Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 4
CASE NO.:
Special Leave Petition (civil) 12883-12884 of 2000
PETITIONER:
MAHARASHTRA STATE ELECTRICITY BOARD
Vs.
RESPONDENT:
STERILITE INDUSTRIES (INDIA) & ANR.
DATE OF JUDGMENT: 09/10/2001
BENCH:
S. Rajendra Babu & Doraiswamy Raju
JUDGMENT:
J U D G M E N T
RAJENDRA BABU, J. :
On certain disputes having arisen between the Maharashtra State
Electricity Board and Sterilite Industries (India) in connection with the
failure to supply certain goods the matter was referred to Arbitral
Tribunal consisting of three arbitrators. The petitioners made a claim in
a sum of Rs. 70,28,572.05p as damages for breach of contract sustained
by them on account of failure of the respondents to supply the entire
material ordered from them. In addition to this claim for damages,
interest on the said amount at 18% per annum for the period between
May 9, 1989 to October 29, 1990 amounting to Rs. 18,62,571.55p was
also made. Thus the total claim for damages and interest is in a sum of
Rs. 88,91,143.16p.
It is stated that the contract for supply of goods was cancelled by
the petitioners on April 17, 1989 on the basis that the material which
was not supplied by the respondents was procured by the petitioners
from other suppliers at a price much higher than what was tendered by
the respondents. The petitioners referred to various orders placed by
them with different parties. The damages were thus claimed on the basis
that the material which was not supplied by the respondents was
actually purchased or procured by the petitioners and the damages were
computed on the ground of higher price being required to be paid in
order to make good the short supply by the respondents. The claim of the
petitioners was contested by the respondents on several grounds.
The arbitrators raised two issues for consideration, which are as
follows :-
(1) Whether the respondents have committed breach of contract
or
whether the claimants have committed breach of contract
and on account of such breach it became impossible for the
respondents to supply the requisite material under the
contract?
(2) Whether under the terms of the contract the damages as
claimed can be sustained?
On consideration of the relevant material and arguments placed
before the arbitrators, per majority, they held that the breach of the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 4
contract is committed by the respondents and not by the petitioners. As
regards damages claimed by the petitioners, they adverted to clause 14 of
the contract to the effect that the purchaser has a right to purchase
upon such terms and in such a manner as he may deem appropriate
equipment similar to that terminated and then the contractor will be
liable to the purchaser for any additional cost for such similar equipment
and/or for liquidated damages for delay as defined in Article 22 of the
General Conditions until such reasonable time as may be required for
the final supply of equipment and construed the same as providing for
(i) that the contractor is liable to reimburse the purchaser the additional
cost of similar equipment which the purchaser has purchased and (ii)
that in addition to that or alternatively, the contractor is liable for
liquidated damages for delay until such reasonable time as may be
required for the supply of equipment and the provision regarding
liquidated damages was not attracted in the present case. Clause 14(ii)
was thus held to be a special provision with regard to quantum of
damages and the quantum is to be determined with reference to the
additional cost involved in purchasing the equipment which the
contractor had failed to deliver; that in view of this special provision the
mode of computation of damages provided for under Section 73 of the
Indian Contract Act is not attracted; that, the measure of damages upon
a breach of contract for sale of goods is the difference between the
contract price and the market price on the date of breach and it is open
to the parties to lay down a different rule; that the petitioners had failed
to prove that consequent upon the failure of the respondents to supply
the material in accordance with the contract, the petitioners had, after
the cancellation of the contract, purchased any material in lieu of the
material short supplied by the respondents; that the contracts relied
upon by the petitioners for similar material were already entered into by
the petitioners and the supply made thereunder had no relationship with
the short supply made by the respondents; that the petitioners had,
therefore, failed to prove that they had suffered any damages as
contemplated by clause 14 of the contract; that the concept of award of
compensation is bound up with loss or damage that results from the
breach of contract and where no loss or damages has ensued, there can
be no question awarding compensation; that even under Section 73 of
the Indian Contract Act where a claim for damages on the ground of
breach of contract is made by a party, the party claiming damages is
under an obligation to prove the loss; that the claimants in the instance
case had failed to prove that they had suffered any loss. On this basis,
the arbitrators held that the petitioners were not entitled to invoke the
provisions of Section 73 of the Indian Contract Act and they had failed to
prove that any additional purchases were made to make up for the short
supply resulting from the breach of contract by the respondents and
even otherwise, the petitioners had failed to prove that they had suffered
any damages and were, therefore, not entitled to any damages.
Accordingly, the claim made by the petitioners was dismissed.
The minority view expressed by another arbitrator is that clause
14(ii) of the contract enables the purchaser the right to purchase upon
such terms and manner as he may deem appropriate and that gives only
an additional option without affecting the rights arising under general
Law and, therefore, he was of the view that the claim should be allowed.
On the award being sought to be made the decree of the court,
objections were raised in the proceedings before a learned Single Judge
of the High Court, who, on examination adverted to the award and, in
particular, to the scope of clause 14(ii) of the contract entered into
between the parties. The learned Single Judge is of the view that if the
arbitrators have given reasons in support of their decision, it would be
open to the court to set aside the order if it finds that the error of law has
been committed by the arbitrators, though reasonableness thereof
cannot be challenged. He is influenced by the fact that what is found in
the award on the aspect of loss and quantum of damages against the
petitioners is pure finding of fact based on appreciation of evidence and,
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 4
therefore, could not be examined by the court. He is further of the
view that where loss in terms of money can be determined, the party
claiming compensation must prove the loss suffered by it in order to
attract Section 73 of the Indian Contract Act; that the concept of award
of compensation is bound up with the loss or damage that results from
the breach of contract and where no loss or damage has ensued, there
can be no question of awarding compensation; that the majority of the
arbitrators have said that the petitioners had failed to prove that they
had suffered any loss and, therefore, are not entitled to claim any
damages and thus the claim had to be rejected. The learned Single
Judge took the view that an award can only be set aside if there is an
error of fact or an error of law and unless such error is apparent on the
face of the record, the objections cannot be sustained and, hence he
overruled the objections holding that the award is unassailable in
proceedings under Section 30 of the Arbitration Act.
Appeals were filed against this order of the learned Single Judge on
the Letters Patent side and a Division Bench of the High Court reiterated
the view taken by the learned Single Judge after reappraisal of the facts,
the award made by the arbitrators and the contentions raised in the
appeals. It is against this order of the Division Bench, these special leave
petitions are filed.
Shri T.R. Andhyarujina, learned Senior Advocate appearing for the
petitioners, contended that the view taken by the arbitrators and the
High Court on the construction of clause 14(ii) is plainly wrong; that
under clause 14(ii) of the contract a right was reserved in favour of the
petitioners to purchase upon such terms and in such manner as the
petitioners deemed appropriate, equipments similar to that contracted
and the respondents are liable to the petitioners for any additional costs
for such similar equipments and/or for liquidated damages for delay as
defined in Article 22 of the General Conditions until such reasonable
time as may be required for final supply of the equipments; that this
reservation in favour of the petitioners is an additional right to claim
damages from the respondents for an additional costs that might be
incurred for such purchases and has not been taken away from the
petitioners their general right to claim damages under Section 73 of the
Indian Contract Act; that for invoking the provisions of Section 73 of the
Indian Contract Act it was not necessary for the petitioners to have
purchased the equipments and materials not supplied by the
respondents from the open market; that even in such an event, the
petitioners are entitled to claim damages from the respondents on the
basis of the difference between the contract price and the market price
of the materials on the date of the breach of the agreement by the
respondents.
The position in law has been noticed by this Court in Union of
India vs. A.L. Rallia Ram, AIR 1963 SC 1685, and Firm Madanlal
Roshanlal Mahajan vs. Hukumchand Mills Ltd., Indore, 1967 (1)
SCR 105, to the effect that the arbitrators award both on facts and law is
final; that there is no appeal from his verdict; that the court cannot
review his award and correct any mistake in his adjudication, unless the
objection to the legality of the award is apparent on the face of it. In
understanding what would be an error of law on the face of the award,
the following observations in Champsey Bhara & Company vs. Jivraj
Balloo Spinning and Weaving Company Ltd., L.R. 50 I.A. 324, a
decision of the Privy Council, are relevant:-
An error in law on the face of the award means, in their
Lordships view, that you can find in the award or a document
actually incorporated thereto, as for instance a note appended by
the arbitrator stating the reasons for his judgment, some legal
proposition which is the basis of the award and which you can
then say is erroneous.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 4
In Arosan Enterprises Ltd. vs. Union of India & Anr., 1999 (9)
SCC 449, this Court again examined this matter and stated that where
the error of finding of fact having a bearing on the award is patent and is
easily demonstrable without the necessity of carefully weighing the
various possible view points, the interference in the award based on
erroneous finding of fact is permissible and similarly, if an award is
based by applying a principle of law which is patently erroneous, and but
for such erroneous application of legal principle, the award could not
have been made, such award is liable to be set aside by holding that
there has been a legal misconduct on the part of the arbitrator.
In the Russell on Arbitration [17th Edition], the position in law is
thus stated :-
Where an arbitrator makes a mistake either in law or in fact in
determining the matters referred, but such mistake does not
appear on the face of the award, the award is good notwithstanding
the mistake, and will not be remitted or set aside.
The general rule is that, as the parties choose their own arbitrator
to be the Judge in the disputes between them, they cannot, when
the award is good on its face, object to his decision, either upon
the law or the facts.
In the light of this enunciation of law, we are of the view that
unless the error of law sought to be pointed out by the learned counsel
for the petitioners in the instant case is patent on the face of the award
neither the High Court nor this Court can interfere with the award. The
exercise to be done by examining clause 14(ii) of the contract entered into
between the parties, construing the same properly and thereafter
applying the law to it to come to a conclusion one way or the other, is too
involved a process and it cannot be stated that such an error is apparent
or patent on the face of the award. Whether under the context of the
terms and conditions of a contract, a stipulation in the form and nature
of clause 14(ii) operates as a special provision to the exclusion of Section
73 of the Indian Contract Act is a matter of appreciation of facts in a
case, and when the decision thereon is not patently absurd or wholly
unreasonable, there is no scope for interference by courts dealing with a
challenge to the award. Therefore, we think, the view taken by the High
Court in this matter is correct and calls for no interference.
If as construed by the arbitrators that clause 14(ii) excludes
applicability of Section 73 of the Indian Contract Act and the proposition
of law stated by the arbitrators is correct, then Section 73 is not
attracted to the case.
In this view of the matter, we find absolutely no substance in these
petitions and they are dismissed with costs of the respondents quantified
at Rs.5,000/- in each set.
J.
[ S. RAJENDRA BABU ]
J.
[ DORAISWAMY RAJU ]
OCTOBER 9, 2001.