KAMAL KRISHAN CHIBBER vs UNION TERRITORY OF J AND K (POWER DEVELOPMENT) AND ORS.

Court
Jammu and Kashmir High Court


HIGH COURT OF JAMMU & KASHMIR AND LADAKH
AT SRINAGAR.


Case No: Arb App No.05/2024


Reserved on: 10.07.2026
Pronounced on: 06.10.2026
Uploaded on: 06.10.2026


Whether the operative part or full
Judgment is pronounced :Full


Kamal Krishan Chibber
(aged 83 years)
S/O Sh. Noralta Singh
Chibber,
R/O Ram Nivas, Ist Floor
M.K.Road, Khanna, Panjab
through his duly constituted
attorney Jeevan Chibber S/O
Kamal Krishan Chibber R/O
st
Ram Nivas, 1 Floor,
M.K.Road, Khanna, Panjab.


……Appellant(s)…..

Through: Mr. M. A. Dar, Advocate.

v/s

1. UT of J&K
(Previously State of
J&K) through Chief
Secretary, new
Secretariat,
Srinagar/Jammu.
2. Commissioner
Secretary, Power
Development
Department, New
Secretariat,
Srinagar/Jammu.
3. Managing Director,
Power
Development
Corporation,

Arb App No. 05/2024 Page 1 of 27

Boulevard Road,
Srinagar.
4. Chief Engineer,
Generation In-
Charge USHP-II
PDD Complex,
Bemina Srinagar.

5. Executive
Engineer, Civil
Maintenance
Division, Formerly
Wangat Link
Division (USH)),
Kangan.



Through:
Mr. M. A. Chashoo, Sr. Advocate, with
Ms. Hikma Advocate.

…Respondent(s)…



CORAM: HON’BLE MR. JUSTICE RAJNESH OSWAL, JUDGE
HON’BLE MR. JUSTICE RAHUL BHARTI, JUDGE

JUDGMENT


PER RAJNESH OSWAL-J


1. This is an appeal under Section 37 of the Jammu & Kashmir
Arbitration and Conciliation Act, 1997 (in short, “the Act”),
directed against a judgment dated 04.07.2024 passed in Arb.
P.No.5/2019, whereby the learned Single Bench has allowed
an application under Section 34 of the Act filed by the
respondents and has come to set aside sole arbitrator’s final
award dated 31.12.2018 which otherwise was in favour of the
appellant.

Arb App No. 05/2024 Page 2 of 27

Factual Matrix:
2. Vide a letter of award bearing No. USHP-II/EC/27 dated
30.06.1988 , the appellant was awarded a contract for
execution of balance work of Wangat Weir at USHP-II, Kangan.
As per the terms and conditions of consequent agreement
executed between the parties, period of completion stipulated
was up to 30.11.1989.
3. As the appellant was not able to complete the work within the
stipulated time and also within extended period of time, i.e. up
to year 1992, so the Executive Engineer concerned served a
termination notice No. 214-16 dated 05.05.1998 ,
subsequently followed by instant termination of the contract
on 05.05.1998.
4. The total cost of allotted work was fixed at Rs. 199.06 lakhs
against which the appellant is said to have completed the work
only to extent of Rs. 113.00 lakhs up to 01.04.1994.
5. The appellant had started approaching the respondents
through series of representations dated 29.11.2000,
30.12.2000, 22.05.2001, 11.04.2001, 25.07.2003,
31.07.2004, 03.09.2005 and 26.02.2011 for settlement of
his claim/s.
6. When his repeated communications received no response, the
appellant invoked section 11 of the Act whereby in terms of an
order dated 04.11.2013 in AA No. 19/2013, Mr. G.M. Dar,

Arb App No. 05/2024 Page 3 of 27

District and Sessions Judge (Retd), was appointed as sole
arbitrator, who entered upon the reference on 15.04.2014.
7. Before the Sole Arbitrator, the appellant, through his counsel,
submitted his statement of claims. The composition of the
statement of claims submitted by the appellant is as under : -
a. Balance escalation costs : Rs.21,43,536/-
b. Balance amount of the final bill : Rs. 76,865/-
c. Flood damages : Rs. 24,25,987/-
d. Diversion of Nallah : Rs. 11,32,774/-
e. On account of security deposit
and amount of earnest money deposit : Rs.8,05,000/-.
f. Interest @ 18% compound from
1999 to 2013 : Rs.1,77,77,237/-.


8. It was stated by the appellant that, at one point of time, the
respondents took a plea that some civil suit litigation was
pending before the Civil Court of learned Additional District
Judge, Srinagar; therefore, the release of payment due to the
appellant was to remain on hold which had made the
appellant to seek the indulgence of said Civil Court to obtain a
clarification on 18.08.2005 , wherein it stood stated that there
is no prohibitory order in operation on the strength of which
the settlement of claims and its payment to the appellant
could be denied to the appellant, but despite furnishing of said
clarification, nothing was done in the matter, and the officials
of the respondents continued to sit over the matter thereby
causing an irreparable loss to the appellant .

Arb App No. 05/2024 Page 4 of 27

9. It was stated by the appellant that, acting upon the
communication dated 26.02.2011 , the officials of the
respondents prepared a final bill which was submitted to the
Executive Engineer in response to query raised by him vide
communication dated 11.07.2012 .
10. The appellant, thereafter, obtained the requisite information
under the Right to Information Act, wherein it was disclosed
that an amount of Rs. 21,43,536/- was payable to the
appellant towards escalation. It was further indicated that a
final bill had been passed for payment of Rs. 76,865/-.
11. The appellant submitted that, apart from the aforesaid
undisputed amounts payable to him, he was also entitled to
payment towards restoration of flood damages and
construction of a bund, the works which were executed at the
instance and on the directions of the Engineering Department
of the respondent-Corporation.

12. The claimant further sought refund of the amounts deducted
from his running bills and retained as security deposit,
amounting to Rs. 7,75,000/- , besides the earnest money
deposit of Rs. 50,000/-.

13. Accordingly, the appellant asserted his entitlement to the
aforesaid amounts as well as to the other claims arising out of
the execution and termination of the contract
.
14. The respondents, in their reply, submitted that the appellant
had executed the work to the tune of Rs.113.00 lakhs up to

Arb App No. 05/2024 Page 5 of 27

01.04.1994 and thereafter abandoned the same and
consequently, the respondents were compelled to re-allot the
balance of the work to M/s M & Co., who executed it through
M/s Chibber and Co. The date of commencement of the said
work was 01.08.1998 , at revised rates amounting to
Rs.125.71 lakhs. It was further stated that the restoration
work necessitated by the floods of 1992 and 1995 had been
paid for in full.
15. The respondents further submitted that merely because the
contractor had raised a claim before the competent authority
did not mean that the amount claimed towards the contract,
including the amounts deducted from the running bills and
the earnest money deposit, would be released. According to
the respondents, the release of such amounts was subject to
clearance of the M-80 work at site and verification of the
relevant accounts by the concerned authorities.
16. The learned sole arbitrator, in terms of award dated
30.12.2018 , held the appellant entitled to the following
amounts:
Head Amount
Payment on account of restoration work. Rs. 25,75,036/-
Payment on account of earnest money. Rs. 50,000/-
Payment on account of security deposit. Rs. 8,10,000/-
Payment on account of escalation. Rs. 21,43,536/-
Payment on account of final bill. Rs. 76,865/-

Arb App No. 05/2024 Page 6 of 27

17. Further, the appellant was held entitled to interest on the
aforesaid amount at the rate of 6% per annum from the date of
filing of the arbitration petition till the date of the award and at
the rate of 18% per annum after one month from the date of
passing of the award till the final payment of the awarded
amount. The respondents were also directed to pay an amount
of Rs.1,00,000/- towards the Arbitrator’s fee, to be released
along with the award.

18. It needs to be noted that an interim award dated 20.01.2015
was passed, whereby the appellant was held entitled to
escalation charges to the tune of Rs.21,43,536/-.
19. The said interim award was assailed by the respondents by
filing time barred application under Section 34 of the Act but
the learned Principal District Judge, Srinagar, vide an order
dated 08.02.2017 , had dismissed the challenge as being
barred by limitation.
20. Said order dated 08.02.2017 passed by the learned Principal
District Judge, Srinagar, was thereafter upheld by the learned
Single Bench in terms of order dated 21.09.2023 in Arb.
Appeal No. 06/2017.
21. Learned Single Bench, in para 20 of the impugned judgment
dated 04.07.2024, came up with formulation of points of
determination relatable to adjudication of section 34 petition

Arb App No. 05/2024 Page 7 of 27

so filed by the respondents and which points of determination
are as under:
(i) Whether the claims entertained and awarded by the
learned arbitrator in terms of the impugned arbitral
award are stale and time barred and thereby
rendering the arbitral award in conflict with public
policy of the State and such claims are otherwise
beyond the scope of submission of arbitration?
(ii) Whether the award on an amount of Rs. 25,82,609/-
on account of restoration of flood damaged works in
the presence of clause 21 of the agreement ( ‘force
majeure’ clause) does not fall within the terms of
submission to arbitration?
(iii) Whether the interest awarded by the arbitrator is
contrary to statutory provisions of the Act and
therefore renders the award against public policy of
the State.

(iv) Whether the interim arbitral award dated 21.01.2015
is an independent final award quo the item of claim it
has decided and therefore does not merge with the
impugned arbitral (final) award?
22. Learned Single Bench, with respect to number (i) point of
determination related to limitation aspect, came to hold that
cause of action had accrued to the appellant on the
th
termination of the contract taking place on 5 of May, 1998
from which date onwards the appellant had become entitled to
claim payments, be it in relation to the work executed or by
way of damages for the breach of contract.

Arb App No. 05/2024 Page 8 of 27

23. Learned Single Bench has come to hold that the last leg of the
th
cause of action which otherwise had set-off w.e.f., 5 of May,
th
1998, for the appellant to act was on 12 of September,
2000 when the claims put-forth from his end was repudiated
by the respondents and that being the position, the laying of
his claims by the appellant before the learned arbitrator is to
be deemed to have been on 04.11.2013 which rendered the
arbitration proceedings as seriously time barred.
24. Learned Single Bench has, however, salvaged the interim
award dated 20.01.2015 in terms whereof claim of the
appellant for amount of Rs. 21,43,536/- stood granted and
held the interim award having attained the finality in the
manner as has been set out by the learned Single Bench in its
judgment.
25. The learned Single Bench came up with the final words of
adjudication, in exercise of jurisdiction under section 34 of the
Act, as set out in para 54, which is reproduced for the sake of
easy reference:
“For the foregoing reasons, this petition is allowed and
the entire award is set aside except arbitrator’s fee.
The award of a sum of Rs. 21,43,536/- on account of
st
escalation (covered by interim award dated 21
January, 2015) is found redundant and is held so.
However, the respondent-Contractor shall be entitled to
an amount of Rs. 21,43,536/- in terms of interim
st
arbitral award dated 21 January, 2015. The
respondent-Contractor shall be free to put interim
award to execution if not already done. The learned

Arb App No. 05/2024 Page 9 of 27

arbitrator shall be entitled to a sum of Rs. 1.00 lac
along with interest @ 6% per annum to be reckoned
st
with effect from the 31 December, 2018, till the same
is paid to the learned arbitrator by the petitioners
provided the same is not already paid.”

Grounds of Challenge:
26. The impugned judgment is challenged, inter alia , on the
following grounds:
a.
that the learned Single Bench has committed a grave
error in law in not taking a holistic view of the matter
while not considering the effect of communication dated
12.09.2000 which in unequivocal and expressed terms,
indicated that payment would not be released until the
litigation pending in the civil court is decided. In that
view of the matter, the cause of action got deferred till
2011 when the suit was finally dismissed, and the said
information was conveyed to the respondent department
vide communication dated 26.02.2011 based on which
communication, a final bill in relation to subject contract
along with bill for payment of escalation was submitted
for payment as is evident from the forwarding letter dated
17.07.2012 accompanying the escalation/final bill, but
the learned Single Bench has failed to take into
consideration the acknowledgement of liability by the
respondent department in its communication (supra).
b. that the learned Single Bench has nowhere provided
reason for not accepting the view taken by the learned
sole arbitrator whose finding about claim not being time-
barred was duly supported by cogent reasons. The
learned Arbitrator had elaborately dealt with the accrual

Arb App No. 05/2024 Page 10 of 27

of cause of action as in the present case, the cause of
action, be it to seek constitution of arbitral tribunal or
submit the claims before arbitral tribunal, had actually
accrued only after submission of bill for payment of
escalation/final bill in the year 2012, therefore,
considering this intervening period, no fault could be
found in the findings recorded by the learned arbitrator.
c. that the learned Single Bench has not taken note of the
observations made in the judgment in the case of
M/s B&T AG Vs. Ministry of Defense providing for
extension of limitation upon exclusion of the period in
facts and circumstances of the case.
d. that the plea of limitation was mixed question of law and
fact and learned arbitrator, after taking into account the
material placed on record, found the plea of limitation
unsustainable, therefore, learned Single Bench, vested
with limited scope of interference with the award as
provided under Section 34, could not have interfered with
the findings returned by the learned Arbitrator.
e. that the learned Single Bench has failed to take note of
and give effect to the provisions of section 19 of the J&K
Limitation Act, Samvat 1995 which provides for a fresh
period of limitation where, before the expiry of the
prescribed period, an acknowledgment of liability is made
in writing and signed by the party against whom such
right or claim is asserted. The appellant was, therefore,
entitled to the benefit of section 19 of the Limitation Act,
Samvat 1995, in view of the express acknowledgment of
liability made by the Executive Engineer vide
communication dated 12.09.2000 . The learned Single
Bench, however, failed to appreciate the legal impact and
effect of the said acknowledgment and consequently

Arb App No. 05/2024 Page 11 of 27

erred in holding the appellant’s claim to be barred by
limitation.
f. that the learned Single Bench ought to have considered
that the dismissal of pending suit in the month of
February 2011 provided a fresh cause of action to the
appellant, and within three years therefrom the appellant
resorted to arbitration.
g. that the case in hand was required to be dealt with in
accordance with the law prevailing prior to the year 2015,
during which period the petition under Section 11 of the
Act was filed, and during the said period the issue of
limitation was determined during adjudication of the
application under Section 11 of the Act, and that being
the legal position, the learned Single Bench was not
required to go into the controversy regarding limitation,
which was raised neither during proceedings under
section 11 of the Act, nor before the learned arbitrator,
but was raised for the first time during submission of
written arguments.
Submissions :
27. Learned counsel for the appellant has submitted that the
learned Single Bench has committed an error while
considering the effect of communication dated 12.09.2000 , as
limitation runs from the date when the right to sue accrues. In
terms of communication dated 12.09.2000 , the Executive
Engineer of the respondents stated that the final bill shall be
entertained after the proceedings pending before the civil
Court come to an end. Once the respondents themselves
deferred the consideration of the final bill subject to the

Arb App No. 05/2024 Page 12 of 27

outcome of the suit pending before the civil court, the cause of
action stood deferred and accrued afresh only when the suit
was dismissed in the month of February 2011. He has further
submitted that the Department itself acknowledged the
accrual of a fresh cause of action when the final bill dated
26.02.2011 was prepared by the Department and, within a
period of three years, a petition under Section 11 of the Act
was filed i.e. in the year 2013.
28. Learned counsel for the appellant has further submitted that
the explicit acknowledgment of specific outstanding amounts
of Rs.21,43,536/- towards escalation and Rs.76,865/-
towards the final bill, contained in the 2011 response under
the Right to Information Act, triggered the invocation of
Section 19 of the Act, and this acknowledgment having been
made within the three-year limitation window w.e.f. 2011,
therefore, the petition filed by the appellant in the year 2013
and the claims of the appellant ceased to be time-barred. He
has further argued that the deferment was constituted as a
contingent contract under Section 31 of the Contract Act;
therefore, the application of the respondents was required to
be dismissed. He has further argued that, in terms of Section
4 of the Act, in case of failure to invoke Section 16 of the Act,
the respondents cannot raise the defence that was available
and knowingly waived during the proceedings under Section
11 of the Act (supra). It is also contended that the learned

Arb App No. 05/2024 Page 13 of 27

Single Bench has not taken into consideration that an interim
award was passed by the learned arbitrator, which operates as
res-judicata with regard to the timeliness of the claim of
Rs.21,43,536/-. It is further argued that the learned Single
Bench has wrongly applied the judicial precedents to the
present case, as the judicial precedents relied upon by the
learned Single Bench were distinguishable on facts and in law.
29. Per contra, Mr. Chashoo, learned Senior Advocate appearing
for the respondents, has submitted that the appellant in his
statement of claims, nowhere explained or justified delay from
the year 2004 up to the year 2012, despite having issued
various communications from 2000 to 2004, as to what
prevented him from approaching the Court. Rather, the
appellant has taken a lame excuse that, on account of the civil
dispute pending between him and his brother before the Court
of the Additional District Judge, he could not initiate the
proceedings. However, in his petition, the appellant has
specifically mentioned that in the year 2005, he obtained the
status of the case pending before the civil court, wherein he
was informed that there was no injunctive or prohibitory
order. In such circumstances, nothing prevented the appellant
from invoking arbitration and as such, it is evident that the
cause of action accrued to the appellant in the year 2005, but
he remained silent till the year 2013 and thereafter
approached the court after a gap of eight years.

Arb App No. 05/2024 Page 14 of 27

30. He has further submitted that the findings of the learned
arbitrator sought to be relied upon to overcome the issue of

limitation, are vague, perverse and without any legal basis.
31. He further argued that Clause 54 of the Agreement provides
that there should be a reasoned award, whereas the arbitrator
has worked out the quantum without disclosing the basis
thereof or making any reference to the documentary or oral
evidence.
32. He further contended that the learned Arbitrator relied upon
certain final bills and observed that instead of aforesaid
amount only Rs.9,64,225/- , have been paid and, as such,
held the contractor entitled to Rs.25,75,036/-, which is
beyond the record and the material available on the file. The
Arbitrator, in fact, has gone beyond the pleadings.
33. He has further argued that Clause 32 of the Agreement (force
majeure) provides that, if during execution of the work any
force majeure event, such as an earthquake, war, flood, etc.,
takes place, neither of the parties could be fastened with any
liability. However, the learned Arbitrator ignored the said
clause. In fact, the claim for flood damages was not supported

by any clause in the Agreement.
34. He has further argued that the claims on account of security
deposit and earnest money deposit were not tenable, as the
appellant never challenged the termination of the contract by

Arb App No. 05/2024 Page 15 of 27

the respondents as illegal and, rather, filed the petition/claims
only for the alleged work done by him. He has further argued
that because of the inaction and indolence of the appellant,
the Agreement was terminated, due to which the respondent-
Department suffered huge losses and as such the appellant is
not entitled to any amount .
Appreciation :
35. Before addressing the appellant’s contentions, it is appropriate
to note that the appellant is pressing only the claims relating
to flood damages, security deposit, earnest money , and the
final bill , which were set aside by the learned Single Bench.
The claim regarding price escalation has already been
adjudicated under the learned arbitrator's interim award
which has attained finality.
36. The first contention raised by the appellant is that, in terms of
communication dated 12.09.2000 , it was stated that the
payment would not be released until the decision of the civil
litigation pending before the Civil Court. It is urged that in
view thereof, the cause of action stood deferred till 2011, when
the suit was finally dismissed.
37.
It needs to be noted that in the claims filed before the learned
arbitrator, no such communication was appended with the
claims submitted by the appellant. Be that as it may, the
learned Sole Arbitrator has placed considerable reliance upon

Arb App No. 05/2024 Page 16 of 27

this communication to hold that the claim of the appellant was
within the period of limitation.
38. A perusal of the communication dated 12.09.2000 reveals
that it was issued in response to the letter dated 16.06.2000.
In the said communication, it is stated that the termination of
the contract was a direct result of the withdrawal of the power
of attorney executed by the appellant in favour of Mr. D.K.
Chibber, who was looking after the work till the same was
withdrawn by the appellant through telegram dated
10.04.1998 . The reasons for withdrawal were detailed by the
appellant in the communication dated 05.05.1998 regarding

the FIR lodged against D.K. Chibber at Police Station, Kangan.
39. In the said communication, the claims put forth by the
appellant under Part A and B were outrightly rejected, and it
was stated that the claims were nothing but distortion of facts.
It was further stated that the appellant's backing out of the
contract and its consequent termination had rendered the
whole process infructuous and was contrary to the interest of
the Project, and that the Project was not supposed to provide
any relief to a defaulting contractor under the terms of the

Agreement.
40. Regarding flood damages for the years 1995-96 and
construction of diversion bunds, it was stated that the same
had been submitted to the Managing Director, PDC, for accord
of approval. However, it was found that the estimated amount

Arb App No. 05/2024 Page 17 of 27

was repeatedly claimed as dues by the appellant and, as per
the record, the appellant had already been paid in full for the
quantities of work done prior to the floods of 1995. Therefore,
the claims on that account were denied. As per the records,
the flood damages were covered by the “Force Majeure” clause
of the Agreement, which prohibited either of the parties from
claiming damages from the other.
41. Accordingly, the claim of the appellant on the aforesaid
grounds was rejected, and it was stated that the appellant had
been paid Rs.25,82,609/- towards the work of reconstruction
of flood damages, etc., and diversion bund up to 05.05.1998 ,
which payments were accepted by the appellant in terms of
communication dated 16.05.1998 . It was also stated that the
balance unexecuted work covered by these estimates was
completed through a new agency, namely, M/s M & Co.
42. Regarding escalation, it was stated that the net payable
amount and release of earnest money, etc., were subject to the
imposition of the penalty clause of the Agreement by the
competent authority and liquidation of other outstanding dues
against the appellant in the shape of departmental materials,

pending electricity bills, etc.
43. After making these observations, the Executive Engineer
concerned, in the concluding paragraph, observed as under:
“Nothing is withheld in your running account bills
as claimed by you. You know that your erstwhile

Arb App No. 05/2024 Page 18 of 27

attorney holder Sh. D.K.Chibber has filed a suit
against you regarding the contract allotted to you.
The proceedings are underway in the Hon’ble Court
and its decision is awaited. Final bills shall be
entertained thereafter, for further necessary action
by this officer.
Project authorities are ready to discuss all pending
issues in light of agreement only. You can attend
this office for further discussions so that the issues
are made clear to you as per relevant records.”
44. In the said communication, the claims of the appellant under
Parts A and B regarding restoration of flood damages and
construction of diversion bunds were rejected and not
accepted by the respondents at all.
45. Regarding the final bill, the amount is merely Rs. 76,865.
46. The communication dated 12.09.2000 unequivocally
establishes that the claims under Parts C and D regarding
escalation and Parts E and F regarding the net payable
amount on account of final bill, security deposit etc. were only
to be examined.
47. The text of the communication dated 12.09.2000 clearly
restricts the consideration of the appellant’s claim for the final
bill, security deposit and earnest money, etc. So far as the
escalation amounting to Rs.21,43,536/- is concerned, the
same already stands granted to the appellant in terms of the

interim award.

Arb App No. 05/2024 Page 19 of 27

48. Thus, it cannot be said that the concluding paragraph of the
communication dated 12.09.2000 deferred consideration of
the entire claim of the appellant regarding awaiting the
decision of the civil court. The claim regarding the restoration
work and the diversion bunds had already been outrightly
rejected, but still the appellant did not invoke arbitration for
the said claims. Thus, the claims on account of restoration
work and the diversion bunds were time barred.
49. A perusal of the award passed by the learned Arbitrator
reveals that the learned Arbitrator has returned a perverse
finding with regard to the communication dated 12.09.2000 ,
whereby he has observed that, in terms of the said
communication, the respondent-department had declined
payment on account of the pendency of the civil suit and the
claimant was informed to wait till the outcome of the suit
(page 29 of the award). Therefore, the very basis of the learned
Arbitrator’s finding that the claim was within limitation stands
removed.
50. The second contention also stressed by the learned counsel
appearing for the appellant is that dismissal of the suit in the
month of February 2011 provided the cause of action to the
appellant in light of communication dated 12.09.2000.
51. We have already held above that the appellant cannot claim
the benefit of communication dated 12.09.2000 . Moreso, it is
the case of the appellant that though the medium of the

Arb App No. 05/2024 Page 20 of 27

clarification was sought from the Civil Court in the month of
August 2005 yet there was no prohibitory/restraint order
regarding payment of the claims of the appellant and despite
his request, the respondents did not release the amount.

52. Thus, there is an admission on the part of the appellant that
the respondents had wrongly retained the amount due to him
in the year 2005. However, the appellant remained silent,
while submitting his claim, as nothing prevented him from
invoking arbitration for settlement of his claim till the year
2013, within a period of three years from August 2005. Even if
it is assumed, for the sake of arguments, that, in terms of
communication dated 12.09.2000 , the respondents had
deferred consideration of the final bill, security deposit and
earnest money deposit of the appellant till the outcome of the
suit, still the claims of the appellant would be time barred. In
our opinion, the learned Single Bench rightly observed that
12.09.2000 was, at the very least, the date on which the right
to sue accrued to the appellant.
53. The appellant filed the arbitration seeking petition under
Section 11 of the Act in the year 2013, i.e. after a period of
eight years from the submission of the said clarification to the
respondents, and by that time, the claim of the appellant had
already become time-barred.
54. The learned Arbitrator accepted the plea of the appellant that
the cause of action accrued to appellant only in the month of

Arb App No. 05/2024 Page 21 of 27

February 2011, when the suit pending before the Civil Court
was dismissed. The appellant himself informed the
respondents in 2005 of the absence of any civil court restraint
on releasing of the amount. Consequently, this plea cannot
save his claim from the rigors of limitation. Therefore, the
learned arbitrator could not have held that the claim of the
appellant was within the period of limitation.
55. It was also urged that the final bill was prepared 26.02.2011
and, on that account also, a fresh cause of action accrued to

the appellant in the year 2011.
56. This bill, as per the own admission of the appellant, included
claim on account of escalation i.e. Rs. 21,43,536/- and final
bill of Rs. 76,865/- . At the cost of repetition, it is stated the
claim on account of escalation forms part of interim award,
which has attained finality. Learned counsel for the appellant
vehemently argued that in terms of Section 19 of the
Limitation Act, it amounted to an acknowledgment of liability
by the respondents and, as such, a fresh period of limitation
accrued in favour of the appellant. In this context, it would be
appropriate to extract Section 19 of the Limitation Act, which

reads as under:
“ 19. Effect of acknowledgment in writing.—(1)
Where, before the expiration of the prescribed period
for a suit or application in respect of any property or
right, an acknowledgment of liability in respect of
such property or right has been made in writing
signed by the party against whom such property or
right is claimed, or by any person through whom he

Arb App No. 05/2024 Page 22 of 27

derives his title or liability, a fresh period of
limitation shall be computed from the time when the
acknowledgment was so signed.
(2) Where the writing containing the acknowledgment
is undated, oral evidence may be given of the time
when it was signed; but subject to the provisions of
the Evidence Act, (XIII of 1977), oral evidence of its
contents shall not be received.”

57. It is worthwhile to note that mere preparation of a final bill
would not amount to an acknowledgment of liability by the
respondents, more particularly when the same was allegedly
prepared in the month of Feb 2011.
58. The respondents are right in submitting that the preparation
of the final bill, without an approval by the competent
authority, could in no manner be considered as an
acknowledgment of liability so as to furnish any fresh cause of
action to the appellant. As already mentioned above, the
claims of the appellant had already become time barred by
2012, and even if it were to be assumed for the sake of
arguments that preparation of bill would amount to
acknowledgement of liability, the said acknowledgement was
made after the claim had already become time barred, as
such, there is no force in this contention as well, and the same
is rejected .
59. Under Section 34(2)(b)(ii) of the Arbitration and Conciliation
Act, 1997, an arbitral award may be set aside if it conflicts
with the Public Policy of India.

Arb App No. 05/2024 Page 23 of 27

60. Pursuant to Section 43 of the Act, the Limitation Act applies
directly to arbitration proceedings. Consequently, entertaining
a time-barred claim violates statutory mandate, rendering the
resulting award vulnerable to being set aside for violating
Public Policy. In the present case, the learned Arbitrator erred
by entertaining a claim expressly barred by limitation.
61. It was also urged by learned counsel for the appellant that by
participating in the arbitration proceedings and not raising the
plea of limitation during proceedings in application under
section 11 of the Act, the respondents had waived the ground
of limitation in respect of the claims raised by the appellant.
62. The learned Single Bench has observed that the application
filed by the appellant under Section 11 of the Act for
appointment of an arbitrator was barred by limitation, as
patently stale claims were raised. On account of the fact that
the issue of limitation was not raised in relation to the
application filed by the appellant under Section 11 of the Act,
the learned Single Bench found himself handicapped in
examining the same in the proceedings under Section 34 of
the Act. At the same time, the learned Single Bench observed
that the claims adjudicated upon by the learned arbitrator
would be deemed to have been filed in the year 2013, i.e. on
commencement of the arbitral proceedings, but were
nevertheless time-barred.

Arb App No. 05/2024 Page 24 of 27

63. In Bharat Sanchar Nigam Limited and another Vs. Nortel
Networks India Pvt Ltd. (2021)5 SCC 738 it has been
observed by the Hon’ble Apex Court that the question as to
whether the claim is time-barred is otherwise to be decided by

the arbitral Tribunal itself.
64. Accordingly, we are of the considered view that there is no
force in the contention of the appellant that the respondents
had waived their right to object to the claims of the appellant
by participating in the arbitral proceedings and not raising any
objection with regard to the stale claims during the
proceedings under Section 11 of the Act, as such, the same is

rejected.
65. Lastly, it was contended that the respondents ought to have
resorted to section 16 of the Act to challenge the arbitrator’s
jurisdiction on ground of limitation, but the respondents failed
to do so. The relevant paras of the judgment of the Hon’ble
Supreme Court in BSNL’s case, are extracted as under:
“40. The issue of limitation, in essence, goes to the
maintainability or admissibility of the claim, which
is to be decided by the Arbitral Tribunal. For
instance, a challenge that a claim is time-barred, or
prohibited until some precondition is fulfilled, is a
challenge to the admissibility of that claim, and not
a challenge to the jurisdiction of the arbitrator to
decide the claim itself.
Xx xx xx xx
51. The period of limitation for issuing notice of
arbitration would not get extended by mere
exchange of letters , [ v. ,
S.S. Rathore State of M.P.
(1989) 4 SCC 582 : 1990 SCC (L&S) 50; Union of
India v. Har Dayal , (2010) 1 SCC 394; CLP (India) (P)
Ltd. v. Gujarat Urja Vikas Nigam Ltd. , (2020) 5 SCC
185] or mere settlement discussions, where a

Arb App No. 05/2024 Page 25 of 27

final bill is rejected by making deductions or
otherwise. Sections 5 to 20 of the Limitation Act do
not exclude the time taken on account of settlement
discussions. Section 9 of the Limitation Act makes it
clear that: “where once the time has begun to run,
no subsequent disability or inability to institute a
suit or make an application stops it.” -------"

66. The procedural issues, including the claims being time barred,
cannot be confused with jurisdictional issues which only can
be raised by invoking Section 16 of the Act. Thus, it cannot be
said that failure to invoke section 16 of the Act would, by
itself, amount to a waiver of the respondents’ right to raise an
objection to the stale and time barred claims of the appellant.
67. We have examined the judgment passed by the learned Single
Bench, who has relied upon the judgments of the Hon’ble
Supreme Court in M/s B and T AG v. Ministry of Defence ,
(2023) 7 SCR 599, and M/s Arif Azim Co. Ltd. v. M/s Aptech
Ltd. ,2024 INSC 155. We do not find any error in the approach
adopted by the learned Single Bench while setting aside the
award except to the extent of Arbitrator’s fee.
68. In view of the foregoing discussion and the findings recorded
hereinabove, we find no merit in the present appeal. The
learned Single Bench has rightly appreciated the material on
record and has correctly concluded that the claims entertained
and adjudicated upon by the learned Arbitrator were barred by
limitation. The appellant has failed to demonstrate any error of
law or jurisdictional infirmity in the judgment impugned

Arb App No. 05/2024 Page 26 of 27

herein warranting interference by this Court in exercise of its
appellate jurisdiction under Section 37 of the Arbitration and
Conciliation Act, 1997. The appeal is, accordingly, dismissed.
There shall be no order as to costs.
(Rahul Bharti) (Rajnesh Oswal)
Judge Judge
Jammu
06.10.2026
Madan Verma-Secy


Whether order is speaking? Yes.
Whether order is reportable ? Yes.



Arb App No. 05/2024 Page 27 of 27