Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 13
PETITIONER:
SATYABRATA GHOSE
Vs.
RESPONDENT:
MUGNEERAM BANGUR & CO., AND ANOTHER
DATE OF JUDGMENT:
16/11/1953
BENCH:
MUKHERJEA, B.K.
BENCH:
MUKHERJEA, B.K.
BOSE, VIVIAN
BHAGWATI, NATWARLAL H.
CITATION:
1954 AIR 44 1954 SCR 310
CITATOR INFO :
R 1958 SC 328 (25)
RF 1959 SC 135 (20)
R 1965 SC1523 (1)
R 1968 SC1024 (8)
R 1971 SC1756 (11)
F 1977 SC1019 (1,11)
A 1980 SC1717 (26)
A 1980 SC1717 (26)
ACT:
Indian Contract Act (IX of 1872), s. 56- Agreement to sell
land-Doctrine of frustration- Applicability-Doctrine whether
applicable in India- Scope of s. 56 Impossible meaning of-
Agreement for sale of land-Buyer’s rights-English and Indian
law.
HEADNOTE:
The doctrine of frustration is really an aspect or part of
the law of discharge of contract by reason of supervening
impossibility or illegality of the act agreed to be done and
hence comes within the purview of S. 56 of the Indian
Contract Act.. The view that s. 56 applies only to cases of
physical impossibility and that where this section is not
applicable recourse can be had to the principles of English
law on the subject of frustration is not correct. English
cases can have only a persuasive value, and are only helpful
in showing how English courts decided cases under similar
circumstances.
Section 56 of the Indian Contract Act lays down a rule of
positive law and does not leave the matter to be determined
according to the intention of the parties.
According to the Indian Contract Act. a promise may be
express or implied. In cases, therefore, where the court
gathers as a matter of construction that the contract itself
contained impliedly or expressly a term, according to which
it would stand discharged on the happening of certain
circumstances, the dissolution of the contract would take
place under the terms of the contract itself and such cases
would be outside the purview of S. 56 altogether. Although
in English law these cases are treated as cases of
frustration, in India they would be dealt with under s. 32
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 13
of the Indian Contract Act which deals with contingent
contracts or similar other provisions contained in the Act.
In the large majority of cases however the doctrine of
frustration. is applied not on the ground that the parties
themselves agreed to an implied term which operated to
release
311
them from the performance of the contract. The relief is
given by the court on the ground of subsequent impossibility
when it finds that the whole purpose or basis of a contract
was frustrated by the intrusion or occurrence of an
unexpected event or change of circumstances which was beyond
what was contemplated by the parties at the time when they
entered into the agreement. Here there is no question of
finding out an implied term agreed to by the parties
embodying a provision for discharge, because the parties did
not think about the matter at all nor could possibly have
any intention regarding it. When’ such an event or change
of circumstance occurs which is so, fundamental as to be
regarded by law as striking at the root of the contract as a
whole, it is the court which can pronounce the contract to
be frustrated and at an end. The court undoubtedly has to
examine the contract and the circumstances under which it
was made. The belief, knowledge and intention of the
parties are evidence, but evidence only on which the court
has to form its own conclusion whether the changed circum-
stances destroyed altogether the basis of the adventure and
its underlying object. This may be called a rule of
construction by English Judges but it is certainly not a
principle of giving effect to the intention of the parties
which underlies all rules of construction. This is really a
rule of positive law and as such comes within the purview of
s. 56 of the Indian Contract Act.
The reason underlying the rule of English law that the
doctrine of frustration does not apply to contracts for the
sale of land. is that under the English law, ,is soon as the
agreement to sell is complete the buyer becomes the owner of
the land in equity. As a mere agreement to sell does not
confer any rights of ownership on the buyer under the Indian
law, the doctrine of frustration is as applicable in India
to agreements for sale of land as in the case of other
agreements.
In 1940 as an integral part of a development scheme of an
extensive area of land- started by the defendant company, it
entered into a contract with the plaintiff’s predecessor for
the sale of a Plot of land to the latter accepting a small
sum of money as earnest. It undertook to construct roads
and drains and the conveyance was to be completed soon after
the completion of tile roads on payment of the balance of
the Price. As a considerable portion of the area comporised
in the scheme was requisitioned by the Government for
military Purposes in 1941, the company wrote to the
defendant that the road construction could not be taken up
for an indefinite period and required him to treat the
agreement as cancelled and receive back his earnest: Held.
that having regard to the nature and terms of the contracts
the actual existence of war condition at the time when it
was entered into the extent of the work involved in the
scheme fixing no time limit in the agreement for the cons-
truction of the roads etc., and the fact that the order of
requisition was in its very nature of a temporary character,
the requisition did not affect the fundamental basis of the
contract; nor
312
did the performance of the contract become illegal by reason
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 13
of the requisition, and the contract had not therefore
become impossible within the meaning of s. 56 of the Indian
Contract Act.
Joseph Constantine Steamship Co. v. Imperial Smelting Cor-
poration Ltd. ([1942] A.C. 154), Tamplin Steamship Co. Ltd.
v. Anglo American Products Co. Ltd. ([1916] A.C. 397),
Kesari Chand v. Governor General in Council (I.L.R. 1949
Nag. 718), Ganga Saran v. Ram Charan ([1952] S.C.R. 36),
Taylor v. Caldwell (3 B. and S. 826), Robinson v. Davison
(L.R. 6 Ex. 269) Denny Mott and Dickson Ltd. v. James B.
Frazer & Co. Ltd. [1944] A.C. 265) referred to.
JUDGMENT:
CIVIL APPELLATE JURISDICTION: Civil Appeal No. 80 of 1952.
Appeal from the Judgment and Decree dated the 6th September,
1950, of the High Court of Judicature at Calcutta (Das Gupta
and Lahiri JJ.) in Appellate Decree No. 318 of 1949 from the
Judgment and Decree dated the 25th February, 1949. of the
Court of the District Judge of Zillah 24 Parganas in Title
Appeal No. 8 of 1948 arising out of the Judgment and Decree
dated the 10th October, 1947, of the Court of the Additional
Subordinate Judge, 7th Court, Alipore.
M.C. Setalvad, Attorney-General for India (Aurobindo Guha
and Gobinda Mohan Roy, with him) for the appellant.
Atul Chandra Gupta (Bijan Behari Das Gupta, with him) for
respondent No. 1
1953. November 16. The Judgment of the Court was delivered
by
MUKHERJEA J.The facts giving rise to this appeal are, for
the most part, uncontroverted and the dispute between the
parties centres round the short point as to whether a
contract for sale of land to which this litigation relates,
was discharged and came to an end by reason of certain
supervening circumstances which affected the performance of
a material part of it.
To appreciate the merits of controversy, it will be
necessary to give a brief narrative of the material facts.
The defendant company, which is the main respondent in this
appeal, is the owner of a large tract of land situated, in
the vicinity of the Dhakuria Lakes within Greater Calcutta.
The
313
company started a scheme for development of this land for
residential purposes which was described as Lake Colony
Scheme No. I and in furtherance of the scheme the entire
area was divided into a large number of plots for the sale
of which offers were invited from intending purchasers. The
company’s plan of work seemed to be, to enter into agree-
ments with different purchasers for sale of these plots of
land and accept from them only a small portion of the con-
sideration money by way of earnest at the time of the agree-
ment. The company undertook to construct the roads and,
drains necessary for making the lands suitable for building
and residential purposes and as soon as they were completed.
the purchaser would be called upon to complete the con-
veyance by payment of the balance of the consideration
money. Bejoy Krishna Roy, who was defendant No. 2 in the
suit and figures as a pro forma respondent in this appeal,
was one of such purchasers who entered into a contract with
the company for purchase of a plot of land covered by the
scheme. His contract is dated the 5th of August, 1940, and
he paid Rs. 101 as earnest money. In the receipt granted by
the vendor for this earnest money, the terms of the agree-
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 13
ment are thus set out:--
"Received with thanks from Babu Bejoy Krishna Roy of 28
Tollygunge Circular Road, Tollygunge, the sum of Rs. 101
(Rupees one hundred and one only) as earnest money having
agreed to sell to him or his nominee 5 K. more or less in
plot No. 76 on 20 and 30 ft. Road in Premises No. Lake
Colony Scheme No. 1, Southern Block at the average rate of
Rs. 1,000 (Rupees one thousand only) per Cotta.
The conveyance must be completed within one month from the
date of completion of roads on payment of the balance of the
consideration money, time being deemed as the Essence of the
Contract. In case of default this agreement will be
considered as cancelled with forfeiture of earnest money.
Mokarari Mourashi
314
Terms of payment:One third to be paid at the time of
registration and the balance within six years bearing Rs. 6
per cent. interest per annum".
On 30th November, 1941, the plaintiff appellant was made a
nominee by the purchaser for purposes of the contract and
although he brought the present suit in the character of a
nominee, it has been held by the trial judge as well as by
the lower appellate court, that he was really an assignee of
Bejoy Krishna Roy in respect to the latter’s rights under
the contract. Some time before this date, there was an
order passed by the Collector, 24-Parganas, on 12th of
November, 1941 under section 79 of the Defence of India
Rules, on the strength of which a portion of the land
covered by the scheme was requisitioned for military
purposes. Another part of the land was requisitioned by the
Government on 20th of December, 1941. while a third order of
requisition, which related to the balance of the land
comprised in the scheme, was passed sometime later. In
November, 1943, the company addressed a letter to Bejoy
Krishna Roy informing him of the requisitioning of the lands
by the Government and stating inter alia that a considerable
portion of the land-appertaining to the scheme was taken
possession of by the Government and there was no knowing how
long the Government would retain possession of the same.
The constructs of the proposed roads and drains, therefore,
could not be taken up during the continuance of the war and
possibly for many years after its termination. In these
circumstances,, the company decided to treat the agreement
for sale with the addressee as cancelled and give him the
option of taking back the earnest money within one month
from the receipt of the letter. There was offer made in the
alternative that in case the purchaser refused to treat the
contract as cancelled, he could, if he liked, complete the
conveyance within one month from the receipt of the letter
by paying the balance of the consideration money and take
the land in the condition in which it existed at that time,
the company undertaking to construct the roads and the
drains, as circumstances might permit, after the termination
of the war.
315
The letter ended by saying that in the event of the
addressee not accepting either of the two alternatives, the
agreement would be deemed to be cancelled and the earnest
money would stand forfeited. This letter was handed over by
Bejoy Krishna to his nominee, the plaintiff, and there was
some correspondence after that, between the plaintiff on the
one hand and the company on the other through their
respective lawyers into the details of which it is not
necessary to enter. It is enough to state that the
plaintiff refused to accept either of the two alternatives
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 13
offered by the company and stated categorically that the
latter was bound by the terms of the agreement from which it
could not, in law, resile. On 18th of January, 1946, the
suit, out of which this appeal arises, was commenced by the
plaintiff against the defendant company, to which Bejoy
Krishna Roy was made a party defendant and the prayers in
the plaint were for a two-fold declaration, namely, (1) that
the contract dated the 5th of August, 1940, between the
first and the second defendant, or rather his nominee, the
plaintiff, was still subsisting; and (2) that the plaintiff
was entitled to get a conveyance executed and registered by
the defendant on payment of the consideration money
mentioned in the agreement and in the manner and under the
conditions specified therein.
The suit was resisted by the defendant company who raised a
large number of defences in answer to the plaintiff’s claim,
most of which are not relevant for our present purpose. The
principal contentions raised on behalf of the defendant were
that a suit of this description was not maintainable under
section 42 of the Specific Relief Act and that the plaintiff
had no locus standi to institute the suit. The most
material plea was that the contract of sale stood discharged
by frustration as it became impossible by reason of the
supervening events to perform a material part of it. Bejoy
Krishna Roy did not file any written statement and he was
examined by the plaintiff as a witness on his behalf.
316
The trial judge by his judgment dated 10th October, 1.947,
overruled all the pleas taken by the defendant and decreed
the plaintiff’s suit. An appeal taken by the defendant to
the Court of the District Judge of 24-Parganas was dismissed
on the 25th February, 1949, and the judgment of the trial
court was affirmed. The defendant company thereupon
preferred a second appeal to the High Court which was heard
by a Division Bench consisting ’of Das Gupta and Lahiri JJ.
The only question canvassed before the High Court was,
whether the contract of sale was frustrated by reason of the
requisition orders issued by the Government? The learned
Judges answered this question in the affirmative in favour
of the defendant and on that ground alone dismissed the
plaintiff’s suit. The plaintiff has now come before us on
the strength of a certificate granted by the High Court
under article 133(I)(c) of the Constitution of India.
The learned Attorney General, who appeared in support of the
appeal, has put forward a three-fold contention on behalf of
his client. He has contended in the first place that the
doctrine of English law relating to frustration of contract,
upon which the learned Judges of the High Court based their
Decision has no application to India in view of the
statutory provision contained in section 56 of the Indian
Contract Act. it is argued in the second place, that even if
the English law Applies, it can have no application to
contracts for sale of land and that is in fact the opinion
expressed by the English ,judges themselves. His third and
the last argument is that on the admitted faacts and
circumstances of this case there was no frustrating event
which could be said to have taken away the basis of the
contract or tendered its performance impossible in any sense
of the word.
The first argument advanced by the learned AttorneyGeneral
raises a somewhat debatable point regarding the true scope
and effect of section 56 of the Indian Contract Act and to
what extent, if any, it incorporates the English rule of
frustration of contracts.
317
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 6 of 13
Section 56 occurs in Chapter IV of the Indian Contract Act
which relates to performance of contracts and it purports to
deal with one circumstances under which performance of a,
contract is excused or dispensed with on the ground of the
contract being-void. The section stands as follows:
"An agreement to do an act impossible in itself is void.
A contract to do an act which after the contract is made,
becomes impossible, or, by reason of some event which the
promiser could not prevent, unlawful, becomes void when the
act becomes impossible or unlawful.
Where one person has promised to do something which he knew,
or, with reasonable diligence, might have known, and which
the promisee did not know to be impossible or unlawful, such
promisor must make compensation to such promisee for any
loss which such promise sustains through the non-performance
of the promise".
The first_paragraph of the section lays down the law in the
same way as in England. It speaks of something which is
impossible inherently or by its very nature, and no one can
obviously be directed to an act. The second paragraph
enunciates the law relating to discharge of contract by
reason of supervening impossibility or illegality of the act
agreed to be done. The wording of this paragraph is quite
general, and though the illustrations attached to it are not
at all happy, they cannotderogate from the general words
used in the enactment. This much is clear that the word
"impossible" has not been used here in the sense of physical
or literal impossibility. The performance of an act may not
be literally impossible but it may be impracticbale and
useless from the point of view of the object and purpose
which the parties had in view and if an untoward event or
change of circumstances totally upset the very foundation
upon which the parties rested their bargain, it can very
well be said that the promisor
L/B(D)2SCI-6(a)
318
found it impossible to do the act which he promised to do.
Although various theories have been propounded by the Judges
and jurists in England regarding the juridical basis of the
doctrine of frustration, yet the essential idea upon which
the doctrine is based is that of impossibility of
performance of the contract: in fact impossibility and
frustration are often used as interchangeable expressions.
The changed circumstances, it is said, make the performance
of the contract impossible and the parties are absolved from
the further performance of it as they did not promise to
perform an impossibility The parties shall be excused, as
Lord Loreburn says(1),
"if substantially the whole contract becomes impossible of
performance or in other words impracticable by some cause
for which neither was responsible,."
In Joseph Constantine Steamship Line Limited v. Imperial
Smelting Corporation Ltd.(2), Viscount Maugham obseryed that
the "doctrine of frustration is only a special case of the
discharge of contract by an impossibility of performance
arising after the contract was made." Lord Porter agreed
with this view and rested the doctrine on the same basis.
The question was considered and discussed by a Division
Bench of the Nagpur High Court in Kesari Chand v. Governor-
General in Council(3) and it was held that the doctrine of
frustration comes into play when a contract becomes impossi-
ble of performance, after it is made, on account of circum-
stances beyond the control of the parties. The doctrine is
a special case of impossibility and as such comes under
section 56 of the Indian Contract Act. We are in entire
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 7 of 13
agreement with this view which is fortified by a recent
pronouncement of this court in Ganga Saran v. Ram Charan(4),
where Fazl
(1) See Tamplin Steamship Co. Ltd. v. Anglo-Mexican
Petroleum Products Co. Ltd.[1916] 2 A.C. 397, 403.
(2) [1942] A.C. 154 at 168.
(3) I.L.R. 1949 Nag. 718.
(4) [1952] S.C.R. 36 at 52.
319
Ali J., in speaking about frustration, observed in his
judgment as follows:
"It seems necessary for us to emphasise that so far as the
courts in this country are concerned, they must loot
primarily to the law as embodied in sections 32 and 56 of
the Indian Contract Act, 1872."
We hold, therefore, that the doctrine of frustration is
really an aspect or part of the law of discharge of contract
by reason of supervening impossibility or illegality of the
act agreed to be done and hence comes within the purview of
section 56 of the Indian Contract Act. It would be incorrect
to say that section 56 of the Contract Act applies only to
cases of physical impossibility and that where this section
is not applicable, recourse can be had to the principles of
English law on the subject of frustration. It must be held
also that to the extent that the Indian Contract Act deals
with a particular subject, it is exhaustive upon the same
and it is not permissible to import the principles of
English law dehors these statutory provisions. The
decisions of the English courts possess only a persuasive
value and may be helpful in showing how the courts in
England have decided cases under circumstances similar to
those which have come before our courts.
It seems necessary however to clear up some misconception
which is likely to arise because of the complexities of the
English law on the subject. The law of frustration in
England developed, as is well known, under the guise of
reading implied terms into contracts. The court implies a
term or exception and treats that as part of the contract.
In the case of Taylor v. Caldwell(1), Blackburn J. first
formulated the doctrine in its modern form. The court there
was dealing with a case where a music hall in which one of
the contracting parties had agreed to give concerts on
certain specified days was accidentally burnt by fire. It
was held that such a contract must be regarded "as subject
to an implied condition that the parties shall be excused,
in case, before breach, performance becomes impossible from
perishing of the thing without
(1) 3 B & S. 826.
320
default of. the contractor." Again in Robinson v. Davison(1)
there was a contract between the plaintiff and the
defendant’s wife (as the agent of her husband) that she
should play the piano at a concert to be given by the
plaintifl on a specified day. On the day in question she
was unable to perform through illness. The contract did not
contain any term as to what was to be done in case of her
being too ill to perform. In an action against the
defendant for breach of contract, it was held that the
wife’s illness and the consequent incapacity excused her and
that the contract was in its nature not absolute but
conditional upon her being well enough to perform. Bramwell
B. pointed out in course of his judgment that in holding
that the illness of the defendant incapaciated her from
performing the agreement the court was not really engrafting
a new term upon an express contract. It was not that the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 8 of 13
obligation was absolute in the original agreement and a new
condition was subsequently added to it; the whole question
was whether the original contract was absolute or
conditional and having regard to the terms of the bargain,
it must be held to be conditional.
The English law passed through various stages of development
since then and the principles enunciated in the various
decided authorities cannot be said to be in any way uniform.
In many of the pronouncements of the highest courts in
England the doctrine of frustration was held "to be a device
by which the rules as to absolute contracts are reconciled
with a special exception which justice demands"(2). The
court, it is said, cannot claim to exercise a dispensing
power or to modify or alter contracts. But when an
unexpected event or change of circumstance occurs, the
possibility of which the parties did not circumstance
occurs, the possibility contract is taken to be not what the
parties actual intended, but what they as fair and
reasonable men would presumably have intended and agreed
upon, if having such possibility in view they had made
express provsion as to their rights and liabilities in the
event of such occurrence(1). As Loard Wright
(1) (1871) L.R. 6 Exch. 269.
(2) Vide Hirji Mulji v. Cheong Yue Steamship Co. Ltd.
[1926] A.C. 497 at 510.
(3) Vide Dahl v. Nelson, Donkinand Co. (1881) 6 App. Cas.
38 at 59.
321
observed in Joseph Constantine Steamship Co. v. Imperial
Smelting Corporation Ltd.(1).
"In ascertaining the meaning of the contract and its
application to the actual occurrences, the court has to
decide, not what the parties actually intended but what as
reasonable men they should have intended. The court
personifies for this purpose the reasonable man."
Lord Wright clarified the position still further in the
later case of Denny, Mott and Dickson Ltd. v. James B.
Fraser & Co. Ltd.(1), where he made the following
observations:
"Though it has been constantly said by high authority,
including Lord Sumner, that the explanation of the rule is
to be found in the theory that it depends on an implied con-
dition of the contract, that is really no explanation. It
only pushes back the problem a single stage. It leaves the
question what is the reason for implying a term. Nor can I
reconcile that theory with the view that the result does not
depend on what the parties might, or would, as hard
bargainers, have agreed. The doctrine is invented by the
court in order to supplement the defects of the actual
contract...... To my mind the theory of the implied
condition is not really consistent with the true theory of
frustration. It has never been acted on by the court as a
ground of decision, but is merely stated as a theoretical
explanation."
In the recent case of British Movietonews Ltd. v. London and
District Cinemas Ltd.(1), Denning L. J. in the Court of
Appeal took the view expressed by Lord Wright as stated
above as meaning that "the court really exercises a
qualifying power-a power to qualify the absolute., literal
or wide terms of the contract in order to do what is just
and reasonable in the new situation". "The day is gone,"
(1) [1942] A.C. 154 at 185.
(2) [1944] A.C. 265 at 275.
(3) [1951] 1 K. B. 190.
L/ B(D) 2SCI-7
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 9 of 13
322
the learned Judge went on to say, "when we can excuse an
unforeseen injustice by saying to the sufferer ’it is your
own folly, you ought not to have passed that form of words.
You ought to have put in a clause to protect yourself’. We
no longer credit a party with the foresight of a Prophet or
his lawyer with the draftsmanship of a Chalmers. We realise
that they have their limitations and make allowances accor-
dingly. It is better thus. The old maxim reminds us that
he who clings to the letter clings to the dry and barren
shell and misses the truth and substance of the matter. We
have of late paid heed to this warning, and we must pay like
heed now."
This decision of the Court of Appeal was reversed by the
House of Lords and Viscount Simon in course of his judgment
expressed disapproval of the way in which the law was stated
by Denning L.J. It was held that there was no change in the
law as a result of which the courts could exercise a wider
power in this regard than they used to do previously. "The
principle remains the same", thus observed his Lordship.
"Particular applications of it may greatly vary and
theoretical lawyers may debate whether the rule should be
regarded as arising from implied term or because the basis
of the contract no longer exists. In any view, it is a
question of construction as Lord Wright pointed out in
Constantine’s case and as has been repeatedly asserted by
other masters of law."(1)
These differences in the way of formulating legal theories
really do not concern us so long as we have a statutory
provision in the Indian Contract Act. In deciding cases in
India the only doctrine that we have to go by is that of
supervening impossibility or illegality as laid down in
section 56 of the Contract Act taking the word "Impossible"
in its practical and not literal sense. It must be borne in
mind, however, that section 56 lays down a rule of positive
law and does not leave the matter to be determined according
to the intention of the parties.
(1) [1952] A.C. 166 at 184.
323
In the latest decision of the House of Lords referred to
above, the Lord Chancellor puts the whole doctrine upon the
principle of construction. But the question of construction
may manifest itself in two totally different ways. In one
class of cases the question may simply be, as to what the
parties themselves had actually intended and whether or not
there as a condition in the contract itself, express or
implied, which operated, according to the agreement of the
Parties themselves to release them from their obligations;
this would be a question of construction pure and simple and
the ordinary rules of construction would have to be applied
to find out what the real intention of the parties was.
According to the Indian Contract Act, a promise may be
express or implied(1). In cases, therefore, where the court
gathers as a matter of construction that the contract itself
contained impliedly or expressly a term, according to which
it would stand discharged on the happening of certain
circumstances the dissolution on of the contract would take
place under the terms of the contract itself and such cases
would be outside the purview of section 56 altogether.
Although in English law these cases are treated as cases of
frustration, in India they would be dealt with under section
32 of the Indian Contract Act which deals with contingent
contracts or similar other provisions contained in the Act.
In the large majority of cases however the doctrine of
frustration is applied not on the ground that the parties
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 10 of 13
themselves agreed to an implied term which operated to
release them from the performance of the contract. The
relief is given by the court on the ground of subsequent
impossibility when it finds that the whole purpose or basis
of a contract was frustrated by the intrusion or occurrence
of an unexpected event or change of circumstances which was
beyond what was contemplated by the parties at the time when
they entered into the agreement. Here there is no question
of finding out an implied term agreed to by the parties em-
bodying a provision for discharge, because the parties did
not think about the matter at all nor could possibly have
any intention regarding it. When such an event or change of
(1) Vide section 9.
L/B(D)2SCI-7(a)
324
circumstance occurs which is so fundamental as to be re-
garded by law as striking at the root of the contract as a
whole, it is the court which can pronounce the contract to
be frustrated and at an end. The court undoubtedly has to
examine the contract and the circumstances under which it
was made. The belief, knowledge and intention of the
parties are evidence, but evidence only on which the court
has to form its own conclusion whether the changed cir-
cumstances destroyed altogether the basis of the adventure
and its underlying object(1). This may be called a rule of
construction by English Judges but it is certainly not a,
principle of giving effect to the intention of the parties
which underlies all rules of construction. This is really a
rule of positive law and as such comes within the purview of
section 56 of the Indian Contract Act.
It must be pointed out here that if the parties do con-
template the possibility of an intervening circumstance
which might affect the performance of the contract, but
expressly stipulate that the contract would stand despite
such circumstances, there can be no case of frustration
because the basis of the contract being to demand
performance despite the happening of a particular event, it
cannot disappear when that event happens. As Lord Atkinson
said in Matthey v. Curling(1), "a person who expressly
contracts absolutely to do a thing not naturally impossible
is not excused for nonperformance because of being prevented
by the act of God or the King’s enemies......... or vis
major". This being the legal position, a contention in the
extreme form that the doctrine of frustration as recognised
in English law does no come at all within the purview of
section 56 of the Indian Contract Act cannot be accepted..
The second contention raised by the Attorney General can be
disposed of in few words. It is true that in England the
judicial opinion generally expressed is, that the doctrine
of frustration does not operate in the case of contracts for
(1) Vide Morgan v. Manser (1947] 2 AU E.R. 666.
(2) [1922] 2 A.C. 180 at 234.
325
sale of land(1). But the reason underlying this view is
that under the English law as soon as there is a concluded
contract by A to sell land to B at certain price, B becomes
in equity, the owner of the land, subject to his obligation
to pay the purchase money’. On the other hand, A in spite
of his having the legal estate holds the same in trust for
the purchaser and whatever rights he still retains in the
land are referable to his right to recover and receive the
purchase money. The rule of frustration can only put an end
to purely contractual obligations, but it cannot destroy an
estate in land which has already accrued in favour of a
contracting party. According to the Indian law, which is
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 11 of 13
embodied in section 54 of the Transfer of Property Act, a
contract for sale of land does not of itself create any
interest in the property which is the subject-matter of the
contract. The obligations of the parties to a contract for
sale of land are, therefore, the same as in other ordinary
contracts and consequendy there is no conceivable reason why
the doctrine of frustration should not be applicable to
contracts for sale of land in India. This contention of the
Attorney General must, therefore, fail.
We now come to the last and most important point in this
case which raises the question as to whether, as a result of
the requisition orders, under which the lands comprised in
the development scheme of the defendant company were
requisitioned by Government, the contract of sale between
the defendant company and the plaintiff’s predecessor stood
dissolved by frustration or in other words became impossible
of performance.
It is well settled and not disputed before us that if and
when there is frustration the dissolution of the contract
occurs automatically. It does not depend, as does
rescission of a contract on the ground of repudiation or
breach, or on the choice or election of either party. It
depends on the effect
(1) Vida Billington Estates Co. v. Stonfield Estate Ltd.
[1952] 1 All E.R.853.
326
of what has actually happened on the possibility of
performing the contrat (1). What happens generally in such
cases and has happened here is that one party claims that
the contract has been frustrated while the other party
denies it. The issue has got to be decided by the court "ex
post facto, on the actual circumstances of the case"(2).
We will now proceed to examine the nature and terms of the
contract before us and the circumstances under which it was
entered into to determine whether or not the disturbing
element,which is allowed to have happened here, has
substantially prevented the performance of the contract as a
whole.
It may be stated at the outset that the. contract before
us cannot be looked upon as an ordinary contract for sale
and purchase of a piece of land; it is an integral part of a
development scheme started by the defendant company and is
one of the many contracts that have been entered into by a
large number of persons with the company. The object of the
company was undoubtedly to develop a fairly extensive area
which was still undeveloped and make it usable for
residential purposes by making roads and constructing drains
through it. The purchaser. on the other hand, wanted the
land in regard to which he entered into the contract to be
developed and make ready for building purposes before he
could be called upon to complete the purchase. The most
material thing which deserves notice is, that there is abso-
lutely no time limit within which. the roads and drains are
to be made. The learned District Judge of Alipore, who
heard the appeal, from the trial court’s judgment found it
as a fact, on the evidence in the record, that there was not
an understanding between the parties on this point. As a
matter of fact, the first requisition order was passed
nearly 15 months after the contract was made and apparently
no work was done by the defendant company in the meantime.
Another important thing that requires notice in this con
(1) Per Lord Wright in Denny, Mott and Dicksom Ltd. v.
Jameso B. Fraser and Co., Ltd. [1944] A.C. 265, 274,
(2) Ibid.
327
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 12 of 13
nection is that the war was already on, when the parties
entered into the contract. Requisition orders for taking
temporary possession of lands for war purposes were normal
events during this period. Apart from requisition orders
there were other difficulties in doing construction work at
that time because of the scarcity of materials and the
various restrictions which the Government had imposed in
respect of them. That there were certain risks and
difficulties involved in carrying on operations like these,
could not but be in the contemplation of the parties at the
time when they entered into the contract, and that is
probably the reason why no definite time limit was mentioned
in the contract within which the roads and drains are to be
completed. This was left entirely to the convenience of the
company and as at matter of fact the purchaser did not feel
concerned about it. It is against this background that we
are to consider to what extent the passing of the
requisition orders affected the performance of the contract
in the present case.
The company, it must be admitted, bad not commenced the
development work when the requisition order was passed in
November, 1941. There was no question, therefore, of any
work or service being interrupted for an indefinite period
of time. Undoubtedly the commencement of the work was
delayed but was the delay going to be so great and of such a
character that it would totally upset the basis of the
bargain and comercial object which the parties had in view?
The requisition orders, it must be remembered, were’ by
their very nature, of a temporary character and the
requisitioning authorities could, in law, occupy the
position of a licensee in regard to the requisitioned
property. The order might continue during the whole period
of the war and even for some time after that or it could
have been withdrawn before the war terminated. If there was
a definite time limit agreed to by the parties within which
the construction work was to be finished, it could be said
with perfect propriety that delay for an indefinite period
would
328
make the performance of the contract impossible within the
specified time and this would seriously affect the object
and purpose of the venture. But when there is no time limit
whatsoever in the contract, nor even an understanding bet-
ween the parties on that point and when during the war the
parties could naturally anticipate restrictions of various
kinds which would make the carrying on of these operations
more tardy and difficult than in times of peace, we do not
think that the order of requisition affected the fundamental
basis upon which the agreement rested or struck at the roots
of the adventure.
The learned Judges of the High Court in deciding the case
against the plaintiff relied entirely on the time factor.
It is true that the parties could not contemplate an
absolutely unlimited period of time to fulfil their
contract. They might certainly have in mind a period of
time which was reasonable having regard to the nature and
magnitude of the work to be done as well as the conditions
of war prevailing at that time. Das Gupta, J., who
delivered the judgment of the High Court, says first of all
that the company had in contemplation a period of time not
much exceeding 2 or 3 years as the time for performance of
the contract; the purchaser also had the same period of time
in contemplation. The learned Judge records his finding on
the point in the following words:
"My conclusion on a consideration of the surrounding
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 13 of 13
circumstances of the contract is that the parties
contemplated that the roads and drains would be constructed
and the conveyance would be completed in the not distant
future."
This finding is inconclusive and goes contrary to what
has been held by the District Judge who was undoubtedly the
last court of facts. In our opinion, having regard to the
nature and terms of the contract, the actual existence of
war conditions at the time when it was entered into, the
extent of the work involved in the development scheme and
last though not the least the total absence of any definite
period of time agreed to by the parties within which the
work was
329
to be completed, it cannot be said that the requisition
order vitally affected the contract or made its performance
impossible.
Mr. Gupta, who appeared for the respondent company. put
forward an alternative argument that even if the performance
of the contract was not made impossible. it certainly became
illegal as a result of the requisition order and con-
sequently the contract became void under section 56 of the
Indian Contract Act as soon as the requisition order was
made. In support of his contention the learned counsel
placed reliance upon certain provisions of the Defence of
India Rules and also upon illustration (d) to section 56 of
the Contract Act. All that the Defence Regulations show is
that the violation of a requisition order could be punished
as a criminal offence. But no matter in whichever way the
requisition order could be enforced, in substance it did
nothing else but impose a prohibition on the use of the land
during the period that it remained in force. The effect of
such prohibition on the performance of the contract, we have
discussed above, and we do not think that the mere fact that
the requisition order was capable of being enforced by a
criminal sanction made any difference in this respect. In
any view this question was not raised in any of the courts
below and has not been indicated even in the respondent’s
statement of the case. We do not think that it would be
proper to allow this question to be raised for the first
time before us, as it requires consideration of the
different provisions of the Defence of India Act and also of
the implication of illustration (d) appended to section 56
of the Contract Act. In our opinion, the events which have
happened here cannot be said to have made the performance of
the contract impossible and the contract has not been
frustrated at all. The result is that the appeal is
allowed, the judgment and decree of the High Court of
Calcutta are set aside and those of the courts below
restored. The plaintiff will have his costs in all the
courts.
Appeal allowed.
Agent for the appellant: S. C. Banerjee.
Agent for the respondent No. I : R. R. Biswas.
330