Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 24
PETITIONER:
S. P. BHATNAGAR ETC.
Vs.
RESPONDENT:
STATE OF MAHARASHTRA
DATE OF JUDGMENT04/01/1979
BENCH:
SINGH, JASWANT
BENCH:
SINGH, JASWANT
REDDY, O. CHINNAPPA (J)
CITATION:
1979 AIR 826 1979 SCR (2) 875
1979 SCC (2) 535
ACT:
Prevention of Corruption Act, 1947 s. 5(1) (d) & s.
5(2)-Scope of-Proof of guilt based on circumstantial
evidence-Tests for deciding.
HEADNOTE:
Both the appellants were officers of Indian Oil
Corporation. The Corporation invited tenders from
experienced contractors for rock cutting, filling and
levelling of certain land acquired by it. On the notified
date it opened the tenders received from eleven contractors.
But in the meantime since it made a change in the
specification of work to be done it asked the tenderers to
submit revised tender. The direction to submit fresh tenders
was restricted only to the original 11 tenderers. Even so it
was alleged that a tender form was issued by the appellants
to A-4, who was not one of the 11 tenderers. there was again
a change in the specification of the work to be done at the
suggestion of foreign collaborators. The appellants were
alleged to have asked the concerned officers of the
Corporation to make a fresh survey along with A-4, keeping
in view the suggestion of the foreign collaborators.
Eventually the contract was given to A-4. The prosecution
alleged that (1) the conduct of the appellants showed their
keenness to have the contract entrusted to A-4. (2) the
issue of work order was inflated with figures relating to
rock cutting and filling; and (3) the appellants removed
certain original documents from the departmental files and
substituted in their place fabricated material.
The appellants who were charged with offences under s.
120B and s. 109 IPC and s. 5(2) read with s. 5(1)(d) of the
Prevention of Corruption Act, 1947 were convicted and
sentenced to undergo imprisonment.
On the question whether the appellants had been rightly
convicted under s. 5(1)(d) of the Prevention of Corruption
Act.
Allowing the appeals,
^
HELD: 1. An analysis of the circumstantial evidence
adduced by the prosecution did not lead to the unerring
certainty that the appellants acted with any dishonest or
corrupt motive or abused their position. [904 F]
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 24
2. (a) It is well settled that abuse of position, in
order to come within the mischief of s. 5(1)(d) of the Act,
must necessarily be dishonest so that it may be proved that
the accused caused deliberate loss to the department.
Further it is for the prosecution to prove affirmatively
that the accused, by corrupt or illegal means or by abusing
his position, obtained any pecuniary advantage for some
other person. [892 G; 893 A].
(b) Again, the fundamental rule relating to the proof
of guilt based on circumstantial evidence is that there is
always danger that conjecture or suspicion might take the
place of legal proof. In such cases the mind is apt to take
a pleasure in adapting circumstances to one another and even
in straining them a
876
little, if need be to force them to form parts of one
connected whole and the more ingenious the mind of the
individual the more likely it is, in considering such
matters, to over-reach and mislead itself to supply some
little link that is wanting, to take for granted some fact
consistent with its previous theories and necessary to
render them complete. [893 B-D].
(c) In cases where the evidence is of a circumstantial
nature, the circumstances from which the conclusion of guilt
is to be drawn should in the first instance be fully
established, and all the facts so established should be
consistent only with the hypothesis of the guilt of the
accused. Again, the circumstances should be of a conclusive
nature and should be such as to exclude every hypothesis but
the one proposed to be proved. In other words there must be
a chain of evidence so far complete as not to give any
reasonable ground for a conclusion consistent with the
innocence of the accused and it must be such as to show that
within all human probability the act must have been done by
the accused. [893 D-F].
M. Narayanana Nambiar v. State of Kerala, [1963]
Supp. 2 SCR 724; Major S. K. Kale v. State of
Maharashtra, AIR 1977 SC 822; Hanumant Govind
Nergundkar v. State of M.P., [1952] SCR 1091, AIR 1952
SC 343; Palvinder Kaur v. State of Punjab, [1953] SCR
94: AIR 1952 SC 354; Charan Singh v. State of U.P., AIR
1967 SC 529; referred to.
(d) The principle that inculpatory fact must be
inconsistent with the innocence of the accused and incapable
of explanation on any other hypothesis than that of guilt
does not mean that any extravagant hypothesis would be
sufficient to sustain the principle, but that the hypothesis
suggested must be reasonable. [893 G].
Govinda Reddy v. State of Mysore, AIR 1960 SC 29;
referred to.
In the instant case the conduct of the appellants in
preferring A-4 to any new contractor did not savour of
dishonest intentions on their part. Although the notice was
sent by registered post to the 11 original tenderers there
is nothing in that notice or elsewhere on the record to
indicate that other contractors were precluded from
submitting their tenders or that the corrigendum extending
the date for submission of the tenders was neither intended
to be published nor was it actually published. The High
Court had missed this fact. The High Court was also wrong in
thinking that out of the nine contractors who submitted
their revised tenders eight were from the original nine
tenderers and the ninth was A-4. In fact five of the
contractors that submitted the fresh tenders were fresh
tenderers. Moreover none of the officers of the Finance and
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 24
Engineering Department of the Corporation who handled the
file relating to the grant of contract ever raised any
objection regarding the improper reception or entertainment
of A-4’s tender. This showed that there was nothing wrong
about the issue of tender Form to A-4 or its entertainment
by the appellants. The contract in question was not a
specialised job requiring any extra ordinary skill. A-4 was
the Corporation’s old and tried contractor who had
previously executed a number of works including rock
cutting.
(2) Though it cannot be gainsaid that the second
appellant had been extremely negligent in not scrutinising
the papers, he affixed his signature in a routine manner to
the work order prepared by his subordinates without
realising
877
the importance of his act, placing implicit faith in the
integrity of the latter. [900 E-F]
(3) There is no clear, cogent and convincing evidence
to show that the appellants had a hand in the removal of the
level plans from the departmental file relating to the
contract and substitution of the faked plans. [900 G].
JUDGMENT:
CRIMINAL APPELLATE JURISDICTION: Criminal Appeal Nos.
346 and 387 of 1975.
Appeals by Special Leave from the Judgment and Order
dated 6-8-75 of the Bombay High Court in Criminal Appeal No.
1005 and 1006 of 1973.
Lalit Chari, P. R. Guna, A. K. Srivastava and Vineet
Kumar for the Appellant in Crl. A. No. 387/75.
R. L. Kohli, P. P. Rao, R. C. Kohli and R. Nagarathnam
for the Appellant in Crl. A. No. 346/75.
V. S. Desai, H. R. Khanna and M. N. Shroff for the
Respondent in both the appeals.
The Judgment of the Court was delivered by
JASWANT SINGH, J.-The above noted two criminal appeals
which are directed against the common judgment and order
dated August 6, 1975 of the High Court of Judicature at
Bombay affirming on appeal the judgment and order dated
August 6, 1973 of the Special Judge, Greater Bombay,
convicting S. P. Bhatnagar, appellant in the aforesaid first
appeal, (hereinafter described as A-1) under s. 120B read
with sections 409 and 109 of the Indian Penal Code and s.
5(2) of the Prevention of Corruption Act, 1947, and
sentencing him to six months simple imprisonment on each of
the said two courts as well as convicting A. S.
Krishnaswamy, appellant in the aforesaid second appeal
(hereinafter described as A-2) under the aforesaid two
counts but reducing his sentence from nine months’
imprisonment to six months simple imprisonment on each one
of those counts, shall be disposed of by this judgment.
Briefly put the case as set up by the prosecution was:
In 1964, the Indian Oil Corporation (hereinafter
referred to as ’the Corporation’) which is a Government
owned company, decided to purchase 13 acres and odd of a
hilly tract of land situate in village Mahul in Trombay
(Bombay) from the Tatas for the purpose of erecting black
furnace oil storage tanks and construction of administrative
buildings. After the area was taken over by the Corporation
Varandani (P. W. 20), Junior Engineer of the Corporation
surveyed the land in October, 1964, under the directions of
A-1 and A-2, the Engineering Manager and Senior Engineer
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 24
respectively of the Engi-
878
neering Department of the Marketing Division of the
Corporation with a view to find out the extent of rock
cutting and filling which might be required to be done for
levelling the area of 7 acres out of the said tract of land.
The kacha level plan (Exh. 125) and worksheets prepared by
Varandani on October 13, 1964 and November 3, 1964
respectively during the course of his aforesaid survey
(which were signed by A-1 and A-2, showed that 16,80,000
cft. of rock cutting work and 8,00,000 cft. of filling work
would have to be done to suit the purpose for which the land
was acquired. Estimate (Exh. 27) prepared by Varandani
indicated that expenditure at the rate of Rs. 30/- per 100
cft. for rock cutting and Rs. 10/- per 100 cft. for filling
would have to be incurred. Pucca tracing (Exh. 34) of level
plan (Exh. 125) and copies thereof signed by A-1 and A-2,
and contour plan prepared by Varandani and approved by
Engineering Manager were kept on the record. On the basis of
the survey and the estimate of expenditure made by
Varandani, notice (Exh. 28) inviting tenders from
experienced civil contractors for rock cutting, filling and
levelling of the land in question was prepared by A-2 on
February 2, 1965, and was forwarded (under his signatures)
by A-1 to the Finance Department for approval on February 5,
1965. After the approval of the Finance Department, the
Public Relations Officer of the Corporation by his letter
(Exh. 29) dated February 11, 1965 requested Times of India,
Indian Express and Free Press to publish the tender notice
(Exh. 28) wherein it was stated that the tenders which
should reach the Corporation by 2.30 P.M. on March 2, 1965
would be opened at 3.00 P.M. on that date. In response to
this notice eleven firms of contractors including Ram & Co.
submitted their tenders. N. N. Desai (hereinafter described
as A-4) however abstained from submitting his tender. In the
meanwhile, it was decided that instead of having stack
measurement as provided in Exhibit 28, it would be desirable
to have the measurements on the basis of differences between
the existing and finished levels. Accordingly, on March 5,
1965, the aforesaid eleven tenderers were asked to submit
revised tenders on the basis of the amended tender notice by
March 15, 1965.
Although fresh tenders were restricted to the original
eleven tenderers, a tender form was issued to A-4 in
response to the application made by him on March 8, 1965. On
opening the tenders on March 15, 1965, it was found that
five out of the eleven original tenderers and four new ones
including A-4 had submitted their tenders, that the tender
of Ram & Co. whereby it had quoted Rs. 28/-per 100 cft. for
cutting work and ’nil amount for filling was the
879
lowest and that the second lowest tender was of A-4 who had
quoted Rs. 26/- per 100 cft. for cutting and Rs. 6/- per 100
cft. for filling work. Thus, the actual amount as per
quotation of Ram & Co. was Rs. 4,70,400/- and that of A-4
was Rs. 4,84,800/- for 16,80,000 cft. of cutting work and
8,00,000 cft. of filling work. On discovering that the
tender of his firm was the lowest, Roshan Lal, a partner of
Ram & Co. addressed communication dated March 20, 1965 to
the Managing Director of the Corporation requesting him that
the aforesaid job of rock cutting and filling be entrusted
to his firm in view of its working experience detailed
therein but handed over the same to A-1. At or about this
time, Messrs Labitos Oil Fields Limited, a British firm whom
the Corporation was trying to collaborate in its project
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 24
advised the Corporation that instead of three levels
(steppings) which had been planned as per cantour map (Exh.
34) there should be a single level and instead of the survey
being on the basis of 100 ft. spacing as done earlier by
Varadani, it should be on the basis of 10 ft. spacing.
Accordingly A-1 and A-2 told Varadani (P.W. 20) and S. D.
Vaidya, another Assistant Engineer (hereinafter described as
A-3) to make a fresh survey alongwith A-4 according to the
advice of Messers Labitos Oil Fields Limited as it had been
almost decided to entrust the aforesaid work to A-4.
Pursuant to the instructions of A-1 and A-2, B. N. Desai, a
representative of A-4 was associated with the revised survey
which was carried from March 21 to March 26, 1965. As a
result of the joint survey, kacha level plan (Exh. 22) and
work-sheet (Exh. 23) were prepared by A-3 under the
directions of Varandani. As a result of this survey, it was
found that rock cutting and filling would have to be done to
the extent of 23,30,454 cft. and 31,500 cft. respectively as
against 16,80,000 cft. and 8,00,000 cft. respectively as
found as a result of the earlier survey. Notwithstanding the
large variations in the cutting and filling work which
required to be done as a result of the revised joint survey,
the Engineering Department did not invite fresh tenders but
instead prepared another comparative statement on the basis
of the rates quoted by Ram & Co. and A-4 in their tenders
opened on March 15, 1965 and showed therein that the tender
of A-4 had turned out to be the lowest and that of Ram & Co.
to be the second lowest. On April 7, 1965, A-2 drew up
tender committee proceedings (Exh. 16) as reproduced below
and got them signed by A-1 in the hope that the
recommendations made therein would be accepted by
Srivastava, (P.W. 5) the Financial Controller and Patel, the
Operation Manager of the Corporation, who were the other
members of the Tender Committee, in addition to A-1 and
finally by Gopal Krishan, the then Chairman of the Company
:-
880
"Ref. No. ENG/ASK/Q 250 April 7, 1965.
Subject : Tender Committee proceedings for the finalisation
of rock cutting, levelling of plot, taken over
from M/s. Tata at Bombay.
(1) We had taken over 13.5 acres of land from M/s.
Tata Power House at Trombay. It was intended to level
this plot of land and recover about 7 acres of land by
cutting and levelling in order to put up our Black
Storage tanks and other allied facilities. Due to the
uneven terrain, it was decided to have two steppings so
that the storage tanks may be installed at a higher
level and the remaining administrative blocks, were
house stores etc., at a lower level. Accordingly,
Public Tenders were invited for rock cutting and
filling this area on 100 cft. basis.
(2) Subsequently, M/s. Lobitos Oil Fields Ltd.
Ellesmere Port, Wirral, Cheshire, had negotiations with
us for putting up a Transformer Oil Blending Plant at
this site. The representatives of the above firm during
their discussions with C. & S. M. and M. E. (accused
No. 1) stated, that they would like to have only plain
piece of land instead of steppings as was decided by us
previously. This will entail additional cutting and
minimise the quantity of filling.
(3) Our estimated quantity previously was
16,80,000 cft. of cutting and 8,00,000 cft. of filling.
As per the revision in the levels to be maintained at
this site that the total quantity of cutting comes to
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 6 of 24
23,30,456 cft. The quantity of filling comes to 31,500
cft. The total estimated cost for the original work was
Rs. 6,13,200/-.
A comparative statement has been drawn as per the
tendered rates quoted by the various parties and the
position of the first three is as follows:-
____________________________________________________________
S. Name of Contractor Qty. Rate Amount Total
No. %Cft.
____________________________________________________________
1 N.N. Desai Cutting 23,30,450
26/- Sd. 605917 607807
Filing 31500 Cft. 1890
6/-
2 Ram & Co. Cutting 2330450 652526 652526
28/- Cft.
Filing 31500 -
Cft. free
3 Library Construction Cutting 2330450 652526
28/- Cft. 655676
Filing 31500 Cft. 3150
____________________________________________________________
881
M/s. N. N. Desai, Contractor are the lowest. The Tender
Committee therefore recommends that this work may be
allotted to M/s. N. N. Desai, Contractor at their
quoted rate of Rs. 6,07,807/- being the lowest
tenderer.
Sd/-
(S. P. Bhatnagar)
M. E.
(A. K. Srivastava)
F.O.
(H. B. Patel)
O.M.
Approved
(P. A. Gopalakrishnan)
Chairman."
Contrary to the expectations of A-1 and A-2, Srivastava
(P.W. 5) refused to be a party to the Tender Committee
recommendations. Ignoring not only the opposition of
Srivastava and the suggestion of the Accounts Officer of the
Finance Department and the Assistant Finance Controller of
the Corporation made vide Exhibit 68 and Exhibit 31
respectively while processing the tender committee
proceedings that in view of the fact that both the quantity
and value of the work had increased substantially as a
result of the revised survey, it would be fair and proper to
ask all the contractors who had responded to the tender
notice to re-submit their quotations but also the offer made
by Ram & Co. (which possessed the requisite skill and
equipment) to execute the contract at the lower rates of Rs.
20/- per 100 cft. for rock cutting and Rs. 15/- per 100 cft.
for filling as well as the flat refusal to reduce his rates
given by A-4 during the negotiations conducted at the
suggestion of the Accounts Department of the Corporation on
April 17, 1965 with the three contractors mentioned in
Exhibit 16, A-2 carried on, in pursuance of the conspiracy
entered into between himself and A-1 and A-4 fresh
negotiations with A-4 on or about April 20, 1965 without
associating any member of the Finance Department and
persuaded him to accept the lowest revised rates offered by
Ram & Co. although he did not possess the requisite
experience in and equipment for rock cutting and filling and
by passing the Financial Controller forwarded the papers to
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 7 of 24
the Operation Manager who not being conversant with the
proceedings supported A-2 for entrusting the contract to A-4
at the lowest rates offered by Ram & Co. On the Tender
Committee recommendations reaching him in circulation.
Srivastava put on record his bold and emphatic protest but
eventually reluctantly gave his con-
882
currence to the recommendations made by A-1 and the
Operation Manager as is evident from the concluding sentence
of the Note:
"The case is recommended for acceptance of the
Chairman only because the Engineering Manager has
certified that he would not be able to accept any
responsibility about the deadline if work is not given
to Desai."
Although according to A-2’s note (Exh. 33) dated April
19, 1965, the Coordinator and Sales Manager was keen to have
the site developed as early as possible, the latter held up
the matter for nearly three months in the vain expectation
that the work would be done free of cost either by the
Government of Maharashtra or the Bharat Sevak Samaj and it
was not before July 15, 1967 that he gave his approval to A-
1’s proposal to award the contract to A-4 whereafter
accepting the said proposal the Managing Director of the
Marketing Division and Chairman of the Board of Directors of
the Corporation accorded sanction to the entrustment of the
work to A-4. On receipt of the sanction, A-1 forwarded the
papers with his endorsement to the Financial Controller on
July 29, 1965. On July 30, 1965, work order (Exh. 19)
manifesting quantity of rock cutting work as 29,30,450 cft.,
filling work as 90,000 cft. and value of the work as Rs.
5,99,590/- as against the corresponding figures of 23,30,450
cft., 31,500 cft. and Rs. 4,70,000/- respectively as
specified in the final sanction which was based on the
aforesaid level statement (Exh. 22) and work sheet (Exh. 23)
was prepared and handed over by A-2 to A-4. Copies of the
work order were also endorsed by A-2 to the Bills Section of
the Engineering Department and the Accounts Section of the
Finance Department of the Corporation with the endorsement
"the above has Chairman’s approval on our note of even
reference dated 7th April 1965. Please have the agreement
executed. Earnest money of unsuccessful tenderers may also
please be refunded early." On July 30, 1965, formal contract
(Exh. 74) mentioning only the number and date of the work
order in the blank columns of the printed form was prepared
and signed by A-4 and a representative of the Company. The
joint level statement Exhibit 22 and the work sheet Exhibit
23 in respect of the joint survey made between March 21 and
26, 1965 for ascertaining the extent of rock cutting and
filling which formed the basis for invitation of tenders and
the final sanction in favour of A-4 were not only left
unsigned by the concerned but were actually removed from the
file and were substituted by spurious level plan (Exh. 24)
and its copy (Exh. 38) which were fabricated by A-3 to
justify the inflated figures of rock cutting and filling
work mentioned in the work order (Exh. 19) dated
883
July 29/30, 1965. On August 19, 1965, fabricated level plans
(Exhibits 24 and 38) prepared by A-3 were sent to A-4 as
annexures to Exhibit 106 which ran as under:-
"We are enclosing herewith two prints of spot level of
land area to be dressed and levelled at our Trombay
plot.
The whole plot should be brought to a level of
102.00 as directed.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 8 of 24
Please return to us a copy of the Blue Print
showing spot levels duly signed as a token of
acceptance of the same for payment."
While A-4 retained one of the spurious plans viz.
Exhibit 38 with himself, he returned the other viz. Exhibit
24 after putting his initials thereon. Thereafter A-3
endorsed on the letter Exhibit 106 that ’the print signed by
A-4 should be filed by Sukhtankar (P.W. 13) who is in charge
of the filing section.’ Accordingly, Sukhtankar filed
Exhibit 106 alongwith Exhibit 24 in the Bill Section. The
actual rock cutting operations commenced with effect from
August 1, 1965 and on August 27, 1965, A-4 prepared and
submitted the first running bill (Exhibit 51) indicating
that 8,00,000 cft. of cutting work and 80,000 cft. of
filling work had been completed. This bill was accompanied
by the certificate of A-3 reading as under :-
"The measurements on which column No. 3 of this
bill are based were taken by me on 24-8-65 and recorded
at pages of MMC No. 7201. Certified that the quantities
of work actually executed as shown in column No. 4 has
actually been done and in no case less than the on
account payments claimed."
The above certificate was countersigned by A-2 on
August 26, 1965. A-2, A-3 and A-4 also signed measurement
certificate (Exhibit 52) which read as follows:-
"We certify that the measurements given above are
the actual works carried out in accordance with the
drawings and specifications as indicated in the work
order referred to above."
On the basis of these certificates, the first on
account running bill was passed and paid for. Thereafter the
second and third running bills and measurement certificates
Exhibits 53 and 54 dated Septem-
884
ber 16, 1965 and November 17, 1965 respectively claiming
that the additional cutting work of 5,00,000 cft. and
8,00,000 cft. had been done were likewise prepared by A-4
and signed by A-3 and counter-signed by A-2. The fourth
running bill and measurement certificate (Exh. 55) dated
February 22, 1966 claiming that additional work to the
extent of 7,00,000 cft. had been done was prepared by A-4
and signed by A-3. This bill which was countersigned by K.
S. Joshi, another Senior Engineer who was put incharge of
the Project in the absence of A-2 who had been transferred
to Delhi was also paid.
On November 8, 1966, one Gurunath Naik (P.W. 17) who
was working as a Junior or Assistant Engineer for some time
in Bombay and for the remaining period at Allahabad, Kanpur
and Mugalsarai was called by A-1 and asked to see Ramrao,
the then Junior Engineering Manager. Accordingly Naik met
Ramrao who directed him to go to the spot and have the level
drawings. Pursuant to this direction, Naik went to the site
for spot verification and reported to Ramrao vide Exhibit 18
that excepting at one place where he got a level of 102-9
nowhere else did he get a level of 102. Naik also reported
that as against an area of 7.4 acres which had to be
levelled hardly an area of 4.8 acres was attempted to be
levelled. On December 30, 1966, A-4 submitted his final bill
(Exh. 56) claiming to have completed the work by August 11,
1966. This bill bore the certificate dated December 29, 1966
of A-3 to the effect that the measurements on which column
No. 3 of the bill was based was taken by him on that date,
and had been recorded in the measurements of the M.B.M.C.
book. A-3 also recorded a further certificate to the effect
that the work had been completed 100% according to the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 9 of 24
specifications and drawings. This certificate of A-3 was
followed by another certificate of A-4 that he accepted the
above certificate and certified that the amount of payment
which he received on that bill would be in full and final
settlement of all his claims in respect of the work
excepting the refund of his security deposit. By this bill,
A-4 claimed to have done 3,84,720 cft. of cutting work and
18,200 cft. of filling work in addition to the work covered
by the four earlier running bills. Thus A-4 claimed to have
done 31,84,720 cft. of rock cutting work and 98,200 cft. of
filling work. On this bill, which bore the certificates of
A-3 and A-4 was countersigned by Ramrao on December 30, 1961
and wherein it was falsely claimed by A-4 that the work was
completed on August 11, 1966-although that date was also
much beyond the stipulated date-A-3 recorded the following
note:-
885
"The final bill amounts to Rs. 6,51,674/- and is
in excess of work order amount by Rs. 52,084.
Since this excess is within 10% of the ordered
amount, M.E. may kindly approve."
Accordingly the papers were laid before A-1 who
accorded the desired approval the moment the bill was laid
before him and sent it for payment to the Accounts Officer
ignoring the practice which required all such bills
involving an excess of 10% over the sanctioned amount to be
submitted to the Chairman for sanction. On the bill coming
before the Accounts Department for scrutiny, it pointed out
that since the actual work exceeded the sanctioned amount by
Rs. 52,084/- for which originally the approval of the
Chairman was taken, the excess needed to be regularised by
obtaining his sanction. It was also pointed out that as the
contractor had not completed the work within the stipulated
time, the question of imposition of penalty also required to
be considered. On the pay order being returned to the
Engineering Department, Ramrao, the then Deputy Engineering
Manager, submitted the following reply vide Exhibit 59 dated
January 12, 1967:-
"The work is now completed as required. However to
acquire the required level and gradient, the quantity
of work has increased. The party has now submitted
their final bill for this work amounting to Rs.
6,51,674/- which is in excess by Rs. 52,084/- than the
original amount of work order.
The excess is within 10% of the original estimate,
M.D. is therefore requested to kindly approve the
excess work done and to pass the final bill for Rs.
6,51,674/-.
As per the work order, the work was to be
completed within 4 months (120 working days). However,
the Contractors could not complete this work including
the disposal of the excavated stuff within this time
limit due to the fact that there was no approach
available to this plot. The party has completed the
work expeditiously, after the approach was given to
them by M/s. Tatas.
M. D. is therefore, requested to consider this
aspect and approve the time limit extension upto 11-8-
1966, the date on which the party has completed the
work."
886
On the matter coming back to the Finance Department,
Shende (P.W. 16) pointed out that not only the quantities of
rock cutting and filling work which were found as a result
of the survey made between March 21 and 26, 1965 had been
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 10 of 24
enormously inflated in the work order but the work claimed
to have been done also exceeded the inflated figures
mentioned in the work order. He, therefore, suggested that
the Department might agree to the payment of extra amount to
A-4 subject to A-1’s obtaining the Board’s ratification.
Sometime before March 28, 1967, Krishnaswamy Rajam (P.W. 1),
the Chief Internal Auditor, was summoned by the Managing
Director and the General Manager and was asked to have a
personal talk with A-3 in connection with the matter. On
P.W. 1’s questioning A-3 on March 28, 1967, the latter made
confessional statement (Exh. 21) which is reproduced below
for facility of reference:-
"Regarding rock cutting and filling at Trombay
site I wish to bring to your kind attention the
following:
I was assigned to this job after the
work was started at site by M/s N. N. Desai.
The original estimates for cutting and
filling were 16,80,000 cft. and 8,00,000 cft.
respectively. It was later revised to
23,30,450 cft. and 31,500 cft. for cutting
and filling. I have got the workings for this
revision with me at Ahmedabad. (He refers to
the genuine level statements and plans and
worksheets Exs. 22 and 23 which were prepared
by him under the directions of Varandani
between 21st and 26th March, 1965).
Later on I was advised by my superiors
to give a still further upward revision
giving the quantities as 29,30,450 cft. for
cutting and 90,000 cft. for filling. The work
sheets prepared by me and signed by
contractor only (N. N. Desai) has no bearing
to actual quantities involved. I had merely
acted as asked by my superiors in preparing
worksheets accordingly which has resulted in
this upward revision. I have also given
measurement certificates in this regard in
line with the revised wrong quantities. I
realise now this has resulted in making
excess payments to the contractor. I beg to
be excused for having done such a thing which
was done solely at the instance of my
superiors in Engineering Depart-
887
ment. E.M. (accused No. 1) and Dy. E.M. are
aware of this."
Thereupon P.W. 1 put up the papers before the Managing
Director and the General Manager who advised him to start
investigation on particular lines. During the course of the
inquiry, A-2 told P.W. 1 that the work order which as far as
he remembered was prepared by A-3 was cursorily signed by
him due to heavy rush of work and that while checking the
running bills submitted for payment, he normally checked the
percentage of progress of work certified by the Assistant
Engineer. On further investigation made on April 1, 1967, A-
3 produced the genuine level statement (Exh. 22) and the
work sheet (Exh. 23) before P.W. 1 and told him that the
substitution of the fabricated level statement and work
sheet relating to rock cutting and filling at Trombay was
done at the instance of Joshi, A-2 and A-1 and that they
were aware of the same. To the further question as to what
was the basis for the work order for the figure of 29,00,000
cft. of rock cutting and 90,000 cft. of filling, A-3 told
P.W. 1 that there was no basis for the work order and the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 11 of 24
quantities were fixed to suit sanctioned amount. On a query
being made by P.W. 1 from Ramrao regarding the final bill,
he admitted that he had not personally checked the
calculations and had counter-signed the bill relying on the
accuracy of the measurements shown in the bill which was
prepared by A-3. He further stated that he had not
personally checked the calculations based on the final bill
and initialled joint levels which according to him were
normally done by the Assistant Engineer. During the course
of this inquiry, Murthy (P.W. 18) was deputed by A-1 and
Krishnaswamy (P.W. 1) to go to the spot and find out the
work which had actually been done. Thereupon, Murthy (P.W.
18) submitted his interim report on April 6, 1967 pointing
out that at only one place the level was 103.94 and
elsewhere it remained much more. By his final report (Exh.
44) dated April 20, 1967, Murthy (P.W. 18) pointed out that
actually on the spot only 9,73,000 cft. of rock cutting and
50,000 cft. of filling had been done. After recording the
statements of A-2, A-3 and A-4, Krishnaswamy (P.W. 1)
submitted a detailed report (Exh. 25) on April 8, 1967 to
the Managing Director through the Financial Controller. In
his report, P.W. 1 also pointed out that contour plan/levels
statement which in case of this nature are jointly signed by
the contractor and the representative of the Engineering
Department were not available in the instant case for
inspection and that A-3 had produced a level statement
alleged to have been processed by him and Varandani which
was not signed by any body including A-3’s superiors. P.W. 1
also
888
pointed out in the course of the report that the quantities
of rock cutting and filling shown in the work order were
29,30,450 cft. and 90,000 cft. respectively and that there
was an increase of 6,00,000 cft. of rock cutting
straightaway. Krishnaswamy (P.W. 1) also mentioned in his
report that according to A-3, the level statement giving the
figure of 29,30,450 cft. for cutting and 90,000 cft. for
filling had been signed by A-4.
On the report being put up before the then Financial
Controller, he directed that before proceeding with the
matter, it was necessary to call for the comments of A-1.
Thereupon after calling for a report from Ramrao, A-1 gave
his comments vide Exhibit 178 dated April 17, 1967 wherein
after doubting the competence and qualification of P.W. 1 to
hold the investigation, he offered to send one of the senior
engineers from Western Branch to carry out an independent
survey to find out the quantity of work done by A-4 and
suggested that measurements might be made by reference to
the kacha level statement (Exh. 125), the work sheet (Exh.
126) and the contour plan (Exh. 34) which were checked by A-
2 and approved by him and which must be with the department.
On April 18, 1967, A-1 sent for A-3 and questioned him in
regard to the matter. In the statement penned by A-3
himself, he stated that he changed the levels of drawing of
Trombay plot regarding rock cutting and filling job at the
instance of A-2 and KSJ (i.e. Joshi) but did not inform A-1.
On May 3, 1967, A-1 issued show cause notices to A-2
and A-3 with a view to hold departmental enquiry against
them. By his reply dated May 20, 1967 to the show cause
notice, A-3 stated that he had changed the original contour
plan at the instance of A-2.
On getting information on July 15, 1967 that A-4 was
having some rock cutting done on the site although he had in
his final bill claimed that he had fully completed the work
on August 11, 1966, A-1 and A-2 visited the site along with
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 12 of 24
Lakshmanan, the Operations Manager and finding that the work
of rock cutting was still going on and that the claim of A-4
as certified by A-3 and countersigned by Ramrao about the
work having been completed on August 11, 1966 was apparently
false had the measurements of rock cutting and filling work
taken by Ganapathy. As the measurements taken by Ganpathy
were on the basis of level plans prepared by Tatas in which
the bench mark was 94.5 as against the bench mark of 100 for
the survey in question, the Managing Director had the
measurements taken by M/s R. L. Dalal & Co. The report of
Dalal & Co. showed that the rock cutting work done was
9,60,000 cft. and filling work was 1,96,000 cft. only.
889
On July 28, 1967, the Managing Director issued a charge
sheet to A-1, A-2, A-3 and Ramrao. In his reply (Exh.64)
dated August 4, 1967 to the charge sheet, A-3 submitted that
whatever he did was under the orders of A-1 and the Deputy
Engineering Manager. This time he did not mention A-2 to be
responsible for anything done by him. On the same day i.e.
August 4, 1967, A-1 sent for A-3 in his cabin and questioned
him in the presence of three other officers viz. Roy
Chowdhary (P.W.2), who was the Deputy Financial Controller,
Shriyan (P.W.23), the Assistant Engineer, and Vora, the
Senior Engineer. On this Occasion, A-3 allegedly made
statement (Exh.43) absolving A-1 and throwing the entire
responsibility on A-2. While the three other officers and A-
1 signed the statement (Exh.48) made by A-3, A-3 declined to
sign it and fled away from the chamber on some excuse and
rushed to the chamber of Krishnaswamy, Chief Internal
Auditor whereupon Roy Chowdhary (P.W.2) also followed A-3 to
the chamber of Krishnaswamy. In the chamber of Krishnaswamy,
A-3 resiled from the statement. Having regard to the
position adopted by A-3 in resiling from his earlier
statement of that very day before A-1, Roy Chowdhary
reminded him that in the morning in his presence, he had
stated that it was A-2 who was responsible for asking him to
change the drawing and increase the quantities. To this
question of Roy Chowdhary in the chamber of Krishnaswamy, A-
3 replied in the negative and stated that A-1 called him and
Joshi into his room and instructed him personally to
increase the quantity. When questioned by Roy Chowdhary as
to why he did not come out with that truth in the room of A-
1 in the presence of Roy Chowdhary, A-3 replied that he did
not do so out of fear or A-1.
In his reply to the charge sheet, Ramrao inter alia
stated that he signed the bill (Exh.56) relying on the
certificate of A-3 who had been assigned to the job and
added that according to the practice prevailing in the
Corporation, Senior Engineers were not expected to verify
the measurements. Elaborating his explanation, he stated
that just as Senior Engineer, Doraiswamy could not proceed
to a BPI nor Senior Engineer Vora nor Senior Engineer Chari
could proceed to an installation just to verify the billed
quantities in view of the fact that there were a number of
bills on each work order and so many work orders for each
location. Similarly in the Branches, Senior Engineers who
were controlling the work for so many depots and
installations were not expected to verify the quantities in
each bill; that however, if there was a dispute with the
contractor or there was some other reason to doubt the
correctness of the Assistant Engineer’s certificate, the
Senior
890
Engineer might either take measurements himself or get them
taken by another Assistant Engineer; that subsequent to the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 13 of 24
counter signature by the Senior Engineer, the bill was
passed on to the Engineering Bills Section where the bills
were checked by the Accountant against sanctions, work
order, rates and amounts, deductions for cement A.C. sheets
or other materials supplied and security; deposit etc; that
the Accountant prepared the pay order giving all these
details for signature by a Senior Engineer as far as
possible other than the countersigning Senior Engineer; that
the bill then went to the Accounts Department where it was
subjected to further detailed scrutiny before payment; that
on December 30, 1966 Vaidya brought the bill for Rs.79,
674/- dated December 30, 1966 to him for counter signature;
that it would have normally been put up to K. S. Joshi but
was brought to him as he was not available; that Vaidya was
the Assistant Engineer who had handled that contract from
the time of placing the work order; that the bill was for
the work carried out by the Contractor subsequent to the
previous ’on account bill’ 21-2-66 (nearly 10 months
earlier) i.e. about 3.18 lakhs cft. at Rs. 20/- per 100 cft.
of cutting and 18,200 cft. of filling at Rs. 15/- per 100
cft; that he had visited Trombay number of times in
connection with other works during the period commencing
from August, 1966 and was aware that the Contractor had
carried out approximately that much work during 1966; that
the extra quantity required sanction of competent authority;
that the previous bills passed showed that the major portion
of the work was carried out during the period August to
December, 1965 and about 7 lakhs CFT of cutting during
December, 1965 to February, 1966; that A. S. Krishnaswamy
who placed the work order had countersigned bills upto 21
lakhs cft. of cutting and 80,000 cft. of filling as early as
November 17, 1965 and subsequently K. S. Joshi had
countersigned a bill for an additional 7 lakhs cft. of
cutting and the contractor had already been paid Rs. 5.72
lakhs less security deposit; that he, therefore
countersigned the bill dated December 30, 1966 and passed it
on to M.E. for approval of the extra quantity of cutting;
that M.E. approved on the same date and the bills was sent
to Engineering Bills for scrutiny by the Accountant in
respect of sanctions, work order terms etc; that he also
particularly instructed that the bill should be shown to K.
S. Joshi before the pay order was issued since normally the
bill should have gone to him for counter signature; that the
Accountant carried out his instructions; that the counter
signature did not denote final passing of a bill but only
that it might be proceeded further and subjected to all the
necessary administrative and financial checks before
payment; that all the bills for the work had been certified
by the Assistant Engineer incharge who was fully familiar
with work and the previous bills had been counter-
891
signed by colleagues of status equal to him; that he had no
reasons to suspect any malpractice or mistakes and also
there was no dispute with contractor; that he had exercise
the normal technical checks which were the functions denoted
by counter signature as per the prevailing practice and that
countersignature did not imply correctness of the quantities
certified by the Assistant Engineer (who alone was
responsible for the correctness) in either the current or
previous bills.
When the matter was thus pending, a confidential
information reached Rege, the Deputy Superintendent of
Police, C.B.I. (P.W. 27) who registered the case on December
27, 1967. During the course of investigation, he visited the
office of the Corporation, took charge of all the concerned
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 14 of 24
documents, had the site measured by Shivashankar, Technical
Examiner, Central Intelligence Service, (P.W.4) according to
whom the cutting and filling work done by the contractor was
to the extent of 9,61,000 cft. and 1,50,000 cft.
respectively and after securing the requisite sanction,
prosecuted A-1, A-2 and A-3 and also submitted the charge
sheet against A-4 with the result that all the four accused
were convicted.
In these appeals, we have had the advantage of hearing
full dressed arguments of counsel on both sides who
diligently prepared the case and put across their respective
contentions with great ability.
We must point out at the outset that although the trial
court had clearly acquitted A-1 of the charge under section
409 read with section 120-B and section 109 of the Indian
Penal Code it unfortunately forgot to keep that fact in mind
with the result that while concluding its judgment it held
him guilty on that charge as well. In the circumstances, it
was not open to the High Court in the appeal by A-1 to go
into that charge and reverse the findings arrived at by the
trial court. We will accordingly be concerned with the
question of validity of A-1’s conviction under section 5(2)
read with section 5(1)(d) of the Prevention of Corruption
Act only but so far as A-2 is concerned, we will have to
examine the validity of his conviction under all the
charges. Before examining the sufficiency or otherwise of
the material bearing, on the charges against both the
appellants, we consider it necessary to have a clear concept
of the meaning and ambit of the phraseology "by corrupt or
illegal means or by otherwise abusing his position as public
servant" used in section 5(1)(d) of the Prevention of
Corruption Act, 1947 (hereinafter referred to as ’the Act’)
for the contravention of which the appellants have been
convicted. It will be advantageous in this connection to
refer to two decisions rendered by this
892
Court in M. Narayanana Nambiar v. State of Kerala(1) and
Major S. K. Kale v. State of Maharashtra.(2) In the first
case, Subba Rao, J. (as he then was) while construing clause
(d) of sub-section (1) of section 5 of the Act observed:-
"The pharaseology ’by otherwise abusing his position as
public servant’ covers acts done otherwise than by
corrupt or illegal means by an officer abusing his
position. The gist of the offence under this clause is
that a public officer abusing his position as a public
servant obtains for himself or for any other person any
valuable thing or pecuniary advantage. "Abuse" means
misuse i.e. using his position for something for which
it is not intended. That abuse may be by corrupt or
illegal means or otherwise than those means. The word
’otherwise’ has wide connotation and if no limitation
is placed on it the words ’corrupt’, ’illegal’ and
’otherwise’ mentioned in the clause become surplusage,
for on that construction every abuse of position is
gathered by the clause. So some limitation will have to
be put on that word and that limitation is that it
takes colour from the preceding words along with which
it appears in the clause, that is to say something
savouring of dishonest act on his part. The contention
of the learned counsel that if the clause is widely
construed even a recommendation made by a public
servant for securing a job for another may come within
the clause and that could not have been the intention
of the Legislature. But in our view such inocuous acts
will not be covered by the said clause. The
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 15 of 24
juxtaposition of the word otherwise’ with the words
"corrupt or illegal means" and the dishonesty implict
in the word "abuse" indicate the necessity for a
dishonest intention on his part to bring him within the
meaning of the clause. Whether he abused his position
or not depends upon the facts of each case."
Following the decision in M. Narayanan Nambiar v. State
of Kerala (supra), it was held by this Court in Major S. K.
Kale v. State of Maharashtra (supra) that the abuse of a
position in order to come within the mischief of the section
must necessarily be dishonest so that it may be proved that
the accused caused deliberate loss to the department. It was
further held in this case that it is for the prosecution to
prove affirmatively that the accused by corrupt or illegal
means or by abusing his position obtained any pecuniary
advantage for some other
893
person. It would, therefore, be necessary to find out in
this case as to whether the accused abused their position
and acted dishonestly or with a corrupt or oblique motive in
having the contract in question entrusted to A-4. As the
courts below have rested their judgments on a constellation
of circumstances, it would be well to bear in mind the
fundamental rule relating to the proof of guilt based on
circumstantial evidence which has been settled by a long
line of decisions of this Court. The rule is to the effect
that in cases depending on circumstantial evidence, there is
always the danger that conjecture or suspicion may take the
place of legal proof. In such cases the mind is apt to take
a pleasure in adapting circumstances to one another, and
even in straining them a little, if need be, to force them
to form parts of one connected whole; and the more ingenious
the mind of the individual, the more likely it is,
considering such matters to cover reach and mislead itself,
to supply some little link that is wanting, to take for
granted some fact consistent with its previous theories and
necessary to render them complete.
In cases where the evidence is of a circumstantial
nature, the circumstances from which the conclusion of guilt
is to be drawn should in the first instance be fully
established, and all the facts so established should be
consistent only with the hypotheisis of the guilt of the
accused. Again, the circumstances should be of a conclusive
nature and they should be such as to exclude every
hypothesis but the one proposed to be proved. In other
words, there must be a chain of evidence so far complete as
not to leave any reasonable grounds for a conclusion
consistent with the innocence of the accused and it must be
such as to show that within all human probability the act
must have been done by the accused. (See Hanumant Govind
Nargundkar v. State of M.P.,(1) Palvinder Kaur v. State of
Punjab(2) and Charan Singh v. State of U.P.(3).
The principle that inculpatory fact must be
inconsistent with the innocence of the accused and incapable
of explanation on any other hypothesis than that of guilt
does not mean that any extravagant hypothesis would be
sufficient to sustain the principle, but that the hypothesis
suggested must be reasonable. (See Govinda Reddy v. State of
Mysore(4).
894
Keeping in view the aforesaid construction placed on
section 5(1)(d) of the Act and the principles with regard to
proof of guilt based on circumstantial evidence, let us now
turn to the various circumstances which have been relied
upon by the High Court in holding the appellants guilty and
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 16 of 24
see whether they factually exist and if so whether they are
of such a character as to be wholly incompatible with the
innocence of the appellants and consistent only with their
guilt. In so doing, we purpose to divide the aforesaid
circumstances under the following broad heads and deal with
them seriatim:-
1. The conduct of the appellants evidencing
their keenness to have the contract entrusted
to A-4.
2. Issue of work order (Exh. 19) with inflated
figures relating to rock cutting and filling.
3. Removal of statement of level plan (Exh. 22)
and work sheet (Exh. 23) from the
departmental file and fabrication and
substitution in their place of the fabricated
ones by A-3.
4. Despatch on August 19, 1965 of spurious level
plan (Exh. 24) and its copy (Exh. 38) by A-2
to A-4 as annexures to Exhibit 106.
5. Counter-signing of the on running bills by A-
2.
6. The initialling of the final bill by A-1.
The first circumstance relied upon by the High Court in
this behalf is that though the revised tender notice was
limited to the eleven contractors who had originally
submitted their tenders in response to the Tender Notice
(Exh. 28), the appellants improperly got a tender form
issued to A-4 and entertained by the Tender Committee. It is
true that the copies of Exhibit 15 on which the prosecution
has sought to rely were sent by registered post to the
eleven original tenderers by the Engineering Department of
the Corporation but it cannot be overlooked that there is
nothing in Exhibit 15 or elshhere on the record to indicate
that other contractors were precluded from submitting their
tenders or that the corrigendum extending the date for
submission of the tenders was neither intended to be
published nor was it actually published. It seems that the
attention of the High Court was not drawn to the
communication (Exh. 29) dated March 9, 1965 addressed by
Ranganath, Public Relations
895
Officer, to the Advertisement Manager, Times of India and
others and the corrigendum forming annexure thereto which
ran as under:-
" INDIAN OIL CORPORATION LIMITED (MARKETING DIVISION)
Clarke Road, Mahalaxmi, Bombay-34, WB, India
IN REPLY PLEASE REFER TO PR 31 317
9th March, 1965
To
The Advertisement Manager,
The Times of India, (Bombay)
The Indian Express, (Bombay)
Free Press Journal, (Bombay)
Dear Sir,
Subject: Tender No. 249/65 Corrigendum
Attached is text of an advertisement for IMMEDIATE
Publication utilising the minimum possible space under
Public Notice/Tenders or in its appropriate place.
We would appreciate your treating this request as
URGENT. Thanking you.
Yours faithfully,
Sd/-
(B. V. Ranganath)
Public Relations Officer
Encl: One.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 17 of 24
c.c. Engineering Manager, H.O. with reference to
their inter-office memo No- Eng/ASK dated 9-3-
1965. We are trying to get it published on March
10.
INDIAN OIL CORPORATION LTD. (MARKETING DIVISION)
Corrigendum to Public Tender No. 249/65
The last date for receiving this Tender has been
extended to 15th March, 1965 at 2-30 P.M. and will
be opened the same day at 3-00 P.M."
896
The attention of the High Court also does not seem to
have been invited to the above noted endorsement at the foot
of Exhibit 29.
The High Court also seems to be wrong in thinking that
out of the nine contractors who submitted their tenders in
response to the revised tender notice, eight were from the
original nine tenders and the ninth was A-4. A comparison of
the two lists viz. the one of the original tenders and the
other of those contactors who submitted their tenders in
response to the revised tender notice would make it clear
that five contractors appearing in the second list were
fresh tenderers.
The Financial Controller’s note (Exh. 17) dated April
2, 1965 which appears to be the outcome of some personal
pique itself shows that it was only on April 15, 1965 that
it was agreed between the members of the Tender Committee
that the grant of the contract would be confined to one the
of the three lowest tenderers, one of whom was A-4.
The fact that none of the eleven officers of the
Finance and the Engineering Department of the Corporation
who handled the file relating to the grant of the contract
in question ever raised any objection regarding the improper
reception or entertainment of A-4’s tender by the
Engineering Department is a proof positive of the fact that
there was nothing wrong about the issue of tender form to A-
4 or its entertainment by the appellants.
Thus it is clear that the first circumstance relied
upon by the High Court had no factual existence and could
not be pressed into service against the appellants.
The next finding of the High Court that while Ram & Co.
was best fitted for entrustment of the contract in question
in view of the vast experience and equipment possessed by
it, A-4 did not have any such merit. It is a matter of
common knowledge that rock cutting is not a specialised job
and no extra-ordinary skill or experience is required for
the same and that every civil construction involves some
sort of rock cutting. It is also in evidence that A-4 who
was the Corporation’s old and tried contractor had
previously executed 98 works including the one on the An-top
Hill in Bombay for the Corporation to its entire
satisfication, and out of the aforesaid works many related
to installations which were more complicated than rock
cutting and filling. It would also be noticed that in the
notes put up
897
by them neither Srivastava (P.W. 5) nor Shivananda,
Superintendent, nor Khurana, Assistant Financial Controller
of the Finance Department, nor the Operation Manager ever
pointed out that A14 lacked the requisite experience or
competence which disentitled him to the grant of the
contract. In fact Shivananda and Khurana had suggested as an
alternative to inviting fresh tenders that A-4 should be
asked to reduce his rates in view of the revised figures on
account of which the value of the contract had gone up
considerably.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 18 of 24
It would also be noticed that the High Court while
rightly holding that Exhibit 122 was not delivered to A-1 by
Roshan Lal (P.W. 19) tell into an error in observing that A-
1 had a hand in suppressing it. It seems to have escaped its
notice that at the negotiations conducted on April 17, 1965
with the three lowest tenderers viz. Ram and Co., Liberty
and Co., and A-4 by the Tender Committee, of which P.W. 5
was a prominent member, Roshan Lal was present and while
pressing his firm’s claim to the grant of the contract he
did draw the attention of the members of the Committee to
the contents of Ext. 122 sent earlier by his firm to the
Corporation. This is evident from Roshan Lal’s own admission
that he informed the corporation in writing as to his
experience in the line and whatever he had written he had
also told the concerned officers who were two or there in
number. If A-1 would have had a hand in suppressing Ext. 122
he would not have allowed it is to remain on the file. That
apart a bare perusal of report Ext. 33 which is fairly
detailed is enough to show that neither A-1 nor A-2 was
interested in suppressing or distorting any material fact.
There was, therefore, hardly any justification for the
observation in question.
The third finding of the High Court that the appellants
told Vrindani (P.W. 20) and Vaidya (A-3) that it had already
been decided to entrust the contract to A-4 and in order not
to loose time, a joint survey should be made, is also
erroneous. It is unbelievable that A-1 and A-2 who were pre-
occupied with several projects would go and tell Vrindani
who was three or four steps below them and was admittedly
not a member of the conspiracy nor concerned with policy
matters that it had been already decided to assign the
contract to A-4. The aforesaid briefing attributed to the
appellants also seems to be incredible in view of the fact
that it was only on the basis of the level measurements
taken by P.W. 20 and A-3 during the survey made by them
between March 20 and 26, 1965 that A-4 turned out to be the
lowest tenderer and at the time when the briefing is alleged
to have been given the lowest tender was of Ram & Co.
898
The insinuation implicit in the fourth finding of the
High Court that Exts. 16, 17, 30-33 and 123 led to the
inference that A-1 was the author and architect of the
proposal for acceptance of A-4’s tender, is also
unwarranted. There is nothing in these documents which can
be interpreted to indicate that the appellant was actuated
by any ulterior or corrupt motive or that he was guilty of
any mis-demeanour, irregularity or impropriety. On the
contrary the said documents particularly Exts. 16 and 33,
which like an open book fairly set-out all the facts and
circumstances bearing upon the allotment of the contract in
question including the claim thereto of Ram & Co. not only
manifest, that the procedure referred to by P.W. 1 in his
deposition for inviting and finalizing the tenders was
meticulously followed in the present case, but also
establish A-1’s bona fides. It has also to be borne in mind
that the Tender Committee which comprised of the Operation
Manager and the Financial Controller in addition to A-1 had
only an advisory role to play and the decision to entrust
the contract to a particular contractor lay with the
Chairman of the Board of Directors in consultation with the
coordinator and Sales Manager who was above the Tender
Committee. That the appellant’s proposal favouring A-4 was
in the interest of the corporation both from the point of
view of economy as well as speedy and satisfactory execution
of work and was solely inspired by his concern to avoid the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 19 of 24
sad experience which the corporation had in respect of rock
cutting work at An-top hill with the Kore Brothers which was
a new party is evident from the following endorsement made
on A-33 by H. B. Patel, Operation Manager:-
"In view of the urgency and our past experience
with a new party at An-top hill, I agree to Senior
Engineer’s proposal that we give the job to M/s. N. N.
Desai at the lowest tendered rates."
The fifth finding of the High Court that the appellants
had negotiations on their own with A-4 with a sinister
object is also against the weight of the material on the
record. The act of the appellants in trying to ascertain
from A-4 whether he was prepared to reduce his rates to the
level of M/s. Ram & Co. which seems to have been taken in
consultation and agreement with P.W. 5 was, in our opinion,
guiltless, It would be well to remember in this connection
that Shrivastava P.W. 5 himself admitted in the course of
his deposition that there was practice in their corporation
of asking the second lowest tenderer to match his rates with
the lowest tender. The proposal about the allotment of work
in favour of A-4 was, therefore, not only consistent with
the practice but was also in the interest of the
corporation.
899
In view of the foregoing we are inclined to think that
the conduct of the appellants in prefering A-4 to any new
contractor did not savour of dishonest intention.
Re. 2: Coming to the work order (Exh. 19) containing
inflated figures which is the corner stone of the
prosecution case, it may be pointed out that the prosecution
has not been able to produce any evidence showing the
circumstances under which it was prepared. The observation
od the High Court that the work order must be the creation
of not only A-2 but of A-1 as well seems to be based upon
mere conjecture. It would be noticed that the work order
does not bear the signatures of A-1 and there is nothing to
show that in the normal course, the work order had to come
to A-1 before being issued to A-4 We cannot also in this
connection afford to lose sight of the observations made by
the trial court at page 279 of the Paper Book that ’it is a
common ground that accused No. 1 is not concerned with the
making of the order and that it is also a common ground that
a work order is issued by the Engineer Incharge’. In these
circumstances, it is difficult to understand how the High
Court came to the conclusion that the work order (Exh. 19)
was the creation of not only A-2 but of A-1 as well. It
seems that the finding of the High Court was influenced by
its finding with regard to Exhibits 16 and 33. In view,
however, of our finding with regard to Exhibits 16 and 33,
the observation of the High Court that the work order was
also the creation of A-1 cannot be substained. We will,
accordingly advert to the material on the record with a view
only to see how far it reflects on the bonafides of A-2. The
prosecution has not led any evidence to prove that A-2
dictated or prepared the work order. The proven facts show
that according to the normal practice prevalent in the
department it is not the Senior Engineer like appellant No.
2 who is incharge of the Project that prepared a work order
but an assistant or Junior Engineer in charge of the work
working under him. Although Varandani has in the course of
his deposition tried to suggest that the work order was
prepared by A-2, his suggestion cannot be relied upon in the
face of Exhibit 67 wherein he told P.W. 1 that the work
order was presumably prepared by Vaidya, A-3. It is highly
improbable that on the very day of the grant of the sanction
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 20 of 24
of the contract in question A-2 would take the extremely
hazardous step of inflating the figures to obtain undue
advantage for A-4 specially when he knew that the fraud
would be at once discovered by reference to the sanction
which had been transmitted to the Finance Department.
The prosecution theory that the work order giving
inflated figures was not only signed but was also prepared
by A-2 is also negatived
900
by the following endorsement on the copy of the work order
sent to the Bills and Accounts Sections of the Engineering
Department of the Corporation:
"The above has Chairman’s approval on our note of
even reference dated 7th April, 1965. Please have the
agreement executed. Earnest money of unsuccessful
tenderers may be refunded early."
The above quoted endorsement completely demolished the
prosecution case. If A-2 had been the author of Exhibit 19,
or had suspected that his subordinate would have dared to
inflate the quantities of the work, it is inconceivable that
he would have made the above quoted insertion giving the
particulars of the above mentioned note meant for the
Chairman’s aproval in the copy of the work order addressed
to the Bills and Accounts Sections which would have
furnished a valuable clue for the speedy detection of the
fraud that is alleged to have been perpetrated.
Again if A-2 were really a conspirator who had falsely
inflated the figures of rock cutting and filling in the work
order he would have seen to it that the potential
documentary evidence embodied in Exhibit 125 which showed
the genuine levels on the spot was destroyed or done away
with. The fact that he did not do anything of the kind
raises a strong doubt about his culpability.
Thus though it cannot be gainsaid that A-2 has been
extremely negligent in not scrutinising the papers, it seems
to us that he affixed his signatures in a routine manner to
the work order prepared by his subordinate engineer without
realizing the importance of his act placing implicit faith
in the integrity of the latter.
Re. 3: There is no clear, cogent and convincing
evidence to show that A-1 or A-2 or both had a hand in the
removal of the level plan (Exh. 22) or the work sheet (Exh.
23) from the departmental file relating to the contract in
question and substitution in their place of the faked level
plan (Exh. 24) and work sheet (Exh. 38) which were
admittedly fabricated by A-3. The statements made from time
to time by A-3 in this behalf being contradictory and
discrepant as would be evident from the following table:
____________________________________________________________
S. Date No.of Text of the statement
No the Exhi-
bit
____________________________________________________________
1 28-3-1967 21 The Original estimates for cutting
and filling were 16,80,000 cft. and
8,00,000 cft. respectively. It was
later revised 23,30,450 cft. and
31,500 cft
901
____________________________________________________________
S. Date No.of Text of the statement
No the Exhi-
bit
____________________________________________________________
for cutting and filing.. Later on I
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 21 of 24
was advised by my superior in Engg.
Dept., E and Dy. E.M. to give a
still further upward revision
giving the quantities as 29,30,450
cft. for cutting and 90,000 cft.
for filling.
2 1-4-1967 36 ASK, KSJ and SPB asked me to substi-
tute SHS relating to rock cutting &
filling at Trombay which was
resulted in larger quantities of
cutting and filling and they are
fully aware of it.
3 18-4-1967 39 & 41 I told R. Krishnaswamy when he
called me on 29-3-1967 that A.S.
Krishnaswamy and K.S. Joshi told
me to change the levels of drawings
of Trombay plot regarding rock
cutting/filling job . In reply to
the further query of R. Krishna-
swamy, I told him that I did not
inform M.E. about this and that he
might be knowing.
5 20-5-1967 69 In addition to the statement dated
18-4-1967, I have to submit that I
was asked to change the original
contour, place by A.S. Krishnaswamy,
Senior Engineer.
6 4-8-1967 43 Sometime in September, 1965, A.S.
Krishnaswamy told me to increase
the levels at random and bring the
quality to about 30 lakhs cft. I did
so accordingly.
7 4-8-1967 42 The Engineering Manager called me
and Shri Joshi into his room one day
and instructed me personally to
increase the quantity.
____________________________________________________________
the prosecution ought to have made a serious attempt to
produce K. S. Joshi whose testimony was essential to clear
up the mystery in which the whole affair is shrouded. The
non-production of K. S. Joshi who appears to have been one
of the main actors in the drama has left a lacuna which is
very difficult to bridge. In the present state of evidence,
it is inconceivable that A-1 who admittedly had a
meritorious record of service, had won commendation from the
Board of Directors for designing a tank and saving
considerable sums of money and who was the only Head of
Department to be given three advance increments for his
integrity and efficient work and who had no are to grind
would be a party to the unholy conspiracy for the removal of
genuine level plan and work sheet and their substitution by
spurious ones simply to obtain some pecuniary advantage for
A-4 who was neither his friend nor relative. The position of
A-2 is also
902
not materially different as in his case also the prosecution
has not been able to show that he derived any monetary gain
out of the transaction.
Re. 4 :-A bare perusal of statement contained in
Exhibit 43 which according to H.N. Roy Chowdhary (P.W. 2)
and C. L. Shriyan (P.W. 23) was voluntarily and without any
pressure made by A-3 is enough to show that it was in
September, 1965 that A-3 increased the levels shown in the
original drawings and brought up the quantity of rock
cutting to 30 lakhs cft. This statement totally knocks the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 22 of 24
bottom out of the prosecution case that the spurious level
plan and the work sheet were despatched to A-4 on August 19,
1965 as annexures to Exhibit 106. If the spurious plan and
the work sheet came into existence in September, 1965, it is
difficult to understand how they could be despatched to A-4
alongwith Exhibit 106 on August 19, 1965. The conclusion,
therefore, is irresistible that when the communication (Exh.
106) was despatched to A-4, it was not accompanied by
fabricated level plan (Exh. 24) and work sheet (Exh. 38) but
by the genuine ones viz. Exhibits 22 and 23 and that it was
later on that the genuine ones were removed and retained by
A-3 who during the course of the enquiry by R. Krishnaswamy
(P.W. 1) brought them from Ahmedabad and handed them over to
P.W. 1. The ommission on the part of Shriyan who claims to
be certain that A-3 got the tracings Exhibits 24 and 38
prepared by him in April/May, 1965 to contradict A-3 when he
made the aforesaid statement (Exh. 43) is also intriguing
and lends assurance to the correctness of our conclusion.
Re. 5:-The first thing to be borne in mind with regard
to the measurement certificates on the running bills is that
it is the Assistant Engineer incharge of the work who is
responsible for taking measurements of the actual quantities
of the work executed by the contractor for entering the same
in the measurement book and for recording a certificate that
the measurements given in the bill are of the actual work
carried out on spot in accordance with the Department’s
drawings and specifications. It has also to be remembered
that A-1 had to look after the Corporation’s projects and
installations all over India and A-2 had to look after and
supervise a large number of the Corporation’s projects under
the Western Branch which included installations at
Sabarmati, Ahmedabad, Okha and Kandla in Gujarat and Sewri,
Wadala and Trombay in Maharashtra and parts of Madhya
Pradesh. It cannot also be ignored that according to Ganpati
(D.W. 3) when a Senior Engineer visits the site, he
determines the progress of the work by visual inspection
determining visually the approximate
903
quantity of the work done. All this apart, an examination of
the running bills (Exhibits 51, 53, 54, 55 and 56) shows
that all of them bear the certificates as referred to and
reproduced at page 11 of this judgment. It would be noted
that whereas first three of these bills bear the counter-
signatures of A-2, Bill (Exh. 55) bears the
countersignatures of K. S. Joshi, Senior Engineer and Bill
(Exh. 56) bears the counter-signatures of Ramrao, another
Senior Engineer, who was absolved in the departmental
enquiry. Now the fact that A-2 countersigned the first three
bills does not appear to be material in view of the
following statement made by Ramrao vide Exhibit 107:-
"I had no reason to doubt Shri Vaidya’s figures.
Countersignature of a bill as per our prevailing
practice is not indicative of verification but only
indicates that there is no reason to doubt the
correctness of the figures."
The fact that K. S. Joshi, Senior Engineer, also
countersigned the bill (Exh. 55) which contains inflated
figures and no action was taken against him also lends
assurance to the inference that the counter-signatures were
appended merely as a routine by the Senior Engineers who
seem to have reposed blind and unflinching faith on the
honesty of their subordinates.
Now if Ramrao who countersigned the bill (Exh. 56)
showing the quantity of cutting work as 31 lakhs cft. was
exonerated in the departmental enquiry and no action was
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 23 of 24
taken against K. S. Joshi who made the wrong endorsement in
respect of the measurement on Exhibit 55 or against Vora who
had prepared the note (Exh. 58) showing that the work had
been completed, it is difficult to understand how A-2 could
be treated differently and criminal intention attributed to
him. The finding of the High Court in respect of the third
running bill (Exh. 54) that the very defence of A-2 would
itself furnish the best evidence of the conspiracy involving
A-1 is not correct for apart from other infirmities from
which if suffer, it is well settled that the defence taken
by one accused cannot in law be treated as evidence against
his co-accused.
Re. 6 :-The finding of the High Court that A-1 signed
the bill (Exh. 56) and sanctioned excess amount involved
knowing full well that the bill was not true is also against
weight of the evidence on the record. It cannot in the first
instance be forgotten that it was on July 29, 1965 that A-1
could have had occasion to see the figures of the work for
which sanction was granted by the Chairman of the Board of
Directors and the bill (Exh. 56) was put up to him on
904
December 30, 1967. In the absence of the sanction from which
the genuine figures could have been gleaned, it would not be
reasonable to expect A-1 to remember the sanctioned figures
after the lapse of 17 months specially when it is admitted
on all hands that being the head of the Engineering
Department, he had to tour extensively to supervise several
projects spread all over the country and to discharge
multifarious duties in connection therewith. The bill, it
would be noted was prepared by A-3 and was countersigned by
no less a functionary than the Deputy Engineering Manager,
Ramrao, who was next below A-1 in the hierarchy of the
Department. In the note prepared by him, it was not pointed
out by A-3 that the bill had to go to the Managing Director.
The evidence in the case also shows that A-1 was not
expected to meticulously scrutinize the bill but was
concerned only with the initialling of the note which
although it had passed through several hands did not
indicate that the competent authority to grant sanction for
the excess amount was the Chairman of the Board of
Directors.
It will also be wrong to hold A-1 responsible for
simply initialling the note contained in Exhibit 56 without
examining Ramrao who approved the bill including the note
and also countersigned the measurement certificate before it
came to A-1. In the circumstances, the mere initialling by
A-1 of the bill alongside the note marked for him by A-2 is,
therefore not a circumstance which can unmistakably be said
to point to the guilt of the appellant.
An analysis of the circumstantial evidence adduced by
the prosecution does not in our opinion lead to an unerring
certainty that A-1 and A-2 acted with any dishonest or
corrupt motive or abused their position.
In conclusion we cannot help observing that non-
examination by the prosecution of Ramrao, Joshi, Vora and
Patel who were material witnesses for the unfolding of its
case has left some yawning gaps in the evidence which we
have found very difficult to bridge. If these persons had
been produce many of the points which have remained obscure
and hidden up would have been cleared up.
For the foregoing reasons, we allow the appeals, set
aside the convictions of the appellants and the sentences
imposed upon them and acquit them of the offences with which
they were charged.
P.B.R. Appeals allowed.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 24 of 24
905