Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 12
CASE NO.:
Appeal (civil) 8360-8361 of 2003
Appeal (civil) 8362-8363 of 2003
PETITIONER:
BSES Limited
RESPONDENT:
M/s Tata Power Co. Ltd. & Ors.
DATE OF JUDGMENT: 17/10/2003
BENCH:
R.C. Lahoti & G.P. Mathur
JUDGMENT:
JUDGMENT
(Arising out of Special Leave Petition (Civil) Nos.10877-10878 of 2003)
(Arising out of SLP(C) Nos.11461-11462 of 2003)
G.P. Mathur, J.
Leave granted.
These appeals, by special leave, have been preferred against the
judgment and order dated 3.6.2003 of Bombay High Court in MERC Appeal
No.1 of 2002 (The Tata Power Company v. BSES Ltd. & Ors.) and MERC
Appeal No.2 of 2002 (BSES Ltd. & Ors. v. The Tata Power Company) which
had been preferred under Section 27 of the Electricity Regulatory
Commissions Act, 1998 (hereinafter called "the Act") challenging the order
dated 7.12.2001 of Maharashtra Electricity Regulatory Commission (for short
’the Commission’).
2. The Tata Power Company Ltd. (for short ’TPC’) is a generating
company within the meaning of Sub-section 4A of Section 2 and a bulk
licensee within the meaning of Sub-section (3) of Section 2 of the Electricity
(Supply) Act, 1948. An agreement was arrived at between Maharashtra State
Electricity Board (for short ’MSEB’) and TPC in or about March, 1985,
whereby TPC was provided 300 MVA standby facility from MSEB and it
was further agreed that in view of the growing requirement of the city of
Bombay, the said standby facility would stand enhanced by a quantum of 50
MVA per year. This standby facility increased to 550 MVA by the year 1990
and payment for the same was to be made irrespective of the fact whether
electricity was drawn or not and if electricity was drawn, actual payment for
the same was to be made over and above the standby charges. In the year
1990, it was agreed that the annual increase in the standby facility would no
longer be operational and henceforth TPC would be entitled to avail of and
pay for the standby facility of only 550 MVA. This agreement was reduced
in writing by way of letter dated 6.7.1990 addressed by MSEB to TPC.
3. The Bombay Suburban Electric Supply Company (for short ’BSES’)
had been granted a distribution licence in the year 1926 which was amended
in the year 1976 to enable it to become a generator of electricity in order to
take care of enhanced demand in the city of Bombay. The licence was further
amended on 30.5.1992 and it contained a clause requiring BSES to execute
suitable interconnection with the system of TPC with the approval of Central
Electricity Authority, New Delhi. A meeting was held between TPC and
BSES on 29.6.1992 regarding technical/commercial aspect of said
interconnection. It was agreed that as TPC already had an arrangement with
MSEB whereby standby facility was provided to it, similar standby facility
may be provided to BSES from the standby capacity reserved by TPC with
MSEB and appropriate sharing of charges could be worked out. The power
plant established by BSES at Dahanu became operational in 1995 and with
effect from August 1995 it started supplying power to the city of Bombay as
per the conditions of the licence.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 12
4. Due to dispute on commercial terms between TPC and BSES the
interconnection was not established for a long time though technical
arrangements had been made. The Maharashtra Government appointed a
Committee under the chairmanship of Principal Secretary, Energy, of which
representatives of MSEB, TPC and BSES were members. After taking into
account the recommendation of the Committee the Government of
Maharashtra on 19.1.1998 directed TPC and BSES to interconnect with one
another and further directed TPC to provide to BSES standby supply of 275
MVA. It was further directed that BSES would pay Rs.3.5 crores per month
to TPC for such standby facility. It was also mentioned in the order that
standby charges were based upon existing tariffs of TPC and BSES and the
same may be reviewed during tariff revision in future. An agreement in that
regard was thereafter executed between TPC and BSES on 31.1.1998 and the
interconnection between the two systems was established on 14.2.1998.
5. The MSEB was charging an amount of Rs.24.75 crores per month from
TPC for providing the standby facility of 550 MVA. On 31.8.1998 MSEB
served a notice on TPC intimating its intention to enhance the charges for this
standby facility from Rs.24.75 crores to Rs.30 crores per month with effect
from 1.12.1998. The TPC then gave a notice dated 30.9.1998 to BSES of its
intention to enhance the charges for the standby facility of 275 MVA provided
by it from Rs.3.5 crores per month to Rs.15.125 crores per month with effect
from 1.12.1998. The notices were given under the third proviso to para 1 of
Sixth Schedule to Electricity (Supply) Act, 1948, which lays down that
licensee shall not enhance the charges for the supply of electricity until after
the expiry of a notice in writing of not less than sixty clear days of its
intention to so enhance the charges. On account of the notice given by TPC
for increasing charges of standby supply of 275 MVA, a dispute arose and a
meeting was convened on 4.3.1999, wherein the Deputy Chief Minister,
Government of Maharashtra and representatives of both the sides were
present. The Deputy Chief Minister though advised both the parties to settle
the issue amicably between themselves without referring to the Government
but at the same time issued certain directions, namely, BSES should share
Rs.9 crores out of Rs.22 crores additional standby charges levied by MSEB
upon TPC for the period 1.12.1998 to 31.3.1999 and the issue regarding
sharing of standby charges for the period 1.4.1999 onwards be referred to a
Committee to be constituted by the State Government. The Government of
Maharashtra thereafter constituted a Committee on 27.5.1999 to study certain
issues including that of standby charges to be paid by BSES to TPC and to
submit a report. Shortly, thereafter a notification was issued on 5.8.1999
constituting the Maharashtra Electricity Regulatory Commission (for short
’the Commission’). The Committee constituted by the Government of
Maharashtra on 27.5.1999 in its meeting held on 2.5.2000 resolved that in
view of constitution of the Commission the question of payment of standby
charges could only be determined by the Commission and accordingly
resolved that the said issue be referred to the Commission for determination.
An intimation in this regard was also sent to the respective parties. However,
the Government of Maharashtra passed an order on 22.3.2000 whereby BSES
was directed to pay standby charges to TPC at the rate of 50 per cent of the
amount of standby charges payable by TPC to MSEB. This was done on the
basis that MSEB was providing standby facility of 550 MVA to TPC and as
TPC was providing standby facility of 275 MVA to BSES, it should pay half
of the said amount. The order further provided that for the period 1.12.1998
to 31.3.1999 BSES should pay Rs.9 crores as standby charges to TPC. BSES
was not satisfied with the aforesaid order of the Government and made
repeated requests for review of the same and lastly on 6.10.2000, it sent a
detailed letter to the Government requesting for reconsideration of the matter.
6. The Government of Maharashtra issued a notification on 27.10.2000
conferring upon the Commission powers to adjudicate upon the disputes and
differences between licensees and utilities and to refer the matter for
arbitration as provided in clause (n) of Sub-section (2) of Section 22 of the
Electricity Regulatory Commissions Act, 1998. The Government wrote a
letter to TPC on 30.10.2000 informing that in view of conferment of power
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 12
under Section 22(2)(n) of the Act upon the Commission the dispute regarding
the standby charges between TPC and BSES has to be submitted to the said
Commission. Thereafter, BSES filed a petition before the Commission for
resolution of dispute regarding the charges for standby facility of 275 MVA
provided to it by TPC and the petition was registered as Case No.7 of 2000.
On 5.12.2000, the Government of Maharashtra informed TPC and BSES that
its earlier order dated 22.3.2000 is being put on hold till the decision of the
Commission is given.
7. After considering the submissions made by the representatives for the
parties, the Commission decided the petition filed by BSES by the order
dated 7.12.2001. The main part of the order was written by two Members of
the Commission who directed as under :
1. BSES shall make payment of Rs.77.06 crores together with
interest thereon at the rate then applicable with effect from
1.4.2000 to TPC within four weeks from the date of the
order for the year 1999-2000. While making payments
due credit shall be made for the amounts paid by them.
2. The TPC shall, in turn, pay the balance amount remaining
out of Rs.363 crores due as standby charges together with
interest due thereon at the rate then applicable to MSEB
for the year 1999-2000 within a week thereafter and close
the matter so far as the year 1999-2000 is concerned.
3. Based on the principles outlined in the order, calculations
for the year 2000-2001 should also be made and payments
effected suitably by BSES and TPC so that the dues to the
MSEB in respect of standby charges are settled for the
past period within three months from the date of the order.
4. For the current financial year 2001-2002 such calculations
will not be possible till the close of the year, whereafter
only the cost and other relevant accounting details will
become available. In terms of the minutes of the order
passed by Bombay High Court on 19.3.2001 in Writ
Petition No.31 of 2001 filed by TPC against BSES, it had
undertaken to deposit Rs.8.25 crores per month with the
Commission on the 15th day of each month until the
Commission disposed of the petition finally and subject to
such adjustments, as may be necessary, as a result thereof.
On the same analogy for the year 2001-2002, BSES should
pay to TPC Rs.10 crores per month (Rs.119.06 crores
divided by 12) as their share of standby charges till such
time the calculations are made and consequential
adjustment is made.
8. The Chairman of the Commission gave a separate and dissenting order
and he arrived at a different amount.
9. Both BSES and TPC were not satisfied with the order passed by the
Commission and accordingly preferred separate appeals before the Bombay
High Court which have been decided by a common judgment and order dated
3.6.2003 which is the subject matter of challenge in the present appeals. The
High Court allowed both the appeals and set aside the orders passed by the
Commission and the proceedings have been remitted back to the Commission
for de novo consideration and decision in accordance with law in the light of
the observations made in the order. It has been directed that during the
pendency of the proceedings before the Commission for the period from
1.7.2003, BSES shall pay to TPC 50 per cent of the standby charges that are
payable by TPC to MSEB for the standby facility provided to it. It has also
been directed that TPC shall pay to MSEB 50 per cent of the standby charges
payable by it to MSEB for standby facility of 550 MVA and shall also
promptly make over to MSEB the amount paid to it by BSES pursuant to the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 12
order. So far as the arrears of standby charges are concerned, it has been
directed that 80 per cent of the said amount shall be paid by BSES to TPC and
the TPC shall immediately pay that amount to MSEB. The remaining 20 per
cent of amount of arrears shall be paid by TPC to MSEB. The question of
interest on the amount of arrears has been left open to be considered by the
Commission.
10. The TPC in its appeal has assailed the order of the High Court in
remitting the matter back to the Commission for de novo consideration. Shri
F.S. Nariman, learned senior counsel for TPC has submitted that the dispute
regarding sharing of standby charges for providing 275 MVA standby facility
to BSES by TPC is not an issue of tariff, but is a dispute relating to sharing or
apportionment of the charges being paid by TPC to MSEB for providing the
former with a standby facility of 550 MVA and, therefore, it does not come
within the purview of the Commission under sub-section (1) of Section 22 of
the Act. It has been urged that under the terms of the licence granted by the
Government to BSES and as amended in 1992, the Government continues to
have the jurisdiction to decide any kind of dispute. The Maharashtra
Government had decided the dispute vide order dated 22.3.2000 and when the
powers under Section 22(2)(n) of the Act were conferred upon the
Commission on 27.10.2000, there was no existing dispute between the parties
regarding the share of the parties as the same had already been decided and
consequently, the Commission had no jurisdiction to entertain the petition
filed by BSES. It has further been contended that the standby facility is
essential for every generator of electricity and since TPC was providing
standby facility of 275 MVA to BSES out of the standby facility of 550 MVA
being provided by MSEB to TPC, then logically BSES should pay half of the
said amount. Lastly, it has been urged that the order passed by the State
Government on 5.12.2000, whereby it was communicated to the parties that
the order of the Government dated 22.3.2000 is being put on hold till the
Commission’s decision is given, would cease to be operative after the decision
of the Commission and consequently the order dated 22.3.2000 would revive
and would bind the parties. It has also been urged that the BSES having not
challenged the order of the State Government dated 22.3.2000 by taking
appropriate proceedings, it was fully bound by it and consequently it should
pay standby charges to TPC on the same rate on which TPC pays standby
charges to MSEB for 550 MVA standby facility to it.
11. Shri Kapil Sibal, learned senior counsel for BSES, has submitted that
the dispute between the parties was essentially relating to determination of
tariff which squarely falls within the jurisdiction of the Commission under
Section 22 of the Act. The Electricity Regulatory Commissions Act had
come into force on 25.4.1998 and Maharashtra Regulatory Commission had
been constituted on 5.8.1999 and after constitution of the Commission, it was
the said body alone which had the jurisdiction to decide the dispute and the
State Government had no authority to pass the order dated 22.3.2000 and,
therefore, said order was wholly without jurisdiction and was not binding
upon BSES. Learned counsel has also submitted that the order dated
5.12.2000 passed by the State Government by which its earlier order dated
22.3.2000 was put on hold till the decision of the Commission, cannot be
interpreted to mean that the said order will stand revived and become
operative after the dispute had been decided by the Commission as it will lead
to a very queer situation. Learned counsel has also urged that in the facts and
circumstances of the case, the order passed by the High Court in so far as it
has remitted the proceedings back to the Commission for de novo
consideration is perfectly justified and calls for no interference.
12. In order to appreciate the contention raised by the learned counsel for
the parties, it is necessary to briefly examine the provisions of the Act. The
rapidly growing demand for energy brought about by economic liberalization
has created enormous problems. To overcome these problems and other
issues facing the power sector, the Government of India organized two
Conferences of Chief Ministers to discuss the whole gamut of issues in the
power sector and the outcome of these meetings was the adoption of the
Common Minimum National Action Plan for Power. Under this action plan
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 12
it was considered necessary to create a Regulatory Commission as a step to
arrest deteriorating condition of the State Electricity Boards and to make plans
for the future developments. The Administrative Staff College, Hyderabad to
whom the Ministry of Power assigned the task of studying the restructuring
needs of the system, strongly recommended the creation of independent
Electricity Commissions, both at the Centre and the States to give effect to the
aforesaid recommendations. The Electricity Regulatory Commissions Bill
was thereafter introduced in the Parliament. The Objects and Reasons of the
Act show that the main function of the State Electricity Regulatory
Commission shall be (i) to determine the tariff for electricity, wholesale, bulk,
grid and retail; (ii) to determine the tariff payable for use of the transmission
facilities; and (iii) to regulate power purchase and procurement process of the
transmission utilities, etc. The changed scenario may give rise to problems
of highly complex and technical nature between the generator, supplier and
distributor of energy, which can be better resolved by technically qualified
people who may constitute the aforesaid Regulatory Commission. They will
have the additional advantage of taking assistance from consultants, experts
and professional persons Therefore, it will be proper to interpret the Act in a
broad manner and not in a narrow or restrictive sense in so far as the
jurisdiction of the Commission is concerned, so that the purpose for which the
Act has been enacted may be achieved.
Chapter V of the Act deals with Powers And Functions of the State
Commission and Sub-section (1) of Section 22 therein reads as under :
Section 22. Functions of State Commission
(1) Subject to the provisions of Chapter III, the State
Commission shall discharge the following functions, namely:-
(a) to determine the tariff for electricity, wholesale, bulk, grid
or retail, as the case may be, in the manner provided in
Section 29;
(b) to determine the tariff payable for the use of the
transmission facilities in the manner provided in Section
29;
(c) to regulate power purchase and procurement process of the
transmission utilities and distribution utilities including the
price at which the power shall be procured from the
generating companies, generating stations or from other
sources for transmission, sale, distribution and supply in
the State;
(d) to promote competition, efficiency and economy in the
activities of the electricity industry to achieve the objects
and purposes of this Act."
Sub-sections (1) and (2) of Section 29 read as under :
Section 29 Determination of tariff by State Commission
(1) Notwithstanding anything contained in any other law, the
tariff for intra-State transmission of electricity and the tariff for
supply of electricity, grid, wholesale, bulk or retail, as the case
may be, in a State (hereinafter referred to as the tariff), shall be
subject to the provisions of this Act and the tariff shall be
determined by the State Commission of that State in accordance
with the provisions of this Act.
[Provided that in State or Union territories where Joint Electricity
Regulatory Commission has been constituted, such Joint
Electricity Regulatory Commission shall determine different
tariff for each of the participating States or Union territories.]
(2) The State Commission shall determine by regulations the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 6 of 12
terms and conditions for the fixation to tariff, and in doing so,
shall be guided by the following, namely:-
(a) the principles and their applications provided in sections
46, 57 and 57A of the Electricity (Supply) Act, 1948 (54 of
1948) and the Sixth Schedule thereto;
(b) in the case of the Board or its successor entities, the
principles under section 59 of the Electricity (Supply) Act,
1948 (54 of 1948);
(c) that the tariff progressively reflects the cost of supply of
electricity at an adequate and improving level of
efficiency;
(d) the factors which would encourage efficiency, economical
use of the resources, good performance, optimum
investments, and other matters which the State
Commission considers appropriate for the purpose of this
Act;
(e) the interests of the consumers are safeguarded and at the
same time, the consumers pay for the use of electricity in a
reasonable manner based on the average cost of supply of
energy;
(f) the electricity generation, transmission, distribution and
supply are conducted on commercial principles;
(g) national power plans formulated by the Central
Government.
13. Sub-section (2) of Section 22 empowers the State Government to confer
by notification in the Official Gazette various functions upon the State
Commission which are enumerated from clauses (a) to (p) in the said sub-
section. One of the function which can be conferred under clause (n) is to
adjudicate upon the dispute and differences between the licensees and utilities
and to refer the matter for arbitration.
14. Section 58 of the Act empowers the State Commission to make
Regulations consistent with the Act and the Rules made thereunder to carry
out the purposes of the Act. Clause (d) of Sub-section (2) of this Section lays
down that Regulation may provide the manner in which charges for energy
may be determined under Sub-section (2) of Section 29.
15. Maharashtra Electricity Regulatory Commission ( Conduct of Business)
Regulations, 1999 framed under the aforesaid provision also have a bearing on
the controversy in dispute and Regulations 72, 73, 78, 79, 80, 82 and 83
which are relevant are being reproduced below :
72. (1) No generating Company, except that which has
entered into or otherwise has a composite scheme for
generation and sale of electricity in more than one State,
shall charge their customers any tariff for supply of
electricity without the general or specific approval of
such tariff by the Commission.
(2) No utility shall fix any tariff for intra-state
transmission, distribution or supply of electricity and
terms and conditions for the supply of electricity, without
the general or specific approval of the Commission:
Provided that the existing tariff being charged by
generating companies shall continue to be charged after
the date of effect of these regulations for such period as
may be specified by a notification, without prejudice to
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 7 of 12
the powers of the Commission to take up any matter
relating to tariff falling within the scope of Section 22 of
the Act.
73. Any generating company proposing to enter into
any agreement for supply of electricity between the
generating company and any buying party shall get the
approval of the Commission for the tariff before entering
into such contracts.
78. Utilities, who are required to get their tariff
approved by the Commission, shall evolve tariff
proposals based on the terms and conditions as may be
notified by the Commission and shall submit the same for
approval, in accordance with the procedure prescribed by
the Commission.
79. All petitions for approval of tariff (generation,
transmission, distribution and supply) and terms and
conditions of supply shall be made strictly in accordance
with regulations and procedures as may be prescribed by
the Commission and shall also be in conformity with the
requirements relating to petitions as prescribed in
Chapter II of these Regulations.
80. The Commission may approve the proposed tariff
on such stipulations as may be considered appropriate
and as may be specified in the Order.
82. The utilities concerned shall publish the tariff as
approved by the Commission in the manner as may be
prescribed. The tariff so published shall be in force from
the date specified in the said publication not being earlier
than the date of such publication and shall be in force
until any amendment is approved by the Commission and
published.
83. Any utility found to be charging a tariff different
from the one approved by the Commission shall be
deemed to have not complied with the directions of the
Commission and shall be liable to penalties under
Section 45 of the Act, without prejudice to any other
penalty to which it may be liable under any other Act.
Any excess charge of tariff by any utility in any year
shall be dealt with as per the directions of the
Commission.
16. The word "tariff" has not been defined in the Act. "Tariff" is a cartel
of commerce and normally it is a book of rates. It will mean a schedule of
standard prices or charges provided to the category or categories of customers
specified in the tariff. Sub-section (1) of Section 22 clearly lays down that
the State Commission shall determine the tariff for electricity (wholesale,
bulk, grid or retail) and also for use of transmission facilities. It has also the
power to regulate power purchase of the distribution utilities including the
price at which the power shall be procured from the generating companies for
transmission, sale, distribution and supply in the State. ’Utility’ has been
defined in Section 2(l) of the Act and it means any person or entity engaged in
the generation, transmission, sale, distribution or supply, as the case may be,
of energy. Section 29 lays down that the tariff for intra-State transmission of
electricity and tariff for supply of electricity, wholesale, bulk or retail in a
State shall be subject to the provisions of the Act and the tariff shall be
determined by the State Commission. Sub-section (2) of Section 29 shows
that terms and conditions for fixation of tariff shall be determined by
Regulations and while doing so, the Commission shall be guided by the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 8 of 12
factors enumerated in clauses (a) to (g) thereof. The Regulations referred to
earlier show that generating companies and utilities have to first approach the
Commission for approval of their tariff whether for generation, transmission,
distribution or supply and also for terms and conditions of supply. They can
charge from their customers only such tariff which has been approved by the
Commission. Charging of a tariff which has not been approved by the
Commission is an offence which is punishable under Section 45 of the Act.
The provisions of the Act and Regulations show that the Commission has the
exclusive power to determine the tariff. The tariff approved by the
Commission is final and binding and it is not permissible for the licensee,
utility or any one else to charge a different tariff.
17. There is a sound logic for conferment of such a power on the Electricity
Regulatory Commission. Hitherto the supply of electricity was being made
by only one body, namely, State Electricity Boards which being an
instrumentality of the State and functioning under the control of the State
Government were not likely to enhance the tariff in an exorbitant or arbitrary
manner. In fact, Electricity Boards of many States in the country were
running on huge losses. The Electricity Regulatory Commissions Act, 1998
has been enacted to enhance the generation of electricity and improve
efficiency by bringing in private operators. If a licensee (who may be private
operator) after getting the licence for supply of electricity in a particular area
increases the tariff arbitrarily, the consumers will have no option but to pay
the same. In order to guard against such an eventuality, provision has been
made that while granting a licence conditions may be imposed and further no
tariff can be implemented unless the same has been approved by the
Commission.
18. Electricity is not a commodity which may be stored or kept in reserve.
It has to be continuously generated and it is so continuously generated
electricity which is made available to consumers. Any generator of
electricity has to have some alternate arrangement to fall back upon in the
event of its generating machinery coming to a halt. The standby arrangement
for 550 MVA made by TPC was for the purpose that in the event its
generation fell short for any reason, it will be able to immediately draw the
aforesaid quantity of power from MSEB. Similarly, the arrangement entered
into by BSES with TPC ensured the former of immediate availability of 275
MVA power in the event of any breakdown or stoppage of generation in its
Dahanu generation facility. Heavy investment is required for generation of
power. For this kind of a guarantee and availability of power, TPC had to
pay charges for the same to MSEB. This payment was in addition to the
charges or price which the TPC had to pay to MSEB for the actual drawal of
electrical energy. The same is the case with BSES qua TPC. The charges
paid for this kind of an arrangement whereby a fixed quantity of electrical
energy was guaranteed to TPC and BSES at their desire, is bound to constitute
a component of the price which they (BSES and TPC) would be charging
from their consumers towards the cost of the electrical energy actually
consumed by them. The determination or quantification of the amount which
is payable for this kind of standby arrangement made in favour of TPC and
BSES would in reality mean determination of the price or charges for
wholesale or bulk supply of electricity. It will, therefore, clearly fall within
the expression "determine the tariff for electricity, wholesale, bulk, grid or
retail " as used in sub-clause (a) of Sub-section (1) of Section 22 and also in
the expression "regulate power purchase \005.. including the price at which
the power shall be procured from the generating companies\005\005." as used in
sub-clause (c) of sub-section (1) of Section 22. Therefore, the determination
or quantification of the amount which BSES has to pay to TPC falls within
the jurisdiction of the State Commission under Section 22 of the Act. This
legal position is also reflected by Section 29 of the Act which confers an
overriding power and clearly lays down that notwithstanding anything
contained in any other law the tariff for supply of electricity, wholesale, bulk
or retail shall be subject to the provisions of the Act and shall be determined
by the State Commission. This clearly ousts the jurisdiction of any other
authority to determine the tariff. It may be noted here that the Act came into
force on 25.4.1998 and Maharashtra Electricity Regulatory Commission was
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 9 of 12
formed on 5.8.1999. Therefore, it is not possible to accept the contention of
Shri Nariman that the State Government had the authority or jurisdiction on
22.3.2000 to determine or quantify the charges which BSES had to pay to
TPC under the terms of the license granted to the former as this was
subsequent to the formation of the Maharashtra Electricity Regulatory
Commission.
19. Shri Nariman has submitted that TPC gave a notice on 30.9.1998 of
their intention to enhance the charges of standby facility provided to BSES
from Rs.3.5 crores to Rs.15.125 crores per month and this notice having been
given under Sixth Schedule (paragraph 1, 3rd proviso) of the Electricity
(Supply) Act, 1948, the enhanced charges became effective and operative
after expiry of 60 days of notice i.e. with effect from 1.2.1998. The
submission is that by operation of law the charges for standby facility stood
revised and enhanced with effect from 1.12.1998. In our opinion, the
contention raised has no substance. The legal position has undergone a
complete change with the enforcement of the Electricity Regulatory
Commissions Act, 1998. In view of Section 29 of the Act, the tariff for intra-
State transmission of electricity and tariff for supply of electricity in
wholesale, bulk or retail has to be determined by the Electricity Regulatory
Commission of the State and a licensee cannot by its unilateral action enhance
the charges. The provisions of the Act have an overriding effect by virtue of
Section 52 of the Act and, therefore, any provisions of Electricity (Supply)
Act, 1948, which are inconsistent with the Act would cease to apply and
consequently the provisions of Sixth Schedule of the said Act can have no
application now. The Sixth Schedule has been made by virtue of Section 57
and 57A of the Electricity (Supply) Act, 1948 and Section 57A contemplates
constitution of a Rating Committee by the State Government to examine
licensee’s charges for the supply of electricity. Section 29 (6) of the Act
specifically lays down that notwithstanding anything contained in Section
57A and 57B of the Electricity (Supply) Act, 1948, no Rating Committee shall
be constituted after the date of the commencement of the Act. The effect of
Section 29 and the Regulations framed thereunder is that it is no longer open
to a licensee or utility to unilaterally increase the tariff. The tariff can be
enhanced only after approval of the Commission and charging of an enhanced
tariff which has not been approved by the Commission will amount to
commission of an offence. Therefore, the notice to enhance the charges
given by TPC, which was subsequent to the enforcement of the Act, can have
no legal effect.
20. Shri Nariman has also submitted that even assuming that the standby
charges are a matter relating to tariff as the same are passed on to the
consumers, but the sharing of standby charges between TPC and BSES is not
a matter relating to determination of tariff and, therefore, the Commission can
have no jurisdiction to enter into such an exercise under Section 22 of the Act.
The submission proceeds on an assumption that the dispute relates to sharing
of standby charges. In fact, the whole case of BSES is that they are under no
obligation to share the charges which are being paid by TPC to MSEB for
providing them with standby facility. It may be noted that the standby
facility of 300 MVA was provided to TPC in the year 1985 which gradually
rose to 550 MVA in the year 1990. The licence of BSES was amended in
1992 whereunder for the first time it was provided that they should interlink
with the system of TPC and ultimately their systems were interlinked on
14.2.1998 in pursuance of the order passed by the Government of Maharashtra
on 19.1.1998. The question of payment of standby charges by BSES to TPC
has, therefore, arisen for the first time in 1998 which is almost 13 years after
TPC started paying standby charges to MSEB. In substance, the dispute is
what should be paid by BSES to TPC for the standby facility provided by it.
The strict and narrow interpretation sought to be placed by the learned counsel
so as to oust the jurisdiction of the Commission cannot be accepted as it will
defeat the very object of enacting the Electricity Regulatory Commissions
Act.
21. It may be mentioned here that both TPC and MSEB always treated the
charges for standby facility as a matter relating to tariff. TPC gave a notice to
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 10 of 12
Government of Maharashtra and MSEB on 30.7.1996 for revision of tariff,
where they themselves described the enhancement of demand charges made
by MSEB for standby facility as "revision of tariff". The charges for standby
facility given by them to BSES were also described as "tariff". MSEB gave a
notice to TPC on 31.8.1998 where the demand charges for 550 MVA were
described as "tariff for bulk supply". Again the notice given by TPC on
30.8.1998 of their intention to increase the charges for standby facility given
to BSES from Rs.3.5 crores to Rs.15.125 crores was described by them as
"revision of tariffs". In the correspondence exchanged amongst TPC, MSEB
and BSES the charges for standby facility have been described as a matter
relating to "tariff". TPC filed a petition before the Commission on
18.10.1999 regarding their dispute of standby charges with BSES and the
subject of application/petition was described as "Revision in Tariff". The
relevant part thereof is being extracted below :
"\005\005..We are advised that the matter be submitted to
Maharashtra Electricity Regulatory Commission (MERC) since
the tariff and inter-connected issue of quantum of standby and
charges is now to be determined by the MERC. We are
accordingly, referring this matter to you by submitting a copy
of the notice of Tariff Revision.
The 60 days Notice of tariff revision commences from 1st
October 1999 and ends on 30th November, 1999. The new tariff
is applicable only for 4 months in the current financial year, i.e.
from 1st December 1999 to 30th March 2000. Hence, is the
urgency to obtain a timely decision to ensure that the
Companies earn reasonable return for the current year.
The tariff has been formulated after considering available date
on necessary expenses listed in the Sixth Schedule to earn
Reasonable Return by the Licensee. A major item of this
expenditure pertains to the quantum of standby required by
TEC and the connected charges payable to MSEB. The issue of
standby charges is vitally inter-connected with the tariff
revision process. Hence, making such realistic assumptions as
possible, the proposal for tariff revision has been worked out."
22. The contention of Shri Nariman that in view of the language used in the
order dated 5.12.2000, the Government’s earlier order dated 22.3.2000 stood
revived after the decision of the Commission, has hardly any merit. If such a
contention is accepted, it would lead to queer results as after the decision of
the Commission two conflicting and contrary orders viz., the order of the
State Government dated 22.3.2000 and the order of the Commission would
come into force. This can never be the intention of the State Government.
The effect of the order dated 5.12.2000 was that the earlier order dated
22.3.2000 would no longer be operative and the decision of the Commission
would govern the situation. Even otherwise as discussed earlier, after the
enforcement of the Act it is the Commission which has the jurisdiction to
decide the controversy and not the State Government.
23. Several reasons have been given by the High Court for remitting the
matter to the Commission for a de novo consideration. The Commission
devised a formula for determination of the charges for standby facility which
was to be paid by BSES to TPC. Both the sides complained before the High
Court that before adopting the formula they were not given an opportunity to
place their point of view before the Commission for arriving at a just formula
and they were not informed about the exact nature of the formula which was
being adopted. The order of the Commission shows that for working out the
formula it had appointed consultants. Two members of the Commission had
several meetings with the consultants and thereafter the formula was worked
out. But the Chairman of the Commission was not present in these meetings.
In his dissenting order the Chairman has recorded as under :
Para 60. I have had the opportunity to peruse in detail the draft of
an order approved and circulated by my colleagues in the
Commission, and I am appending a separate dissenting
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 11 of 12
note, in view of my disagreement with them in regard to
their calculations.
Para 63. As is reflected in paragraph 50 of the order of my
colleagues, the order itself is based on the report of the
Consultants and the calculations shown in their report.
In this behalf, I understand that my colleagues have had
several meetings with the consultants and it is on the
basis of the working that has been provided by my
colleagues that the report has been compiled.
Para 64. I am afraid that I was not informed of any of the
meetings that my colleagues had with the Consultants,
nor was I advised of any minutes of the said meetings till
the draft order was circulated. In the circumstances,
since the BSES’ share that was purported to have been
communicated by the Commission, it cannot be deemed
to be or considered to be a communication made by the
Commission, unless the communication was considered
by all the Members of the Commission. It would
tantamount to only two of the Members taking upon
themselves the liberty to communicate the same."
24. The facts mentioned above clearly show that the procedure adopted by
the Commission was not fair and proper inasmuch as the Chairman did not
participate in the meetings which other two members had with the
Consultants, whereunder a formula was devised. Under Regulation 21, the
quorum for proceedings before the Commission shall be three. In these
circumstances, the High Court was perfectly justified in remitting the matter
to the Commission for de novo consideration and no exception can be taken to
such a course of action.
25. BSES is aggrieved only against the interim arrangement made by the
High Court, whereby it has been directed to pay 50 per cent of the standby
charges that are payable by TPC to MSEB for its standby facility of 550
MVA. Shri Kapil Sibal, learned senior counsel for BSES, has submitted that
the State Government had, on the basis of the recommendation made by the
Committee, passed an order on 19.1.1998 directing BSES to pay Rs.3.5 crores
per month to TPC when the liability of TPC to MSEB was Rs.24.75 crores per
month. This shows that the State Government did not apportion the liability
of BSES as half of that of TPC. He has also submitted that TPC sells 35 per
cent of the power generated by it to BSES and consequently a portion of this
burden of Rs.24,75 crores which TPC is liable to pay to MSEB is passed on
by it to the consumers of BSES. Therefore, BSES cannot be saddled with
liability to pay half of the amount only on the ground that it has been provided
with a standby facility of 275 MVA which is half of the standby facility
provided by MSEB to TPC. Learned counsel has also submitted that at
best there can be some kind of a sharing on the amount which TPC has to pay
to MSEB over and above Rs.24.75 crores but up to the extent of the aforesaid
amount the liability of BSES cannot exceed Rs.3.5 crores. Shri Sibal has also
assailed the order of the High Court on the ground that while making the
interim arrangement for equal sharing of standby charges, reliance has been
placed on the order of the State Government dated 22.3.2000, though the High
Court itself has, in the earlier part of the judgment, held the said order to be
without jurisdiction. Shri Chidambaram, learned senior counsel appearing for
TPC, has, on the other hand, submitted that the order passed by the State
Government on 19.1.1998, whereby BSES was directed to pay Rs.3.5 crores
out of the liability of Rs.24.75 crores of TPC towards MSEB, was only a pro
tem arrangement, as the order itself mentioned that this was subject to revision
in tariff. Therefore, the said order has no legal sanctity and cannot bind TPC
in any manner. He has also submitted that with effect from 1.4.1999 TPC has
only paid half of the standby charges to MSEB and, therefore, the burden of
the entire amount has not been passed on to the consumers. Shri Altaf
Ahmad, Addl. Solicitor General, appearing for MSEB has submitted that the
TPC owes a huge amount to MSEB and the interim arrangement made by the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 12 of 12
High Court should not be changed or altered in a manner which may
prejudicially affect the interest of MSEB.
26. An interim arrangement is normally made on a prima facie
consideration of the matter and on broad principles without examining the
matter in depth. The matter has been remitted to the Commission by the High
Court by the judgment and order dated 3.6.2003 and a period of nearly three
and a half months has already elapsed. Regulation 101 of the Central
Electricity Regulatory Commission provides that the Commission may
normally dispose of the petitions finally within six months of admission. The
State Commissions are also expected to follow this time limit for disposal of
petitions. Since the order made by the High Court is only by way of interim
arrangement and the Commission is expected to decide the disputes finally
within a short period, we do not consider it proper to interfere with the order
made by the High Court in this regard. After the decision of the Commission,
the equities can be adjusted and the excess amount paid by any party can be
refunded to it along with appropriate interest or can be adjusted in future bills.
27. The Appeals are accordingly dismissed with costs. The Maharashtra
Electricity Regulatory Commission is directed to decide the dispute
expeditiously, preferably within three months of presentation of a certified
copy of this order before it. While passing the final order, the Commission
will also make a direction regarding the liability of the parties keeping in view
the deposits made by them as a result of the interim arrangement made by the
High Court.