Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 11
PETITIONER:
VINEET KUMAR MATHUR
Vs.
RESPONDENT:
UNION OF INDIA AND ORS.
DATE OF JUDGMENT08/11/1995
BENCH:
JEEVAN REDDY, B.P. (J)
BENCH:
JEEVAN REDDY, B.P. (J)
NANAVATI G.T. (J)
CITATION:
1996 SCC (1) 119 JT 1995 (8) 27
1995 SCALE (6)241
ACT:
HEADNOTE:
JUDGMENT:
J U D G M E N T
B.P. JEEVAN REDDY.
A letter written by Sri Vineet Kumar Mathur pointing
out the pollution caused in the river Gomti and its causes
was treated as a writ petition by this Court and orders
passed from time to time. Mohan Meakins Breweries is said to
be one of the industries polluting the river. It is not
necessary to refer to the various orders passed in this
matter from time to time. It would be sufficient to refer to
the order made on January 15, 1993 which reads as under:
"The following order will apply to: (1)
M/s. Mohan Meakins, Daliganj, Lucknow;
(2) M/s. Oudh Sugar Mill, Hargaon,
Sitapur; (3) M/s. Bajaj Hindustan Ltd.,
Gola Gorakhnath, Kheri (Sugar Unit-
Distillery); (4) M/s. Sharda Sugar Mill,
Palia Lakhimpur Kheri (New Name - Bajaj
Hindustan Ltd., Unit Palia Lakhimpur
Kheri); (5) M/s. Balaji Vegetable
Product, Sitapur; (6) M/s. Kissan
Cooperative Sugar Mill, Majhola,
Pilibhit; (7) M/s. U.P. State Sugar
Corpn, Maholi, Sitapur; (8) M/s. HAL
Lucknow; (9) M/s. Lucknow Producers Milk
Union, Lucknow Industries.
"The officers of the State
Pollution Board will visit the above
industrial establishments and make a
fresh inspection of the effluent
treatment plants installed in the said
establishments and of their working. If
there are any applications made by these
industries for consent of the Board,
they will be disposed of after
inspection and within three weeks from
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 11
today. If after inspection, it is found
that the treatment plants are deficient
in any respect or the deficiency pointed
out earlier still continues, the Board
will give reasonable time for the
industries to cure the deficiencies.
However, the time so given should not
extend beyond 21st March, 1993.
The officers of the Pollution Board
will visit the industrial establishments
concerned after the expiry of the time
given to them to cure the deficiencies,
and, make their report to this Court
before 7th April, 1993.
If the industries in question do
not obtain the consent of the State
Pollution Board for running their units,
before 31st March, 1993, the industries
will stop functioning after 31st March,
1993.
As regards the Municipal Boards of
Pilibhit, Barabanki, Sitapur, Sultanpur,
Jaunpur, Lakhimpur Kheri, they are
directed to instal the effluent
treatment plant on or before 30th April,
1993 and obtain a certificate from the
State Pollution Board that the plant
installed is upto the standard and its
working is satisfactory. The Chief
Officers and the Presiding Officers of
the concerned Municipalities are
required to file their affidavits on or
before 30th April, 1993 that they have
complied with the above directions.
Mr.R.B. Misra appears for the State
Government. The State Government is
directed to let the Court know what
steps they have taken to release the
funds to the Jal Nigam for installation
of the sewerage treatment plant at
Lucknow. The affidavit to be filed on or
before 30th April, 1993.
As regards the industries, the
matter shall come up for hearing on 7th
April, 1993. As regards the
municipalities, it would come up for
hearing on 3rd May, 1993."
Inasmuch as Mohan Meakins did not remove the
deficiencies in its effluent treatment plant by 21st March,
1993, no consent was granted to it by the Pollution Control
Board. It stopped functioning from Ist April, 1993 onwards.
The letter dated March 31, 1993 addressed to Mohan Meakins
by the Uttar Pradesh Pollution Control Board (at Pages 422-
425 of the record) states that in the circumstances stated
therein, consent cannot be granted to Mohan Meakins under
the Water (Control of Pollution) Act, 1974 (for short, the
"Water Act").
On April 2, 1993, Mohan Meakins addressed a letter to
the Pollution Control Board (P.C.B.) stating that they have
since complied with the order of this Court and, therefore,
the consent may now be granted to them under the Water Act.
Before we refer to the orders passed on this application, we
may refer to some other developments which have taken place
in the meanwhile.
On April 6, 1993, the P.C.B. filed an affidavit in this
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 11
Court stating, inter alia, that the consent has been refused
to Mohan Meakins for failing to remove the deficiencies in
effluent treatment plant.
On 6th and 7th April, 1993, Mohan Meakins filed two
affidavits in this Court. In the first affidavit, Mohan
Meakins stated that the sudden shut down of the plant is
likely to result in not only emission of poisonous gases but
is also likely to damage the machinery and the plant beyond
repair on account of the solidification of the spentwash and
that with a view to avoid the said untoward consequences, it
is felt necessary to run the plant intermittently for a
period not exceeding two days in all between 7th and 11th of
April, 1993. By such running, it was submitted, the company
does not mean to nor should it be understood to have
violated the order of this Court dated January 15, 1993. In
the other affidavit filed by Mohan Meakins, it stated that
inasmuch as they have since rectified the deficiencies in
the effluent treatment plant and have brought it upto the
desired level, the order dated January 15, 1993 may be
extended till December 31, 1993, which is the date specified
in the Government of India Notification dated February 12,
1992.
On April 15, 1993, this Court passed an order (at Page
520 of the record) holding that running of the plant between
7th and 11th of April, 1993 by Mohan Meakins prima facie
amounts to violation of this Court’s order dated January 15,
1993. Accordingly, notices were issued to the Managing
Director of Mohan Meakins, Brig. Kapil Mohan, and to the
Chief Executive Officer, Sri Yogesh Kumar, to show cause why
they should not be proceeded against for contempt of this
Court.
Now, coming back to the application made by the P.C.B.
on April 2, 1993 to grant consent, the P.C.B. granted the
consent on April 21, 1993. This fact was, however, not
brought to the notice of this Court immediately either by
P.C.B. or by Mohan Meakins. Though an affidavit was filed by
Sri Yogesh Kumar on April 27, 1993 in response to the
contempt notice issued to him on April 15, 1993, this fact
was not disclosed. Similarly, the Managing Director, Brig.
Kapil Mohan also did not disclose this fact in his affidavit
filed in reply to the contempt notice. On May 3, 1993, the
P.C.B. also filed an affidavit stating that working of the
factory for two days by Mohan Meakins is not justified but
even here the P.C.B. did not disclose the fact that the
consent has since been granted to Mohan Meakins on April 21,
1993. It, however, appears that during the course of
arguments, this fact was brought to the notice of this
Court. Thereupon, Sri P.H. Parekh, Advocate, who was
appointed by this Court as Amicus Curiae in this matter
addressed a letter, on May 8, 1993, to the learned Advocate
for Mohan Meakins to confirm whether the plant/factory of
Mohan Meakins has started working since April 23, 1993 and
if so, on what basis. Sri Parekh sent a reminder on May 14,
1993. There was no reply from Mohan Meakins to either of
these letters.
On October 8, 1993, this Court passed the following
order in view of the failure of Mohan Meakins to respond to
the letters from Sri Parekh:
"Inspite of the letter written by the
learned counsel for petitioner on May 8,
1993 requesting the learned advocate for
the 2nd respondent to send him copies of
all the applications for consent,
appeals together with the annexures and
copies of the orders, passed either by
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 11
the U.P. Pollution Control Board or by
the Appellate Authorities under which
the respondent Industry has been working
since 23rd April, 1993, no documents
have been supplied to him till date. Mr.
Bhandare, learned counsel for the 2nd
respondent states that they were under
the impression that the petitioner must
be in possession of the said documents.
The reply is most unsatisfactory and
distressing as well. We adjourn the
matter to 5th November, 1993. The 2nd
respondent to supply the documents in
question on affidavit. The respondent
No.2 to pay the cost of adjournment
which is fixed at Rs. 10,000/- as a
condition precedent. The matter will be
before this Bench as part-heard."
In compliance with the above order, an affidavit was
filed on October 24, 1993 on behalf of Mohan Meakins (at
Page 595 of the record) disclosing that on the basis of
their letter dated April 2, 1993, the P.C.B. has granted
consent on April 21, 1993 and that while granting the said
consent the P.C.B. was fully aware of the order of this
Court dated April 15, 1993 (issuing contempt notices to the
Managing Director and Chief Executive Officer of Mohan
Meakins). It was disclosed further that on the basis of the
said consent their plant had started functioning with effect
from April 23, 1993.
In the light of the facts disclosed in the affidavit
filed on behalf of Mohan Meakins, this Court issued a notice
to Sri Darshan Singh, Member-Secretary, Uttar Pradesh
Pollution Control Board to show cause why he should not be
punished for contempt of this Court for granting consent in
violation of the orders of this Court dated January 15,
1993. Counsel for the State of Uttar Pradesh was also
directed to produce the entire Government record relating to
the said matter alongwith an affidavit detailing the
circumstances in which the Government had issued the order
dated April 20, 1993 (referred to in the ‘consent’ order) to
Sri Darshan Singh. On May 13, 1994, Sri Darshan Singh filed
an affidavit in response to the contempt notice issued to
him. In his affidavit, he referred to (1) Government of
India Notification dated February 12, 1992 adding sub-rules
(6) and (7) in Rule 3 of Environment (Protection) Rules,
1986 and to sub-rule (6) in particular; (2) to Section 18 of
the Water Act which empowered the Central Government to give
directions to the P.C.B.; (3) to the order of this Court
dated January 15, 1993 and (4) to the closure of Mohan
Meakins on and with effect from April 1, 1993 in compliance
with this Court’s order dated January 15, 1993 and then
stated that he had put up a note to the Chairman for
granting consent to Mohan Meakins in view of the Uttar
Pradesh Government order dated April 20, 1993, mentioning at
the same time that the consent so granted shall be subject
to the orders of this Court. He stated that "the Chairman,
U.P. Pollution Control Board/Secretary (Environment),
Government of U.P. directed the deponent not to raise any
objection in granting consent to M/s. Mohan Meakins in view
of G.O. dated 20.4.1993 since this unit has been established
before 16.5.1991 and requested time till 31.12.1993 to
achieve the standard". He submitted that in view of the said
direction, he had to and did issue the ’consent’. He also
referred to Section 27(2) of the Water Act which empowered
the Board to review its order refusing consent.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 11
On July 20, 1994, an affidavit was filed on behalf of
the State Government (sworn-to by Sri S.N.Shukla, Special
Secretary, Environment) affirming the direction given by the
Uttar Pradesh Government to the Pollution Control Board but
stating at the same time that they were general instructions
and were not meant for a particular industry. It was further
stated in this affidavit that any such general instructions
were not supposed to be relied upon by the P.C.B. to act in
contravention of this court’s order.
In view of the affidavit of Sri Darshan Singh and the
affidavit of the Government of Uttar Pradesh aforesaid, this
Court directed, on May 4, 1995, notice to Sri Pradeep Kumar,
the then Chairman of the Uttar Pradesh Pollution Control
Board-cum-Secretary (Environment) to show cause as to why he
should not be punished for contempt of this Court. Sri
Pradeep Kumar filed an affidavit in response to the said
notice stating that inasmuch as Mohan Meakins was a unit
established before May 16, 1991 and had installed effluent
treatment plant and also because the B.O.D. level was only
marginally higher than the prescribed norms, "it was
considered appropriate to review the matter in the light of
the provisions of Section 27(2) of the Water (Prevention and
Control of Pollution) Act, 1974", particularly in view of
the orders issued by the Government of Uttar Pradesh on
April 20, 1993. Paragraphs 11, 12 and 13 of his affidavit
are relevant and may be extracted:
"11. That in aforesaid circumstances the
Member-Secretary of the Board had moved
a proposal for reviewing the orders of
the Board regarding refusal of the
consent on 21.4.1993. It has been
suggested by Member-Secretary that
consent may be given to the industry
subject to the condition that the unit
will treat the effluents to the extent
possible in ETP and also subject to the
orders of the Hon’ble Supreme Court in
W.P. No. 327/90 Vineet Kumar Mathur
Versus Union of India & Ors.
12. That the proposal of the Member-
Secretary was approved by the deponent
and it was directed not to raise any
objections as per the provisions of the
G.O. dated 20.4.93. But such approval of
the deponent for reviewing consent does
not mean that M/s. Mohan Meakins was
allowed to operate its industrial plant
after 31.3.93 in defiance of the order
dated 15.1.1993 passed by this Hon’ble
Court.
13. That in the consent letter, it has
been made clear that the same is issued
subject to the orders passed by this
Hon’ble Court. True English translation
of letter dated 21.4.1993 issued to M/s.
Mohan Meakins is being filed herewith
and marked as Annexure IV to this
affidavit."
Since this Court was not satisfied with the explanation
so offered, a notice was issued on August 25, 1995 calling
upon Sri Pradeep Kumar to answer the charge of contempt in
response to which Sri Pradeep Kumar filed an affidavit on
October 12, 1995. In this affidavit, he tendered his
unconditional apology for violating the orders of this Court
and prayed that in the circumstances stated therein his
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 6 of 11
unconditional apology may be accepted. In this affidavit, he
stated that after the closure of several industries on or
with effect from April 1, 1993, they made a representation
to the Government of Uttar Pradesh referring, inter alia, to
the Government of India Notification dated February 12, 1992
(referred to supra) whereupon he consulted the Law
Department of Uttar Pradesh and on the basis of its legal
opinion and after considering the matter at the highest
level in the Government (including the Advisor to H.E. the
Governor) he put up a proposal to issue appropriate orders
to P.C.B. that the industry established before May 16, 1981
may not be refused consent and that such industries may be
given time till December 31, 1993 for achieving the
prescribed level of efficiency in their effluent treatment
plants. Accordingly, the Government issued orders on April
20, 1993 following which Sri Darshan Singh, Member
Secretary, Uttar Pradesh Pollution Control Board put up a
proposal for granting consent, which he approved stating
that no objection be raised for granting consent to Mohan
Meakins. In his note, he made it clear that any such consent
shall be subject to the orders of this Court. Sri Pradeep
Kumar admitted that it was a lepse on his part, as a
Chairman of the Pollution Control Board, in not ensuring
that this Court is informed of the said consent immediately
and in not obtaining appropriate orders in that behalf. He
further stated that he is a senior member of the I.A.S.
cadre, that in his entire career he has never violated the
orders of the Court and that in the circumstances stated in
the affidavit, he may be pardoned. He assured that he would
never give any occasion for similar complaint.
When the matter came up on October 14, 1995, we heard
the matter fully insofar as Sri Pradeep Kumar and Sri
Darshan Singh are concerned. Insofar as the contempt notice
related to Mohan Meakins is concerned, it transpired during
the course of hearing that the notice issued to the Managing
Director and the Chief Executive Officer pertained only to
their runnig the factory/plant on two days between 7th and
11th of April, 1993 and not to their obtaining consent on
April 21, 1993 and running their plant contrary to the
orders of this Court. Accordingly, we issued a fresh notice
to the officers of the Mohan Meakins to show cause why they
should not be punished for violating the orders of this
Court dated January 15, 1993 by obtaining consent from the
P.C.B. on April 21, 1993 in violation of the orders of this
Court. Notice was made returnable within four weeks, during
which time the said contemnors were entitled to file a
counter to the said notice. For this reason, we are
delinking the contempt notice insofar as it pertains to
Mohan Meakins which will be dealt with and disposed of
later, though we have concluded the arguments with respect
to the notice already issued to them. We think it
appropriate that orders are passed with respect to Mohan
Meakins after hearing them in response to the fresh notice
issued on October 13, 1995. These orders are, therefore,
confined to Sri Pradeep Kumar and Sri Darshan Singh only.
Sri Pradeep Kumar was the Chairman and Sri Darshan
Singh was the Member-Secretary of the Uttar Pradesh
Pollution Control Board at the relevant time.
We are of the opinion that the consent granted by
Pollution Control Board to Mohan Meakins on April 21, 1993
is clearly in contravention of this Court’s order dated
January 15,1993. The order of this Court had expressly
directed that the reasonable time to be given to the various
industries for removal of deficiencies in their effluent
treatment plants shall not be beyond March 21, 1993. The
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 7 of 11
inspection by the P.C.B., the removal of deficiencies et al
were all to be completed by March 21, 1993. All those
industries which did not remove the deficiencies within the
said date and did not obtain the consent of P.C.B. by March
31,1993 were to close down. Mohan Meakins were indeed
refused consent by P.C.B. on March 31, 1993 and it was
closed on and with effect from April 1, 1993. Yet a consent
was granted on April 21, 1993 by the Pollution Control Board
whereunder it has been allowed to operate its plant and
factory with the condition that it should remove the
deficiencies on or before December 31,1993. It may be
noticed that the amendment of Environment Rules effected by
the Central Government by Notification dated February 12,
1992 was long prior to this Court’s order dated January 15,
1993. Though the said amendment provided for granting time
for removal on deficiencies till December 31, 1993 in case
of industries established before May 16, 1981, this Court
had yet ordered that it should be done on or before March
21, 1993. In such a situation, it was not open to the
Pollution Control Board to grant consent on April 21, 1993
asking Mohan Meakins to remove the deficiencies by December
31, 1993. It must be remembered that both the Uttar Pradesh
Pollution Control Board and Mohan Meakins were Parties to
the order dated January 15, 1993. We are, therefore, of the
clear opinion that the said grant of consent to Mohan
Meakins was in clear contravention of the order dated
January 15, 1993.
So far as the addition of the words, "this consent
order is subject to the orders passed by the Hon’ble Supreme
Court of India in W.P.327 of 1990 (Vineet Kumar Mathur
V.Union of India)" are concerned, we think that it was a
clever ploy by the person(s) issuing the consent. Firstly,
the order of this Court dated January 15, 1993 precluded
grant of any consent subsequent to March 31, 1993. Secondly,
there was no point in saying that the said consent was
"subject to the orders passed by the Hon’ble Supreme Court"
when the consent being granted was itself in plain
contravention of the order of this Court. If really the
Pollution Control Board meant what it now says, the least -
and probably the only course open to it - it could have done
was to apply to this Court for permission to issue a
‘consent’ for the reasons stated by it. It did nothing of
the sort. It went ahead and issued a consent with the said
misleading words allowing the industry to operate contrary
to the orders of this Court. Yet another fact to be noticed
in this behalf is the variance between the ground stated in
Mohan Meakins’ application (for consent) dated April 2, 1993
and the terms subject to which it was granted consent by
P.C.B. In their application dated April 2, 1993, It may be
recalled, Mohan Meakins stated that inasmuch as they have
complied with the prescribed norms they should be granted
consent whereas the consent actually granted contemplates
Mohan Meakins achieving the prescribed norms by December
31,1993. The consent letter does not also say that Mohan
Meakins will be entitled to act upon the said consent only
after obtaining the orders of this Court therefor. In the
absence of any such stipulation, the addition of the said
words in the consent order had no meaning and were evidently
meant to be used as a cover in future if and when someone
complained of violation of the order of this Court. In this
view of this matter, both the Member-Secretary, Sri Darshan
Singh and the Chairman of the Pollution Control Board, Sri
Pradeep Kumar must be held to be guilty of violation of the
order of this Court dated January 15, 1993. Question then
arises, whether the unconditional apology tendered by them
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 8 of 11
should be accepted, or not?
Sri Pradeep Kumar has filed two affidavits to which
reference has already been made. In the earlier affidavit,
an attempt was made to show that there was no violation in
view of the facts stated therein by the second affidavit, he
has accepted that there was a lapse on his part. Of course,
even in this second affidavit, he has tried to explain that
his orders were passed upon the note put up by Sri Darshan
Singh, Member-Secretary, the legal opinion tendered by the
Law Secretary and the decision taken by his superiors
including the Advisor to H.E. the Governor. At the time of
arguments, however, Sri Kapil Sibal, learned counsel for Sri
Pradeep Kumar, made no attempt to justify his conduct. Sri
Sibal plainly admitted that what has been done was in clear
violation of the orders of this Court dated January 15,
1993. Sri Sibal submitted that in view of the unblemished
record of the officer and in view of the circumstances
stated in his second affidavit and his assurance that he
will never allow any such situation to arise in future, the
unconditional apology tendered by him may be accepted.
Counsel submitted that Sri Pradeep Kumar is truly repenting
his lapse and the unconditional apology by him is born of
genuine contriteness.
Sri Darshan Singh has filed only one affidavit. While
tendering an unconditional and unqualified apology, Sri
Darshan Singh has stated that in view of the amendment of
Environment Rules on February 12, 1992, and the power of
review inhering in the Pollution Control Board by virtue of
Section 27(2) of the Water Act, he put up a note for grant
of consent on the basis of the application made by Mohan
Meakins on April 2,1993. The relevant paras in his affidavit
are Paras 13 to 17 which read thus:
"13. That the deponent on 21.4.93
keeping in view the orders passed by
this Hon’ble Court, G.O. dt.20.4.93 and
provisions of the Act and Rules
submitted a proposal for grant of
consent to M/s. Mohan Meakins before the
Chairman of the Board wherein it was
specifically mentioned that this consent
will be subject to orders passed by this
Hon’ble Court in this case.
14. That the Charman, U.P.Pollution
Control Board/Secretary, Environment,
Government of U.P. directed the deponent
not to raise any objection in grating
consent to M/s.Mohan Meakins in view of
G.O. dt.20.4.93 since this unit has been
established before 16.5.1981 and
requested time till 31.12.1993 to
achieve the standard.
15. That in view of these directions
the deponent granted consent to
M/s.Mohan Meakins vide order dated
21.4.93. But it has been specifically
mentioned in this order that this
consent is being granted subject to the
orders of this Hon’ble Court passed in
the abovementioned case. Since the unit
has already been closed in pursuance of
order dt.15.1.93 passed by this Hob’ble
Court w.e.f. 1.4.93, the same ought not
to have been operated without seeking
permission of this Hon’ble court because
consent was granted subject to order
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 9 of 11
dated 15.1.93. Merely because
application seeking consent has been
disposed of the Board does not mean that
permission to operate the industry was
granted by the deponent.
16. That in case the U.P. Pollution
Control Board did not dispose of the
application of any industries seeking
consent within 4 months as per sub-
section 7 of Section 25 of the Water
(Prevention and Control of Pollution)
Act, 1974 it will be deemed to be
granted unconditionally.
17. That in the light of the
abovementioned facts and circumstances,
it is most respectfully submitted before
this Hon’ble Court that the deponent had
never intended to permit the industry to
operate their plant and while issuing
consent order the deponent has
specifically mentioned therein that this
order is subject to order passed by this
Hon’ble Court in the above noted writ
petition. As there is a specific
condition in the above noted order, the
industry without ensuring compliance of
such condition cannot operate its
industrial plant as the same was already
lying closed down pursuant to order
dated 15.1.93 of this Hon’ble Court."
An extract of the note put up by Sri Darshan Singh as
also the orders passed thereon by Sri Pradeep Kumar are
placed before us. The relevant portion of the note reads as
under:
"Wherefore under provisions of Section
18 read with section 27(2) clause B of
the Water Act, 1974, pursuant to above
mentioned Govt. Order dt.20.4.93 read
with letter dt.2.4.93 of M/s. Mohan
Meakins, Lucknow regarding water
consent, after reviewing the water
consent refusal of the industry under
Section 25 of the Water Act, 1974 in
exercise of the power conferred under
clause B of sub-section (2) of Section
27 proposal to grant the water consent
by the State Board to the industry for
the year 1993 is submitted for approval.
While granting the water consent in said
consent order alongwith other various
conditions this specific condition has
been proposed to be imposed essentially
that as the industry have installed
E.T.P. hence the industry shall
discharge its trade effluent only after
treatment of the same in accordance with
prescribed standard. It is also proposed
to mention specifically in consent order
that said consent order shall be subject
to order/directions issued by the
Hon’ble Supreme Court in W.P.No.327/90
Vineet Kumar Mathur Vs.Union of India.
Accordingly after issuing the consent
order to the industry, it is proposed
that these facts be placed before
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 10 of 11
Hon’ble Supreme Court. Copy of Order
dt.15.4.93 passed by Hon’ble Supreme
Court is enclosed herewith.
Submitted for perusal.
sd/-IIIegible
21.4.93
(Darshan singh)
Member Secretary
U.P.Pollution Control Board,
Lucknow
To chairman
Instead of the condition stated in part
A it is proposed that this condition be
imposed that the industry will discharge
its trade effluent after treating it to
whatever extent it is competent to do so
and continue to treat the effluent
regularly and will ensure to achieve the
standard by 31.12.93.
sd/- IIlegible
21.4.93
Member Secretary
By Chairman
This industry has been established prior
to 16.5.81 and it has requested for time
till 31.12.93 to achieve the standard.
Pursuant to Government Order dated
20.4.93 no objections should be raised
for grant of consent. However, while
granting consent, this condition be
imposed that the unit shall not make any
wilfull default in operation of its
E.T.P. and will discharge its effluent
after treating the same to bring down
the E.O.D. to the extent for which its
E.T.P. is capable to achieve.
Sd/- Illegible
21.4.93
(Pradeep Kumar)
Chairman
U.P.Pollution Control Board
Lucknow
Member Secretary/C-V
sd/- Illegible"
It is significant to note that Para 3 of this Note does
refer to the order of this Court dated January 15, 1993 and
to the refusal of consent by P.C.B. to Mohan Meakins on
March 31,1993, yet it says that in view of the instructions
issued by the Uttar Pradesh Government on April 20, 1993,
the order dated March 31, 1993 refusing consent is liable to
be reviewd under Section 27 of the Water Act. It singularly
fails to point out that the refusal of consent on March 31,
1993 was pursuant to and in terms of the Court’s order dated
January 15, 1993 and cannot, therefore, be reviewed without
reference to this Court. It is equally significant to notice
that Sri Pradeep Kumar too does not refer to this aspect in
his endorsement. As a matter of fact, his endorsement does
not even say specifically that consent be granted subject to
the orders of this Court. It looks as if for both of them,
the orders of the Uttar Pradesh Government issued on April
20, 1993 were sacrosant and superseded the orders of this
Court as well. It is a matter of regret that even
responsible and senior officers of the Government have acted
in this manner. It is clear enough that the officials were
anxious to somehow make out a case for enabling the Mohan
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 11 of 11
Meakins to operate its plant and machinery regardless of the
orders of this Court. We may also incidentally notice the
unusual speed with which the matter was processed. The Uttar
Pradesh Government’s orders, general in nature, are dated
April 20, 1993. On the very next day, Sri Darshan Singh put
up the note, which was approved by Sri Pradeep Kumar on the
same day and the ‘consent’ also issued on the same day.
Sri V.R. Reddy, learned Additional Solicitor General,
appearing for Sri Darshan Singh reiterated the reasons and
circumstances in which the Member-Secretary had put up the
said note. He submitted that the Member-Secretary was bound
by the direction given by the Chairman and that he had no
option but to issue the consent pursuant to the orders of
the Chairman. Learned counsel affirmed the unconditional
apology tendered by Sri Darshan Singh and pleaded for its
acceptance as a true expression of contriteness on his part.
Taking into consideration all the facts and
circumstances aforesaid, we hold that Sri Pradeep Kumar and
Sri Darshan Singh are both guilty of violation of this
Court’s Order dated January 15,1993. In view of the
explanation put forward by them and the several
circumstances stated by them, however, we are inclined to
accept their unconditional apology. At the same time, we
administer a severe warning to both the officers that
repetition of any such violation shall be viewed seriously.
A copy of this Order shall form part of the service record
of both the officers.
The contempt petition is ordered accordingly.
As stated hereinabove, insofar as the contempt
proceedings against Brig.Kapil Mohan and Sri Yogesh Kumar,
Managing Director and Chief Executive Officer respectively,
of Mohan Meakins are concerned, orders will be passed later
after hearing them on the fresh notice issued on October 12,