EASTERN COALFIELDS LTD. vs. INDIA POWER CORP. LTD.

Case Type: Not Found

Date of Judgment: 15-03-2022

Preview image for EASTERN COALFIELDS LTD. vs. INDIA POWER CORP. LTD.

Full Judgment Text

NON­REPORTABLE IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION M.A. Diary No.20972 of 2021 In Civil Appeal No.9847 of 2014 INDIA POWER CORPORATION LTD.                …APPELLANT VERSUS EASTERN COALFIELDS LIMITED      RESPONDENT/ APPLICANT J U D G M E N T VIKRAM NATH, J. 1 Civil   Appeal   No.9847   of   2014   was   allowed   vide   order   dated 17.10.2014 whereby Justice S.S. Nijjar, a former Judge of this Court was   appointed   as   sole   Arbitrator   to   arbitrate   upon   the   disputes between the parties. The said order is reproduced below: ­ “     Leave granted.  Heard Mr. Kapil Sibal, learned senior counsel appearing for the petitioner and Mr. Anupam Lal Das, learned counsel for respondent no.1.  Signature Not Verified Digitally signed by Chetan Kumar Date: 2022.03.15 16:48:21 IST Reason: In the course of hearing, learned counsel for the parties very fairly submitted that they have no objection if a former 1 Judge   of   this   Court   is   appointed   as   a   Sole   Arbitrator   to arbitrate upon the disputes that have arisen in respect of the contract.  Regard   being   had   to   the   aforesaid   submission,   we appoint Justice S.S. Nijjar, a former Judge of this Court as the Sole  Arbitrator to arbitrate  upon the  disputes. The  learned arbitrator   shall   decide   the   terms   and   conditions   after deliberating with the parties.  Registry is directed to forward a copy of this order to the learned Arbitrator.  The appeal is allowed on above terms. There shall be no order as to costs. ” 2. The   sole   Arbitrator   gave   the   award   dated   15.02.2021,   after considering the claims and counter claims of the parties. The operative portion of the award as contained in paragraph 162 is reproduced below: ­ “162. In view of the aforesaid conclusions the following award is made: (a)   The   Respondent   shall   pay   to   the   Claimant   a   sum   of Rs.24.7256 Crores as WDV. (b) The aforesaid amount shall be paid with interest @9% with effect from 06.10.2016 till payment of the amount.  (c)   The   Claimant   shall   pay   to   the   Respondent   a   sum   of Rs.18,66,86,521/­  (d) The aforesaid amount shall be paid with interest @9% with effect from 06.10.2016 till payment of the amount.  (e) All other Claims and Counter­Claims are hereby dismissed.  COSTS: In   the   peculiar   facts   and   circumstances   of   this arbitration, both the parties shall bear their own costs.  This Award is being issued on a stamp paper of Rs.200/­. The   Claimant   shall   pay   the   differential   stamp   duty   in accordance with law.” 2 3. M.A.   No.   20972   of   2021   has   been   filed   by   the   respondent ‘Eastern Coalfields Limited’ (hereinafter referred to as the “ECL”) with a prayer to appoint a sole arbitrator to examine the issue pertaining to the report submitted by MECON as mentioned in paragraph 160 of the award. The relief claimed by means of this application is reproduced below: ­ “ PRAYER In   view   of   the   facts   and   circumstances   of   the   case,   your Lordship may graciously be pleased to: a) Appoint a Sole Arbitrator to examine the issue pertaining to the report submitted by MECON more particularly mentioned in paragraph No.160 of the Award which was not adjudicated by the Hon’ble Tribunal; b) Pass any other order/orders which this Hon’ble Court may deem fit.” 4. The   only   ground   raised   for   seeking   a   fresh   appointment   of Arbitrator is to the contents of paragraph 160 of the award.  It is for this reason that the present application has been filed for appointment of Sole Arbitrator. 5. According   to   the   respondent­applicant,   the   learned   Arbitrator could not adjudicate upon the MECON report, as it required further evidence   to   be   recorded,   and   soon   after   delivering   the   award,   on 15.02.2021, the learned Arbitrator died on 26.03.2021.  6. Learned Counsel for the applicant, ECL during the course of the arguments   not   only   requested   for   appointment   of   Arbitrator   with respect to the contents of the paragraph 160 of the award but raised a 3 further issue relating to Section 33 of the Arbitration and Conciliation Act,   1996   (hereinafter   referred   to   as   ‘the   1996   Act’)   for   requiring correction in the computation of the rent payable to the applicant ECL for the period March 2016 till October 2016 which was inadvertently left out by the learned Arbitrator while giving the award.   Reference was made to paragraphs 126 to 130 and 132 of the award.  It is also submitted that although limitation for moving an application under Section 33 is 30 days but in the present case as the limitation has stopped running and stood extended by the orders passed by this Court in the   suo moto   petition, the applicant would have a right to maintain an application under Section 33 for correction of the award nd for which the present application has been filed on 2   September, 2021. 7. On   the   other   hand,   learned   counsel   for   the   appellant   ‘India Power   Corporation   Limited’   (hereinafter   referred   to   as   the   “IPCL”) vehemently   opposed   the   application   and   made   the   following submissions: i)   Paragraph   160   of   the   award   may   not   be   read   in isolation.   The background for the same should also be read   as   recorded   in   the   preceding   and   succeeding paragraphs.  Paragraphs 157 to 161 of the award may be read as a whole.   The same will completely clarify the position.  4 ii)   In   the   part   covering   paragraphs   157   to   161,   the learned   Arbitrator   was   dealing   with   amendment   of counter claim filed by the respondent­applicant i.e. ECL. After   considering   all   aspects   of   the   matter,   the application for amendment was dismissed as it would not serve any useful purpose in determining the real question in controversy. Reference may be had to paragraph 161 of the award. iii) The contents of paragraph 160 of the award records the submission advanced by the counsel for the claimant i.e.   the   appellant  IPCL.   If   paragraph   160  is   examined carefully, the submissions advanced by the counsel for the respondent­applicant may not have much substance.  iv)  Award dated 15.02.2021 was a final award and not an   interim   award;   The   learned   arbitrator   had   not   left anything   for   further   deliberation   but   had   settled   the claim and the counter claim between the parties  in toto . v)  The remedy available to the respondent­applicant was to file objections under Section 34 of the 1996 Act against the award, if it had any grievance.  vi) Further,   the   objection   under   Section   34   of   the 1996 Act were filed before the Delhi High Court which was   registered   as   O.M.P.(COMM)   328/2021,   CAV 49/2021,   I.A.   Nos.   14204­14207/2021,   Eastern 5 Coalfields   Limited   vs.   India   Power   Corporation Limited . The said objection has since been decided by the Delhi High Court vide judgment dated 29.10.2021 and   the   same   has   been   dismissed.   A   copy   of   the judgment of Delhi High Court dated 29.10.2021 has been filed   by   the   respondent­applicant   along   with I.A.No.154735 of 2021. vii) The issue relating to Section 33 of the 1996 Act with respect to correct computation of rent cannot be considered for several reasons. There is not a whisper in the application for direction regarding the issue raised under Section 33. Such a plea cannot be raised during the course of the arguments by way of oral or written submissions.   viii) Even   otherwise   no   correction   as   raised   was required inasmuch as no computation was undertaken by the learned Arbitrator and the amount awarded as rent   was   the   same   as   claimed   by   the   applicant   ECL. Even on merits such plea was not tenable.  8. Having considered the submissions, we now proceed to analyse both the contentions of the applicant.   6 9. Paragraph 160 of the award cannot be read in isolation.  It was a part of the award dealing with the “ Application for amendment of counter claim ” filed by respondent­ECL.  The award carried the above sub­title   before   paragraph   157.     Paragraph   160   contains   mere submissions advanced on behalf of the appellant/claimant. MECON report was called with respect to the amendment of the counter claim regarding   expenses   required   for   putting   the   plant   into   running condition. After deliberating upon the said amendment, at the end of paragraph   161,   the   conclusion   was   that   the   application   for amendment stood dismissed.   Thus, the paragraphs 157 to 161 will have   to   be   read   as   a   whole   to   understand   as   to   how   the   award proceeds   to   deal   with   the   amendment   to   the   counter   claim. Paragraphs 157 to 161 of the award being relevant are reproduced hereunder: ­ “157. At this stage it may be noticed that the Respondent filed an   application   dated   20.11.2019   seeking  permission   of   the Tribunal   to   amend   the   Counter­claim.     Claimant   was permitted to file reply to the same on or before 22.11.2019. Claimant   has   filed   the   reply   on   20.11.2019.     Thereafter arguments   in   Rejoinder   were   heard   on   27.11.2019   and 02.12.2019.  However, no oral submissions were made on the application by either party.  I have considered the application on the basis of the pleadings.  It has been noticed earlier that Respondent had issued a Notice inviting Tender on 16.01.2012 for “…(a) Replacement of Existing twenty (20 year old 3X10 MW   stoker­fired   boilers   by   3X10   MW   Fluidised   bed combustion (FBC) boilers, wherein the successful bidder will made his own investment for replacement of existing stoker fired boilers by FBC Boilers and associated other plant and machineries  including  the  civil  works  and  enter  into  Lease Agreement   with   ECL   for   running   of   the   power   plant….”. Therefore,   it   appears   that   the   run   down   condition   of   the existing   stoker­fires   boilers   had   become   irrelevant.     The 7 application   for   amendment   of   the   counter­claim   can   be dismissed at this stage only. 158. Even from the evidence on record it is evident that the plant was in running condition at the time when the lease expired by efflux of time. The Respondent was fully aware that the plant being in running condition was wholly irrelevant, yet the controversy continued even after the issuance of the NIT. The NIT clearly indicates in clause 1(b) that the Power Plant is offered for lease "on as is where is basis''. Clause 1(c) further makes   it   clear   that   "the   existing   plant   is   in   operating condition. The plant is to be operated as a Captive Power Plant of ECL”. In view of the above clauses, the Respondent cannot now be permitted to raise a further Claim on the ground that the Power Plant had to be put into running condition. 159. Had the possession been taken before issuing the NIT, undoubtedly,   the   Plant   was   operating   and   therefore   clearly cannot be said to be not in running condition. It appears that the deterioration, if any, occurred when the Claimant failed to handover the possession as there was no agreement on the determination of WDV of the Plant. It has come in evidence that   in   four   year's   time   the   Plant   and   machinery   had deteriorated considerably as the Plant was lying idle. In view of the detailed submissions made in this regard, on behalf of the Claimant, which are noted at paragraphs 84 to 99 and the reply thereto on behalf of the Respondent, which are noted in paragraphs 104 till 112, it would not be possible to hold that the Claimant is solely responsible for the delayed delivery of possession to the Respondent.  On the one hand Claimant was insisting on the basis of the Clause III(a) for the determination and   payment   of   the   WDV   simultaneously   to   delivery   of possession. On the other hand, Respondent had demanded delivery of possession much prior to the determination of the WDV.   Even   when   the   WDV   was   determined   by   the Respondent,   it   was   at   such   a   variance   to   the   amount determined   by   the   Claimant,   making   it   impossible   for   the parties to reach a consensus on the WDV to be paid. In fact, as noticed earlier the Claimant had filed a Writ Petition No.20948 of 2012.  In the Calcutta High Court seeking payment of WDV and handing over possession of the Plant. This Petition was disposed of by the High Court on 19.03.2013.   The Learned Single Judge noticed “…that there is a subsisting dispute as regards computation of written down value in respect of the additions   and   alterations   made   by   the   writ   petitioners   in relation to the said generating station. It is for this reason the dispute still remains unresolved. The petitioners continue to remain   in   possession   of   the   generating   station   and   the respondent coal company has also not taken any legal step to recover   possession   of   the   station…”.   It   is   noticed   by   the Learned Single Judge that the main prayer in the Writ Petition is   “to   prevent   the   respondents   from   obtaining   recovery   of 8 possession   of   the   generating   station   without   releasing   the written down value of the added assets, as per computation of the   petitioners.”     It   is   also   noticed   that   in   spite   of   orders passed by the Court on 12.10.2012 that “…steps ought to be taken by the committee to not only physically verify the plant and   machinery   but   also   other   assets   of   the   plant   by ascertaining the book value thereof…”. no steps were taken. This exercise was to be completed by 12.12.2012.  Since, the exercise   was   not   completed   by   that   time,   the   time   was extended till 08.01.2013.  At the time of final disposal of the Writ   Petition   the   Learned   Single   Judge   observed   that   the dispute does not seem to be resolvable by the committee set up by the respondent. It is noticed that the issues involved are also highly disputed factual issues. The matter was therefore referred to arbitration under the relevant clause of the lease deed. In appeal the Division Bench upheld the order of the Learned Single Judge on 19.03.2014. As noticed earlier the Supreme Court referred the matter to the Sole Arbitrator by order October 17, 2014, with the observation that the Sole Arbitrator is “to arbitrate upon the disputes”. From the above, it   seems   apparent   that   the   reference   to   arbitration   is   not limited to disputes that existed prior to the passing of the order by the Supreme Court. Therefore, it cannot be accepted that the reference to arbitration would not cover the Counter­ Claims. 160. It must also be noticed here that the Claimant has raised a preliminary objection on the ground that the application for amendment suffers from delay and laches. Therefore, seeks it’s dismissal on this short ground. It is submitted that Claimant has already filed its objection to the MECON report and also filed a report submitted by M/s AKB Power Consultants Pvt. Ltd. For consideration of these two reports, further evidence will have to be recorded on behalf of both the parties. 161. It is matter of record that the application for amendment was filed at the time when the Respondent was to commence its arguments. In my opinion that the application cannot be allowed at this stage. The amendment must be necessary for the purpose of determining the real question in controversy. As noticed above, the issuance of the NIT clearly demonstrates the   intention   of   the   respondent   was   to   replace   the   old machinery and plant to Stoker Fired Boilers by Fluidised bed Combustion   Boilers.   Therefore,   the   condition   of   the   old machinery as well as the question of plant being in a running condition had become irrelevant. For the reasons stated above, the application for amendment is dismissed as it will serve no useful   purpose   in   determining   the   real   questions   in controversy between the parties.”  9 10. By means of the said amendment, the ECL had claimed that the power plant should be put into running condition before handing over its possession.   The learned Arbitrator deals with the issue in detail and after considering the pleadings of the parties as also the order passed   by   the   Calcutta   High   Court   found   that   the   counter   claim sought to be raised by the said amendment regarding the plant being in a running condition was irrelevant in view of the dispute raised.  11. The MECON report and the M/s AKB Power Consultants Pvt. Ltd. report, both related to the expenses sought to be incurred in bringing back the plant into running condition.  Parties had filed their objections to both the reports as there was substantial difference in the figures indicated in the two reports.  But once the Arbitrator found that the amendment in the Counter­claim itself was not relevant for the adjudication, there was no question of proceeding any further in inviting evidence etc. with respect to the reports.   The submission therefore, that there is requirement of the appointment of Arbitrator to carry out the exercise as per paragraph 160 of the award is therefore completely untenable.  The submission is based upon the misreading and misrepresentation of the said paragraph, in isolation bereft of preceding   and   succeeding   paragraphs.   The   same   is   accordingly rejected.     10 12. A bare perusal of the award, in particular paragraph 162, which is the operative portion, does not in any manner indicate any kind of it being an interim award or that any aspect of the matter was to be further considered. In any case, the learned arbitrator did not record any further observation that for leading of further evidence any date has to be fixed or the parties were given opportunity to produce their evidence.  It was  a mere  submission that  consideration  of MECON report   would   require   further   evidence   but   was   not   found   to   be necessary by implication.  13. The next submission relating to the applicability of Section 33 of the 1996 Act also has to fail for two reasons.  Firstly, that the same is neither pleaded nor prayed in the application and secondly, once the Arbitrator, while awarding rent as counter claim had accepted the figures as quoted by the ECL, no issue of any error on the part of the Arbitrator in not correctly calculating the rent could be raised.   The figure as claimed by the ECL is quoted in paragraph 73(1)(ii) of the award which has been accepted by the Arbitrator in the award. 14. There   is   another   aspect   of   the   matter   which   disentitles   the applicant   from   any   relief   in   this   application.     A   perusal   of   the judgment   of   the   Delhi   High   Court   in   Section   34   of   the   1996   Act proceedings clearly reveals that the point which is being raised here was raised before the Delhi High Court. The Delhi High Court also did 11 not   agree   with   the   submission   of   the   respondent­applicant   after considering paragraphs 157 to 161 and proceeded to hold that the observations made  in  paragraph 160  do  not  render  the impugned order to be interim in nature, and that the award finally decided the dispute which was subject matter of the reference.   15. For all the reasons recorded above, the application deserves to be rejected and is accordingly rejected. ………….........................J. [VIKRAM NATH] …………..........................J. [M.M. SUNDRESH] NEW DELHI MARCH  15, 2022. 12