Full Judgment Text
Reportable
IN THE SUPREME COURT OF INDIA
CIVIL ORIGINAL JURISDICTION
IA No 68608 of 2023
in
Suo Moto Writ (Civil) No 2 of 2019
In Re: Felling of Trees in Aarey Forest (Maharashtra)
J U D G M E N T
Dr Dhananjaya Y Chandrachud, CJI
1
1 Mumbai Metro Rail Corporation Limited seeks a clarification of the order of this
Court dated 29 November 2022. By the order of this Court, MMRCL was
permitted to move the Tree Authority for felling 84 trees. MMRCL submits that
177 trees have to be felled or, as the case may be, transplanted for the Metro
Car Shed Land at Aarey Colony admeasuring approximately 33 hectares for
Mumbai Metro Line-3. Permission is hence sought to implement the permission
which has been granted on 15 March 2023 by the Superintendent of Gardens of
the Municipal Corporation of Greater Mumbai for felling 124 trees and
transplanting 53 trees.
Signature Not Verified
Digitally signed by
Sanjay Kumar
Date: 2023.04.19
14:32:59 IST
Reason:
1 “MMRCL”
1
2 By the order of this Court dated 29 November 2022, an earlier order directing
the preservation of the status quo on felling trees was modified, so as to permit
MMRCL to move the Tree Authority on its application for felling 84 trees.
Following the order of this Court, an application was initially moved on 19
December 2022 for permission to fell 84 trees. On 2 January 2023, MMRCL,
however, sought permission to cut 185 trees, without moving this Court.
3 By a communication dated 20 December 2022, the Deputy Superintendent of
Gardens intimated the Deputy General Manager (Depot) of MMRCL that the site
was jointly inspected by his staff, together with the representatives of MMRCL on
19 December 2022. Following the inspection, the Deputy Superintendent of
Gardens sought compliance on the following aspects:
“1. Submit updated proposal for the current status of trees
as per a fresh survey.
2. Mention missing/dead/fallen trees and also any new
addition to the list of affected trees as a long period has
lapsed since the last survey.
3. Number all such trees on the sites with black and white
paint;
4. Submit details of land where the trees are to be proposed
for transplantation and compensatory plantation.”
4 On 12 January 2023, the Superintendent of Gardens issued a public notice
indicating that 185 trees would be affected of which 124 trees would be felled
and 53 trees would be transplanted.
2
5 Since the action proposed was in excess of the 84 trees which were permitted to
2
be felled by the order of this Court, a public interest litigation was moved before
the High Court of Judicature at Bombay. The Division Bench, by its order dated 9
March 2023, observed:
“Public Notice has been issued by the Tree Authority. The
Petitioner has already raised objection before the Tree Authority.
The Petitioner can bring it to the notice of the Tree Authority,
the order of the Apex Court. No final order has been passed by
the Tree Authority. It is for the Tree Authority to consider
whether those trees beyond 84 were shrubs or otherwise.”
6 On 15 March 2023, the Superintendent of Gardens and Tree Officer granted
permission for felling 124 trees and transplanting 53 trees, subject to the
condition that 1533 trees would be planted on the property. This led to the
3
institution of another public interest litigation before the High Court. The
Division Bench, by its order dated 31 March 2023, observed and, in our view,
correctly, that this Court had granted permission to move the Tree Authority only
to the extent of 84 trees. Hence, the permission which was granted in respect of
177 trees was beyond the permission granted by this Court on 29 November
2022. The High Court held that propriety would require that trees shall not be
felled in pursuance of the order dated 15 March 2023 until a clarification was
sought from this Court. It is in view of the above factual background, that the
application for clarification has been filed by MMRCL.
2 “Public Interest Litigation (L) No 2169 of 2023
3 Public Interest Litigation (L) No 8655 of 2023
3
7 We have heard Mr Tushar Mehta, Solicitor General appearing on behalf of
MMRCL, Mr Dhruv Mehta, senior counsel appearing on behalf of the Municipal
Corporation, and Mr C U Singh and Mr Gopal Sankaranarayanan, senior counsel
appearing on behalf of the respondents.
8 At the outset, the Court must take notice of the fact that when the order dated
29 November 2022 was passed, it was on the specific request of MMRCL that it
should be permitted to pursue its application before the Tree Authority for
permission to fell 84 trees for the purpose of the work of the ramp. The Court
modified the earlier order of status quo which held the field, to the above extent.
If the number of trees that are required to be felled was in excess of the
permission which was granted by this Court, to move the Tree Authority to fell 84
trees, propriety required that an application had to be moved before this Court
for its permission and for modification of its order dated 29 November 2022.
Instead, it appears from the record that though initially the application was
made for felling 84 trees, subsequently, a stand was adopted that actual number
of trees would be in excess of what was originally envisaged.
9 As a matter of fact, it would be necessary to refer to the affidavit which was filed
by the Chief Project Manager of MMRCL before the High Court of Judicature at
Bombay in which the following averments were incorporated:
“24) In the aforesaid and such other relevant background of
facts, in the humble submission of this Respondent, the
number of trees that are required to be felled is an
aspect which is incidental to the proposal which is
pending for consideration before the first Respondent in
respect of which the Hon’ble Supreme Court has granted
liberty to the present Respondent to pursue, which is
4
being done by the present Respondent. I therefore say
that not permitting the answering Respondents to
prosecute the present application in issue covering more
number of trees over and above the number of trees
incidentally mentioned in the aforesaid order of the
Hon’ble Supreme court, in fact would amount to
frustrating the said order and/or preventing its
implementation in its true letter and spirit.
*
26) I hasten to state that if the contention of the Petitioner is
accepted that will in fact amount to causing impediment
in the effective implementation of the order of the
Hon’ble Supreme Court. At this juncture, it also will be
apposite to consider the well settled principle of law that
the Judgment of the Hon’ble Supreme Court and/or of
this Hon’ble Court cannot be read as a statute. I say
that the Petitioner wants this Hon’ble Court to read the
order of the Hon’ble Supreme Court as a statute, which
is impermissible.”
10 The above averments in the affidavit which was filed by MMRCL indicate that it
was well aware of the fact that the order of this Court continued to operate.
MMRCL sought to justify its application for felling of trees in excess of what was
permitted by the specific directions of this Court. Such an exercise was clearly
not contemplated in the order of this Court. We are constrained to observe that
MMRCL has made an attempt to overreach the jurisdiction of this Court.
11 The issue which, however, needs to be considered in the application for
clarification is whether permission should be granted in terms of the order which
has been passed by the Superintendent of Gardens.
12 In the IA for clarification, it has been submitted that subsequent to the order of
29 November 2022, a joint inspection took place on 19 December 2022 between
the officers of the Municipal Corporation and MMRCL since a period of
5
approximately three years and ten months covering four monsoon seasons had
elapsed from the date of the previous inspection which took place on 20 March
2019. It has been stated that in the course of the joint inspection, it was found
that some trees were “missing/dead/fallen” and additional plants and trees had
grown since the date of the previous inspection. Hence, it has been sought to be
urged that the updated number of affected trees were estimated at 185,
pursuant to which a public notice notice was issued by the Tree Authority on 12
January 2023.
13 The Solicitor General, while adverting to the contents of the IA, also submitted
that a compilation of relevant documents was placed on the record of this Court
on 5 April 2023.
14 On the other hand, it has been submitted by Mr C U Singh and Mr Gopal
Sankaranarayanan that a survey was conducted in 2020 and, as a matter of fact,
it was based on the survey that MMRCL had sought permission to prune a certain
number of trees and to fell 84 trees. Senior counsel submitted that this Court
permitted MMRCL to move the Tree Authority specifically with reference to the
proposal for 84 trees. In other words, it has been urged before this Court that
the fresh proposal which was made before the Tree Authority after the order of
this Court dated 29 November 2022 was clearly not bona fide having due regard
to the events which had transpired, resulting in the order of this Court.
15 It was improper on the part of MMRCL to move the Tree Authority for the felling
of any trees in excess of 84 trees. If circumstances had transpired which led to a
variation in the number of trees to be cut, the only correct course of action
6
would have been to move this Court. We are, hence, of the view that it would be
necessary for the Court to penalize MMRCL for its conduct. Having said that, the
issue is as to whether the permission which has been granted on 15 March 2023
should be stayed by the Court, at the present stage. Any such direction will
have the consequences of bringing the public project to a standstill. Such a
course of action would not be desirable. As the Court noted in its previous order,
substantial steps have already been taken by felling over 2000 trees for the
purpose of the project. In this backdrop, we modify the previous order by
permitting MMRCL to act in compliance with the order dated 15 March 2023.
However, this shall be subject to the following directions:
(i) MMRCL shall, within a period of two weeks, deposit an amount of
Rupees Ten Lakhs with the Conservator of Forests;
(ii) The Conservator of Forests shall ensure that all directions which
have been contained in the previous orders of the Tree Authority for
afforestation have been duly complied with;
(iii) The Conservator of Forests shall submit a report before this Court
indicating the status of compliance in regard to the directions which
have been issued up-to-date for afforestation and for
transplantation of trees; and
(iv) In order to enable this Court to have objective assistance in regard
to the compliance of the directions for afforestation, we request the
Director of IIT Bombay to depute a team for the purpose of verifying
7
compliance. A report shall accordingly be submitted before this
Court within a period of four weeks. The costs, charges and
expenses payable shall be borne by MMRCL.
16 The IA is accordingly disposed of.
..…..…....…........……………….…........CJI.
[Dr Dhananjaya Y Chandrachud]
…..…..…....…........……………….…........J.
[Pamidighantam Sri Narasimha]
…..…..…....…........……………….…........J.
[J B Pardiwala]
New Delhi;
April 17, 2023
-S-
8
ITEM NO.8 COURT NO.1 SECTION PIL-W
S U P R E M E C O U R T O F I N D I A
RECORD OF PROCEEDINGS
IA 68608/2023 in SMWP (Civil) No.2/2019
IN RE: FELLING OF TREES IN AAREY FOREST (MAHARASHTRA)
(IA No. 68608/2023 - CLARIFICATION)
Date : 17-04-2023 This application was called on for hearing today.
CORAM :
HON'BLE THE CHIEF JUSTICE
HON'BLE MR. JUSTICE PAMIDIGHANTAM SRI NARASIMHA
HON'BLE MR. JUSTICE J.B. PARDIWALA
For Petitioner(s)
By Courts Motion, AOR
For Respondent(s) Mr. Tushar Mehta, Sr. Adv.
Mr. Chirag Shah, Adv.
Ms. Rukhmini Bobde, Adv.
Ms. Soumya Priyadarshinee, Adv.
Mr. Ankit Ambasta, Adv.
Mr. Amit Kumar Shrivastava, Adv.
Mr. Amlaan Kumar, Adv.
Mr. Vishal Prasad, AOR
Mr. Shyam Divan, Sr. Adv.
Mr. Gopal Sankaranarayan, Sr. Adv.
Ms. Pooja Dhar, AOR
Mr. Tushad Kakalia, Adv.
Mr. Sudipto Sarkar, Adv.
Ms. Aditi Gupta, Adv.
Mr. Dhruv Mehta, Sr. Adv.
Mr. Ashish Wad, Adv.
Mr. Sandip Patil, Adv.
Mr. Sidharth Mahajan, Adv.
Mr. Ajeyo Sharma, Adv.
Mr. Shyam Agarwal, Adv.
M/S. J S Wad And Co, AOR
9
Mr. Maninder Singh, Sr. Adv.
Mr. Siddharth Dharmadhikari, Adv.
Mr. Aaditya Aniruddha Pande, AOR
Mr. Bharat Bagla, Adv.
Mr. Sourav Singh, Adv.
Mr. Shree Pal Singh, AOR
Mr. C.U. Singh, Sr. Adv.
Ms. Anitha Shenoy, Adv.
Ms. Srishti Agnihotri, AOR
Ms. Sanjana Thomas, Adv.
UPON hearing the counsel the Court made the following
O R D E R
The IA is disposed of in terms of the signed reportable judgment.
(SANJAY KUMAR-I) (SAROJ KUMARI GAUR)
DEPUTY REGISTRAR ASSISTANT REGISTRAR
(Signed reportable judgment is placed on the file)
10