Full Judgment Text
1
Non-Reportable
IN THE SUPREME COURT OF INDIA
CIVIL APPEAL NO. 7222 of 2016
(Arising out of SLP (Civil) No.16860 of 2012)
M/s Electrotherm (India) Ltd. ….Appellant
Versus
Patel Vipulkumar Ramjibhai & Ors. …. Respondents
J U D G M E N T
JUDGMENT
Uday Umesh Lalit, J.
1. Leave granted.
2. This appeal challenges the judgment and order dated 11.05.2012
passed by the High Court of Gujarat allowing Special Civil Application
No.5986/2010 setting aside the Environmental Clearance dated 27.01.2010
and directing that the operations of the entire plant of the Appellant be
Page 1
2
stopped and that the operations could be continued only after fresh
Environmental Clearance was accorded in its favour by the Ministry of
Environment and Forests and Union of India.
| Impact A | ssessment |
|---|
issued by the Central Government in exercise of powers conferred by
sub-section(1) and Clause V of sub-section(2) of Section 3 of the
Environment (Protection) Act, 1986 read with Clause(d) of sub-rule(2) of
Rule 5 of the Environment (Protection) Rules, 1986 stipulated inter alia that
in case of expansion or modernization of any activity, if pollution load
exceeded the existing one or the new project was listed in Schedule I to
the said Notification, such activity would not be undertaken unless the
Environmental Clearance was accorded by the Central Government. Same
thought was carried and finds expressly stipulated in the Notification dated
JUDGMENT
14.09.2006 issued by the Central Government in supersession of the
Notification dated 27.01.1994. The Notification dated 14.09.2006 directed
that the required construction of new projects or activities or the expansion
or modernization of existing projects or activities listed in the Schedule to
the Notification entailing capacity addition with change in process and or
technology would be undertaken only after prior Environmental Clearance
from the Central Government or as the case may be by the State Level
Page 2
3
Environment Impact Assessment Authority. Clauses 2 and 4 of the
Notification deal with requirements of prior Environmental Clearance and
Categorization of Projects and Activities respectively. Under Clause 7
| ce process | comprise |
|---|
order, namely, (1)- Screening, (2) Scoping, (3) Public Consultation and (4)
Appraisal.
4. The Appellant set up a Steel Plant at Village Samakhiyali, for
manufacturing various products after having received No Objection
Certificate from Gujarat Pollution Control Board (“GPCB”, for short) on
25.02.2005, which thereafter granted consent vide Authorization Order
dated 10.11.2005 for manufacture of Pig Iron, Steel Billets/Slabs, Steel
Bars and Rods, etc.
5. The Appellant had set up the Plant and begun manufacturing process
JUDGMENT
and later by its letter dated 30.11.2007 applied for Environmental Clearance.
On 20.02.2008 the Government of India, Ministry of Environment and
Forests granted Environmental Clearance, the relevant portions of the
Clearance being:-
“2.0 The Ministry of Environment and Forests has examined
the application. It is noted M/s. Electrotherm (India) Ltd. have
proposed expansion of Pig Iron Plant (150 to 350 TPD) with
Captive Lignite/Coal char based Power Plant (24 MW) and
WHRB (6MW) at Samakhiyali, Bhachhu, Kutch, Gujarat.
Page 3
4
Total project area is 100.6276 ha. and expansion will be carried
out in 20.79 ha. No National Park of Wildlife Sanctuary is
located within 10 km ………………………...............................
……….. Total cost of project is Rs. 90.00 Crores……………...
| e scrubber<br>ions from | s, bag lett<br>WHRB, |
|---|
4.0 Public hearing/Public consultation meeting was held on
th
12 June, 2007.
5.0 The Ministry of Environment and Forests hereby accords
Environmental Clearance the above project under EIA
th
Notification dated 14 September, 2006 subject to strict
compliance of the following conditions………………………”
JUDGMENT
The Environmental Clearance then sets out certain specific conditions
and general conditions.
6. The Appellant thereafter, applied for expansion of Steel Plant. The
matter was dealt with in the Ninety First Meeting of the Re-constituted
Expert Appraisal Committee (Industry) held during 9-11 February, 2009.
The Appellant had informed that Public hearing for the previous project was
held on 12.06.2007 and that the proposed expansion would be within the
Page 4
5
existing industrial premises and no extra land would be required. The
matter was dealt with by the Committee and the relevant minutes were :-
th
“PAs vide letter dated 29 December, 2008 informed
th
that Public hearing for the previous project was held on 12
| tter No.J-<br>is also info | 11011/503/<br>rmed that |
|---|
M/s Electrotherm (India) Ltd. have proposed for the
expansion of Steel plant at Milestone No. 310 of NH No. 8A,
Village Samkhiyali, Taluka Bhachau, Kutch, Gujarat. PAs
have mentioned that Sponge Iron, DI Pipes, Steel Rolling
Mill, Induction Furnace are existing after getting ‘NOC’ from
GPCB. Environment clearance for Pig Iron Plant and CPP (30
th
MW) is accorded vide letter dated 20 February, 2008.
Expansion will be carried out in 20.24 ha within the existing
industrial premises of 100.62 ha. No National Park/Wild Life
Sanctuary/Reserve Forest is located within 10 km radius of the
project site. Total cost of the project is Rs.274.00 Crores.
Rs.5.89 Crores and Rs.0.40 Crores will be earmarked towards
total capital cost and recurring cost/annum for environmental
pollution control measures. ………….
Iron Ore (65,400 MTPM), Limestone (8,856 MTPM),
Manganese Ore (465 MTPM), Quartizite (1,068 MTPM),
Dolomite (2,471 MTPM) and Lime Dolofines (968 MTPM)
will be used as raw material.
JUDGMENT
Sponge Iron will be produced using DRI method. Iron
oxide will be chemically reduced to ‘hot metal’ in Blast
furnace. Sinter Plant will use iron ore fines, mill scales and
flue dust. Sinter produced will be used in BF Billets from
Steel Melt Shop (SMS) will be put into Billet in Reheating
Furnace. Reheated Billets will be used to manufacture TMT
Bars. Pig Iron will be heated in Induction Furnace (IF) to
prepare Duct Iron pipes. Scrap and sponge iron will be changed
to IF and then poured to Ladle Refining Furnace (LRF) and
Page 5
6
then molten material will be changed to continuous casting
machine (CCM) to produce billets, rods and bars. Waste gases
from DRI will be used in WHRB. No AFBC is proposed
during expansion.
| at Recover<br>Fugitive e | y Boiler (<br>missions w |
|---|
Total water requirement from Gujarat Water
Infrastructure Ltd. (GWIL) will be 2,165 m3/day. PAs
nd
submitted the water allotment letter dated 22 October, 2008
from GWIL. Air-cooled condenser will be provided to WHRB.
The waste water from power plant will be treated in
neutralization plant. Treated waste water will be used for water
sprinkling during dust suppression and green belt development.
Sewage will be disposed of through septic tank & soak pit.
JUDGMENT
Fly ash (2,820 MTPM), bed ash (600 MTPM) will be
used in captive brick manufacturing plant and additionally have
a tie up with Cement manufacturing units. Coal char (5,400
MTPM) will be used in existing power plant. Slag (5,124
MTPM) will be sold to cement/brick manufacturing units. Iron
ore fines, mill scale, flue dust etc. will be used in Sinter Plant.
BF slag will be granulated and provided to cement
manufacturers. Used/spent oil will be sold to authorized
recyclers.
Out of total 100.62 ha, green belt is earmarked for 8 ha.
in existing and 5.47 ha. in proposed expansion. Thus, total
13.47 ha. is proposed for the green belt development. Coke,
Page 6
7
coal and waste heat from DRI will be used as
fuel………………………………………………………”
7. After setting out the details of the proposed expansion of the project
| of the Ex | pert Comm |
|---|
“The Expert Committee (Industry) decided that PAs may
be communicated the above ‘TORs’ for the preparation of
EIA/EMP. As soon as the draft EIA/EMP report is prepared as
per the ‘General Structure of EIA’ given in Appendix III and
IIIA in the EIA Notification, 2006, the same may be submitted
by the PAs to the MOEF for prior Environmental Clearance.
PAs informed to the Committee that Environment Clearance
has been accorded to M/s Electrotherm India Ltd. for the
th
existing plant vide letter dated 20 February, 2008 with public
th
hearing on 12 June, 2007 and requested for the exemption.
The Committee considered the request and exempted from the
public hearing as per Section 7(ii) of EIA Notification, 2006
due to no additional land requirement, ground water drawl,
utilization of DR and BF gases in WHRB & char in AFBC
boiler, fly ash and BF slag to cement manufacturers, etc.”
8. The matter was thereafter considered for grant of Environmental
JUDGMENT
Clearance which came to be granted by Government of India, Ministry of
Environment and Forests by communication dated 27.01.2010, relevant
portion of which was:-
“The Ministry of Environment and Forests has examined the
application. It is noted that proposal is for the expansion of
Steel plant at Milestone No.310 of NH No.8A,
Village-Samkhiyali, Taluka Bhachau, Kutch, Gujarat by M/s.
Electrotherm India Limited. Expansion will be carried out in
Page 7
8
| No. PC/CCA/KUTCH-294/28080, dated 13th September, 2006<br>and PC/CCA-KUTCH-294(3)13208 dated 30th April, 2008.<br>Environmental Clearance for the existing plant (Pig Iron Plant<br>and Captive Power Plant (30 MW) is accorded vide Ministry’s<br>letter No.J-11011/503/2006-IA-II(I) dated 20th February, 2008.<br>Following are the details of the existing and proposed facilities:<br>Sr.No. Products Production Capacity<br>(MTPM)<br>Existing Proposed Total<br>1 Sponge Iron 6,000 18,000 24,000<br>2 D.I. Pipes 4,000 12,000 16,000<br>3 Captive Power 30 MW 15 MW 45 MW<br>WHRB 6 MW 15 MW 21 MW<br>FBC 24 MW 24 MW<br>4 Pig Iron (Blast 4,500 18,600 23,100<br>Furnace)<br>5 Sinter Plant - 32,400 32,400<br>6 Steel Rolling 5,833 10,500 16,333<br>JUDGMENT<br>Mill<br>7 MS 5,833 30,000 35,833<br>Billets/Bars<br>8 Stainless Steel 25,000 -- 25,000<br>Billets<br>9 Alloy Nickel 416 -- 416<br>10 Induction 17Sets/ -- 17 sets<br>Furnaces Month<br>11 Electric Cycle 83 Sets/ -- 83 sets<br>and Vehicle Month | |||||
|---|---|---|---|---|---|
| Sr.No. | Products<br>(M<br>E | Production Capacity<br>TPM)<br>xisting Proposed Total | |||
| 1<br>2 | Sponge Iron<br>D.I. Pipes | 6,000<br>4,000 | 18,000<br>12,000 | 24,000<br>16,000 | |
| 3 | Captive Power<br>WHRB<br>FBC | 30 MW<br>6 MW<br>24 MW | 15 MW<br>15 MW | 45 MW<br>21 MW<br>24 MW | |
| 4 | Pig Iron (Blast<br>Furnace) | 4,500 | 18,600 | 23,100 | |
| 5 | Sinter Plant | - | 32,400 | 32,400 | |
| 6 | Steel Rolling<br>JUDG<br>Mill | 5,833<br>ME | 10,500<br>NT | 16,333 | |
| 7 | MS<br>Billets/Bars | 5,833 | 30,000 | 35,833 | |
| 8 | Stainless Steel<br>Billets | 25,000 | -- | 25,000 | |
| 9 | Alloy Nickel | 416 | -- | 416 | |
| 10 | Induction<br>Furnaces | 17Sets/<br>Month | -- | 17 sets | |
| 11 | Electric Cycle 8<br>and Vehicle | 3 Sets/<br>Month | -- | 83 sets |
3.0 Sponge Iron will be produced using DRI method. Iron
oxide will be chemically reduce to ‘hot metal’ in blast furnace
Page 8
9
| ars. Billet<br>ing furnace | s from ste<br>to manuf |
|---|
4.0 Electrostatic precipitator (ESP), dust settling chamber
(DSC), after burning chamber (ABC), gas cleaning system with
bag house, bag filters, multi-cyclones, dust collectors, stack of
adequate height, dust suppression and extraction system will be
provided to control air emissions. Total water requirement from
Gujarat Water Infrastructure Ltd. (GWIL) will be 2,165 m³/day
nd
and water is allotted vide letter dated 22 October, 2008. No
ground water will be utilized. Air-cooled condenser will be
provided to WHRB. No waste water will be discharged from
sponge iron plant, pig iron plant, sinter plant, WHRB power
plant, TMT bar plant, BI pipe and induction/arc furnace. The
waste water from power plant will be treated and used for dust
suppression and green belt development. Coal char will be
used in existing power plant, coal dust in the boiler, iron ore
fines, mill scales, flue dust etc. in sinter plant. Fly ash will be
used in captive brick manufacturing plant and also provided to
cement manufacturing units.
JUDGMENT
Slag will be sold to cement/brick manufacturing units. Bed ash
will be disposed off in secured landfills.
th
5.0 Public hearing for the existing plant was held on 12
June, 2007 and is exempted for the proposed exemption as per
Section-7(ii) of EIA Notification, 2006.”
9. On or about 10.05.2010 Respondent No.1 herein filed Special Civil
Application No.5986 of 2010 in the High Court of Gujarat, in public
Page 9
10
interest, seeking revocation of Environment Clearance granted to the
Appellant for expansion of its plant. It was submitted inter alia that as a
result of expansion the proposed capacity and activities of the Appellant
| tially and t | hat the En |
|---|
for expansion of plant was not in conformity with EIA Notification of 2006.
The Appellant which was Respondent No. 3 in the High Court, in its reply
submitted inter alia that the petition was not in public interest and
Respondent No.1 was set up by the business rivals of the Appellant and that
the Appellant had complied with all the norms and requirements and was
rightly granted Environment Clearance for expansion of the plant. The
responses filed on behalf of the Ministry of Environment and Forest, Govt.
of India and Gujarat Pollution Control Board also submitted that the
Environmental Clearance was rightly granted and that the activities of the
JUDGMENT
Appellant were periodically and regularly being monitored to ensure that
stipulated Environmental safeguards were complied with.
10. After hearing rival submissions, the High Court by its judgment and
order dated 11.5.2012 allowed Special Civil Application No.5986 of 2010
principally on the ground that the Environmental Clearance dated 27.1.2010
was granted without there being public consultation or public hearing which
Page 10
11
was a mandatory requirement under 2006 Notification. The observations of
the High Court in that behalf were as under:-
| t responden<br>and start | t no.3 set-<br>ed operati |
|---|
19. Thus, the only question for our consideration is as to
whether the Environmental Clearance dated 27.1.2010 can be
termed as illegal in the absence of public consultation or public
hearing as mandatorily provided by Notifications dated 2006.
We agree with learned Counsel Mr. Oza that there is a basic
flaw in the Environmental Clearance granted in favour of
respondent No.3. It is apparent that when public hearing took
place in the year 2007, the same was on the basis of the first
application which respondent No.3 had preferred for expansion
of the steel plant. Objections were raised by the persons
concerned. However, when Environmental Clearance came to
th
be granted vide order dated 27 January 2010 pursuant to the
th
second application dated 8 June 2009 preferred by respondent
no.3 for enhancing the production capacity, the requirement of
public hearing/public consultation was waived by the authority
on the assumption that in the year 2007 public hearing was
already undertaken. It is undisputed that in the year 2007 when
the public hearing was given, the objections and suggestions
were taken into consideration by the authority and
Environmental Clearance was accorded in the year 2008 but,
th
thereafter, when the second application was preferred dated 8
JUDGMENT
June 2009 for enhancing the production capacity by more than
double, people were not made aware of this proposal of
Page 11
12
respondent No.3 and the authority proceeded to accord
Environmental Clearance waiving public hearing.”
The High Court also placed reliance on the pronouncement of this
| f Lafarg | e Umiam |
|---|
High Court thus set aside Environmental Clearance dated 27.01.2010 and
directed the appellant to stop operations of the entire plant and further
directed that the operations could be restarted only after fresh Environmental
Clearance was accorded in its favour by the Ministry of Environmental and
Forests and Union of India. The decision of the High Court is presently
under challenge.
11. In this appeal by Special Leave, this Court issued notice on
15.05.2012 and by further order dated 18.05.2012 stayed the operation of the
JUDGMENT
judgment and order of the High Court. It also directed the Central Pollution
Control Board to file status report in respect of plant and compliance of
statutory requirements by the appellant. On 18.7.2012 an affidavit was filed
on behalf of CPCB stating that during its visit half of the plant was not in
operation and as such actual compliance of the statutory requirements could
not be ascertained. It further stated that the industry of the Appellant was
1
2011 (7) SCC 338
Page 12
13
non-compliant with pollution standards in one or the other area made certain
recommendations.
| Court:- |
|---|
“The matter has been almost fully heard. Having regard
to the submissions of the learned senior counsel and the
Notifications of 1994 and 2006, it has become necessary to get
the joint inspection done of the petitioner’s project from the
Gujarat Pollution Control Board and Central Pollution Control
Board (CPCB) and report submitted to this Court whether the
petitioners has complied with the recommendations of the
Central Pollution Control Board which are specified in para 7
of the affidavit of Mr. R.K. Purohit, Senior Executive Director
of the petitioner in response to the affidavit of Central Pollution
Control Board dated 18.7.2012.
We, accordingly, direct the Central Pollution Control
Board and Gujarat Pollution Control Board to make a joint
rd
inspection of the petitioner’s project in the 3 week of June,
2014 and report about the compliance of the recommendations
as set-out in the above affidavit. The report shall be submitted
on or before 5.7.2014. We make it clear that if from the report
it transpires that the petitioner has not yet complied fully with
the recommendations specified in the affidavit noted above, the
special leave petition shall have to be dismissed. On the other
hand, if the full compliance of the above recommendations is
found to have been made, the impugned order of the High
Court will be set-aside…………………………”
JUDGMENT
13. In the affidavit filed on 07.07.2014 on behalf of CPCB it was stated
inter alia that pursuant to the order dated 22.04.2014 passed by this Court, a
Page 13
14
joint inspection was carried out as directed and that the industry of the
Appellant had complied with most of the recommendations, though there
were still certain shortcomings.
| ereafter ta | ken up for |
|---|
of the appeal Dr. A.M. Singhvi, learned Senior Advocate submitted that most
of the recommendations made in the affidavit dated 18.07.2012 having been
complied with, the matter now stood in a narrow compass. Mr. Huzefa
Ahmadi, learned Senior Advocate appearing for Respondent No.1 however
submitted that the infirmity on account of absence of public hearing/public
consultation which is a mandatory requirement under the EIA Notification of
2006, rendered the Environmental Clearance dated 27.01.2010 invalid and
illegal.
JUDGMENT
15. The facts on record are clear that while granting Environmental
Clearance on 20.02.2008, public consultation/public hearing was undertaken
on 12.06.2007. As on that date the status of the project was that the capacity
of Pig Iron Plant was to be 350 TPD, Power Plant to be 24 MW, the total
cost of the project was 90.00 crores and the total Water requirement was 650
M /Day. ᶟ The High Court was absolutely right that after expansion the
capacity of the plant was to increase three-fold. The tabular chart given in
Page 14
15
Environmental Clearance dated 27.01.2010 itself shows the tremendous
increase in the capacity. Consequently, the pollution load would naturally be
of greater order than the one which was contemplated when the earlier
| ic hearing | was under |
|---|
the water requirement had also risen from 650 M /Day to 2165 M /Day. The
ᶟ ᶟ
increase in pollution load and water requirement were certainly matters
where public in general and those living in the vicinity in particular had and
continue to have a stake.
16. Public consultation/public hearing is one of the important stages while
considering the matter for grant of Environmental Clearance. The minutes
of the meetings held on 9-11 February, 2009 show that the request of the
Appellant for exemption from the requirement of public hearing was
accepted by the Committee. The observations of the Committee suggest that
JUDGMENT
there would be no additional land requirement, ground water drawl and
certain other features. However the water requirement, which is a
community resource, was definitely going to be of greater order in addition
to the fact that the expansion of the project would have entailed additional
pollution load.
Page 15
16
17. It must be stated here that after EIA Notification of 2006 a draft
Notification was issued on 09.01.2009 wherein an amendment was
suggested in paragraph 7(ii) of EIA Notification dated 14.09.2006 to the
| pansion of | projects in |
|---|
than 50% holding of public consultation/public hearing was essential;
implying thereby that in cases where expansion was less than 50% public
consultation/public hearing could be exempted. Without going into the
question whether public consultation/public hearing could be so exempted, it
is relevant to note that this idea in the draft Notification was not accepted,
after a Committee constituted to advise in the matter had given its report on
30.10.2009 to the contrary. As a result, the final Notification dated
01.12.2009 did not carry or contain the amendment that was suggested by
way of draft Notification. Consequently, no exemption on that count could
JUDGMENT
be given when the Environmental Clearance came to be issued on
27.01.2010.
18. In the case of Lafarge (supra) public consultation/public hearing was
considered and found to be mandatory requirement of the Environmental
Clearance process by this Court. In its conclusions culled out in paragraph
122 (xiv) as regards public consultation/public hearing, it was observed by
this Court:-
Page 16
17
“(xiv) The public consultation or public hearing as it is
commonly known, is a mandatory requirement of the
Environment Clearance process and provides an effective
forum for any person aggrieved by any aspect of any project to
register and seek redressal of his/her grievances.
discussion in paragraph 119 are quite eloquent:-
“……It cannot be gainsaid that utilization of the environment
and its natural resources has to be in a way that is consistent
with principles of sustainable development and
intergenerational equity, but balancing of these equities may
entail policy choices. In the circumstances, barring exceptions,
decisions relating to utilization of natural resources have to be
tested on the anvil of the well-recognised principles of judicial
review. Have all the relevant factors been taken into account?
Have any extraneous factors influenced the decision? Is the
decision strictly in accordance with the legislative policy
underlying the law (if any) that governs the field? Is the
decision consistent with the principles of sustainable
development in the sense that has the decision-maker taken into
account the said principle and, on the basis of relevant
considerations, arrived at a balanced decision? Thus, the Court
should review the decision-making process to ensure that the
decision of MoEF is fair and fully informed, based on the
correct principles, and free from any bias or restraint.”
JUDGMENT
In terms of the principles as laid down by this Court in the case of
Lafarge (supra), we find that the decision making process in doing away
with or in granting exemption from public consultation/public hearing, was
Page 17
18
not based on correct principles and as such the decision was invalid and
improper.
| e dated 27. | 01.2010, t |
|---|
been undertaken and as reported by CPCB in its affidavit filed on
07.07.2014, most of the recommendations made by CPCB are complied
with. In our considered view, the interest of justice would be sub-served if
that part of the decision exempting public consultation/public hearing is set
aside and the matter is relegated back to the concerned Authorities to
effectuate public consultation/public hearing. However, since the expansion
has been undertaken and the industry has been functioning, we do not deem
it appropriate to order closure of the entire plant as directed by the High
Court. If the public consultation/public hearing results in a negative
JUDGMENT
mandate against the expansion of the project, the Authorities would do well
to direct and ensure scaling down of the activities to the level that was
permitted by Environmental Clearance dated 20.02.2008. If public
consultation/public hearing reflects in favour of the expansion of the project,
Environmental Clearance dated 27.01.2010 would hold good and be fully
operative. In other words, at this length of time when the expansion has
already been undertaken, in the peculiar facts of this case and in order to
Page 18
19
meet ends of justice, we deem it appropriate to change the nature of
requirement of public consultation/public hearing from pre-decisional to
post-decisional. The public consultation/public hearing shall be organized
| ties in thre | e months f |
|---|
21. This appeal therefore stands disposed of with the aforesaid
modifications. No order as to costs.
…..
…………………CJI.
(T. S. Thakur)
| R. Banumathi | ) |
|---|
…...……………………J
(Uday Umesh Lalit)
New Delhi,
August 02, 2016
JUDGMENT
Page 19