BANGALORE DEVELOPMENT AUTHORITY vs M/S NCC LIMITED

Court
Karnataka High Court

- 1 -
COMAP No. 175 of 2026


RD
RESERVED ON 03 AUGUST 2026

IN THE HIGH COURT OF KARNATAKA AT BENGALURU

TH
DATED THIS THE 30 DAY OF SEPTEMBER, 2026

PRESENT

THE HON'BLE MR. VIBHU BAKHRU, CHIEF JUSTICE

AND

THE HON'BLE MRS. JUSTICE K.S. HEMALEKHA

COMMERCIAL APPEAL NO.175 OF 2026

BETWEEN:

BANGALORE DEVELOPMENT AUTHORITY
T. CHOWDAIAH ROAD, KUMARAPARK WEST,
BENGALURU - 560 020. REP. BY EXECUTIVE
ENGINEER MR. NIRANJAN K.M.
…APPELLANT

(BY SRI. K. ARVIND KAMATH, SENIOR ADVOCATE FOR
SRI. AJAY KUMAR M., ADVOCATE)

AND:

M/S NCC LIMITED,
#301, BATAVIA CHAMBERS,
8, KUMARA KRUPA ROAD,
BANGALORE - 560001.
…RESPONDENT

(BY SRI. SRIRANGA S., SENIOR ADVOCATE FOR
SMT. SUMANA NAGANAND & SMT. SUPRIYA N., ADVOCATES)

THIS COMMERCIAL APPEAL IS FILED UNDER SECTION 37(1)(C)
R/W SECTION 13(1A) OF THE COMMERCIAL COURTS ACT, 2015,
PRAYING TO CALL FOR RECORDS; ALLOW THE APPEAL AND SET ASIDE
THE JUDGMENT DATED 24.02.2026 IN COM.A.P.NO.161/2024 ON THE
FILE OF THE LXXXII ADDITIONAL CITY CIVIL & SESSIONS JUDGE,
BENGALURU AND CONSEQUENTLY SET ASIDE THE ARBITRAL AWARD
DATED 05.08.2024 PASSED BY THE ARBITRAL TRIBUNAL OF HON'BLE
CHIEF JUSTICE (RETD.) MANMOHAN SARIN.

THIS COMAP HAVING BEEN HEARD AND RESERVED FOR
JUDGMENT, COMING ON FOR PRONOUNCEMENT THIS DAY, JUDGMENT
WAS PRONOUNCED AS UNDER:




















Digitally signed
by C K LATHA
Location: High
Court of
Karnataka

- 2 -
COMAP No. 175 of 2026


CORAM: HON'BLE MR. VIBHU BAKHRU ,CHIEF JUSTICE
and
HON'BLE MRS. JUSTICE K.S. HEMALEKHA

C.A.V. JUDGMENT

(PER: HON'BLE MRS. JUSTICE K.S. HEMALEKHA)

1. The appellant, Bangalore Development Authority (BDA), has
preferred the present appeal under Section 37 (1) (C) of the
Arbitration and Conciliation Act, 1996 [A&C Act ] read with
Section 13 (1A) of the Commercial Courts Act, 2015, impugning the
judgment dated 24.02.2026 [ the impugned judgment ] passed by
the learned LXXXII Additional City Civil and Sessions Judge,
Bengaluru [ Commercial Court ] in Com. A.P No. 161/2024. By the
impugned judgment, the learned Commercial Court dismissed the
petition filed by the BDA under Section 34 of the A&C Act and
consequently declined to interfere with the arbitral award dated
05.08.2024 [ the impugned award ] passed by the learned Sole
Arbitrator [ the Arbitral Tribunal ].
Brief facts
2. The BDA entrusted the respondent, (M/s. NCC) with the
work of renovation and reconstruction of the "Puttanna Kanagal
Theatre" and adjoining shopping complexes at 4th Block,
Jayanagar, Bengaluru. Pursuant there to, the parties entered into

- 3 -
COMAP No. 175 of 2026


an agreement dated 27.06.2012 (agreement) for a contract price
of ` 252.27 crores.
3. The work comprised demolition and reconstruction of 4
blocks, namely, blocks 1 to 4. Under the contract data, possession
of Block No.1 was required to be handed over within 7 days from
the date of work order. Insofar as Blocks 2 to 4 were concerned,
clause 8 of the contract data contemplated that they were to be
handed over upon completion and rehabilitation of Block No.1.
4. The existing premises in Block Nos.2 to 4 were occupied by
vendors/lessees. The arrangement contemplated under the
agreement, required such occupants to be relocated to the
rehabilitated Block No.1 before possession of Block Nos.2 to 4
could be made available for execution of the remaining work.
5. Clause 7 of the Special Conditions of Contract [ SCC ]
contained provisions governing claims for compensation on
account of delay in commencement or execution of the work and
stipulated that the employer would not accept liability towards
claims for overheads and profits, except to the extent specifically
contemplated under the contract.

- 4 -
COMAP No. 175 of 2026


6. The work relating to Block No.1, which was stipulated to be
completed within 8 months from the date of the notice to proceed,
was completed only in December 2014/January 2015. Possession
of Block No.1 was thereafter handed over to the Bruhat Bengaluru
Manahanagara Palike [ BBMP ] on 06.01.2018. The relocation of the
vendors/lessees occupying Block Nos.2 to 4 and consequential
handing over the said blocks for execution of the remaining work
did not take place within the time period originally contemplated. In
the interregnum, proceedings were initiated before the Lokayukta
concerning the relocation of the occupants, and the process of
shifting the vendors and making the remaining blocks available for
execution was further delayed. These circumstances ultimately
resulted in disputes between the parties concerning the execution
of the balance work and the financial consequences arising there
from.
7. M/s NCC invoked the arbitration clause, and on 28.09.2018
commenced arbitral proceedings. The learned Arbitrator was
appointed to adjudicate the disputes between the parties.
8. Before the Arbitral Tribunal, M/s. NCC raised 10 claims,
aggregating to ` 117,29,36,970, apart from the applicable taxes

- 5 -
COMAP No. 175 of 2026


under various head. The claims made by M/s. NCC and the
amount claimed are extracted below in a tabular form :
Sl. Particulars of Claim Amount
No. Claimed ( `) `) `) `)
1 Amounts due on account of
40% of bill amount
(deferred payment)
withheld from RA bills
18,38,37,654
2 Interest for the amounts
due on account of 40% of
the bill amount (deferred
payment) withheld from RA
bills
12,76,13,557
3 Amount due on RA Bill 99,91,790
No.16
4 Interest due on delayed 24,66,743
payment of RA bills
5 Additional expenses
incurred towards extension
of bank guarantees
96,66,856
6 Excess interest recovered 2,74,24,477
on mobilization advance
7 Expenses incurred towards 12,45,58,313
idle plant & machinery
Expenses incurred towards
8 17,86,91,250
site overheads
9 Loss of profit at 10% on the
value of balance of
unexecuted work
22,28,40,568
10 Interest @ 13% p.a. 28,58,45,761

9. The Arbitral Tribunal, after completion of the arbitral
proceedings, passed the arbitral award dated 05.08.2024 partly
allowing the claims. The BDA being aggrieved by the said award
instituted proceedings under Section 34 of the A&C Act before the
Commercial Court. The said petition came to be dismissed by the

- 6 -
COMAP No. 175 of 2026


judgment resulting in the present appeal. By the impugned award
dated 05.08.2024, the Arbitral Tribunal partly allowed the claim
Nos.1 to 4 and 7 to 9, while claim Nos.5 and 6 were rejected. In
addition to claim No.1, an amount awarded under claim Nos.2, 3, 4,
7, 8 and 9 aggregated to ` 26,86,80,705. With respect to claim
No.1, ` 18,38,37,654 had already been allowed pursuant to an
interim award dated 16.01.2021. The Arbitral Tribunal awarded
pendente lite interest on claim Nos.4, 7 and 8, future interest at
11% per annum on the amount awarded and cost of ` 15,00,000.
Reasons by the Arbitral Tribunal
Claim Nos.1 and 2 - Deferred payment and interest

10. As regard claim No.1, the Arbitral Tribunal noted that the
claim of release of 40% of the bill amount retained as a deferred
payment had already been allowed by an interim award dated
16.01.2021 and that the award had been complied with. The
Arbitral Tribunal accordingly treated the principal amount as
payable. In respect of claim No.2, the Arbitral Tribunal held that the
deferred payment had become payable in terms of the contract and
the interest was payable for the period during which the amount
remained unpaid. It accordingly awarded ` 4,91,72,794 towards
interest for the period from 01.02.2019 to 22.02.2021.


- 7 -
COMAP No. 175 of 2026


Claim Nos. 3 and 4 - RA Bill No. 16 and delayed RA bills
11. In relation to claim No.3, the Arbitral Tribunal noted that the
principal amount under RA Bill No. 16 had been reconciled and
paid. It therefore awarded ` 53,059 towards interest for the period
from 07.06.2022 to 24.08.2022. Under claim No.4, the Arbitral
Tribunal found that there had been a delay in payment of running
account bills and awarded ` 5,15,760 towards interest together with
pendente lite interest at 11% per annum.
Claim Nos.5 and 6 – bank guarantee charges and mobilization
advance

12. The Arbitral Tribunal rejected claim No.5 relating to additional
expenses towards extension of the bank guarantees and claim
No.6 relating to excess interest recovered on the mobilization
advance. No amount was consequently awarded under these
heads.
Claim No.7 - Idle plant and machinery
13. The Arbitral Tribunal considered the contractual requirement
regarding the deployment of plant and machinery and the evidence
produced by M/s NCC concerning the machinery maintained for
execution of the work. The Arbitral Tribunal found that the
commencement and progress of the works were affected by the

- 8 -
COMAP No. 175 of 2026


failure to obtain an encumbrance free site, particularly on account
of the continued occupation of the premises by vendors. It noted
that even after completion of Block No.1, M/s. NCC was unable to
proceed with Block Nos.2 to 4 because the occupants had not
been shifted and the remaining site had not been made available.
The Arbitral Tribunal also took note of M/s. NCC's correspondence
and its efforts to continue with the work. On that basis, the Arbitral
Tribunal accepted that M/s. NCC incurred expenditure towards idle
`
plant and machinery, but restricted the amount recoverable to
61,12,080 with pendente lite interest at 11% per annum.
Claim No. 8 - Site overheads
14. The Arbitral Tribunal proceeded on the basis that the
prolonged delay in making the remaining site available had resulted
in continuation of the project beyond the original stipulated period
and consequently caused additional site overheads. It therefore
`
partly allowed claim No.8 and awarded 78,83,437 with pendente
lite interest at 11% per annum.
Claim No. 9 - loss of profit
15. The Arbitral Tribunal treated the inability to proceed with
Blocks 2 to 4 as having resulted in M/s.NCC losing the opportunity
to execute the balance work. The Arbitral Tribunal recorded that

- 9 -
COMAP No. 175 of 2026


notwithstanding the difficulties, M/s.NCC had remained willing to
proceed with the construction of Block Nos.2 to 4 and even offered
to do so on basis of the proposal placed before the parties. It found
that no concrete steps had been taken by the BDA after completion
of Block No.1 to obtain requisite consent of the State Government
and to enable M/s.NCC to proceed with the balance work. The
Arbitral Tribunal consequently held that M/s.NCC was entitled to
10% loss of profit on the balance unexecuted work. Taking the
` `
value of the balance work as 204,94,35,755, it awarded
20,49,43,575 towards loss of profit.
Cost and fee
16. The Arbitral Tribunal held that M/s NCC is entitled to the
`
legal fee amounting to 15,00,000.
Submissions
17. Sri K Arvind Kamath, learned Senior Counsel appearing for
BDA, would essentially reiterate the contentions urged before the
learned Commercial Court in the proceedings under Section 34 of
the A&C Act. The principal submission is with regard to clause No.
7 of the SCC. It is contended that clause 7 expressly stipulates that
the contractor shall not be entitled to any compensation for any
loss suffered on account of delay, in commencing or executing the

- 10 -
COMAP No. 175 of 2026


work, irrespective of the cause of such delay. The clause further
provides that the employer would not accept liability towards any
amount on account of the overheads or profits of the contractor,
except to the extent specifically contemplated under the contract.
According to the learned Senior Counsel, notwithstanding the
express contractual prohibition, the Arbitral Tribunal proceeded to
award substantial amount under claim Nos.7 to 9. Such an
approach, it is submitted, amounts to rewriting the bargain between
the parties and travelling beyond the terms of contract. The learned
Arbitrator, being a creature of the contract could not have awarded
amounts expressly excluded by the contract.
18. Reliance is placed upon the judgment of the Hon'ble
Supreme Court in Oil and Natural Gas Corporation vs Wig
1
Brothers Builders and Engineers Private Limited , to contend
that where the contract contains an express bar against payment of
compensation for delay, the Arbitrator cannot award such
compensation contrary to the contractual stipulation, even where
the delay is alleged to be attributable to the employer. It is further
submitted that the reliance placed by the Arbitral Tribunal upon
K.N.Sathyapalan (Dead) by LRs vs State of Kerala and

1
(2010) 13 SCC 377

- 11 -
COMAP No. 175 of 2026


2
Another is misplaced. According to the learned Senior Counsel,
the said decision concerned reimbursement of actual additional
costs incurred by the contractor, including extra expenditure
attributable to interference with the work, escalation during an
extended period of completion and additional transportation costs
occasioned by non-availability of the suitable dumping yard for
dumping excess earth. The said decision, it is submitted as
rendered in the context of specific findings regarding the actual
additional expenditure incurred and did not lay down any general
proposition permitting an Arbitrator to award notional loss of profit
calculated at the percentage of the value of the unexecuted work.
19. It is submitted that the decision in K.N Sathyapalan (supra)
3
followed the principles stated in P.M. Paul vs Union of India and
4
T.P George vs State of Kerala , where the claims related to
additional costs and escalation arising from identified defaults.
Those decisions, according to BDA cannot be treated as an
authority for awarding loss of profit in the present case. Learned
Senior Counsel submits that the clause 7 of the SCC is a stand
alone substantive term of the contract and is not merely a clause

2
(2007) 13 SCC 43
3
1989 Supp (1) SCC 368
4
(2001) 2 SCC 758

- 12 -
COMAP No. 175 of 2026


prescribing rates or methodology for computation. Consequently,
claims 7, 8 and 9 which relate respectively to the idle plant and
machinery, site overheads and loss of profit were expressly
excluded by the contractual bargain. It is submitted that the Arbitral
Tribunal could not have ignored the said clause and awarded
compensation by resorting to general principle of damages.
20. Reliance is placed upon the judgment of the Delhi High Court
in M/S Plus91 Security Solutions vs NEC Corporation India
5
Private Ltd. wherein it was held that a construction of the contract
falls within the domain of the Arbitrator. The submission, however,
is that while the Arbitral Tribunal may interpret the contract, it
cannot alter, rewrite or disregard any express contractual
stipulation and thereby confer upon a party an entitlement which
the contract itself excludes. According to the BDA, the errors
identified above go to the root of the award and constitute a patent
illegality within the meaning of Section 34(2A) of the A&C Act
warranting interference by this Court under Section 37.
21. Sri Sriranga S, learned Senior Counsel appearing for M/s.
NCC, would support the impugned judgment of the learned
Commercial Court as well as the arbitral award. It is submitted that

5
FAO(OS)(COMM) 36/2024, DD 29.07.2024

- 13 -
COMAP No. 175 of 2026


BDA is in substance seeking a re-appreciation of the evidence and
re-interpretation of the contractual provision, which is impermissible
in proceedings under Sections 34 and 37 of the A&C Act. The
learned Arbitrator being the chosen adjudicator of the parties, has
considered the contractual provisions, the correspondence
exchanged between the parties and evidence placed before him
and had therefore recorded findings on each of the claims.
22. As regards clause 7 of the SCC, it is contended that the
clause cannot be read in isolation or as an absolute immunity to the
BDA from the consequences of its own breaches or failures. The
Arbitral Tribunal was required to consider the agreement as a
whole and determine whether the circumstances which prevented
M/s. NCC from proceeding with the work fell within the contractual
prohibition relied upon by BDA. It is submitted that the Arbitral
Tribunal recorded the specific finding that M/s. NCC could not
proceed with Blocks 2 to 4 because the site was not made
available in the condition in which the remaining work could be
executed. The continued occupation of the premises by vendors
and failure to complete this rehabilitation materially affected M/s.
NCC's ability to proceed with the balance work. M/s. NCC had,
despite these impediments, remained willing to complete the

- 14 -
COMAP No. 175 of 2026


contract and had made proposals for proceeding with the balance
of construction. It is therefore contended that the Arbitral Tribunal
did not rewrite the contract but merely applied its terms to the
factual matrix established before him.
23. Insofar as claim Nos.7 and 8 are concerned, it is submitted
that the Arbitral Tribunal had considered the prolonged detention of
M/s.NCC's resources and continuation of the project beyond the
stipulated period. The amounts awarded were substantially lower
than the amounts claimed, demonstrating that the Arbitral Tribunal
has scrutinized the claim and has not mechanically accepted M/s.
`
NCC's computation. The Arbitral Tribunal awarded only
61,12,080 towards idle plant and machinery and ` 78,83,437
towards site overheads along with pendente lite interests.
24. With regard to claim No.9, learned Senior Counsel would
submit that the Arbitral Tribunal recorded a specific finding that
M/s.NCC had remained ready and willing to execute the balance
work, but that no concrete steps were taken by the BDA to enable
commencement of the remaining work after completion of Block
No.1. The Arbitral Tribunal consequently concluded that M/s.NCC
had lost opportunity to earn profit on the balance unexecuted work
and awarded 10% of the value thereof.

- 15 -
COMAP No. 175 of 2026


Reasons and conclusions
25. It is settled law that jurisdiction under Section 37 of the A&C
Act is limited. The court does not sit as an appellate court over the
arbitral award and is not expected to re-appreciate the evidence
merely because another view is possible. At the same time, the
limited scope of interference cannot mean that an award which
disregards an express and binding contractual stipulation or
ignores material evidence bearing directly upon the entitlement to a
claim, or awards damages without any evidentiary foundation is
immune from scrutiny. The Supreme Court in Ssangyong
Engineering and Construction Ld. vs National Highway
6
Authority of India has held that an Arbitrator cannot award
anything contrary to an express term of the contract and that an
award, ignoring such stipulation, may constitute patent illegality.
26. In the present case, the principal difficulty with the award
under claim Nos.7, 8 and 9 arises from clause 7 of the SCC. The
said clause expressly stipulates that the contractor shall not be
entitled to compensation for the loss. The clause reads thus :
“7. The Contractor shall not be entitled to any
compensation for any loss suffered by him on account of
delays, in commencing or executing the work, whatever the

6
(2019) 15 SCC 131

- 16 -
COMAP No. 175 of 2026


cause of delays may be, including delays arising out of
modifications to the work entrusted to him or in any sub-
contract connected therewith or delays in awarding
contracts for other trades of the project or in
commencement or completion of such works or in procuring
Government controlled or other building materials or in
obtaining water and power connections for construction
purposes or for any claim in respect thereof. The Employer
does not accept any liability for any sum towards loss of
overheads and profits of the contractor, besides the tender
amount subject to such variations as are provided for herein
and subject to Certification by the Architect/Engineer for
payment post work."

27. The aforesaid clause expressly stipulates that the contractor
shall not be entitled to compensation for loss suffered on account
of delay in commencing or executing the work, irrespective of the
cause of delay, and further provides that the employer would not
accept liability towards loss of overheads and profits of the
contractor, except as specifically contemplated by the contract.
28. M/s NCC has sought to sustain the award notwithstanding
clause 7 of the SCC by contending that an exclusion clause cannot
absolve the employer from the consequences of a breach
attributable to itself. In this context, it is necessary to consider the
decisions concerning contractual stipulation which restrict or
exclude the contractor's entitlement to compensation on account of
delay. In Ramnath International Construction (P) Ltd. v. Union

- 17 -
COMAP No. 175 of 2026


7
of India clauses 11 (A) to (C), which governed delay in execution
of the works and extension of time, fell for consideration before the
Supreme Court. The Supreme Court held that where the delay is
attributable to the employer (Union of India), the award of damages
is barred construing the contractual stipulations. A different
approach was adopted by the Supreme Court in Asian Techs
8
Limited vs Union of India and Others . The Supreme Court
construed that the clauses 11 (A) to (C) restricted the departmental
authorities from entertaining a claim for compensation, but not as
denuding the Arbitrator of the power to award damages otherwise
recoverable on account of breach by the employer and held that
the contractual stipulation did not constitute an absolute bar to the
Arbitrator awarding damages.
29. The Delhi High Court in Simplex Concrete Piles (India)
9
Limited vs Union of India while examining whether a contractual
stipulation which disentitles a contractor from claiming damages
otherwise recoverable under Sections 55 and 73 of the Indian
Contract Act, 1872 could withstand the scrutiny under Section 23 of
the Contract Act. In the said decision, the learned Judge observed

7
(2007) 2 SCC 453
8
(2009) 10 SCC 354
9
2010 SCC OnLine Del 821

- 18 -
COMAP No. 175 of 2026


that there was conflict of decisions of co-equal Benches of the
Supreme Court in Ramnath (supra) and Asian Techs (supra),
concerning the effect of an award of damages notwithstanding
such a clause. However, in Simplex Concrete Piles there was no
distinction made between a clause excluding an entire liability of
contracting party and a clause excluding compensation only for a
specified category of breach.
30. The Division Bench of the Delhi High Court in M/S Plus91
Security Solutions (supra) (of which one of us i.e. Hon’ble Vibhu
Bakhru C. J. is a member of the Bench, is instructive on this
aspect) considered an arbitral award granting loss of profit
notwithstanding an express contractual provision excluding liability
for loss of revenue or profit. It was held at paras 64, 65, 67 as
under :
“64. It is essential to maintain the bargain entered into
between the parties. The parties agreed that they would not
be liable for (i) any indirect, special, or consequential loss or
damage; (ii) any loss or damages due to loss of goodwill;
and, (iii) loss of revenue or profit arising from or in
connection with the MOU. If the MOU is accepted as a
binding agreement, this is clearly a part of the bargain
struck by the parties. Disregarding the said stipulation would
in effect amount to re-writing the bargain between the
parties.

65. This Court has some reservations as to the decision
rendered by the learned Single Judge in Simplex Concrete
Piles (India) Ltd. v. Union of India . However, it is not
necessary to examine the same as it is not applicable to the

- 19 -
COMAP No. 175 of 2026


facts in the present case. Reliance on the said decision is
clearly misplaced. In that case, the Court was considering a
clause, which precluded a contractor from claiming loss on
account of delay in execution of the contract even though
the delay in execution of the contract was for the reasons
attributable to the employer. The learned Single Judge
observed that there was a conflict of decision between the
Supreme Court in regard to award of damages
notwithstanding such a clause. The learned Single Judge
noted that whereas, in the case of Ramnath International
Construction (P) Ltd. v. Union of India , the Supreme
Court had held that even if the employer (Union of India) is
at fault, the award of damages is barred. However, in a
latter decision in Asian Techs Limited v. Union of India &
Ors. , the Supreme Court had held in the context of a similar
clause, that it only prevented the department from granting
damages but did not prevent the arbitrator from awarding
damages. After noting the said conflicting decision, the
learned Single Judge held that the decision in the case of
Asian Techs Limited v. Union of India & Ors. furthered
the object of the Contract Act. However, the learned Single
Judge also observed that “To permit a contractual clause
having the object to defeat the very contract itself, is a
matter of grave public interest. If such a clause is allowed to
stand, then, the same will defeat the basis and existence of
the Contract Act.” For the aforesaid reasoning the learned
Single Judge held that the contractual clauses such as the
Clauses in question in the said case [Clause 11(A) to 11(C)]
which disentitle a party to the benefits of Sections 55 and 73
of the Contract Act would be violative of Section 23 of the
Contract Act.

x x x

67. It is essential to understand the contract between the
parties. A clause limiting the liability is clearly a part of the
contractual bargain and the same cannot be disregarded.
The question whether a liability on account of breach of a
contract can be limited in terms of the contract is not res
integra . The decision of the Supreme Court in Asian Techs
Limited. v. Union of India & Ors. rested on the
interpretation of the relevant clauses. The Supreme Court
had read the relevant clauses in that case as well as the
facts of that case. The clause in question – which was
similar to the clause considered by the Supreme Court in
Ramnath International Construction (P) Ltd. v. Union of

- 20 -
COMAP No. 175 of 2026


India – stipulated hat “no claim in respect of compensation
or otherwise, howsoever arising, as a result of extension
granted under Conditions (A) and (B) above shall be
admitted.” Notwithstanding the said clause, the concerned
officials of the respondent had represented that separate
rates would be negotiated. The Supreme Court held that on
the said specific assurance held out by the respondent, the
contractor was persuaded to continue the work. In the given
facts, the Supreme Court held that it was not open to the
respondent to now contend that no further claim could be
made due to Clause 11(C) of the contract in question and
the Arbitrator had no jurisdiction to entertain such claims.
The Supreme Court also interpreted Clause 11 of the
contract in that case to mean that it only prohibited the
department from entertaining a claim and did not curtail the
jurisdiction of the arbitrator. Plainly, the decision in Asian
Techs Limited. v. Union of India & Ors. rested on the
interpretation of the relevant clause of the contract. It is also
material to note that the earlier decision in the case of
Ramnath International Construction (P) Ltd. v. Union of
India was not brought to the notice of the Supreme Court."

31. Further in M/S Plus91 Security Solutions (supra), the Oil
and Natural Gas Corporation (supra) was referred where the
Supreme Court faulted the Arbitral Tribunal for awarding
compensation by ignoring the express provisions of the contract
and paras 6 and 7 of the said judgment was referred which reads
as under :
"6. ……….But Clause 5-A of the contract pertains to
extension of time for completion of work and specifically
bars any claim for damages. The said clause is extracted
below:

“In the event of delay by the Engineer-in-Charge to
hand over to the contractor possession of land/lands
necessary for the execution of the work or to give
the necessary notice to the contractor to commence
work or to provide the necessary drawing or
instructions or to do any act or thing which has the

- 21 -
COMAP No. 175 of 2026


effect of delaying the execution of the work, then
notwithstanding anything contained in the contract
or alter the character thereof or entitle the contractor
to any damages or compensation thereof but in all
such cases the Engineer-in-Charge may grant such
extension or extensions of the completion date as
may be deemed fair and reasonable by the
Engineer-in Charge and such decision shall be final
and binding.”

7. In view of the above, in the event of the work being
delayed for whatsoever reason, that is, even delay which is
attributable to ONGC, the contractor will only be entitled to
extension of time for completion of work but will not be
entitled to any compensation or damages. The arbitrator
exceeded his jurisdiction in ignoring the said express bar
contained in the contract and in awarding the compensation
of Rs.9.5 lakhs………”

[Emphasis added]

32. The court held that the Arbitrator derives his jurisdiction from
the contract and must act within the confines of the bargain struck
by the parties. This principle is of direct relevance here.
33. The Supreme Court in Oil and Natural Gas Corporation
(supra) while relying on Ramnath (supra) observed that where the
contractual clause constituted a clear bar against any claim for
compensation arising from delays in respect of which extension of
time had been sought and obtained by the contractor from the
employer, the contractor could not claim damages contrary to the
express terms of the contract.

- 22 -
COMAP No. 175 of 2026


34. In Oil and Natural Gas Corporation (supra) it was observed
at para 10 as under :
" 10. In Ramnath International Construction (P) Ltd. v.
Union of India [(2007) 2 SCC 453] a similar issue was
considered. This Court held that Clause 11(C) of the
general conditions of contract (similar to Clause 5-A under
consideration in this case) was a clear bar to any claim for
compensation for delays, in respect of which extensions
had been sought and obtained. This Court further held that
such a clause amounts to a specific consent by the
contractor to accept extension of time alone in satisfaction
of claims for delay and not to claim any compensation; and
that in view of such a bar contained in the contract in regard
to award of damages on account of delay, if an arbitrator
awards compensation, he would be exceeding his
jurisdiction."

35. We came across an article titled 'Commercial Law
monologues : Does Section 23 of the Indian Contract Act void
10
limitation of liability clauses?' which emphasise the contours of
limitation and exclusion of liability clauses under Indian Contract
law. The article draws distinction between clauses which limit or
exclude liability in respect of specified breaches and those which
purport to exclude liability altogether. The said Article referred to
Bharathi Knitting Company vs DHL Wordlwide Express

10
Pachnanda G (2026) Commercial Law Law monologues : Does Section 23 of
the Indian Contract Act void limitation of liability clauses?, Bar and Bench -
Indian Legal News Available at :
https://www.barandbench.com/columns/commercial-law-monologues-does-
section-23-of-the-indian-contract-act-1872-void-limitation-of-liability-clauses .

- 23 -
COMAP No. 175 of 2026


11
Courier Division of Airfreight Limited , Ramnath and ONGC
(supra). The author notes that the Supreme Court had in
appropriate cases recognized and given effect to contractual
stipulations limiting or excluding the employer's liability for specified
breaches including delay.
36. In this case, the contractual provision under Clause 7 states
that in respect of compensation arising on account of delay in the
commencement or execution of the work, the employer shall not be
liable for claims towards overheads or profits, except to the extent
that such compensation is specifically contemplated elsewhere
under the contract. Therefore, the clause explicitly excluded
specific types of damages, such as claims for overheads and
profits, while maintaining any right that may have been specifically
specified in the terms of the contract.
37. The Arbitral Tribunal was undoubtedly entitled to interpret the
contract. However, the power of interpretation does not extend to
neutralizing an express exclusion contained in the contract. The
Arbitral Tribunal was required, at the threshold to determine the
applicability and effect of clause 7 before examining whether claim
Nos.7, 8 and 9 could at all be awarded. An award which proceeds

11
(1996) 4 SCC 704

- 24 -
COMAP No. 175 of 2026


to grant compensation towards idle plant and machinery, site
overheads and loss of profit, notwithstanding the express
contractual exclusion, without first recording a sustainable finding
as to why the exclusion was inapplicable, cannot be sustained
merely on the ground that the Arbitral Tribunal had adopted one
possible interpretation of the contract. The statutory obligation
under Section 28 (3) of the A&C Act also requires the Arbitral
Tribunal to take into account the terms of contract while making the
award.
38. The reliance placed by the Arbitral Tribunal on
K.N.Sathyapalan (supra), does not in our view advance the case
of M/s NCC. The principle emerging from the said decision, as
relied upon before us, concerns reimbursement of additional
expenditure actually incurred and established by evidence on
account of circumstances attributable to the employer. It cannot be
treated as an authority for awarding notional loss of profit
calculated at 10% of the value of the balance unexecuted work,
particularly when the contract contains an express stipulation
excluding liabilities towards overheads and profits. In the present
case, the Arbitral Tribunal awarded ` 61,12,080/- under claim No.7
towards idle plant and machinery and ` 78,83,437 under claim

- 25 -
COMAP No. 175 of 2026


No.8 towards site overheads. The BDA had specifically disputed
the actual deployment of machinery and actual expenditure
towards additional overheads. The distinction between a contractor
being required under the contract to maintain certain machinery at
site and the contractor actually establishing that such machinery
was kept idle for the period claimed, resulting in a quantifiable loss
is material. The latter required proof.
39. The same infirmity is more pronounced in claim No. 9 under
`
which the Arbitral Tribunal awarded 20,49,43,575 towards loss of
profit, calculated at 10% of the value of balance unexecuted work.
The award does not disclose a satisfactory evidentiary foundation
for adopting 10% as the measure of M/s NCC’s alleged loss. There
is also no adequate finding demonstrating the actual loss of profit
suffered by M/s NCC. The Arbitral Tribunal proceeds from the fact
that the balance work remained unexecuted to the conclusion that
M/s NCC had thereby lost 10% profit on such work. Such an
approach, in the absence of proof and in the face of the contractual
exclusion contained in clause 7, cannot be sustained.
40. The fact that M/s NCC was unable to proceed with Blocks 2
to 4 may furnish the factual background to its grievance. However
the existence of delay or obstruction does not, by itself create an

- 26 -
COMAP No. 175 of 2026


entitlement to compensation contrary to an express contractual bar.
The contract data under clause 8 further stipulates the time and
sequence for possession of different blocks, providing that the first
block was to be handed over within 7 days from the date of the
work order, whereas Blocks 2, 3 and 4 were to be handed over on
completion and rehabilitation of the first block. These are not
incidental provisions. They constitute express terms of the bargain
struck between the parties. If the agreement is accepted as a
binding contract, as it undisputedly is, the aforesaid clauses form a
clear and substantive part of the bargain. The parties, while
entering into the contract, consciously agreed to the consequences
of delay and in particular, agreed that the contractor would not
claim compensation for the loss on account of delay and the
employer could not be liable for overheads and profits. Therefore, it
was required that these provisions be given effect while
determining their claims.
41. An Arbitrator can certainly interpret the terms of contract. But
interpretation is not synonymous with rewriting. Where the contract
contains an express prohibition against a particular claim, the
Arbitral Tribunal cannot create an entitlement which the parties
themselves have expressly excluded. This principle is also

- 27 -
COMAP No. 175 of 2026


consistent with Section 28(3) of the A&C Act, which requires the
Arbitral Tribunal while deciding and making an award to take into
account the terms of contract and trade usages applicable to the
transaction. Thus, the question before us is not whether the Arbitral
Tribunal was entitled to interpret clause 7. It undoubtedly was. The
question is whether having noticed clause 7, it could nevertheless
award an amount which falls squarely within the contractual
exclusion. In our considered opinion, the answer must be ‘no’.
42. The reliance placed upon M/s. A. T. Brij Paul Singh and
12
Others vs State of Gujarat does not advance the case of M/s
NCC. The principle recognized in M/s A.T. Brij Paul Singh is that,
in an appropriate case, a contractor may be entitled to damages
towards loss of profit on the unexecuted portion of the contract,
where the contract has been wrongfully terminated or contractor
has otherwise been deprived of an opportunity to execute the work.
The principle cannot, however, be divorced from the terms of
contract governing the parties. The present case stands on a
materially different footing. Here the parties have expressly agreed
by clause 7 that the contractor could not be entitled to

12
(1984) 4 SCC 59

- 28 -
COMAP No. 175 of 2026


compensation for loss occasioned by delay and that the employer
would not accept liability towards overheads and profits.
43. The question, therefore, is not merely whether the loss of
profit can, as a matter of general contract law, constitute
recoverable head of damages. The question is whether the parties
had contractually excluded that entitlement. The Delhi High Court
in M/s Nandi Infratech Pvt. Ltd. vs M/s. R. K. Bararia and
13
Another , wherein one of us i.e., Hon’ble Vibhu Bakhru C. J was a
member of the Bench, the court observed that A.T. Brij Paul
Singh (supra) does not constitute an authority for the proposition
that an express contractual bar against a claim for overheads on
profits can simply be discarded. It emphasized that a contractor
claiming damages must establish the loss suffered by it. A
percentage built into a rate or a standard formula cannot, by itself
establish that the contractor actually suffered the corresponding
loss or that such percentage represents the profit which the
contractor would have earned. The same principle was applied in
relation to the use of the formula such as Hudson Formula. A
formula cannot substitute the evidentiary foundation required for a
claim for damages. The claimant must establish the factual basis

13
FAO (COMM) 49 of 2023 and CM No. 9287/2023

- 29 -
COMAP No. 175 of 2026


for the loss and the nexus between the breach and alleged loss
and held at paras 55, 56 and 57 as under :
“55. Second, an inclusive allowance of 15% on the item of
rates translates to an allowance of 13.04% on the value of
item rate. This can be clearly illustrated by assuming the
costs of a component of extra item at 100/-, a 15% inclusive
allowance would translate to an item rate of 115/-. A profit
mark up of 15/- on the item rate of 115/- would translate into

13.04% ( 15/115). Thus, if it is assumed that the balance
work was akin to an extra item, the same would include an
allowance of 13.04% on the value of the work as mark up
on account of overheads, profits and establishment
expenses. Thus, the assumption that the loss of profits is
15% of the remaining value of the work is ex facie
erroneous.

56. Third, all inclusive allowance of 15% includes an
allowance for overheads and establishment expenses in
addition to an allowance for profits. RKB’s claim was
confined to loss of profits alone. Thus, in any event, it would
not be apposite to assume a profit margin of 15% on the
basis of analysis of rates for extra items. The said analysis
would inapposite as the all inclusive allowance of 15% of
costs also includes establishment expenses and overheads.

57. In Edifice Developers and Projects Engineers Ltd.
v. Essar Projects (India) Ltd. (supra) , a Division Bench of
the Bombay High Court had upheld the decision of the
learned Single Judge faulting the Arbitral Tribunal in
awarding the claims for overhead losses without any
evidence. In the said case, the Arbitral Tribunal, following
the decision in the case of AT Brij Paul Singh v State of
Gujarat: AIR 1984 SC 1703 had allowed the claims for
overhead losses. In the said context, the Division Bench
held as under:

“10. Brij Paul Singh’s case therefore does not
stipulate as a doctrine of law that the formula which
has been prescribed in Hudson's treatise must
invariably be accepted in all cases as a measure of
damages sustained on account of loss of overheads.
On the other hand in the subsequent decision of the
Supreme Court in McDermott International (supra),

- 30 -
COMAP No. 175 of 2026


the Supreme Court has relied upon the following
observations contained in the earlier decision in M.N.
Gangappa v. Atmakur Nagabhushanam Setty & Co.
(1973) 3 SCC 406.

“In the assessment of damages, the court must
consider only strict legal obligations, and not
the expectations, however reasonable, of one
contractor that the other will do something that
he has assumed no legal obligation to do.”

11. The judgment in McDermott International
(supra) considers various formulae including
Hudson's Formula, Emden Formula and Eichleay
Formula. As regards Hudson's Formula the Supreme
Court has noted, in the following extract, that
although it has received judicial support in many
cases, it has been the subject matter of criticism:

“(a) Hudson Formula : In Hudson's Building and
Engineering Contracts, Hudson formula is
stated in the following terms:

“Contract head office overhead & contract sum
period of delay” profit percentage x ----------------
----- x
contract period

In the Hudson formula, the head office overhead
percentage is taken from the contract. Although the
Hudson formula has received judicial support in many
cases, it has been criticized principally because it
adopts the head office overhead percentage from the
contract as the factor for calculating the costs, and
this may bear little or no relation to the actual head
office costs of the contractor.”

(emphasis supplied)

12. In McDermott International (supra) the Supreme
Court has held that it is an accepted position that different
formulae can be applied in different circumstances and the
question as to whether damages should be computed by
taking recourse to one or other formula, having regard to
the facts and circumstances of a particular case, would fall
within the domain of the Arbitrator. In the present case no

- 31 -
COMAP No. 175 of 2026


other formula other than Hudson's formula has been
considered in the arbitral award. In the present case the
Arbitrator proceeded on the basis that it was only Hudson's
Formula which was to be applied and that even though no
direct evidence had been adduced on behalf of the
Appellant, nonetheless the Appellant would be entitled to
damages measured with reference to the aforesaid formula.
This approach of the Arbitrator is manifestly in the teeth of
the law laid down by the Supreme Court in McDermott
International. Section 28(1)(a) requires that the Arbitral
Tribunal shall decide a dispute submitted to arbitration in
accordance with the substantive law for the time being in
force in India. Section 28(3) requires the Arbitral Tribunal to
decide in accordance with the terms of the contract and
take into account the usages of the trade applicable to the
transaction. The Arbitral Tribunal under Section 28(2) can
act as amiable compositeur and can decide ex aequo et
bono only if parties have expressly authorized it to do so. In
the present case, the Learned Single Judge was correct in
coming to the conclusion that the award of the Arbitrator
proceeds on the manifestly misconceived notion that a
contractor is entitled to claim overhead losses even in the
absence of evidence on the basis of Hudson's Formula.
Similarly, the Arbitral Tribunal proceeded on a misconceived
premise that this formula is invariably adopted for
quantification of claims for overhead losses in India. In the
present case the Appellant produced no evidence in support
of its claim; this has been so stated in the Award. The
award of the claim is on the misconceived basis that the
Hudson's Formula must be applied despite the absence of
evidence. Since the fundamental basis that has permeated
the award is contrary to law, the judgment of the Single
Judge cannot be faulted in setting aside the arbitral award
on that aspect.”

44. The Division Bench of the Bombay High Court in Edifice
Developers and Projects Engineers Ltd. vs Essar Projects
14
(India) Ltd. found fault with the Arbitral Tribunal in awarding the
claims for overhead losses without any evidence.

14
2013 SCC OnLine Bom 5

- 32 -
COMAP No. 175 of 2026


15
45. In M/s N.N.Constructions vs Union of India and Others
similar emphasis has been laid down that loss of profit is not a
presumptive entitlement and requires cogent evidence of financial
injury. This principle assumes particular significance in the present
case. It is held at paras 36 to 38 as under :
"36. The decision of the Supreme Court in M/s AT Brij Paul
Singh (supra) is not an authority for the proposition that no
evidence is required to be led to prove the measure of
damages on account of loss of profits. It would be
erroneous to proceed on the basis that in all cases where
the arbitral tribunal or court finds that the contracts have
been terminated illegally, a loss of profits quantified at 15%
of the balance works would be payable as damages.

37. In M/s AT Brij Paul Singh (supra) , the Supreme Court
had found that the respondent had breached the contract
and thus, the appellant in the said case (M/s. AT Brij Paul
Singh) was entitled to claim damages on account of loss of
profits. Insofar as measure of damages is concerned, the
Supreme Court noted that in another proceeding relating to
a similar contract between the same parties, the High Court
had accepted a claim for loss of profits computed at the rate
of 15% of the value of the unexecuted works. It is on the
facts of that case, that the Supreme Court concluded that
the appellant therein was entitled to 15% of the value of the
unexecuted works as damages.

38. In Edifice Developers and Projects Engineers
Limited V. Essar Projects (India) Limited , the Division
Bench of the Bombay High Court considered a challenge to
an arbitral award where the arbitral tribunal had relied on
the decision of M/s. AT Brij Paul Singh (supra) and had
awarded a claim relating to overhead losses, even though
the claimant had not produced evidence to establish the
same. The learned Single Judge of the Bombay High Court
had set aside the arbitral award, and the said decision was
challenged before the Division Bench. In the aforesaid
context, the Division Bench rejected the contention that

15
Commercial Appeal 177 of 2026, DD 02.07.2026

- 33 -
COMAP No. 175 of 2026


award of overhead losses could be sustained without
producing evidence. In the said case, the arbitral tribunal
had awarded a claim of loss of profits at the rate of 10% of
the value of the remaining works. The Bombay High Court
faulted the arbitral tribunal for awarding a claim for loss of
profits without any evidence to support the same. We
consider it apposite to set out the following extract from the
said decision:

"7. Learned senior counsel appearing on behalf of
the Appellant submits that in the present case the
Appellant had relied upon documentary material
consisting of correspondence exchanged between
the parties. It was urged that if the Appellant had
sought to establish the claim for overhead losses on
the basis of that correspondence, it would have
become necessary to lead evidence in support of
the claim set out by the Appellant in its letters.
However, the Appellant sought to claim a lesser
amount. Hence, it was urged that the Arbitrator was
justified in taking recourse to Hudson's Formula.
Moreover it was sought to be urged that the reliance
which was placed on the judgment of the Supreme
Court in Brij Paul Singh's case by the Arbitrator
cannot be faulted.

8. The arbitral award, ex facie, demonstrates that
the Arbitrator proceeded on the basis that the
Appellant had not produced either the basis of the
account or any oral evidence to prove the overhead
losses caused to or suffered by it. Despite that
finding the Arbitrator held that in the construction
industry a contractor becomes entitled to overhead
losses on the basis of Hudson's Formula, even in
the absence of direct evidence to prove such losses
when resources are mobilized and delay is caused
in the execution of the work not attributable to the
contractor. In holding this the Arbitrator relied upon
the judgment of the Supreme Court in Brij Paul
Singh's case (supra).

9. The Learned Single Judge, in our view, was
justified in coming to the conclusion that the
Arbitrator was manifestly in error in awarding the
claim for overhead losses in spite of the fact that no
oral evidence was adduced on behalf of the

- 34 -
COMAP No. 175 of 2026


Appellant. In Brij Paul Singh's case the Supreme
Court noted that it was not disputed that where in a
works contract a party entrusted with the work
commits a breach of the contract, the contractor
would be entitled to claim damages for loss of profit
which he expected to earn by undertaking the
contract. The Supreme Court, however, noted that
what must be the measure of the profit and what
evidence should be tendered to sustain the claim
are different matters. The judgment of the Supreme
Court adverts to the fact that in that case the High
Court had referred to Hudson's treatise on Building
and Engineering Contracts. Hudson states there that
in major contracts subject to competitive tender on a
national basis, the evidence given in litigation on
many occasions suggests that head office
overheads and profits are between 3 to 7% of the
total price of cost which is added to the tender. The
High Court in that case had rejected the claim of the
contractor. The Supreme Court noted that in an
identical contract with regard to another portion of
the same road and for the same type of work the
High Court had accepted loss of profit at 15% of the
price of the balance of work as a reasonable
measure of damages if the State is guilty of a
breach of contract. It was on this basis that the
Supreme Court came to the conclusion that since for
the same type of work, between the same parties
involving a nearby portion of the same road a certain
measure of damages had been adopted by the High
Court, the same measure ought to have been
adopted in that case as well.

10. xx xx

11. xx xx

12. xx xx

13. The Arbitrator, as noted earlier, also awarded
claims in respect of loss of profit, for under utilized
plant and equipment and for reimbursement of
infrastructure expenses. In respect of loss of profits,
the Arbitrator merely held that a measure of 10% on
the value of the remaining part of the works contract
cannot be said to be unreasonable. The Arbitrator
observed that a percentage representing 10% of the

- 35 -
COMAP No. 175 of 2026


rate of profit is invariably accepted in the
construction industry. Evidently save and except for
an priori assumption, no evidence whatsoever was
led before the Arbitrator in that regard. In P.R. Shah,
Shares and Stock Brokers Private Limited v. B.H.H.
Securities Private Limited the Supreme Court has
held that while an Arbitral Tribunal cannot make use
of its personal knowledge of the facts of the dispute,
which is not a part of the record, the Tribunal can
certainly use its expert or technical knowledge or the
general knowledge about the particular trade in
deciding a matter. That is why in many arbitrations,
persons with technical knowledge are appointed
since they may be well-versed with the practices
and customs in the respective fields. The Arbitrator
in the present case was not an arbitrator drawn from
the trade. No basis whatsoever has been indicated
in the award for accepting 10% as a measure
representing loss of profits. No material was
produced before the Arbitrator on the nature of the
practice in the trade. During the course of the
hearing no basis has been indicated to the Court
from the record to suggest that any practice of that
nature in the construction industry was brought to
the notice of the Arbitral Tribunal. In the
circumstances, the arbitral award to the extent that it
allows the claim for loss of profits is based on pure
conjecture and in the absence of any evidence
whatsoever was correctly set aside. Similarly, in
regard to the claim for underutilized plant and
equipment and for reimbursement of expenses of
infrastructure, it is evident that the Arbitrator has
merely awarded a sum which he considered to be
reasonable. No evidence whatsoever was led before
the Arbitral Tribunal.""

46. When considering claim Nos. 7 and 8 relating respectively to
the idle plant and machinery and site overheads, the Arbitral
Tribunal awarded ` 61,12,080 towards idle plant and machinery
and ` 78,83,437 towards site overheads. The BDA had specifically
disputed whether machinery was actually kept idle at site during

- 36 -
COMAP No. 175 of 2026


the relevant period and whether M/s NCC had actually incurred the
additional overhead expenditure claimed. There is no evidence
demonstrating actual expenditure and the cash expenditure and in
the absence of any evidence, an award based merely upon a
formula, rates or assumption cannot be sustained.
47. When considering claim No.9, the Arbitral Tribunal awarded
` 20,49,43,575 towards loss of profit calculated at 10% on the
value of the balance unexecuted work. There is no satisfactory
evidentiary foundation for calculating 10% as a measure of the
NCC's loss of profit. There is neither material demonstrating that
NCC's actual profit margin on this particular contract was 10% nor
is there any material demonstrating that M/s NCC did suffer loss of
profit to that extent as a consequence of the alleged delay. The
award does not adequately address the express exclusion
contained in clause 7. Thus, on two independent infirmities in claim
No. 9, (i) the claim is hit by express contractual prohibition
contained in clause 7 and (ii) even otherwise, the quantum of loss
of profit has not been established by evidence. The reliance on M/s
A.T.Brij Paul Singh (supra) cannot cure the either defect. The
Edifice Developers and Projects Engineers Limited (supra)
which has been relied consistently by this Court and by the

- 37 -
COMAP No. 175 of 2026


different High Courts is that a formula cannot itself constitute proof
of loss. Consequently, even assuming that M/s NCC was entitled
in principle to claim loss of profit, it was still required to establish
the factual basis and quantum of the alleged loss and applying
10% to the value of the unexecuted work by the Arbitral Tribunal is
unpersuasive.
48. In so far as claim No.2 is concerned, the Arbitral Tribunal
awarded interest from 01.02.2019 to 22.02.2021, after the expiry of
48 month period, as contemplated under clause 37.1 of the
General Conditions of Contract. Clause 37.1 reads thus :
"37.1. The employer shall pay the contractor 60% of the bill
amount within 60 days of submission of the bill certified by
the engineer in charge of the work. Balance 40% of the bill
amount will be released after the completion of the work up
to 48 months (inclusive of defect liability period of 24
months) from the certified date of completion. Payment
shall be in 16 (Sixteen) equal installments payable on
quarterly basis from the date of certified completion of
works."

49. BDA did not dispute this liability towards the principal
deferred amount. The learned Senior Counsel appearing for the
BDA placed considerable reliance on Exs.R10 and R11. Ex.R10 is
the resolution dated 09.06.2017, whereby the BDA resolved to
release the outstanding deferred amount subject to M/s NCC
furnishing a bank guarantee for 40% of the deferred payment.

- 38 -
COMAP No. 175 of 2026


Ex.R11 is a consequential communication calling upon M/s NCC to
furnish the bank guarantee and collect the deferred amount. It is
therefore contended that the BDA had offered to release the
amount as early as in June 2017 and that M/s NCC, having failed
to furnish the bank guarantee cannot claim interest for the
subsequent period.
50. We are unable to accept the said contention. The liability to
pay the principal amount being undisputed, the BDA cannot avoid
consequences of a delayed payment. Exs.R10 and R11 by
themselves do not establish either of the circumstances. We do
not find any ground to interfere with the award under claim No.2
and the BDA's challenge to award interest on the deferred payment
is rejected.
51. For the foregoing reasons, we are of the considered view
that the BDA has made out a case, the appeal merits acceptance
in part. Accordingly, the appeal is partly allowed. The judgment of
the Commercial Court is set aside to the extent that it upholds the
arbitral award under claim Nos.7, 8 and 9. Consequently, the
arbitral award is set aside to the extent of the amount awarded
under claim Nos.7, 8 and 9. The direction of future interest shall

- 39 -
COMAP No. 175 of 2026


correspondingly operate only on the amounts which survive after
the aforesaid severance. The award of costs is not disturbed.
52. The pending interlocutory application stands disposed of.


Sd/-
(VIBHU BAKHRU)
CHIEF JUSTICE



Sd/-
(K.S. HEMALEKHA)
JUDGE

CKL