Ingram Micro India Private Limited vs Best Hawk Infosystems Private Limited
- Court
- Bombay High Court
CNR No : HCBM020236542026
2026:BHC-OS:22104
carbpl263653-2026-J.doc
AGK
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ORDINARY ORIGINAL CIVIL JURISDICTION
IN ITS COMMERCIAL DIVISION
COMM ARBITRATION PETITION (L) NO.23653 of 2026
Ingram Micro India Private Limited
… Petitioner
Vs.
Best Hawk Infosystems Private Limited
… Respondent
ATUL
GANESH
KULKARNI
Mr. Sagar Wagle with Mr. Kashyap Samant, and Ms.
Lisa Rasquinha i/by K & P Legal Combine LLP for the
Petitioner.
Digitally signed by
ATUL GANESH
KULKARNI
Date: 2026.10.09
12:38:03 +0530
Ms. Sonal with Mr. Vaibhav Singh, Ms. Anushka Parab,
and Mr. Mohammad Adil i/by The Max Legal for the
Respondent.
CORAM : AMIT BORKAR, J.
RESERVED ON : OCTOBER 8, 2026
PRONOUNCED ON : OCTOBER 9, 2026
JUDGMENT:
1. By the present Petition filed under Section 9 of the
Arbitration and Conciliation Act, 1996, the Petitioner seeks ad-
interim relief during the time when the Arbitral Tribunal is yet to
be constituted. According to the Petitioner, the Respondent is
facing financial difficulties and there is a possibility that the
Respondent may deal with its assets in a manner which may cause
prejudice to the Petitioner. The Petitioner seeks a direction to the
1
Uploaded on - 09/10/2026 Downloaded on - 09/10/2026 12:57:12
carbpl263653-2026-J.doc
Respondent to pay the outstanding amount. The Petitioner seeks
an injunction restraining the Respondent from selling, transferring
or otherwise dealing with its assets or creating any third party
rights therein. The Petitioner seeks disclosure on oath of all
movable and immovable properties of the Respondent and such
other reliefs as this Court may consider proper.
2. According to the Petitioner, the relevant facts which have
resulted in filing of the present Petition are as follows. The
Petitioner states that it supplied goods to the Respondent in good
faith. The Respondent received and used the goods for its own
benefit, but the payments payable to the Petitioner remained
outstanding. According to the Petitioner, the Respondent
repeatedly assured that the outstanding amounts would be paid,
but the payments have not been made till date. As the Respondent
did not clear the outstanding dues, despite repeated assurances,
the Petitioner has invoked the Arbitration Clauses contained in its
invoices. According to the Petitioner, by accepting the invoices, the
Respondent became bound by the Arbitration Agreement
contained therein. The Petitioner states that between 26 July 2024
and 30 April 2025, it raised various invoices upon the Respondent
for the supplies made by it. The amounts under these invoices
remained unpaid and are the subject matter of the present
Petition. On 18 March 2025, the Respondent sent an email to the
Petitioner confirming the unpaid balance amount as Rs.
23,84,35,447000/-. On 6 April 2025, as the Petitioner was still
waiting for payment of the outstanding amount, it requested the
Respondent to make arrangements for payment. The Respondent
2
Uploaded on - 09/10/2026 Downloaded on - 09/10/2026 12:57:12
carbpl263653-2026-J.doc
thereafter sent an email in relation to such arrangement towards
the amount payable to the Petitioner. On 10 June 2025, the
Petitioner addressed a demand letter to the Respondent and its
Directors. In the said letter, the Petitioner pointed out that the
Respondent had accepted delivery of the goods supplied by the
Petitioner and that there was no valid reason for withholding
payment of the invoices.
3. On 29 July 2025, the Respondent sent an email
acknowledging that an amount of Rs. 24,06,01,649.69/- was
outstanding. The Respondent stated that it was in discussion with
the local branch of the Petitioner Company and had held a meeting
with the said branch. Thereafter, on 20 August 2025, after several
follow-ups, the Respondent sent another email. The Petitioner had
sought payment of Rs. 15.32 crores. The Respondent assured that
it would make payment of approximately Rs. 6 to 8 crores by the
end of August 2025. As the outstanding amount was still not paid,
the Petitioner deposited Cheque No. 181675 dated 18 February
2026 for an amount of Rs. 24,03,01,646/-. The cheque was
dishonoured on the same date. The Bank Memo gave the reason
for dishonour as “Account Closed”. Thereafter, the Petitioner issued
a demand notice under Section 138 of the Negotiable Instruments
Act to the Respondent. On 1 April 2026, the Petitioner issued a
demand notice in Form-4, along with the relevant invoices, at the
Registered Office of the Respondent. The Respondent replied to
the said notice on 16 April 2026 and did not admit its liability. The
Petitioner thereafter replied to the Respondent by its letter dated
24 April 2026. According to the Petitioner, even as on date, an
3
Uploaded on - 09/10/2026 Downloaded on - 09/10/2026 12:57:12
carbpl263653-2026-J.doc
amount of Rs. 32,60,37,480/- remains payable by the Respondent.
The Petitioner has filed the present Arbitration Petition.
4. Mr. Wagle, learned Advocate for the Petitioner, submits that
on 18 March 2025, at 7.13 p.m., the Respondent sent an email
confirming the balance amount payable to the Petitioner as Rs.
23,84,35,447000/-. He submits that the balance confirmed by the
Respondent in the statement signed and stamped by it and
attached to the said email did not include the invoices
subsequently raised for supplies made at the request of the
Respondent. According to him, these supplies were made on a
revolving credit basis so that the Respondent could use such
supplies for liquidating its earlier outstanding dues. He submits
that the said balance confirmation did not include those invoices
which had not become due on the date on which the balance
confirmation was signed, stamped and issued. It is submitted that
the Respondent had acknowledged the amount due to the
Petitioner but failed to make payment of the said amount. He
submits that despite repeated follow-ups, the Respondent did not
clear the outstanding amount. The Petitioner, by its email dated 20
August 2025 sent at 6.42 p.m., had sought payment of Rs. 15.32
crores. In response, the Respondent sent an email on the same day
at 7.55 p.m. assuring that an amount of Rs. 6 to 8 crores would be
paid by the end of August 2025. The Respondent referred to
rotational billing and thereby sought supplies from the Petitioner
even though a substantial amount was outstanding from the
Respondent. He submits that even after the balance amount was
confirmed and repeated assurances of payment were given, the
4
Uploaded on - 09/10/2026 Downloaded on - 09/10/2026 12:57:12
carbpl263653-2026-J.doc
Respondent did not clear the outstanding dues. As no payment was
made despite several reminders, the Petitioner was required to
exercise its rights under the agreed terms of supply. The Petitioner
deposited Cheque No. 181675 dated 18 February 2026 for an
amount of Rs. 24,03,01,646/- (Rupees Twenty Four Crores Three
Lakhs One Thousand Six Hundred and Forty Six Only), drawn on
HSBC, the bankers of the Respondent. According to the Petitioner,
the cheque had been issued in accordance with the agreed terms of
supply. However, when the cheque was deposited with the
Petitioner's banker, Axis Bank Limited, Vikhroli Branch, it was
returned unpaid. The Petitioner received the Bank Memo dated 18
February 2026 stating that the cheque was dishonoured for the
reason “Account Closed”.
5. Learned Advocate appearing for the Petitioner, inviting my
attention to paragraph 12 of the additional affidavit, submitted
that the Respondent's Balance Sheet and Statement of Profit and
Loss Account for the year ended 31 March 2025, duly certified by
the Respondent's statutory auditors, show a net loss of Rs. 15.23
crores. He submitted that, in the preceding financial year 2023-24,
the Respondent had shown a profit of Rs. 0.82 crores. He
submitted that for the financial year 2024-25, the reserves and net
worth of the Respondent are shown as negative at Rs. 12.01
crores, whereas in the previous financial year the same were
positive. According to him, these figures show that there has been
diminution in the assets and financial strength of the Respondent.
He submitted that the Respondent had suffered a net loss of
approximately Rs. 15.23 crores for the year ended 31 March 2025,
5
Uploaded on - 09/10/2026 Downloaded on - 09/10/2026 12:57:12
carbpl263653-2026-J.doc
as against a net profit of approximately Rs. 0.82 crores in the
preceding financial year. He submitted that the Respondent has
current liabilities exceeding Rs. 120 crores, whereas its cash and
cash equivalents are only about Rs. 0.73 crores. He pointed out
that the basic and diluted loss per share for the year is Rs. 43.60,
as against earnings of Rs. 2.37 per share in the preceding year.
According to the learned Advocate, these financial figures show a
substantial deterioration in the financial position of the
Respondent.
6. Learned Advocate for the Petitioner submitted that the
disclosure affidavit filed by the Respondent pursuant to the order
passed by this Court does not disclose any movable properties of
the Respondent. According to him, when the Respondent has been
directed to disclose its assets and the disclosure affidavit does not
show any movable assets, the same raises a serious doubt
regarding the manner in which the Respondent is dealing with its
assets. He submitted that the material placed on record is
sufficient to show a likelihood of diminution of the assets of the
Respondent and that the Petitioner has made out a case for grant
of protection under Section 9 of the Arbitration and Conciliation
Act, 1996.
7. Learned Advocate appearing for the Petitioner relied upon
the judgment of the Division Bench of this Court in Sunfield Global
Pte Limited Vs Liberty Investments Private Limited, Commercial
Arbitration Appeal No. 1634 of 2026, decided on 22 September
2026. He submitted that, in paragraph 21 of the said judgment,
the Division Bench has approved the test relating to diminution of
6
Uploaded on - 09/10/2026 Downloaded on - 09/10/2026 12:57:12
carbpl263653-2026-J.doc
assets laid down by a learned Single Judge of this Court in Norvik
Shipping Asia PTE Limited . According to him, the said test is
required to be applied while considering whether the Petitioner
has made out a case for grant of interim protection on the ground
that the assets of the Respondent are likely to be diminished.
8. Ms. Sonal, learned Advocate for the Respondent, submits
that it is important to note that although the Petitioner has
presented the cheque as a cheque dated in the year 2026, the
cheque leaf belongs to an old cheque series relating to the
Respondent's earlier HSBC account. According to her, the cheque
had been handed over in blank as a security instrument during the
earlier business dealings between the parties. She submits that the
cheque was never issued in the year 2026 pursuant to any fresh
reconciliation of accounts or as an acknowledgement of the
particular amount now claimed by the Petitioner. She submits that
the banking records available at the relevant time are important.
According to her, the Respondent's HSBC bank statement for the
period October to December 2019 shows that cheque instruments
from the said account were regularly used during that period and
several cheques were presented and cleared in October and
November 2019. She submits that the records of the Respondent
show that the cheque leaf now relied upon by the Petitioner was
part of the old cheque series which was being used during the said
period. In these circumstances, according to her, the Petitioner's
attempt to show that the cheque was a fresh cheque issued in the
year 2026 towards payment of the alleged liability of Rs. 24 crores
is contrary to the banking record and requires strict proof. She
7
Uploaded on - 09/10/2026 Downloaded on - 09/10/2026 12:57:12
carbpl263653-2026-J.doc
submits that the HSBC account on which the cheque was drawn
was subsequently closed in March 2021. Thus, according to the
Respondent, the said account had been closed several years before
the date appearing on the cheque now relied upon by the
Petitioner.
9. She submits that after the aforesaid HSBC current account
was closed, the Respondent continued its regular business
payments through other banking arrangements, particularly
through Jammu & Kashmir Bank. The documents produced on
record are, according to her, only examples of the payments made
through the said bank and do not contain the complete details of
all payments made by the Respondent. She submits that, for
example, the correspondence exchanged in July 2022 records
several RTGS payments made by the Respondent to the Petitioner
through Jammu & Kashmir Bank. Those payments were duly
received and acted upon by the Petitioner. She submits that the
Petitioner's own subsequent correspondence shows that the
Petitioner was aware of the banking arrangements then being used
by the Respondent. By communication dated 30 September 2024,
the Petitioner's representative sought confirmation regarding two
cheques of Rs. 1.50 crores each, making a total amount of Rs. 3
crores, drawn on Jammu & Kashmir Bank. According to her, these
documents are produced only as examples of the regular course of
dealings between the parties and are not relied upon as a complete
record of all such dealings.
10. Learned Advocate submitted that the balance confirmation
relied upon by the Petitioner cannot be treated as a final admission
8
Uploaded on - 09/10/2026 Downloaded on - 09/10/2026 12:57:12
carbpl263653-2026-J.doc
of liability. According to her, the said confirmation was only
provisional and was prepared for the purpose of insurance. She
submitted that the Petitioner is seeking to rely upon such
provisional statement as if it was a final and binding
acknowledgement of the amount claimed by the Petitioner.
11. She submitted that the cheque relied upon by the Petitioner
was a blank cheque which had been issued much prior to the date
on which it was presented. According to her, the said cheque was
given to the Petitioner as a security instrument and has
subsequently been misused by filling in the date and other
particulars. She submitted that the bank account on which the
cheque was drawn had been closed in March 2021. According to
her, there was no possibility of the Respondent issuing the said
cheque in the year 2026. She submitted that the Petitioner has
subsequently filled in the cheque and inserted a date falling in the
year 2026. On this basis, she submitted that the cheque cannot be
treated as proof of the present liability claimed by the Petitioner.
REASONS AND FINDINGS:
12. I have considered the submissions made by the learned
Advocates appearing for both sides
13. At the outset, it has to be kept in mind that the prayer is for
protecting the amount till the arbitration proceedings are
completed. In prayer clause (a), the Petitioner has asked that
Rs.32,60,37,480/- be deposited with this Court, which consists of
the principal amount under the invoices and interest calculated
thereon, or such other amount and in such manner as this Court
9
Uploaded on - 09/10/2026 Downloaded on - 09/10/2026 12:57:12
carbpl263653-2026-J.doc
may think proper.
14. The Petitioner has placed on record the invoices which were
raised from time to time. These invoices contain an arbitration
clause.
15. From the material before the Court, it appears that the
Respondent had accepted the goods supplied by the Petitioner. No
material has been shown to me which indicates that at the relevant
time there was any dispute regarding the quality or delivery of the
goods. The dispute which is now raised by the Respondent is
regarding what amount is payable after taking into account
reconciliation, credit notes, rebates and other adjustments which,
according to the Respondent, are required.
16. The case of the Petitioner gets some support from the
correspondence between the parties. The record contains the email
dated 18 March 2025 by which the balance confirmation was
forwarded. The attachment shows closing balance of
approximately Rs.23.84 crores as on 15 February 2025. After that,
the correspondence does not show any immediate and clear denial
of the outstanding amount. On 29 July 2025, the Respondent
acknowledged outstanding amount of Rs.24,06,01,649.69 and
stated that it was working with the local branch of the Petitioner.
Thereafter, on 20 August 2025, the Respondent assured payment
of approximately Rs.6 to 8 crores by the end of the month, when
the Petitioner had asked for payment of Rs.15.32 crores.
17. These communications are being considered only for seeing
the prima facie position at this stage. I am conscious that every
10
Uploaded on - 09/10/2026 Downloaded on - 09/10/2026 12:57:12
carbpl263653-2026-J.doc
statement in correspondence cannot always be treated as a
admission. The Respondent will have the right to place its full
accounts before the Arbitral Tribunal and to show the adjustments
which, according to it, are payable or deductible. But at this stage,
the Court cannot ignore the repeated references made to the
outstanding amounts and the assurances given for payment. If the
correspondence of the Respondent is seen as a whole, it does not
support the case that from the beginning there was a genuine
denial that no amount was payable.
18. I have considered the submission of the Respondent that the
balance confirmation was only provisional and was prepared for
the purpose of insurance. The Respondent has relied upon later
correspondence relating to credit notes, OEM adjustments,
reconciliation and rotational billing. There is material showing that
the business relationship between the parties continued and that
credit notes and other adjustments were being discussed. The
Respondent has relied upon the communication of the Petitioner
dated 19 September 2025 concerning schemes, discounts, and
credit notes. That communication shows that Ingram Micro had a
process for issuing and adjusting credit notes and for avoiding
reconciliation problems.
19. Therefore, I am not proceeding on the basis that every rupee
claimed by the Petitioner has been decided or admitted by the
Respondent. The contention of the Respondent regarding
reconciliation will remain open before the Arbitral Tribunal.
11
Uploaded on - 09/10/2026 Downloaded on - 09/10/2026 12:57:12
carbpl263653-2026-J.doc
20. The Respondent has relied to a large extent upon cheque
bearing No.181675. According to the Respondent, this was an old
blank cheque given as security and the HSBC account on which the
cheque was drawn had been closed in March 2021. The
Respondent has produced the HSBC bank statement for October to
December 2019 and the material showing closure of the account in
March 2021. Therefore, according to the Respondent, there could
not have been any fresh issue of the cheque in the year 2026. This
submission does raise an issue which will have to be examined in
the proper proceedings. Therefore, I do not treat the dishonoured
cheque as proof of the whole monetary claim of the Petitioner. At
the same time, the dispute regarding the cheque does not take
away the other material placed by the Petitioner. The invoices,
correspondence between the parties, balance confirmation, later
assurances for payment and the financial statements of the
Respondent are all different pieces of material. Therefore, the
request for interim protection is not based only on the cheque.
21. In my view, the more important circumstance is the present
financial position of the Respondent. The Petitioner has placed on
record the Balance Sheet and Statement of Profit and Loss of the
Respondent for the year ending 31 March 2025. These are stated
to have been certified by the statutory auditors of the Respondent.
Paragraph 12 of the affidavit of the Petitioner records that the
Respondent suffered a net loss of approximately Rs.15.23 crores
during the financial year 2024-25, whereas in the previous year
there was a net profit of approximately Rs.0.82 crores. The same
financial statements show reserves and surplus of approximately
12
Uploaded on - 09/10/2026 Downloaded on - 09/10/2026 12:57:12
carbpl263653-2026-J.doc
Rs.12.01 crores in negative, whereas in the previous year there
were positive reserves and surplus of approximately Rs.3.21
crores. The short-term borrowings are approximately Rs.33.57
crores and trade payables are approximately Rs.87.01 crores.
Against this, the cash and cash equivalents are only approximately
Rs.0.73 crores. The basic and diluted earnings per share are shown
as a loss of Rs.43.69, as against earnings of Rs.2.37 in the earlier
year. These figures are not figures prepared only by the Petitioner
for this case. These are figures which appear in the financial
statements of the Respondent and are stated to have been certified
by its statutory auditors. Therefore, these figures have importance.
They show that the financial position of the Respondent has
changed substantially in one financial year. There is a change from
profit to loss of Rs.15.23 crores. There are negative reserves and
surplus. There is a large difference between the liabilities and the
cash which is available. These circumstances cannot be treated as
only a normal change in the financial position.
22. The Respondent has stated in its disclosure affidavit that it
"continue[s] to remain financially solvent and operationally
viable". I have considered this submission. Merely because the
Respondent is continuing its business, that does not answer the
concern which arises from its own audited financial statements. A
company may continue its business and still may not have enough
assets which are readily available for satisfying a substantial
arbitral award. For the present purpose, what is important is
whether the assets which may be available for execution are
sufficiently protected.
13
Uploaded on - 09/10/2026 Downloaded on - 09/10/2026 12:57:12
carbpl263653-2026-J.doc
23. The Respondent has disclosed three immovable properties.
As stated in its affidavit, the first property is valued at more than
Rs.2.5 crores, the second property is valued at more than Rs.2.5
crores and the third property is valued at more than Rs.7.5 crores.
The Respondent has stated that there are charges over some of
these properties. It has given an undertaking not to sell, transfer,
alienate, encumber, mortgage or otherwise deal with these
properties till orders of this Court. Even then, this disclosure does
not completely remove the concern raised before the Court. The
Petitioner has pointed out that independent valuation reports, title
documents, encumbrance certificates and bank documents
supporting the values and charges have not been annexed with the
disclosure. The Petitioner has pointed out that the disclosure does
not give details of movable assets, bank balances, fixed deposits,
trade receivables and other current assets. Even if the values stated
by the Respondent are accepted, the gross value of the three
properties together is approximately Rs.12.5 crores, whereas the
claim before the Court is substantially more than Rs.30 crores. If
the encumbrances disclosed are considered, the Petitioner says that
the actual value which is available as security would be much less.
24. I do not accept that merely because movable properties are
not disclosed in the affidavit, it proves that the Respondent had
dishonest intention. For such a finding, stronger material would be
required. But for granting protection under Section 9, the Court is
not required to first find dishonest intention. What has to be seen
is whether, if all the circumstances are considered together, there is
a sufficiently strong possibility that the assets available for
14
Uploaded on - 09/10/2026 Downloaded on - 09/10/2026 12:57:12
carbpl263653-2026-J.doc
satisfying the claim may reduce or may become unavailable.
25. This takes the Court to the judgment of the Division Bench of
this Court in Commercial Arbitration Appeal (L) No.1634 of 2026 .
In paragraph 21, while considering the judgment in Norvic
Shipping Asia PTE Ltd. v. Zigma International , the Division Bench
recorded the following principles:
“the applicant need not prove dishonest
transfer/concealment. A "strong possibility" of diminution
suffices something more than bare suspicion, but short of
absolute proof, based on objective material on record.”
26. The Division Bench observed that assets can become
unavailable even due to ordinary commercial reasons such as
losses, charges to lenders and assignment of receivables. It held
that "diminution of assets" can include reduction in value, creation
of new encumbrances, increase in secured liabilities, transfer of
receivables or any other circumstance which substantially reduces
the assets available for execution. The Division Bench has made an
important distinction. The Court need not wait till the asset has
actually disappeared or has been transferred. Section 9 is
preventive in nature. Its purpose is to protect the effectiveness of
the arbitral award before the situation becomes irreversible. At the
same time, the power under Section 9 cannot be used only because
arbitration proceedings are pending. There must be some objective
material showing a real possibility that the assets may reduce or
may become unavailable. In paragraph 22 of the said judgment,
the Division Bench expressly stated that it was "in respectful
agreement with these findings and reaffirm[ed] the law
15
Uploaded on - 09/10/2026 Downloaded on - 09/10/2026 12:57:12
carbpl263653-2026-J.doc
enunciated in Norvic Shipping Asia PTE Ltd ." The said judgment
gives guidance which is relevant while considering the present
Petition.
27. If this test is applied to the present case, I find that the
Petitioner has gone beyond the stage of merely having a suspicion.
There is objective material before the Court. The audited financial
statements of the Respondent show a net loss of Rs.15.23 crores,
negative reserves and surplus of approximately Rs.12.01 crores,
short-term borrowings of approximately Rs.33.57 crores and trade
payables of approximately Rs.87.01 crores against cash and cash
equivalents of only approximately Rs.0.73 crores. The Respondent
has disclosed only three immovable properties. Their total gross
value, even according to the Respondent's own figures, is
approximately Rs.12.5 crores and some of them are stated to be
encumbered.
28. The Petitioner has placed on record that insolvency
proceedings under Section 9 of the Insolvency and Bankruptcy
Code have been initiated against the Respondent by another
creditor before the National Company Law Tribunal. Mere
pendency of such proceedings does not mean that the claim of the
Petitioner will necessarily fail. But when this circumstance is seen
together with the audited financial loss, negative net worth,
substantial liabilities and limited assets disclosed by the
Respondent, it adds to the circumstances which show that
protection of the assets is required.
16
Uploaded on - 09/10/2026 Downloaded on - 09/10/2026 12:57:12
carbpl263653-2026-J.doc
29. The Respondent has submitted that its financial position
should not be treated as proof of any intention to dissipate its
assets. To this limited extent, the submission is correct. Financial
difficulty cannot be treated as proof of dishonest intention. But
the principle stated in Norvic , as approved by the Division Bench,
does not require the Petitioner to prove dishonest intention. A
“strong possibility” of diminution, when supported by objective
material, is sufficient. Therefore, the present case has to be
considered on the financial position of the Respondent and the
likely availability of assets for execution, and not on any
assumption regarding the personal intention of the Respondent.
30. I have considered the submission of the Respondent that the
Court has protected the three properties disclosed by it and no
relief is required. The Respondent submits that if the entire claim
is secured, it would become recovery of the amount before the
award. There is substance in the general submission that Section 9
cannot be used as a substitute for final adjudication. Merely
because a monetary claim is made, the Court should not direct
payment of the amount before the dispute is decided.
31. The present case is on a different footing. The direction
contemplated by prayer clause (a) is not being made because this
Court has decided that the Respondent is liable to pay
Rs.32,60,37,480/-. The direction is being made because the
material before the Court shows a strong possibility that the assets
presently available may not remain sufficient or may become
unavailable by the time the arbitral award is passed and becomes
enforceable. Therefore, the purpose of directing deposit or security
17
Uploaded on - 09/10/2026 Downloaded on - 09/10/2026 12:57:12
carbpl263653-2026-J.doc
is to preserve the amount and not to recover the amount.
32. The balance of convenience has to be considered. If the
amount is secured and the Respondent succeeds in the arbitration,
the amount will remain subject to appropriate orders and the
rights of the Respondent will not be lost. On the other side, if the
amount is not secured, and the financial position of the
Respondent becomes weak, and the Petitioner succeeds in
arbitration, the Petitioner may have an award which cannot be
effectively realised. In such a situation, the prejudice to the
Petitioner would be much more serious. The Division Bench, in
paragraph 26, observed, where the material showed a strong
prima facie case, that "The criteria, namely, a strong prima facie
case, balance of convenience and irreparable loss are squarely in
favour of the Appellant." The Division Bench observed in
paragraph 27 that the Court should not turn a blind eye to the
conduct of a party where such conduct may frustrate the claim or
delay payment of dues.
33. In the present case, I find that these three considerations are
substantially satisfied. The Petitioner has produced the invoices for
the supplies, correspondence showing the outstanding amounts,
the balance confirmation, later assurances for payment and the
dishonoured cheque. The Respondent has raised disputes
regarding reconciliation and regarding the nature and use of the
cheque. Those questions will have to be decided in arbitration. But
at this stage, these disputes do not outweigh the material which
shows substantial deterioration in the financial position of the
Respondent.
18
Uploaded on - 09/10/2026 Downloaded on - 09/10/2026 12:57:12
carbpl263653-2026-J.doc
34. As presently claimed, the amount of the Petitioner's claim is
Rs.32,60,37,480/-. Prayer clause (a) gives the breakup of this
amount as Rs.24,01,76,646/- towards outstanding invoices and
Rs.8,58,60,833/- towards interest calculated up to 25 June 2026.
The Respondent disputes the final liability and disputes the
interest. Therefore, it is made clear that the Arbitral Tribunal will
decide the final principal amount, the effect of credit notes and
reconciliation and the entitlement to interest and the applicable
rate of interest, without being influenced by the present order. At
the same time, for the limited purpose of interim protection, I find
that the Petitioner has shown sufficient grounds for securing the
amount claimed. The relief is proportionate to the circumstances.
The Respondent is not being directed to pay the amount to the
Petitioner at this stage. The amount is only required to be secured
till the dispute is decided. In this way, the Respondent is protected
from immediate recovery, while the Petitioner is protected against
the possibility of having an arbitral award which may later become
difficult to enforce.
35. I find on merits that the Petitioner has established a prima
facie case. There is a strong possibility of diminution or
insufficiency of the assets which may be available for execution.
The balance of convenience is in favour of securing the claim of
the Petitioner. If such protection is refused, the Petitioner may
suffer serious prejudice if it succeeds in the arbitration and finds
that the award cannot be effectively realised. Consequently, prayer
clause (a) deserves to be granted. The Respondent shall secure the
Petitioner's claim of Rs.32,60,37,480/- by depositing the said
19
Uploaded on - 09/10/2026 Downloaded on - 09/10/2026 12:57:12
carbpl263653-2026-J.doc
amount with this Court or by furnishing security in such form as
may be acceptable to the Prothonotary and Senior Master. This
protection is only an interim measure and shall remain subject to
the final decision of the Arbitral Tribunal. Nothing stated in this
order shall be understood as a final finding that the Respondent is
liable to pay the entire amount of Rs.32,60,37,480/-.
36. In view of the foregoing discussion, and upon overall
assessment of the material record, the relief is granted in terms of
prayer clause (a), subject to the following directions:
i) The Respondent shall, within four weeks from today,
deposit with the Prothonotary and Senior Master of this
Court an amount of Rs.32,60,37,480/- or, in the alternative,
furnish a bank guarantee of a Nationalised Bank or
Scheduled Commercial Bank for the said amount, to the
satisfaction of the Prothonotary and Senior Master;
ii) The amount deposited or secured shall remain subject
to orders of this Court and the final decision of the Arbitral
Tribunal;
iii) The Respondent shall not seek withdrawal, release or
cancellation of the security except with the permission of this
Court or in accordance with the final award and orders
passed thereon;
iv) It is clarified that the present order is an order for
securing the amount in dispute. It shall not be treated as an
adjudication or decree directing payment of
Rs.32,60,37,480/- in favour of the Petitioner;
20
Uploaded on - 09/10/2026 Downloaded on - 09/10/2026 12:57:12
carbpl263653-2026-J.doc
v) The rights and contentions of both parties regarding
the merits of the monetary claim, reconciliation, credit notes,
interest, and the validity and effect of the cheque are
expressly kept open for determination in the arbitration.
37. The Arbitration Petition stands disposed off in above terms.