Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 14
PETITIONER:
M/S RAYMOND LIMITED & ANR., ETC. ETC.
Vs.
RESPONDENT:
MADHYA PRADESH ELECTRICITY BOARD & ORS.,ETC.ETC.
DATE OF JUDGMENT: 16/11/2000
BENCH:
B.N.Kirpal, Doraiswamy Raju, K.G.Balakrishna
JUDGMENT:
RAJU, J.
L.....I.........T.......T.......T.......T.......T.......T..J
The above batch of appeals arise out of a common
judgment rendered in a batch of Writ Petitions by a Full
Bench of the Madhya Pradesh High Court, since reported in
AIR 1999 Madhya Pradesh 143 and also the consequential
separate orders passed subsequently by the Division Bench
dismissing the Writ Petitions. The Writ Petitioner -
Industries filed appeals against that portion of the opinion
of the Full Bench confining the declaration of law made for
prospective application only and the dismissal of the Writ
Petitions, whereas, the Electricity Board had filed appeals
against that portion of the opinion of the Full Bench
declaring the position of law that whenever the contracted
supply falls short of 40% of the contract load then the
Board shall be entitled to charge only for the reduced
energy actually supplied and not for 40% of the contract
load as minimum charges and thereby overruling an earlier
decision of a Division Bench of the said High Court reported
in M/s Gwalior Steels Private Ltd. vs M.P. Electricity
Board (AIR 1993 M.P. 118). For the purpose of appreciating
the points raised, we would advert to the facts in one of
these appeals, particularly those in M/s Raymond Ltd. in
C.A. Nos. 4218-4219 of 1998.
The appellant M/s Raymond Ltd., a company registered
under the Companies Act, 1956 and having its cement
manufacturing division within the State of Madhya Pradesh,
entered into an agreement with the Madhya Pradesh
Electricity Board on 27.3.1979 renewed periodically for
supply and purchase of high tension electric energy for use
in the manufacture of cement. The minimum contractual
demand was for 33 MW (38,822 KVA) per day and clause 19
provided for the Tariff, while clause 21 stipulated the term
relating to minimum guarantee in the following terms:
21(a) The consumer shall from the date of utilisation
of electrical energy, or from the date of expiry of the
three months notice mentioned in clause 2 hereof guarantee
such minimum consumption as when calculated at the tariff
(excluding charges due to fuel adjustment clause, meter rent
and miscellaneous charges) will yield an annual revenue of
Rs.5,40,000/- (Rupees Five Lakhs Forty Thousand Only) or pay
this sum as a minimum. The deficit, if any, between the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 14
guaranteed minimum charges and the actual charges shall be
payable by the Consumer.
(b) The minimum guarantee specified in Clause 21(a)
above shall at all times be without prejudice to realisation
by the Board of the minimum prescribed under the tariff
referred to in Clause 19 hereof.
(c) It hereby agreed further that the Board shall be
entitled to fix and charge enhanced amount of annual revenue
if the Board, on completion of all works for supply to the
Consumer, finds it has incurred higher expenditure than the
pre- estimated cost and in that case the Consumer shall pay
to the Board the enhanced annual revenue so fixed by the
Board without any objection and will not raise any dispute
regarding the same.
Clause 19 of the agreement read as follows:
The Consumer shall pay to the Board every month,
charges for the electrical energy supplied to the Consumer
during the preceding month, at the Boards tariff applicable
to the class of service and in force from time to time. A
copy of the current H.T. tariff No.1-A of notification
No.5/GA/147-A dated 11.03.1976 as amended applicable to the
Consumer is set out in the Schedule attached to this
Agreement.
Under the notification issued for High Tension for 132
KV/220 KV supply, the minimum tariff prescribed for cement
factories is said to be as hereunder:
The consumer will guarantee a minimum monthly
consumption (KWH) equivalent to 40% load factor of the
contract demand. The consumer will be required to pay the
energy charges on the said minimum monthly consumption plus
the demand charges on the billing demand for the month as
minimum monthly payment irrespective of whether any energy
is consumed or not during the month. An average power
factor of 0.9 will be applied for the calculation of
corresponding unit of 40% load factor on contractual
demand.
The Senior Account Officer concerned of the
Electricity Board issued a bill dated 18.10.1995 raising a
demand of Rs.2,83,18.581/- for the consumption period from
15.9.1995 to 15.10.1995. While recording the actual
consumption in units of the electrical energy and the
charges therefor, the ultimate bill and demand came to be
raised on the basis of the minimum guarantee charges
equivalent to 40% load factor of contract demand. This,
according to the appellant, resulted in a demand of
Rs.87,45,685/- in addition to the charges really due on the
actual consumption of energy during the period in question.
Challenging the same, Writ Petition No. 3616 of 1995 came
to be filed, claiming either for refund or adjustment of the
said excess amount against future demands, the said sum
being for electrical energy not really consumed by them.
During the pendency of the said Writ Petition, another bill
dated 18.10.96 for the consumption period from 1.12.95 to
15.12.95 was said to have been issued for Rs.10,24,867/-
towards minimum guarantee charges equivalent to 40% load
factor of contract demand. As against this, Writ Petition
No. 4711 of 1996 came to be filed challenging the demand
and seeking for either refund of the same or for adjustment
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 14
thereof against future demands. The Electricity Board
contested the claim of the appellants and others contending
that as per the terms of the agreement entered into
governing the supply of electrical energy, the sum demanded
is quite, in accordance with law, justified and cannot be
avoided by any of the appellants, and the details of their
defence will be adverted to hereinafter, at the appropriate
stage.
The batch of Writ Petitions initially came up before a
Division Bench and keeping in view the earlier decision of a
Division Bench reported in AIR 1993 M.P. 118 (Supra), by an
order dated 11.9.97, the matter was placed before a Full
Bench with the following observations:
After reviewing all these cases on the subject we are
impressed with the arguments that the matter requires
consideration by the larger Bench because notwithstanding
the fact that as per the terms of the agreement, an
obligation has been cast on the consumer 40% load factor of
the contract demand and pay for the same every month. But
there is no corresponding obligation on the Electricity
Board to supply 40% load factor of the contract demand.
When there is no corresponding duty on the part of the
Electricity Board to supply minimum 40% of the contract
demand load every month still the consumer is under an
obligation to 40% of the contract demand load. This
prima-facie sound in equitable. Therefore, we think it
proper that since this is a larger issue which involve
serious interpretation of the aforesaid tariff clause of the
Electricity Board as much, yet the matter may be referred to
a Larger Bench so that the matter can be placed beyond the
pale of any further controversy in the matter. Papers maybe
placed before the Chief Justice for constituting a Larger
Bench.
The Full Bench, which heard the matter, by its opinion
dated 5.3.98 held as follows:@@
JJJJJJJJJJJJJJJJJJJJJJJ
25. After considering all aspects of the matter, we
are of the opinion that the view taken by the learned
Division bench of this Court in the case of M/s Gwalior
Steels Private Limited v M.P.Electricity Board, AIR 1993
Madh Pra 118, does not lay down a correct law and we hold
with reference to Clause 23(b) of the Agreement read with
Tariff, that whenever contracted supply falls short of 40%
of the contract load, then the Board shall be entitled to
charge for the reduced energy (actually supplied) and will
not be entitled to charge 40% of the contract load. This
interpretation which appears to us to be more equitable,
just and reasonable shall be applicable only prospectively
that is from the date of the order and will not have any
retrospective operation. This is being done keeping in view
that the Division Bench judgment of this Court has held the
field since 1993 and the Board has been billing the
consumers in the State on that basis and now since we are
taking a different view from that of the Division Bench of
this Court and we are interpreting the provision contrary to
the view taken by the Division Bench in the above case of
M/s Gwalior Steel Private Limited it would be more just and
equitable to give this interpretation a prospective effect
and not retrospective. Similar course of action was adopted
by the Hon. Supreme Court in the case of L.Chandra Kumar v.
Union of India, AIR 1997 SC 1125. Therefore, we hold that
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 14
the present interpretation will be prospective in nature and
not retrospective.
Thereupon, the Writ Petitions came to be posted before
the Division Bench, and apparently on account of the
prospective declaration of law, no relief as prayed for in
respect of particular demands for the earlier period could
be granted and the Writ Petitions came to be dismissed.
Hence, the appeals by the Writ Petitioners before the High
Court. So far as the Electricity Board is concerned, they
filed appeals, felt aggrieved by the judgment of the Full
Bench insofar as it overruled the earlier judgment reported
in AIR 1993 M.P. 118 (Supra). This Court, while granting
leave in the Special Leave Petitions filed, on 24.8.98
directed the appeals to be placed before a Bench of three
judges in view of the decision of this Court in Orissa State
Electricity Board & Another vs IPI Steel Ltd. & Others
reported in 1995 (4) SCC 320.
Heard the learned counsel appearing on either side.
Shri C.S. Vaidyanathan, learned senior counsel for the
Electricity Board, took us at length through the various
clauses in the agreements and contended that the minimum
charges expressly guaranteed in favour of the Board is not
subject to either actual supply by the Board or consumption
by the consumer and the payment of such minimum guarantee at
a rate equivalent to 40% load factor of the contract demand
is in substance a partial return for various investments in
the various installations and to meet recurring expenses for
maintenance and the consumers, having specifically
undertaken to do so with no provision for any reduction or
deduction in the contract as such for such reasons or
grounds, cannot go back upon the solemn commitments and
undertaking under clause 19. In reinforcing the said stand
it is further contended that whenever the State Government
pass orders under Section 22 B imposing power
cuts/reduction/staggering in supply both parties are obliged
to carry out the same and it would be futile for the
consumers to read into the word consumption, the element
of supply too. The load factor envisaged is said to be a
measure of liability for minimum guarantee and not to cast
any obligation on the Board to effect supply of energy to
that extent so as to make it a condition precedent for
casting liability on the consumer to pay the minimum
guaranteed charges. It is further contended that the
minimum guarantee has been fixed for various industries such
as cement, steel etc. depending upon the different minimum
load factors having regard to the investments on
establishments and recurring maintenance expenditure and it
is never considered to be part of the tariff but really
relate to the realm of mechanics of price fixation,
exclusively within the discretion of the Board and
consequently the High Court could not have interfered with
the same.
On behalf of the consumer industries Shri G.L.Sanghi,
learned senior Advocate, made the leading arguments followed
by Sarvashri A.K. Chitale, Bhimrao Naik, Ravindra
Srivastava, Senior Advocates, and S.Ganesh, U.A.Rana,
A.K.Sanghi and others. Adverting to clauses 1(a), 3(a),
(b), 8, 11, 12, 18, 19, 21 and 23, it was strenuously
contended that the contract must be construed as a whole in
the context of the object underlying the same and the basic
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 14
contract being for supply continuously 33 KV electrical
energy on day to day basis, it should really be meaningful
and really useful and possible of consumption for the
purposes of the industries concerned. It is further stated
that the quality, the quantity and manner of supply has also
to be taken into account in assessing the usefulness of the
energy for industrial purposes and if it is shown that the
supply actually made did not conform to these vital aspects
of supply then the undertaking to pay the minimum guaranteed
amount should itself have to go and any other construction
would result in grave injustice besides being also
inequitable and unconscionable. The further plea is that
the Board during the period in dispute did not supply even
the bare minimum quality of energy required to run the
essential machineries to keep the manufacturing process
going and continuous and the supply actually made was of
poor quality, not really useful, erratic and non-
continuous, fluctuating and accentuated with frequent
trippings and in effect not only dislocating the normal
working of the industries but also damaging the machineries
and retarding production and therefore, no exception could
be taken to the manner of construction placed on the clauses
in the contract as well as the conclusions arrived at in
respect of the statutory and other liabilities of the
consumers, by the High Court. The learned counsel appearing
also endeavoured to highlight some of the individual factual
details pertaining to their cases and also invited our
attention to some of the correspondence exchanged between
parties regarding their grievances about the quality as well
as the quantity of supply made to them. We may make it
clear even at this stage that we do not propose to undertake
an enquiry into or adjudication of such factual claims in
these proceedings, particularly in the teeth of the manner
of disposal given by the Division Bench after the opinion of
the Full Bench and the desire of the learned counsel
themselves to relegate to the High Court the matters, if
need be, for determination of such claims.
Though there was an attempt for the consumers to
contend that any shortfall in the supply of the total
quantity of contract demand agreed to be made would relieve
them of all liabilities from payment of the minimum
guaranteed sum undertaken, we are unable to countenance any
such claim, particularly in view of the very question that
was actually referred to and decided by the Full Bench of
the High Court and which on the face of it merely pertained
to the liability or otherwise of the consumer industries to
pay the minimum guaranteed charges even when the minimum 40%
of the contract demand energy is not supplied during the
relevant period by the Board. As a matter of fact, we find,
in the light of the decision in AIR 1993 M.P. 118 (Supra)
the correctness of which was taken up for consideration by
the Full Bench, the question referred to the Full Bench
itself is as to whether the consumer is required to pay
minimum tariff of 40% of the contract load irrespective of
the fact that even 40% of the contract load energy has been
supplied or not to the consumer. Therefore, it is not
permissible for the consumer industries in these appeals to
invite a decision as to the liability or otherwise of the
consumers to pay the minimum guaranteed charges undertaken,
notwithstanding the factual position that the supply made
was actually 40% or even more though not of the extent of
total contract demand agreed to between the parties under
the respective contracts. That apart, countenancing such
claims to be agitated in proceedings under Article 226 of
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 6 of 14
the Constitution would amount to the extraordinary
jurisdiction being permitted to be availed to rewrite the
contract and read just contractual liabilities and thereby
undertaking an adjudication of rights of parties flowing
under a contract - a function normally assigned to the
ordinary civil courts of the land.
Apart from making such submissions on the merits of
their claim, on the basis of the very decision of the High
Court and drawing sustenance to substantiate such claims,
the consumer industries also attacked that portion of the
judgment which purported to confine the declaration of law
made for future application only by applying the principle
of prospective overruling, contending that such principles
cannot be invoked by the High Courts exercising jurisdiction
under Article 226 of the Constitution of India and that the
High Court, in any event, committed an error in not
affording an opportunity to them to make their submissions
on the applicability or otherwise of the principle of
prospective overruling to the cases on hand.
Claims similar to the one sought to be now asserted,
have come up for consideration before this Court, though in
somewhat different background of facts and pattern of
contracts between consumers and Electricity Boards, and
either of the parties before us tried to lay their hands on
some or the other of the observations made in those cases,
to justify their respective stand. In M/s Northern India
Iron and Steel Co. vs. State of Haryana & Anr. (1976 (2)
SCC 877) the dispute arose between the parties as to whether
in a situation where there were substantial power cuts and
the Board was not able to supply the energy required by the
consumer in terms of the contract entered into, the Board
was entitled to get any demand charge and if so, to what
extent and whether the State could demand any duty on such
demand charge. This Court adverted to the existence of two
well-known systems of tariff - one the flat rate system in
which a flat rate on units of energy consumed and the other
known as the two-part tariff system, meant for big consumers
of electricity comprising of (i) what is known as ‘demand
charges to cover investment, installation and the standing
charges to some extent and (ii) energy charges for the
actual amount of energy consumed. The Court ultimately
decided the question on the basis of the specific
stipulation contained in clause 4(f) of the contract
therein, which entitled the consumer to a proportionate
reduction of demand charges/minimum charges, if the
consumer was not able to consume any part of the electrical
energy due to any circumstance beyond its control and for
that purpose the circumstance of power cut which disabled
the Board to give the full supply to the consumer because of
the government order made under Section 22 B of the
Electricity Act, 1910, was considered to be a circumstance
which disabled the consumer from consuming electricity as
per the contract.
In Bihar State Electricity Board & Anr. vs M/s
Dhanawat Rice & Oil Mills (1989 (1) SCC 452), this Court
while applying the decision in 1976 (2) SCC 877 (supra)
construed clause 13 of the contract between parties in that
case which specifically provided for the proportionate
reduction of the annual minimum guarantee bills, as merely
entitling the consumer to a proportionate reduction only and
not completely avoid payment of annual minimum guarantee
bills, even in cases where there was failure on the part of
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 7 of 14
the Board to supply electrical energy as per demand of the
consumer under the contract. In Bihar State Electricity
Board, Patna & Others vs M/s Green Rubber Industries &
Others (1990 (1) SCC 731, this Court, while repelling a
challenge to the clause in the agreement which provided for
payment of minimum guaranteed charges irrespective of
whether energy was consumed or not, observed that the same
was reasonable and valid for the reason that the supply of
electricity to a consumer involves incurring of overhead
installation expenses by the Board which do not vary with
the quantity of electricity consumed and also for the reason
that those installations have to be continued and must be
maintained until the agreement itself comes to an end. Such
a stipulation was also considered to be not by way of
penalty for not consuming the specified quantity of energy
but more for the obligation of the Board to keep the energy
available to the consumer at his end. Again in Andhra Steel
Corporation Ltd. & Others vs Andhra Pradesh State
Electricity Board & Others (1991 (3) SCC 263) this Court
held that the purpose of prescribing minimum charges is to
ensure that no undue loss is caused to the Electricity Board
due to the tendency of the consumer to have connection for
inflated requirement and the Boards agreement to meet such
requirement and the readiness to maintain the supply up to
that requirement, even if no or very little energy is
consumed. The decision of the State Government under
Section 78 A of the Supply Act, 1948, to fix concessional
tariff was also held not sufficient to absolve the consumer
from the liability undertaken to pay the minimum guaranteed
charges. In coming to such a conclusion, reliance has also
been placed upon the decisions reported in 1990 (1) SCC 731
(Supra) and The Amalgamated Electricity Company Ltd. vs The
Jalgaon Borough Municipality (1975 (2) SCC 508) wherein this
Court observed as follows:
9. Moreover it is obvious that if the plaintiff
company was to give bulk supply of electricity at a
concessional rate 0.5 anna per unit it had to lay down lines
and to keep the power ready for being supplied as and when
required. The consumers could put their switches on
whenever they liked and therefore the plaintiff had to keep
everything ready so that power is supplied the moment the
switch was put on. In these circumstances it was absolutely
essential that the plaintiff should have been ensured the
payment of the minimum charges for the supply of electrical
energy whether consumed or not so that it may be able to
meet the bare maintenance expenses.
In Orissa State Electricity Board & Another vs IPI
Steel Ltd. & Others (1995 (4) SCC 320) this Court had an
occasion once again to deal with these issues in the light
of the earlier case law on the subject. This Court
explained therein the meaning of the expressions maximum
demand charges, consumption charges and dealt with the
role as well as purpose of installing two meters - the
normal meter meant for recording the total quantity of
energy consumed over a given period, in variably a month and
trivector meter meant for recording the highest level/
load at which the energy is drawn over any thirty minute
period in a month. While explaining the two part tariff
system meant for big/bulk consumers of electricity, this
Court has emphasised and reiterated the justification and
reasonableness of the same, observing the following:
Normally speaking, a factory utilises energy at a
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 8 of 14
broadly constant level. May be, on certain occasions,
whether on account of breakdowns, strikes or shutdowns or
for other reasons, the factory may not utilise energy at the
requisite level over certain periods, but these are
exceptions. Every factory expects to work normally. So
does the Electricity Board expect - and accordingly produces
energy required by the factory and keeps it in readiness for
that factory - keeping it ready on tap, so to speak. As
already emphasised, electricity once generated cannot be
stored for future use. This is the reason and the
justification for the demand charges and the manner of
charging for it. There is yet another justification for
this type of levy and it is this: demand charges and
consumption charges are intended to defray different items.
Broadly speaking, while demand charges are meant to defray
the capital costs, consumption charges are supposed to meet
the running charges. Every Electricity Board requires
machinery, plant, equipment, sub-stations, transmission
lines and so on, all of which require a huge capital outlay.
The Board like any other corporation has to raise funds for
the purpose which means it has to obtain loans. The loans
have to be repaid, and with interest. Provision has to be
made for depreciation of machinery, equipment and buildings.
Plants, machines, stations and transmission lines have to be
maintained, all of which require a huge staff. It is to
meet the capital outlay that demand charges are levied and
collected whereas the consumption charges are levied and
collected to meet the running charges.
Adverting to the actual grievance of the consumer in
that case that where the cut in supply, be it even for the
reason of an order passed by the Government under Section 22
B of the 1910 Act, is only to the extent of half of the
contract demand, it was held that during such periods of
restricted supply the consumer had to pay the energy charges
for the actual consumption plus maximum demand charges for
the maximum demand availed of by him at the rate prescribed
in the agreement. As in the cases before us, it seems to
have been projected there also that even during the periods
of restricted supply there were frequent cuts and break
downs as well as irregular supply and the Board cannot levy
full demand charges merely because in any thirty minute
period in a given month, the power is availed at the maximum
demand level, and that except the actual consumption charges
nothing further, particularly the full demand charges could
be collected. After referring to the decisions reported in
1990 (1) SCC 731 (Supra), and the other decisions which were
quoted with approval therein such as AIR 1936 Cal.265 (Saila
Bala Roy vs Chairman, Darjeeling Municipality and 1969 (1)
Madras Law Journal 69 (M.G.Natesa Chettiar vs Mad. SEB)
which were quoted with approval earlier by this Court, the
challenge by the consumer came to be rejected. It was also
observed that breakdowns and trippings etc. which are not
confined to periods of restricted supply alone but may occur
during normal times also does not affect the liability of
the consumer and only if there is no supply at all for
considerable periods, the situation would be different,
whether it happens during the period of normal supply or
restricted supply, though on facts the case considered by
the Court was not found to be one such.
We have carefully considered the submissions of the
learned counsel appearing on either side, in the light of
the provisions of the 1910 Act and 1948 Act, the contract
entered into between the parties, the general conditions for
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 9 of 14
supply and the tariff rates prescribed as well as the
governing principles as laid down by this Court. The terms
and conditions of supply, as envisaged in the contract and
the statutory provisions and general conditions have been
standardised for uniform application among consumers with
variations merely necessitated by the different class or
categories of consumers and there is no scope otherwise for
expecting any scope for individual or free bargaining right
in this regard by each consumer with the Board. Therefore,
it is futile for a consumer to contend that the Board was at
the dictating end and the parties were not equally
positioned in settling the terms of the contract. The
further attempt made to contend that the failure on the part
of the Board to effect supply up to the contract demand
level relieved the consumers from the obligation undertaken
to pay a minimum guaranteed sum per month, as though the
contract demand is the minimum guaranteed for supply, not
only lack any basis in law or on the terms of the contract
governing the supply but also directly runs counter to the
terms in the contract which makes different stipulations
relating to contract demand and the minimum guarantee in the
form of a portion or percentage of the contract demand,
only. The question of exonerating the consumer from the
liability undertaken to pay minimum guaranteed charges for a
month and billing only for the actual consumption of energy
or allowing a consumer to pay the rates on the actual
consumption of electricity measured in units will and can
arise and has also been considered for determination only in
case the supply by the Board itself fell short of the
minimum of energy, the consumption of which go to make up
the minimum guaranteed sum. It is well settled and there
could be no controversy over the position that if only the
supply was available for consumption but the consumer did
not consume so much of energy up to the extent of the
obligation cast upon him to pay the minimum charge, there is
no escape from the payment of the minimum guaranteed
charges, except in very exceptional cases envisaged under
clause 23 of the contract, and that too subject to the
stipulations and restrictions contained therein.
In the light of the serious controversies raised as to
the duration, quantity, manner and quality of supply of
electrical energy expected to be made by the Board, it
becomes inevitably necessary to decide first the question
relating to the unit or standard of measurement, which
invariably must have relevance, in our view, only to the
billing cycle envisaged in the contract and the tariff which
is only a month. The payment by the consumer is to be on
the electrical energy supplied during the preceding month.
The parties have also agreed that the maximum demand of the
supply is to be measured with reference to the month at the
point of supply of the consumer and will be determined on
the basis of the supply during any consecutive thirty
minutes in that month as recorded by the trivector meter.
The power factor, according to the statutory conditions of
supply which form part and parcel of the supply of energy to
a consumer, is also to be determined with reference to the
supply of energy to a consumer, and that factor is also to
be determined with reference to the supply of electrical
energy made during a month. The minimum consumption of
energy guaranteed, as per the tariff notification, is also
in terms of a monthly minimum. While that be the position,
it is futile for the consumers to contend that they will not
be liable to abide by the minimum guaranteed charges
undertaken, unless on every day of the month/year and during
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 10 of 14
the twenty four hours or round the clock the load factor and
power supply agreed to be made, at one and is the same level
without any shortfall, tripping or low voltage. The
provisions of Section 56 of the Contract Act, 1872 sought to
be relied upon have no relevance or application to the cases
on hand. Countenancing of such claims would not only defeat
the very purpose, object and aim of providing for a minimum
charges guarantee clause but would ultimately result in
mutilation of the very fabric of tariff structure rendering
thereby the schemes of generation and supply of power at the
agreed concessional rates uneconomical and non-viable for
the Board. This would also result in the re-writing of many
of the clauses in the contract and rendering nugatory the
tariff pattern and system itself throwing into disarray and
disharmony the efficient execution of the power supply
schemes.
The further claim asserted on behalf of the consumers
that since what was agreed to between the parties was to
make the supply available continuously except during
situations envisaged in clause 11 of the contract, the
failure to effect such supply by the Board renders the very
contract relating to the payment of minimum guaranteed
charges unenforceable against them, does not merit
acceptance in our hands. It cannot legitimately be
contended that the word continuously has one definite
meaning only to convey uninterruptedness in time sequence or
essence and on the other hand the very word would also mean
‘recurring at repeated intervals so as to be of repeated
occurrence‘. That apart, used as an adjective it draws
colour from the context too, and in the light of the texture
of clause 11 as well as clause 12 and clause 23 (b) and also
Section 22 B of the 1948 Act and orders passed therein which
are binding with equal force upon both the consumer and the
Board, the word is incapable of being construed in such
absolute terms as endeavoured by the learned counsel for the
consumers.
The High Court was of the view that it would be more
just, equitable and reasonable to hold whenever the
contracted supply fell short of 40% of the contract load
which alone accounts for the minimum guaranteed sum, then
the Board shall be entitled to charge for the reduced energy
actually supplied and not the minimum of 40% of the contract
demand. As noticed supra, on behalf of the consumers, not
only inspiration is drawn to support their claim in this
regard but an extreme stand is also sought to be taken by
contending that in such cases as also in cases where the
supply is not of the contracted load and to the extent of
the agreed load factor without interruptions so as to cause
any disturbance or dislocation of the smooth functioning of
their industry concerned, the obligation under the clause in
the agreement providing for the payment of the minimum
guaranteed charges to the tune of 40% of the contract load
also would automatically stand snapped and not only that the
consumers will be relieved of their liability but they can
be made answerable only to the extent of energy actually
supplied and which has been consumed. There is no
justification for countenancing this extreme stand either
under any of the provisions of the Act or the regulations
made thereunder or under the provisions of the contract
entered into between the parties and tariff schedule
notified and made binding upon the consumers. This would,
if accepted, give credence to the plea vaguely and
indirectly projected as though the contract demand is the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 11 of 14
minimum supply undertaken to be made by the Board, whereas
in contrast clause 23 of the general conditions for supply
of electrical energy by the Board applicable to all
consumers in unmistakable terms stipulate that the maximum
demand agreed to be supplied and taken under the agreement
shall be the consumers contract demand and that if as a
matter of fact in any given case the consumption exceeds
this level, then only the contract provides for additional
charges to be paid by the consumers.
As a matter of general principle, any stipulation for
payment of minimum guarantee charges is unexceptionable, in
a contract of this nature wherein, the Board which
undertakes generation, transmission and supply of electrical
energy has to, in order to fulfil its obligation lay down
lines and install the required equipment and gadgets and
constantly keep them in a state of good repair and condition
to render it possible for the consumer to draw the supply
required at any and all times. These commitments are
irrespective of the capacity of the Board to generate at a
given point of time or during a relevant period the total
quantum required for the consumption of all consumers of
various categories or even during the days of breakdown
envisaged or staggering necessitated on account of orders of
Government regulating the distribution and consumption of
energy as well as during periods when for reasons personal
or peculiar to the consumers or even beyond their control
the consumption is not and could not be of the mutually
agreed extent. The Board undertakes to generate and supply
energy, in public interest also at concessional rates of
varying nature and it cannot be stated that the rates so
fixed invariably are to meet the expenditure incurred by the
Board for generation and supply of energy, to the last pie.
Consequently, if either in the general conditions and terms
of supply or the contract or the tariff rates as the case
may there be any stipulation, in clear and unmistakable
terms that the liability relating to the payment of
guaranteed minimum charge could or will be enforced
irrespective of the actual consumption rate of the consumer
or even dehors the capacity or otherwise of the Board to
supply even the minimum of the contract demanded energy,
there could be no valid objection in law for any such
stipulation being made and the consumer will be bound to
honour such commitment. The contract for the supply of
electrical energy cannot be treated on par with any other
contacts of mutual rights and obligations, having regard to
the peculiar problems involved in the generation,
transmission and supply which invariably depend upon the
vagaries of monsoon as well short supply to them of the
required coal and oil in time and similar other problems
over which the Board cannot have any absolute control. The
recurring commitments relating to constant and periodical
maintenance of supply lines and other installations cannot
be anytheless even during such times and such onerous
liabilities cannot be left to fall exclusively upon the
Board and it is only keeping in view all these aspects,
payment of minimum guaranteed charges is necessarily in
built in the tariff system of the Board and the
reasonableness or legality of the same cannot be considered
either in the abstract or in isolation of all these aspects.
It is for this reason that all over and the consumer is also
made to share the constraints on Boards economy even during
such periods. In fact the tariff inclusive of such a
provision for payment of a minimum guaranteed sum
irrespective of the supply/consumption factor appears to be
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 12 of 14
the consideration for the commitments undertaken by the
Board as a package deal and it is not possible or
permissible to allow the consumer to wriggle out of such
commitments merely on the ground that the Board is not able
to supply at any point of time or period the required or
agreed quantum of supply or even supply up to the level of
the minimum guaranteed rate of charges. Tinkering with
portions of contracts for any such reasons, merely on
considerations of equity or reasonableness pleaded for and
vis-a-vis one party alone will amount to mutilation of the
whole scheme underlying the contract and render thereby the
very generation and supply of electrical energy economically
unviable for the Board. Consumers, who enter into such
commitments openly and knowing fully well all these hazards
involved in the generation, transmission and supply, will be
estopped from going behind the solemn commitment and
undertaking on their/its part under the contract. The High
Court does not seem to have properly appreciated the ratio
of the several decisions noticed except merely referring to
them in extenso, and yet ultimately just, arrived at a
conclusion merely for the reason that the court considered
it to be ‘more equitable, just and reasonable to do so.
So far as the cases under consideration and the
liability of the consumers relating to minimum guarantee are
concerned, the relevant clause relating to minimum guarantee
charges as well as the tariff notification relied upon,
would go to show that what was guaranteed was not the
payment of a flat sum or amount of money to be calculated
with reference to a particular number or percentage of
units, dehors the quantum of electrical energy distributed
and supplied by the Board. In other words, the guarantee
was of such minimum consumption as when calculated at the
tariff.. will yield a particular monthly/annual sum to the
Board. Even going by the tariff notification which
prescribes also a minimum entitling the Board to collect it
[vide clause 21 (b)] it merely casts liability on the
consumer to guarantee a minimum monthly consumption
equivalent to 40% load factor of the contract demand.
Consequently, for the consumer to honour his/its commitment
so undertaken to give a minimum consumption there should
essentially be corresponding supply by the Board at least to
that extent, without which the consumption of the agreed
minimum is rendered impossible by the very lapse of the
Board. The minimum guarantee, thus, appears to be not in
terms of any fixed or stipulated amount but in terms of
merely the energy to be consumed. The right, therefore, of
the Board to demand the minimum guaranteed charges, by the
very terms of the language in the contract as well as the
one used in the tariff notification is made enforceable
depending upon a corresponding duty, impliedly undertaken to
supply electrical energy at least to that extent, and not
otherwise. It is for this and only reason we find that the
ultimate conclusion arrived at by the Full Bench of the High
Court does not call for any interference in these appeals.
Shri C. S. Vaidyanathan, learned senior counsel for
the Board, further contended that the High Court committed
an error in overlooking the facts placed on record in the
form of statements showing the units which were made
available to the consumers during the periods in question
and the units determined on which the minimum charges became
payable and that those statements sufficiently substantiated
the position that the units made available were more than
sufficient to cover the payment of minimum charges and the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 13 of 14
contentions to the contrary that the Board had not been able
to supply even 40% of the contract demand to insist upon the
payment of minimum guaranteed charges has no basis or merit
of acceptance. In this connection, our attention has been
drawn by the counsel on either side to those materials and
particulars placed along with the counter affidavits/Return
of the Board filed before the High Court, the annexures
thereto and some of the correspondence between the officers
of the Board and the consumers concerned. Unfortunately,
even the Division Bench, before which the matters were
posted for further hearing and disposal pursuant to the
opinion given by the Division Bench, did not undertake to
adjudicate this vital aspect of the issues involved which,
in our view, became very much relevant and essential in the
light of the opinion of the Full Bench. Apparently, on
account of the fact that the Full Bench confined the
operation of its decision for future application only, and
the liability for the periods under challenge therefore
stood governed by the position of law as declared by the
decision in AIR 1993 MP 118 (supra) which held the field,
the Division Bench might have thought such an exercise to be
superfluous. But, in the light of our conclusion that, as
the matter stands, on the basis of the existing clauses in
the contract as well as the Tariff notification the minimum
guarantee assured was of the monthly consumption equivalent
to 40% load factor of the contract demand which obligated
the Board also to ensure supply at least to that extent to
insist upon the payment of the minimum charges, it becomes
necessary to undertake an exercise, to decide in individual
cases, the question of actual supply said to have been made
in order to find out whether the units of energy to the
extent of minimum of 40% of the contract demand has been
made available for consumption. For this purpose, these
cases have to be necessarily and are hereby remitted to the
High Court, for being restored to their original number to
find out the actual position about claim/dispute relating to
the supply of energy equivalent to 40% load factor of the
contract demand. Wherever the High Court finds this fact in
favour of the Board, the consumer has to pay the minimum
guaranteed consumption charges as claimed, without any
further challenge to the said liability. Both parties shall
be at liberty to substantiate their respective stand in the
light of the materials already on record or that may be
produced further before the High Court in the relegated
proceedings.
So far as the challenge made to the judgment of the
Full Bench of the High Court, in confining its operation and
applicability only for future period, Shri G.L. Sanghi,
learned counsel, followed by the others have strongly
contended that the High Court as such cannot apply the
principle of prospective over ruling. Reliance in this
regard has been placed upon the decision reported in State
of H.P. & Others vs Nurpur Private Bus Operators Union &
Others [1999 (9) SCC 559] to which one of us (B.N.Kirpal,
J.) was a party. Passing reference has been made to the
decision in Golak Nath vs State of Punjab (AIR 1967 SC 1643)
and the observation contained therein that the doctrine of
prospective overruling can be invoked only in matters
arising under the Constitution and that it can be applied by
the Supreme Court of India. The decision in Golak Naths
case as such was subsequently overruled by the decision
reported in Kesavananda Bharati vs State of Kerala (AIR 1973
SC 1461) though not specifically on this point. Reliance
has also been placed upon the decision reported in M/s
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 14 of 14
K.S.Venkataraman & Co. vs State of Madras (AIR 1966 SC
1089) even to contend that if the High Court had no such
power, this Court while hearing an appeal from such judgment
of the High Court, will equally cannot exercise such powers.
This submission of the learned counsel overlooks the vital
fact in that case that not only the High Court was found to
exercise under Section 66 of the Income Tax Act, 1922, a
special advisory jurisdiction the scope of which stood
limited by the section conferring such jurisdiction but even
the appeal to the Supreme Court having been made only under
Section 66 A (2) of the said Act was noticed to hold that
the jurisdiction of this Court also does not get enlarged
and that the Supreme Court can also only do what the High
Court could do. Apart from the fact that the writ
jurisdiction conferred upon High Courts under Article 226 of
the Constitution does not carry any restriction in the
quality and content of such the powers, this Court could
always have recourse to the said doctrine or principle or
even dehors the necessity to fall back upon the said
principle pass such orders under powers which are inherent
in its being the highest court in the country whose
dictates, declaration and mandate runs throughout the
country and binds all Courts and every authority or persons
therein and having regard to Articles 141 and 142 of the
Constitution of India. The Appellate powers under Article
136 of the Constitution itself would also be sufficient to
pass any such orders. This Court has been from time to time
exercising such powers whenever found to be necessary in
balancing the rights of parties and in the interests of
justice. [vide: Union of India vs Mohd. Ramzan Khan 1991
(1) SCC 588; Managing Director ECIL vs B. Karunakar &
Others 1993 (4) SCC 727; India Cement Ltd. vs State of
Tamil Nadu AIR 1990 S.C.85.] The decision reported in
1999(9) SCC 559 (Supra) at any rate is no authority for any
contra position to deny such powers to this Court.
The peculiar facts and circumstances of these cases
and the interests of justice, in our view, necessitate the
application of the Law declared therein only prospectively.
The electricity Board is a public authority of the State
engaged in the generation and supply of electrical energy at
concessional rates to different class and category of
consumers in the State. The construction placed by us is
likely to have serious and adverse impact upon the finances
and the economic viability of the scheme underlying tariff
and minimum guarantee charges already determined. It is
impossible for the Board, at this point of time to make up
or change the pattern of tariff retrospectively to retrieve
itself in this regard for the past period. The construction
and execution of various developmental schemes and works are
likely to suffer thereby a serious set back also. Keeping
in view all these aspects we will be justified in declaring
that the law declared in these cases shall be for future
application only and not for the earlier period.
For all the reasons stated above, the appeals are
disposed of in the light of the directions and observations
contained herein and the High Court shall restore the
proceedings to its original file and dispose of the same in
accordance with the directions contained in this judgment.
The parties will bear their respective costs.