Ashok Kumar vs Municipal Corporation Of Delhi
- Court
- Delhi High Court
- Case type
- Not found
- Decided on
- 24-02-2026
$
* IN THE HIGH COURT OF DELHI AT NEW DELHI
% Judgment Reserved on : 12.02.2026
Judgment delivered on : 24.02.2026
Judgment uploaded on : As per Digital Signature~
+ W.P.(C) 1737/2026 CM APPL. 8482/2026
JAGTAR SINGH .....Petitioner
versus
MUNICIPAL CORPORATION OF DELHI .....Respondent
+ W.P.(C) 1738/2026 CM APPL. 8484/2026
M/S L J CONTRACTORS PVT LTD .....Petitioner
versus
MUNICIPAL CORPORATION OF DELHI .....Respondent
+ W.P.(C) 1986/2026 CM APPL. 9677/2026
ASHOK KUMAR .....Petitioner
versus
MUNICIPAL CORPORATION OF DELHI .....Respondent
+ W.P.(C) 1959/2026 CM APPL. 9465/2026
JAGDAMBA SINGH .....Petitioner
versus
MUNICIPAL CORPORATION OF DELHI .....Respondent
Advocates who appeared in this case
For the Petitioners : Mr. Sudhir Nandrajog, Senior Adv., Mr.
Arun Batta, Ms. Indra Marla, Advocates.
Mr. Rohan Sharma, Advocate.
Mr Sandeep Bajaj, Mr. Soayib Qureshi, Ms.
Anchal Kushwaha, Mr. Mayank Biyani,
Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:24.02.2026
17:01:01
WP(C) No.1737/2026 and connected matters Page 1 of 22
Advocates.
For the Respondent : Mr. Tushar Sannu, SC, Mr. Priyankar
Tiwary, Ms. Shambhavi Vatsa, Mr. Umesh
Kumar Sisodia, Advocates.
Sh. Niraj Kumar, Assistant Commissioner,
Sh. Rajiv Kumar, ADC, Mr. Shailender,
Admin Officer, Sh. Vinay Kumar, Admin
Officer, Mukesh Kumar, JE and Ankush
Tanwar, JSA
CORAM:
HON'BLE MR. JUSTICE V. KAMESWAR RAO
HON'BLE MS. JUSTICE MANMEET PRITAM SINGH ARORA
JUDGMENT
V. KAMESWAR RAO, J.
1. The petitioners in all four petitions are authorised parking contractors
with the respondent/ Municipal Corporation of Delhi (MCD). The issues that
arise in these petitions are with respect to a Tender dated 15.01.2026 floated
by the respondent MCD bearing No. AC/RPC/MCD/2026/D-1419, whereby
e-bids have been invited for allotment of authorised surface parking sites
under the jurisdiction of MCD on a Monthly License Fee (MLF) basis.
2. It is the case of the petitioners that they have been allotted various
parking sites through earlier Tender dated 27.09.2022 bearing No.
AC/RPC/MCD/D-907, which have now been placed in the new Tender
bearing No. AC/RPC/MCD/2026/D-1419 dated 15.01.2026, despite the fact
that the terms of the earlier Tender are subsisting. They also contend that the
respondent failed to consider the contractual provision for extending the
terms of the earlier tender.
3. Since the captioned petitions agitate the same issue and challenge the
same tender dated 15.01.2026, we shall deal with them together. At the
Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:24.02.2026
17:01:01
WP(C) No.1737/2026 and connected matters Page 2 of 22
outset, we may narrate a brief factual background of the controversy, as seen
from the petitions.
4. The respondent/MCD vide Notice Inviting Tender (NIT) bearing No.
AC/RPC/MCD/D-907 floated a tender for allotment of various authorised
parking sites on MLF basis. In terms thereof, the tenure for which the
parking sites were being offered for allotment was three years, further
extendable for another two years subject to satisfactory performance and as
decided by the Competent Authority, from the date of signing of the
Agreement/handing over the possession of the parking site to the contractor
(whichever was earlier). According to the petitioner, to cut out any
ambiguity in relation to granting extensions, what constituted as satisfactory
performance was also defined in the said NIT by the respondent.
5. The petitioners, relying upon the express representation contained in
the NIT regarding the 3+2 year tenure, submitted their respective bids,
which were accepted by the respondents, and office letters were issued
allotting different parking sites to the petitioners. The details of the
allotment to each of the petitioners are as follows:
S. NO. W.P.(C) No. ALLOTTED PARKING SITES WITH
ALLOTMENT NOS.
1. 1737/2026 Community Centre, Adjoining Road No. 44 –
AC/RPC/MCD/2022/D-1635 dated 02.01.2023.
J Block, Community Centre, Rajouri Garden -
AC/RPC/MCD/2022/D-625 dated 31.12.2022.
Near Delhi Police Apartment, Mayur Vihar
AC/RPC/MCD/2022/D- dated 03.01.2023.
Cluster Inside Ajmal Khan Park, Main Gate and
DB Gupta Road- AC/RPC/MCD/2022/D-1670
Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:24.02.2026
17:01:01
WP(C) No.1737/2026 and connected matters Page 3 of 22
dated 04.01.2023.
Qutub Road, Near Tanga Stand, Sadar Bazar-
AC/RPC/MCD/2022/D-1945 dated 02.02.2023.
Sukha Ped, Mori Gate -
AC/RPC/MCD/2022/D-1941 dated 02.02.2023.
2. 1738/2026
Near Tanga Stand, Seelampur-
AC/RPC/MCD/2022/D-1620 dated 31.12.2022.
Auto Repair Market, B Block, Wazirpur
Industrial Area AC/RPC/MCD/2023/D-1733
dated 12.01.2023.
Main Market, Model Town-II –
AC/RPC/MCD/2023/D-1723 dated 10.01.2023.
Old SP Zonal Building -
AC/RPC/MCD/2022/D-1680 dated 05.01.2023.
3. 1959/2026 Cluster - New Friends Colony.
Cluster - Okhla Station Max House.
4. 1986/2026 Near Batra Hospital (Tughlakabad Institutional
Area) - AC/RPC/MCD/2022/D-1461 dated
15.12.2022.
Dr. Keshav Baliram Hadewar 52 Block, Old
Rajender Nagar – AC/RPC/MCD/2022/D-1462
dated 15.12.2022.
6. The offer letters reiterated that the allotment of the parking sites were
for an initial period of three years, extendable by a further period of two
years subject to satisfactory performance and the decision of the Competent
Authority.
Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:24.02.2026
17:01:01
WP(C) No.1737/2026 and connected matters Page 4 of 22
7. As the initial three year periods neared their completion, the
petitioners submitted requests for extension of further two years, in
accordance with Clauses 8 and 10 of the NIT No. 907 dated 27.09.2022.
Through the requests, they asserted that throughout the tenures, they have
ensured smooth and efficient management of the parking sites, with no dues
pending and all operations conducted strictly in accordance with MCD
guidelines. The petitioners further stated that bidders participate in MCD e-
tenders and plan their investments on the basis of the declared „3+2 years‟
tenure framework, and that as on date there had been no change in the
approved parking areas or parking rates which would warrant deviation from
the said framework.
8. The petitioners, relying upon the express terms of the NIT and the
consistent past practice of MCD in granting extensions on satisfactory
performance, requested grant of the two-year extension in the interest of
operational continuity, fairness and efficient site management. The said
representations were duly received by the respondent, but no decision,
adverse communication or reasoned order has been passed thereon till date.
9. Mr. Sudhir Nandrajog, learned Senior Counsel appearing for the
petitioners stated that the impugned actions of the respondent, who is a State
within the meaning of Article 12 of the Constitution of India, are highly
arbitrary, illegal, perverse and contrary to the principles of natural justice
and fair play.
10. He submitted that the respondent, being a State within the meaning of
Article 12 of the Constitution, is bound to act in a fair, transparent and non-
arbitrary manner even in matters arising out of contracts and tenders. The
tender governing the petitioners‟ allotment expressly contemplated tenure of
Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:24.02.2026
17:01:01
WP(C) No.1737/2026 and connected matters Page 5 of 22
three years extendable by a further two years, subject to satisfactory
performance, thereby creating a structured regime and not a short-term or
ad-hoc arrangement. By proceeding to re-tender the very same sites without
first undertaking any performance assessment or passing reasoned decisions
on extension, the respondent has acted in a manner that defeats its own
declared tender framework. Such conduct squarely attracts the doctrine that
Article 14 “strikes at arbitrariness” in State action, as held in Ramana
Dayaram Shetty v. International Airport Authority of India (1979) 3 SCC
489 .
11. It is his submission that conjoint and purposive reading of Clause 8
and Clause 10 of NIT No. 907 establishes that the extension of the contract
for a further period of two years is a contractual right accruing to the
successful bidder upon satisfaction of the stipulated condition of
„satisfactory performance‟, and not a matter of unfettered or unguided
discretion. Clause 8 stipulates that the contract shall be for three years and
may be further extended for two years on satisfactory performance, while
Clause 10 reinforces this structure by providing that the parking sites shall
be allotted for a period of three years, further extendable to another period of
two years subject to satisfactory performance and decision of the Competent
Authority. Read harmoniously, these clauses create a two stage tenure
architecture, where the second stage of two years is contractually embedded
and is triggered upon fulfillment of the objective benchmark of satisfactory
performance.
12. He submitted that the role of the Competent Authority under Clause
10 is therefore not to decide extension on whim or policy preference, but
only to ascertain whether the condition precedent for extension stands
Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:24.02.2026
17:01:01
WP(C) No.1737/2026 and connected matters Page 6 of 22
satisfied. The discretion reserved to the Competent Authority under Clause
10 is a limited administrative discretion to verify performance, and not
discretion to deny extension arbitrarily once satisfactory performance is
established. The words “ as decided by the Competent Authority ” cannot be
read in isolation or as conferring absolute discretion divorced from the rest
of the clause. Such discretion is circumscribed by the tender framework
itself and must operate within the boundaries of the condition expressly
stipulated, namely satisfactory performance. Any interpretation that treats
the extension as a matter of pure choice or benevolence would defeat the
express language of “ further extendable to another period of two years ” and
convert a structured contractual promise into an illusory one, which is
impermissible in law.
13. Once satisfactory performance is demonstrated, the discretion of the
Competent Authority stands exhausted, and the extension follows as a
matter of contractual consequence. He stated that it is a settled principle of
contractual and administrative law that where discretion is conditioned upon
fulfillment of objective criteria, the authority‟s discretion is confined to
examining whether such criteria are met. Upon satisfaction thereof, the
authority cannot refuse the consequential benefit without recorded,
demonstrable reasons showing non-fulfillment of the condition. In the
absence of such reasons, refusal or circumvention of extension amounts to
non-exercise of jurisdiction and arbitrary denial of a vested contractual
benefit.
14. He stated that the petitioners have complied with all the Terms and
Conditions of the contract and have duly and regularly paid the MLF to the
respondent. Further Clause 10 (B) of Section II of the Instruction to Bidders
Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:24.02.2026
17:01:01
WP(C) No.1737/2026 and connected matters Page 7 of 22
in the NIT D-907, which refers to the satisfactory performance criteria, have
at all times been complied with by the petitioners.
15. He submitted that there are no change of circumstances in the fresh
tender being floated by the respondent corporation. The area of the parking
sites, site maps and the rates chargeable by the contractors from the
customers remain the same in the old and new tenders and have neither been
revised nor changed. Further, there is no change in any policy with respect
to allotment of the parking sites. As such, there is no requirement of any
fresh tender to be floated by the respondent.
16. Further, the fresh Tender floated by the respondent is again being
tendered for a period of 3+2 years, which makes it clear that the intention of
the respondent is to float tenders for a period of 5 years. In case the intention
of the respondent to limit the Tenders of the parking sites for a period of 3
years then they ought not to have floated the fresh tender for a period of
(3+2) years.
17. It is also stated that the respondent has acted in patent breach of its
public law obligation to exercise jurisdiction vested in it, inasmuch as
despite the petitioners having formally and timely invoked Clause 8 and
Clause 10 of NIT No. 907 by way of detailed representations dated
21.10.2025 and 08.10.2025 addressed to the Commissioner, MCD, seeking
extension of the contracts on the expressly stipulated parameters of
satisfactory performance and absence of dues, the respondent has failed to
take any decision whatsoever on the said requests. Such administrative
silence, in the face of a contractually contemplated and duly invoked
discretionary power, constitutes non-exercise of jurisdiction, which is itself a
recognised ground for judicial review.
Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:24.02.2026
17:01:01
WP(C) No.1737/2026 and connected matters Page 8 of 22
18. He submitted that, proceeding to include the petitioners‟ already
allotted and operational parking sites in a fresh tender without first deciding
the pending extension requests amounts to an impermissible circumvention
of the tender framework, renders the extension mechanism illusory, and
vitiates the impugned action on the ground of procedural unfairness, non-
application of mind and arbitrariness, independently attracting interference
under Article 226 of the Constitution of India.
19. Mr. Nandrajog further submitted that the tender documents
themselves conclusively demonstrate that the financial and compliance
architecture of the contract was designed on the footing of full five-year
tenures and not truncated three-year engagements. The petitioners were
required, at the threshold, to deposit substantial amounts towards Earnest
Money Deposit, Security Deposit/Performance Guarantee, and advance
MLF, all of which were calculated with reference to the license fee structure
governing the entire contractual tenure. The Security Deposits/Performance
Guarantees were mandated to be furnished with long-term validity, and
advance MLF were required to be deposited upfront and adjusted over the
contractual period, reflecting a front-loaded financial commitment tied to
continuity of the contracts.
20. He submitted that there were mandatory continuous and recurring
compliance obligations, such as quarterly self-declarations, CCTV
maintenance, staff verification, uniform compliance, display of information
boards, and proof of regular MLF payments, throughout the subsistence of
the contracts. These obligations are not episodic or short-term in nature but
are intended to operate seamlessly over the entire tenure, including the
extension period, reinforcing that the contractual framework contemplates a
Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:24.02.2026
17:01:01
WP(C) No.1737/2026 and connected matters Page 9 of 22
single, integrated five-year operational cycle rather than a hard stop at three
years. When the tender conditions relating to security deposits, advance
MLF, performance guarantees, and recurring compliance documentation are
read conjointly, it becomes clear that the contracts are economically and
administratively structured on the assumption of 5-year tenure, with the
extension forming an integral and inseparable part of the contractual design.
Any interpretation that treats the extension as a discretionary afterthought,
rather than as a continuation of the same contractual regime upon
satisfactory performance, would render the deposit, security, and compliance
framework commercially irrational and legally unsustainable.
21. He stated that the inclusion of the petitioners‟ allotted sites in a fresh
tender, while leaving the extension requests undecided, exposes the
petitioners to fait accomplis , renders the contractual extension clause
nugatory, and defeats the principle that State instrumentalities must act
transparently, predictably and fairly in matters involving public contracts.
22. The respondent has taken a pre-emptive and colourable step which
effectively nullifies the petitioners‟ subsisting contractual position without
due process. By including the petitioners‟ sites in a fresh tender, the
respondent has practically foreclosed the possibility of extension even
before deciding on the pending requests. This amounts to doing indirectly
what cannot be done directly. A reference is made to the judgment of the
Supreme Court in Union of India v. Dinesh Engineering Corporation
(2001) 8 SCC 491 wherein it was categorically held that even where
contractual clauses confer discretion, such discretion cannot be exercised
arbitrarily or for collateral purposes. The impugned action demonstrates a
non-application of mind and constitutes an abuse of administrative
Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:24.02.2026
17:01:01
WP(C) No.1737/2026 and connected matters Page 10 of 22
discretion.
23. He has also contended that extension applications were submitted by
the petitioners strictly in accordance with Clause 8 and Clause 10 of NIT
No. 907 and they still remain undecided, rendering the impugned tender
procedurally premature and legally unsustainable. The petitioners, well
before the expiry of the initial three-year terms, formally sought extension
for the additional two-year periods, expressly asserting satisfactory
performance, absence of dues, and reliance on the 3+2 tenure while
investing in the sites. The respondent has neither accepted nor rejected this
request; no speaking order exists. Issuance of a fresh tender during the
pendency of a statutorily and contractually contemplated extension process
amounts to bypassing the procedure laid down by the respondent itself,
vitiating the impugned action on grounds of procedural impropriety alone.
24. It is further stated that the complete absence of any show-cause
notices, adverse inspection reports or performance-related communications
conclusively establishes that the petitioners satisfied the only contractual
condition for extension, namely, satisfactory performance. The extension
clause under NIT No. 907 is performance-linked. Throughout the entire
tenure, no show-cause notice was issued, no default was alleged, no penalty
was imposed, and no dissatisfaction was recorded. On the contrary, MCD
continued to regulate, revise and permit the petitioners‟ operations. In law,
where an authority makes performance the sole criterion, silence coupled
with continued acceptance of performance operates as tacit affirmation.
According to Mr. Nandrajog, re-tendering in the face of such silence is
arbitrary and violates basic principles of administrative fairness.
25. That apart, he submitted that the impugned re-tendering amounts to a
Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:24.02.2026
17:01:01
WP(C) No.1737/2026 and connected matters Page 11 of 22
constructive termination of the subsisting contractual rights of the petitioners
without notice, hearing or reasons. Though no order of termination has been
passed, the practical effect of re-tendering the same sites is identical to
termination. The law does not permit the State to do indirectly what it
cannot do directly. Constructive terminations without due process violate
Article 14 of the Constitution and the principles of natural justice,
particularly when the contract itself contemplates continuation subject to
performance.
26. Mr. Nandrajog stated that permitting such re-tendering will set a
dangerous precedent whereby municipal authorities can defeat extension
clauses by administrative inaction followed by fresh tenders. If the
respondent‟s conduct is upheld, any public authority could simply avoid
deciding an extension request and issue a fresh tender, thereby nullifying
extension clauses across municipal contracts. This would erode bidder
confidence, distort tender pricing, and undermine the integrity of public
procurement. Judicial intervention is therefore necessary not only to protect
the petitioners, but to preserve systemic fairness in municipal contracting.
The action of the respondent undermines certainty, predictability and
credibility in public tendering, which is contrary to public interest. Public
tenders function on trust that the terms published by the authority will be
honoured in substance and not merely in form. If municipal bodies are
permitted to disregard extension frameworks without reason, bidders will
either refrain from participation or inflate bids to hedge against
governmental unpredictability. He has drawn our attention to the judgment
of the Supreme Court in Noble Resources Ltd. v. State of Orissa (2006) 10
SCC 236 wherein it was observed that arbitrary cancellation or re-tendering
Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:24.02.2026
17:01:01
WP(C) No.1737/2026 and connected matters Page 12 of 22
of contracts invites judicial review because it undermines public interest and
fair competition.
27. Mr. S. Bajaj, learned counsel would make similar submissions as has
been made by Mr. Nandrajog. Apart from this, he submitted that the
petitioners having applied for extension of contract for a further period of
two years and since they continue to execute the contract even after expiry
of initial three years, it must be deemed that the contract has been extended
by the respondents for a further period of two years. He also stated that the
petitioners have made a request for extension of further two years by
specifically relying upon Clause 8 & 10 of the NIT, which provides that the
contract period is three years and can be further extended by two years. His
endeavour has been to submit that the petitioners have managed the
operations smoothly and no dues are pending on the expiry of three years of
contract.
28. He stated that on the conjoint reading of Clauses 8 and 10 of the NIT
No.907, the extension of the contract for a further period of two years is a
not a matter of benevolence or unfettered discretion but a contractual
consequence that ensues once the benchmark of satisfactory performance is
made. In the present case, the petitioners‟ performance has not been merely
satisfactory but demonstrably beyond satisfactory.
29. That apart, his plea is also that the denial of extension violates the
petitioners‟ legitimate expectation. The governing tender and offer
framework expressly stipulates a tenure of three years extendable by a
further period of two years on satisfactory performance and it was on the
faith of such structured tenure that the petitioners have substantially altered
the position by utilising manpower, withdrawing capital, establishing
Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:24.02.2026
17:01:01
WP(C) No.1737/2026 and connected matters Page 13 of 22
systems and investing in operational infrastructure in public parking
contracts; equipment of investment is necessarily calibrated over the full 3 +
2 horizon and premature or disruptive retendering destroys this commercial
premise and renders the explanation clause nugatory. In support of this
submission, reliance has been placed on Union of India v. Hindustan
Development Corporation, 1993 (3) SCC 499 . In substance, it is his plea
that the action of the respondents is in violation of Article 14 of the
Constitution of India.
30. They have sought the prayers as made in the petitions.
31. Per contra , Mr. Tushar Sannu, learned counsel for the respondent-
MCD would contest the submissions made on behalf of the petitioners, by
stating that invoking the extension of the contracts is solely at the discretion
of the MCD. The original contract period was set for three years and post
completion, it is the prerogative of the MCD to decide whether or not to
grant an extension of additional two years. Such discretion is apparent from
the terms of the contract itself. The grant of extension is not mandatory for
the MCD, which has to exercise financial prudence in deciding whether or
not to extend the contract. The extension should also be financially
beneficial to the MCD, who is duty bound to maximise its revenue. As a
public statutory local body, MCD has a fiduciary responsibility to maximise
the value derived from public resources.
32. He submitted that the re-tendering was decided considering the
market alignment. He also submitted that the parking spaces are becoming
more in demand and the market has responded very well to the recent tender
floated by the MCD. As such, price discovery was to be done to maximise
the revenue of the MCD, which is reeling under financial stress. Hence,
Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:24.02.2026
17:01:01
WP(C) No.1737/2026 and connected matters Page 14 of 22
protecting and augmenting the revenue is critical to MCD, which has a
responsibility to receive optimal value for public resources and prevent the
undervaluation of parking spaces.
33. Mr. Sannu stated that the extension of the contract based on under
valuation of valuable public resources may result in significant revenue
losses to the MCD, which is why the decision was taken by the competent
authority not to extend the contract. He has also stated that the decision and
the reasons for the non extension was communicated to the petitioners vide
order dated 11.02.2026, which has been placed on record during the course
of hearing.
34. He would also refer to Section 200 of the Delhi Municipal
Corporation Act, 1957 to contend that the said provision contemplates that
all contracts to be executed have to be in a fair manner and the endeavour
should be to use the resources of the MCD to ensure maximum profitability.
He has relied upon the following judgments in support of his submissions:-
i. Provash Chandra Dalui v. Biswanath Banerjee, 1989 Supp (1)
SCC 487.
ii. Sevoke Properties Ltd. v. W.B. State Electricity Distribution
Co. Ltd., (2020) 11 SCC 782.
iii. BSNL v. Plintron India (O) Ltd., 2024 SCC OnLine Del 6245.
iv. Secretary to Govt. of Karnataka v. V. Harishbabu, (1996) 5
SCC 400.
v. Nilkantha Sidramappa Ningashetti v. Kashinath Somanna
Ningashetti, 1961 SCC OnLine SC 75.
vi. M/s Milestone Security and Placement Services Regd Thr its
Proprietor v. MCD, O.M.P.(I) (Comm.) 14/2025.
Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:24.02.2026
17:01:01
WP(C) No.1737/2026 and connected matters Page 15 of 22
vii. Himalayan Flora and Aromas Pvt. Ltd. v. MCD, W.P.(C)
5350/2025.
viii. Himalayan Flora and Aromas Pvt. Ltd. v. MCD, LPA
351/2025 .
A NALYSIS AND CONCLUSION
35. Having heard the learned counsel for the parties and perused the
record, the short issue which arises for consideration is whether the
petitioners are entitled to extension of contract for a further period of two
years. The submission of Mr. Nandrajog are primarily the following:-
i. The NIT stipulates the initial period as three years, extendable
to two years;
ii. If the performance of the party is satisfactory then the contract
necessarily to be extended by further period of two years;
iii. As the performance of the petitioners has been satisfactory as
conceded by Mr. Sannu, the contract need to be extended by a
further period of five years.
iv. Even otherwise the petitioners have deposited post dated
cheques as bank guarantee/license fee/security deposit for 63
months, which means that the petitioners have a right to have
the contract extended for a further period of two years.
36. The submission of Mr. Bajaj is that the petitioners having sought the
extension of the contracts beyond the permissible period of three years and
having continued to work beyond the period of three years, the contracts are
deemed to have been extended.
37. We are unable to agree with the submissions made by Mr. Nandrajog
Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:24.02.2026
17:01:01
WP(C) No.1737/2026 and connected matters Page 16 of 22
and Mr. Bajaj. Clause 10 on which much reliance has been placed by Mr.
Nandrajog and Mr. Bajaj reads as under:-
“10. Term of the contract:
The parking site/sites shall be allotted for a period of
three years and further extendable to another period of
two years subject to satisfactory performance of the
firm and as decided by the Competent Authority, from
the date of signing of agreement/handing over of
possession of the parking site to the contractor
(whichever is earlier)…”
38. The above stipulates that the parking sites shall be allotted for a
period of three years and further extendable for another period of two years,
subject to satisfactory performance of the firm and as decided by the
Competent Authority.
39. An identical stipulation came up for interpretation before a co-
ordinate bench of this Court in Himalayan Flora and Aromas Pvt. Ltd v.
MCD, LPA No. 351/2025 . Clause 7 therein, is similar to Clause 10 in the
present matter, and is reproduced as under:
“The contract period shall be for a period of 03 years
and further extendable for another 02 years subject to
satisfactory performance of the firm and as decided by
the Commissioner, EDMC and 10% enhancement in
awarded MLF from 4th year and also 10% increase on
awarded MLF every year during the extended period, if
extended by the Commissioner EDMC.”
40. The Court, in paragraphs 24 and 25 of the judgment interpreted the
clause in the following manner:
“24.…whereas in Clause 7 of the contract in the
present case provides that after completion of initial
period of three years, the contract is extendable subject
not only to satisfactory performance of the firm but
Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:24.02.2026
17:01:01
WP(C) No.1737/2026 and connected matters Page 17 of 22
also “as decided by the Commissioner, EDMC”.
25. Thus, in our opinion, Clause 7, as noticed above,
gives a larger discretion to the Commissioner of the
MCD in the present case and, therefore, apart from
satisfactory performance of the firm other relevant
aspects could also have been taken into account by the
Commissioner while taking a decision on the prayer
made by the appellant seeking extension in the term of
the contract. The judgment in SK Associates (supra) is
thus clearly distinguishable.”
41. As seen from the above, the Court held that the large discretion
granted to the Commissioner of the MCD means that apart from satisfactory
performance of the firm, other relevant aspects could also be considered by
the Commissioner while taking a decision on extension of the contract. The
clause therein and the one in the matter at hand being the same, the said
conclusion would be squarely applicable to the facts of this case.
42. Further, we have also considered Clause 10 independently and find
that the word „and ‟ used between the words „ satisfactory performance of the
firm ‟ and „ as decided by the Competent Authority ‟ makes it clear that the
two conditions are independent of each other and have to be read
disjunctively. What is being contemplated is a twin condition- satisfactory
performance of the firm during the said tenure, and also the satisfaction of
the Competent Authority. Even if the performance of the firm is satisfactory,
that itself cannot be considered to be the sole factor for the respondents to
automatically extend the contract of the petitioners. The construction of the
clause has to be interpreted to mean that the Competent Authority is vested
with the discretion to take a decision on the extension. If that be so, the
petitioners cannot claim extension of the contract solely on the basis that
their performance has been satisfactory.
Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:24.02.2026
17:01:01
WP(C) No.1737/2026 and connected matters Page 18 of 22
43. The reason given by the respondents for not granting the extensions
for two years can be seen from the communication dated 11.02.2026 issued
to the petitioners, which we reproduce as under:-
“1. Contractual Stipulations:-
As per the terms of the original contract, the contract
period was set for three years, with the possibility of
extension solely at the discretion of the MCD. After the
completion of the three-year term, it was within the
MCD's prerogative to decide whether or not to grant
an extension for an additional two years. Extension of
contract is not mandatory for MCD. MCD has to
exercise financial prudence in taking decision on
whether or not to extend the contract. The extension
should also be financially beneficial to MCD. MCD is
not legal bound to extend the contract, it is duty bound
to maximize its revenue. As a public statutory local
body, the MCD has a fiduciary responsibility to
maximize the value derived from public resources.
2. Re-Tendering for Market Alignment
The market improving situation for parking space is in
more demand and market has respond very well to the
recent tenders floated by the department. As such price
discovery should be done to maximize the revenue of
MCD. MCD is reeling under financial stress. Hence,
protecting and augmenting the revenue of MCD is very
critical and no efforts should be spared to maximize
the revenue of MCD. In light this approach will ensure
that MCD receives optimal value for public resources
and prevents the undervaluation of parking space
Conclusion
Extension of contract based on the undervaluation of
valuable public resource may result in significant
revenue losses to the Municipal Corporation of Delhi
(MCD).
Furthermore, the terms of the contracts stipulate that
extensions are at the discretion of MCD and do not
mandate automatic renewal. The justifications and
Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:24.02.2026
17:01:01
WP(C) No.1737/2026 and connected matters Page 19 of 22
conditions as outlined above necessitate a thorough
reconsideration of the management of public
resources. The current stand of MCD aligns with
prevailing market trends and ensures the optimization
and augmentation of revenue. As the custodian of
public resources, MCD has a responsibility to
prioritize actions that maximize public benefit. The
same has been demonstrated effectively through recent
tenders. Accordingly, it has been decided that the
extension of contract beyond three-year term, has not
been granted.”
44. In view of the above, we find that the decision of the respondent to
not extend the contract and to issue the fresh NIT for the parking sites
cannot be said to be arbitrary or unreasonable so as to warrant intervention
by this Court.
45. The plea of Mr. Nandrajog and Mr. Bajaj that the petitioners have
deposited bank guarantees for 63 months and as such there is a legitimate
expectation that the contract shall be extended for a further period of two
years is unmerited, for the simple reason that there is an understanding
between the parties that the initial contract is for three years, which is
extendable for an additional two years, subject to the decision of the
respondent/Competent Authority. It is on the basis of such an understanding
that the petitioners submitted their representations seeking extension of the
contract, which has been rejected by the respondent. This would mean that
the petitioners were well aware that the extension of the contract for two
extra years is conditional, and not automatic. As such, the petitioners cannot
claim any legitimate expectation to have their contracts extended beyond the
initial period of three years.
46. Another plea of Mr. Nandrajog and Mr. Bajaj is that there is a deemed
Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:24.02.2026
17:01:01
WP(C) No.1737/2026 and connected matters Page 20 of 22
extension of the contract as they have continued working even after applying
for the extension. This cannot be accepted, for the reason already explained
above, that when a request for extension is made, the Competent Authority
in view of Clause 10, has the discretion to decide whether to extend the
contract or not. In the present case, the Competent Authority has decided not
to extend the contracts, which we have already held to be justified.
47. An issue has been raised that the re-tendering practically amounts to
constructive termination of the earlier tender, without issuing any notice or
providing an opportunity of hearing to the petitioners. We are not in
agreement with the submission of the learned counsel for the petitioners, for
the reason that when the tender dated 15.01.2026 was floated, the three year
period from the date of handing over possession of the parking sites
contemplated by the earlier tender dated 27.09.2022 had already expired. In
that sense, the initial contract had already expired by the efflux of time.
Hence, there is no question of constructive termination as sought to be
canvassed.
48. Insofar as the judgment relied upon by Mr. Nandrajog in the case of
S. K. Associates v. MCD, W.P.(C) 3160/2024 is concerned, the said
judgment (which was co-authored by one of us- Manmeet Pritam Singh
Arora, J.) has no applicability in the facts of this case as the Court therein
was concerned with Clause 4 of the NIT therein, which is reproduced as
under:-
“4. Duration of Contract:
The duration of the contract/license will be for the
duration of three years with effect from the date of
handing over the site to the licensee. After the expiry of
two years, the monthly license fee will be enhanced by
05% (five percent for the next year, subject to the
Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:24.02.2026
17:01:01
WP(C) No.1737/2026 and connected matters Page 21 of 22
satisfactory completion of period of first two years of
contract. The parking site allowed operating beyond
three years period (in any circumstances) then the
contractor has to pay monthly license fee by enhancing
05% of last/ current MLF. ”
49. As can be seen from the above, in that case, there was a stipulation
that after the expiry of two years, the MLF shall be enhanced by 5% for the
next year, subject to the satisfactory completion of two years of contract. It
is in that factual situation that this Court interpreted the same to mean that
when the licensee successfully completes the first two years of the license,
without there being any discretion vested with the Competent Authority, if
there is a satisfactory performance of the contract in the first two years then
the contract necessarily has to be extended.
50. Insofar as the reliance placed by Mr. Nandrajog on paragraphs 9 to 19
of the judgment in the case of Godra Electricity, (1975) 1 SCC 199 is
concerned, we are of the view that the said judgment also has no
applicability in the facts of this case.
51. In view our conclusion drawn above, and as we have held that the
issue is covered by the judgment of this Court in the case of Himalayan
Flora and Aromas Pvt. Ltd (supra), we are of the view that these petitions
lack merit and are liable to be dismissed. We order accordingly.
52. Pending applications are dismissed. No costs.
V. KAMESWAR RAO, J
MANMEET PRITAM SINGH ARORA, J
FEBRUARY 24, 2026 /sr