Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 9
PETITIONER:
STATE OF ORISSA
Vs.
RESPONDENT:
DANDASI SAHU
DATE OF JUDGMENT22/07/1988
BENCH:
MUKHARJI, SABYASACHI (J)
BENCH:
MUKHARJI, SABYASACHI (J)
RANGNATHAN, S.
CITATION:
1988 AIR 1791 1988 SCR Supl. (1) 562
1988 SCC (4) 12 JT 1988 (3) 364
1988 SCALE (2)285
CITATOR INFO :
R 1990 SC1128 (5)
ACT:
Constitution of India, 1950: Article 136-Decision of
larger bench pending on the question of unreasoned award-
Plea to await that decision-Whether could be allowed.
Arbitration Act, 1940: Section 14-Unreasoned award-Not
perse bad-Plea to await decision of larger bench-Whether
justified.
Sections 16 and 30- Whether award becomes bad merely
because the amount awarded is quite high-Factors to be
considered-only if there is error apparent on the face of
award, can be remitted or set aside-Validity of award-
Whether the points, upon which arbitrator adjudicated,
covered, by the exception clause in the contract.
Section 29-Interest pendente lite-Whether arbitrator
has jurisdiction to award.
HEADNOTE:
The construction of the Irrigation Project was
entrusted to the respondent. As per the contract the work
commenced on 4th May, 1973 and was actually completed on
30th December, 1975, the stipulated date being 4th November,
1974. According to the appellant, the respondent accepted
the final payment and was duly paid a sum of Rs.23,74,001
for the work done by him including the extra work. The last
payment was alleged to have been made to the respondent in
September, 1976. A ’nil’ bill was the last bill prepared.
Thereafter, the respondent raised a claim and gave notice
for appointment of an arbitrator. One Nanda was appointed as
the arbitrator by the Chief Engineer. But on an application
made by the respondent, the Subordinate Judge removed Nanda
and appointed one Patnaik as the arbitrator. Again an
application for removal of the arbitrator was made, but was
dismissed.
The Respondent filed his claims before the arbitrator.
These claims were for the alleged extra work in respect of
which the decision of the Superintending Engineer under
clause 11 of the contract was final and the same was
excluded from the purview of the arbitration
563
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 9
clause. The appellant initially contended that the
arbitrator had no jurisdiction to deal with such claims but
later filed a counter claim, and denied all the claims of
the respondent. While the application for removal of the
arbitrator was pending, an adjournment was sought for from
the arbitrator and it was refused. After hearing the parties
and considering the evidence produced, the arbitrator made a
non-speaking and non-reasoned award for Rs.15,23,657 plus
interest @ 10% in favour of the respondent. Objections to
the award were filed in the Court. The Subordinate Judge
upheld the objection and set aside the award. On appeal, the
High Court set aside the judgment of the Subordinate Judge
and made the award rule of the Court, and directed payment
of future interest at 6%.
In this appeal, by special leave, against the High
Court judgment, the appellant-State submitted that the award
is without any reason. It also suggested that since the
validity of the non-reasoned award is being gone into by a
larger Bench of this Court, that decision should be awaited.
Dismissing the appeal,
^
HELD: 1.1 The law as it stands today is that award
without reasons is not bad per se. Indeed, an award can be
set aside only on the ground of misconduct or an error of
law apparent on the face of the award. [567F]
1.2 In the instant case, the plea that the award was
bad being an unreasoned one, was neither mooted before the
learned Subordinate Judge nor before the High Court. It was
also not raised in the objection to the award, filed
originally. It is only in the special leave petition that
such a plea has been raised for the first time. Arbitration
is restored to as a speedy method of adjudication of
disputes. Stale and old adjudication should not be set at
naught, or examination of that question kept at bay on the
plea that the point is pending determination by a larger
Bench of this Court. Even if it is held ultimately that the
unreasoned award per Se is bad, it is not sure whether such
a decision would upset all the awards in this country which
have not been challenged so far. Certainly, in the exercise
of discretion under Article 136 of the Constitution, and in
view of the facts and circumstances of the present case, it
would not be justified in allowing the party to further
prolong or upset adjudication of old and stale dispute.
[567C-E]
2. Clause 11 of the contract between the parties makes
the deci-
564
sion of the Engineer-in-Charge final in respect of some
issues. Proviso of Clause 11 stipulates that in case of
dispute about the rates and time for completion of the work
and any dispute as to proportion that the additional work
bears to the original contract work, the decision of the
Superintending Engineer of the Circle would be final. The
points upon which the arbitrator in the instant case has
adjudicated are not those which are excepted or covered by
Clause 11 of the agreement. ID that view of the matter, this
clause has no application in the instant controversy. [570B-
D]
Bombay Housing Board (now the Maharashtra Housing
Board) v. Kharbase Naik & Co., Sholapur, [1975] 3 SCR 407;
Chief Administrator, Dandakaranya Project, koraput, Orissa &
Anr. v. M/s. Prabartak Comercial Corpn. Ltd. Calcutta, AIR
1975 MP 152 and Food Corporation of India. v. P.L. Juneja,
AIR 1981 Delhi 43 distinguished.
State of orissa v. Gokulchandra Kanungo, [1981] 52 Cut
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 9
LT 416 referred to.
3.1 It is well-settled that when the parties choose
their own arbitrator to be the judge in the dispute between
them, they cannot, when this award is good on the face of
it, object to the decision either upon law or on facts.
Therefore, when arbitrator commits a mistake either in law
or in fact in determining the matters referred to him, where
such mistake does not appear on the face of the award and
the documents appended to or incorporated so as to form part
of it, the award will neither be remitted nor set aside.
[571F-G]
3.2 The fact that merely the award amount is quite high
or that a large amount has been awarded, does not vitiate
the award as such. If’ there is any evidence of malady of
racket of arbitration, the Court may scrutinise the award
carefully in each such case. [572A-B]
3.3 It is clear from the facts of this case that the
arbitrator is a highly qualified person having several
Indian and foreign Degrees and at the relevant time was
acting as Chief Engineer-in-Charge of the State Government.
Having regard to the nature of claims involved, and the fact
that the additional work has been done for which large
amounts have been-paid in this case, it is evident that all
due opportunities were given to the parties to adduce all
evidence. It cannot be said that the award was so
disproportionate as to shock the conscience of the Court
leading it to hold that the award was bad per Se. The High
Court was
565
right in dismissing the challenge to the award on this
ground. [572C-D]
Union of India v. Bungo Steel Furniture Pvt. Ltd.,
[1967] 1 SCR 324 and Allen Berry & Co. (P) Ltd. v. Union of
India, [1971] 3 SCR 282 relied on.
State of Orissa & Ors. v. Gangaram Chhapolia & Anr.,
AIR 1982 Orissa 277 referred to.
4.1 It is now well-settled that the interest pendente
lite is not a matter within the jurisdiction of the
arbitrator. [572G-H]
4.2 In the instant case, the order of the High Court is
modified to the extent that the award is confirmed subject
to the deletion of the interest pendente lite. It is made
clear that interest for the period from 26.9.1981 to
18.3.1983 (the date of the award) is deleted. However, the
interest granted by the High Court from the date of the
decree is sustained. [573A-B]
Executive Engineer (Irrigation), Balimella & Ors. v.
Abhaduta Jena, [1988] 1 SCC 418, followed.
JUDGMENT:
CIVIL APPELLATE JURISDICTION: Civil Appeal No. 1389 of
1988.
From the Judgment and order dated 6.7.1987 of the
Orissa High Court in C.M.C. No. 375 of 1984.
R.K. Mehta and Miss Mona Mehta for the Appellant.
G.L. Sanghi and Vinoo Bhagat for the Respondents.
The Judgment of the Court was delivered by
SABYASACHI MUKHARJI, J. This is an appeal by special
leave from the judgment and order of the High Court of
orissa, dated 6th July, 1987. It arises out of a contract
entered into between the State and the respondent for the
construction of certain projects for irrigation. During
1973-74 the respondent was entrusted with the job of
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 9
’Construction of Ramaguda Minor Irrigation project in
Kukudakhandi Block’ vide agreement No. 4-F-2. The value of
the work was Rs.9,99,510. The work pursuant to the contract
commenced on 4th May, 1973 and 4th November, 1974 was the
stipulated date of com-
566
pletion of the work. However, on 30th December, 1975 the
work was actually completed. It is asserted by the appellant
that the respondent contractor accepted the final payment
and was duly paid a sum of Rs.23,74,001 for the work done by
him including the extra work. Thereafter, no amount was due
to the respondent, according to the appellant, and he did
not raise any claim whatsoever before the Department. On
28th September, 1976 the last payment was alleged to have
been made by the respondent. On 30th October, 1976 the last
bill was prepared which was nil one. The respondent,
thereafter, raised a claim and gave notice for appointment
of an arbitrator. Consequently, the Chief Engineer appointed
one Shri A.N. Nanda as the arbitrator in terms of the
arbitration clause. However, on the application of the
respondent the learned Subordinate Judge removed Shri A.N
Nanda and appointed one Shri B. Patnaik as the arbitrator.
It may be mentioned that the application was made for
removal of the arbitrator Shri B. Patnaik but the same was
ultimately dismissed. Before the arbitrator, the respondent
filed the claim raising some claims which, according to the
appellant, were fictitious and baseless. These claims were
for the alleged extra work in respect of which the decision
of the Superintending Engineer under clause 11 of the
contract was final and the same was excluded from the
purview of the arbitration clause.
It was contended on behalf of the appellant that the
arbitrator had no jurisdiction to deal with such claims. The
appellant filed a counter claim for Rs.2,11,400, denying all
the claims of the respondent. All the documents and relevant
papers were produced before the arbitrator. It is stated
that as the application for removal of Shri B. Patnaik as
arbitrator was pending, an application had been made before
Shri S. Patnaik to adjourn the proceeding which was refused
and the award was made. This award was claimed to have been
made virtually ex parte. This, however, was not so and it
appeared that the arbitrator on hearing the parties and
considering the evidence produced before him made the award.
The arbitrator made the said award on 18th March, 1983 but
the same was a non-speaking and nonreasoned award for a lump
sum of Rs.15,23,657 plus interest @ 10% from 9.9.1975 till
the date of payment or decree. Objections to the said award
were filed in the Court. The learned Subordinate Judge
upheld the objection to the award and set aside the award on
15th September, 1984. There was an appeal to the High Court
and the High Court set aside the judgment of the learned
Subordinate Judge and made the award of the arbitrator, rule
of the Court. It also directed payment of further interest
at 6%.
567
Being aggrieved thereby the State of Orissa has
preferred this appeal. In support of this appeal, it was
submitted that the award in question was a lump sum af money
and it was without any reason, in favour of the respondent.
It was also submitted that the validity of the non-reasoned
award is awaiting determination by a larger Bench of this
Court. Hence, it was urged that this question should await
decision of the larger Bench. In the facts and circumstances
of the case, we are of the opinion that we would not be
justified in acceding to this request on the part of the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 9
appellant. In this case the submission that the award was
bad being an unreasoned one, was neither mooted before the
learned Subordinate Judge nor before the High Court. This
contention was also not raised in the objection to the
award, filed originally. It is only in the special leave
petition that such a plea has been raised for the first
time. Arbitration is resorted to as a speedy method of
adjudication of disputes. Stale and old adjudication should
not be set at naught or examination of that question kept at
bay on the plea that the point is pending determination by a
larger Bench of this Court. Even if it is held ultimately
that the unreasoned award per se is bad, it is not sure
whether such a decision would upset all the awards in this
country which have not been challenged so far. Certainly, in
the exercise of our discretion under Article 136 of the
Constitution and in view of the facts and circumstances of
this case, we would not be justified in allowing the party
to further prolong or upset adjudication of old and stale
disputes.
In that view of the matter, we think that the pendency
of this point before the larger Bench should not postpone
the adjudication and disposal of this appeal in the facts of
this case. The law as it stands today is that award without
reasons are not bad per se. Indeed, an award can be set
aside only on the ground of misconduct or on an error of law
apparent on the face of the award. This is the state of law
as it is today and in that context the contention that the
award being an unreasoned one is per se bad, has no place on
this aspect as the law is now. This contention is rejected.
It was next contended that in view of clause 11 of the
contract the matters upon which the arbitrator has
adjudicated were excluded and these were not arbitrable. It
was submitted that clause 11 of the contract between the
parties made on these matters the decision of the Engineer
Incharge final and binding. Hence, inasmuch as the
arbitrator has purported to act upon this field which was
only to be decided by the Engineer-in-charge, the award was
bad. The disputes over which the arbitrator has purported to
make an award, were regarding
568
works covered by the agreement. lt was submitted that the
provision to clause 11 af the agreement categorically
provided that in the event of dispute over a claim for
additional work, the decision of the Superintending Engineer
of the Circle would be final and, hence, the arbitrator by
entertaining the additional claim of the contractor had
exercised a jurisdiction not vested in him and, as such,
misconducted himself.
In order to judge this contention, therefore, it is
Imperative first to refer to clause 11 of the agreement. It
provides as follows:
"Clause 11-The Engineer-in-charge shall have the
power to make any alteration in or additions to
the original specifications, drawings designs, and
instructions that may appear to him necessary or
advisable during the progress of work and the
contractor shall be bound to carry out the work in
accordance with any instructions which may be
given to him in writing signed by the Engineer-in-
charge and such alteration shall not invalidate
the contract. Any additional work which the
contractor may be directed to do in the matter
above specified as part of the work, shall be
carried out by the contractor on the same
conditions in all respects on which he agreed to
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 6 of 9
do the main work and at the same rates as are
specified in the tender for the main work. The
time for the completion of the work shall be
extended in the proportion that the additional
work bears to the original contract work and the
certificates of the Engineer in charge shall be
conclusive as to such proportion and if the
additional work includes any class of work shall
be carried out at the rates entered in the
sanctioned schedule of rates of the locality
during the period when the work being carried on
and if such last mentioned class of work is not
entered in the schedule of the rate of the
district, then the contractor shall within 7 days
intimate the rate which it is his intention to
charge for such class of work and if the Engineer-
in-charge does not agree to this rate he shall by
notice in writing be at liberty to cancel his
order to carry out such class of work and arrange
to carry such class of work and arrange to carry
out in such manner as he may consider advisable.
No deviation from the specification stipulated in
the contract or additional items of work shall
ordinarily be carried by the contractor and should
any altered, additional or substituted work be
carried out by him unless the rates of the
substituted, altered or additional
569
items have been approved as fixed in writing by
the Engineer-in-charge.
The contractor shall be bound to submit his
claim for any additional work done during any
month or before the 15th day of the following
months accompanied by the copy of the order in
writing of the Engineer-in-Charge for the
additional work and that the contractor shall not
be entitled to any payment in respect of such
additional work if he fails to submit his claim
within the aforesaid period.
Provided it always that if the contractor
shall commence work or incur any expenditure in
regard thereof before the rates will have been
determined as lastly herein before mentioned, then
in such case he shall only be entitled to be paid
in respect of the determination of the rates as
aforesaid accordingly to such rate of rates as
shall be fixed by the Engineer-in-Charge. In the
event of a dispute the decision of the
Superintending Engineer of the Circle will be
final. "
This clause has to be read in conjunction with the
arbitration clause i.e. clause 23, which provides as
follows:
"Clause 23: Except where otherwise provided in the
contract all questions and disputes relating to
the meaning of the specifications, designs and
instructions hereinbefore mentioned and as to the
quality of workmanship or materials used on the
work or as to any other question, claim, right
matter, or thing whatsoever in any way arising out
of, or relating to the contract, designs, drawing
specifications, estimates, instructions, orders or
these conditions or otherwise concerning the works
or the execution or failure to execute the same
whether arising during the progress of work, or
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 7 of 9
after the completion or abandonment thereof shall
be referred to the sole arbitration of a
Superintending Engineer of the Circle. It will be
no objection to any such appointment that the
arbitrator so appointed is a Government servant.
The award of the arbitrator so appointed shall be
final. conclusive and binding on all parties to
this contract.
The learned Subordinate Judge was inclined to hold that
the
570
arbitrator had no jurisdiction to arbitrate on disputes
which he has purported to do but in view of the Bench
decision of the High Court of Orissa in State of orissa v.
Gokulchandra Kanungo, [1981] 52 CLT 416, he held that he was
not free to decide that the dispute was not arbitrable and
rejected this plea. The High Court also did not entertain
this objection. It was canvassed before us and submitted
that in view of clause 11, the matters in dispute and the
amount due for the alleged additional work, were not
arbitrable at all. We have noticed clause 11 which makes the
decision of the Engineer-in-Charge final in respect of some
issues. In this connection, it is important to refer to the
proviso of Clause 11 which states that in case of dispute
about the rates and time for completion of the work and any
dispute as to proportion that the additional work bears to
the original contract work, the decision of the
Superintending Engineer of the Circle would be final. The
points upon which the arbitrator in the instant case has
adjudicated are not those which are excepted or covered by
Clause 11 of the agreement. In that view of the matter, this
clause has no application in the instant controversy.
Our attention was drawn to certain observations of this
Court in Bombay Housing Board (Now the Maharashtra Housing
Board) v. Karbhase Naik & Co., Sholapur, s
[1975] 3 SCR 407. There in view of clause 14 of the said
contract, it was open to the respondent to make claim on the
basis of the rates quoted. There, Clause 14 was more or less
identical to Clause 11 in the present case. This particular
contention, however, did not arise in that case. The Court
held that the respondent there being contractor, was not
bound to carry out additional or altered work and there was
no reply to the notice stating the rates intended to be
charged and the respondent there was not free to commence
and complete the work on the basis that since the rates
quoted were not accepted, it would be paid at such rates to
be fixed by the Engineer-in-charge and that if it was
dissatisfied with the rate or rates fixed by the Engineer-
in-charge, it could raise a dispute before the
Superintending Engineer and that the time limit for
completion would be extended in all cases. This Court
observed that only the rates were settled by the agreement.
The respondents were under no obligation to carry out the
additional or altered work but that is not the dispute
before us in the present case. On the construction of Clause
11 of the contract, we are unable to accept the contention
but on the points that the arbitrator has awarded in this
case, were excluded by Clause 11 of the contract herein.
Shri Mehta, however, strongly relied on certain observations
of a Bench decision of Madhya Pradesh High Court in case of
the Chief Administrator, Dandakaranya Project,
571
Koraput, Orissa & Anr. v. M/s. Prabartak Commercial Corpn.
Ltd. Calcutta, AIR 1975 MP 152, wherein while considering
Clause 13A of the agreement there the High Court held that
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 8 of 9
the dispute whether charges for stone chips could be
adjudicated, was not arbitrable. That was a case of rates
which was within the jurisdiction of the Engineer-in-charge
by Clause 13A of the bargain between the parties. In the
instant case it is not the rate which is in dispute. The
Madhya Pradesh High Court referred to several decisions of
this type and came to the conclusion on the construction of
Clause 13A in that case that the dispute that had arisen
between the parties in arbitration, was excluded by Clause
13A of the agreement. In view of the Clause in the instant
case and the nature of the dispute which had arisen, we are
of the opinion that such decisions also cannot give much
assistance to the appellant. Reliance was also placed on
certain observations of the Delhi High Court in the case of
Food Corporation of India v. P.L. Juneja, AIR 1981 Delhi 43.
There the Division Bench of the High Court was concerned
with the questions which were to be decided by the Court and
not by the arbitration. There also the Clause was very much
dissimilar to the present one which is set out hereinbefore.
Clause 15(c) provided that the question whether a particular
service is or is not to be covered by any of the services
specifically described and provided for the contract, or is
or is not material to any such services shall be decided by
the Regional Manager whose decision shall be final and
binding. It was not the case whether any additional work was
done and if so, the extent of such work. In the aforesaid
view of the matter it is not possible to hold that in view
of nature of instant dispute, the matters at issue were not
excluded and the arbitrator did not commit any wrong in
proceeding with the arbitration.
It was next contended that an amount of Rs.15,23,657
has been granted for additional work over and above the
payment of Rs.23,74,001 and this was disproportionately high
and the award for this amount was per se bad. It is well-
settled that when the parties choose their own arbitrator to
be the judge in dispute between them, they cannot, when the
award is good on the face of it, object to the decision
either upon law or on facts. Therefore, when arbitrator
commits a mistake either in law or in fact in determining
the matters referred to him, where such mistake does not
appear on the face of the award and the documents appended
to or incorporated so as to form part of it, the award will
neither be remitted nor set aside. The law on this point is
well-settled. See in this connection the observations of
this Court in Union of lndia v. Bungo Steel Furniture P.
Ltd., [1967] 1 SCR 324 and Allen Berry & Co. (P) Ltd. v.
Union of India, [1971] 3 SCR
572
282. It was, however, contended that the amount of the award
was shockingly high that it shocked the conscience of the
Court and the award must be set aside. The fact that merely
the award amount is quite high as commented by the High
Court or that a large amount has been awarded, does not
vitiate the award as such. In the instant case the original
award was for Rs.9,99,510. Admittedly, additional work was
done and payment for such work was determined at
Rs.23,74,001 and claim for further additional work was made
for Rs. 15,23,657. One has to judge whether the amount of
the award was so disproportionately high to make it per se
bad in the facts and circumstances of a particular case. It
is clear from the facts that the arbitrator is a highly
qualified person having several Indian and foreign Degrees
and at the relevant time was acting as Chief Engineer-in-
charge of the State Government. Having regard to the nature
of claims involved and the fact that the additional work has
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 9 of 9
been done for which large amounts have been paid and in this
case it is evident that all due opportunities were given to
the parties to adduce all evidence, we are unable to accept
the submission that the award was so disproportionate as to
shock the conscience of the Court and, as such, it cannot be
held that the award was bad per se. In our opinion, the High
Court was right in dismissing the challenge to the award on
this ground.
In support of the submission that the award must be
held to be bad in this case, Mr. Mehta drew our attention to
certain observations of Orissa High Court in State of Orissa
& Ors. v. Gangaram Chhapolia & Anr., AIR 1982 Orissa 277,
where at page 279 the learned Judge observed the malady of
the racket of arbitration was rampant in Orissa. Though the
learned Judge was apparently heeding to the observations of
Justice Holmes of America observed that the Court should
take note of "the felt necessities of the time".
In our opinion, the evidence of such state of affairs
should make this Court scrutinise the award carefully in
each particular case but that does not make the Court
declare that all high amounts of award would be bad per se.
As mentioned hereinbefore, it cannot be said that the amount
of award was disproportionately high to hurt the conscience
of the Court in this case.
It is now well-settled that the interest pendente lite
is not a matter within the jurisdiction of the arbitrator.
In this connection reference may be made to the observations
of this Court in Executive Engineer (Irrigation), Balimela &
Ors., v. Abhaduta Jena & Ors., [1988] 1 SCC 418 where this
Court held that the arbitrator could not
573
grant interest pendente lite. In the aforesaid view of the
matter this A direction in the award for the payment of such
interest must be deleted from the award. The order of the
High Court is modified to the extent that the award is
confirmed subject to deletion of the interest pendente lite.
We make it clear that in the facts of this case interest for
the period from 26.9.81 to 18.3.83, the date of the award be
deleted. The High Court has, however, granted interest from
the date of the decree. That is sustained.
The appeal is, therefore, dismissed except to the
extent indicated above. In the facts and circumstances of
the case the parties will pay and bear their own costs.
G.N. Appeal dismissed.
574