Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 9
PETITIONER:
KONAPPA RUDRAPPA NADGOUDA
Vs.
RESPONDENT:
VISHWANATH REDDY & ANR.
DATE OF JUDGMENT:
18/07/1968
BENCH:
HIDAYATULLAH, M. (CJ)
BENCH:
HIDAYATULLAH, M. (CJ)
MITTER, G.K.
CITATION:
1969 AIR 447 1969 SCR (1) 395
CITATOR INFO :
AFR 1969 SC 604 (12,14)
D 1981 SC1177 (14,17)
ACT:
Representation of the People Act, 1951, s. 9A-Agreements
between, respondent’s firm and State Government for building
a road and a dispensary-work at first certified as-
completed later certificates cancelled Agreements containing
clauses requiring contractor to repair faulty work-if
contracts subsisting on date of nomination-Respondents’
partnership firm dissolved before nomination without notice
to Government of.
HEADNOTE:
The appellant and the first respondent were candidates for
election in February, 1967 from the Yadagiri constituency
which was won by the first respondent. The appellant
challenged his election by a petition on the ground that he
was a partner in a firm which had two contracts with the
State Government, one for the construction of a road and the
other for the construction of a dispensary building, which
were subsisting on, the day when nominations were filed; he
was therefore disqualified from being a candidate under s.
9A of the Representation of the People Act, 1951 and his
election was void. The appellant also claimed that he was
entitled to be declared elected as the votes cast in favour
of the first respondent must be regarded as thrown away.
From the evidence led before the High Court it was clear
that the first respondent had obtained certificates from
officers of the State Government to the effect that the
contracts were complete but that these certificates were
subsequently cancelled as it was considered that the work
was not completed. After appraising the evidence, the High
Court came to the conclusion that although some of the items
from the two contracts might not have been completed, the
contracts as a whole were substantially performed and,
therefore, there was no bar to the candidature of the first
respondent. It also held that although the agreements
contained clauses for maintenance and repairs over a period
of time after the completion of the work of construction,
the did not have the effect of making them subsisting
contracts. The High Court therefore dismissed the election
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 9
petition.
HELD : On appeal to this Court,
The High Court was in error in holding that the contracts
had been fully performed and s. 9A did not apply. The
appeal must therefore be allowed and the election of the
first respondent declared void. Furthermore the votes caste
in favour of the first respondent must be treated as thrown
away and in the absence of any other contesting candidate,
the appellant declared elected [403 F, 404 B-C]
(i) Taking the fact that some portion of the original
contracts remained to be performed with the fact that under
the contracts the con tractor was required not only to
complete the original work but to repair defects or do
something which he had not properly done, the matter must be
regarded as falling within s. 9A of the Act. In the context
of construction of buildings and roads, it is obvious that
if some part is found defective and has to be done again,
the contract of execution as such is still to be fully
performed. It is possible to describe the action, taken as
one to repair the defect, but in essence it is a, part of
the contract
396
of execution, because no execution can be said to be proper
or complete till it is properly executed. [403 B-D]
(ii) There was no force in the contention that under Art.
299 the ,contract in question had to be signed by the
Secretary to the Government whereas in the present case it
was signed by the Executive Engineer. [403 G]
Chatturbhuj Vithaldas Jasani v. Moreshwar Parashran and
Others, [1954] S.C.R. 817, applied.
(iii) The law requires that a candidate should not have
any interest in any contract with Government and therefore
even a partner in a firm has an interest sufficient to
attract the provisions of s. 9A. The fact that the
partnership itself had been dissolved in the present case
would have no effect upon the relations between the first
respondent and, the Government. [403 H]
The first respondent could not by a private dissolution of
the partnership escape his liability under the contract to
the Government, and there was here no notation, because
notice of the dissolution was not given to Government and
the Government had not accepted the person to whom the
business was transferred in place of the respondent’s firm.
[404 A]
JUDGMENT:
CIVIL APPELLATE JURISDICTION : Civil Appeal No. 1705 of
1967.
Appeal under section 1 1 6 A of the Representation of People
Act, 1951 from the judgment and order dated September 15,
1967 of the Mysore High Court in Election Petition No. 8 of
1967.
M. C. Chagla, S. S. Javali and B. Datta, for the
appellant.
D. Narsaraju, B. S. Patil and R. V. Pillai, for respondent
No. 1.
The Judgment of the Court was delivered by
Hidayatullah, C.J. This is an appeal from the judgment and
order of the High Court of Mysore, September 15, 1967, in an
election matter in which the present appellant was the
election petitioner. The election concerned the Yadagiri
constituency and was held in February 1967 during the last
general elections. To begin with, there were seven
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 9
candidates. Of these five withdrew leaving the seat to be
contested by the appellant and the first respondent here.
The first respondent was returned as the successful
candidate having obtained 4,000 and odd votes in excess of
his rival. On March 30, 1967 the defeated candidate
preferred an election petition which has given rise to the
present appeal. The election petition was dismissed by the
High Court and in this appeal, the election petitioner
claims that the decision of the High Court was erroneous and
that the election of the first respondent was void for
reasons to be stated hereafter.
The first respondent was a partner in a firm known as that
Yadagiri Construction Company, Yadagiri. This firm held
397
several contracts from the Mysore Government. In this
appeal, we are concerned with two contracts only which were
the construction of (1) a road known as "Nalwar Sonthi Road"
in Gulbarga Division for a distance of four miles and (2) a
dispensary building for the Primary Health Centre at
Wadagara. The contention of the, election petitioner was
that these contracts were subsisting on January 20, 1967
when the nominations were filed and the subsistence of the
contracts with the Government rendered the election of the
first respondent void. The election petitioner claimed that
he was entitled to be declared elected after considering
that the votes cast in favour of the 1st respondent as
thrown away. The High Court in its judgment held that the
contracts were not subsisting and that the election was
therefore not affected.
The matter is one of fact but it is necessary, before we
enter into an examination of the facts, to set out the law
relating to disqualification of candidates on this ground.
Under s. 9A of the ’Representation of the People Act, 1951
it is provided as follows
"A person shall be disqualified if, and for so
long as there subsists a contract entered into
by him in course of his trade or business with
the appropriate Government for the supply of
goods to, or for the execution of any works
undertaken by, that Government.
Explanation : For the purpose of this section
where a contract has been fully performed by
the person by whom it has been entered into
with the appropriate Government, the contract
shall be deemed not to subsist by reason only
of the fact that the Government has not
performed its part of the contract either
wholly or in part."
It may be mentioned here that previously the section did not
contain the Explanation. In Chatturbhuj Vithaldas Jasani v.
Moreshwar Parashram and others(1), the existence of the
liability on the part of the Government to pay for a fully
executed contract was held to be a disqualification. It
appears that Parliament thought that since Government moves
slowly and many bills remain outstanding for a long time,
this part of the disability may be removed. The amendment,
therefore, takes away from the ban of the section the
subsistence of one side of the contract, viz. the
performance thereof by Government by paying for the goods
supplied or the work executed. In other respects, the law
remains very much the same as it was when the ruling
referred to above was given. We shall have to refer to
certain observations in the ruling which in our opinion must
be taken into
(1) (1954) S.C.R. 817.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 9
LI 2S.CI/68-11
398
account before reaching the conclusion whether the contract
or contracts continued to subsist on the date on which the
candidate offered himself for election. We shall now
continue our narration of the facts.
As has been stated already, there were two contracts one for
the construction of a road for a distance of four miles and
the other for the construction of a dispensary building.
Two separate agreements have been produced which were
entered into by the Yadagiri Construction Company with the
Government for the execution and performance of these
contracts. It was urged in the High Court by the election
petitioner that both these contracts remained incomplete
and, therefore, they subsisted and that the candidate was
under a disqualification and could not stand for the
election. The contract for the construction of the road,
,entered into by the Yadagiri Construction Company, included
’twelve items which the firm had to complete. They are
conveniently described as items 1 to 7 and 8 to 12. The
case of the election petitioner was that although item 1 to
7 had been completed, items 8 to 12 remained to be
completed. In the Schedule to the contract for the building
of the dispensary, a number of items were included in the
Schedule. Of these, 8 items were found to be incomplete
and, therefore, the same position ensued as in the case of
road. The evidence led in the case consisted of documents
from the Public Works Department and oral testimony ,of the
engineers who- were in charge of these constructions and
others. After appraising the evidence, the High Court came
to the conclusion that although some of the items from these
two ,contracts might not have been completed, still the
contracts as a whole were substantially performed and,
therefore, there was no bar to the candidature of the 1st
respondent. The High Court also held that although these
agreements contained a clause for maintenance and repairs
over a period of time after the completion of the work of
construction, that did not make the contracts to subsist and
therefore, that too was not a disability.
Mr. Chagla in arguing the appeal tries to establish that
both the conclusion of the High Court are erroneous. The
evidence in the case, as is usual, is widely discrepant
between the parties. They both held certificates issued by
the Public Works Department, one set showing that the work
had been completed and a subsequently issued set showing
that something remained to be done and that the contracts
were still subsisting. We shall refer to these documents
now.
The contract in relation to the road was entered into on
December 17, 1962 and is evidenced by Ex. P-10. The
Schedule to the contract showed that the construction had to
be completed according to it. The contract went on to
provide by cl. 20 as follows
399
"........ The contractor is to maintain the
reconstructed portion of the road for a period
of three months after the Executive Engineer
has certified the same to be completed to his
satisfaction".
The Schedule to this contract provided for surfacing of the
road, collection of Shahabad soling stones, collection of
muram for earth work, spreading muram over soling and metal
etc. In addition to the proper construction of the road, it
was the duty of the contractor to supply and fix mile and
hectometer stones and to fix the road boundaries and
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 9
demarcation stones etc. This work represents items 8 to 12.
Those relating to the road proper are items 1-7 to which
also reference has been made earlier.
Now it is agreed on both sides that items 1-7 were duty
completed. The dispute is with regard to items 8-12. Nomi-
nation to the Assembly had to be filed on 20th January, 1967
at the latest. 21st January was fixed for scrutiny of the
nomination papers and the election was to follow in the
month of February. On 18th January, 1967, the first
respondent obtained a certificate (Ex. P-1) that his
contracts had been fully performed. He approached the
Executive Engineer on the 19th. The Executive Engineer was
busy throughout the day. The respondent therefore asked his
Personal Assistant (who incidentally is a gazetted officer
of the rank of an Assistant Engineer) to give him the
necessary certificate. The Personal Assistant telephoned to
the Assistant Engineers in charge and on their statement
that the work had been physically completed, he granted the
certificates to that effect. It appears that the election
petitioner was also busy in his turn. He obtained
cancellation of these certificates from the Executive
Engineer on the following day. The Executive Engineer asked
the Assistant Engineers to state whether the work had been
completed and the Assistant Engineer thereupon gave the
certificate that items 8-12 of the first contract were not
complete. We have so far described the contract dealing
with the road.
The contract for the construction of the dispensary was exe-
cuted on February 23, 1966. The schedule to that contract
contained a description of 27 items which had to be
completed. In addition, there was the requirement that the
entire premises would be cleaned and put in habitable state
and then handed over. Here also the dispute is whether the
entire contract had been completed or not. It is the case
of the election petitioner that 9 items were left incomplete
including the construction of a compound wall 30 ft. long
for the quadrangular open yard, supplying welded mesh for
the front waiting room and to the rear opening, whitewashing
of one room, paint work, floors etc. This also was certi-
fied at first to be completed but later the certificate was
revised
400
and it was stated that the work was not complete. It is
between these two rival certificates and the evidence
relating to them that the matter has to be decided.
In respect of the road, the Assistant Engineer in charge of
the work gave a notice on December 20, 1966 saying that
certain work was not complete. Items 8-12 were, however,
not mentioned there. The High Court was of the opinion that
this omission completely demonstrated that portion of the
work which is now stated to be incomplete must have been
completed. In answer to this, Mr. Chagla has contended that
he had asked for the issue of a Commission in the High Court
for the inspection of the spot (which petition he has
repeated here) and he stated that even today, this part of
the work has not been completed. However we do not go by
such petitions nor are we inclined to issue a Commission
which has been asked for in this Court. We consider the
evidence, such as it is, and we find the correct situation
to be this. P.W. 3, the Assistant Engineer no doubt stated
in his notice that the "balance items" were only three. lie
had really mentioned 4 items, but had struck out item No. 2.
That, however, did not show that no other work remained to
be done. The certificates are there. That in favour of the
completion of the work were given by the Personal Assistant
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 6 of 9
to the Executive Engineer on the day the Executive Engineer
was absent. No doubt, the Personal Assistant worked as the
head of the office in the absence of the Executive Engineer,
but it is on record and duly proved that he had no authority
to issue the completion certificates which he did. The
Personal Assistant explained that he had issued the
certificates because they were urgently required for
election purposes and because the Assistant Engineer under
whose supervision the construction of the road was taking
place had reported completion of the work. The Executive
Engineer, however, verified this again from the Assistant
Engineer and found that items 8-12 remained to be completed.
Mr. Narasaraju complains of the conduct of the Executive
Engineer by saying that he did not visit the spot to see for
himself whether the completion had been made or not. He
states that in Ex. P-11 in which the completion was
reported on 18-1-1967 there is no mention of items 8-12 and
it is different in language from Ex. C-1 in which items 8-
12 are shown not to have been completed. We do not think
that anything turns on that. The Officers of the Public
Works Department have come to the witness box and have
maintained that these items were in fact not completed be-
fore the election took place. We are satisfied that
although the construction of the road was complete the
additional items which are described as "miscellaneous" in
the contract still remained to be completed. What bearing
this will have upon the election of the first respondent is
something which we shall consider after we have analysed the
evidence with regard to the hospital.
401
In respect of the hospital also, the first respondent
obtained ,the certificate from the Personal Assistant to the
Executive Engineer that the work had been completed. This
is Ex. P-1. Here again, the Assistant Engineer was
consulted and the certificate showed that there were
physical completion of the work. Later this certificate was
also contradicted by the issuance of another certificate by
the Executive Engineer that the work remained incomplete.
This information was given by the Executive Engineer to the
Returning Officer by Ex. P. 13 because it was an important
matter connected with the election. Mr. Narasaraju hinted
that some outside influence was at work in the cancellation
of the earlier certificate inasmuch as the Minister for the
Public Works Department was present at Yadagiri and had also
camped at Gulbarga on the following day. He pointed out
that the Chief Engineer and the Executive Engineer were also
present. The insinuation is that this was done under the
pressure of the Minister, because the Congress had been
consistently losing the seat at Yadagiri and it was intended
that the first respondent should be knocked out to ensure
Congress victory. We do not find any evidence which shows
that the Minister took any interest in this matter although
his presence may give rise to some suspicion. We cannot go
on suspicion alone. It is obvious that both sides were
straining every nerve to get some documentary evidence in
their hands to prove, one that the work was incomplete and
the other, that the work was completed. The later
certificates clearly show that certain parts of the work
remained to be completed and they certainly were overlooked
when the first certificate was given. That they were minor
items is not much to the purpose. The contracts as such
were not fully performed. Although we were hesitating
whether to apply the de minimis rule to this case we think
that there are other considerations why we should refrain
from applying that rule. We make our position clear. If
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 7 of 9
the work is completed, it would not mean that the contract
is subsisting, if, say, a glass pane is found broken or a
tower bolt or a drop bolt or a handle has not been fixed
where it should have been. The law is not so strict as all
that and a sensible view of the section will have to be
taken. The right of a person to stand for an election is a
valuable right just as a right of a person to vote was con-
sidered a valuable right in the leading case of. Ashby v.
White(1). But if the contract subsists in such manner that
it cannot be said to have been substantially completed, the
law must take ;Its own course. It is of the essence of the
law of Elections that candidates must be free to perform
their duties without any personal motives being attributed
to them. A contractor who is still holding a contract with
Government is considered disqualified, because he is in a
position after successful election to get concession for
himself in the performance of his contract. That he may not
do so
(1) [1703] 2 Ld. Raym, 938.
402
is not relevant. The possibility being there, the law
regards it necessary to keep him out of the elections
altogether. But as we stated, this will be only where the
contract has not been fully performed, although what is full
performance of a contract or completion, is a matter on
which we do not wish to express a final opinion in this
case, because it depends on the circumstances of each case
and more particularly because there is here another
condition to which we have referred.
In both the contracts, there was a condition that for a
period of three months in one and for a period of one year
in the other, the contractor would make due repairs to all
the defective parts in the execution of the contract. The
question is whether the contract can be said to be
subsisting in view of this clause. Both sides referred us
to Hudson’s Building and Engineering Contracts. In one
passage, Hudson regarded such a clause as in the nature of a
’repair clause. But Hudson was not dealing with the law of
election when he was discussing a clause such as we have in
this case. We have to interpret this clause in the context
of election law. Now the contract must be said to subsist
if a portion of it is required to be performed at any time,
because so long as the contract has not been discharged, by
full performance, it must be taken to, subsist. Mr.
Narasaraju contends that the phrase " contract for the
execution of the work" shows that it is the execution of the
original work which is contemplated and not any condition of
guarantee for repair. In our opinion, this argument,
however, ingenious, is not acceptable because a similar
point arose in the case to which we referred earlier. In
Chatturbhuj Vithaldas Jasani’s(1) case, Bose J. dealt with a
similar point in the following words :
"It was argued that assuming that to be the
case, then there were no longer any contracts
for the " supply of goods" in existence but
only an obligation arising under the guarantee
clause. We are unable to accept such a narrow
construction. This term of the contract,
whatever the parties may have chosen
to call
it, was a term in a contract for the supply of
goods. When a contract consists of a number
of terms and conditions each condition does
not form a separate contract but is an item in
the one contract of which it is a part. The
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 8 of 9
consideration for each condition in a case
like this is the consideration for the
contract taken as a whole. It is not split up
into several considerations apportioned
between each term separately. But quite apart
from that, the obligation, even under this
term, was to supply fresh stocks for these
three depots in exchange for the stocks which
were returned and so eve
(1) [1954] S.C.R. 817.
403
when regarded from that narrow angle it would
be a contract for the supply of goods. It is
true they are replacements but a contract to
replace goods is still one for the supply of
the goods which are sent as replacements."
Applying these observations in the context of construction
of buildings and roads, it is obvious that if some part is
found defective and has to be done again, the contract of
execution as such is still to be fully performed. It is
possible to describe the action taken as one to repair the
defect, but in essence, it -is a part of the contract of
execution, because no execution can be said to be proper or
complete till it is properly executed. Taking the fact that
some portion of the original contracts remained to be
performed with the fact that under the contracts the
contractor was required not only to complete the original
work but to repair defects or re-do something which he had
not properly done, we think this matter must fall within s.
9A of the Representation of the People Act. This is not a
case like the supply of a refrigerator which after giving
service for some time goes out of order and something has to
be done to replace a part which is defective. The analogy
is not quite apposite. Here the building was completed very
recently and the flooring had to be re-done and various
other things were left unfinished and these had to be
completed by the contractor. Similarly in relation to the
road, although the surface was prepared and the road was in
actual use, under the contract, mile and hectometer stones
had to be fixed and certain other stones fixed at curves and
boundaries. This was not done. The two contracts therefore
were not fully performed and under cl. 20 of the agreement,
it was incumbent upon the contractor to complete this part
of his obligation. In our opinion, the High Court was in
error in holding that the contracts had been fully performed
and therefore s. 9A did not apply.
Mr. Narasaraju raises three legal points. The first is that
under Art. 299, the contract had to be signed by the
Secretary to the Government whereas the contract was signed
by the Executive Engineer. This point was also considered
in Jasani’s(1) case and it was held that it did not go to
save the bar of the election law to the candidature. Next
it is argued that the section is applicable to a person
whereas the contract was with a firm and therefore the first
respondent was not barred from standing for the election.
In our opinion, the High Court has taken the right view of
the matter. The law requires that a candidate should not
have any interest in any contract with Government and even a
partner has an interest sufficient to attract the provisions
of s. 9A. Lastly it is argued that the partnership
(1) (1954.) S C.R. 817.
404
itself had been dissolved. That would have no effect upon
the relations between the first respondent and the
Government. The first respondent could not by a private
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 9 of 9
dissolution of the partnership escape his liability under
the contract to the Government, and there was here notation,
because notice of the dissolution was not given to
Government and the Government had not accepted Hampanna to
whom the ’business was transferred in place of the firm. We
view the transfer of the entire contracts to Hampanna with
some suspicion. It appears that on the eve of the election,
the first respondent who wished to contest the seat from
Yadagiri, hurried through his contracts, managed to get a
completion certificate which was not quite accurate,
dissolved the partnership with a view to clear himself from
all connections with the contracts so that he could stand
for the election. In this effort, he has distinctly failed.
We are satisfied that this appeal must succeed and the
appeal is therefore allowed, the election of the first
respondent is declared void. In this view of the matter,
the votes cast in favour of the first respondent must be
treated as thrown away. As there was no other contesting
candidate we declare the appellant (election petitioner)
elected to the seat from the Yadagiri constituency. The
first respondent shall bear the costs of the appellant
throughout.
R.K.P.S.
Appeal allowed.
405