Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 5
PETITIONER:
V. PARUKUTTY MANNADISSIAR & ANR.
Vs.
RESPONDENT:
STATE OF KERALA & ORS.
DATE OF JUDGMENT05/09/1989
BENCH:
MISRA RANGNATH
BENCH:
MISRA RANGNATH
VENKATACHALLIAH, M.N. (J)
CITATION:
1990 AIR 817 1989 SCR Supl. (1) 37
1990 SCC Supl. 245 JT 1989 (3) 572
1989 SCALE (2)529
ACT:
Kerala Private Forests (Vesting and Assignment) Act,
1971: Sections 2(f), 3(2)--Vesting of private
forests--Decision of Tribunal-Whether Government could alter
by administrative order.
HEADNOTE:
The High Court, in an appeal against a decision of the
Forest Tribunal, under the provisions of the Kerala Forests
(Vesting & Assignment) Act, 1971, held that 92 acres of
forest land were to be given back to the appellants. Accord-
ingly, the Forest Department returned certain lands. Later
on they realised that the lands constituted thick forests
and had valuable trees thereon and refused the timber trans-
it permits applied for by the appellants.
Aggrieved against the decision, the appellants ap-
proached the High Court by way of a Writ Petition. The High
Court held that the appellants were not entitled to any
relief with regard to rosewood and other trees cut from the
lands that did not form part of the land ordered to be
restored to them. The High Court directed the Forest Depart-
ment to consider the application of the appellants and pass
appropriate orders after giving an opportunity to the appel-
lants to put forward their contentions.
This appeal, by special leave, is against the said order
of the High Court.
Allowing the appeal in part,
HELD: 1.1 The appellants are entitled to return of 92
acres of land and not 80 acres..This is on the ground that
the direction of the High Court in the first appeal became
final and in terms of such direction 92 acres were to go
back to the appellants. Government had no authority to alter
the decision by an administrative order as has been done in
this case. [41D]
1.2 There is no dispute that 56.31 acres have been
restored to the appellants.. By the affidavit of 24th June,
1989, 23.69 acres have been
38
offered to be restored from three survey numbers indicated
therein. With the restoration of 23.69 acres the appellants
would have got back 80 acres of land. There would still be
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 5
12 acres to be returned to the appellants. The respondents
shall have a direction to trace these 12 acres in the local-
ity and make over vacant possession to the appellants there-
of within four months. [41E]
1.3 In case 23.69 acres or any part thereof as indicated
in the affidavit Cannot be delivered possession and the
balance 12 acres are not identified and possession thereof
cannot be delivered, the appellants shall be entitled to
compensation in respect of the shortfall out of 35.69 acres
in all which remain to be delivered and compensation for
such shortfall shall be determined as if it were acquisition
under the provisions of the Land Acquisition Act, the date
of the preliminary notification being deemed to be the date
of judgment of the Division Bench in MFA 401/78. The direc-
tions indicated above shall be worked out by the respondents
within a total period of six months. [41F-G]
2. The High Court called upon the respondents to consid-
er the appellants’ plea for timber transit permits in re-
spect of trees cut from certain other lands. There is no
material on record as to whether that has been complied
with. In case the respondents have not done the same yet,
they are directed to comply with the order of the High Court
within three months. [41H; 42A]
JUDGMENT:
CIVIL APPELLATE JURISDICTION: Civil Appeal Nos. 3694-
3695 of 1989.
From the Judgment and Order dated 22.9. 1987 of the
Kerala High Court in O.P. Nos. 4932 of 1983 and 1091 of
1982.
T.S. Krishnamurthy Iyer and E.M.S. Anam for the Appel-
ants.
P.S. Poti and P.K. Pillai for the Respondents.
The Judgment of the Court was delivered by
RANGANATH MISRA, J. Special leave granted. We have
heard learned counsel for the parties.
In disposing of the appeal against a decision of the
Forest Tribunal under the provisions of the Kerala Private
Forests (Vesting &
39
Assignment) Act, 1971, a Division Bench of the Kerala High
Court in MFA No. 401/78 disposed of on 14th of July, 1980,
directed:
"It follows that out of 102 acres 25 acres
over which teak was planted in 1967 and euca-
lyptus was planted in 1955 will be private
forest coming within the Private Forests
(Vesting & Assignment) Act. But since this
area is under the personal cultivation of the
respondent she will be entitled to 15 acres
under Section 3(2) of the Act. The rest 10
acres will vest with the Government.
In the result the appeal is partly
allowed and the order of the lower court is
modified as follows:
It is declared that 75 acres over
which the respondent had planted teak-wood,
orange and soft wood prior to 14th December,
1949, is held to be not a private forest under
the Madras Preservation of Private Forests
Act, 1949 and Kerala Private Forests (Vesting
& Assignment) Act, 26 of 197 1. But of the
rest 2 acres over which the respondent had
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 5
planted cashew is declared to be not a private
forest under Section 2(f)(1)(i)(A) and (C) of
the Act. Another 15 acres under the personal
cultivation of the respondent is also held not
to vest under the above Act under Section 3(2)
of the Act. The Custodian shall demarcate this
15 acres in such a manner that it will be
convenient for the enjoyment of the respond-
ent. The balance 10 acres will vest. with the
Government. With the demarcation and identifi-
cation of that 10 acres the case is sent back
to the Forest Tribunal. If the Custodian has
taken possession of the area declared not to
vest, he will surrender the same to the re-
spondent forthwith ....."
In terms of this judgment 92 acres (being the total of
75 acres + 15 acres + 2 acres) were to be given back to the
appellants. In the process of implementation of this direc-
tion certain lands were returned to the appellants by the
Forest officials. These lands constituted thick forests and
had valuable trees thereon. This fact was realised by the
higher officers of the Department and timber transit permits
were not issued to the appellants when applied for. There-
upon the appellants filed a writ petition before the High
Court for a direction to the State Government and its offi-
cers to issue the requisite transit permits to enable the
appellants to transport the rosewood trees and other
40
timber. The claim contested. The High Court came to the
conclusion:
"It is made clear that the petitioners are not
entitled to any relief with regard to rosewood
and other trees cut from the lands which do
not form part of the lands ordered to be
restored to the petitioner in O .P. No. 4832
of 1983 and are vested in the Government. With
respect to the trees cut from the properties
ordered to be restored to the petitioner,
respondents 1 to 3 are directed to consider
the applications filed by the petitioner for
issue of transit permits and pass appropriate
orders according to law. Before determining
this question also the respondents may give an
opportunity to both the petitioners to put
forward their contentions and a final decision
may be taken after considering their objec-
tions."
This order of the High Court is the subject-matter of the
present appeal.
In an affidavit filed in this appeal by the conservator
and Custodian of Vested Forests it has been accepted that in
terms of the judgment of the High Court in MFA No. 40 1/78,
92 acres were found not to vest in the State under the Act.
In the judgment the survey numbers with the respective
extents had been furnished. It is stated that 12 acres had
not been taken possession of and, therefore, surrender had
to be made of 80 acres only. A further affidavit has been
filed by the said Custodian where it has been said:
"Hence only 80 acres are to be restored and
out of this 56.31 acres have admittedly been
restored already. For the remaining 23.69
acres, Government are pleased to restore the
same as follows vide G.O. Rt. No. 1345/82/AD
dated 24.5.82, in lieu of the land wrongly
handed over to the petitioner.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 5
Survey No. Area to be restored.
1518 10.19 acres
1580 6.03 acres
1580 7.47 acres"
It has been further stated therein that in case any part of
such land is not available, the Government are prepared to
pay reasonable compensation for such shortfall as if the
same had been acquired by the State for a public purpose.
41
We are of the view that the High Court was right in
refusing to act upon the footing that pursuant to the direc-
tion by the High Court about 36 acres of land containing
forest growth had been surrendered to the appellants and,
therefore, they were entitled to appropriate the trees. In
fact within the ambit of the writ petition as filed before
the High Court, the only question that fell for considera-
tion was whether timber transit permits should or should not
be issued to the appellants to enable them to transport the
felled timber from the area which should not have been
delivered to the appellants. Since we do not intend to
differ from the High Court on that issue this appeal de-
serves to be dismissed but with a view to doing complete
justice to the parties and give a final verdict in the
matter we had enquired from Mr. Poti appearing for the
respondent-State on 27.3.1989 as to how Government proposed
to comply with the binding direction of the High Court given
in the first appeal. The affidavit of 24th of June, 1989 by
the Custodian of Vested Forests is in answer to that query.
We would like to reiterate that the appellants are
entitled to return of 92 acres of land and not 80 acres.
This is on the ground that the direction of the High Court
in the first appeal became final and in terms of such direc-
tion 92 acres were to go back to the appellants. Government
had no authority to alter the decision by an .administrative
order as has been done on 22.5.1982. There is no dispute
that 56.31 acres have been restored to the appellants. By
the affidavit of 24th of June, 1989, 23.69 acres have been
offered to be restored from three survey numbers indicated
therein. With the restoration of 23.69 acres the appellants
would have got back 80 acres of land. There would still be
12 acres to be returned to the appellants. The respondents
shall have a direction to trace these 12 acres in the local-
ity and make over vacant possession to the appellants there-
of within four months hence. In case 23.69 acres or any part
thereof as indicated in the affidavit cannot be delivered
possession and the balance 12 acres are not identified and
possession thereof cannot be delivered, the appellants shall
be entitled to compensation in respect of the shortfall out
of 35.69 acres in all which remain to be delivered and
compensation for such shortfall shall be determined as if it
were acquisition under the provisions of the Land Acquisi-
tion Act, the date of the preliminary notification being
deemed to be the date of judgment in MFA 401/78. The direc-
tions indicated above shall be worked out by the respondents
within a total period of six months from today.
The High Court called upon the respondents to consider
the appellants’ plea for timber transit permits in respect
of trees cut from
42
certain other lands. There is no material on record as to
whether that has been complied with. In case the respondents
have not done the same yet they are directed to comply with
the order of the High Court within three months from today.
The appeal is allowed in part. Parties are directed to
bear their respective costs.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 5
G .N. Appeal allowed
partly.
43