CITY MALL VIKASH PRIVATE LIMITED AND ANR vs UNION OF INDIA AND ORS.

Court
Calcutta High Court

IN THE HIGH COURT AT CALCUTTA
(Constitutional Writ Jurisdiction)
APPELLATE SIDE

Present:
The Hon’ble Justice Krishna Rao

WPA No. 7776 of 2026

City Mall Vikash Private Limited & Anr.
Versus
The Union of India and Others

Mr. Krishnaraj Thaker, Sr. Adv.
Ms. Reshmi Ghosh
Mr. Rohit Banerjee
Mr. Sayan Sengupta
.....For the petitioners.

Mr. Ajit Kumar Mishra
Mr. Sovan Mukherjee
.....For the U.O.I.

Mr. Barnik Ghosh
.....For the M.S.T.C. Ltd.

Mr. Kishore Dutta, Ld. A.G.
Mr. Snehashis Sen
Mr. Ajit Kumar Mishra
Mr. Abhishek Banerjee

2

Mr. Debdatta Mukhopadhyay
.....For the respondent no. 3.

Mr. Abhrajit Mitra, Sr. Adv.
Mr. Deepan Kumar Sarkar
Mr. Yash Singhi
Mr. Sourav Bhagat
Mr. Jishnujit Roy
Mr. Biswajit Roy
Ms. Deveshi Bose
.....For the respondent no. 4.

Hearing Concluded On : 20.04.2026
Judgment on : 23.04.2026
Krishna Rao, J.:
1. The petitioners have filed the present writ petition praying for a
direction upon the respondents to permit the petitioner No. 1 Company
and other bidders to participate in the tender auction being NIT No.
th
SMP/KDS/LND/131-2025 dated 5 November, 2025 from the stage of
bidding as at 10.40 p.m. The respondent no. 3 has issued the above
th
mentioned tender notice dated 5 November, 2025, inviting bids for
allotment of land inside CME compound at plot No. 130/25(A), situated
at 8, Garden Reach Road, Kolkata, on long term lease of 30 years, on
‘as is where is basis’ , without renewal option, against payment on
annual rent/ upfront basis.

th
2. The petitioners have participated in the said tender on 24 March,
2026, upon evaluation of the techno-commercial bid, the petitioners

3

were declared techno-commercially qualified and was invited to
participate in the forward e-auction stage conducted through the MSTC
e-auction portal. The said auction was scheduled to start at 12.00 noon
th
on 26 March, 2026 and accordingly, the petitioners have logged into
the MSTC e-auction portal on the scheduled date and time and
participated in the live bidding process.


3. Mr. Krishnaraj Thaker, Learned Senior Advocate appearing for the
petitioners, submits that during the bidding process through online
mode suddenly at around 10:40 p.m. after almost 10 hours 40 minutes
of active participation by the petitioners, the computer system of the
petitioners’ suffers a technical glitch. He submits that due to such
sudden disconnection and technical malfunction, the petitioners were
automatically logged out of the MSTC e-auction portal, due to which
the petitioners were unable to participate in the remaining portion of
the bidding process.

4. Mr. Thaker submits that immediately the petitioners attempts to
reconnect the internet and log back to the MSTC e-auction portal in
order to continue participating in the bidding process but due to the
limited time remaining in the auction window and the technical
disruption experienced, the petitioners were unable to successfully re-
enter the live bidding process within the stipulated period of time.

5. Mr. Thaker submits that immediately the petitioners have
communicated through e-mail to the respondents regarding the

4

technical difficulties faced by the petitioners during the live auction and
requested the respondents to verify the system logs available with the
portal or the concerned technical agency conducting the auction in
order to ascertain the occurrence of such technical glitch.

6. Mr. Thaker submits that the petitioners requested the respondent
authorities to consider for rescheduling the auction by extending the
bidding time or otherwise providing an opportunity to the petitioners to
participate further in the bidding process. He submits that the
petitioners have submitted reminder to the respondent authorities on
th
27 March, 2026, explaining in details the circumstances leading to
the disconnection from the MSTC portal and the inability of the
petitioners to continue participation in the auction process despite the
petitioners is having the financial capability to submit higher bids.

7. Mr. Kishore Dutta, Learned Advocate General appearing for the
respondent no. 3 submits that due to technical glitch, the petitioners
were unable to participate in the live e-auction bid after 10:40 P.M. and
if the petitioners are intending to pay the higher bid amount then the
private respondent and the respondent no. 3 will consider the same in
accordance with law.

8. Mr. Barnik Ghosh, Learned Advocate appearing for the M.S.T.C
th
submits that the bidding portal was continued till 22:41:34 on 26
March, 2026 and the added respondent has quoted the bid amount of
Rs. 4,45,10,628/- wherein the petitioners have lastly participated in

5

the live e-auction bid at 22:38:15 and quoted Rs. 4,44,99,626/- and
thereafter the petitioners have not participated in the live e-auction bid.
He submits that there is no technical glitch on the part of the MSTC.
The respondent no. 2 referred paragraphs 9 of the writ petition and
submits that it is the admitted case of the petitioners that at 10:40
p.m., the petitioners’ computer system suffered a technical glitch and
as such the petitioners cannot pray for allowing the petitioners to
participate in the tender process further.

th
9. Mr. Ghosh submits that on 30 March, 2026, reply was sent to the
petitioners clarifying the position that on 22:41:34 hours, the final bid
of the auction was placed. At 22:45 hours, the connection of the
petitioners’ was restored, the bidding window was remain open for over
four minutes i.e. up till 22.49.34 hours but the petitioners have not
placed any bid during the said four minutes when the bidding window
of the petitioners was open. He further submits that on 22:49:34 hours,
the auction was officially closed.


10. Mr. Ghosh submits that though there was a technical glitch in the
system of the petitioners but at 22.45 hours, the connection of the
petitioners was resorted and remaining 4 minutes to participate in the
bid as the window was open till 22:49:34 hours but the petitioners
failed to put the bid amount within the said four minutes. Mr. Ghosh
has relied upon the judgment in the case of Maharashtra Housing
Development Authority vs. Shapoorji Pallonji & Co. Pvt. Ltd. &
Ors. reported in (2018) 3 SCC 13 and submits that in the absence of

6

any technical glitch at the site of the MSTC, the petitioners cannot
claim any benefit for allowing the petitioners to participate in the said
tender any further.

11. Mr. Ghosh has further relied upon the judgment in the case of Jindal
Steel & Power Ltd. & Anr. Vs. Union of India & Ors. reported in
2023 SCC OnLine Del 4401 and submits that the Hon’ble Division
Bench of the Delhi High Court held that there was no glitch on the
portal of the MSTC, on which e-auctions were conducted, it would be
improper to set aside the result of the present e-auction only on the
ground that the petitioner was prepared to give a higher bid. He has
further relied upon the judgment in the case of Deep Blue Xpress Ltd.
vs. Municipal Corporation of Delhi, reported in 2023 SCC OnLine
Del 5493 and submits that if there is no technical glitch on the bidding
portal, no relief can be granted to the petitioner.

12. Mr. Abhrajit Mitra, Learned Senior Advocate, appearing for the private
respondent submits that the petitioners have admitted that there is no
technical glitch on the part of the MSTC. He submits that in Clause 12
of the Techno-Commercial Bid, it is specified that the scheduled closing
time of e-auction shall be automatically extended, in case a techno-
commercially qualified bidder submits a bid within 8 minutes of
scheduled closing time of e-auction. He submits that as per the case of
the petitioners, there was a technical glitch in the computer of the
petitioners at 10.40 p.m. but as per the report submitted by the MSTC,
the bidding window of the petitioners re-opened at 22:45 hours and the

7

petitioners got further 4 minutes to participate in the said tender but
the petitioners fails to place his bids uptil 22:49:34 hours, accordingly,
the bid was closed and now the petitioners cannot claim to allow the
petitioners to participate in the tender process further.

13. Mr. Mitra has relied upon the judgment in the case of Subodh Kumar
Singh Rathour vs. Chief Executive Officer & Ors. reported in 2024
SCC OnLine SC 1682 and submits that cancellation of a contract
deprives a person of his very valuable rights and is a very drastic steps,
often due to significant investments having already been made by the
parties involved during the subsistence of the contract. He submits that
the added respondent has quoted the highest bid amount and also
deposited the bid amounts with the respondents and as such if the bid
proceeding is cancelled the private respondent will suffer irreparable
loss.

14. Mr. Mitra has further relied upon the judgment in the case of Bharat
Earth Movers and Transporters vs. Eastern Coalfields Limited &
Ors. reported in (2017) 1 WBLR (CAL) 22 and submits that tendering
authority is not responsible for system failures in hardware/software
internet connectivity at the end of the bidder.

15. Heard the Learned Counsel for the respective parties, perused the
materials on record. The issues in the present writ petition :
i. Whether even the computer system of the petitioners
suffer technical glitch during e-auction process, the
respondent nos. 2 and 3 shall be responsible for the
same.

8

ii. Whether if the respondent no. 3 has not finalized the
tender of the private respondent, the petitioners can
be given an opportunity to participate in the bid
auction through online from the stage of the bidding
at 10.40 p.m.


16. It is admitted by the petitioners that suddenly around 10.40 P.M. after
almost 10 hours 40 minutes of active participation by the petitioners,
the petitioners’ computer system suffered a technical glitch. Clause 16
of General Information to the bidders provides that neither SMP,
Kolkata nor MSTC shall be responsible for any problem at the bidders’
end like failure of electricity, disruption of internet connection, any
trouble with bidder’s PC etc., which may cause inconvenience or
prevent the bidder from bidding in the e-tender-cum-e-auction.

17. As per the bid history produced by the respondent no. 2, it reveals that
the private respondent has participated in the last bid at 22:41:34 and
put the bid amount of Rs. 44,51,0628/-. The respondent no. 2 also
th
produced the e-mail dated 30 March, 2026 wherein it reveals that at
22:40 hours to 22:45 hours, the petitioners could not participate in the
e-auction process due to computer glitch in the computer of the
petitioners. The private respondent has quoted his final bid amount at
22:41:34 hours. The system of the petitioners restored at 22:45 hours
and the bidding window remain open for about 4 minutes but even
after the restoration of the connection of the petitioners at 22:45 hours,
the petitioners have not placed their bid amount during this four

9

minutes and accordingly at 22:49:34 hours, the respondent no. 2
officially closed the e-bidding process.

18. In the case of Maharashtra Housing Development Authority (supra),
the Hon’ble Supreme Court has held that lack of any timely response of
the first respondent when the system had failed to generate an
acknowledgement of the bid documents in a situation where the first
respondent claims to have press the freeze button, the generation of
acknowledgment in respect of other bidders and in the absence of any
glitch in the technology would strongly indicate that the said bid
submitted by the first respondent was not a valid bid and the directions
issued by the High Court in favour of the first respondent virtually
conferred on the said respondent a second opportunity, which cannot
be countenanced.

19. In the case of Jindal Steel and Power Limited (supra), the Hon’ble
Division Bench of the Delhi High Court held that if there is no glitch on
the portal of MSTC, on which the e-auctions were being conducted it
would be improper to set aside the result of e-auction only on the
ground that the petitioner was not prepared to give a higher bid. In the
case of Deep Blue Xpress Ltd. (supra) , the Division Bench of the Delhi
High Court has relied upon the judgment in the case of Jindal Steel
and Power Limited (supra).

20. This Court finds that it is the admitted case of the petitioners that the
computer system of the petitioners suffered technical glitch at 10.40

10

hours due to which the petitioners could not participate in the further
e-bid process but from the report submitted by the respondent no. 2, it
reveals that at 22:45 hours, the system of the petitioners restored and
the petitioners got the four minutes time to participate in the bid by
putting the bid amount but the petitioners have not utilized the said
four minutes and accordingly, 22:49:34 hours, the respondent no. 2
officially closed the auction. Clause 16 of the tender document also
specified that neither the respondent no. 2 nor the respondent no. 3
shall be responsible for any problem at the bidder’s end like failure of
electricity, disruption of internet connection, any trouble with bidders
PC etc., which may cause inconvenience to prevent the bidders from
bidding in the e-tender of e-auction, thus this Court is of the view that
there is no fault on the part of the respondents, accordingly, the issue
no. 1 is decided against the petitioners.

21. As regard to the issue no. 2, Clause 23 of the tender document provides
that after finalization of the tender through e-tender or e-auction, the
allotment letters will be made to the successful bidders by hard copy,
and successful bidders shall be required to formally accept the terms
and conditions of the allotment of the lease and remit requisite advance
annual rent. The respondents have accepted the bid amount. It is upon
the respondent no. 3 to issue allotment order to the private respondent
or to take any further decision to cancel the tender process if the
authorities found any difficulty to accept the bid amount of the private
respondent. Mere the allotment letter is not issued to the private

11

respondent, will not create any right upon the petitioners to participate
th
in the tender process from the stage at 10.40 p.m. on 26 March, 2026
along with other bidders, which is already closed at 22:49:34 hours.

22. The petitioners have admitted that due to technical glitch in the
computer of the petitioners, the petitioners could not participate in the
e-tender process after 10:40 hours but this Court has already held that
the petitioners failed to utilize the four minutes from 22:45 to 22:49
hours, thus the petitioners cannot claim that if the work order is not
issued, the petitioners can be allowed to further participate in the bid
process from the stage of the bidding at 10:40 p.m.

23. Considering the above, this Court did not find any merit in the present
writ petition. Accordingly, WPA No. 7776 of 2026 is dismissed . No
order as to costs.

Parties shall be entitled to act on the basis of a server copy of the
Judgment placed on the official website of the Court.

Urgent Xerox certified photocopies of this judgment, if applied for,
be given to the parties upon compliance of the requisite formalities.

(Krishna Rao, J.)