Ms Narendra Builders In Jv vs National Highways And Infrastructure Development Corporation Limited

Court
Delhi High Court

$~
* IN THE HIGH COURT OF DELHI AT NEW DELHI
Reserved on: 14 October 2026
Pronounced on: 19 November 2026

+ O.M.P.(I) (COMM.) 482/2026 & I.A. 28576/2026
# CNR No. DLHC010497742026

MS NARENDRA BUILDERS IN JV .....Petitioner
Through: Mr. Anil Kumar, Adv.
versus

NATIONAL HIGHWAYS AND INFRASTRUCTURE
DEVELOPMENT CORPORATION LIMITED .....Respondent

Through: Mr. A. P. Singh, Adv.

CORAM:
HON'BLE MR. JUSTICE VINOD KUMAR
O R D E R
% 19.11.2026
I.A. 28577/2026 (Exemption)
1. Exemption is allowed, subject to all just exceptions.
2. The application is disposed of.
I.A. 28578/2026 (under Section 151 CPC filed on behalf of petitioner
seeking permission to file lengthy synopsis and list of dates)

3. For the reasons stated in the application, lengthy synopsis and list
of dates are allowed.
4. The application is disposed of.
O.M.P.(I) (COMM.) 482/2026
5. This is a petition under Section of 9 of Arbitration and
Conciliation Act, 1996 seeking interim measures of protection.


I.A. 28575/2026 in O.M.P.(I)(COMM.)482/2026 Page 1 of 4

Signature Not Verified
Signed By:PRAMOD
KUMAR VATS
Signing Date:20.11.2026
10:52:12

6. Issue notice.
7. Learned Counsel for the respondent accepts notice on behalf of
respondent.
8. Reply be filed within four weeks. Rejoinder thereto, if any, be
filed within two weeks thereafter.

9. Re-notify on the next date of hearing.
I.A. 28575/2026 (under Section 151 CPC for ad-interim and ex-parte
stay/order for interim measure of protection.

10. This is an application under Section 151 CPC filed on behalf of
petitioner for ad-interim and ex-parte stay/order for interim measure of
protection praying to stay the operation, implementation and effect of
temporary suspension order bearing No. NHIDCL/Tripura/Mtc./2026-
27/2153 dated 25.09.2026 issued by the Respondent-National Highways
and Infrastructure Development Corporation Limited (in short
‘NHIDCL’).
11. Vide the aforesaid notice, the Respondent has temporarily
suspended the Petitioner from participating in ongoing and future
bidding process of NHIDCL, Ministry of Road, Transport and Highways
(in short ‘MoRTH’).
12. The case of Petitioner is that the Petitioner is an Engineering,
Procurement and Construction (in short ‘EPC’) contractor in respect of
improvement and widening of two lanes with paved shoulder of road on
Fultali-Jurichhara Section of NH-208 (Package-II), State of Tripura. This
contract was awarded to the Petitioner vide Letter of Acceptance dated
24.11.2020.
13. It is submitted by the Learned Counsel for the Petitioner that the


I.A. 28575/2026 in O.M.P.(I)(COMM.)482/2026 Page 2 of 4

Signature Not Verified
Signed By:PRAMOD
KUMAR VATS
Signing Date:20.11.2026
10:52:12

project was completed on 02.02.2023 and completion certificate,
thereafter, was issued by the Respondent. The project is under the Defect
Liability and Maintenance Period. It is submitted that the Respondent
observed certain defects and issued a cure notice of sixty days to carry
out.

14. Vide impugned temporary suspension notice dated 25.09.2026, in
view of failing to complete rectification within the prescribed time and
failure to start the maintenance and repairs, in exercise of powers
conferred by MoRTH circular dated 06.10.2021, the Petitioner was
temporarily suspended from participating in ongoing and future bidding
of NHIDCL, MoRTH.
15. The Learned Counsel for Petitioner has drawn my attention to the
MoRTH circular dated 06.10.2021. Clause 5 of the said circular enjoins
upon Respondent to issue a notice to the contractor by giving 15 days
time to furnish its written reply and allow personal hearing before the
Competent Authority before passing an order of barring the contractor
from bidding for other construction.
16. It is further submitted by the Learned Counsel for the Plaintiff that
without any such show cause notice, the impugned order has been
passed, suspending the Petitioner from participating in ongoing/future
bidding of NHIDCL, MoRTH for one month.
17. The Learned Counsel for the Respondent submits that he requires
to seek the instructions from the Department.
18. I have carefully perused the MoRTH circular dated 06.10.2021.
19. I agree with the Learned Counsel for Plaintiff that a 15 days notice
was required to be given to the Petitioner before suspending him for


I.A. 28575/2026 in O.M.P.(I)(COMM.)482/2026 Page 3 of 4

Signature Not Verified
Signed By:PRAMOD
KUMAR VATS
Signing Date:20.11.2026
10:52:12

participating in ongoing future bidding of NHIDCL, MoRTH.
20. Accordingly, I stay the operation of impugned order dated
25.09.2026 till further orders.
21. Re-notify on 28.01.2027.


VINOD KUMAR, J
NOVEMBER 19, 2026/cd