) with effect from 1.1.1991 to the
date of the award and further interest at the rate of 6% per
annum of the said amount from the date of the award till the
date of the decree or payment whichever is earlier.
The appellant applied for a decree in terms of the
award while the respondent filed objections. The District
Judge granted decree in terms of the award. In the appeal
which was filed before the High Court, the High Court has,
inter alia. disallowed the claim for extra earth work beyond
lip cutting in the reach 189.50 to 190.70 kms. on the ground
that the arbitrator travelled beyond the scope of his
reference in granting the said amount. The appeal of the
appellant before us challenged this finding of the High
Court. The respondent in its cross appeal has challenged
the award of interest by the arbitrator at the rate of 18%
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 5
per annum for 1.1.1991 to the date of the award.
The first item of dispute relates to the work of
excavating the canal section from kms. 189,50 to kms. 190.70
in addition to the earth work involved in lip cutting for
this section and lining it. According to the respondent, in
the Technical Specifications annexed to the contract,
paragraph 2.09.01 stated that from kms. 190.70 to kms. 197
earth work involved is in lip cutting; and from kms. 189.5
to kms.190.7 whole of the anal section is to be excavated.
In the pre-bid conference which was held, the minutes of the
meeting record that departmental machines will be working
from kms.190.7 to kms.197. The canal cross section
available will be irregular and the contractor will have to
excavate the remaining quantity to the dimensions shown.
Between kms. 189.5 and kms. 190.7 whole of the canal cross
section is to be excavated below ground level by the
contractor. The respondent contends that excavating the
canal is not extra work. But the rate for this work is not
specified anywhere. Bill of Quantity, which is also annexed
to the contract specified the rates for different kinds of
work which the contractor has to carry out. Item at S.No.1
provides for payment at the rate of Rs. 19/- per cubic metre
of earth for "the earth work in lip cutting, transportation
in embankment or spoil bank including all lead lifts
mechanical compaction, dressing, dewatering as per
specification". The rate for the work of excavation of the
canal does not appear to be specified. The respondent
contended before the arbitrator that payment at the rate of
Rs. 19/- per cubic metre covered every kind of earth work
and not just the earth work involved in lip cutting. While
according to the appellant, this was extra work for which
payment had not been specified and had to be agreed upon.
There was clearly a dispute on the issue and the reference
to arbitration clearly covers this dispute. The first item
of Office Memorandum referring the dispute to arbitration
relates to rate for extra work of earth work beyond lip
cutting in the reach kms. 189.50 to Kms. 190.70. In view of
the fact that this dispute was expressly referred to
arbitration, we fail to see how it can be said that the
decision on this dispute by the arbitrator is beyond the
scope of the reference. Both parties argued this question
before the arbitrator. The arbitrator has given a speaking
award giving detailed reasons why he considers this work as
extra work for which payment is required to be made to the
contractor. We are not examining the correctness or
otherwise of the conclusion reached by the arbitrator. It
is a matter of interpretation of the contract and was
referred by the parties to arbitration. The High Court was
not right in coming to the conclusion that this dispute was
beyond the scope of the reference to arbitration.
The other dispute between the parties relates to the
award by the arbitrator of interest for the period 1.1.1991
till the date of the award. The appellant has very fairly
conceded that the arbitrator has no jurisdiction to grant
any interest for the pre-reference period. Clause 1.18 of
the Technical Specifications annexed to the contract
provides as follows:
"No claim for interest or damage
will be entertained by the
Government with respect to any
money or balance which may be lying
with the Government or may become
due owing to any dispute,
difference or misunderstanding
between the Engineer-in-Charge on
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 5
the one hand and the contractor on
the other hand or with respect to
any delay on the part of the
Engineer-in-Charge in making
periodical or final payment or in
any other respect whatsoever."
Clause 51 of the contract which deals with arbitration
provides that all the disputes or differences in respect of
which the decision has not been final shall be referred for
arbitration to a Sole arbitrator as specified therein.
Neither Clause 1.18 of the Technical Specification nor
clause 51 excludes the jurisdiction of the arbitrator to
ward interest pendente lite. As far back as in 1992 a
constitution Bench of this Court in the case of Secretary,
Irrigation Department, Government of Orissa & Ors. vs. G.C.
Roy (1992 1 SCC 508), considered an arbitrator’s power to
award interest pendente lite. It held that when the terms
of the arbitration agreement did not exclude the
jurisdiction of the arbitrator to entertain a claim for
interest the arbitrator was competent to award interest
pendente lite. His power was analogous to the power of the
court under Section 34 of the Civil Procedure Code to award
interest in order to do complete justice between the
parties. In paragraph 43 of the said judgment, the
Constitution Bench has enumerated the principles for grant
of interest pendente lite by the arbitrator. Interest
pendente lite is not a matter of substantive law like
interest for the period anterior to reference (pre-reference
period). The power to award interest pendente lite has to e
inferred on the analogy of section 34 of the Civil Procedure
Code for doing complete justice between the parties. This
decision has been followed in many subsequent case. One
such decision shown to us is Sudhir Brothers vs. Delhi
Development Authority & Anr. (1996 1 SCC 32), where this
court observed that the decision in G.C. Roy’s case (supra)
holds the field as far as interest pendente lite is
concerned. The respondent, however, relied upon a decision
of this Court in Durga Ram Parsad vs. Government of Andhra
Pradesh (1995 1 SCC 418). The substantial body of the
judgment deals with the power of the arbitrator to grant
interest for the pre-reference period. The judgment has
also relied upon G.C. Roy’s case (supra) for interest
pendente lite. However, in the last paragraph of the
judgment the Court has declined to grant interest for the
pre-reference period as also interest pendente lite.
Presumably this is because of clause 69 of the contract
which is set out in paragraph 3 of the judgment although no
reasons are given in the judgment for excluding interest
pendente lite. In the present case, however, we have
produced clause 1.18 on which the respondent is relying. In
our view this clause does not debar an arbitrator from
granting interest during the pendency of the reference if,
in his discretion, he considers it appropriate to award it.
As is held by the Constitution Bench in the case of G.C. Roy
(supra), the power of the arbitrator to grant interest
pendente lite is based on principles analogous to Section 34
of the Civil Procedure Code. Such interest is granted by
the arbitrator in order to do complete justice between the
parties. This is not a matter of substantive law as is the
case regarding the arbitrator’s power to grant interest for
the pre-reference period. Whether interest should be
awarded pendente lite or not is a matter of discretion for
the court or the arbitrator. When parties go before an
arbitrator, they expect that the disputes will be decided
had the decision been of a court of law. Hence the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 5
arbitrator can exercise a power analogous to the power given
to the courts under Section 34 of the Civil Procedure Code.
The appellant is, therefore, entitled to interest on the
principal amount awarded by the arbitrator from the date of
the reference till the date of the award. The appellant is,
however, not entitled to any interest for the pre-reference
period.
In the premises the appeal arising out of S.L.P. (c)
No. 4328/1997 is allowed save and except that the appellant
will not be entitled to any interest on the principal amount
awarded prior to the arbitrator entering upon the reference.
The appeal of the respondent is dismissed with the above
modification. There will, however, be no order as to
costs.