ABDUL ALIM vs ASRAFUL HOQUE AND ORS

Court
Calcutta High Court

Form No. J(2)


In the High Court at Calcutta
Civil Appellate Jurisdiction
Appellate Side

Present: The Hon’be Justice Sabyasachi Bhattacharyya
And
The Hon’ble Justice Biswaroop Chowdhury


F.M.A. 1464 of 2025
IA No: CAN 1 of 2025

Abdul Alim
Vs.
Asraful Hoque and others



For the appellants : Mr. Partha Pratim Roy
Mr. Sarbananda Sanyal
Mr. Samrat Chakraborty

For the respondent no.3 : Mr. Kingsuk Mondal
Mr. Tapodip Gupta
Mr. Suman Das

Heard on : 07.05.2026

Judgment on : 07.05.2026


Sabyasachi Bhattacharyya, J.:-



1. Affidavit-of-service filed in court today be kept on record.
2. Although service has not been effectively completed in respect of
all the plaintiffs/respondents, that is, plaintiffs/respondent nos.
1 to 3, respondent no.3 is represented today through counsel.

2

3. However, since the suit from which the present appeal arises
has been filed by respondent nos.1 to 3 jointly as plaintiffs, we
deem the appearance of one of them to be effective
representation for all.
4. Accordingly, the application is taken up for hearing.

5. The present challenge has been preferred against an order
whereby temporary injunction has been granted by the learned
Trial Judge directing both parties to maintain status quo
regarding nature and character of the suit property till disposal
of the suit.
6. Learned counsel for the appellant submits that from the
Commissioner’s report, which was a part of the trial court
records, it would be evident that the defendant/appellant is
constructing in his demarcated portion of the suit property,
which is separated from the other portion of the property,
occupied by the plaintiffs/respondents, by a boundary wall.
7. Learned counsel further submits that from the title deeds
produced in the trial court, it would also be evident that the
original owners of the property sold demarcated portions of the
same by separate deeds in favour of the plaintiffs/respondent
nos.1 to 3 and the defendant/appellant respectively.

3

8. Thus, it is argued that as the appellant has already completed
construction of the ground floor of the building up to the roof
level, the injunction at this stage would violate the test of
balance of convenience and inconvenience.
9. Learned counsel for the plaintiffs/respondent no. 3 controverts
such contentions.
10. However, from the Commissioner’s report, we find substance in
the contention of the appellant that the appellant has already
completed construction up to the roof level of the new building,
that too, in a demarcated portion separated by boundary wall
from the portion of the suit property where the plaintiffs are
residing.
11. As such, we do not find that any irreparable injury could be
caused to the plaintiffs/respondent nos.1 to 3 if such
construction is permitted to be completed.
12. That apart, the balance of convenience and inconvenience, in the
peculiar facts and circumstances of the case, is in favour of
refusal of injunction rather than granting the same.
13. In any event, even if the defendant/appellant is permitted to
make the construction, the appellant shall comply with the
riders which we intend to stipulate.

4

14. Accordingly, FMA 1464 of 2025 is allowed, thereby setting aside
the impugned order, bearing Order No.9 dated June 21, 2025
passed by the learned Civil Judge, Senior Division at Kandi,
District- Murshidabad in Partition Suit No.273 of 2024, and
quashing the status quo/injunction granted thereby.

15. However, the above order shall be subject to the condition that
the appellant shall make construction, if any, only on his
demarcated portion of the suit property, and the same shall be
strictly in accordance with the Building Rules and Regulations
governing such constructions in the area where the suit property
is located.
16. Moreover, the defendant/appellant shall not claim any special
equity or rights merely by virtue of such construction and such
construction shall be without prejudice to the rights and
contentions of the parties at all stages of the suit.
17. Also, such construction shall be made entirely at the cost of the
appellant.

18. Furthermore, in the event the suit is decreed against the
appellant and/or the portion where the construction is being
made is allocated at the final hearing of the partition suit to
other parties than the appellant, the appellant shall demolish

5

the construction made by him on the said portion at his own
cost.
19. CAN 1 of 2025 is disposed of in the light of the above
observations.
20. There will be no order as to costs.

21. Urgent photostat copies of this order, if applied for, be given to
the parties upon compliance of all requisite formalities.






(Sabyasachi Bhattacharyya, J.)
I agree.


(Biswaroop Chowdhury, J.)
AD-51