Amit Kumar vs The State of Bihar
- Court
- Patna High Court
IN THE HIGH COURT OF JUDICATURE AT PATNA
Civil Writ Jurisdiction Case No.17356 of 2026
CNR No. BRHC011205852026
======================================================
Amit Kumar, Son of Late Ravi Ranjan Kumar, Resident of Village- Aranda,
P.S.- Obra, District Aurangabad.
... ... Petitioner/s
Versus
1. The State of Bihar through its Principal Secretary, Energy Department, 1st
Floor, Vidyut Bhawan- II, Bailey Road, Patna.
2. South Bihar Power Distribution Company Limited (SBPDCL), through its
Chairman -cum- Managing Director, Vidyut Bhawan, Bailey Road, Patna-
800021.
3. The Chairman -cum- Managing Director, South Bihar Power Distribution
Company Limited, Vidyut Bhawan, Bailey Road, Patna- 800021.
4. The General Manager (Revenue), South Bihar Power Distribution Company
Limited, Vidyut Bhawan, Bailey Road, Patna- 800021 (Shri Arvind Kumar).
5. The Electrical Executive Engineer, HT Cell, South Bihar Power Distribution
Company Limited, Patna.
6. The Executive Engineer, Electricity Supply Division, Daudnagar, District
Aurangabad, Bihar.
... ... Respondent/s
======================================================
Appearance :
For the Petitioner/s : Mr. Madhav Raj, Advocate
For the Respondent/s : Mr. Abhinav Mishra, GA- 6
Mr. Vaibhava Veer Shanker, AC to GA- 6
Mr. Vatsal Vishal, Advocate
Mr. Priyanshu Singh, Advocate
Ms. Simran Kumari, Advocate
For Resp. Nos. 2 to 6 : Mr. Kunal Tiwary, Advocate
======================================================
CORAM: HONOURABLE MR. JUSTICE HARISH KUMAR
ORAL JUDGMENT
Date : 19-11-2026
Heard Mr. Madhav Raj, learned Advocate for the
petitioner and Mr. Kunal Tiwary, learned Advocate for
respondent nos. 2 to 6. The State is represented through Mr.
Abhinav Mishra, learned Advocate.
Patna High Court CWJC No.17356 of 2026 dt.19-11-2026
2/6
2. The petitioner, working as Director of M/s
Narayani Agro Product, has approached this Court assailing a
notice/order dated 02.11.2026, issued under Section 56 of the
Electricity Act, 2003, by the Electrical Executive Engineer, HT
Cell, SBPDCL, Patna, asking the petitioner to pay a sum of Rs.
3,44,54,179/- within a period of 15 days, failing which
electricity supply of the premises will be disconnected without
prejudice to its right to recover such charges or other sum by
suit. Challenge has also been made to Letter No. 3708 dated
01.09.2026 issued by the General Manager (Revenue),
SBPDCL, asking the petitioner to deposit a sum of Rs.
3,41,86,053/- for the period 10.09.2020 to 28.07.2026. The sole
justification in the bill is the remark: “Actual M.F. was 05(five)
but billing was done in M.F. 01 (one). Hence, supplementary
Bill is also served and in case of failure to pay, the same would
be added as DPS in the electricity Bills”.
3. While assailing the impugned notice/order,
learned Advocate for the petitioner made manifold submissions,
inter alia , that at the time of inspection, the petitioner was
neither allowed to remain present nor any notice or the
inspection report has been served upon him.
4. Referring to the impugned notice, it is also
Patna High Court CWJC No.17356 of 2026 dt.19-11-2026
3/6
argued that from a bare perusal thereof, it is evident that on
account of defect in the meter, it could not make the right
assessment of the bills, due to which the petitioner cannot be
faulted. All the more, the bill raised by the South Bihar Power
Distribution Company Limited is barred under Section 56(2) of
the Electricity Act, 2003 (hereinafter referred to as ‘the Act,
2003’).
5. To support the aforesaid contention, reliance has
been placed on a decision of the Hon’ble Supreme Court in the
case of Assistant Engineer (D1) Ajmer Vidyut Vitran Nigam
Ltd. Vs. Rahamatullah Khan @ Rahmajulla : (2020) 4 SCC
650 .
6. Dispelling the aforesaid contention, Mr. Tiwary,
learned advocate for the SBPDCL, primarily submitted that the
petitioner has efficacious alternative remedy for raising his
grievance before the Consumer Grievance Redressal Forum
duly constituted under Section 42(5) of the Act, 2003. To fortify
the aforesaid contention, he has also placed reliance upon a
decision passed in Assistant Collector of Central Excise,
Chandan Nagar, West Bengal Vs. Dunlop India Limited &
Ors. : (1985) 1 SCC 260 where the Hon’ble Supreme Court
categorically ruled that Article 226 is not meant to short-circuit
Patna High Court CWJC No.17356 of 2026 dt.19-11-2026
4/6
or circumvent statutory procedures. It is only where statutory
remedies are entirely ill-suited to meet the demands of
extraordinary situations, as for instance where the very vires of
the statute is in question or where private or public wrongs are
so inextricably mixed up and the prevention of public injury and
the vindication of public justice require it, that recourse may be
had to Article 226 of the Constitution.
7. Further reliance has been placed on a decision in
the case of Jaipur Vidyut Vitran Nigam Limited & Ors. Vs.
MB Power (Madhya Pradesh) Limited & Ors. : (2024) 8 SCC
513 , especially paragraph 128 thereof, which reads as follows:
“128. We find that the High Court
was not justified in entertaining the petition. The
Constitution Bench of this Court in PTC [PTC
India Ltd. v. CERC, (2010) 4 SCC 603 : 2010
INSC 146] has held that the Electricity Act is an
exhaustive code on all matters concerning
electricity. Under the Electricity Act, all issues
dealing with electricity have to be considered by
the authorities constituted under the said Act. As
held by the Constitution Bench of this Court, the
State Electricity Commission and the learned
A PTEL have ample powers to adjudicate in the
matters with regard to electricity. Not only that,
these Tribunals are tribunals consisting of experts
having vast experience in the field of electricity.
Patna High Court CWJC No.17356 of 2026 dt.19-11-2026
5/6
As such, we find that the High Court erred in
directly entertaining the writ petition when
Respondent 1 i.e. the writ petitioner before the
High Court had an adequate alternate remedy of
approaching the State Electricity Commission.”
8. Besides the preliminary objection with regard to
the maintainability of the writ petition, he further drew the
attention of this Court to a decision rendered by the Hon’ble
Supreme Court in the case of Prem Cortex Vs. Uttar Haryana
Bijli Vitran Nigam Limited & Ors. : (2021) 20 SCC 200 to
dispel the submission of the petitioner on the point of the bill
raised by the Corporation is barred by limitation.
9. Considering the submissions advanced by the
learned Advocate for the respective parties, without delving into
the merit of the case, this Court, prima facie , is of the
considered opinion that before approaching this Court, the
petitioner has efficacious alternative remedy to approach before
the Consumer Grievance Redressal Forum in order to ventilate
his grievance.
10. In view thereof, this Court deems it fit and
proper to direct the petitioner to file an appropriate application
before the Consumer Grievance Redressal Forum along with all
the necessary documents and the decisions on which he is
Patna High Court CWJC No.17356 of 2026 dt.19-11-2026
6/6
placing reliance, preferably within a period of three weeks from
today.
11. It is expected that the concerned respondent
shall not proceed in the matter in terms of the impugned notice,
till three weeks from today.
12. It is needless to observe that the petitioner shall
also make a prayer for stay of the operation of the impugned
notice in the said petition, which shall also be dealt with by the
Consumer Grievance Redressal Forum on its own merit.
13. The writ petition stands disposed of.
(Harish Kumar, J)
uday/-
AFR/NAFR NAFR
CAV DATE NA
Date of Pronouncement 19.11.2026
Uploading Date 20.11.2026
Transmission Date NA