Full Judgment Text
1
Non-Reportable
IN THE SUPREME COURT OF INDIA
| APPELLAT | E JURISD |
|---|---|
CIVIL APPEAL NO. 6568 OF 2016
(Arising out of SLP (C) No.17475/2008)
ELECTRICAL MFG. CO. LTD. … APPELLANT
VERSUS
POWER GRID CORPN. OF INDIA LTD. & ANR … RESPONDENTS
J U D G M E N T
JUDGMENT
Uday Umesh Lalit.J
1. Leave granted.
2. This appeal is directed against the judgment and order dated 04.07.2008
passed by the Division Bench of the High Court of Delhi allowing FAO
(OS) No.196/2006, setting aside the judgment and order dated 10.02.2006
Page 1
2
passed by the Single Judge of the High Court of Delhi in CS(OS) No.1201
of 1993.
3. A Contract for “400 KV Transmission Line Power Package for Rihand –
| r Line” w | as awarde |
|---|
Corporation (hereinafter referred to as “NTPC”) to the appellant herein.
Clause 26 of the Contract titled “Arbitration” was to the following effect:-
“26.0 ARBITRATION
26.1 If any dispute or difference of any kind whatsoever shall
arise between the Owner and the Contractor, arising out
of the Contract for the performance of the Works whether
during the progress of the Works or after its completion
or whether before or after the termination, abandonment
or breach of the Contract, it shall, in the first place, be
referred to and settled by the Engineer, who, within a
period of thirty (30) days after being requested by either
party to do so, shall give written notice of his decision to
the Owner and the Contractor.
26.2 Save as hereinafter provided, such decision in respect of
every matter so referred shall be final and binding upon
the parties until completion of the Works and shall
forthwith be given effect to by the Contractor who shall
proceed with the Works with all due diligence, whether
he or the Owner requires arbitration as hereinafter
provided or not.
JUDGMENT
26.3 If after the Engineer has given written notice of his
decision to the parties, no claim to arbitration has been
communicated to him by either party within thirty (30)
days from the receipt of such notice, the said decision
shall become final and binding on the parties.
26.4 In the event of the Engineer failing to notify his decision
as aforesaid within thirty (30) days after being requested
Page 2
3
| s or diffe | rences in |
|---|
26.6.1 The arbitration shall be conducted by three arbitrators,
one each to be nominated by the Contractor and the
Owner and the third to be named by the President of the
Institution of Engineers, India. If either of the parties
fails to appoint its arbitrator within sixty (60) days after
receipt of a notice from the other party invoking the
Arbitration Clause, the President of the Institution of
Engineers, India, shall have the power at the request of
either of the parties, to appoint the arbitrator. A certified
copy of the said President making such an appointment
shall be furnished to both the parties.
26.6.2 The arbitration shall be conducted in accordance with the
provisions of the Indian Arbitration Act, 1940 or any
statutory modification thereof. The venue of arbitration
shall be New Delhi, India.
JUDGMENT
26.7 The decision of the majority of the arbitrators shall be
final and binding upon the parties. The expenses of the
arbitration shall be paid as may be determined by the
arbitrators. The arbitrators may, from time to time, with
the consent of all the parties enlarge the time for making
the award. In the event of any of the aforesaid arbitrators
dying, neglecting, resigning or being unable to act for
any reason, it will be lawful for the party concerned to
nominate another arbitrator in place of the outgoing
arbitrator.
Page 3
4
26.8 The arbitrator shall have full powers to review and/or
| e said deci | sion. |
|---|
aforegoing provisions shall disqualify him as being called
as a witness or giving evidence before the arbitrators on
any matter whatsoever relevant to the dispute or
difference referred to the arbitrators as aforesaid.”
4. The Contract was completed and the aforesaid line was taken over by NTPC.
In respect of certain claims and issues raised by the appellant, negotiations
took place and thereafter a Committee constituted to consider the claims by
its report dated 03.01.1991 recommended that claim in respect of Rs.10.35
lakhs could be accepted, provided the appellant confirmed that there were no
further claims. The appellant thereafter vide letter dated 18.07.1991
JUDGMENT
addressed to the Executive Director (NR), National Thermal Power
Corporation Ltd., Indira Bhawan, Civil Lines, Allahabad, sought decision in
respect of pending disputes/matters. It was stated that the decision in
respect of issues so raised be conveyed to the appellant within 30 days of the
date of the letter. It appears that by letter dated 14.08.1991 the appellant was
informed that “Engineer” in respect of the Contract in question was General
Manager (TL-NR) and that the letter dated 18.07.1991 was forwarded to
Page 4
5
him. Soon thereafter i.e., on 02.09.1991 the appellant wrote to General
Manager (TL-NR), National Thermal Power Corporation Ltd., Indira
Bhawan, Civil Lines, Allahabad that the aforesaid letter dated 18.07.1991
| o him as “ | Engineer” |
|---|
with Clause 27 of the Contract required notice was deemed to have been
served and that the appellant was waiting for reply in return. However,
nothing was heard within 30 days.
5. On 28.11.1991 NTPC wrote to the appellant that under the directions of the
Government of India, NTPC and National Power Transmission Corporation
Ltd. (“NPTC”, for short) had entered into an agreement on 13.08.1991 for
management of construction, operation and maintenance of Transmission
System and assorted facilities of NTPC, pending completion of legal
formalities for transfer of ownership of the Transmission System to NPTC in
JUDGMENT
due course of time. It was further stated that NPTC would administer the
Contract for and on behalf of NTPC and all further correspondence be
addressed to NPTC.
6. Though letters issued on 18.07.1991 and 02.09.1991 were admittedly
received by NTPC which requested the Engineer to act in terms of the
relevant Clause of the Contract, no action was taken in that behalf. Even
after issuance of letter dated 28.11.1991, for next more than three months
Page 5
6
nothing was done either by NTPC or NPTC. Therefore, by letter dated
20.03.1992 addressed to NTPC the appellant informed that in as much as the
“Engineer” had failed to notify his decision within the period specified as
| ontract, the | appellant |
|---|
the Contract regarding arbitration and nominating Shri J.C. Jain as its
Arbitrator. The appellant requested NTPC to appoint its Arbitrator and give
intimation to the President of the Institution of Engineer (India) in order to
enable appointment of the third Arbitrator so that adjudication proceedings
could be proceeded with. A copy of this letter was forwarded to and received
by NPTC. However, nothing was done for next more than three months.
7. On 7.07.1992, the appellant wrote to the President, Institution of Engineers
(India) drawing his attention to the letter dated 20.03.1992 and stated that
despite being called upon to appoint an Arbitrator on their behalf within the
JUDGMENT
period specified, there was complete failure on the part of NTPC. Since the
prescribed period of 60 days had expired, a request was made vide said letter
to appoint an Arbitrator and that a copy of such appointment be furnished to
both the parties and further steps be taken in the matter. A copy of this letter
was sent to the Chairman and Managing Director of NTPC. On 24.08.1992
a telegram was sent by Sr. Manager (P&C) of NPTC to the President,
Institution of Engineers(India) to the following effect:-
“MESSAGE FORM
Page 6
7
TO
PRESIDENT INSTITUTION OF ENGINEERS(INDIA)
8-GOKHLE ROAD, CALCUTTA-700 020.
| FOR DI<br>O. 01/00 | SPUTES<br>-75/177/-a |
|---|
(P.N.GUPTA)
SR. MANAGER(P&C)
Confirmation copy by post to: SIGNATURE (of person
By REGD. POST authorized to approve)
1. President Institution of NAME:P.N.GUPTA
Engineers(India), 8, Ghokhle DESGN.: SR.MANAGER
Road, Calcutta- 700 029 DEPTT. P&C
2. M/s EMC Stealal Ltd.,
51, Catnal East Road
Calcutta CHECKED FOR DESPATCH
3. Shri V.L. Dua, S M (C)
JUDGMENT
N.D.
4. Shri Gurman Singh,
C.L.D. CC.N.D.
Dt. 24.08.92
th
Regd. Office: Hemkunt Chambers, 10 Floor, 89, Nehru Place,
New Delhi-110 019 (Tel. 646 3390 91-92 Grams:‘ NATGRID’”
8. Since there was no follow up action and nothing was done for more than a
month, the Institution of Engineers (India) on 29.09.1992 appointed Shri
P.P.Agrawal, Chief Consulting Engineer, Water and Power Consultancy
Page 7
8
Services (India) Ltd. as the Second Arbitrator in terms of the Contract. On
the same date Shri Som Gupta, Fellow of Institution of Engineers was
appointed as the Third Arbitrator in the matter. Intimation in that behalf was
| 09.1992 to | the Chai |
|---|
NTPC.
9.
On 08.01.1993, the “National Thermal Power Corporation Ltd, National
Hydro Electric Corporation Ltd. and the North-Eastern Electric Power
Corporation Ltd. (Acquisition and Transfer of Power Transmission
Systems) Ordinance, 1993” (No.10/1993) was promulgated by the President
of India. As per Section 3 of the Ordinance, the Power Transmission System
and the right, title and interest of these three companies in relation to their
power transmission systems stood transferred to and vested in the Central
Government on and with effect from the appointed day. The power
JUDGMENT
transmission system so vested in the Central Government, immediately
thereafter was deemed to have been transferred to and vested in the Power
Grid Corporation India Ltd., i.e. respondent No.1 herein. The appointed
st
day under the Ordinance was 1 April, 1992.
10.On 13.01.1993, first meeting of the Arbitral Tribunal consisting of three
Arbitrators, namely, Shri J.C. Jain, nominated by the appellant, Shri P.P.
Agrawal, nominated as the Second Arbitrator by the President, Institution of
Page 8
9
Engineers (India) and Shri Om Gupta, nominated as the Third Arbitrator by
the President, Institution of Engineers (India) was held. The Arbitral
Tribunal entered upon reference in respect of the dispute in question. It was
| o hold the | next meeti |
|---|
the minutes of this meeting were forwarded to the appellant and the
Chairman and Managing Director, NTPC.
11.On 04.02.1993, a letter was written by respondent No.1 to the appellant that
in terms of Clause 26 of the Contract, arbitration could be invoked only if
there was failure to settle the dispute amicably and this being pre-condition
of the contract, the matter was not mature for arbitration and any step in that
behalf would be in violation of the Contract. A copy of this letter was
marked to the President, Institution of Engineers (India).
12.On 06.02.1993, the appellant filed its Statement of Claim in the sum of
JUDGMENT
Rs.3.98 crores before the Arbitral Tribunal. On 11.02.1993 second meeting
of the Arbitral Tribunal was held. The representative of the appellant
brought the aforesaid Ordinance to the notice of the Arbitral Tribunal and
submitted that in view of the Ordinance, respondent No.1 be made party to
the proceedings. The Statement of Claim along with annexures and copy of
the Contract were taken on record and the appellant was directed to supply
copies of the Statement of Claim to both NTPC and respondent No.1.
Page 9
10
NTPC was directed to submit their reply to the statement of claim by
04.03.1993 and all parties, namely, the appellant, NTPC and respondent
No.1 were requested to attend the next meeting of the Arbitral Tribunal
| 3.1993. C | opies of th |
|---|
forwarded to NTPC as well as respondent No.1. On 23.02.1993, a letter was
written on behalf of NTPC with copies to the Arbitrators and respondent
No.1 that after promulgation of the aforesaid Ordinance, NTPC had nothing
to do in the matter. Copy of the minutes of the meeting dated 11.02.1993 of
the Arbitral Tribunal was forwarded by NTPC to respondent No.1 along
with copy of this letter dated 23.02.1993.
13.As the date fixed for the next meeting, i.e., 25.03.1993 was a public holiday,
a telegram was sent by the appellant to the Arbitrators and to respondent
No.1 that the meeting be adjourned. On 12.03.1993 the Convener Arbitrator
JUDGMENT
sent telegram to the appellant and respondent No.1 confirming the
adjournment of the case to 05.04.1993. On 20.03.1993 another telegram
was sent by the Convener Arbitrator to the appellant and to respondent No.1
that the date of hearing was shifted to 07.04.1993.
14.On 07.04.1993 third meeting of the Arbitral Tribunal was held. Though the
appellant was present, respondent No.1 was absent. It was noted that the
minutes of the second meeting held on 11.02.1993 were sent to NTPC and
Page 10
11
respondent No.1 and were received by them. The relevant portion of the
minutes of the meeting dated 07.04.1993 was as under:
| em. |
|---|
It was however noted with regret that no representative of
M/s NTPC and/or M/s PGCIL turned up for the hearing.
No compliance was made by the aforesaid two
respondents to the directive given to them in the second
meeting regarding filing their replies to the statement of claim
filed by M/s EMC.
During the third meeting Mr. M.K. Kureshi of M/s EMC
requested that despite no response from respondents, the case
should be proceeded with and the arbitrators were requested to
deliver the award within the statutory period of 4 months which
th
expired on 12 May, 1993.
Under the circumstances, it was decided that the next
hearing in the matter will commence from 10.30 a.m. on
th
20.04.1993 and continue on all the days upto 25 April, 1993.
Each day the meeting shall commence from 10.30 a.m. and
continue during the day in an effort to complete the items on the
agenda as specified in the following para.
JUDGMENT
In the meantime respondents are again requested to file
their replies to the statement of claim filed by the claimants and
such other documents that they may like to file before the
th
Arbitrators by 14 April, 1993 giving copies to all the three
arbitrators and the claimants.
M/s EMC are also requested to file such other documents
that they may like to present to the arbitrators by 14.04.1993
giving copies to respondents.
Page 11
12
Following matters will be taken up during the hearings
th th
from 20 April, 1993 upto 25 April, 1993:
| ences by th<br>ments by | e claimant<br>claimants; |
|---|
15.On 09.04.1993, a letter was addressed by one Mr. Sunil Narula, Advocate,
on behalf of respondent No.1 to three Arbitrators and the appellant. It was
stated in the letter as under:-
“…………..Since M/s Electrical Mfg. Co. Ltd. Calcutta,
have raised some disputes in the above-said contract and
instead of settling the matter amicably with our client despite
our client’s repeated requests, have directly invoked the
Arbitration Clause which is not in consonance with the terms
and conditions of the above referred agreement and therefore,
the appointment of the arbitrators in this matter is void ab initio.
M/s Electrical Mfg. Co. Ltd., Calcutta have chosen to neglect
their own written submissions to our client in which they had
agreed to discuss and settle the matter amicably with our client
in accordance with the terms and conditions of the agreement
and this was also a condition precedent to the invocation of
Arbitration Clause 26.1 of the said agreement.
JUDGMENT
Our clients M/s Power Grid Corporation of India Ltd. are
initiating the appropriate legal proceedings in the Hon’ble High
Court of Delhi to challenge the appointment of Shri J.C.Jain,
Shri P.P. Agarwal and Shri Som Gupta, the addressee No. 1,2
and 3, herein as Arbitrators in the above mentioned matter. As
the dispute in this matter is to the effect of legality of the
appointment of all the three learned Arbitrators, you are
requested to abstain from and/or postpone the arbitration
proceedings for a period of 60 days, which shall be just,
reasonable and in the interest of justice and during this period
Page 12
13
our client shall be able to obtain necessary orders from the
Hon’ble High Court of Delhi.”
16.On 20.4.1993, fourth meeting of the Arbitral Tribunal was held at 10.30 a.m.
| ant minutes | of the me |
|---|
“It was noted that the minutes of the third meeting held on
th
7 April, 1993 were sent to M/s NTPC and M/S PGCIL and
have been acknowledged by them. Acknowledgement copy
taken into record.
It was, however, noted that regret that no representative of
M/s NTPC, M/s PGCIL turned up for the hearing.
No compliance was made by the aforesaid respondents to
the directives given to them in the second and third meetings
th
dated 11.02.1993 and 7 April, 1993, respectively.
Despite repeated directives from the Arbitrators
respondents did not appear for the hearing of 20.04.1993 at
10.30 a.m.. In pursuance of the decision taken by the Arbitrators
at the hearing dated 7.04.1993 the Arbitrators proceeded with the
hearing ex-parte.
JUDGMENT
The Arbitrators received on 17.04.1993 at Lucknow a
th
letter dated 9 April, 1993 from one Mr. Sunil Narula, Advocate
claiming to be acting under instructions from PGCIL. The
contents of the letter were considered. Arguments of EMC’s
representative Mr. M.K. Kureshi were also heard. The
Arbitrators decided to proceed with the hearing.
At 11.10 a.m. Mr. Sunil Narula accompanied by an officer
of PCGIL came to the hearing. Since Mr. Narula did not have a
proper letter of authority to appear before the Arbitrators on
behalf of PGCIL in respect of the dispute under arbitration, and
since the directives given by the Arbitrators in the previous
meetings had not been complied with by PGCIL, the Arbitrators
Page 13
14
were unable to entertain any submission of Mr. Narula. The
hearing proceeded further thereafter.
| ng issues w | ere frame |
|---|
1. Whether EMC is entitled to the various claims
mentioned in para 6, Clause (i) to (xvi) and para 7, 8, 9
and 17(d) of the Statement of Claim? If so, to what
effect and extent.
2. Whether EMC is entitled to claim interest mentioned at
the end of Para 17(d)? If so, to what effect and extent.
3. Whether EMC is entitled to say other relief in the
present circumstances? If so, to what effect and extent.
Mr. M.K. Kureshi proceeded to get various documents
produced by him before Arbitrators, proved by Mr. Kalyan
Kumar Ghosh, Manager (Project Monitoring) EMC Ltd., Exhibit
I to XXV as per details enclosed with minutes were got proved.
st
The hearing will continue on Wednesday the 21 April,
1993 at the same place and venue i.e. 89, Sundar Nagar, New
Delhi at 10.30 a.m.”
JUDGMENT
17. The aforesaid minutes noted the appearance of Mr. Sunil Narula at
about 11.10 a.m. and that since he did not have appropriate authority, and
the directives given in the previous meeting were not complied with, no
submissions were entertained by the Arbitrators. Said Mr. Narula within an
hour thereafter sent an Express Telegram to the Convener Arbitrator as
under:-
Page 14
15
“EXPRESS TELEGRAM
Sh. Som Gupta
Convenor Arbitrator Sh Som Gupta
89, Sunder Nagar (Ist Floor) C-8/3, Park Road
New Delhi Lucknow-226 001
Ref.: Arbitration proceedings regarding contract 01/CC/75-77
for 400KV Kanpur-Etah & Kanpur-Kanpur Line.
I appeared on 20.4.93 on behalf of POWERGRID before
the learned arbitrators at 89, Sunder Nagar, New Delhi and
submitted a Vakalatnama duly authorizing me to represent
(POWERGRID CORPORATION before the learned
Arbitrators. The learned arbitrators refused to accept the
Vakalatnama and made a pre-condition to the effect that
POWERGRID should first make the payment of expenses of
the Arbitration Proceedings and also submit a proper authority
letter granting extension of time for making the award by
another 4 months in order to allow the POWERGRID to present
the case before the Learned Arbitrators.
In the above circumstances, the arbitration proceedings
being held by the Learned Arbitrators in the above matter is
illegal, arbitrary and against the principles of natural justice.
JUDGMENT
(SUNIL NARULA)
ADVOCATE, DELHI
20.4.1993”
18. Nobody appeared on behalf of respondent No.1 before the Arbitral
st nd rd
Tribunal on 21 , 22 and 23 April, 1993. The matter having been
concluded by 23.04.1993, the Arbitral Tribunal by its award dated
05.05.1993 found that the appellant had proved its case and was entitled to a
Page 15
16
sum of Rs. 72,69,096/- as against its claim of Rs.3.98 crores. The award
was then forwarded to the Court to be made Rule of the Court in terms of the
provisions of the Arbitration Act, 1940 (hereinafter referred to as the “Act”).
| notice of fi | ling of the |
|---|
all the parties. The application for making the award Rule of the Court was
registered as CS(OS) No.1201 of 1993 and objections under Section 30
and 33 of the Act filed by respondent No.1 were numbered as IA No.8638
of 1993.
19. By his judgment and order dated 10.02.2006, the Single Judge of the
High Court dismissed the objections preferred by respondent No.1 and made
award dated 5.05.1993 awarding a sum of Rs. 72,69,096/- in favour of
appellant, Rule of the Court against respondent No.1. The appellant was
also held entitled to simple interest @ 12 % per annum from the date of the
JUDGMENT
award till the date of the decree and to simple interest @ 9% per annum
from the date of the decree till its realization. The appellant was also held
entitled to costs from respondent No.1 which were quantified at Rs.7,500/-.
During the course of his judgment, the learned Single Judge observed as
under:-
“29.It is not in dispute that notices were duly served upon
respondent No.1. It is also not in dispute that respondent No.2
Page 16
17
| hat ought<br>ent No.2 in | to have b<br>place of r |
|---|
30.The respondent No.2 even appeared subsequently but instead of
participating in the matter was only interested in adjournment.
The Arbitrators, even assuming the arguments of the counsel
appearing before the Arbitrator to be correct, wanted an
extension of time failing which they wanted to proceed with the
Arbitration so that the award could be made within the statutory
period of time. Respondent No.2 was not willing to join in the
extension of time. In such a situation respondent No.2 ought to
have taken immediate legal remedy to at least challenge the
constitution of the Tribunal if so advised. This respondent No.2
did not do but just kept silent over the matter. The allegations
and submissions that the statement of claim was not available
with respondent No.2 or that the record is silent about the same
or as to what transpired on 20.4.1993 are clearly afterthoughts.
It is also to be kept in mind that there was a panel of
Arbitrators. Two Arbitrators were appointed by an independent
agency. There could have been hardly any grievance made by
respondent No.2 about the composition of the Tribunal.
JUDGMENT
31.Respondent No.2 itself had addressed a communication dated
24.8.1992 to the Institute of Engineers and have made
admission themselves in paragraph 2.26 (iii) of the objections
that they had received intimation of the appointment of
Arbitrators on 12.11.1992. The proceedings have also been
sent to respondent No. 2. Respondent No. 2 having not
appeared negligently or willfully, a further opportunity was
given by the Arbitrators to the said respondent on
7.4.1993……….…………….. Respondent No. 2 apparently
was not willing to join the Arbitration proceedings and
negligently kept away and did not even take steps to challenge
such Arbitration proceedings. There cannot be an indefinite
Page 17
18
| 991 that th<br>efore the E | e disputes<br>ngineer or |
|---|
20. The matter was carried further by respondent No.1 by filng FAO(OS)
No.196 of 2006 which appeal came to be allowed by the Division Bench of
the High Court vide its judgment and order dated 4.07.2008. The Division
Bench found that the Arbitral Tribunal had acted in utter haste in rushing
through the arbitration proceedings without affording proper and adequate
opportunity to respondent No.1 in presenting its case. The Division Bench
JUDGMENT
felt that the interest of justice would be best served if the matter was
referred again to a Sole Arbitrator to adjudicate the dispute between the
parties afresh after giving due opportunity to both the parties. Allowing the
appeal and setting aside the order passed by the learned Single Judge and the
award made by the Arbitrator, the matter was referred to the Sole Arbitrator.
During the course of its judgment, the Division Bench of the High Court
observed, inter alia:-
Page 18
19
| ory notice<br>hem. Even | to the app<br>after pro |
|---|
th
“… The appellant had appeared on 9 April, 1993 as well
th
as on 20 April, 1993, but they were not allowed to participate
1
in the proceedings and thereafter within four days i.e. from
21.4.1993 to 25.04.1993 the same were concluded. ……..”
“……….Although, the conduct of both the corporations
i.e., NTPC & NPTC, (appellant) in adopting a very casual and
lackadaisical approach, in not timely taking the actions
including for an appointment of an arbitrator and also for their
non-appearance before the Arbitral Tribunal exhibits their total
insensitivity to the monetary claims of the duly appointed
contractor and their own financial interests yet at the same time
the said contractor i.e., EMC cannot completely absolve itself
to share the blame by not adhering to the said communication
dated 28.11.1992. The respondent EMC was not oblivious of
the said fact of transfer of ownership of the transmission system
by NPTC in favour of the appellant (NPTC), although the same
came to be notified through an ordinance on 8.1.1993.”
JUDGMENT
21. While issuing notice in the petition for special leave to appeal
preferred by the appellant, this Court by its order dated 01.08.2008 stayed
1
This observation is not correct. On 9.4.1993 a letter was addressed by the Advocate.
No hearing was fixed on 9.4.1993.
Page 19
20
the operation of the judgment and order passed by the Division Bench.
Consequently, the matter did not proceed before the Sole Arbitrator named
in the judgment of the Division Bench. The parties having exchanged the
| r. C.Muku | nd, learne |
|---|
appellant and Mr. Parag Tripathi, learned Senior Advocate for respondent
No.1.
22. Having heard the learned Counsel and gone through the record, in our
view, the instant matter raises questions ; a) Whether arbitration was validly
invoked in the matter; b) Whether the appointment of the Arbitrators was in
terms of the relevant Clauses of the Contract; c) Whether respondent No.1
was aware of such invocation and consequential proceedings; and d)
Whether the Arbitral Tribunal was right in refusing to adjourn the
proceedings and proceed with the matter. Our answers to these questions are
JUDGMENT
as under:-
a) In terms of the provisions of Clause 26 (1) of the Contract, the
appellant vide letters dated 18.7.1991 and 02.09.1991 had requested the
“Engineer” to look into the disputes as raised by the appellant. These letters
were admittedly received by NTPC. As stipulated in Clause 26 (1) read with
Clause 26 (4), in the event of the “Engineer” failing to notify his decision
Page 20
21
within 30 days after being requested, the concerned party would be within its
rights to require that the matters in dispute be referred to arbitration. Since
nothing was done with respect to the request made by the appellant within
| f communi | cation dat |
|---|
dated 02.09.1991, the appellant could validly require that the matters in
dispute be referred to arbitration. Even assuming that in terms of letter dated
28.11.1991, it was NPTC who was to be concerned with the matters in
dispute, no appropriate decision was taken even within 30 days of this
communication. In the circumstances, invocation of arbitration by the
appellant vide its letter dated 20.03.1992 was perfectly valid and in terms of
the Contract.
b) A copy of aforesaid letter dated 20.03.1992 addressed to NTPC was
admittedly forwarded to and received by NPTC. Neither of them took
JUDGMENT
appropriate and required steps in the matter within 60 days as contemplated
by Clause 26.6.1 of the Contract. In the circumstances, the step taken by the
appellant to approach Institution of Engineers (India) requesting its President
to appoint the arbitrator in terms of said Clause, vide its letter dated
07.07.1992 was also in keeping with the express terms of the Contract. It is
crucial to note that a telegram was sent on 24.08.1992 on behalf of NPTC
requesting the President, Institution of Engineers (India) to keep the action
Page 21
22
regarding appointment of arbitrator on their behalf in abeyance. It was
stated that a detailed letter was to follow. However nothing was done in the
matter for more than a month and the detailed letter was never sent. In the
| dent, Instit | ution of E |
|---|
right and justified in making the appointment of the Second Arbitrator on
29.09.1992. The appointment of the Third Arbitrator was in any case within
the powers of the President. Thus, appointment of the Second and Third
Arbitrator and constitution of the Tribunal cannot be found fault with.
c) The record is clear that NTPC was aware of the communications
dated 18.07.1991 and 02.09.1991. If under the directions of the Government
of India, NPTC was to take over matters including those related with the
Contract in question, NPTC ought to have been appraised of the issues in
question by NTPC. In any case, the telegram dated 24.08.1992 as stated
JUDGMENT
above, expressly shows complete awareness on part of NPTC and yet no
further steps were taken by NPTC. No detailed letter as stated in the
telegram was ever sent. Further, respondent No.1 which is the successor-in-
interest was made aware of the pendency of proceedings before the Arbitral
Tribunal but chose not to appear and take part. Minutes of first two meetings
of the Arbitral Tribunal were forwarded to and received by respondent
No.1. Even telegrams seeking and granting adjournment of the proceedings
Page 22
23
were sent to respondent No.1. When in the meeting dated 07.04.1993 the
Schedule for days beginning from 20.04.1993 was fixed and copy of the
minutes was sent to respondent No.1, the Advocate for the respondent No.1
| e Arbitrati | on on 09. |
|---|
indicates complete awareness of the proceedings but displays definite idea
having crystallized to initiate appropriate proceedings in the High Court. If
that be so, nothing stopped respondent No.1 from initiating such challenge,
which never happened. The least that it could do in the circumstances was to
be ready to participate in the proceedings and be ready on merits of the
matter. However even on 20.04.1993, i.e. eleven days after the letter was
sent, it was not willing to participate. If it wanted adjournment in the matter,
it ought to have consented to the extension of time as the Arbitral Tribunal
had rightly indicated. The conduct of respondent No.1 as rightly commented
JUDGMENT
by the Division Bench of the High Court, was extremely casual.
d) The Arbitral Tribunal in the present case had entered upon reference and
held its first meeting on 13.01.1993. The mandate of Section 28(1) and (2)
of the Act read with Schedule I, Clause 3 of the Act was that the statutory
period to complete the proceedings and make the award was four months
after entering on the reference. The minutes of the meeting dated 07.04.1993
show awareness that the period would expire on 12.05.1993. The law on the
Page 23
24
point is clear that in such circumstances, the enlargement of time could be
possible if parties to the arbitration agreement consent to such enlargement.
The decision of this Court in Hari Krishna Wattal v . Vaikunth Nath
| .2 is quite | eloquent a |
|---|
are:-
“6. Section 3 of the Arbitration Act, 1940 provides:
“An arbitration agreement, unless a different
intention is expressed therein, shall be deemed to
include the provisions set out in the First Schedule
insofar as they are applicable to the reference.”
7. The First Schedule has 8 clauses describing the implied
conditions of an arbitration agreement. Clause 3 reads as
follows:
“The arbitrators shall make their award
within four months after entering on the reference
or after having been called upon to act by notice in
writing from any party to the arbitration agreement
or within such extended time as the Court may
allow.”
JUDGMENT
10. The question depends upon the true construction of
Section 28. There is no doubt that the Arbitrator is expected to
make his award within four months of his entering on the
reference or on his being called upon to act or within such
extended time as the Court may allow. Reading Clause 3 of the
Schedule along with Section 28 one finds that the power to
2
1973 (2) SCC 510
Page 24
25
| ead-note o<br>w by provi | f Section 2<br>ding that t |
|---|
11. Sub-section (2) of Section 28, however, indicates one
exception to the above rule that the Arbitrator cannot enlarge
the time, and that is when the parties agree to such an
enlargement. The occasion for the Arbitrator to enlarge the time
occurs only after he is called upon to proceed with the
arbitration or he enters upon the reference. Hence, it is clear
that if the parties agree to the enlargement of time after the
Arbitrator has entered on the reference, the Arbitrator has the
power to enlarge it in accordance with the mutual agreement or
consent of the parties. That such a consent must be a post
reference consent, is also clear from Section 28(2) which
renders null and void a provision in the original agreement to
that effect. In a sense where a provision is made in the original
agreement that the Arbitrator may enlarge the time, such a
provision always implies mutual consent for enlargement but
such mutual consent initially expressed in the original
agreement does not save the provision from being void. It is,
therefore, clear that the Arbitrator gets the jurisdiction to
enlarge the time for making the award only in a case where
after entering on the Arbitration the parties to the arbitration
agreement consent to such enlargement of time.”
JUDGMENT
In the circumstances, if the Arbitral Tribunal insisted upon appropriate
consent to extend the time, no fault could be found with. At the same time, if
respondent No.1 was not willing to give such consent, the Arbitral Tribunal
had to go on with the matter and make the award within the statutory period.
Page 25
26
The Division Bench was not right in observing that the Arbitral Tribunal
showed undue haste in the matter.
| side the ju | dgment a |
|---|
Judge. We, therefore, allow this appeal, set aside the judgment and order
passed by the Division Bench of the High Court of Delhi and restore the
judgment and order dated 10.02.2006 passed by the Single Judge of the High
Court of Delhi.
24. This appeal is allowed with no order as to costs.
….....………………………………J.
(Fakkir Mohamed Ibrahim Kalifulla,)
....…………………………………J.
JUDGMENT
(Uday Umesh Lalit)
New Delhi,
July 20, 2016
Page 26