Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 8
PETITIONER:
M/S. KANORIA CHEMICALS AND INDUSTRIES LTD. ETC.
Vs.
RESPONDENT:
U.P. STATE ELECTRICITY BOARD & ORS.
DATE OF JUDGMENT: 10/03/1997
BENCH:
B.P. JEEVAN REDDY, K.S. PARIPOORNAN
ACT:
HEADNOTE:
JUDGMENT:
J U D G M E N T
B.P. JEEVAN REDDY, J.
Civil Appeals [Arising out of SLP (C) Nos.6588/94,
21905-06/93, 21913-14/93, 6479/94 & 23250/94
Leave granted in Special Leave Petitions.
These appeals are preferred against the judgment of a
Division Bench of the Allahabad High Court dismissing the
writ petitions filed by the appellants. The appellants are
large consumers of electricity.
By a Notification dated April 21, 1990, the Uttar
Pradesh State Electricity Board had revised the electricity
Board had revised the electricity rates/tariffs under
Section 49 of the Electricity (Supply) Act, 1948. The
Notification inter alia provided for payment of interest in
case the bill amount is not paid within the specified
period. Clause 7(b) read as follows:
"7(b) For delayed payment:
In the event of any bill of
whatever nature it may be not being
paid by the due date specified
therein, the consumer shall pay an
additional charge per day of seven
paise per hundred rupees or part
thereof on the unpaid amount of the
bill for the period by which the
payment is delayed, beyond the due
dated specified in the bill,
without prejudice to the right of
the Board to disconnect the
supply."
The validity of the aforesaid Notification was
questioned in the Allahabad High Court by way of a writ
petition filed by the Eastern U.P. Chamber of commerce and
Industry, Allahabad and certain individual consumers. On the
Interlocutory Application filed in the said writ petition,
the High Court passed the following Order on July 25, 1990:
"In this case S/Sri Sudhir Agarwal
and S.C. Budhwar have filed
appearance on behalf of
Respondents. They pray for and are
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 8
granted two weeks’ time for filing
rejoinder affidavit. List this
petition for disposal, if possible
at the admission stage, on 16th
August, 1990. This is necessary in
view of recurrence of this matter
in large number of cases and
revenue in large scale being
affected for electricity charges.
Meanwhile till 23-8-1990 unless
recalled earlier, the operation of
the notification dated 21.4.1990
shall remain stayed. The
respondents are restrained from
realising the additional amount of
electricity charges from
petitioners in pursuance of the
said notification. However, the
petitioner shall continue to pay at
the old rate."
[Emphasis added]
The said order was continued by subsequent Order dated
August 30, 1990 and September 7, 1990.
It appears that besides the above writ petition,
several other writ petitions were filed questioning the
aforesaid Notification. In every writ petition, there was an
Interlocutory Application praying for stay of operation of
the said Notification but there does not appear to be any
uniformity in the interim orders made by the High Court in
those writ petitions. For example, in Writ Petition
No.300097 of 1990 filed by the Employer Association of
Northern India, the interim order was to the following
effect:
"Meanwhile effect shall not be
given to the notification dated
21st April, 1990 as against the
petitioners. However, it is made
clear that in the event of failure
of the writ petition the petitions
shall deposit with the relevant
authority within a period of one
month from the date of dismissal of
the writ petition the difference
between the amount of electricity
dues, which will be paid
hereinafter by the petitioners
under our order and the sum which
may be calculated on the basis of
the impugned notification."
[Emphasis added]
All the said writ petitions challenging the said
Notification were ultimately dismissed by a Division Bench
on March 1, 1993.
From this stage onwards, we will refer to the facts and
contentions in civil appeal arising from Special Leave
Petition (C) No.6588 of 1990 [preferred by M/s. Kanoria
Chemicals and Industries Limited], as representative of the
facts and contention in all the matters being disposed of
under this judgment. Though the individual facts vary, the
questions arising in these appeals are common.
After the dismissal of the writ petitions on March 1,
1993 as aforesaid, Kanoria says, it deposited the difference
amount between pre-revised and the revised electricity
rates. It did not, however, deposit the "additional charges"
leviable under clause 7(b), referred to above, which are
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 8
generally referred to - and referred to hereinafter - as
"late payment surcharge". Thereupon, the Board issued a
notice of demand calling upon Kanoria to pay the late
payment surcharge in a sum of Rs.3,27,01,408.88p.
[calculated upto February 28, 1993]. Similar demand notices
were served upon other appellants also. A fresh batch of
writ petitions were filed by several consumers including the
appellants herein questioning the notices demanding late
payment surcharge under clause 7(b). The main contention of
the appellants before the High Court was that inasmuch as
the High Court had stayed the operation of the Notification
dated April 21, 1990 [by its Order dated July 25, 1990 as
continued from time to time], clause 7(b) remained
inoperative during the period July 25, 1990 to March 1, 1993
and, therefore, no late payment surcharge can be levied on
the amount withheld by appellants under the orders of the
court, even though their writ petitions were dismissed
ultimately. According to the appellants, it was not a case
where the court injuncted the Board from collection the
dues according to the aforesaid Notification, or was it a
case where the collection of bill amount was stayed
simplicitor. It was a case, they submitted, where the
operation of the very Notification was stayed which meant
that from the date of the stay order, clause 7(b) did not
operate and was not effective till the dismissal of the writ
petitions. Strong reliance was placed upon the decision of
this Court in Adoni Ginning Factory v. Secretary, Andhra
Pradesh State Electricity Board [1979 (4) S.C.C. 560]. The
said contention has been rejected by the Division Bench.
R.A. Sharma, J., speaking for the Division Bench, first
examined the nature and effect of the interim orders passed
by courts pending disposal of substantive matters and then
opined that in Adoni Ginning, this Court cannot be said to
have held that in the case of stay of operation of the
Notification, interest does not accrue at all. Sharma, J.
pointed out that the said decision was concerned only with
the period during which an order of injunction restraining
the Board from collecting the revised charges was in
operation and this Court opined that an order of injunction
does not prevent the accrual of interest provided by the
relevant tariffs/rules. Sharma, J. pointed out that the
recoverability of the interest amount of the period covered
by an order of stay of the Notification was not at all in
issue in Adoni Ginning and, therefore, it cannot be said
that there is any decision on the said question. Affirming
the opt-repeated principle that a decision is an authority
only for what it actually decides, the learned Judge opined
that the consumers are liable to pay the late payment
surcharge under clause 7(b) of the said Notification even
for the period covered by the aforementioned order dated
July 25, 1990 [as extended from time to time]. The learned
Judge also pointed out that the interim orders passed in
various writ petitions were not uniform and by way
illustration set out in the interim order in Writ Petition
No.30097 of 1990 [quoted by us hereinabove]. The correctness
of the judgment is called in question in this batch of
appeals.
Sri R. Vaidyanathan, who lead the arguments on behalf
of the appellants, submitted that the impugned decision of
the High Court is clearly contrary to the principles
enunciated by this Court in Adoni Ginning and cannot,
therefore, stand. Counsel relied upon another order this
Court dated April 23, 1996 in special leave Petition (C)
No.9087-88 of 1996 [M/s. Hindalco Industries Limited v.
State of Uttar Pradesh]. Learned counsel submitted that
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 8
clause 7(b) of the Notification dated April 21, 1990 was
penal in nature inasmuch as the late payment surcharge
provided by it works out to 25.5 interest per annum. Such
high rate of interest, learned counsel submitted, cannot but
be characterized as penal.
Inasmuch as the decision in Adoni Ginning constitutes
the sheet-anchor of the appellant’s case, it is necessary to
closely examine the facts and ratio of the said decision.
Electricity charges were enhanced by the Government of
Andhra Pradesh under an Order dated 30th January, 1955. The
enhancement was questioned by certain consumer by way of
writ petitions in Andhra Pradesh High Court. The High Court
stayed the operation of the Government Order enhancing the
rates. The writ petitions came up for hearing before a
learned Single Judge on February 22, 1957 and were allowed.
The Government of Andhra Pradesh preferred writ appeals
which were allowed by a Division Bench of that court on 19th
December, 1958 upholding the validity of the enhancement.
Thereafter, the Andhra Pradesh State Electricity Undertaking
with effect from Ist April, 1959 issued bills to several
consumer call in upon them to pay the arrears of enhanced
charges. No demand was made under these notices for
surcharge [for delayed payment of Bill amount] on the
arrears. Meanwhile several consumers approached this court
and obtained order of injunction restraining the
Government/Board from realising from them the "amount of
arrears occasioned by the enhancement of rates". Injunction
was granted by this Court subject to certain conditions
including the condition that in the event of the dismissal
of their appeals, the appellants shall pay the arrears with
interest calculated @ one percent per annum. All the appeals
were dismissed by this Court on 25th March, 1964.
Thereafter, the Electricity Board issued demand notices
calling upon the consumers to pay surcharge @ twelve percent
per annum on the arrears in respect of which they had
obtained order of injunction pending their appeals before
this court. On receipt of these demand notices, the
consumers again approached the High Court by way of writ
petitions questioning the demand. Their writ petitions were
allowed by a learned Single Judge observing that no
surcharge was leviable during the period when the order of
injunction granted by this Court was operation. The writ
appeal preferred by the Board were, however, allowed by a
Division Bench against which decision some of the consumers
approach this Court again. It is, therefore, clear that the
only dispute in Adoni Ginning pertained to the liability of
the consumers to pay surcharge @ twelve percent per annum on
the amount not collected from them under the orders of
injunction granted by this Court pending their appeals. It
is significant to notice that the dispute in the said case
did not pertain to the liability of the consumers to pay the
surcharge amount for the period covered by the order of stay
granted by the High Court; the Board did not choose to
demand any surcharge for that period. The contention of the
appellants in Adoni Ginning was that by virtue of the
injunction order granted by this Court, the consumers cannot
be said to be in default in paying the electricity charges
and, therefore, no surcharge was leviable. The contention
was rejected by this Court [D.A. Desai and O. Chinnappa
Reddy, JJ.]. The Court pointed out that according to clause
(9), a consumer was liable to pay the bill amount within
thirty days, in default of which he was liable to pay "an
additional charge of on e percent on the amount of the bill
for every month delay or part thereof". The contention urged
by the appellant therein was repelled in the following
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 8
words:
"The injunction granted by this
court restrained the government
from realising the arrears of
enhanced charges..... All that the
injunction did was to restrain the
Board from realising the arrears
which meant that the Board was
restrained from taking any coercive
action such as disconnection of
supply of electricity etc. for the
realisation of the arrears. The
operation of G.O. No.187 dated 30th
January, 1955, as such was not
stayed. Thus the obligation of the
consumers to pay charges at the
enhanced rates was not suspended
though the Electricity Board was
prevented from realising the
arrears. It was up to the consumers
to pay or not to pay the arrears.
If they paid the arrears they
relieved themselves against the
liability to pay surcharge. If they
did not pay the arrears they were
bound to pay the surcharge if they
failed in the appeals before the
Supreme Court. This was precisely
what was pointed out by the
Electricity Board in the Bills
issued to the consumers after the
Supreme Court granted the
injunction. We may mention here
that the Electricity Board is not
demanding any surcharge on the
arrears for the period during which
the Andhra Pradesh High Court had
granted stay. It was explained by
the learned Counsel for the
Electricity Board that no surcharge
was claimed for that period as the
operation of G.O.No.187 dated 30th
January 1955 had itself been stayed
at that time. Surcharge was claimed
for the period during which the
appeals were pending in the Supreme
court since the Supreme Court did
not stay the operation of
G.O.No.187 but only restrained the
Board from collecting the arrears.
That no stay of G.O.No.187 was ever
intended to be granted by the
Supreme Court is also clear from
the circumstance that there was no
injunction restraining the
Electricity Board from collecting
future charge at the enhanced
rates. the Electricity Board was,
therefore, right in claiming
surcharge for the period the during
which the appeals were pending in
the Supreme Court and not Claiming
surcharge for the period during
which the Writ Petition and Writ
appeals were pending in the High
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 6 of 8
Court."
[Emphasis added]
The learned counsel for the appellants in the appeals
before us rely upon the portions underlined in the above
passage as a decision supporting their contention that where
the operation of Government Order is stayed, no surcharge
can be demanded upon the amount withheld. We find it
difficult to agree. In our respectful opinion, the
underlined portions do not constitute the decision of the
court. They merely refer to the fact that the Board itself
did not make a demand for surcharge amount in respect of the
period covered by stay under its own understanding of the
effect of the stayed order granted by the High Court and
that it was justified in its opinion. The demand was , the
court pointed out, in respect of the period covered by the
order of injunction granted by this Court. This Court held
expressly that the grant of and injunction does not relieve
the consumers of their obligation to pay the charges at the
enhanced rates and, therefore, the demand for
surcharge/interest for such period is not illegal. The
portions underlined cannot be understood as laying down the
proposition that in respect of the period covered by stay,
no demand can be made. No such proposition can be deduced
from the said passage for the reason that the liability for
the said was not at all in issue in the said decision.
Unless put in issue and pronounced upon, it cannot be said
that there was a decision on the said issue. There was no
list between the parties with respect to the period covered
by the stay order of the High Court. If so, it cannot be
said that any decision was rendered by this court on the
said issue or aspect, as it may be called. We, therefore,
agree with the High Court that Adoni Ginning cannot be read
as laying down the proposition that the grant of stay of a
Notification revising the electricity charges has the effect
of relieving the consumers/petitioners of their obligation
to pay late payment surcharge/interest on the amount
withheld by them even when their writ petitions are
dismissed ultimately. Holding otherwise would mean that even
though the Electricity Board, who was the respondent in the
writ petitions succeeded therein, is yet deprived of the
late payment surcharge which is due to it under the tariff
rules/regulation. It would be a case where the Board
suffers prejudice on account of the order of the court and
for no fault of it’s. It succeeds in the writ petition and
yet loses. The consumer files the writ petition, obtains
stay of operation of the Notification revising the rates and
fails in his attack upon the validity of the Notification
and yet he is relieved of the obligation to pay the late
payment surcharge for the period of stay, which he is liable
to pay according to the statutory terms and conditions
indeed form part of the contract of supply entered into by
him with the Board. We do not think that any such unfair and
inequitable proposition can be sustained in law. No such
proposition flows from Adoni Ginning. It is a matter of
common knowledge that several petitioners [their counsel]
word the stay petition differently. On petitioner may ask
for injunction, another may ask for stay of demand notice,
the third on may ask for stay of collection of the amount
demanded and the fourth one may ask for the stay of the very
Notification. Such distinctions are bound to occur where a
large number of writ petitions are filed challenging the
same Notification. the interim orders made by the Court may
also vary in their phraseology in such a situation. Take
this very case while the consumers has asked for stay of
operation of the Government Order revising the rates, those
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 7 of 8
very consumers asked for an injunction when they came to
Supreme Court. Furthermore, as pointed out rightly by the
High Court, the order of the stay granted by the High Court
in writ petitions questioning the validity of the
Notification dated April 21, 1990 were not uniform. In the
case of writ petition filed by the Eastern U.P. Chamber of
Commerce and Industry, Allahabad, the operation of the
Notification was stayed while in the case of the writ
petition filed by the Employers Association of Northern
India, it was directed that "effect shall not be given to
the notification dated 21st April, 1990 as against the
petitioner shall deposit with the relevant authority within
a period of one month from the date of dismissal of the
writ petition the difference between the amount of
electricity dues to be paid hereinafter by the petitioner
under our orders and the sum which may be calculated on the
basis of the impugned notification". The words "sum which
may be calculated on the basis of the impugned notification"
in the later order clearly mean and include the late payment
surcharge as well. The acceptance of the appellants’
argument would thus bring about a discrimination between a
petitioner and a petitioner just because of the variation of
the language employed by the court while granting the
interim order though in substance and in all relevant
aspects, they are similarly situated. It is equally well
settled that an order of stay granted pending disposal of a
writ petition/suit or other proceeding, comes to an end with
the dismissal of the substantive proceeding and that it is
the duty of the court in such a case to put the parties in
the same position they would have been but for the interim
order of the court. Any other view would result in the act
or order of the court prejudicing a party [Board in this
case] for no fault of its and would also mean rewarding a
writ petitioner inspite of his failure. We do not think that
any such unjust consequence can be countenanced by the
courts. As a matter of fact, the contention of the consumers
herein, extended logically should mean that even the
enhanced rates are also not payable for the period covered
by the order of stay because the operation of the very
Notification revising/enhancing the tariff rates was stayed.
Mercifully, no such argument was urged by the appellants. It
is ununderstandable how the enhanced rates can be said to be
payable but not he late payment surcharge are provided by
the same Notification - the operation of which was stayed.
As has been pointed out by S.C. Agrawal, J., speaking
for a three-Judge Bench in Shree Chamundi Mopeds Ltd. vs.
Church of South India Trust Association, Madras [
1992 (3) S.C.C.1], "while considering the effect of an
interim order staying the operation of the order under
challenge, a distinction has to be made between quashing of
an order and stay of operation of an order. Quashing of an
order results in the restoration of the position was it
stood on the date of the passing of the order which has been
quashed. The stay of operation of an order does not,
however, lead to such a result. It only means that the order
which has been stayed would not be operative from the date
of the passing of the stay order and it does not mean that
the said order has been wiped cut from existence."
Sri Vaidyanathan relied upon an unreported order dated
April 23, 1996 in Special Leave Petition (C) Nos.9087-88 of
1996 [Hindalco Industries v. State of U.P.]. We have seen
the order but we do not find anything in the said order
supporting the contention of the learned counsel.
Sri Vaidyanathan contended that the rate of ‘late
payment surcharge’ provided by clause 7(b) is really penal
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 8 of 8
in nature inasmuch as it works out to 25.5 percent per
annum. Learned counsel also submitted that the petitioners
understood the decision in Adoni Ginning as relieving them
of their obligation to pay interest for the period covered
by the interim order and that since they were acting
bonafide they should not be mulcted with such high rate of
interest. We cannot agree that the rate of late payment
surcharge provided by clause 7(b) is penal, but having
regard to the particular facts and circumstances of this
case and having regard to the fact that petitioners could
possibly have understood the decision in Adoni Ginning as
relieving them of their obligation to pay interest/late
payment surcharge for the period of stay, we reduce the rate
of late payment surcharge payable under clause 7(b) to
eighteen percent. But this direction is confined only to the
period covered by the stay orders in writ petitions filed
challenging the Notification dated April 21, 1990 and
limited to March 1, 1993, the date on which those writ
petitions were dismissed.
For the above reasons, the appeals fail and are
dismissed subject to the above mentioned direction with
respect to the rate of levy of late payment surcharge under
clause 7(b) of the Notification dated April 21, 1990.
Writ Petition (C) No.761 of 1993
Writ Petition (C) No.761 of 1993 too is dismissed for
the same reasons.
No costs.