Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 13
CASE NO.:
Appeal (civil) 2440 of 2007
PETITIONER:
M/s. Gas Authority of India Ltd. and anr
RESPONDENT:
M/s. Keti Construction (I) Ltd. and ors
DATE OF JUDGMENT: 11/05/2007
BENCH:
G.P. Mathur & Lokeshwar Singh Panta
JUDGMENT:
J U D G M E N T
CIVIL APPEAL NO. 2440 OF 2007
(@ Special Leave Petition (Civil) No.11391 of 2005)
G.P. Mathur, J.
Leave granted.
2. This appeal, by special leave, has been preferred against the
judgment and order dated 7.12.2004 of a Division Bench of Delhi
High Court by which the appeal filed by M/s Keti Construction (I)
Ltd. - Contractor (Respondent No.1 herein) under Section 37 of the
Arbitration and Conciliation Act, 1996 (hereinafter referred to as ’the
Act’) was allowed and the judgment and order dated 20.10.2003 of a
learned Single Judge by which the petition filed by respondent no.1
under Section 34 of the Act was dismissed, was set aside and the
award given by the arbitrator (respondent no.2 in the present appeal)
on 19.4.2000, was also set aside. It was further directed that Brig.
Nardip Singh (Retd.) who was appointed by respondent no.1 shall
proceed with the arbitration in accordance with law and give the
award.
3. Gas Authority of India \026 (GAIL, appellant no.1 herein) awarded
four contracts for its project at Petro-Chemical Complex, Dibiyapur,
District Etawah (U.P.) to M/s Keti Construction (I) Ltd., Indore \026
(Contractor), which is arrayed as respondent no.1 in the present
appeal. All the four contracts were awarded in the year 1995 and
they related to construction of certain types of houses for GAIL Vihar
Township, pre-mix bitumen carpeting and repair of roads in GAIL
Vihar Colony, construction of external sewerage line and construction
of certain residential quarters in UPPC Complex, Dibiyapur. Certain
disputes arose between the parties regarding completion of the
construction work in accordance with the design and cost of
construction, etc. The contracts entered into between the parties
contained arbitration clause. Appellant no.1 referred the dispute with
regard to contract dated 28.9.1995 for arbitration to Justice N.N.
Goswami (Retd.) who was formerly a Judge of Delhi High Court.
The arbitrator gave a ’no claim award’ on 19.4.2000. Respondent
no.1 filed a petition under Section 34 of the Act in the Delhi High
Court for setting aside the award. A learned Single Judge who heard
the petition, after detailed discussion of the material on record, found
that the petition was devoid of merits and accordingly dismissed the
same by the judgment and order dated 20.10.2003. Respondent no.1
then preferred an appeal before the Division Bench of the High Court
under Section 37 of the Act which allowed the same by the judgment
and order dated 7.12.2004 and set aside the award of the arbitrator. It
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 13
was further directed in the order that parties shall appear before Brig.
Nardip Singh (Retd.) who had been nominated as arbitrator by
respondent no.1 (contractor) and he shall proceed in accordance with
law and give the award.
4. The principal ground on which the petition under Section 34 of
the Act had been filed by respondent no.1 was that it had invoked the
arbitration clause by sending a notice to appellant no.1 on 17.7.1999
and accordingly the appellant no.1 was required to send a panel of
three names for arbitration within 30 days of receipt of notice. Since
appellant no.1 did not respond to the notice and did not send a panel
within 30 days, it forfeited its right to nominate a panel and thereafter
respondent no.1 sent its own panel on 28.10.1999. Appellant no.1
again did not make any response and did not choose anyone from the
panel nominated by respondent no.1 and accordingly it informed
appellant no.1 on 10.12.1999 that it had selected Brig. Nardip Singh
(Retd.) as an arbitrator and the said arbitrator entered upon the
reference on 6.1.2000. Appellant no.1 appointed Justice N.N.
Goswami (Retd.) as an arbitrator subsequently on 13.1.2000 which
appointment was not valid being contrary to the terms of the
agreement entered into between the parties. Respondent no.1 thus
submitted that the appointment of Justice N.N. Goswami (Retd.) was
invalid and the award given by him was liable to be set aside in view
of Section 34(2)(v) of the Act.
5. The petition was contested by the appellants on the grounds,
inter alia, that appellant no.1 had already sent a panel of three names
on 16.2.1999 in which the name of Justice N.N. Goswami (Retd.) was
mentioned at serial no.1 and it was mentioned that disputes between
the parties relating to all the contracts be resolved by the same
arbitrator. In reply to the notice of respondent no.1, the appellants’
advocate Mr. Sushil Chauhan had sent a reply on 31.7.1999 asking to
choose any one from the said panel. This was again reiterated by a
letter dated 15.11.1999 when respondent no.1 sent its own panel on
28.10.1999. The appointment of Brig. Nardip Singh (Retd.) as an
arbitrator made by respondent no.1 which was communicated by its
letter of 10.12.1999 was challenged by appellant no.1 by sending a
letter dated 31.12.1999 and a letter was also sent in this regard to Brig.
Nardip Singh (Retd.) to desist from proceeding with arbitration. It
was further submitted that respondent no.1 did not challenge the
jurisdiction of the arbitrator appointed by appellant no.1 in accordance
with Section 16 of the Act. The contractor did not at all appear before
the arbitrator appointed by appellant no.1, viz. Justice N.N. Goswami
(Retd.) and did not submit any statement of claim. In these
circumstances, there was no ground for setting aside the award made
by Justice N.N. Goswami (Retd.) on 19.4.2000 and the petition under
Section 34 of the Act filed by respondent no.1 was liable to be
dismissed.
6. We have heard Mr. Mohan Parasaran, Additional Solicitor
General for the appellant and Mr. P.C. Markanda, Senior Advocate for
respondent no.1 and have perused the record.
7. Gas Authority of India (appellant no.1 herein) awarded four
contracts to M/s Keti Construction (I) Ltd. (respondent no.1 herein)
for various construction work at its Petro-Chemical Complex,
Dibiyapur, District Itawah (U.P.) which were as follows :-
"(A) Work Order No. CE/AUR/Ph-II Extn. B. Works/
97A/95 dated 26.5.95: Balance work of
construction of C-6 and D-2 Houses at GAIL
Vihar Township, Dibiyapur;
(B) Work Order No. CE/115/Auriaya/Gail/Gail Vihar
Road Work/95 dated 10.2.95: Construction of
premix bitumen carpeting and repairs of roads in
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 13
Gail Vihar Colony and Compressor station;
(C) Work Order No. CE/137/Auriaya/Ext/SER/95
dated 1.11.95: Construction of external sewerage
line at UPPC Nagar, Dibiyapur; and
(D) Work Order No. CE/136/Auriaya/Housing/95
dated 28.9.95: Construction of residential quarters
Type A-25 units, Type B-105 units, Type C-55
units for UPPC Complex, Dibiyapur."
8. The dispute here pertains to contract no. (D) dated 28.9.1995.
Clause 107 of the agreement, which is relevant for the controversy in
dispute reads as follows :
"107.1 All disputes or differences whatsoever which
shall at any time arise between the parties hereto
touching or concerning the WORKS or the execution or
maintenance thereof of this CONTRACT or the rights
touching or concerning the WORKS or the execution
effect thereof or to the rights or liabilities or the
construction meaning operation or effect whether during
or after completion of the CONTRACT or whether
before or after determination, foreclosure or breach of the
CONTRACT (other than those in respect of which the
decision of any person is by the CONTRACT expressed
to be final and binding) shall after written notice by
either party to the CONTRACT to the other of them and
to the Appointing Authority hereinafter mentioned be
referred for adjudication to a sole arbitrator to be
appointed as hereinafter provided.
107.2 For the purpose of appointing the sole arbitrator
referred to above, the Appointing Authority will send
within thirty days of the receipt of the notice to the
CONTRACTOR, a panel of three persons who shall all
be presently unconnected with the organization for which
the WORK is executed.
The CONTRACTOR shall on receipt of the names,
as aforesaid, select any one of the persons named to be
appointed as a sole Arbitrator and communicate his name
to the Appointing Authority within thirty days of receipt
of names. The Appointing Authority shall thereupon
without any delay appoint the said person as the sole
arbitrator. If the CONTRACTOR fails to communicate
such selection as provided above within the period
specified, the Appointing Authority shall make the
selection and appoint the selected as the Sole Arbitrator.
If the Appointing Authority fails to send to the
CONTRACTOR the panel of three names as aforesaid
within the period specified, the CONTRACTOR shall
send the Appointing Authority a panel of three names of
persons who shall all be unconnected with either party.
The Appointing Authority shall on receipt of the names
as aforesaid select any one of the persons named and
appoint him as the sole arbitrator. If the Appointing
Authority fails to select the person and appoint him as the
sole Arbitrator within 30 days of the receipt of the panel
and inform the CONTRACTOR accordingly, the
CONTRACTOR shall be entitled to appoint one of the
persons from the panel as the sole arbitrator and
communicate his name to the Appointing Authority.
If the Arbitrator so appointed is unable to or
unwilling to act or resigns his appointment or vacates his
office due to any reason whatsoever, another sole
arbitrator shall be appointed as aforesaid.
The WORK under the CONTRACT shall,
however, continue during the Arbitration proceedings
and no payment due or payable to the CONTRACTOR
shall be withheld on account of such proceedings.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 13
The Arbitrator shall be deemed to have entered on
the reference on the date he issues notice to both the
parties fixing the date of the first hearing.
The Arbitrator may, from time to time, with the
consent of the parties, enlarge the time for making and
publishing the award.
The venue of the arbitration shall be New Delhi.
The fees, if any, of the Arbitrator shall, if required
to be paid before the award is made and published, be
paid half AND half by each of the parties. The costs of
the reference and of the award including the fees, if any,
of the Arbitrator shall be in the discretion of the
Arbitrator who may direct to and by whom and in what
manner, such costs or any part thereof shall be paid and
may fix or settle the amount of costs to be so paid.
The award of the Arbitrator shall be final and
binding on both the parties.
Subject to aforesaid the provisions of the
Arbitration Act, 1940 or any statutory modification or re-
enactment thereof and the rules made thereunder, and for
the time being in force, shall apply to the arbitration
proceedings under this clause."
A perusal of clause 107 would show that on a dispute being
raised by the contractor, the appointing authority was required to send
a panel of three names to the contractor and he was entitled to select
anyone of them as sole arbitrator and to communicate his decision to
the appointing authority within 30 days. Thereafter, the appointing
authority was under an obligation to appoint the said person as sole
arbitrator. However, if the appointing authority failed to send the
panel of three names within the stipulated period, the contractor was
given the option to send a panel of three names to appellant no.1,
which was required to select anyone of them and communicate the
said fact within 30 days.
9. The plea taken by respondent no.1 is that the completion
certificate with regard to the work in dispute was issued on 24.1.1998
and it wrote several times for settling the accounts. It invoked the
arbitration clause on 17.7.1999 by sending a letter to the appointing
authority to send a panel but as there was no response, it sent its own
panel of three names on 28.10.1999 and finally informed vide letter
dated 10.12.1999 that it had nominated Brig. Nardip Singh (Retd.) as
the arbitrator. Voluminous correspondence was exchanged between
the parties and many such letters were placed on record before the
learned Single Judge of the High Court. It appears that some dispute
had been raised by respondent no.1 regarding balance work of
construction of C-6 and D-2 numbers of houses at GAIL Vihar
Township at Dibiyapur and a letter had been sent by it to appellant
no.1 on 16.1.1999. A reply was given on behalf of appellant no.1 to
respondent no.1 on 16.2.1999, relevant part of which reads as under :-
"Sir,
This has reference to your letter vide ref.
no.IND.KT.44(6)/99 DATED 16/1/99, we would like to
bring to your kind notice that you have not so far
informed us the nature of disputes you want to refer for
resolution by the Arbitrator.
However, in the meantime, we are suggesting you
a panel of three persons to select one of them as Sole
Arbitrator :
1. Mr. Justice N.N. Goswami
Retd. Judge Delhi High Court
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 13
2. Dr. Avtar Singh
Professor of Law
3. Mr. Harish Chandra
Director General CPWD (Retd.) & Ex.
Member UPSC
Further, it is suggested to appoint the same
Arbitrator and to club the Arbitration proceedings in both
the matters so as to reduce on cost and time incurred in
the said Arbitration.
Accordingly, you are called upon to select any one
of the above named persons as Sole Arbitrator in both the
matters."
10. The evidence on record shows that in connection with the
dispute with regard to all the four contracts several meetings had
taken place in the office of GAIL also and in the office of their
consultant, M/s C.P. Kukreja & Associates in which the
representatives of respondent no.1 had participated. This fact is not
in dispute that several meetings did take place to resolve the dispute
regarding all the four contracts between the representatives of
appellant no.1 and respondent no.1. The Senior Manager (Civil) of
appellant no.1 sent a letter dated 15.11.1999 to respondent no.1 which
has considerable bearing on the controversy in hand and, therefore,
the same is being reproduced below :-
"Ref.:CE/GAIL/99 November 15, 1999
M/s Keti Constructions (I) Ltd.
31/6, Sneh Nagar, Main Road
Opp. Sapna Sangeeta Theatre
Indore (MP).
SUBJECT : DISPUTES RELATING TO :
(A) WORK ORDER NO.: CE/AUR/PH-II EXTN. B.
WORKS/97A/95 DATED 26.05.95.
BALANCE WORK OF CONSTRUCTION OF
C-6 AND D-2 NOS. OF HOUSES AT GAIL
VIHAR TOWNSHIP, DIBIYAPUR;
(B) WORK ORDER NO. CE/115/AURIAYA/GAIL/
GAIL VIHAR ROAD WORK/95 DATED
10.02.95
CONSTRUCTION OF PREMIX BITUMEN
CARPETING AND REPAIRS OF ROADS IN
GAIL VIHAR COLONY AND COMPRESSOR
STATION.
(C) WORK ORDER NO. CE/137/AURIAYA/EXT/
SER/95 DATED 1.11.95:
CONSTRUCTION OF EXTERNAL SEWERAGE
LINE AT UPPC NAGAR, DIBIYAPUR.
(D) WORK ORDER NO. CE/136/AURIAYA/
HOUSING/95 DATED 28.9.95
CONSTRUCTION OF RESIDENTIAL
QUARTERS TYPE A-25 UNITS, TYPE B-105
UNITS, TYPE C-55 UNITS FOR UPPC
COMPLEX, DIBIYAPUR.
-------------------------------------------------------------
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 6 of 13
Dear Sir,
Kindly recall various meetings held in our office and also
in the office of Consultant, M/s C.P. Kukreja Associates
in respect of the above referred contracts and the disputes
arising therefrom, wherein it was agreed between us to
settle the disputes amicably and through discussions.
Despite this clear understanding, you had vide your
letters dated 25.08.98 invoked Arbitration clause in
respect of Work Order Nos. : (1) CE/AUR/PH-II/EXTN.
B. WORK/97A/95 dated 26.05.95 relating to balance
work of Construction of C-6 and D-2 number of houses
at GAIL Vihar Township of Dibiyapur and (2)
CE/115/AURIAYA/GAIL/GAIL VIHAR ROAD
WORK/95 dated 10.2.95 relating to construction of
premix bitumen carpeting and repairs of roads in Gail
Vihar Colony & Compressor Station.
Subsequently, vide your letters dated 5.10.98 in respect
of the above work orders, you submitted a panel of three
Arbitrators asking us to select one of them to act as Sole
Arbitrator on the above two cases. However, we
responded to your communications vide our letters dated
16.02.99 and as per the terms of the contract suggested
the following panel of three distinguished persons :-
1. Mr. Justice N.N. Goswami (R) Judge Delhi High Court
2. Dr. Avtar Singh, (V) Prof. of Law, IIM, Lucknow.
3. Mr. Harish Chandra, Director General CPWD (Retd.)
& Ex-Member, UPSC.
You were requested to select any of them to act as Sole
Arbitrator. However, no action has been taken by you so
far and even the issues which seem to have been resolved
by discussions have not been confirmed, keeping the
matters pending unnecessarily.
During our meetings, we have suggested to you that all
the disputes arising out of the above contracts which
cannot be settled by mutual discussions, may be referred
to a Sole Arbitrator selected by you from among the
panel of distinguished persons mentioned above, so that
the resolution of disputes by reference to Arbitration
becomes cost effective, economical and quick.
In view of the above, you are requested once again to
select any of the persons mentioned herein to act as a
Sole Arbitrator in all the above disputes.
Assuring you of our best co-operation at all times.
Yours faithfully,
Sd/-
( P.K. Sarkar )
Sr. Manager (Civil)"
11. It may be noted that the above noted letter of 15.11.1999 was
written by the Senior Manager (Civil) of appellant no.1 in connection
with the disputes relating to all the four contracts, viz. (A), (B), (C)
and (D). In this letter reference was made to the earlier letter dated
16.2.1999 sent by appellant no.1 and the same panel of three names in
which name of Justice N.N. Goswami (Retd.) was at serial no.1 was
reiterated. The last paragraph of the above quoted letter is very
important where it was clearly mentioned that the dispute arising out
of the four contracts which cannot be mutually settled may be referred
to a sole arbitrator selected by respondent no.1 from amongst the
persons mentioned in the panel so that the resolution of disputes by
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 7 of 13
reference to arbitration becomes cost effective, economical and quick.
Towards the end of the letter a request was made to respondent no.1 to
select anyone of the persons mentioned in the said letter to act as sole
arbitrator in all the above disputes, which means all the disputes
relating to contract nos.(A), (B), (C) and (D). It is, therefore, clear
that a panel of three names had been sent by the appellant to
respondent no.1 on 16.2.1999 which was categorically reiterated in
the letter dated 15.11.1999, sent by the Senior Manager (Civil) of Gas
Authority of India Ltd. (appellant no.1) to respondent no.1. This
letter was not confined to any particular contract but specifically
referred to all the four contracts including the disputed contract no.(D)
dated 28.9.1995. The stand of appellant no.1 was quite reasonable
that if all the disputes were referred to a single arbitrator, the
arbitration proceedings would be cost effective, economical and
quick. After receipt of this letter dated 15.11.1999, wherein the
earlier panel communicated vide letter dated 16.2.1999 had been
reiterated, there was no occasion for respondent no.1 to appoint Brig.
Nardip Singh (Retd.) as arbitrator by sending a communication to that
effect subsequently on 10.12.1999. The stand of the appellant had
been made very clear and explicit by the aforesaid two letters and it
was not required to respond again specifically to the letter dated
28.10.1999 sent by respondent no.1 to select an arbitrator from the
panel intimated by it. The stand of respondent no.1 to the effect that
as the appellant did not respond to its letter dated 28.10.1999, it
selected Brig. Nardip Singh (Retd.) by sending a communication on
10.12.1999 is, therefore, wholly unjustified.
12. There is contemporaneous evidence which shows that a number
of meetings had taken place between the representatives of appellant
no.1 and the representatives of respondent no.1, wherein effort was
made to resolve the disputes without reference to arbitration and an
understanding had been reached between the parties that unresolved
disputes of all the four contracts shall be referred to a sole arbitrator to
make the arbitration proceedings quick and cost effective. After
respondent no.1 had sent the letter dated 10.12.1999 to the appellant
that it had nominated Brig. Nardip Singh (Retd.) for the purpose of
arbitration, the Senior Deputy Manager (Law) of appellant no.1 sent a
letter to him on 31.12.1999 requesting him to desist from entering
upon the reference or taking any further steps in view of the fact that
in the meeting held between the representatives of the two
organisations, it was clearly agreed that the matter shall be referred to
a sole arbitrator and respondent no.1 was expected to select a name
from the panel suggested by appellant no.1. The letter is self-eloquent
and is being reproduced below :-
" December 31, 1999
Brig. Nardip Singh
Chief Engineer, MES (Retd)
B-64, Sector 30
NOIDA
Dear Sir,
Sub : Letter by Keti Const. Ltd. IND/KTIL/908/99
dated 20.12.99 in the matter of construction
of residential quarters of UPPC, Dibiyapur,
Etawah, U.P.
This has reference to the captioned communication on
the subject cited above.
M/s Keti Constructions have been awarded contracts by
GAIL for execution of a number of its projects. In
relation to some of which contracts including the contract
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 8 of 13
in question now sought to be placed before you, certain
disputes are alleged to remain outstanding, as per Keti
Constructions.
Keti Constructions made their requests for resolution of
interse disputes with GAIL by reference to Arbitration,
including in the contract in question.
Upon receipt of these requests of Keti Constructions by
GAIL, GAIL made suggestion for resolution of disputes
by a Sole Arbitrator and sent to Keti Constructions a
panel of three distinguished persons who may be
appointed as Sole Arbitrator. Thereupon, Keti
Constructions came forward for negotiations. During
these discussions/negotiation, the representatives of Keti
Constructions were repeatedly suggested to refer all
unresolved issues of various contracts to a Sole
Arbitrator selected by them from amongst the panel
suggested by GAIL. Representatives of Keti
Constructions agreed to our suggestion as it was less time
consuming and GAIL in turn took liberal view on various
issues with clear objective of resolving these disputes
without reference to arbitration. These efforts yielded
results and the requests for arbitration of Keti
Constructions were withdrawn by them.
As all these matters were between two organisations and
it was clearly agreed by the parties to refer unresolved
disputes of all contracts to a sole arbitrator to make the
arbitration proceedings quick and cost effective. We
would have expected Keti Constructions to have sent a
name from the panel suggested by GAIL in accordance
with the spirit of the discussions held and the principles
accepted therein for resolution of interse disputes, which
have been acted upon as aforesaid.
Unfortunately, Keti Constructions has unilaterally sought
to nominate your goodself, despite the overwhelming
record to the contrary.
In this factual background we request you to desist from
entering upon the reference or taking any further steps in
pursuance to the captioned communication, keeping the
cherished values you have maintained in high esteem all
through your distinguished career in armed forces.
Assuring you of our best attention at all times.
Yours faithfully,
Sd/-
(CH. HARNATH )
SR. DY. MANAGER (LAW)
CC to
Keti Constructions (I) Ltd.
31/6, Sneh Nagar, Main Road
Opposite Sapna Sangeeta Theatre
INDORE 452 001 (M.P.)"
13. It may be noted that the four contracts (A), (B), (C) and (D)
were awarded on different dates in quick succession between
10.2.1995 and 1.11.1995 and related to various construction works in
Petro-Chemical Complex, Dibiapur, District Etawah (U.P.). The terms
of the agreement have to be understood in a broad commonsense
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 9 of 13
manner. The material placed on record before the learned Single
Judge shows that the discussion which took place in the meetings held
between the representatives of appellant no.1 and representatives of
respondent no.1 were not confined to the dispute relating to a single
contract, but they related to disputes concerning all the four contracts.
It will not be proper to segregate or compartmentalize the
correspondence exchanged between the parties as if a particular letter
was confined to a particular contract alone. The correspondence
exchanged between the parties is not like evidence in a suit or trial
where a piece of evidence given in a particular suit or trial cannot be
read or taken into consideration in another suit or trial. The stand of
the appellant right from the beginning was that all the disputes should
be referred to a single arbitrator, which will be cost effective,
economical and quick. There can be no doubt this stand was very
reasonable. Appellant no.1 had sent a panel on 16.2.1999, which was
reiterated in the communication dated 15.11.1999. In these
circumstances, respondent no.1 was not at all entitled to nominate
Brig. Nardip Singh (Retd.) as an arbitrator which it chose to do
subsequently on 10.12.1999. We do not find anything wrong on the
part of the appellant when it intimated vide letter dated 15.11.1999
that a panel had already been sent earlier on 16.2.1999 for
appointment of a single arbitrator for resolution of all the disputes
between the parties.
14. According to the appellants, after respondent no.1 had sent the
notice dated 17.7.1999 invoking the arbitration clause, a reply thereto
was given on their behalf by Mr. Sushil Chauhan, Advocate, on
31.7.1999 wherein it was mentioned as under :
"Ref: Your letter IND/KT/522/99 dated 17.7.99
Pursuant to the discussions held on various occasions by
you and my client, GAIL officials with regard to
settlement of disputes and appointment of sole arbitrator,
I am instructed by my client, Gas Authority of India Ltd.
(GAIL) to call upon you to select the sole arbitrator from
the names of three distinguished persons already
suggested by my clients during discussions in response to
your notices. Please take further necessary action."
Respondent No.1 has seriously challenged the receipt of the
letter dated 31.7.1999 sent by Mr. Sushil Chauhan. It has been urged
that the said letter was not sent by registered post and was not
received by them. We have, therefore, not taken into consideration the
said letter. There is other material on record to show that a panel of
three names had already been sent by appellant no.1 to respondent
no.1 which was a sufficient compliance of the clause of the
agreement. There is neither any such clause in the agreement nor
there is any requirement in law that for each of the contract (A), (B),
(C) and (D) a separate panel ought to have been sent. The same panel
could very well be utilized for resolving the disputes arising out of the
four contracts. In fact, as suggested on behalf of the appellant, it
would have been more convenient, time saving and economical to
have the same person as arbitrator in resolving the disputes between
the parties with regard to all the contracts. The view to the contrary
taken by the Division Bench of the High Court is clearly erroneous in
law.
15. Appellant no.1 sent a communication to Justice N.N. Goswami
(Retd.) on 13.1.2000 appointing him as sole arbitrator for resolution
of disputes relating to the contract in question and a copy of this letter
was also sent to respondent no.1. Justice N.N. Goswami (Retd.) then
entered upon the reference and sent notices to the parties on 11.2.2000
to appear before him on 6.3.2000. Respondent no.1, however, chose
not to put in appearance before Justice N.N. Goswami (Retd.). On
28.3.2000, the arbitrator passed an order holding that his appointment
as arbitrator was in accordance with the terms of the agreement, but in
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 10 of 13
the interest of justice he would give another notice to respondent no.1.
The relevant part of the order passed by him reads as under :
"In terms of my order dated 6.3.2000, M/s Gas
Authority have produced the complete file. On perusal
of the file and after hearing Mr. Chauhan, prima facie I
am satisfied that my appointment as Arbitrator is in
accordance with the terms of Agreement between the
parties. I would have proceeded further, but in the
interest of justice I feel that one final notice be served on
M/s Keti Constructions before publishing the Award.
To come up on April 18, 2000 at 6.30 p.m. The
parties may file their statements of claim before the next
date of hearing."
Since respondent no.1 did not appear on the date fixed, the
arbitrator passed an order fixing 19.4.2000 as the next date of hearing.
A no claim award was finally given by him on 19.4.2000.
16. Respondent no.1 did not at all appear before the arbitrator
appointed by appellant no.1. Respondent no.1 neither filed any
statement of claim nor raised any plea of jurisdiction before the
arbitrator. Section 16 of the Act says that the arbitral tribunal may
rule on its own jurisdiction, including ruling on any objections with
respect to the existence or validity of the arbitration agreement. In
Konkan Railway Corporation Ltd. v. Rani Construction Pvt. Ltd.
(2002) 2 SCC 388 in para 21 a Constitution Bench of 5 learned Judges
has ruled that if the arbitral Tribunal has been improperly constituted,
it would be open to the aggrieved party to require the Arbitral
Tribunal to rule on its own jurisdiction in view of Section 16 of the
Act. It was also observed that the expression used in Sub-section (1)
that the "Arbitral Tribunal may rule on any objections with respect to
the existence or validity of the arbitration agreement" shows that the
Arbitral Tribunal’s authority under Section 16 is not confined to the
width of its jurisdiction, but goes to the very root of its jurisdiction
and there is no impediment in contending before the Arbitral Tribunal
that it had been wrongly constituted. This decision has been partly
overruled on another point by a larger bench of 7 learned Judges in
S.B.P. & Co. v. Patel Engineering Ltd. (2005) 8 SCC 618, but the
aforesaid view has not been dissented from or reversed. This will be
evident from the conclusions arrived at by the larger bench which
have been summarized in para 47 of the report and sub-para (ix)
thereof reads as under :-
"In a case where an Arbitral Tribunal has been
constituted by the parties without having recourse to
Section 11(6) of the Act, the Arbitral Tribunal will have
the jurisdiction to decide all matters as contemplated by
Section 16 of the Act."
17. It will be useful to take note of the preamble of the Arbitration
and Conciliation Act, 1996 which reads as under :-
WHEREAS the United Nations Commission on
International Trade Law (UNCITRAL) has adopted
the UNCITRAL Model Law on International
Commercial Arbitration in 1985;
AND WHEREAS the General Assembly of the
United Nations has recommended that all countries give
due consideration to the said Model Law, in view of the
desirability of uniformity of the law of arbitral
procedures and the specific needs of international
commercial arbitration practice;
AND WHEREAS the UNCITRAL has adopted the
UNCITRAL Conciliation Rules in 1980;
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 11 of 13
AND WHEREAS the General Assembly of the
United Nations has recommended the use of the said
Rules in cases where a dispute arises in the context of
international commercial relations and the parties seek
an amicable settlement of that dispute by recourse to
conciliation;
AND WHEREAS the said Model Law and Rules
make significant contribution to the establishment of a
unified legal framework for the fair and efficient
settlement of disputes arising in international commercial
relations;
AND WHEREAS it is expedient to make law
respecting arbitration and conciliation, taking into
account the aforesaid Model Law and Rules;
The Preamble of the Act makes it amply clear that the
Parliament has enacted the Arbitration and Conciliation Act, 1996
almost on the same lines as the Model Law, which was drafted by
United Nations Commission on International Trade Law. In
Sundaram Finance Ltd. v. NEPC Ltd. AIR 1999 SC 565 it has been
observed that the provisions of the Arbitration and Conciliation Act,
1996 should be interpreted keeping in mind the Model Law as the
concept under the present Act has undergone a complete change. It
will, therefore, be useful to take note of the corresponding provisions
of the UNCITRAL Model Law. Article 16 of the Model Law, which
corresponds to Section 16 of the Act, is being reproduced below :
UNCITRAL Model Law
"Article 16. Competence to rule on own jurisdiction.-
(1) The Arbitral Tribunal has the power to rule on its own
jurisdiction, including any objections with respect to the
existence or validity of the arbitration agreement. For the
purpose, an arbitration clause which forms part of a
contract shall be treated as an agreement independent of
the other terms of the contract. A decision by the Arbitral
Tribunal that the contract is null and void shall not entail
ipso jure the invalidity of the arbitration clause.
(2) A plea that the Arbitral Tribunal does not have
jurisdiction shall be raised not later than in the statement
of defence. A party is not precluded from raising such a
plea by the fact that he has appointed, or participated in
the appointment of, an arbitrator. A plea that the Arbitral
Tribunal is exceeding the scope of its authority shall be
raised promptly after the Arbitral Tribunal has indicated
its intention to decide on the matter alleged to be beyond
the scope of its authority. The Arbitral Tribunal may, in
either case, admit a later plea if it considers the delay
justified.
(3) The Arbitral Tribunal may rule on a plea referred to
in paragraph (2) of this article either as a preliminary
question or in an award on the merits. In either case, a
ruling by the Arbitral Tribunal that it has jurisdiction may
be contested by any party only in an action for setting
aside the arbitral award."
The commentary on the three paragraphs of the Model Law
has been given under the headings A, B, C and D. Note 1 under
heading A and Note 11 under heading D, which are relevant for the
controversy in hand, are being reproduced below :
"A. "Kompetenz-kompetenz" and separability doctrine,
paragraph (1).
1. Article 16 adopts the important principle that it is
initially and primarily for the Arbitral Tribunal itself to
determine whether it has jurisdiction, subject to ultimate
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 12 of 13
Court control (see below paras 12-14). Paragraph (1)
grants the Arbitral Tribunal the power to rule on its own
jurisdiction. Including any objections with respect to the
existence or validity of the arbitration agreement. This
power, often referred to as "Kompetenz-kompetenz", is
an essential and widely accepted feature of modern
international arbitration but, at present is not yet
recognised in all national laws.
D. Ruling by Arbitral Tribunal and judicial control,
paragraph (3) [Corr. to Section 16(5), (6)]
11. Objections to the Arbitral Tribunal’s jurisdiction go to
the very foundation of the arbitration. Jurisdictional
questions are, thus, antecedent to matters of substance
and usually ruled upon first in a separate decision, in
order to avoid possible waste of time and costs. However,
in some cases, in particular, where the question of
jurisdiction is intertwined with the substantive issue, it
may be appropriate to combine the ruling on jurisdiction
with partial or complete decision on the merits of the
case. Article 16 (3), therefore, grants the Arbitral
Tribunal discretion to rule on a plea referred to in
paragraph (2) either as a preliminary question or in an
award on the merits.
So, the commentary on the Model Law which was drafted by
UNCITRAL and has been adopted by many countries including India
shows that where a party asserts that the arbitral tribunal has not been
properly constituted or it has no jurisdiction, then such a plea must be
raised before the arbitral tribunal right at the beginning and normally
not later than in the statement of defence.
18. The whole object and scheme of the Act is to secure an
expeditious resolution of disputes. Therefore, where a party raises a
plea that the arbitral tribunal has not been properly constituted or has
no jurisdiction, it must do so at the threshold before the arbitral
tribunal so that remedial measures may be immediately taken and time
and expense involved in hearing of the matter before the arbitral
tribunal which may ultimately be found to be either not properly
constituted or lacking in jurisdiction, in proceedings for setting aside
the award, may be avoided. The commentary on Model Law clearly
illustrates the aforesaid legal position.
19. Where a party has received notice and he does not raise a plea
of lack of jurisdiction before the arbitral tribunal, he must make out a
strong case why he did not do so if he chooses to move a petition for
setting aside the award under Section 34(2)(v) of the Act on the
ground that the composition of the arbitral tribunal was not in
accordance with the agreement of the parties. If plea of jurisdiction is
not taken before the arbitrator as provided in Section 16 of the Act,
such a plea cannot be permitted to be raised in proceedings under
Section 34 of the Act for setting aside the award, unless good reasons
are shown.
20. Though respondent no.1 had ample opportunity to appear
before Justice N.N. Goswami (Retd.) and raise a plea of jurisdiction to
the effect that he had been wrongly appointed as arbitrator by
appellant no.1, yet, it chose not to do so. This feature of the case
weighs heavily against respondent no.1. The learned Single Judge has
taken this fact as an additional ground for rejecting the petition filed
by respondent no.1 under Section 34 of the Act and we are in
agreement with the said view.
21. For the reasons discussed above, the appeal is allowed with
costs throughout and the judgment and order dated 7.12.2004 of the
Division Bench of the High Court is set aside. The judgment and
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 13 of 13
order dated 20.10.2003 of the learned Single Judge dismissing the
petition under Section 34 of the Act, which was filed by respondent
no.1, is affirmed.