Full Judgment Text
Reportable
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO. 4424 OF 2014
(Arising out of S.L.P. (C) No. 20558 of 2013
| ... Ap | |
|---|---|
| orporation Limited and another<br>Versus<br>/s. Deepak Cables (India) Ltd. .<br>With<br>CIVIL APPEAL NO. 4425 OF 2014<br>(Arising out of S.L.P. (C) No. 29008 of<br>With<br>CIVIL APPEAL NO. 4426 OF 2014<br>(Arising out of S.L.P. (C) No. 29009 of<br>With |
CIVIL APPEAL NO. 4427 OF 2014
(Arising out of S.L.P. (C) No. 29010 of 2013)
JUDGMENT
With
CIVIL APPEAL NO. 4428 OF 2014
(Arising out of S.L.P. (C) No. 29011 of 2013)
With
CIVIL APPEAL NO. 4429 OF 2014
(Arising out of S.L.P. (C) No. 29012 of 2013)
With
Page 1
2
CIVIL APPEAL NO. 4430 OF 2014
(Arising out of S.L.P. (C) No. 29013 of 2013)
With
CIVIL APPEAL NO. 4431 OF 2014
(Arising out of S.L.P. (C) No. 29014 of 2013)
J U D G M E N T
Dipak Misra, J.
Leave granted in all the special leave petitions.
2. The controversy involved in these appeals, preferred
by special leave, being similar, they were heard
together and are disposed of by a common judgment.
JUDGMENT
For the sake of convenience, we shall state the facts
from Civil Appeal arising out of Special Leave Petition
29011 of 2013.
3. The appellant No. 1 is a company wholly owned by
the Government of Karnataka and, being a State
transmission utility, is a deemed licencee in the State.
Page 2
3
It invited tenders for establishing 2x8 MVA, 66/11
Sub-stations at Tavarekere in Channagiri Taluk,
Davanagere District, which included the supply
materials, erection and civil works on partial turnkey
basis. The respondent-company participated in the
bid and it was successful in the tender and,
accordingly, a letter of intent was sent to it. After
taking recourse to certain procedural aspects, a
contract was entered into between the appellant-
company and the respondent. During the
performance of the contract, the respondent raised a
claim before the engineer as per clause 48 of the
general conditions of the contract and called upon the
engineer to settle certain disputes arising in
JUDGMENT
connection with the contract. As the concerned
engineer did not do anything within the prescribed
period of thirty days as provided under clause 48.2,
the respondent filed CMP No. 62 of 2011 under
Section 11(5) and (6) of the Arbitration and
Conciliation Act, 1996 (for brevity “the Act”) before
Page 3
4
the High Court of Karnataka at Bangalore for
appointment of an arbitrator.
4. The said application was resisted by the present
appellants on the singular ground that clause 48 does
not provide for arbitration and the same, under no
circumstances, could be construed as an arbitration
clause. To substantiate the said submission, reliance
was placed on clause 4.1 of the agreement. It was
put forth that as there is no arbitration clause, no
arbitrator could be appointed. The designated Judge
of the Chief Justice placed reliance on the proceedings
in W.P. No. 28710/09 (M/s. Subhash Projects &
Marketing Limited v. Karnataka Power Transmission
Corporation Limited) disposed of on 10.6.2010
JUDGMENT
wherein the appellant-company, being a State owned
Corporation, had not disputed clause 48.2 as an
arbitration clause and, on that foundation, opined that
it was precluded from denying the same in the case
under consideration. The learned designated Judge
interpreted clauses 48 and 4.1 of the agreement and
came to hold that a plain reading of clause 48 would
Page 4
5
indicate that it partakes the character of an
arbitration clause and, accordingly, appointed a sole
arbitrator to adjudicate the matters in dispute.
5. We have heard Mr. K.V. Vishvanathan, learned senior
counsel appearing for the appellants, and Mr.
Dushyant Dave and Mr. Shyam Divan, learned senior
counsel appearing for the respondents.
6. Mr. Vishvanathan, learned senior counsel appearing
for the appellants, assailing the impugned order, has
submitted that clause 48 of the agreement cannot be
remotely construed as an arbitration clause and
hence, the designated Judge could not have invoked
the power under Section 11(5) & (6) of the Act for
appointment of an arbitrator. It is urged by him that
JUDGMENT
an order passed in a writ petition, which was
instituted in a different context, could not have been
placed reliance upon for construing the said clause as
an arbitration clause. It is submitted by him that in
the absence of an express intention for referring the
matter to an arbitrator, it cannot be so inferred from
such a clause and, more so, when there is a specific
Page 5
6
clause, i.e., clause 4 in the agreement which provides
for settlement of disputes that stipulates that all the
references and disputes arising out of the agreement
or touching the subject-matter of the agreement shall
be decided by a competent court at Bangalore. To
bolster his contentions, he has commended us to the
decisions rendered in M.K. Shah Engineers &
1
Contractors v. State of M.P. , Wellington
2
Associates Ltd. v. Kirit Mehta and Jagdish
3
Chander v. Ramesh Chander and others .
7. Mr. Dushyant Dave and Mr. Shyam Divan, learned
senior counsel appearing for the respondents in all
the appeals, in oppugnation, have submitted that
when clause 48 is read as a whole, it is clear as
JUDGMENT
crystal that the intention of the parties is to get the
matter referred to an arbitrator and clause 4.1 only
determines the place of territorial jurisdiction and has
nothing to do with any stipulation for arbitration. It
has been strenuously urged that clause 48 has to be
interpreted on the touchstone of the language
1
(1999) 2 SCC 594
2
(2000) 4 SCC 272
3
(2007) 5 SCC 719
Page 6
7
employed in Section 7 of the Act and when it is
scrutinized on that anvil, there remains no trace of
doubt that clause 48 has all the attributes and
characteristics of an arbitration agreement. Learned
senior counsel have placed reliance on Smt.
Rukmanibai Gupta v. Collector, Jabalpur and
4
others and Punjab State and others v. Dina
5
Nath .
8. Before we advert to the rival submissions advanced at
the Bar, we think it appropriate to refer to Section 7 of
the Act and what it conveys and, thereafter, refer to
few authorities to understand what constitutes an
arbitration clause in an agreement entered into
between two parties. Section 7 of the Act reads as
JUDGMENT
follows:
“7. Arbitration agreement. – (1) In this Part,
“arbitration agreement” means an agreement by
the parties to submit to arbitration all or certain
disputes which have arisen or which may arise
between them in respect of a defined legal
relationship, whether contractual or not.
(2) An arbitration agreement may be in the
form of an arbitration clause in a contract
or in the form of a separate agreement.
4
(1980) 4 SCC 556
5
(2007) 5 SCC 28
Page 7
8
(3) An arbitration agreement shall be in
writing.
(4) An arbitration agreement is in writing if it is
contained in –
(a) a document signed by the parties;
(b) an exchange of letters, telex, telegrams or
other means of telecommunication which
provide a record of the agreement; or
(c) an exchange of statement of claim and
defence in which the existence of the
agreement is alleged by one party and not
denied by the other.
(5) The reference in a contract to a document
containing an arbitration clause constitutes an
arbitration agreement if the contract is in writing
and the reference is such as to make that
arbitration clause part of the contract.”
9. From the aforesaid provision, it is graphically clear
that unless an arbitration agreement stipulates that
the parties agree to submit all or certain disputes
JUDGMENT
which have arisen or which may arise in respect of
defined legal relationship, whether contractual or not,
there cannot be a reference to an arbitrator. To
elaborate, it conveys that there has to be intention,
expressing the consensual acceptance to refer the
disputes to an arbitrator. In the absence of an
arbitration clause in an agreement, as defined in sub-
section (4) of Section 7, the dispute/disputes arising
Page 8
9
between the parties cannot be referred to the arbitral
tribunal for adjudication of the dispute.
10. In Smt. Rukmanibai Gupta (supra), while
considering Clause 15 of the agreement therein, a
two-Judge Bench opined that the clause spelt out an
arbitration agreement between the parties. The said
clause was as follows:-
“Whenever any doubt, difference or dispute
shall hereafter arise touching the construction
of these presents or anything herein contained
or any matter or things connected with the said
lands or the working or non-working thereof or
the amount or payment of any rent or royalty
reserved or made payable hereunder in the
matter in difference shall be decided by the
lessor whose decision shall be final.”
The learned Judges, to appreciate the tenor and
purport of the said clause, referred to Section 2(a) of the
JUDGMENT
1940 Act and reproduced a passage from Russell on
th
Arbitration, 19 Edn., P. 59 which reads as follows: -
“ If it appears from the terms of the agreement
by which a matter is submitted to a person’s
decision that the intention of the parties was
that he should hold an inquiry in the nature of a
judicial inquiry and hear the respective cases of
the parties and decide upon evidence laid
before him, then the case is one of an
arbitration ”
Page 9
10
11. The Court also referred to Chief Conservator of
6
Forest v. Rattan Singh and ruled that:
“In the clause under discussion there is a
provision for referring the disputes to the lessor
and the decision of the lessor is made final. On
its true construction it spells out an arbitration
agreement.”
12. At this juncture, it is apposite to refer to a three-Judge
7
Bench decision in State of U.P. v. Tipper Chand
where the Court was interpreting Clause 22 in the
agreement which was under consideration so as to
find out whether the stipulations therein spelt out an
arbitration clause. The clause involved in the said
case read as follows:-
“Except where otherwise specified in the
contract the decision of the Superintending
Engineer for the time being shall be final,
conclusive and binding on all parties to the
contract upon all questions relating to the
meaning of the specifications, design, drawing
and instructions hereinbefore mentioned. The
decision of such Engineer as to the quality of
workmanship, or materials used on the work, or
as to any other question, claim, right, matter or
things whatsoever, in any way arising out of or
relating to the contract, designs, drawing
specifications, estimates, instructions, orders, or
these conditions, or otherwise concerning the
works, or the execution or failure to execute the
same, whether arising during the progress of
the work, or after the completion or
JUDGMENT
6
AIR 1967 SC 166 : 1966 Supp SCR 158
7
(1980) 2 SCC 341
Page 10
11
abandonment of the contract by the contractor,
shall also be final, conclusive and binding on the
contractor.”
Interpreting the said clause, the Court opined thus:-
“Admittedly the clause does not contain any
express arbitration agreement. Nor can such an
agreement be spelled out from its terms by
implication, there being no mention in it of any
dispute, much less of a reference thereof. On
the other hand, the purpose of the clause
clearly appears to be to vest the Superintending
Engineer with supervision of the execution of
the work and administrative control over if from
time to time.”
13. In that context, the three-Judge Bench approved the
decisions of the High Courts in Governor-General v.
8
Simla Banking and Industrial Company Ltd. ,
9
Dewan Chand v. State of Jammu and Kashmir
10
and Ram Lal v. Punjab State wherein the clauses
were different. In that context, it was opined that the
JUDGMENT
High Courts had rightly interpreted the clause
providing for arbitration. We think it apt to reproduce
the delineation by the learned Judges:-
“In the Jammu and Kashmir case the relevant
clause was couched in these terms:
“For any dispute between the contractor
and the Department the decision of the
Chief Engineer PWD Jammu and Kashmir,
8
AIR 1947 Lah 215 : 226 IC 444
9
AIR 1961 J & K 58
10
AIR 1966 Punj 436 : 68 Punj LR 522 : ILR (1966) 2 Punj 428
Page 11
12
will be final and binding upon the
contractor.”
The language of this clause is materially
different from the clause in the present case
and in our opinion was correctly interpreted as
amounting to an arbitration agreement. In this
connection the use of the words “any dispute
between the contractor and the Department”
are significant. The same is true of the clause in
Ram Lal case which ran thus:
“In matter of dispute the case shall be
referred to the Superintending Engineer of
the Circle, whose order shall be final.”
We need hardly say that this clause refers not
only to a dispute between the parties to the
contract but also specifically mentions a
reference to the Superintending Engineer and
must therefore be held to have been rightly
interpreted as an arbitration agreement.”
14. At this stage, it is useful to refer to a three-Judge
Bench decision in State of Orissa and another etc.
11
v. Sri Damodar Das wherein the Court posed the
JUDGMENT
question whether there was an agreement for the
resolution of disputes as enshrined under Clause 25 of
the agreement. The said clause read as follows:-
“25. Decision of Public Health Engineer to be
final. — Except where otherwise specified in this
contract, the decision of the Public Health
Engineer for the time being shall be final,
conclusive and binding on all parties to the
contract upon all questions relating to the
meaning of the specifications; drawings and
11
AIR 1996 SC 942
Page 12
13
instructions hereinbefore mentioned and as to
the quality of workmanship or materials used on
the work, or as to any other question, claim,
right, matter or thing, whatsoever in any way
arising out of, or relating to, the contract,
drawings, specifications, estimates, instructions,
orders or these conditions, or otherwise
concerning the works or the execution or failure
to execute the same, whether arising during the
progress of the work or after the completion or
the sooner determination thereof of the
contract.”
The three-Judge Bench referred to the principles
stated in Tipper Chand (supra) and observed as follows:-
“We are in respectful agreement with the above
ratio. It is obvious that for resolution of any
dispute or difference arising between two
parties to a contract, the agreement must
provide expressly or by necessary implication, a
reference to an arbitrator named therein or
otherwise of any dispute or difference and in its
absence it is difficult to spell out existence of
such an agreement for reference to an
arbitration to resolve the dispute or difference
contracted between the parties. The ratio in
Smt. Rukmanibai Gupta v. Collector does
not assist the respondent.”
12
15. In K.K. Modi v. K.N. Modi and others , a two-
JUDGMENT
Judge Bench was interpreting Clause 9 of the
agreement which read as follows:-
“Implementation will be done in consultation
with the financial institutions. For all disputes,
clarification etc. in respect of implementation of
this agreement, the same shall be referred to
the Chairman, IFCI or his nominees whose
12
(1998) 3 SCC 573
Page 13
14
decisions will be final and binding on both the
groups.”
The court referred to a passage from Russell on
st
Arbitration, 21 Edn., at p. 37, para 2-014 and the
decisions in Rukmanibai Gupta (supra) and M.
Dayanand Reddy v. A.P. Industrial Infrastructure
13
Corporation Limited And Others and came to hold
that the said clause was not an arbitration clause and
hence, the proceedings before the Chairman, IFCI could not
have been treated as arbitration proceedings. It was so
held on the following ground:-
“Undoubtedly, in the course of correspondence
exchanged by various members of Groups A
and B with the Chairman, IFCI, some of the
members have used the words “arbitration” in
connection with clause 9. That by itself,
however, is not conclusive. The intention of the
parties was not to have any judicial
determination on the basis of evidence led
before the Chairman, IFCI. Nor was the
Chairman, IFCI required to base his decision
only on the material placed before him by the
parties and their submissions. He was free to
make his own inquiries. He had to apply his own
mind and use his own expertise for the purpose.
He was free to take the help of other experts.
He was required to decide the question of
valuation and the division of assets as an expert
and not as an arbitrator. He has been
authorised to nominate another in his place. But
the contract indicates that he has to nominate
JUDGMENT
13
(1993) 3 SCCC 137
Page 14
15
an expert. The fact that submissions were made
before the Chairman, IFCI, would not turn the
decision-making process into an arbitration.”
16. In Bharat Bhushan Bansal v. U.P. Small
14
Industries Corporation Ltd., Kanpur , clauses 23
and 24 of the agreement were projected to make the
foundation of an arbitration clause. That read as
follows:-
“Decision of the Executive Engineer of the
UPSIC to be final on certain matters.
23. Except where otherwise specified in the
contract, the decision of the Executive Engineer
shall be final, conclusive and binding on both
the parties to the contract on all questions
relating to the meaning, the specification,
design, drawings and instructions hereinbefore
mentioned, and as to the quality of
workmanship or materials used on the work or
as to any other question whatsoever in any way
arising out of or relating to the designs,
drawings, specifications, estimates, instructions,
orders or otherwise concerning the works or the
execution or failure to execute the same
whether arising during the progress of the work,
or after the completion thereof or abandonment
of the contract by the contractor shall be final
and conclusive and binding on the contractor.
JUDGMENT
Decision of the MD of the UPSIC on all other
matters shall be final
24. Except as provided in clause 23 hereof, the
decision of the Managing Director of the UPSIC
shall be final, conclusive and binding on both
the parties to the contract upon all questions
14
AIR 1999 SC 899
Page 15
16
relating to any claim, right, matter or thing in
any way arising out of or relating to the contract
or these conditions or concerning abandonment
of the contract by the contractor and in respect
of all other matters arising out of this contract
and not specifically mentioned herein.”
Interpreting the said clauses, the Court opined thus:-
“In the present case, reading clauses 23 and 24
together, it is quite clear that in respect of
questions arising from or relating to any claim
or right, matter or thing in any way connected
with the contract, while the decision of the
Executive Engineer is made final and binding in
respect of certain types of claims or questions,
the decision of the Managing Director is made
final and binding in respect of the remaining
claims. Both the Executive Engineer as well as
the Managing Director are expected to
determine the question or claim on the basis of
their own investigations and material. Neither of
the clauses contemplates a full-fledged
arbitration covered by the Arbitration Act.”
17. In Bihar State Mineral Development Corporation
15
and another v. Encon Builders (I) (P) Ltd. ,while
JUDGMENT
dealing with the arbitration clause of an arbitration
agreement under the Act the Court stated thus:
“(1) There must be a present or a future
difference in connection with some
contemplated affair.
(2) There must be the intention of the parties to
settle such difference by a private tribunal.
15
(2003) 7 SCC 418
Page 16
17
(3) The parties must agree in writing to be
bound by the decision of such tribunal.
(4) The parties must be ad idem”.
In the said case, it has also been opined that the Act
does not prescribe any form of an arbitration agreement.
The term ‘arbitration’ is not required to be specifically
mentioned in the agreement but what is required is to
gather the intention of the parties as to whether they have
agreed for resolution of the disputes through arbitration.
18. In Dina Nath (supra), the clause in the agreement
read as follows: -
“4. Any dispute arising between the department
and the contractor/society shall be referred to the
Superintending Engineer, Anandpur Sahib, Hydel
(Construction) Circle No. 1, Chandigarh for orders
and his decision will be final and
acceptable/binding on both parties.”
JUDGMENT
The two-Judge Bench, basically relying on Tipper
Chand (supra) which has approved the view of Jammu and
Kashmir High Court in Dewan Chand (supra), treated the
aforesaid clause as providing for arbitration because it
categorically mentioned the word “dispute” which would
be referred to the Superintending Engineer and further
Page 17
18
that his decision would be final and acceptable to/binding
on both the parties.
19. In Jagdish Chander (supra), the Court, after referring
to the earlier decisions, culled out certain principles
with regard to the term “arbitration agreement”. The
said principles basically emphasize on certain core
aspects, namely, (i) that though there is no specific
form of an arbitration agreement, yet the intention of
the parties which can be gathered from the terms of
the agreement should disclose a determination and
obligation to go to arbitration; (ii) non-use of the
words “arbitration” and “arbitral tribunal” or
“arbitrator” would not detract from a clause being
interpreted as an arbitration agreement if the
JUDGMENT
attributes or elements of arbitration agreement are
established, i.e., ( a ) The agreement should be in
writing. ( b ) The parties should have agreed to refer
any disputes (present or future) between them to the
decision of a private tribunal. ( c ) The private tribunal
should be empowered to adjudicate upon the disputes
in an impartial manner, giving due opportunity to the
Page 18
19
parties to put forth their case before it. ( d ) The parties
should have agreed that the decision of the private
tribunal in respect of the disputes will be binding on
them; and (iii) where there is specific exclusion of any
of the attributes of an arbitration agreement or
contains anything that detracts from an arbitration
agreement, it would not be an arbitration agreement.
In this context, the two-Judge Bench has given some
examples and we think it apt to reproduce the same: -
“For example, where an agreement requires or
permits an authority to decide a claim or
dispute without hearing, or requires the
authority to act in the interests of only one of
the parties, or provides that the decision of the
authority will not be final and binding on the
parties, or that if either party is not satisfied
with the decision of the authority, he may file a
civil suit seeking relief, it cannot be termed as
an arbitration agreement.”
JUDGMENT
20. In State of Orissa and others v. Bhagyadhar
16
Dash , the Court, while discussing about the non-
requirement of a particular form for constituting an
arbitration agreement and ascertainment of the
intention for reference to arbitration, as has been
16
(2011) 7 SCC 406
Page 19
20
stated in Rukmanibai Gupta (supra), observed thus:
-
“ 16. While we respectfully agree with the
principle stated above, we have our doubts as
to whether the clause considered in Rukmanibai
Gupta case would be an arbitration agreement
if the principles mentioned in the said decision
and the tests mentioned in the subsequent
decision of a larger Bench in Damodar Das are
applied. Be that as it may. In fact, the larger
Bench in Damodar Das clearly held that the
decision in Rukmanibai Gupta was decided on
the special wording of the clause considered
therein: ( Damodar Das case , SCC p. 224, para
11)
“ 11 . … The ratio in Rukmanibai Gupta v.
Collector does not assist the respondent.
From the language therein this Court
inferred, by implication, existence of a
dispute or difference for arbitration.”
21. Keeping in mind the principles laid down by this Court
in the aforesaid authorities relating to under what
circumstances a clause in an agreement can be
JUDGMENT
construed as an arbitration agreement, it is presently
apposite to refer to clause 48 of the agreement. The
said clause reads as follows: -
“48.0 Settlement of disputes:
48.1 Any dispute(s) or difference(s) arising out of
or in connection with the Contract shall, to
the extent possible, be settled amicable
between the parties.
Page 20
21
48.2 If any dispute or difference of any kind
whatsoever shall arise between the owner
and the Contractor, arising out of the
Contract for the Performance of the Works
whether during the progress of the Works or
after its completion or whether before or
after the termination, abandonment or
breach of the contract, it shall, in the first
place, be referred to and settled by the
Engineer, who, within a period of thirty (30)
days after being requested by either party
to do so, shall give written notice of his
decision to the owner and the contractor.
48.3 Save as hereinafter provided, such decision
in respect of every matter so referred shall
be final and binding upon the parties until
the completion of the works and shall
forthwith be given effect to by the
contractor who shall proceed with the works
with all the due diligence.
48.4 During settlement of disputes and Court
proceedings, both parties shall be obliged to
carry out their respective obligations under
the contract.”
22. On a careful reading of the said clause, it is
JUDGMENT
demonstrable that it provides for the parties to
amicably settle any disputes or differences arising in
connection with the contract. This is the first part.
The second part, as is perceptible, is that when
disputes or differences of any kind arise between the
parties to the contract relating to the performance of
the works during progress of the works or after its
Page 21
22
completion or before or after the termination,
abandonment or breach of the contract, it is to be
referred to and settled by the engineer, who, on being
requested by either party, shall give notice of his
decision within thirty days to the owner and the
contractor. There is also a stipulation that his
decision in respect of every matter so referred to
shall be final and binding upon the parties until the
completion of works and is required to be given effect
to by the contractor who shall proceed with the works
with due diligence. To understand the intention of
the parties, this part of the clause is important. On a
studied scrutiny of this postulate, it is graphically
clear that it does not provide any procedure which
JUDGMENT
would remotely indicate that the concerned engineer
is required to act judicially as an adjudicator by
following the principles of natural justice or to
consider the submissions of both the parties. That
apart, the decision of the engineer is only binding
until the completion of the works. It only casts a
burden on the contractor who is required to proceed
Page 22
23
with the works with due diligence. Besides the
aforesaid, during the settlement of disputes and the
court proceedings, both the parties are obliged to
carry out the necessary obligation under the contract.
The said clause, as we understand, has been
engrafted to avoid delay and stoppage of work and
for the purpose of smooth carrying on of the works. It
is interesting to note that the burden is on the
contractor to carry out the works with due diligence
after getting the decision from the engineer until the
completion of the works. Thus, the emphasis is on
the performance of the contract. The language
employed in the clause does not spell out the
intention of the parties to get the disputes
JUDGMENT
adjudicated through arbitration. It does not really
provide for resolution of disputes.
23. Quite apart from the above, clause 4.1 of the
agreement is worthy to be noted. It is as follows: -
“4.1 It is specifically agreed by and between
the parties that all the differences or disputes
arising out of the Agreement or touching the
subject matter of the Agreement, shall be
decided by a competent Court at Bangalore.”
Page 23
24
24. Mr. Vishwanathan, learned senior counsel for the
appellants, laying immense emphasis on the same,
has submitted that the said clause not only provides
the territorial jurisdiction by stating a competent
court at Bangalore but, in essence and in effect, it
stipulates that all the differences or disputes arising
out of the agreement touching the subject-matter of
the agreement shall be decided by a competent court
at Bangalore. Mr. Dave, learned senior counsel for
the respondents, would submit that it only clothes the
competent court at Bangalore the territorial
jurisdiction and cannot be interpreted beyond the
same. The submission of Mr. Dave, if properly
appreciated, would convey that in case an award is
JUDGMENT
passed by the arbitrator, all other proceedings under
any of the provisions of the Act has to be instituted at
the competent court at Bangalore. This construction,
in our opinion, cannot be placed on the said clause. It
really means that the disputes and differences are
left to be adjudicated by the competent civil court.
Thus, clause 48, as we have analysed, read in
Page 24
25
conjunction with clause 4.1, clearly establishes that
there is no arbitration clause in the agreement. The
clauses which were interpreted to be arbitration
clauses, as has been held in Ram Lal (supra) and
Dewan Chand (supra) which have been approved in
Tipper Chand (supra), are differently couched. As
far as Rukmanibai Gupta (supra) is concerned, as
has been opined in Damodar Das (supra) and also in
Bhagyadhar Dash (supra), it has to rest on its own
facts. Clause in Dina Nath (supra) is differently
couched, and clause 48, which we are dealing with,
has no similarity with it. In fact, clause 48, even if it
is stretched, cannot be regarded as an arbitration
clause. The elements and attributes to constitute an
JUDGMENT
arbitration clause, as has been stated in Jagdish
Chander (supra), are absent. Therefore, the
irresistible conclusion is that the High Court has fallen
into grave error by considering the said clause as
providing for arbitration.
25. Consequently, the appeals are allowed and the
judgments and orders passed by the High Court are
Page 25
26
set aside. However, regard being had to the facts
and circumstances of the case, there shall be no
order as to costs.
…..…………………………….J.
[Anil R. Dave]
……………..………………….J.
[Dipak Misra]
New Delhi;
April 07, 2014.
JUDGMENT
Page 26