NATONAL CENTRE FOR BIOLOGICAL SCIENCES vs M/S URC CONSTRUCTIONS PRIVATE LIMITED

Court
Karnataka High Court

- 1 -
COMAP No. 383 of 2025


TH
RESERVED ON 16 APRIL 2026

IN THE HIGH COURT OF KARNATAKA AT BENGALURU


TH
DATED THIS THE 18 DAY OF JUNE, 2026

PRESENT

THE HON'BLE MR. VIBHU BAKHRU, CHIEF JUSTICE

AND

THE HON'BLE MR. JUSTICE C.M. POONACHA

COMMERCIAL APPEAL NO. 383 OF 2025

BETWEEN:

1. NATIONAL CENTRE FOR BIOLOGICAL SCIENCES
TATA INSTITUTE OF FUNDAMENTAL RESEARCH
BELLARY ROAD
BANGALORE - 560 065
REP BY ITS DIRECTOR
…APPELLANT
(BY SRI ARVIND K. KAMATH, ASGI ALONG WITH
SRI A.K. VASANTHA, ADVOCATE)

AND:







1. M/S URC CONSTRUCTIONS PRIVATE LIMITED
ST TH
NO.810, 1 CROSS, 7 MAIN
ND
H.A.L 2 STAGE
INDIRANAGAR
BANGALORE - 560 038
REP. BY AUTHORIZED SIGNATORY
SHRI V. GANESAN

2. HON'BLE JUSTICE PRADEEP D. WAINGANKAR
(FORMER JUDGE, HIGH COURT OF KARNATAKA)
THE HON'BLE SOLE ARBITRATOR
THE ARBITRATION AND CONCILIATION CENTRE
(DOMESTIC AND INTERNATIONAL)
KANIJA BHAVAN, RACECOURSE ROAD
BANGALORE - 560 001
... RESPONDENTS
(SRI T. SURYANARAYANA, SENIOR ADVOCATE
ALONG WITH SRI PRATIK PANY, ADVOCATE AND
SRI ABHILASH RAJU, ADVOCATE FOR C/R-1;
V/O DATED 24-11-2025, NOTICE TO R-2 IS DISPENSED WITH)


Digitally
signed by
AMBIKA H B
Location: High
Court of
Karnataka

- 2 -
COMAP No. 383 of 2025



THIS COMMERCIAL APPEAL IS FILED UNDER SECTION 13 (1-
A) OF COMMERCIAL COURTS ACT 2015 PRAYING TO SET ASIDE
THE JUDGMENT DATED 28.04.2025 PASSED IN COM.AP.
NO.186/2024 IN THE COURT OF LXXXIII ADDITIONAL CITY CIVIL
AND SESSIONS JUDGE, COMMERCIAL COURT (CCH-84) AT
BANGALORE BY CONFIRMING THE ARBITRAL AWARD DATED
31.08.2024 PASSED BY THE LEARNED SOLE ARBITRATOR IN AC
NO.401/2022 & ETC.

THIS COMMERCIAL APPEAL HAVING BEEN HEARD AND
RESERVED FOR JUDGMENT, COMING ON FOR PRONOUNCEMENT
THIS DAY, JUDGMENT WAS PRONOUNCED AS UNDER:

CORAM: HON'BLE MR. VIBHU BAKHRU, CHIEF JUSTICE
and
HON'BLE MR. JUSTICE C.M. POONACHA

C.A.V. JUDGMENT
(PER: HON'BLE MR. VIBHU BAKHRU, CHIEF JUSTICE)

1. The National Centre for Biological Sciences [ NCBS ] has filed
the present appeal under Section 37(1)(c) of the Arbitration and
Conciliation Act, 1996 [ A&C Act ] impugning an order dated
28.04.2025 [ impugned order ] passed by the learned LXXXIII
Additional City Civil and Sessions Judge, Commercial Court at
Bengaluru [ Commercial Court ] in Com. A.P No.186/2024. NCBS
had filed the said petition under Section 34 of the A&C Act seeking
the setting aside of the arbitral award dated 31.08.2024 [ impugned
award ] passed by an arbitral tribunal comprising Respondent No.2
as the sole arbitrator [ Arbitral Tribunal ].

- 3 -
COMAP No. 383 of 2025


2. The Arbitral Tribunal partly allowed the claims of respondent
No.1 [ URC ], which was a claimant before it. The Arbitral Tribunal
awarded a sum of ` 3,52,50,404/- (Rupees Three Crore Fifty Two
Lakh Fifty Thousand Four Hundred and Four only) along with
interest at the rate of 9% per annum in favour of URC in addition to
a sum of ` 5,00,000/- as costs of the arbitral proceedings. The
Arbitral Tribunal also partly allowed the counter-claims of NCBS to
the extent of ` 18,21,310/- (Rupees Eighteen Lakh Twenty One
Thousand Three Hundred and Ten only) along with interest at the
rate of 9% per annum.
3. By the impugned order, the learned Commercial Court
rejected the NCBS’s petition for setting aside the impugned award.
Aggrieved by the same, the NCBS has preferred the present
appeal.
4. The impugned award was rendered in the context of the
disputes that had arisen between the parties in connection with
their Agreement dated 19.06.2017 [ the Agreement ].
5. Mr. Arvind K. Kamath, learned Additional Solicitor General of
India, who appeared for NCBS, confined the present appeal to
setting aside of the impugned award to the extent of a sum of

- 4 -
COMAP No. 383 of 2025


` 1,47,34,311/- which is the difference in the value of the non-
tendered items [ NT items ] executed by URC. According to NCBS,
the value of the said work (excluding GST – Goods and Services
Tax) was ` 8,18,57,285/- and not ` 9,65,91,596/-, as claimed by
URC and as awarded under the impugned award. The difference
between the two figures is on account of the Goods and Services
Tax [ GST ] component in the said value. Whilst NCBS contends
that the amount of ` 9,65,91,596/-, includes 18% GST, URC
disputes the same.
THE CONTEXT
6. NCBS carries out research in the field of basic sciences,
mathematics including biological sciences, molecules, cells,
tissues, organisms and eco-systems. The Institute for Stem Cell
Biology and Regenerative Medicine (hereinafter referred to as
‘InStem’ ) is another Institute established by the Department of
Biotechnology, Government of India, for carrying out research in
stem cell and regenerative medicine including cancer, neural
diseases, cardiomyopathy, etc.
7. For the purpose of construction of buildings for laboratories
and associated facilities for InStem, comprising Balance Civil, PH,
Firefighting, Electrical, AC and External Development works, NCBS

- 5 -
COMAP No. 383 of 2025


floated an Item Rate Tender and Contract Works Notification dated
22.02.2017 [hereinafter referred to as ' NIT '].
8. URC participated in the bidding process conducted pursuant
to the NIT and emerged as the successful bidder (L1).
Consequently, NCBS issued a Work Order dated 01.06.2017 to
URC, for the contract price of ` 43,57,00,753/- (Rupees Forty Three
Crore Fifty Seven Lakh Seven Hundred and Fifty Three only). A
formal agreement was entered into between the parties on
19.06.2017.
9. The tender documents and the Agreement explicitly
stipulated that the estimated cost of work and the quoted rates
were inclusive of all applicable taxes, including Works Contract Tax
[ WCT ] at 4% and Labour Cess at 1%, which were to be recovered
from the bills. Clause 15 of Section 3 and Clause 37 of Section V of
the tender documents stated that all taxes, except service tax,
would be payable by the contractor, and that any service tax paid
would be reimbursed by NCBS upon proof of payment. Clause 38
also provided for reimbursement of any further tax or levy imposed
by a statute after the last date for receipt of tenders.

- 6 -
COMAP No. 383 of 2025


10. In terms of Clause 2 of the Work Order, URC was required
th
to complete all works within 10 months from the 15 day of the
date of issuance of the Work Order, that is, by 15.04.2018. URC
completed the works, albeit after some delay. The completion
certificate issued indicates that URC completed the works on
20.03.2019, that is, approximately 11 months beyond the stipulated
period. According to NCBS, even as on 27.04.2019, certain works
remained unattended and incomplete, including: (i)rectification of
white patches in PU flooring in the animal holding area; (ii)damage
nd rd
to fire curtains on the 2 and 3 floor service levels;
(iii)commissioning of AC works in the CIFF area; and (iv) other
pending snag points. The actual completion cost of the project,
excluding extra/substituted/deviated items, was ` 32,06,63,371/-. In
addition to the original scope, URC executed various non-tendered,
1
extra, substituted, and deviated works , the value of which was
`
accounted for at 9,65,91,596/-.
11. On account of the aforementioned delay in completion, the
Engineer-in-Charge levied a penalty of ` 1,00,000/- (Rupees One
Lakh only) on URC for the period from 15.11.2018 to 20.03.2019.
URC sought reconsideration of the said levy, but the request was

1
NT Items

- 7 -
COMAP No. 383 of 2025


declined by a letter dated 29.04.2019. Additionally, NCBS claimed
that URC failed to submit daily progress reports as required under
Clause 5 of the General Conditions of Contract, and that it had put
URC on notice that it would recover ` 5,000/- per day for each day's
delay in submitting the said reports. NCBS further claimed that two
rd
fire curtains installed by URC on the 3 floor and two installed on
nd rd
the 2 and 3 service floors were not working due to the burning of
the motors. The replacement cost of the curtains was ` 17,21,310/-,
which was directed to be withheld and recovered from the final bill
of URC.
THE GST DISPUTE
12. Immediately following the execution of the Agreement, the
Government of India rolled out the unified tax regime effective from
01.07.2017. The GST subsumed pre-existing indirect taxes,
including Central Sales Tax, Excise Duty, and VAT.
13. In February 2018, URC formally addressed a communication
to NCBS stating that in terms of the statutory transitions under
Notification No.11/2017-Central Tax (Rate) dated 28.06.2017 and
its corresponding State notification, the works contract execution
attracted a flat GST rate of 18% (9% CGST and 9% SGST).

- 8 -
COMAP No. 383 of 2025


Accordingly, URC demanded full statutory reimbursement of the
18% GST component on all invoices.
14. NCBS claimed that the concessional rate of 12% GST was
applicable under the amending Notification No.24/2017-Central Tax
(Rate) dated 21.09.2017, as it is a fully aided research entity under
the administrative control of the Department of Atomic Energy and
is engaged in non-commercial research activities. NCBS also
disputed the calculation of the reimbursement claim on the ground
that the contract price was inclusive of taxes and that the
components of indirect taxes subsumed under the GST regime
were required to be deducted from the contract price before
applying the applicable GST rate to prevent double taxation and
unjust enrichment.
15. To resolve the specific deadlock over the tax rate
classification, URC approached the Authority for Advance Ruling
[ AAR ], Karnataka, constituted under Section 96 of the Karnataka
Goods and Services Tax Act, 2017. The AAR passed an order
dated 23.09.2019, holding that NCBS did not qualify as a
"government entity" or "governmental authority" as defined in the
Rate Notification. Thus, the concessional rate of 12% was
inapplicable, and the standard rate of 18% GST applied.

- 9 -
COMAP No. 383 of 2025


ARBITRAL PROCEEDINGS AND THE IMPUGNED AWARD
16. Despite the AAR ruling, disputes between the parties
persisted. URC issued a notice dated 25.08.2020 under Section 21
of the A&C Act, invoking the arbitration clause. Thereafter, URC
2
filed a petition under Section 11 of the A&C Act seeking the
appointment of an arbitrator. This court allowed the said petition by
an order dated 30.06.2022, and the Arbitral Tribunal was
constituted by appointing a sole arbitrator.
17. URC claimed that the implementation of the GST regime with
effect from 01.07.2017 necessitated an upward revision of
payments to account for the statutory tax burden of 18%. Their
primary claim involved the recovery of a differential GST sum of
` 2,40,73,564/-, along with pre-reference interest amounting to
`
2,29,40,107/-. URC also claimed pendente lite and future interest
at 18% per annum.
18. URC argued that their quoted tender rates did not include
WCT (4%) and Labour Cess (1%) because they were registered as
regular dealers under the VAT regime and had not opted for any
composite tax scheme. URC’s turnover also exceeded the
specified amount. URC claimed that the GST computed at 18% of

2
CMP No.159 of 2021

- 10 -
COMAP No. 383 of 2025


the contract value was an additional statutory liability triggered by
the change in the law.
19. NCBS filed its Statement of Defence and Counter Claim.
NCBS argued that the contract price was composite and inclusive
of all pre-GST statutory levies, including WCT and Labour Cess.
They contended that URC’s failure to isolate and deduct these
subsumed taxes from the contract baseline resulted in an inflated
GST demand. NCBS asserted that the actual amount paid to URC
had already exceeded the legally adjusted contract liability, as they
`
had already paid 39,86,71,646/- to URC, whereas the net payable
amount after permissible deductions was only ` 38,56,34,443/-.
Additionally, NCBS sought damages for project delays and
defective works, claiming that the fire curtains were nonfunctional
and that remedial flooring works were required. Thus, NCBS
sought recovery of the excess payment of ` 1,30,37,202/-, along
with interest of ` 29,04,336/- and costs of ` 30,00,000/-.
20. The Arbitral Tribunal framed the following issues for
determination:
“ 1. Whether the claimant proves that the rate of GST
leviable on the invoices raised by it for the work carried
out by the claimant under the agreement dated
19.06.2017 is at the rate of 18% and not at the
concessional rate of 12%?

- 11 -
COMAP No. 383 of 2025



2. Whether the claimant is entitled to Rs.2,10,12,266
towards the differential GST amount due under the tax
invoices raised for the work done and whether the same
has been paid by the respondent?

3. Whether the claimant proves that Works Contract Tax
(WCT) is’ included in the Value Added Tax (VAT)
component of the claimant's bid submission and is not
over and above the Value Added Tax?

4. Whether the claimant proves that it is entitled to an _
interest on sum of Rs.2,10,12,266 towards pre
reference and pendent lite interest at the rate of 18%
per annum?

5. Whether the claimant is entitled to post award interest
on the award amount at the rate of 12% per annum?

6. Whether ‘the respondent proves that it is entitled to
recover a sum of Rs. 2,32,95,126 from the claimant
towards various recoveries as indicated in para 24 of
the statement of defence?

7. Whether the respondent proves that the respondent
has paid an excess amount of Rs.1,30,37,202 ‘to the
claimant which the respondent is entitled to recover
from the claimant together with interest at the rate of
18% per annum?

8. Whether the claimant is entitled to arbitration and
legal costs?

9. Whether the respondent is entitled to the claim of Rs.
30 lakhs towards cost a including other legal and
arbitration expenses?

10. What award or order? ”

21. The Arbitral Tribunal answered the first issue by referring to
the AAR’s order dated 23.09.2019 and accepted that GST at the

- 12 -
COMAP No. 383 of 2025


rate of 18% was applicable to NCBS in respect of the present
works contract.
22. The impugned award sets out a tabular statement detailing
the differences between the parties' calculations. The said
statement indicated that the difference in the amounts was on four
counts:
(i) Rs.1,47,34,311 on account of the value of NT Items
exclusive of GST. Whilst URC claimed that the value
was Rs.9,65,91,596, NCBS claimed that it was
Rs.8,18,57,285/-;
(ii) Rs.63,370/- on account of the difference in the calculation
of the amount of VAT and Excise Duty included in the
contract price. Whilst URC claimed that taxes of the
aggregate amount of Rs.3,33,98,702 were included in the
contract price, NCBS computed the said amount at
Rs.3,34,62,071;
3
(iii) Rs.1,19,26,211/- on account of WCT . URC claimed that it
was not liable to pay WCT; therefore, the WCT was not
included in the contract price. NCBS claimed that WCT at
the rate of 4% was included in the contract price and was
liable to be reduced from the contract value to determine
the base value of the contract exclusive of taxes; and
(iv) Rs.18,21,310/-, which NCBS claimed was liable to be
recovered from URC on account of a penalty of an amount

3
Works Contract Tax

- 13 -
COMAP No. 383 of 2025


of Rs.1,00,000/- and Rs.17,21,310/- on account of the
value of fire curtains, which were not supplied.

23. In regard to Issues No. 2 and 3, the Arbitral Tribunal noted
that there was no dispute that the value of work after rebate of
3.3% was ` 31,00,81,480/-.
24. The Arbitral Tribunal accepted URC’s claim that the value of
NT items was ` 9,65,91,596/-, exclusive of GST, relying upon the
undisputed final bill signed by URC and certified by the engineers
of NCBS. The said bill reflected the value of NT items as
` 9,65,91,596/- “full and final” without any separate addition of GST,
in contrast to the tendered items where GST of 6% (interim) was
separately added.
25. The Arbitral Tribunal accepted that value of VAT/ED included
in the contract value was ` 3,33,98,702/- as claimed by URC as
against ` 3,34,62,071/- as computed by NCBS. The Arbitral
Tribunal held that the difference of ` 63,370/- was not significant.
26. On the question of reduction of WCT from the contact value,
the Arbitral Tribunal held that since URC is a regular VAT assessee
`
with annual turnover exceeding 50 lakhs, it was not assessable to
WCT at 4%, and therefore, deducting both VAT and WCT from the

- 14 -
COMAP No. 383 of 2025


contract price would amount to double taxation. Accordingly
rejected NCBS contention that ` 1,19,26,211/- was required to be
deducted from the contract value to determine the value exclusive
of taxes.
27. On this basis, the Arbitrator accepted the taxable base for
GST at 18% as ` 37,32,74,374/-, resulting in a GST liability of
` 6,71,89,387/-, and a total amount payable to URC of
` 44,04,63,762/-. After deducting agreed recoveries of
`
2,14,73,817/- towards income tax surcharge, labour cess, TDS,
mobilization advance recovery, electricity charges, etc., the net
amount payable came to ` 41,89,89,945/-. Deducting the total
amount already paid of ` 39,86,71,646/-, the Arbitrator arrived at the
balance principal amount payable to URC as approximately
` 2,03,18,299/-.
28. While answering Issue No.4 on pre-reference interest, the
Arbitrator calculated pre-reference interest at ` 1,02,29,430/-,
making the total sum as on the date of reference at ` 3,05,47,729/-.
In determining Issue No.5, the Arbitral Tribunal computed pendente
`
lite interest at 9% as 47,02,675/-. Thus, the Arbitral Tribunal
awarded an amount of ` 3,52,50,404/- along with post-award

- 15 -
COMAP No. 383 of 2025


interest at 9% per annum from the date of the impugned award till
the date of payment.
29. The Arbitral Tribunal also allowed the counter-claims to the
extent of ` 18,21,310/- comprising the penalty of ` 1,00,000/-
imposed for the period of delayed completion, and ` 17,21,310/-
towards the defective fire curtains, with interest at 9% per annum
from the date of the impugned award till the date of payment.
30. The dispositive part of the impugned award is set out below:
“i. The claim petition filed by the Claimant is partly
allowed with cost.

ii. The Claimant is entitled to recover from the
Respondent a sum of Rs.3,52,50,404/- (Rupees Three
Crores Fifty Two Lakhs Fifty Thousand Four Hundred
and Four Only) together with interest at 9% per annum
from the date of award till the date of payment.

iii. The counter-claim filed by the Respondent is partly
allowed. iv. The Respondent is entitled to recover a
sum of Rs.18,21,310/- (Rupees Eighteen Lakh Twenty
One Thousand Three Hundred and Ten Only) from the
Claimant together with interest at 9% per annum from
the date of award till the date of payment.

v. The Claimant is entitled to Rs.5,00,000/- (Rupees
Five Lakhs Only) towards the cost of this arbitration
proceedings including Advocate fee from the
respondent.

vi. There shall be a lien on this Arbitral Award for any
unpaid costs and Arbitrator's Fee not having been
deposited, if any, by any of the parties as contemplated
under Rule 28 (6) of the Arbitration and Conciliation
Centre Rules, 2012 framed by Arbitration & Conciliation
Centre Bengaluru (Domestic & International).

- 16 -
COMAP No. 383 of 2025



vii. The Claimant is liable to pay stamp duty on this
Award as per the provisions contained in Karnataka
Stamp Act.”

IMPUGNED ORDER
31. NCBS preferred a petition under Section 34 of the A&C Act
seeking the setting aside of the impugned award. NCBS assailed
the award essentially on three fronts. First, it claimed that the final
value of the NT items was inclusive of GST at 18%, and that the
Arbitral Tribunal had erred in concluding otherwise. Second, it was
contended that WCT was a levy that existed prior to the
introduction of the GST regime, and 4% GST is deemed to have
been included in the price quoted by URC. Thus, the said amount
is required to be reduced from the amount payable. And, third the
Arbitral Tribunal had erred in awarding the interest as there is no
clause in the Agreement contemplating payment of interest.
32. The learned Commercial Court did not accept that the
impugned award warranted any interference on the grounds as
urged by NCBS. The learned Commercial Court found that the
final bill specifically mentioned GST at the rate of 6% in respect of
the Bill of Quantities [ BOQ ] items, which was granted towards
interim relief. The Commercial Court noted that, since there is a

- 17 -
COMAP No. 383 of 2025


dispute as to whether GST was payable at 12% or 18%, NCBS had
agreed to pay 6% GST as interim relief. However, the Final Bill did
not include the GST component in respect of NT items and,
therefore, the value of NT items did not include any component of
GST. Paragraph 46 of the impugned order is set out below:
“However, the contention of the employer is that the
said sum stated in the final bill is inclusive of GST of
18%, and if the 18% GST is deducted therefrom, it
comes to Rs.8,18,57,285, which is the value of the
non-tendered items as claimed by the employer. If this
final bill is closely perused, it is noted that at row H,
which is above the non-tendered items, GST of 6% is
added (towards interim relief of GST because at that
time, employer was still contending that, GST is 12%
and not 18% and the difference of 6% GST was given
as interim relief). But the GST component is not added
for non-tendered items. Therefore, the only
conclusion to be drawn is that the sum of
Rs.9,65,91,596, which is given as the total of the
non-tendered items, is exclusive of GST, to which
18% GST has not been added.”

33. The learned Commercial Court also rejected the contention
that WCT was required to be reduced from the contract price as
URC was not assessable to such taxes and thus, the same was not
included in the contract price. The learned Commercial Court also
found no merit in the contention that the award of interest at the
rate 9% per annum was unsustainable.

- 18 -
COMAP No. 383 of 2025


34. In view of the above, the learned Commercial Court passed
the impugned order dismissing NCBS’s petition to set aside the
impugned award.
SUBMISSIONS
35. Mr. Kamath, learned Additional Solicitor General appearing
for NCBS, has confined the present appeal to assailing the
impugned award insofar as it accepted URC's claim that the value
of NT items excluding GST, is ` 9,65,91,596/-. The learned ASG
had also filed additional written submissions expressly stating that
NCBS confines its contention to "the sole issue of whether non-
tendered works valued at ` 9.65 crores is inclusive of 18% GST or
not". Thus, the controversy is narrowed down to the inclusion of a
sum of ` 1,47,34,311/-, which is mentioned at serial No.5 of the
tabular statement set out in the impugned award and as
reproduced herein before. In the aforesaid view, it is not necessary
for this Court to examine any other dispute which was the subject
matter of arbitration before the Arbitral Tribunal.
36. The learned ASG contended that during the execution of the
work, additional non-tendered works were carried out and running
bills were raised. He referred to a tabular statement set out as
Annexure R5. The statement contained a statement of the value of

- 19 -
COMAP No. 383 of 2025


RA bills. He contended that the said submission clearly indicated
that the total of RA bills in respect of NT items aggregated to
` 9,65,91,596/-. He also referred to RA bill Nos. 6, 8, 9, 10, and 14
and pointed out that the values of the said bills conformed to those
mentioned in Annexure-R5. He also pointed out that the said bills
included CGST at 9% and KGST at 9%. Thus, the said value
included total GST of 18%. He submitted that the aforesaid
documents clinched the issue whether GST was included in the
figure ` 9,65,91,596/- which reflected the aggregate value of NT
works. He contended that the said documents had been ignored
by the Arbitral Tribunal. Thus, vitiating the impugned award by
patent illegality.
37. Mr T.Suryanarayana, learned Senior Counsel appearing for
URC, countered the aforesaid submissions. He submitted that one
of the principal disputes regarding the liability to pay GST stems
from the controversy whether GST was leviable on the supply at
the rate of 12% or 18%. It was NCBS's contention that it was a
government organisation and, therefore, GST at the concessional
rate of 12% was payable on the supply. He submitted that the issue
was concluded by the AAR's ruling. He submitted that in view of
the said disputes, NCBS had certified the work done at the pre-

- 20 -
COMAP No. 383 of 2025


GST rates agreed in respect of the BOQ items and with 12% GST
in respect of NT items. However, subsequently, NCBS agreed to
pay the additional 6% GST on BOQ items as an interim relief.
However, that, too, was withheld at the time of the final settlement.
He contended that the said interim relief was only in respect of
BOQ items and not NT items. He submitted that NT items were
always certified at the rate of 12% GST, which was admitted by
NCBS's witness (RW1) in his cross-examination. He referred to the

following extract from the transcript of the cross-examination:
"The contents of RA bill Ex.R7(p) are all true and
correct. The amount of Rs.9,65,91,596/- shown in
column No.2 upto date amount refers to extra/
substitute/ deviated items. The said amount includes
GST component also at 12%. It is false to suggest that
the GST at 12% is not included in the amount of
Rs.9,65,91,596/-."

38. He submitted that the said statement clearly evidenced that
` 9,65,91,596/- includes only 12% GST and URC's claim is only in
respect of the differential amount of 6% GST. He also referred to
paragraph 17 of the impugned award which reads as under:
"17. Coming to item No.9 regarding the payment of
GST @ 18%, as per Claimant, the Respondent is
liable to pay Rs.6,71,89,387/- whereas according to
the Respondent it is liable to pay Rs.6,23,79,087/-.
The Claimant has explained as to how it has arrived at
that figure in the comparative statement. According to
the Claimant, they paid Rs.2,68,55,573/- towards GST
implication over and above the value of original
contract executed. In addition to that they cleared

- 21 -
COMAP No. 383 of 2025


additional GST implications in respect of additional
non-tendered item work amounting to Rs.69,36,113/-.
Thus, the Claimant paid a sum of Rs.6,71,89,387/-
(Rs.3,33,98,702 + 2,68,54,573 + 69,36,113) towards
18% GST. The Respondent failed to establish that it
is liable to reimburse an amount of Rs.6,23,79,087/-
and not Rs.6,71,89,387/-. After deducting VAT and
ED amount of Rs.3,33,98,702/- and adding GST
amount of Rs.6,71,89,387/-. The total amount
payable to the Claimant comes to Rs.44,0463,762/-
and not Rs.40,89,29,570/- as calculated by the
Respondent."

39. He contented that the total GST at the rate of 18% as paid by
URC was quantified at ` 6,71,89,387/-, which comprised of three
components, – ` 3,33,98,702/- (being the tax component embedded
in the values both BOQ and NT items as certified by NCBS),
` 2,68,54,573/- (being the additional GST implication over and
above the tax component embedded in the certified value of BOQ
items); and ` 69,36,113/- (being the additional GST implication over
and above the tax components embedded in the certified value of
NT items). He submitted that URC had claimed and was awarded
only ` 69,36,113/- as reimbursement for additional GST and not
`
18% on the sum of 9,65,91,596/- as contented by NCBS.
40. Insofar as NCBS's reliance on the tax invoices is concerned,
he submitted that in a few initial invoices raised, the value of NT
items and the tax thereon were shown separately. In all other

- 22 -
COMAP No. 383 of 2025


remaining invoices, the value of BOQ and NT items was
aggregated, and the tax thereon was computed. He contended that
initially, URC had raised tax invoices with 18% GST. However,
NCBS failed to pay the invoiced amount with 18% GST. URC, on
NCBS's instructions, substituted the invoices with 12% GST and
issued credit notes. After the AAR had ruled that NCBS was liable
to pay GST at the rate of 18%, URC filed revised returns, which he
submitted would be evident from the GST returns he filed. He
contended that, since the dispute involved a question of fact, the
decision of the Arbitral Tribunal must be accepted as final. He
submitted that this Court cannot, in the proceedings under Section
37 of the A&C Act, reappreciate the evidence and review the
arbitral award.
41. He referred to the decision in the case of Bombay Slum
Redevelopment Corporation Private Limited v Samir Narain
4
Bhojwani and, on the strength of the said decision, contended
that the power to remand should be exercised only in exceptional
cases and not as a matter of routine. He also referred to the recent
decision of the Supreme Court in Punjab State Civil Supplies
Corporation Limited and Another vs. Sanman Rice Mills and

4
(2024) 7 SCC 218

- 23 -
COMAP No. 383 of 2025


5
Others and contended that the scope of intervention in arbitral
matters was prohibited, if not absolutely barred. He contended that
the appellate court could not re-adjudicate the dispute on merits.
REASONS AND CONCLUSIONS
42. As noted above, the controversy in the present case is in a
narrow compass. There is no cavil over the proposition that the
scope of interference in an arbitral award is confined only to the
grounds as set out in Section 34 of the A&C Act. This Court, while
considering an appeal from an order dismissing an application
under Section 34 of the A&C Act to set aside an arbitral award,
cannot reappraise the evidence and adjudicate the disputes as a
first appellate court. The examination under Section 34 or 37 of the
A&C Act is confined to determining whether the impugned award is
liable to be set aside on the grounds as set out in Section 34 of the
A&C Act. In the present case, NCBS has impugned the award on
the ground of patent illegality.
43. NCBS's contention that the impugned award is vitiated by
patently illegality is premised on the basis that the Arbitral Tribunal

had ignored vital evidence.

5
2024 SCC OnLine SC 2632

- 24 -
COMAP No. 383 of 2025


6
44. In Delhi Airport Metro Express (P) Ltd. vs. DMRC , the
Supreme Court had observed as under:
“29. ...The conclusions of the arbitrator which are
based on no evidence or have been arrived at by
ignoring vital evidence are perverse and can be set
aside on the ground of patent illegality.”

45. In Ssangyong Engineering and Construction Co. Ltd. vs.
7
National Highways Authority of India (NHAI) , the Supreme

Court had also observed as under:
“ 41. What is important to note is that a decision which is
perverse, as understood in paras 31 and 32
of Associate Builders [ Associate Builders v. DDA ,
(2015) 3 SCC 49 : (2015) 2 SCC (Civ) 204] , while no
longer being a ground for challenge under “public policy
of India”, would certainly amount to a patent illegality
appearing on the face of the award. Thus, a finding
based on no evidence at all or an award which ignores
vital evidence in arriving at its decision would be
perverse and liable to be set aside on the ground of
patent illegality. Additionally, a finding based on
documents taken behind the back of the parties by the
arbitrator would also qualify as a decision based on no
evidence inasmuch as such decision is not based on
evidence led by the parties, and therefore, would also
have to be characterised as perverse.”

46. In this view, the only issue to be examined is whether the
Arbitral Tribunal has ignored material or evidence that is vital for

adjudicating the subject disputes.

6
(2022) 1 SCC 131
7
(2019) 15 SCC 131

- 25 -
COMAP No. 383 of 2025


47. Before proceeding further, it would be relevant to refer to the
Arbitral Tribunal's reasoning for accepting the URC's contention
that the amount ` 9,65,91,596/- of NT items excluded GST at the
rate of 18% per annum. Paragraph 13 of the impugned award,
which sets out the Arbitral Tribunal's reasoning for accepting the
URC's claim is set out below:
"13. As per the procedure prescribed the Claimant
submitted the final bill for payment to the Engineer in-
charge which is marked as Ex.R7(p) which is relied
upon by the Respondent. Its contents have been
admitted as true and correct by RW-1. If we look at the
bill produced at Ex.R7 (p) it is evident that the same has
been scrutinised and verified by the Engineer
(Electrical) NCBS, EIC (E & HAVC), NCBS, EIC (Civil),
NCBS, Tech Assistant (Civil) who have signed the bill
for having verified the same. The amount shown therein
under various heads has been verified by them and
upon verification, they certified the amount for non-
tendered item work as Rs.9,65,91,596/- exclusive of
GST at 18%. The amount of Rs.8,18,57,285/- shown by
the Respondent is not based on any evidence. It is
contrary to the amount shown and certified in Ex.R7(p).
As such, an amount of Rs.40,66,73076/- show item
No.6 of the comparative statement has been calculated
correctly."

48. As apparent from the above, the only evidence noted by the
st
Arbitral Tribunal was the 21 and final bill. A copy of the said bill
has been produced before this court. The said bill contains a
tabular statement setting out various works and their final value.
The figures are written in red ink against printed figures, which the

- 26 -
COMAP No. 383 of 2025


parties agree were the amounts as settled. At serial No.(I), the
figure in red ink has been scored out, and a figure in
` 4,13,55,937/25 is written in blue ink. At the bottom of the table, the
words ‘measurement and bill accepted in full and final’ are
handwritten in blue ink, and the figure of ` 9,65,91,596/- is noted
against the said statement. The said words and figures appear to
be in the same handwriting and ink as those used in the signatures
appended on behalf of URC.
49. Both parties had relied on the above-mentioned statement as
st
recorded in the 21 and final bill. Whilst it is contended by NCBS
that the words 'full and final' left no scope for URC to demand any
further sum on account of GST, which was already included. On
the other hand, URC contended that the said figure did not include
the incremental value of GST.
50. However, as noted above, it is not contended on behalf of
URC that the price of NT items does not include a GST component;
on the contrary, it is contended that their value includes GST at
12%, not 18%. The contract price (which is the agreed price for
BOQ items) was inclusive of taxes as they were leviable at the
material time. There is no dispute that with the rollout of the GST
regime, NCBS was liable to reimburse URC for the GST imposed

- 27 -
COMAP No. 383 of 2025


on the supply. The contract price was required to be adjusted for
the tax element that was leviable prior to the GST tax coming into
force with effect from 01.07.2017. Thus, the taxes payable by URC
were required to be reduced from the contract price arrived at the
base value (contract price less the element of tax) and GST was
payable on the said amount. NCBS was liable to pay the
incremental amount, being the difference between the quantum of
tax included in the contract price and GST payable on the supply.
However, as far as NT items are concerned, it is not disputed that
no such exercise is required to be conducted, as the same were
not included in the BOQ items and, consequently, in the contract
price. Thus, NCBS was liable to pay for NT items and the
applicable GST.
51. The question of whether the applicable GST rate was the
concessional rate of 12% or 18% did not survive in view of the
AAR’s ruling. Concededly, NCBS is liable to pay GST at the rate of
18%. Thus, the Arbitral Tribunal was required to address the issue
of whether the figure ` 9,65,91,596/- included GST at the rate of
18%.

- 28 -
COMAP No. 383 of 2025


st 8
52. The 21 and final bill referred to by the Arbitral Tribunal
does not expressly indicate whether it was inclusive of GST or
whether the value excluded GST at the rate of 18%. If at all, the
words that the value is "full and final" would support the NCBS's
contention that the figure was a rounded and final figure. However,
the Arbitral Tribunal’s interpretation of the said bill may not be
amenable to review in proceedings under Section 34 of the A&C
Act. However, there was other material on record that is relevant
for addressing the dispute, which was not considered by the
Arbitral Tribunal.
53. NCBS has referred to a statement (Annexure-R5). The said
statement sets out the break-up of the amount of ` 9,65,91,596/-.
The said tabular statement is set out below:
Sl. BILL
No SUBMITTED
VALUE
CERTIFIED
EXECUTED
VALUE AS
PER
ORIGINAL
CONTRACT
CERTIFIED
EXECUTED
VALUE AS
PER
ORIGINAL
CONTRACT
AFTER
REBATE
CERTIFIED
EXTRA
/DEVIATED/
SUBSTITUTE
VALUE
4% WCT VALUE
AFTER
WCT/VAT/ED
FROM
ORIGINAL
CONTRACT
GST @ 18%
ON
COLUMN
10
GST @
18% ON
EXTRA/
DEVIATED
/SUBSTIT
UTED
ITEMS
BASIC
VALUE OF
EXTRA
/DEVIATED
/
SUBSTITU
TE ITEMS
1 2 3 4 6 7 9 10 11 12 13
M.Adv A

M.Adv B

S.Adv C

RAB-04 D 9,023,385 9,040,269 8,741,941 336,228 8,405,712.58 1,513,028


8
Marked as R7

- 29 -
COMAP No. 383 of 2025


RAB-05 E 8,930,068 8,944,378 8,649,214 332,662 8,316,551.61 1,496,979

RAB-06 F 19,130,428 18,466,123 17,856,741 664,305 686,798 17,169,943.24 3,090,590 562,970.34 101,335

RAB-07 G 10,691,448 10,690,060 10,337,288 397,588 9,939,700.18 1,789,146

RAB-08 H 22,474,124 18,516,127 17,905,095 4,005,441 688,658 17,216,437.15 3,098,959 3,394,441.53 610,999

RAB-09 I 10,138,869 9,442,824 9,131,210 695,221 351,200 8,780,010.45 1,580,402 589,170.34 106,051

RAB-10 J 10,752,987 10,573,113 10,224,200 89,196 393,238 9,830,961.86 1,769,573 75,589.83 13,606

RAB-11 L 4,435,850 4,435,850 4,289,467 164,980 4,124,487.05 742,408

RAB-12 M 16,402,611 15,088,420 14,590,502 1,269,248 561,173 14,029,328.85 2,525,279 1,075,633.90 193,614

RAB-13 N

RAB-14 O 43,848,622 26,580,637 25,703,476 16,681,648 988,595 24,714,880.55 4,448,678 14,136,989.83 2,544,658

RAB-15 P 32,673,594 31,926,903 30,873,315 733,038 1,187,435 29,685,879.81 5,343,458 621,218.64 111,819

RAB-16 Q 41,398,682 34,777,519 33,629,861 6,621,200 1,293,456 32,336,404.68 5,820,553 5,611,186.44 1,010,014

RAB-17 R 40,525,815 33,980,110 32,858,766 6,545,588 1,263,799 31,594,967.06 5,687,094 5,547,108.47 998,480

RAB-18 S

RAB-19 T 70,972,537 57,087,193 55,203,316 13,885,760 2,123,204 53,080,111.53 9,554,420 11,767,593.22 2,118,167

REMOVAL
OF ITEMS
FROM
ORIGINAL
CONTRACT
AND
SHIFTED TO
EXTRA
ITEMS
-23,586,267 -22,807,920 23,586,267 -877,228 -21,930,691.73 -3,947,525 19,988,361.86 3,597,905

RAB-FINAL U 84,022,838 54,700,113 52,895,009 21,814,684 2,034,423 50,860,586.04 9,154,905 18,487,020.12 3,327,664

VAT/ED
PORTION AS
PER
M/S.URC
-33,462,071 -6,023,173
TOTAL RA 425,421,858 320,663,371 310,081,480 96,591,596 11,926,209 264,693,200 47,644,776 81,857,285 14,734,311
BILLS


54. There is no dispute as to the value of the bills submitted by
URC. The tabular statement sets out the value of the Bills and the
NT items included in them. The sum total of the value of the NT

- 30 -
COMAP No. 383 of 2025


items included in the Bills adds up to ` 9,65,91,596/-. It is pointed
out that RA bill Nos.6, 8, 9, 10 and 14 are on record, which are the
invoices which separately refer to the value of NT items. These
invoices clearly indicate that the bills raised include 18% GST.
Illustratively, RA bill No.6 includes certified value of NT items
valued at ` 6,64,305/-. URC's invoice for the same, which is on
record, indicates a taxable amount of ` 5,62,970/-, Central GST at
` 50,667/- and State GST at ` 50,667/- and the aggregate value,
`
inclusive of GST, is 6,64,304/-. There is no dispute that the
invoices on record were issued by URC. Thus, undeniably, at least
some of the values of NT items as mentioned in the tabular
statement include GST at the rate of 18%.
55. However, the Arbitral Tribunal had rejected the NCBS's
contention that the value of NT items was inclusive of 18% GST on
the ground that it had failed to establish the same. It is contended
on behalf of URC that some of the initial bills had included the
value of extra items, inclusive of GST at the rate of 18%. However,
subsequent bills did not include the value of GST.
56. URC has also filed memo dated 03.03.2026 setting out the
tabular statement which included reference to the invoices and a
total value of GST at 18%. The value of the said items is reflected

- 31 -
COMAP No. 383 of 2025


as ` 10,35,32,563/-. Thus, according to the said statement, a
part of GST was not included in the aggregate amount of
` 9,65,91,596/-.
57. We may now refer to the tabular statement as set out in the
impugned order, which indicates the difference in the computation
of the amount payable by NCBS on account of GST. The said
statement is set out below:
STATEMENT SHOWING ACTUAL GST PAYABLE AND DIFFERENCE
BETWEEN URC VS NCBS
NCBS
Calculations
as per Ex-R-8
Sl. As per M/s
Description
No.
Difference
URC
Value of bill
1 42,54,21,858 42,54,21,858
submitted
Value of original
2 contract 32,06,63,371 32,06,63,371
executed
Rebate 3.3% of
3 original contract 1,05,81,891 1,05,81,891
value
Value of work
4 31,00,81,480 31,00,81,480
after rebate
Value of Non
5 9,65,91,596 8,18,57,285 (1,47,34,311)
Tendered (NT)
items
Total Executed
6 40,66,73,076 39,19,38,764
Value including

- 32 -
COMAP No. 383 of 2025


NTI items
VAT & ED
7 3,33,98,702 3,34,62,071 (63,370)
Amount
8 Less WCT 4% - 1,19,26,211 (1,19,26,211)
Basic Value
9 excluding GST 37,32,74,374 34,65,50,483
Value
GST Amount
10 6,71,89,387 6,23,79,087
(18%)
Total Amount
Payable as per
CPWD format
after deducting
VAT/ED and
adding 18%
GST
A
44,04,63,762 40,89,29,570
Less Statutory

Deductions
Income Tax TDS
Surcharge on
94,65,297 94,65,297
Income Tax TDS
Labour Cess 45,25,426 45,25,426
TDS under GST 30,52,168 30,52,168
Recovery
towards
Mobilization
advance interest
– work

Recovery
towards
Mobilization
advance interest
– plant and

40,32,169 40,32,169

- 33 -
COMAP No. 383 of 2025


machineries
Electricity
Charges 3,98,757 3,98,757
Recover
Penalty 1,00,000
Misc.
Recoveries
towards Non
supply of
curtains

17,21,310 (18,21,310.00)
B Total 2,14,73,817 2,32,95,127 (18,21,310.00)
NET amount
C 41,89,89,945 38,56,34,443
payable (A-B)
Cumulative
D amount paid till 39,86,71,646 39,86,71,646
12.08.2022
Balance
E Amount 2,03,18,299 -1,30,37,203
Payable (C-D)

58. It is apparent from the above that URC’s calculation is based
`
on the premise that the sum of 9,65,91,596/- at Serial No.5 in the
above table includes no element of GST and is therefore, included
in the amount of ` 40,66,73,076/- (at serial No.6) being the total
value of the works executed including NT items and in the amount
of ` 37,32,74,374/- (at Serial No.9) being the value of works
exclusive of GST. The GST payable is computed at ` 6,71,89,387/-.
The said amount is computed at 18% of the basic value of

- 34 -
COMAP No. 383 of 2025


` 37,32,74,374/- which includes the value of NT items of
` 9,65,91,596/-. This would amount to calculating GST on the value
of NT items, which undisputedly include an element of GST.
59. As noted above, according to NCBS the said figure includes
element of GST of ` 1,47,34,311/-. The learned ASG has been
unable to clearly establish the same. However, it is clearly
9
established that at least four bills (RA Bill Nos.6, 8, 9 and 10 )
included bills for NT items, and the value of those items includes
10
GST aggregating ` 8,31,520/- .
60. The GST on bills for NT items are also reflected in the
tabular statement filed on behalf of URC by a memo dated
26.02.2026.
61. It is not necessary for this Court to examine the record to
ascertain as to the exact amount of GST that may have been
included in the figure of ` 9,65,91,596/-. As that is the question that
is required to be addressed by the Arbitral Tribunal. Suffice it to
state that there is evidence on record, including RA bills and certain
extracts provided by the parties, which clearly establish that the

9
` ` `
1,01,334/- in RA Bill No.6, 6,11,018/- in RA Bill No.8, 1,06,050/- in RA Bill No.9 &
` 13,118/- in RA Bill No.6,
10
CGST of ` 4,15,760/- & SGST of ` 4,15,760/-

- 35 -
COMAP No. 383 of 2025


said amount of ` 9,65,91,596/- includes an element of GST.
Therefore, computing GST at 18% on the said amount is ex facie
erroneous.
62. We also note that there is some material on record which
would support the contention that the amount of ` 9,65,91,596/- did
not include GST to the full extent of 18%. The said material
includes certain communications which indicate that NCBS was not
clearing bills with 18% GST but had accepted that GST was
payable at 12%. This fact is also admitted in the cross-examination
of RW1, which was referred to by the learned counsel for URC.
However, we find that the Arbitral Tribunal has not considered any
material or evidence on record but, has accepted URC’s contention
that the amount of ` 9,65,91,596/- did not include GST only by
st
referring to the 21 and final bill and that NCBS has failed to
establish that the said value includes GST.
63. In view of the above, the impugned award, to the extent that
it proceeds on the basis that the value of NT items exclusive of
GST is ` 9,65,91,596/-, is set aside. The said conclusion ignores
that the said amount is an aggregate of the amount included in the
invoices and bills, and at least some of those invoices, which are
on record, expressly include 18% GST. Failure to consider such

- 36 -
COMAP No. 383 of 2025


relevant and vital evidence renders the impugned award vulnerable
on the grounds of patent illegality.
64. As a consequence of the partial setting aside of the
impugned award, the amount of GST and interest as awarded
would be required to be recomputed.
65. Having stated the above, it is also necessary to observe that
NCBS’s contention that ` 9,65,91,596/- includes GST of
` 1,47,34,311/- is also not established. It would be open for the
URC to re-agitate its claim for the differential value of
` 1,47,34,311/- and other consequential amounts afresh if so
advised.
66. The appeal is disposed of in the aforesaid terms.
67. The pending interlocutory application also stands disposed
of.

Sd/-
(VIBHU BAKHRU)
CHIEF JUSTICE


Sd/-
(C.M. POONACHA)
JUDGE


AHB