K.H. KHAN vs THE STATE OF KARNATAKA
- Court
- Karnataka High Court
- 1 -
CRL.P No. 4986 of 2019
IN THE HIGH COURT OF KARNATAKA AT BENGALURU
TH
DATED THIS THE 9 DAY OF OCTOBER, 2026
BEFORE
THE HON'BLE MR. JUSTICE H.P.SANDESH
CRIMINAL PETITION NO.4986 OF 2019
BETWEEN:
1. K.H. KHAN
AGED ABOUT 67 YEARS
S/O LATE SRI. N.A. KHAN
2. SMT. SHAHEDA BEGUM
AGED ABOUT 63 YEARS
W/O K.H. KHAN
BOTH ARE RESIDING
AT NO.26 (OLD NO.425),
TH
9 CROSS, JAYANAGAR
ND
2 BLOCK
BENGALURU-560011.
3. KARAR AHMED
AGED ABOUT 63 YEARS
S/O LATE SRI. N.A. KHAN
TH
R/AT NO.50, 8 MAIN
ND
2 CROSS, ROSHAN COLONY
TILAK NAGAR
BENGALURU-560011.
…PETITIONERS
(BY SRI. M.T. NANAIAH, SENIOR COUNSEL FOR
SRI. M.R.C.MANOHAR, ADVOCATE)
AND:
1. THE STATE OF KARNATAKA
BY KENGERI POLICE STATION, BENGALURU
REP. BY STATE PUBLIC PROSECUTOR
HIGH COURT COMPLEX
BENGALURU-560 001.
Digitally signed
by DEVIKA M
Location: HIGH
COURT OF
KARNATAKA
- 2 -
CRL.P No. 4986 of 2019
2. K. CHANNAPPA
AGED ABOUT 64 YEARS
R/AT NO.1250/15/5
KANCHANA NILAYA
ST ST
1 MAIN ROAD, 1 CROSS
KENGERI UPANAGARA
BENGALURU-560060.
…RESPONDENTS
(BY SRI. MOHAMMED AYUB ALI, ADDL. SPP FOR R1;
SRI. C.G.SUNDAR, ADVOCATE FOR R2 [ABSENT])
THIS CRIMINAL PETITION IS FILED UNDER SECTION 482
OF CR.P.C PRAYING TO QUASH THE ENTIRE PROCEEDINGS IN
C.C.NO.8921/2019 (CRIME NO.11/2018) REGISTERED BY
KENGERI POLICE STATION, BENGALURU, FOR THE OFFENCES
PUNISHABLE UNDER SECTIONS 406, 420 AND 120-B R/W
SECTION 149 OF IPC, AGAINST THE PETITIONER WHO ARE
ARRAYED AS ACCUSED NO.4, 5 AND 6 RESPECTIVELY AND
CASE IS NOW PENIDNG ON THE FILE OF IV ADDITIONAL CHIEF
METROPOLITAN MAGISTRATE, BENGALURU.
THIS PETITION HAVING BEEN HEARD AND RESERVED
FOR ORDERS ON 28.09.2026, THIS DAY, THE COURT
PRONOUNCED THE FOLLOWING:
CORAM: HON'BLE MR. JUSTICE H.P.SANDESH
CAV ORDER
Heard learned Senior counsel appearing for the
petitioners and learned Additional SPP for respondent
No.1/State. This Court had issued notice to respondent No.2-
complainant and though respondent No.2 is represented
through counsel, but counsel did not turn up.
2. This petition is filed by petitioners, who are
arraigned as accused Nos.4, 5 and 6 praying this Court to
- 3 -
CRL.P No. 4986 of 2019
quash the entire proceedings in C.C.No.8921/2019 arising out
of Crime No.11/2018 registered by the Kengeri Police Station,
Bengaluru, for offences punishable under Sections 406 and 420
read with Section 149 of IPC against the petitioners pending in
the Court of IV Additional Chief Metropolitan Magistrate,
Bengaluru City.
3. The factual matrix of case of respondent No.2-
complainant before respondent No.1 is that he was a (retired)
Deputy Superintendent of Police and in his written complaint,
he has alleged that his daughter by name Dr. Deepa C.V. along
with his son-in-law by name Dr. Nandakishor went near Mysuru
Road, Kengeri site office and both of them have witnessed
Arena No.134/5 advertisement board and demo house. On
enquiry, they came to know that petitioners have entered into
Joint Development Agreement (‘JDA’ for short) for construction
of multi-storied residential apartments with the developers with
M/s. Era Land Mark Limited Company in Sy.No.137/6,
Sy.No.140 and Sy.No.139 totally measuring 2,65,826 sq. ft.
and obtained BBMP khatha in respect of those two sites on
10.05.2011. It is contented that these petitioners are the
owners of said property and in terms of JDA, Power of Attorney
and Addendum agreement, flats will be built by Parinda
- 4 -
CRL.P No. 4986 of 2019
Buildcon Private Limited and the amount can be paid by
installments. Accordingly, Smt. Anjana Sundar, Unit No.31-604,
has entered into an agreement with them to buy the flat and
the same was shown to respondent No.2 and later made
enquiry regarding payment of installments and collected the
broacher and after seeing the demo house and the construction
on 06.06.2011, respondent No.2, his daughter and son-in-law
went together and paid a sum of Rs.1,02,575/- which has been
paid by daughter of respondent No.2 through Cheque in favour
of M/s. Era Land Mark Limited Company and receipt has been
obtained in the site office of Parinda Buildcon Private Limited.
That on 25.06.2011, the said company has sent a welcome
letter to the daughter of respondent No.2 and rate of
Rs.2,400/- per square feet is fixed and flat was also allotted. In
pursuance of the same, on 05.01.2012, a demand letter has
been sent to the daughter of respondent No.2 to pay
Rs.6,39,253/-. Accordingly, the daughter of respondent No.2
paid Rs.6,04,640/- along with service tax through Cheque of
SBI Bank and receipt is also obtained.
4. It is further alleged that the Sales Executive one
Prasanna having given his cell number had assured that he will
get the signature of Senior Officers of the company on behalf of
- 5 -
CRL.P No. 4986 of 2019
the company in the agreement, saying so he has taken the
signature of daughter of respondent No.2 on the agreement
and even inspite of making several visits to the site office, the
said Prasanna has not got the signatures of the officers of the
company. Hence, respondent No.2 called the site office phone,
but nobody responded. On enquiry, they came to know that
office was closed and locked and no officials were there, only
security personnel were there. That on enquiry through the
security personnel, respondent No.2 came to know that only
the foundation has been laid and security guards were
appointed. On enquiry with the guards, they told the land
owners Upkar Developers and Era Company have stopped civil
works. The said companies have collected crores of rupees from
the public by assuring to build the flats and allot them to the
customers, but they cheated the general public. On enquiry, he
came to know that name of Era company has been changed
and also the persons, who are present there told him that they
will construct the flats and give it to the customers after talking
to Upkar Developers. It is alleged that that the said Era Group
and Upkar Developers deliberately given an advertisement to
build apartment and will allot it to the public. That by saying so,
they cheated the daughter of respondent No.2 and the
- 6 -
CRL.P No. 4986 of 2019
respondent No.1, after completing the investigation has filed
the charge sheet. Hence, present petition is filed.
5. The main contention of learned Senior counsel
appearing for the petitioners is that no dispute with regard to
the fact that these petitioners being the owners of land in
Kangeri Village entered into Collaboration Agreement (Joint
Development Agreement) with one M/s. Era Developers, the
Delhi Based Company on 05.07.2008. Simultaneously, the
petitioners also executed General Power of Attorney in favour
of M/s. Era Developers. So also, the petitioners have executed
an Addendum to the Collaboration Agreement on 28.10.2009
(by making title changes in the agreed terms in the
development agreement). On 25.01.2010, M/s. Era Developers
have executed assignment agreement in favour of M/s. Parinda
Buildcon Private Limited. However, these petitioners have not
executed any General Power of Attorney in favour of
M/s.Parinda Developers. It is contended that on 14.07.2010,
petitioners have issued legal notice calling upon developers to
clear the loan amount of Rs.14.50 crores along with interest
and penalty which was obtained by the petitioners from HUDCO
for development of the property. But, developers failed to
comply with the terms of the agreement. Hence, as a result of
- 7 -
CRL.P No. 4986 of 2019
failure and breach of terms of agreement by the developer as
agreed, cancelled the agreement and General Power of
Attorney executed in favour of the developers dated
05.07.2008. The petitioners do not have any personal
knowledge about receipt of the amount by the developer from
respondent No.2 and termination notice was also issued on
17.02.2012 and 22.02.2012 which was also published in the
local newspaper.
6. It is also the contention of the petitioners that on
05.05.2011, BMICAPA issued notice stating that assignee
M/s.Parinda Buildcon Private Limited, developers alone has
signed the application for sanctioned plan without any authority
and called upon them to furnish the signatures of the owners.
But, complaint was registered and police have investigated and
registered the case against Directors of M/s. Era Land Marks
Limited and M/s. Parinda Buildcon Private Limited and these
petitioners have been arraigned as accused. When already
BBMP cancelled the license granted by them for construction
and developers have not done any developmental work,
question of filing the charge sheet against these petitioners
does not arise. The counsel would contend that these
petitioners have not received any amount and there is no
- 8 -
CRL.P No. 4986 of 2019
previty of contract between these petitioners and respondent
No.2-complainant and when the notice was issued and license
was cancelled, question of arraigning these petitioners as
accused does not arise and neither the daughter and son-in-law
of respondent No.2-complainant nor the respondent No.2-
complainant met the petitioners in connection with allotment of
flat No.803-1 and being the owners of the land entered into a
JDA and there was no intention to cheat the customers, much
less the respondent No.2. Hence, there cannot be any criminal
prosecution. The counsel also contend that respondent No.2
has claimed in his complaint the amount of Rs.7,41,828/- has
been paid through Cheques in favour of the builders and this
clearly indicate that alleged amount has been credited to the
account of builder and not to the accounts of the petitioners
and at no point of time, the builders have informed the
petitioners about collecting the said amount. The counsel also
contend that respondent No.2 being the (retired) Deputy
Superintendent of Police, Human Rights Commission have not
contacted the petitioners at any point of time before filing the
complaint and the present complaint was also not filed by the
aggrieved person. The respondent No.2 being the Police Officer
by taking undue advantage of his official position has managed
- 9 -
CRL.P No. 4986 of 2019
to register a false case. Hence, there cannot be any criminal
prosecution.
7. Learned Additional SPP appearing for respondent
No.1/State would vehemently contend that the Court has to
take note that in pursuance of JDA and execution of General
Power of Attorney in the year 2008 as well as Addendum in
2009, all powers are given to the developer and in pursuance of
the same, the complainant made payment and the same is not
denied by the petitioners. The fact that they have executed the
documents of JDA, Power of Attorney and also subsequent
document of Addendum is also not disputed. The counsel also
contend that payments are made when these agreements and
Power of Attorney were in existence and notices are issued
subsequently and cancellation of agreement, if any subsequent
to payments will not create any right in favour of the
petitioners to seek quashing of the proceedings. The
transaction has taken place prior to cancellation and that too, in
pursuance of giving all powers in favour of the developer and in
terms of power given to the developer and subsequent to
executing the document in favour of M/s. Parinda Buildcon
Private Limited by the developer, payments are made in the
month of January 2012 itself and documents are very clear that
- 10 -
CRL.P No. 4986 of 2019
work was undertaken to build the flats and advertisement was
also given and based on the advertisement itself, the
complainant and their family members have visited the spot
and inspected the sites where they intend to put up
construction and thereafter, advanced the money. The
complainant having paid the money, could not start
construction work. The counsel also would contend that the
very contention of learned Senior counsel appearing for the
petitioners that agreement was cancelled and also case was
registered against the developer at the instance of the
petitioners cannot accepted and the same is not a ground to
discharge these petitioners from the criminal case. The specific
allegations are made that all of them joined together and after
collecting the amount, cheated the general public as well as the
complainant. Hence, contention of learned Senior counsel
appearing for the petitioners cannot be accepted.
8. Having heard learned Senior counsel appearing for
the petitioners and learned Additional SPP appearing for the
respondent No.1/State and considering the pleadings of the
petitioners in the petition, it is not in dispute that these
petitioners are the owners of the property. It is also not in
dispute that Collaboration Agreement dated 05.07.2008 was
- 11 -
CRL.P No. 4986 of 2019
executed and apart from that, Power of Attorney was executed
on the same day and so also, petitioners not dispute the fact
that Addendum (Supplementary) to Collaboration Agreement
dated 05.07.2008 was executed on 28.10.2009 i.e., 1½ year of
earlier document of JDA and Power of Attorney. It is also not in
dispute that, in the said Addendum, some minor changes were
made as pleaded by the petitioners.
9. It is also to be noted that complainant gave the
complaint against these petitioners as well as the JDA holder
stating that they made the payment in the month of June 2011
itself. The contention of the petitioners that they gave
termination notice in the year 2012 i.e., on 17.02.2012 and
22.02.2012 to the land developer and also M/s. Parinda
Buildcon Private Limited and there was no cancellation prior to
the said date of transaction of collecting the money from
complainant. But, payments are made based on the earlier
JDA, Power of Attorney and Addendum and claim of the
respondent No.2-complainant is also that payments were made
prior to the said cancellation. The cancellation was also made
by giving notice and paper publication as contented by the
petitioners. It is important to note that the transaction has
taken place prior to cancellation and payments are also not
- 12 -
CRL.P No. 4986 of 2019
disputed and respondent No.2 also relied upon documents as
well as welcome letter addressed to the daughter of the
complainant to M/s. Era Land Marks Family by the developer
which has taken place prior to cancellation. When such being
the case and when the project did not come through and
executing the document of JDA and Power of Attorney and
showing the same itself, the developer had collected the money
even though there was no direct transaction between the
petitioners and also the complainant and petitioners themselves
have not disputed the fact that they have entered into JDA and
executed the Power of Attorney and other documents and
based on those documents, power was given to the developer
to collect the money from the prospective purchasers and
transaction has taken place. The accusation made in the charge
sheet is also very clear that there was an agreement between
these petitioners and accused Nos.1 to 3 and also public
advertisement was given and payments are also made on
06.06.2011 and 25.06.2011 i.e., prior to cancellation.
10. Having received the money, they sent a letter and
even additional payment was also made on 05.01.2012 in
pursuance of the demand and even obtained the signature of
daughter of complainant No.2, but did not get the signature of
- 13 -
CRL.P No. 4986 of 2019
company. Hence, an allegation was made that there was
conspiracy and cheating and the fact that amount was received
on the guise of transaction between these petitioners and also
other accused persons, but did not execute any document for
having received money and specific allegation is made that all
of them joined together and project did not come through, but
the fact that the amount was received is not in dispute. Hence,
I do not find any error on the part of police in investigating the
matter and filing the charge sheet and there was no privity of
contract and the same cannot be considered at this stage and
all these are the defence before the Trial Court whether there
was any conspiracy and whether there was an intention to
cheat at the time of collecting the money. However, if there is
any dispute between the land developer and owner, the same
should not affect the prospective purchasers and filing of
charge sheet against the developer at the instance of the
petitioners is an inter-se dispute between them and merely
because case was registered against the land developer and
others and the same will not come in the way in respect of the
complainant. The payment made by the complainant, in
pursuance of the said project and agreement and hence, the
proceedings cannot be quashed and the matter requires trial.
- 14 -
CRL.P No. 4986 of 2019
11. In view of the discussion made above, I pass the
following:
ORDER
dismissed.
The criminal petition is
Sd/-
(H.P.SANDESH)
JUDGE
ST