MUNICIPAL CORPORATION OF GREATER MUMBAI vs. S.N. THAKKAR CONSTRUCTION

Case Type: N/A

Date of Judgment: 13-02-2019

Preview image for MUNICIPAL CORPORATION OF GREATER MUMBAI vs. S.N. THAKKAR CONSTRUCTION

Full Judgment Text


2019:BHC-OS:4603
Mohite/sg arbp1060­10.doc

                                  IN THE HIGH COURT OF  JUDICATURE AT BOMBAY
ORDINARY ORIGINAL CIVIL JURISDICTION
ARBITRATION PETITION NO.1060 OF 2010
Municipal Corporation of Greater Mumbai .... Petitioner 
vs.
S.N. Thakkar Construction 
Company Private Limited …. Respondents
….
Mr. P.G. Lad, a/w. Mr. R.Y. Sirsikar and Mr. D.S. Shingade, for the
Petitioner. 
Mr. Nikhil Wadikar, a/w. Mr. Pradip Zende, i/b. Mr. S.S. Phadke, for the
Respondent. 
…..
CORAM: S.C.GUPTE, J.
DATED  : FEBRUARY 13, 2019
(Oral Judgement) :
. This arbitration petition challenges an award passed by a
sole arbitrator in the matter of disputes and differences between the
parties   arising   out   of   a   contract   for   construction   for   the   Petitioner
Municipal Corporation. 
2. In 2002, the Petitioner invited tenders for providing and
constructing   diversion   chambers   for   diverting   sewage   from   SWD   to
sewerage   system   at   seven   locations   in   the   city   of   Mumbai.     The
Respondents submitted their offer.  The Petitioner accepted the offer and
issued a work order directing the Respondents to commence the work
from   01.10.2003   and   complete   the   same   by   31.05.2004.     The
                                                                                                                             Pg 1 of 20
::: Uploaded on - 20/07/2019 ::: Downloaded on - 26/06/2024 07:28:57 :::

Mohite/sg arbp1060­10.doc

Respondents were directed to get the work drawings approved before
commencing the work and also to submit a PERT program and seek
approval thereof.  On 08.10.2003, the Respondents submitted a bar chart
and cash flow statement.  (This was after the due date of commencement
of work.)   During the course of the work, the Petitioner wrote several
letters to the Respondents complaining of slow progress as also breaches
of contract on the part of the Respondents and asking the latter for
expediting the work.  It is the case of the Petitioner that on 31.05.2004,
the contract came to an end by efflux of time.   On 09.08.2004, the
Respondents applied for extension of time proposing various conditions,
which, according to the Petitioner, were contrary to the terms of the
contract.  In the alternative, the Respondents requested for finalisation of
accounts on “as is where is” basis.  The Petitioner asked the Respondents
to submit the list of compensatory events with documentary evidence
without prejudice to the right of the Petitioner to grant extension, if any.
It is the Petitioner's case that the Respondents did not submit any details
in response and instead alleged that these details were already available
with the Petitioner.  The Respondents made several allegations claiming
that hindrances were caused to the work by the Petitioner.   In these
circumstances, when the Petitioner sought to invoke the bank guarantees
submitted   for   mobilisation   advance   as   also   for   performance,   the
Respondents offered to pay the amount of the mobilisation advance bank
guarantee after deducting the sum already recovered from their running
account   bills.   The   Respondents   also   submitted   a   pay   order   to   the
Petitioner in lieu of performance bank guarantee.   The Respondents
thereafter   raised   several   claims   including   a   claim   for   wrongful
encashment of bank guarantees under economic duress and financial
                                                                                                                             Pg 2 of 20
::: Uploaded on - 20/07/2019 ::: Downloaded on - 26/06/2024 07:28:57 :::

Mohite/sg arbp1060­10.doc

pressure. Differences and disputes arose between the parties as a result,
which were referred to the learned arbitrator.  The Respondents were the
claimants   before   the   arbitrator,   whereas   the   Petitioner   was   the
respondent/counter claimant.  The Respondents filed in all nine claims.
The   learned   arbitrator,   by   this   impugned   award   dated   04.02.2010,
allowed Claim No.1 (partly), Claims Nos.2 and 3(fully), Claim No.4
(partly), Claim No.8 (partly) and Claim No.9 (partly) and rejected the
counter claim of the Petitioner.  
3.  The award of the Respondents' claims as above has been
challenged by the Petitioner on various grounds.   Learned Counsel for
the Petitioner, however, mainly submitted that the award was based on
no evidence and also was contrary to the documents submitted by the
Petitioner. Learned Counsel submitted that the findings of the learned
arbitrator on the alleged breaches of contract by the Petitioner and in
particular, the delay in issuance of detailed construction drawings, were
contrary to the record as well as the stipulations of the contract.  Learned
Counsel also submitted that the finding of the arbitrator that there was
delay on  the part of the Petitioner  in making the site  available  for
contract work or removing obstructions as also stoppage of work, etc.
were either without evidence or contrary to the record. In particular
reference to the Respondents' claim for loss of profits, learned Counsel
submitted that the award was contrary to public policy of India, since it
wholly disregarded fundamental principles of Indian Law on award of
damages.   It was submitted that out of the contract work of about
Rs.2.70 crores, the Respondents had hardly completed work of about
Rs.16 lakhs.  Learned Counsel contended that in the absence of evidence
                                                                                                                             Pg 3 of 20
::: Uploaded on - 20/07/2019 ::: Downloaded on - 26/06/2024 07:28:57 :::

Mohite/sg arbp1060­10.doc

to suggest that the Respondents were in fact in a position and had kept
themselves ready to complete the contract work, damages for loss of
profits arising from the balance work could not have been awarded by
the arbitrator.  Besides, learned Counsel argued the arbitrator's finding
that   the   Petitioner   was   responsible   for   stoppage   of   work   and   had
committed   breach   of   contract   by   not   permitting   the   Respondent
contractor to complete the work, is clearly perverse and not supported by
any evidence. 
4. So far as Claim Nos.1, 2 and 3 are concerned, these are for
actual   work   done   as  also   extra   work  performed  by   the   Respondent
contractor and refund of performance security and retention amount
based on actuals.  The arbitrator, after taking into account the provisions
of the contract and submissions of  the parties in the light of evidence
placed before him, came to a conclusion that the actual work done as per
th
B.O.Q. and extra items of work done were  reflected in the 5  RA Bill
submitted by the Respondents.  The arbitrator noted that some of these
items were admitted by the Petitioner. The arbitrator considered the
difference between the parties in respect of the other items of work
concerning individual work sites.  After considering the rival cases set up
by the parties, the arbitrator determined that the claim should be worked
out on the basis of measurements recorded by the Petitioner at B.O.Q.
rates   plus   admissible   extra   items,   with   appropriate   deductions.   The
individual   deductions   contested   between   the   parties   were   duly
considered   by   the   arbitrator.   Wherever   there   were   no   joint
measurements, those items were deducted.  So also, wherever any rate or
extra item was to be treated as B.O.Q. rate or item, the arbitrator deleted
                                                                                                                             Pg 4 of 20
::: Uploaded on - 20/07/2019 ::: Downloaded on - 26/06/2024 07:28:57 :::

Mohite/sg arbp1060­10.doc

the same. Thus, after arriving at the total amount of work done including
extra items and giving credit for the amount paid by the Petitioner to the
th
contractor prior to the 5  R.A. Bill, the arbitrator worked out the balance
payable to the Respondents in the sum of Rs.26,27,361/­.   These are
clearly possible views supported by evidence.  Neither the approach of
the learned arbitrator for working out the balance amount payable to the
Respondents for work done nor the actual findings arrived at by the
learned arbitrator could be said to be impossible views, or views which
no fair or judiciously minded person would take, or views that would
shock the conscience of the court.  The award on these claims, therefore,
does not merit any interference.  
5. So far as the enforcement of performance bank guarantee
and withholding of retention amount are concerned, which were the
subject   matters   of   Claim   Nos.2   and   3,   the   arbitrator   came   to   the
conclusion that there was no case for the Petitioner to either encash the
performance bank guarantee or withhold the retention amount from R.A.
Bills due and payable to the Respondents.  No fault can be found with
the award on these two claims.   The Petitioner, having failed to show
that the Respondents were responsible for breach of contract, the refund
of performance security and retention amount ordered by the learned
arbitrator cannot be faulted.  These are all assessments of fact and the
arbitrator's views on these matters are possible views, which do not merit
any interference.
6. When   we   come   to   the   loss   of   profit   claimed   by   the
Respondents, i.e.   the subject  matter  of Claim No.4, the  arbitrator's
                                                                                                                             Pg 5 of 20
::: Uploaded on - 20/07/2019 ::: Downloaded on - 26/06/2024 07:28:57 :::

Mohite/sg arbp1060­10.doc

conclusion that the Petitioner had abandoned the balance work is, in the
very first  place,  contrary  to  the  record  and  based  on  practically   no
evidence.   The    documents considered by the learned  arbitrator for
arriving at this conclusion, namely, Exhibits C­55, C­56, C­57, C­58, C­
60, C­64 and C­67, do not suggest or support the inference drawn by the
learned arbitrator.  Exhibit C­55 is minutes of a review meeting between
the   parties.     It   merely  shows   that   the   contractor   was   instructed   to
mobilise for work at Haji Ali immediately after the scheduled marathon
race   and   pursue   the   matter   of   NOC   with   Traffic   Department   for
commencing the work. This is treated by the arbitrator as stoppage of
work by the Petitioner in the name of the marathon race. It is strange
that express instructions for taking up the contract work immediately
after the marathon race, which was scheduled to be held in a couple of
days,   and   keeping   itself   ready   with   all   permissions   including   traffic
permission by that time so as to commence the work immediately after
the race, are considered to be a breach on the part of the Petitioner by
terming them as instructions for stoppage of work. There is no indication
in the evidence adduced before the arbitrator that the work was stopped
as a result of the marathon race.  Exhibit C­56 is a letter addressed by the
Respondents.   In this letter, the Respondents had claimed that at Kirti
College site, no sewer line was found and arrangements for diverting of
flow were required to be made by provision of P.V.C. pipes and blocking
the arch drain on both sides.  It is not the contractor's case that the work
could not be completed as a result.  This letter also claims that at P. Balu
site, a large size arch drain was wet, which resulted in a more laborious
and time consuming work. This letter was treated as evidence by the
arbitrator of the Petitioner's misrepresentation in drawings.  The whole
                                                                                                                             Pg 6 of 20
::: Uploaded on - 20/07/2019 ::: Downloaded on - 26/06/2024 07:28:57 :::

Mohite/sg arbp1060­10.doc

idea of the letter was to show that there was extra work involved, for
which   the   Respondents   might   charge   extra.   There   was   no   case   of
misrepresentation   even   alleged   by   the   Respondents     in   this   letter.
Exhibit C­60 is a letter by the Respondents.  It is said to be for the Haji
Ali site.  Even this letter does not show that there was any case set up by
the Respondents of any misrepresentation by the Petitioner.  All that it
suggests is that due to site conditions, the drawing had to be revised (in
this case due to the drain being of a larger size as noticed at the site).
There is no indication in the award as to what was the impact of the
particular site condition or need for revised drawings ­ whether or not
the   revised   drawings   were   forwarded   and   when,   and   whether   this
particular grievance resulted into any actionable delay on the part of the
Petitioner employer.   Exhibit C­57 is another letter addressed by the
Respondents. It merely reports that there was no place for storing of
excavated material at Haji Ali site and as per conditions of traffic NOC,
the excavated material had to be immediately removed from the site.
What was claimed was that this item therefore should be treated as an
extra item, to be paid for separately.  One is at a loss to understand as to
how this amounts to any stoppage of work or actionable delay or breach
of   contract   on   the   part   of   Petitioner.     Exhibit   C­58   is   another
communication addressed by the Respondents, which again talks about
variations   necessitated   by   site   conditions.   This   obviously   cannot   be
treated as evidence of any breach on the part of the Petitioner.  Even the
letters at Exhibits C­64 and C­67 do not suggest any breach on the part of
the Petitioner as a result of which the Respondents were prevented from
carrying out the contract work.  These are letters addressed in the course
of the work.  It is natural to expect actual site conditions to be different
                                                                                                                             Pg 7 of 20
::: Uploaded on - 20/07/2019 ::: Downloaded on - 26/06/2024 07:28:57 :::

Mohite/sg arbp1060­10.doc

at times from the suggested drawings and revisions would have to be
made, some of these even entailing extra work, but that is no ground to
show that the Petitioner thereby committed breach of contract, which
resulted in Respondents being denied the opportunity to complete the
work.  The very basis, therefore, for awarding loss of profit is untenable.
There   is   nothing   to   suggest   that   it   was   the   Petitioner,   who   had
abandoned the balance work or denied opportunity to the Respondents
to complete the same.   On these facts, there was no way the learned
arbitrator could have awarded compensation towards loss of profit.
7.    There   is   one   more   serious   challenge   to   the   award   of
damages.  This challenge is on  the ground of determination of quantum
of damages in a rough and ready manner, and by a simplistic thumb rule.
Damages   by   way   of   loss   of   profits   were   calculated   on   a   simple
mathematical calculation of 12 % anticipated profit on the entire balance
work, on the basis of a rate analysis submitted by the Petitioner without
prejudice to its contentions. Learned   Counsel   for   the   Respondents
relies on the Supreme Court decisions in   Dwaraka Das vs. State of
1 2
M.P. ,   M/s.   A.T.   Brij   Paul   Singh   vs.   State   of   Gujarat   and   MSK
3
Projects India (JV) Limited vs. State of Rajasthan .   Learned Counsel
submits that these cases establish that whenever the employer is guilty of
breach of contract or whenever rescission of contract by the employer is
held to be unjustified and the contractor has executed a part of the works
contract, the contractor would be entitled to damages by way of loss of
profits; such claim is legally admissible on proof of breach of contract by
(1999) 3 SCC 500
1
(1984) 4 SCC 59
2
3 (2011) 10 SCC 573
                                                                                                                             Pg 8 of 20
::: Uploaded on - 20/07/2019 ::: Downloaded on - 26/06/2024 07:28:57 :::

Mohite/sg arbp1060­10.doc

the erring employer and without insisting on any strict proof of actual
damages incurred towards such loss of profits.  Learned Counsel submits
that such damages have been awarded on a thumb rule on the basis that
reasonable expectation of profit is implicit in any works contract and its
loss has to be compensated by way of damages if the other party to the
contract is guilty of its breach.
8. The   cases   cited   by   learned   Counsel   do   not   suggest   any
inflexible or absolute rule or proposition of law.  Any award towards loss
of profit would always depend on the facts and circumstances of each
case.  In a case, where the contractor has merely done a negligible part of
his contract work and there is nothing to suggest that the contractor had
kept himself ready with engagement of capital and labour to complete
the entire work and yet he was prevented from carrying out the balance
work on account of a breach on the part of his employer, there is no case
for awarding  loss of profit on a thumb rule such as this.  Profit is usually
an incidence of capital and labour; deployment of these results into or
gives rise to profit. In this particular case, the learned arbitrator has not
gone into the facts of employment of capital or engagement of labour by
the contractor, which was really the subject matter of Claim No.5 (for
idling of resources), because the arbitrator was of the view that claim for
loss of profit could be awarded on a thumb rule. It is not in serious
dispute that a very negligible percentage of work was actually carried out
by the contractor at the stage when the work was stopped.  Out of the
total contract worth of about Rs.2.70 crores, a mere Rs.16 lakhs worth of
work was accomplished out of the B.O.Q. work.  There is no evidence to
suggest that contractor had kept himself ready and in fact was in a
                                                                                                                             Pg 9 of 20
::: Uploaded on - 20/07/2019 ::: Downloaded on - 26/06/2024 07:28:57 :::

Mohite/sg arbp1060­10.doc

position to complete the entire balance work as per the schedule of work
assured to the employer. This is besides the point that there is no case
here, as noticed above, that it was the Petitioner who was actually
responsible for preventing the Respondents from carrying out the balance
work by reason of a breach of contract.
9. In the circumstances, there was really no case for any claim
of loss of profit.  What the learned arbitrator could instead have done
was to consider the contractor's claim for compensation for infructuous
capital     and   labour   expenses.     This   the   learned   arbitrator   did   not
consider, as noted above, since he was considering the case of loss of
profit and awarding the same to the contractor.  The arbitrator's award
on Claim No.4, thus, cannot be sustained and will have to be interfered
with   on   the   ground   of   a   perverse   conclusion,   i.e.   a   conclusion   not
supported by any evidence and also a conclusion in patent breach of
Indian law on damages.  
10. Under Indian law, contained in Section 73 of the Contract
Act, in every case of breach of contract, the only compensation receivable
by the party suffering by such breach is for any loss or damage which
naturally arose in the usual course of things from such breach, or which
the parties knew, when they made the contract, to be likely to result from
the breach of it.
11. Learned Counsel for the Respondents relies on the cases of
Dwaraka Das, A.T. Brij Paul Singh  and  MSK Projects India (JV) Ltd.
(supra), and submits that the contractor would be entitled to claim
                                                                                                                             Pg 10 of 20
::: Uploaded on - 20/07/2019 ::: Downloaded on - 26/06/2024 07:28:57 :::

Mohite/sg arbp1060­10.doc

damages for loss of profit which he expected to earn by undertaking the
works contract, where the party entrusting the work commits a breach of
the contract.  No doubt the contractor is entitled to do so.  Entitlement,
as  a matter of law, is one thing, but the measure of profit and the proof
to be tendered to sustain such claim of profit are quite another.  These
are   not matters of any thumb rule; these have to be   individually
assessed in every given case, and these are essentially matters of facts.  In
Dwaraka Das , the Supreme Court upheld the legal entitlement  of the
aggrieved contractor to be compensated by the erring party.  In  A.T. Brij
Singh ,   the Division Bench of   High Court found 15 per cent of the value
of the balance of the works contract as a reasonable measure of damages
for loss of profit.  That was on the basis of the facts of that case.  The
High Court had earlier considered 15 per cent as  reasonable profit for
another portion of the same road in the vicinity and that was accepted by
the employer State as a fair measure of damages in that case.  The plea
in  A.T. Brij Paul Singh  that the cognate appeal could not be looked into
was, in the premises, found unacceptable by the Supreme Court.   The
Court was of the view that it would be too technical; the work sites being
in the vicinity of each other and the work being of an identical type
between the same parties, the same measure, namely, 15 per cent of the
balance value of the contract found by the High Court could not be said
to be unreasonable.  Even in  MSK Projects India (JV) Ltd.  (supra), the
Supreme Court has reiterated the same principle as stated in   A.T. Brij
Paul Singh .  The Court held that a claim by a contractor for recovery of
damages as expected profit out of the contract cannot be disallowed on
the ground that there was no proof that he suffered actual loss to the
extent of the amount claimed for loss of profits.  In any event, though the
                                                                                                                             Pg 11 of 20
::: Uploaded on - 20/07/2019 ::: Downloaded on - 26/06/2024 07:28:57 :::

Mohite/sg arbp1060­10.doc

Court did say that whilst estimating such damages, the Court should
rather   make   a   broad   evaluation   than   going   into   minute   details,   it
nevertheless reiterated  that what would be the measure of profit would
depend upon the facts and circumstances of each case.  In none of these
cases, the Supreme Court has found 15 per cent or indeed any other
percentage   as   a   reasonable   measure   of   damages   as   a   thumb   rule.
Besides, there is no authority in these, or indeed any other, cases to
support the proposition that just because, whilst accepting the contract
work, the contractor expected to earn a reasonable amount of profit, in
all cases of breach of contract by the employer, without consideration of
peculiar facts and circumstances of the case, and on the basis of the
breach alone, loss of profit ought to be awarded to the contractor as
damages by applying a thumb rule of percentage.
12. On the other hand, the authorities seem to clearly suggest
that the correct measure of damages is in every case a question of
assessment of evidence in the light of the pleas raised.  In  Bharat Coking
4
Coal Ltd. vs. L.K. Ahuja , the arbitrator had awarded 15 per cent of
works contract value as compensation towards loss of profits on account
of prolongation of works.  It was in addition to escalation of wage bills
and price of materials and interest for delayed payments.  The Supreme
Court  found it  difficult  to  accept  that  in  addition  to  escalation and
interest, 15 percent towards loss of profit could be awarded.  The Court
observed that it was not unusual for contractors to claim loss of profit
arising out of diminution of turnover on account of delay in the matter of
completion of work.  The Court held that what should be established in
4 ( 2004) 5 SCC 109
                                                                                                                             Pg 12 of 20
::: Uploaded on - 20/07/2019 ::: Downloaded on - 26/06/2024 07:28:57 :::

Mohite/sg arbp1060­10.doc

such a situation was that had the contractor received the amount due
under the contract, he could have utilised the same for some other
business in which he would have earned profits; unless such  a plea was
raised and established, claim for loss of profits could not have been
granted.  The Court referred to the case of Appeal Court in  Sunley (B.)
5
and Company Limited vs. Cunard White Star Ltd. , discussed below, in
this context.
13. In   Sunley  (B.)  and Company 's  case,   the  plaintiffs  were
public works contractors.   As a result of the defendant's breach, their
machine could not reach  the site of work in time.  For this delay they
claimed damages.  The plaintiffs had failed to prove any facts on which
their damages could be estimated.  They nevertheless relied on law. The
trial judge accepted their case and gave them damages for loss by making
a guesswork of the profit which the machine could have earned for the
plaintiffs for the period of delay relying on a variety of cases.  The Appeal
Court, reversing the order, held that those cases were no authority for
the proposition that, if the owner of a profit – earning chattel does not
prove the loss  he has sustained, the judge may make a guess in the dark
and award him some arbitrary sum.  The Appeal Court instead assessed
the damages  in the following manner :  The machine was a chattel of
commercial value, but on the facts before the court there were only four
possible heads of damage ­ (1) depreciation which was running on, (2)
interest on the money invested which was being wasted, (3) some trivial
amount of maintenance which was no doubt involved, and (4) some
expenditure of wages which were thrown away.  The Court accordingly
5 (1940) 1 KB 740: (1940) 2 ALL ER 97(CA)
                                                                                                                             Pg 13 of 20
::: Uploaded on - 20/07/2019 ::: Downloaded on - 26/06/2024 07:28:57 :::

Mohite/sg arbp1060­10.doc

estimated the depreciation (for a machine having a life of three years)
and   added   some   amount   on   the   three   other   heads,   whilst   making
allowance for receipts, and worked out the total claim.
14. A Division Bench of our Court in   Edifice Developers and
6
Project   Engineers   Ltd.   vs.   Essar   Projects   (India)   Ltd.   did   not
countenance an award, where, without any evidence of damages, the
arbitrator   had   awarded   loss   of   overheads   on   the   basis   of   Hudson's
formula, which was considered by the Supreme Court in   McDermott
7
International Inc. vs. Burn Standard Co. Ltd.   as one of the many
formulae used for assessing loss of overheads in case of a works contract.
The Division Bench observed that in   McDermott International ,   the
Supreme Court had held that it was an accepted position that different
formulae could be applied in different circumstances and the question as
to whether damages should be computed by taking recourse to one or
other   formula,   having   regard   to   the   facts   and   circumstances   of   a
particular  case,  would fall  within  the domain  of  the  arbitrator.  The
arbitrator in the case before the Division Bench had found that though no
direct evidence had been adduced on behalf of the contractor, he would
nonetheless be entitled to damages measured with reference to Hudson's
formula.  This approach was found by the Division Bench manifestly in
the teeth of the law laid down by the Supreme Court in   McDermott
International .  The Division Bench made the following observations in
this behalf:
“Section 28(1)(a) requires that the Arbitral Tribunal shall decide a
6 Appeal No. 11 of 2012 decided on 3 January 2013
7 2006 (2) Arb.L.R. 498 (SC)
                                                                                                                             Pg 14 of 20
::: Uploaded on - 20/07/2019 ::: Downloaded on - 26/06/2024 07:28:57 :::

Mohite/sg arbp1060­10.doc

dispute submitted to arbitration in accordance with the substantive
law for the time being in force in India. Section 28(3) requires the
Arbitral Tribunal to decide in accordance with the terms of the
contract and take into account the usages of the trade applicable to
the transaction. The Arbitral Tribunal under Section 28(2) can act
as amiable compositeur and can decide ex aequo et bono only if
parties have expressly authorized it to do so. In the present case,
the Learned Single Judge was correct in coming to the conclusion
that   the   award   of   the   Arbitrator   proceeds   on   the   manifestly
misconceived notion that a contractor is entitled to claim overhead
losses even in the absence of evidence on the basis of Hudson's
Formula.   Similarly,   the   Arbitral   Tribunal   proceeded   on   a
misconceived premise that this formula is invariably adopted for
quantification of claims for overhead losses in India. In the present
case the Appellant produced no evidence in support of its claim;
this has been so stated in the Award. The award of the claim is on
the misconceived basis that the Hudson's Formula must be applied
despite the absence of evidence. Since the fundamental basis that
has permeated the award is contrary to law, the judgment of the
Single Judge cannot be faulted in setting aside the arbitral award
on that aspect.”
The   Division   Bench   in   Edifice   Developers   (supra)
explained in this context the judgment of  A.T. Brij Paul Singh  (supra) in
the following words :
“In Brij Paul Singh's case the Supreme Court noted that it was not
disputed that where in a works contract a party entrusted with the
work  commits  a   breach   of   the  contract,  the  contractor  would   be
entitled to claim damages for loss of profit which he expected to earn
by undertaking the contract. The Supreme Court, however, noted that
what must be the measure of the profit and what evidence should be
tendered to sustain the claim are different matters. The judgment of
the Supreme Court adverts to the fact that in that case the High Court
had   referred   to   Hudson's   treatise   on   Building   and   Engineering
Contracts.   Hudson   states   there   that   in   major   contracts   subject   to
competitive tender on a national basis, the evidence given in litigation
on many occasions suggests that head office overheads and profits are
between 3 to 7% of the total price of cost which is added to the
tender. The High Court in that case had rejected the claim of the
contractor. The Supreme Court noted that in an identical contract with
                                                                                                                             Pg 15 of 20
::: Uploaded on - 20/07/2019 ::: Downloaded on - 26/06/2024 07:28:57 :::

Mohite/sg arbp1060­10.doc

regard to another portion of the same road and for the same type of
work the High Court had accepted loss of profit at 15% of the price of
the balance of work as a reasonable measure of damages if the State is
guilty of a breach of contract. It was on this basis that the Supreme
Court came to the conclusion that since for the same type of work,
between the same parties involving a nearby portion of the same road
a certain measure of damages had been adopted by the High Court,
the same measure ought to have been adopted in that case as well.
     Brij Paul Singh's case therefore does not stipulate as a doctrine of
law that the formula which has been prescribed in Hudson's treatise
must invariably be accepted in all cases as a measure of damages
sustained on account of loss of overheads.”
15. Following   this   judgment,   a   learned   Single   Judge   of   our
Court   in   Essar   Procurement   Services   Ltd.   vs.   Paramount
8
Constructions   set   aside   an   award   which   had   allowed   a   claim   for
overheads merely on the basis of Hudson's formula without any evidence.
The learned Judge found the approach to be contrary to the principles
laid down by this   Court in   Edifice Developers   (supra), holding the
award  to   be   patently  illegal   and  in   conflict   with   public   policy.   The
learned Judge set aside even a loss of profit award given on the basis of
Hudson's formula, holding as follows:
“113     The principles laid down by the Supreme Court and this court
in the judgments referred to aforesaid while dealing with the claim
for loss of overhead would also apply to the claim for loss of profit.  A
perusal of the impugned award indicates that the claim for loss of
profit is also allowed by the arbitral tribunal simplicitor based on the
Hudson Formula and not based on any evidence and thus the same
also deserves to be set aside.”
16. As the Division Bench of Delhi High Court said in the case of
8 Arbitration Petition No.470 of 2012 decided on 25 November 2016
                                                                                                                             Pg 16 of 20
::: Uploaded on - 20/07/2019 ::: Downloaded on - 26/06/2024 07:28:57 :::

Mohite/sg arbp1060­10.doc

9
Ahluwalia   Contract   (India)   Limited   vs.   Union   of   India ,   that   in
arbitration proceedings, just as in civil cases, an injured party can claim
damages,   does   not   necessarily   translate   into   an   award   for   damages
towards loss of profits in every case unless some diligence is exercised by
the party claiming it.  The Court held that a claim for damages (general
or special) cannot, as a matter   of course, result in an award without
proof of injury.  The arbitral tribunal in that case was unable to discern
any substantial material to justify the claim for damages towards loss of
profits and accordingly denied the claim.  The Court sustained the award,
holding   that     no   interference   was   warranted.     The   Court   briefly
explained the cases of  Bharat Coking Coal  (supra) and  A.T. Brij Paul
Singh  (supra) thus:
“9.   Bharat Coking (supra) and Brij Paul (supra), no doubt, are
authorities for the proposition that the Court even in arbitration
cases should be conscious of and ordinarily should not refuse claims
towards loss of profits.  At the same time, the reference to Section 73
– which finds express mention in Brij Paul (supra) clarifies that
damages claimed cannot be granted as a matter of course; some
material evidence is necessary.”
17. The upshot of the above discussion is that though, as a
matter of law, in a works contract, where the contractor is prevented
from completing the contract work for no fault of his, the contractor may
be entitled to damages for reasonable profits which he expected to earn
in the contract, the measure of such profits is essentially a matter of
evidence. There are well known formulae, one or the other of which may
be used by the adjudicators, having regard to the evidence before them,
for working out such profits.  It may be that in a given case, the employer
9 244 (2017) Delhi Law Times 360 (DB)
                                                                                                                             Pg 17 of 20
::: Uploaded on - 20/07/2019 ::: Downloaded on - 26/06/2024 07:28:57 :::

Mohite/sg arbp1060­10.doc

has been computing profit as a certain proportion of the total value of
the works contract for awarding such contract or making or assessing
tenders; it may be that there  may be a particular industry practice for
any such particular proportion; it may be that in the given contract, a
particular proportion was actually assessed as may be established by
evidence.  These are, however, matters of evidence.  Besides, even where
profit   as   a   proportion   of   total   contract   value   actually   used   is
demonstrable, there may still be difficulties in establishing a claim for
loss of profit on uncompleted work in case of wrongful rescission of
contract.   We are, after all, concerned with the contract price of the
remaining work.     The profit element must be shown vis­a­vis such
balance   contract   price.     Particular   industries   (and   even   particular
contractors in the same industry) are known to price their contracts
differently; the profit percentage, stage­wise or pricing element­wise,
may not be uniform.  The earlier stages or elements of work may be more
profitable,   whereas   the   remaining   stages   or   elements   may   be   less
profitable or even be non­profitable, though   the contract itself as a
whole may be profitable.   So also, in every case   where a contract is
terminated for no fault of the contractor, he cannot claim profits on the
entire balance amount of the unperformed contract.  In the first place, at
the moment the contract was rescinded or determined, he may not be in
a state of readiness to perform the whole of the contract; he may not  be
in a position where his resources are fully committed for the whole of the
balance work.  This may particularly be so, where the performance of the
contract, at the time of its rescission, is at a very early stage.   At that
stage, he may not have deployed capital or spent for labour for the whole
of the balance work.   Can he then claim profit for the whole of the
                                                                                                                             Pg 18 of 20
::: Uploaded on - 20/07/2019 ::: Downloaded on - 26/06/2024 07:28:57 :::

Mohite/sg arbp1060­10.doc

balance work without any commitment of capital and labour?  Profit, as
we have noted above,   is derived from the employment of capital and
labour; without these latter two, no profit can arise.  Besides, depending
on the stage at which the rescission takes place, there would be a duty on
the part of the contractor, as the party suffering from a breach, to
mitigate damages.   Such mitigation would imply that he seeks other
avenues to earn profits and employ his resources elsewhere.  If there is
plentiful work around, there is no reason he should not so divert his
resources.  In fact, in many cases he would have actually done so.  Can
he then seek loss of profit for the whole of the balance contract value?
Will it not amount to his unjust enrichment?
18. These and such other elements are matters to be considered
in any adjudication of damages.  It is no doubt, firstly, for the parties to
plead and prove these elements, consistent with the legal burden of proof
and shifting onus of proof as part of the trial.   It is then   for the
adjudicators to assess the evidence and arrive at a correct measure of
damages.
19. In   the   present   case,   as   noted   above,   none   of   these
considerations appears to have been gone into by the arbitrator. The
contract was abandoned at a much early stage of the anticipated contract
work; only a miniscule percentage of work was accomplished by that
time.  There is no pleading, much less evidence, that the contractor had
actually deployed resources or was even ready, or in a position, to do so.
And yet, by  a simple arithmetical calculation, loss of profits at the rate of
12 per cent of the whole of the balance work was awarded.  Even this 12
                                                                                                                             Pg 19 of 20
::: Uploaded on - 20/07/2019 ::: Downloaded on - 26/06/2024 07:28:57 :::

Mohite/sg arbp1060­10.doc

per cent was on the basis of a rate analysis submitted by the employer
without prejudice to his rights and contentions.  This is a clear error, and
an error of law at that, which  goes to the root of the matter.  It entails a
breach of public policy of India, since Indian law only countenances
compensatory   damages.     The   fundamental   idea   behind   the   Indian
conception of damages is placing the party suffering from the breach of
contract in the same position   in which he would have been had the
breach  not occurred; he must show  what he was in a position to receive
at the time the contract was broken, for it is only that which he would
receive as compensation. 
20. The impugned award on Claim No.4, accordingly, cannot be
sustained and will have to be set aside.  Award on Claim No.8, which was
for interest, will also have to be accordingly modified, since the award on
Claim No.4 is being set aside.
21. In the result, the arbitration petition partly succeeds.   The
impugned award dated 04.02.2000 in so far as it awards Claim No.4, and
Claim No.8 to the extent it includes interest on Claim No.4, is set aside.
The   rest   of   the   award   is   sustained.   The   petition   is   disposed   of
accordingly.
                   ( S.C. GUPTE, J. )
                                                                                                                             Pg 20 of 20
::: Uploaded on - 20/07/2019 ::: Downloaded on - 26/06/2024 07:28:57 :::