Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 7
CASE NO.:
Appeal (civil) 1953 of 2006
PETITIONER:
NATIONAL THERMAL POWER CORPORATION LTD.
RESPONDENT:
SIEMENS ATKEINGESELLSCHAFT
DATE OF JUDGMENT: 28/02/2007
BENCH:
A.K. MATHUR & P.K. BALASUBRAMANYAN
JUDGMENT:
JUDGMENT
A.K. MATHUR, J.
1. This appeal is directed against the order passed by the Delhi High Court
dated 24-5-2005 challenging the partial award given by the International
Chamber of Commerce, Arbitration Tribunal on 31-7-2002.
2. Brief facts which are necessary for disposal of this appeal are that on
6-12-1999 the parties entered into a contract for setting up of 817 MW Gas
Based Combined Cycle Power Project at Dadri, U.P. at a price of DEM
324,405,000 equivalent to Rs.2,190,000,000/- (Rupees two thousand one
hundred ninety million). At the request of the respondent- Siemens
Atkeingesellschaft (hereinafter to be referred to as "SAG") three separate
contracts were entered into with cross-fall breach clause. One contract was
with respondent -SAG known as "First Contract" and the other with its
associates, namely Bharat Heavy Electricals Limited (BHEL), New Delhi and
the third with Siemens Limited, Bombay. Considerable delay occurred in
execution of the contract which was mostly attributable to the appellant-
National Thermal Power Corporation (hereinafter to be referred to as
"NTPC"), due to delay in opening of Letters of Credit in favour of the
respondent-SAG and in obtaining import licences for various equipments from
Statutory Authorities. Respondent raised several claims against the
appellant-NTPC for losses resulting from delay. On the other hand, the
appellant was also facing acute difficulty in getting the critical
components and spare parts and tools from the respondent. In order to sort
out the said disputes, a high-powered meeting of the parties was held on
6th/7th April, 2002 in which several decisions were taken. One of the
decisions taken in the meeting was that the respondent was to supply the
critical components and spare parts etc. to the appellant-NTPC on its part
and on the other hand the appellant-NTPC agreed to look into the claim
raised by the respondent-SAG with more positive approach in view of the
fact that there was delay in arranging import licences and opening of
Letter of Credit by the appellant-NTPC. In pursuance to the decision, the
respondent-SAG supplied the critical components etc. but the appellant-NTPC
did not favourably consider the claim of the respondent-SAG for damages on
account of the aforesaid delay. Subsequently, the respondent-SAG made a
reference to ICC Court of Arbitration, Paris for settlement of their
disputes/claim to compensation on account of delay in terms of Clause 27 of
the Contract. The ICC International Court of Arbitration registered the
reference as Case No. 11728/ACS and on 5th May, 2002 issued terms of
reference. The ICC International Court of Arbitration was comprised of
three Arbitrators, namely Mr. Arthur Marriott QC, Chairman and Mr. Justice
R.S. Pathak and Mr. Justice A.M. Ahmadi, two former Chief Justices of the
Supreme Court of India. While the claim of the respondent-SAG related
largely to compensation on account of delay on the part of the appellant-
NTPC in procuring the import licences and belated opening of the Letter of
Credit in favour of the respondent, the appellant-NTPC besides filing their
defence to the said claims also filed several counter claims on various
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 7
counts amounting to hundreds of crores of rupees against the respondent-
SAG. The respondent-SAG resisted the said counter claims of the appellant-
NTPC inter alia on the grounds that the counter claims were not arbitrable
because the claims had been waived and/or abandoned and/or discharged
and/or satisfied or compromised and the appellant had failed to fulfil the
condition precedent to arbitration specified in Clauses 26 & 27 of the
General Conditions of Contract. Number of issues were framed and the
Tribunal after considering the submissions of the parties, gave a partial
award on 31-7-2002 and held that the claim of the respondent-SAG was
maintainable and was not barred by limitation while the counter claims of
the appellant-NTPC was not admissible because the same were caught by the
agreement contained in the minutes of meeting (MoM) dated 6th/7th April,
2000. Aggrieved against this partial award so far as it non-suited the
appellant-NTPC in respect of their counter claims, the appellant-NTPC
directly approached the High Court by filing an appeal.
3. The preliminary objection which was raised before the High Court was
whether the appeal filed against the partial award of the ICC International
Court of Arbitration was maintainable or not. Learned Single Judge of the
High Court after elaborate discussions on the subject, took the view that
the appeal under Section 37(2)(a) of the Arbitration & Conciliation Act,
1996 (hereinafter to be referred to as "the Act") was not maintainable. It
was observed by the learned Single Judge as follows:
"This Court on a thorough examination of the material obtaining on
record, more particularly on a conjoint reading of the pleadings of
the parties filed before the Arbitral Tribunal, the Terms of
Reference framed by the International Chamber of Commerce, the
written submissions filed by the parties before the Arbitral
Tribunal prior and after the closure of the hearing, the tenor of
the reasoning and finding recorded by the Arbitral Tribunal in its
dispensation titled as "Partial Final Award" and on a true
construction and scope of the provisions of Section 16 and Section
37 of the Act, is clearly of the view that the impugned
dispensation dated 31-7-2002 rendered by the Arbitral Tribunal
cannot by any stretch be said to be an order passed by the Tribunal
either under the provisions of Section 16(2) or Section 16(3) of
the Act and in any case deciding the question of jurisdiction in
the negative which will fall within the ambit of appelable orders
within the meaning of Section 37(2)(a) of the Act. In the opinion
of this Court, the impugned partial Award is nothing but an Award
of interim Award deciding the counter claims of the NTPC finally on
merits. This Court, therefore, must hold that the present appeal
filed by the NTPC against such a Partial Award under the provisions
of Section 37(2)(a) of the Act is misconceived and is not
maintainable.
Aggrieved against this order, the present appeal has been filed by the
appellant-NTPC.
4. We have heard learned counsel for the parties and perused the records.
The question before us in the present appeal is whether the view taken by
learned Single Judge of the High Court that the appeal under Section 37 of
the Act is maintainable against the interim award or not. Learned counsel
for the appellant took us through all the details of the pleadings and
tried to persuade us that the question of jurisdiction and limitation is
involved, therefore, the appeal is maintainable under Section 37 of the
Act. The first and foremost question before us is to examine the provisions
of Section 37 read with Section 16 of the Act. Section 37 of the Act reads
as under:
"37. Appelable orders.- (1) An appeal shall lie from the following
orders (and from no others) to the Court authorized by law to hear
appeals from original decrees of the Court passing the order,
namely:-
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 7
(a) granting or refusing to grant any measure under section 9;
(b) setting aside or refusing to set aside an arbitral award under
section 34.
(2) An appeal shall also lie to a Court from an order granting of
the arbitral tribunal-
(a) accepting the plea referred in sub-section (2) or sub-section
(3) of section 16; or
(b) granting or refusing to grant an interim measure under section
17.
(3) No second appeal shall lie from an order passed in appeal under
this section, but nothing in this section shall affect or take away
any right to appeal to the Supreme Court."
So far as Section 37(1)(a) of the Act is concerned, it contemplates that no
appeal shall lie from any orders except, namely granting or refusing to
grant measure under Section 9. Section 9 deals with interim orders and
Section 37(1)(b) relates to order passed under Section 34 i.e. setting
aside or refusing to set aside an arbitral award under section 34. Sub-
section (2)(a) of Section 37 provides that appeal shall also lie to the
Court from an order of the arbitral tribunal accepting the plea under sub-
section (2) or sub-section (3) of Section 16 and sub-section (2)(b)
contemplates appeal against the order granting or refusing to grant an
interim measure under section 17 i.e. at the time of pendency of the
arbitration proceedings by the Tribunal. Sub-section (3) says that no
second appeal shall lie from the orders passed in appeal under this
section. Now we shall examine the scope of Section 16, which reads as
under:
"16. Competence of arbitral tribunal to rule on its jurisdiction.-
(1) The arbitral tribunal may rule on its own jurisdiction,
including ruling on any objections with respect to the existence or
validity of the arbitration agreement, and for that purpose,
(a) an arbitration clause which forms part of a contract shall be
treated as an agreement independent of the other terms of the
contract; and
(b) a decision by the arbitral tribunal that the contract is null
and void shall not entail ipso jure the invalidity of the
arbitration cause.
(2) A plea that the arbitral tribunal does not have jurisdiction
shall be raised not later than the submission of the statement of
defence; however, a party shall not be precluded from raising such
a plea merely because that he has appointed, or participated in the
appointment of, an arbitrator.
(3) A plea that the arbitral tribunal is exceeding the scope of its
authority shall be raised as soon as the matter alleged to be
beyond the scope of its authority is raised during the arbitral
proceedings.
(4) The arbitral tribunal may, in either of the cases referred to
in sub-section (2) or sub-section (3), admit a later plea if it
considers the delay justified.
(5) The arbitral tribunal shall decide on a plea referred to in
sub-section (2) or sub-section (3) and, where the arbitral tribunal
takes a decision rejecting the plea, continue with the arbitral
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 7
proceedings and make an arbitral award.
(6) A party aggrieved by such an arbitral award may make an
application for setting aside such an arbitral award in accordance
with section 34."
Sub-sections (2) & (3) of Section 16 deal with jurisdiction. Sub-section
(2) of Section 16 says that a plea of lack of jurisdiction of the tribunal
should be raised at the earliest i.e. not later than submission of
statement of defence and it further says that a party shall not be
precluded from raising such a plea merely because he has appointed, or
participated in the appointment of an arbitrator. Sub-section (3) says that
the plea that the arbitral tribunal is exceeding the scope of its authority
shall be raised during the arbitral proceedings. A reading of sub-sections
(2) & (3) of Section 16 makes it clear that it deals with jurisdiction i.e.
that the arbitral tribunal has no jurisdiction or that the arbitral
tribunal has exceeded its jurisdiction. In either of the two situations, a
direct appeal is maintainable under sub-section (2) of Section 37.
Therefore, in the light of this legal position we shall examine whether the
tribunal while awarding an interim award has exceeded its jurisdiction or
it had no jurisdiction whatsoever.
5. So far as sub-section (2) of Section 16 is concerned, we may
straightaway dispose of the question of lack of jurisdiction on the part of
the tribunal since that is not involved in the present case. But the
emphasis in the present case was that the tribunal had exceeded its
jurisdiction in passing a partial award. The facts have already been
mentioned above. It may be relevant to mention here the relevant clause of
the agreement which deals with arbitration. Clauses 26 & 27 of the General
Conditions of Contract reads as under:
"26.0. SETTLEMENT OF DISPUTE
26.1. Any dispute(s) or difference(s) arising out of or in
connection with the Contract shall to the extent possible be
settled amicably between the parties.
26.2. Except as otherwise specifically provided in clause 27.0
herein under all unsettled dispute(s) or difference(s) arising out
of or in connection with the Contract shall in the first instance
be decided by an engineer whose decision shall be final and binding
on the parties.
27.0 ARBITRATION
27.1. If any dispute or difference of any kind whatsoever shall
arise between the Owner and the Contractor, arising out of the
Contract for the performance of the Works whether during the
progress of the Works or after its completion or whether before or
after the termination, abandonment or breach of the Contract, it
shall, in the first place, be referred to and settled by the
Engineer, who, within a period of thirty (30) days after being
requested by either party to do so shall give written notice of his
decision to the Owner and the Contractor.
27.2. Save as hereinafter provided, such decision in respect of
every matter so referred shall be final and binding upon the
parties until the completion of the works and shall forthwith be
given effect to by the Contractor who shall proceed with the Works
with all due diligence whether he or the Owner requires arbitration
as hereinafter provided or not.
27.3. If after the Engineer has given written notice of his
decision to the parties no claim to arbitration has been
communicated to him by either party within thirty (30) days from
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 7
the receipt of such notice, the said decision shall become final
and binding on the parties.
27.4. In the event of the Engineer failing to notify his decision
as aforesaid within thirty (30) days after being requested as
aforesaid, or in the event of either the Owner or the Contractor
being dissatisfied with any such decision, or within thirty (30)
days, as the case may be, either party may require that the matters
in dispute be referred to arbitration as hereinafter provided.
27.5. All disputes or differences in respect of which the decision
if any of the Engineer has not become final or binding as
aforesaid, shall be settled by arbitration in the manner
hereinafter provided.
27.6. In the event of foreign Contractor, the arbitration shall be
conducted by three arbitrators, one each to be nominated by the
Owner and the Contractor and the third to be named by the President
of the International Chamber of Commerce, Paris, save as above all
Rules of Conciliation and Arbitration of the International Chamber
of Commerce shall apply to such arbitrations. The arbitration shall
be conducted at such places as the arbitrators may determine.
27.7. The decision of the majority of the arbitrators shall be
final and binding upon the parties. The expense of the arbitration
shall be paid as may be determined by the arbitrators. The
arbitrators may from time to time, with the consent of all the
parties enlarge the time for making the award. In the event of any
of the aforesaid arbitrators dying, neglecting, resigning or being
unable to act for any reason it will be lawful for the party
concerned to nominate another arbitrator in place of the outgoing
arbitrator."
6. In the present case, when the matter was approached by the respondent
herein before the Engineer, he declined and therefore, the matter was
referred to arbitration and the Arbitrators initiated the proceedings. In
that a counter-claim was made. The counter-claim pertained to the issues
which have already been settled in the minutes of meeting of 6th/7th April,
2000. Therefore, the stand taken by the respondent against the counter-
claim was that it is without jurisdiction and it is not arbitrable because
the counter-claim Nos. 1 to 7 have already been settled by the minutes of
the meeting dated 6th/7th April, 2000. The Arbitrators after considering
the counter-claim came to the finding that as per the minutes of meeting
dated 6th/7th April, 2000 the counter-claims have already been settled.
Each of the counter-claim was examined by the arbitrators. The Arbitrators
in their award observed in Para 4.58 that in the Tribunal’s view none of
these alleged Counterclaims was admissible and majority of these claims
stood settled. It was also observed while discussing each of the counter
claim that counter-claim Nos. 2,3,4,5,6,7,8,9 & 10 were already covered by
the minutes of meeting dated 6th/7th April, 2000 and finally in paragraphs
4.60 & 4.61 it was observed as under:
"4.60 As will be seen, the majority of the Counterclaims is said to
be caught by the settlement agreement of the 6th/7th April, 2000
which was the subject of the exchange of correspondence on the 5th
May 2000 and the 10th May 2000 to which reference has already been
made above. On the fact of it the MOM taken in conjunction with the
subsequent correspondence clearly show a binding agreement for good
consideration whereby a number of claims were compromised. Thus,
paragraphs 2,3 and 4 reflect a discussion about critical components
and operational guarantee. Those matters were settled as appears
from paragraph 5.
"so as to avoid any arbitration on either side in order to ensure
supply of critical components by SAG for the forthcoming overhauls.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 6 of 7
Accordingly, various issue (sic) were discussed and agreements were
reached as per the following paragraphs as a package deal."
4.61. What then follows is a series of specific agreements clearly
recorded as such and thereby setling the disputes which then
existed. And by paragraph 15 there was express confirmation by both
parties:
"that there were no other issues to be resolved in first and third
contracts."
7. The Tribunal also held that certain objections were taken with regard to
the agreement not being binding which was disposed of by the Tribunal as it
had no merits because the agreement was voluntarily made between the
parties and it was not under duress or by deception. In paragraph 4.64 of
the Award it was concluded that so far as counter claim Nos.2,3,4,5,6,8,9 &
10 were concerned, they were caught by settlement. So far as counterclaim
No.7 was concerned, it was mere reservation of right and so far as
counterclaim No. 1 was concerned, it was the opinion of the Tribunal that
five purchase orders were confirmed and supplied and therefore, no dispute
could arise. Accordingly, the Tribunal held that in view of settlement of
issues in the minutes of meeting dated 6th/7th April, 2000 it was
unnecessary for the Tribunal to consider any additional defence to the
counterclaim and it was held that they were not admissible and not capable
of being included in that reference to arbitration. Accordingly, this
partial award was passed by the Tribunal. The Tribunal considered all these
counterclaims and recoded the aforesaid finding.
8. Now, the only question that remains to be decided in the present case is
whether against the order of partial award an appeal is maintainable
directly under Section 37 of the Act or not. We have considered the
submissions of learned counsel for the appellant and after going through
the counterclaim and the partial award, we are of opinion that no question
of jurisdiction arises in the matter so as to enable the appellant to file
a direct appeal under Section 37 of the Act before the High Court. As
already mentioned above, an appeal under sub-section (2) of Section 37 only
lies if there is an order passed under Section 16(2) & (3) of the Act.
Section 16(2) & (3) deals with the exercise of jurisdiction. The plea of
jurisdiction was not taken by the appellant. It was taken by the respondent
in order to meet their counterclaim. But it was not in the context of the
fact that the Tribunal had no jurisdiction, it was in the context that this
question of counterclaim was no more open to be decided for the simple
reason that all the issues which had been raised in counterclaim Nos. 1 to
10 had already been settled in the minutes of meeting dated 6th/7th April,
2000 and it was recorded that no other issues to be resolved in 1st and 3rd
contracts. Therefore, we fail to understand how the question of
jurisdiction was involved in the matter. In fact it was in the context of
the fact that the entire counterclaims have already been satisfied and
settled in the meeting that it was concluded that no further issues
remained to be settled. In this context, the counterclaims filed by the
appellant was opposed. If any grievance was there, that should have been by
the respondent and not by the appellant. It is only the finding of fact
recorded by the Tribunal after considering the counterclaim vis-a-vis the
minutes of the meeting dated 6th/7th April, 2000. Therefore, there was no
question of jurisdiction involved in the matter so as to enable the
appellant to approach the High Court directly. The High Court has also
examined this matter and clearly observed in its order in paragraph 9 as
follows:
"Therefore, in the case in hand it is to be seen if the plea raised
by the Siemens AG in regard to the counter-claims of NTPC was a
plea pertaining to lack of jurisdiction of the Arbitral Tribunal or
arbitrability of the said dispute within the meaning of Section
16(2) or Section 16(3) of the Act or it was the plea in regard to
the merits of the counter-claim and its existence/subsistence on
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 7 of 7
the ground that the counter-claims raised by the NTPC stood settled
and did not subsist any longer more particularly in view of the
decisions taken by the parties as reflected in the MoM dated 6th
and 7th April, 2000."
9. Therefore, the question of jurisdiction in the present controversy did
not arise because the counter-claim was opposed by the respondent-SAG as
the same has since been stood settled. In view of the finding of fact
recorded by the Tribunal that all the counter-claims stood covered by the
decisions of the minutes of meeting though it was initially opposed by the
respondent-SAG that it was not arbitrable or the Tribunal could not go into
counter-claim, despite that it examined on the merit of the matter and on
the merits the Tribunal disposed of the counter-claim by giving partial
award. We fail to understand how can the appellant-NTPC can raise the
question of jurisdiction and bring its case under Section 16(2) & (3).
10. Learned counsel for the appellant tried to refer to some of the
decisions of this Court but we do not think those decisions need to be
noted in the present case as the whole question turned on the facts
involved in the present case and we are satisfied that the partial award
can be given and against this partial award the appellant has remedy under
section 34 of the Act and thereafter they could file appeal under Section
37 of the Act. But no direct appeal would lie before the High Court because
no jurisdictional issue was involved. The counter-claim was disposed of on
the basic fact that the counter-claims had been settled by the MoM dated
6th/7th April, 2000. In this view of the matter, we need not refer to the
decisions cited by learned counsel and other written submissions made by
the appellant. We are satisfied that the view taken by the High Court is
correct, appeal was not maintainable under Section 37(2) of the Act before
the High Court and there is no ground to interfere with the order passed by
the High Court. Accordingly, the appeal is dismissed with no order as to
costs.