National Highways Authority Of India vs Progressive Constructions Limited

Court
Delhi High Court

* IN THE HIGH COURT OF DELHI AT NEW DELHI

% Judgment reserved on : 12.12.2025
Judgment delivered on : 18.06.2026
Judgment uploaded on : As per Digital Signature

+ FAO(OS) (COMM) 206/2023

NATIONAL HIGHWAYS AUTHORITY OF INDIA
..... APPELLANT
versus

PROGRESSIVE CONSTRUCTIONS LIMITED
..... RESPONDENT

Advocates who appeared in this case

For the Appellant : Mr. Ankur Mittal and Mr. Ankur Saboo,
Advocates.

For the Respondent : Mr. C. Mohan Rao, Sr. Advocate with
Mr. Lokesh Kumar Sharma, Advocate

CORAM:
HON'BLE MR. JUSTICE V. KAMESWAR RAO
HON'BLE MR. JUSTICE VINOD KUMAR

JUDGMENT
V. KAMESWAR RAO, J.

1. This appeal has been filed under Section 37(1)(c) of the Arbitration
and Conciliation Act, 1996 (the Act) against the order dated 26.04.2023 in
O.M.P. (COMM) 358/2019 filed under Section 34 read with 16(6) of the Act
whereby a Single Judge of this Court has rejected the appellant’s challenge
to claims Nos.6 and 8 allowed by the Arbitral Tribunal in favour of the


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:18.06.2026
12:35:37
FAO (OS) (COMM) 206/2023 Page 1 of 93

respondent herein. By order dated 03.05.2023, the learned Single Judge has
set aside the impugned award dated 21.02.2019 with regard to claim Nos. 5,
10, 14 and 19.
2. The facts as noted from the appeal are as under:-
a. The appellant herein is the National Highways Authority of
India ( hereinafter referred to as ‘NHAI’ and ‘employer’
interchangeably ), established under the National Highways
Authority of India Act, 1988.
b. The respondent- Progressive Constructions Limited
(hereinafter referred to as ‘contractor’ also) is a company
incorporated under the provisions of the Companies Act, 1956 and
is the contractor under the Contract Agreement dated 08.09.2005.
c. The Government of India, Ministry of Road Transport and
Highways (MoRTH) launched a National Highways Development
Programme, which envisaged the following: i) Four/six laning and
strengthening of existing National Highways connecting four
metropolitan cities of Delhi-Kolkata-Chennai-Mumbai. ii) Four/six
laning and strengthening of existing National Highways network
from north to south and east to west connecting Srinagar to
Kanyakumari and Silchar to Porbandar, respectively.
d. The appellant invited bids for the work of widening and
strengthening of existing National Highways from 2 lane to 4 lane
from KM 30.000 to KM 0.000 of Bijni to West Bengal Border
Section of NH-31 C in Assam on East-West Corridor under Phase-


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:18.06.2026
12:35:37
FAO (OS) (COMM) 206/2023 Page 2 of 93

II Programme of NHDP-Construction Package EWII (AS12).
e. On 11.12.2025, the appellant issued the “Report of Handing
over and taking over of the work site” pursuant to a joint site visit
between the parties whereby the entire 30 KM of project stretch
was handed over to the respondent; however, the contractual
requirement was to handover 10 KM only at the initial stage as
admitted by the respondent. Out of the said land, 6 KM of stretch
from 24 KM to 30 KM required conversion permission from forest
to non-forest which was obtained in the year 2010. On 07.07.2007,
according to the minutes of the meeting between the parties and the
Engineer, the respondent was found guilty of non-performance;
primarily due to absence of adequate and qualified professionals
and lack of machinery to execute the project.
f. On 05.04.2008, various Extensions of Time (EOTs) to
complete the works were sought for different reasons, which were
recommended by the Engineer. A detailed chart attached along with
reflects that in every extension, while recommending EOTs, the
Engineer categorically stated concurrent delay and held that the
respondent is liable for contributing majorly to the delays on
critical path, hence it is not entitled to any prolongation costs. In
May 2010, forest land of 6 KM stretch was handed over. On
30.06.2011, as per the Engineer, work front available was 99.50%.
On 15.11.2010, the respondent stated that the work is halted for the
last 6 months due to heavy rains. In 2012, even after 6 years on the
Project, the respondent did not have the required machinery and


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:18.06.2026
12:35:37
FAO (OS) (COMM) 206/2023 Page 3 of 93

equipment. After 18 months of handing over of the forest land, the
overall progress on the Project was 61%.
g. On 18.01.2014, the Project Director (PD) held that the progress
of work is negligible in last 6 months. Representatives of the
respondent assured that the work will be resumed by January 2014
and the 24 KM stretch would be completed by March 2014.
h. On 05.04.2014 and 15.07.2014, noting the innumerable defaults
in complying with the notices served on the respondent, the
Engineer vide letters dated 05.04.2014 and 15.07.2014 declared the
respondent as a non-performer.

i. On 25.08.2014, the Independent Engineer noted that the
contractor was not working for last one year. On 30.08.2014, in the
inspection note, it was noted that the progress of the work was
negligible in last one year and the PD stated that the respondent has
a cash flow problem, and they are not able to restart the work.
j. On 03.12.2014, the minutes of the meeting recorded that there
is no progress of 4-lane project since last one year. On 16.12.2014,
it was noted that, during the last year, the claimant only achieved
2% progress. The Minister agreed to give further extension to the
respondent only upon its personal assurance that the work will be
completed by 31.03.2016. It was decided that escalation may by
granted as per the contract, but it will be frozen at the period of
eligible EOT and no increase in escalation shall be payable beyond
that period.


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:18.06.2026
12:35:37
FAO (OS) (COMM) 206/2023 Page 4 of 93

k. On 01.04.2015, the respondent failed to renew the Performance
Bank Guarantee w.e.f. 01.04.2015 as per Sub-Clause 10.2 of the
Conditions of Particular Application (COPA). On 15.04.2015, a
Memorandum of Understanding (MOU) was entered between the
parties on the following terms:
a. Payment to suppliers shall be made directly by the appellant.
b. The respondent shall extend validity of Bank Guarantees
against working capital advance, mobilization advance.
c. Performance security and retention money to be as per the
Contract.

d. The respondent undertook to unconditionally extend Bank
Guarantee against performance security up to 31.12.2016 which
is inclusive of the Defect Liability Period (DLP). However,
Bank Guarantee was not extended by the respondent;
l. Thereafter, a show-cause notice dated 07.01.2016 and a final
notice dated 14.01.2016 were issued by the appellant. On
18.01.2016, the respondent replied to the show-cause notice of the
appellant. On 20.01.2016, comments of the Engineer on the
respondent’s reply to the show-cause notice and on 23.01.2016,
further reply by respondent to the show-cause notice were received.
On 10.02.2016, the Engineer issued a letter stating that:-
i. In the last 4 years, the contractor has performed 5.63% of
work and the progress is NIL from April 2014.
ii. The contractor failed to extend performance security of
₹21.83 crore since 01.04.2015.


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:18.06.2026
12:35:37
FAO (OS) (COMM) 206/2023 Page 5 of 93

iii. The contractor has demobilized the machinery despite the
instruction of the Engineer to the contrary.
iv. The contractor has demobilized all-key personnel and other
supporting staff from the project.
v. The contractor has disposed material like aggregates,
boulders from the camp.
vi. In national interest, consolidated EOT up to 24.09.2014 was
granted.
vii. The MOU was entered on 15.04.2015 to complete the
project by 31.12.2015 but failed to renew the performance
security from 01.04.2015. As per Sub-Clause 10.2, the
performance security to be valid from 365 days after expiry
of the DLP.
m. On 14.03.2016, the appellant terminated the contract under
Clause 63.1 (a), b (ii), (d), (f) and (h) of COPA giving 14 days’
notice. On 25.04.2016, the Engineer called the respondent for a
joint inspection and measurement of work at the time of
termination of the contract; On 06.08.2016, the respondent invoked
arbitration; On 09.06.2017, the respondent filed claims before the
Arbitral Tribunal raising 21 claims. No prayer was made for
declaring the termination by the appellant as illegal.
n. On 07.02.2018, the respondent filed an affidavit before the
Tribunal for leading evidence on Claims No. 5, 6 and 8 only.
Admittedly, the witness of the respondent did not have personal
knowledge of the matter and was not present on the site at the time
of execution of the work as per cross examination.


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:18.06.2026
12:35:37
FAO (OS) (COMM) 206/2023 Page 6 of 93

o. On 22.02.2018, an amendment application was filed by the
respondent, revising Claim No. 8 from ₹63,37,75,829/- to
₹102,82,21,205/-.
p. On 24.08.2018, the respondent filed an amendment application
during final arguments seeking replacement of the amount of claim
for Claim No. 1 from ₹8,99,86,974/- to ₹31,41,35,273/-.
q. The Tribunal after conclusion of the arguments vide order dated
03.12.2018, allowed the amendment application regarding claim
no.1 filed by the respondent, and stated that both the parties had
declared that they have nothing more to say.

r. On 20.02.2019, The Tribunal passed the Arbitration Award,
allowing Claims Nos. 1,3, 4, 5, 6, 7, 8, 9, 10, 11, 14,17, 18, 19 and
20 of the respondent and rejecting Claims Nos. 2, 12,13, 15, 16 and
21.
3. Thereafter, the appellant herein filed the petition under Section 34
read with Section 16 (6) of the Act, for setting aside the Arbitration Award
dated 20.02.2019. The appellant’s contention before the learned Single
Judge was that the award is contrary to the agreement between the parties, in
violation of Section 23 of the Act, patently illegal, in conflict with public
policy and results in miscarriage of justice.
4. The learned Single Judge vide order dated 26.04.2023 has held as
under:-
“4. Mr. Kapoor submits that the arbitral tribunal has awarded
claim No.5 [for an extra amount to be paid to the banks for
extending bank guarantees] without any evidence as to the extra
amount, in fact, having been paid by the respondent. In this regard,
he has drawn my attention to paragraph E-5 and E-7 of the award,
which reads as follows:-


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:18.06.2026
12:35:37
FAO (OS) (COMM) 206/2023 Page 7 of 93

“E-5 A reference to Annexure CA-3 on pages 204 to 209 of
SOC shows the details of commission paid by the Claimant to
the bank for the extension of BGs from time to time. However,
no evidence for the various figures of the commission
allegedly paid by the Claimant has been filed.
xxxx xxxx xxxx
E-7 AT is convinced that some commission has to be paid to
the bank for extending the BGs. The claim cannot be denied
simply on the plea of absence of evidence for the same by the
Claimant. In the absence of the appropriate evidence filed by
the Claimant, the AT restricts the claimed amount to 90% of
the claim i.e. Rs.2,93,43,847/- and considers it would be fair
and reasonable to award a sum of Rs.2,64,09,462/- (Rupees
Two Crores Sixty Four Lakh Nine Thousand Four Hundred
Sixty Two only) in favour of the Claimant.”
[Emphasis supplied]
5. As far as claim No. 6 is concerned [claim for extra overhead
charges], Mr. Kapoor submits that the aforesaid claims have also
been upheld without evidence. Paragraph F-5 of the award deals
with this claim in the following manner:-
“F-5 The AT finds that the scheduled date of the completion
of work was 05.04.2008 and the work was terminated by the
Respondent on 29.03.2016. The Claimant appears to have
claimed prolongation for 95 months considering almost the
entire period between the scheduled date of completion and
the date of termination. The AT is not inclined to agree that
the Respondent alone can be held as responsible for the said
delay. However, the Respondent himself has mentioned in its
Statement of Defence on page 26 that the Engineer had
recommended consolidated extension up to 24,09.2014.
Although, no decision was finally communicated by the
Respondent on the said recommendation of the Engineer, it
would be fair to consider that the Claimant was entitled for
extension at least up to 24.09.2014. The period between the
scheduled date of completion and 24.09.2014 works out to
approximately 77 months. AT holds that the Respondent was
responsible for the prolongation cost to the Claimant for the
above period of 77 months less 10% assessed as failure on
the part of the Claimant in mitigating the losses, i.e. for a
period of 69.3 months, say sixty nine months only. The rate of
loss as projected by the Claimant is considered reasonable.
Although the Respondent has objected to applicability of the
Hudson formula, the AT did not agree with the contention of
the Respondent as the basis of Hudson formula has been held
good by various courts of the country. Accordingly, it would


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:18.06.2026
12:35:37
FAO (OS) (COMM) 206/2023 Page 8 of 93

be fair and reasonable to Award a sum of Rs. 35.15 crores to
the Claimant for the above claim, as worked out under: -
Loss due to overhead=0.07xRs. 218,37,82,339/30 months ×
69 months
= Rs. 35,15,88,956/-
Say Rs. 35.15 crores
(Rupees Thirty Five Crores Fifteen Lakh only)
The revised figure of the claim for Rs. 53,78,51,738/- as
projected by the Claimant in its affidavit dated 07.02.2018 is
not being taken into consideration by the AT, while arriving
at the said figure of Rs.35.15 crores.”
[Emphasis supplied]
6. Claim No. 8 was for expenses incurred towards prolongation
costs as a result of working in the extended period of the contract.
As far as this claim is concerned, Mr. Kapoor relies upon
paragraph H-5 , H-6 and H-7of the award, which read as follows:-
“H-5 The contention of the Respondent as regards the
deployment machinery does not stand in view of the fact that
the Respondent itself has filed the details of the machinery
available at site vide its document No. RD-7 (Pages 1188 to
1190). Thus the machinery as required for the work was
available till September 2015. Although. there is no specific
proof of each and every machine being available at the time
of scheduled date of completion of the work, the AT is
inclined to believe that the said machinery was available at
the site since the time of originally scheduled date of
completion. Similarly, the availability of machinery at site up
to March 2016 and April 2016 has also been evidenced by
the Respondent vide its Document No. RD-11 (Pages 1641 to
1645). H-6 As regards revised details of the machinery tiled
by the Claimant in Annexure CA-5 (amended), filed vide
application dated 22.02.2018 for amendment to its Claim
No. 8, the AT is not inclined to agree to the increased
number of working hours shown therein for the reasons that
follow. The period of prolongation as found justifiable by the
AT bas been considered as 69 months beyond the scheduled
date of completion, in the deliberation on Claim No. 6
hereinbefore. The AT holds the same view for allowing the
claim for idling / under utilization of the machinery. The CA-
5 (amended) has considered the idling period as 91.86
months approximately, say 92 months. Proportionately, the
amount of claim for 69 months works out lo Rs.
77,11,651903/- say Rs.77.11 crores. H-7. In view of above
the AT considers that it would be fair and reasonable to
award a sum of Rs.77.l1 crores (Rupees seventy seven crores


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:18.06.2026
12:35:37
FAO (OS) (COMM) 206/2023 Page 9 of 93

eleven lakhs only) against this claim.” [Emphasis supplied]
7. I am of the view that the challenges on claim Nos. 6 and 8 do not
fall within the limited grounds available to the petitioner under
Section 34 of the Act.
8. As far as claim No. 6 is concerned, the respondent’s claim was
based on Hudson’s formula. Although the respondent claimed
prolongation costs for 95 months, the arbitral tribunal has held
that the petitioner was responsible for prolongation only of 69
months. The reasoning given by the arbitral tribunal in paragraph
F-5, extracted hereinabove, is based upon the pleadings of the
petitioner itself in the statement of defence with regard to the
engineer’s recommendation for consolidated extension until
24.09.2014. This period has been further adjusted by 10% for the
respondent’s failure to mitigate its losses. The arbitral tribunal’s
reasoning on this aspect cannot be characterised as perverse or
implausible, so as to require the interference of this Court within
the narrow scope available to the petitioner under Section 34 of the
Act. The arbitral tribunal has thereafter applied Hudson’s formula,
which is a standard formula. The arbitral tribunal’s jurisdiction to
accept one or the other standard formula has been accepted by the
Supreme Court inter alia in Mcdermott International Inc. vs. Burn
Standard Co. Ltd. & Ors. (2006) 11 SCC 181 [paragraph 106].
Hudson’s formula has been specifically referred to in the said
judgment. The application of Hudson’s formula in this regard has
been accepted by this Court inter alia in National Highways
Authority of India vs. Progressive Constructions Ltd. (2015) 5 ARB
LR 71 [paragraph 20]. The arbitral tribunal has applied this
formula to the prolongation of 69 months, and awarded the claim
partially on this basis. I am, therefore, not inclined to accept the
petitioner’s challenge to claim No. 6.
9. On claim No. 8 also, I do not find the petitioner’s grievance to
be made out. The claim has been allowed on the basis of the details
of machinery supplied by the respondent itself in document No.
RD-7 and the availability of the machinery at site upto March,
2016 and April, 2016 by the respondent’s document No. RD-11.
The claimant’s version with regard to the details of the machinery
available has not been accepted and the arbitral tribunal has gone
by the respondent’s documents. The period of prolongation of 69
months, as held by the arbitral tribunal, in answer to claim No. 6,
has been applied to this claim also, and the claim has been allowed
proportionately. The reasoning on this aspect is based entirely on
an evidentiary assessment, which is beyond the scope of challenge
under Section 34 of the Act.
10. The challenge on claims Nos. 6 and 8 is, therefore, rejected.
However, on claim No. 5, I find that the petitioner’s challenge


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:18.06.2026
12:35:37
FAO (OS) (COMM) 206/2023 Page 10 of 93

requires further consideration.
11. Issue notice limited to claim No. 5. Dr. Swaroop George,
learned counsel, accepts notice on behalf of the respondent.
12. List for consideration on this issue on 03.05.2023."


ISSUES INVOLVED
5. As specifically submitted by the counsel for the appellant, the issues
pressed in this appeal are only with respect to Claims No. 1, 6, 7, 8, 9 and
11.
SUBMISSIONS ON BEHALF OF THE APPELLANT
6. Mr. Ankur Mittal, the learned counsel for the appellant/NHAI,
submitted that the erstwhile counsel for NHAI before the learned Single
Judge was neither authorised nor had any instructions from NHAI before
giving up its challenge to claims No. 1,3,4,7,9,11,17,18, and 20 as recorded
in the order dated 26.04.2023. Any statement made by NHAI’s counsel
without authority and approval from the competent authority of NHAI is not
binding on appellant.
7. He submitted that, the appellant has acted against the erstwhile
counsel and has de-empanelled him and has also withdrawn all matters from
him, and such a submission made by a counsel would be invalid as held in
Himalayan Coop. Group Housing Society v. Balwan Singh and Others
(2015) 7 SCC 373 .
8. He also submitted that the giving up of the claim by the erstwhile
counsel is stated to be on the basis that the principal grounds raised in the
petition have already been decided against NHAI in another petition under
Section 34 of the Act between the same parties.
9. He submitted that the said statement by the erstwhile counsel was
without any instructions, and even otherwise, was not based on any factual /


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:18.06.2026
12:35:37
FAO (OS) (COMM) 206/2023 Page 11 of 93

legal foundation, for the following reasons:
a. A different Tribunal was dealing with the arbitration of a contract
for state of Assam in a single entry formation to widen 2 lane to 4
lane. In the said arbitration, the Tribunal has allowed the loss of
profits, claim for increase in rate due to extra stay on work site,
reimbursement towards royalty, reimbursement of extra VAT
@1%, p endente-lite interest and future interest, with regard to
delay analysis, completely different for different contracts. The
Tribunal did not consider the pleading and the material of the
appellant regarding the slow progress.

b. Another Tribunal was dealing with a project in the State of Orissa
for widening 2 lane to 4/6 lane. The Contract Agreement was
entered on 20.08.2001 . The Tribunal allowed 25% (approx.) of
the claim. With regard to loss of profit (Claim No. 11), the
Tribunal declined the Claim No.7 claim for increase in rate due to
extra stay on work site, Claim No. 17- for reimbursement towards
royalty, Claim No.18- reimbursement of extra VAT @1% were
not subject matter. With regard to Claim 20- interest- only future
interest was granted. With regard to delay analysis completely
different for different contracts, the Tribunal gave reasoning
regarding delays.
10. With regard to the finding of the Tribunal on the issue of illegal
termination, he has submitted that the total stretch comprising the project
highway is 30 KM. Out of 30 KM, 24 KM was handed over to respondent
on or about the commencement date of 06.10.2005. The remaining 6 KM
stretch was handed over in May 2010. The respondent/claimant asserts that


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:18.06.2026
12:35:37
FAO (OS) (COMM) 206/2023 Page 12 of 93

for all practical purposes, the handing over date should be construed as
23.12.2010. The claimant asserts that a further 365 days would have been
required to complete highway works. A period of 572 days is stated to be
required for completing bridge works. A small stretch of approx. 300 meters
relating to toll plaza land was lastly handed over on 07.05.2013.
11. He also submitted that the following material documents were
completely ignored by the Tribunal;
a. Manpower status from MPRs reflects, key professional staff was
not available between 31.01.2014 – May 2015.
b. In the minutes of the meeting dated 16.12.2014, it is noted that in
last one year only 2% work has been done.
c. In the show-cause notice dated 07.01.2016, it was asserted that
during 2012-13, only 2.05% work has been done, and during
2013-14 only 0.93% work has been done. It is further stated that
since January 2015 only 0.492% work has been done.
d. The Engineer’s letter dated 10.02.2016 states in para (a) and (b),
that in the last 4 years, only 5.63% work has been done.
e. In the termination letter dated 14.03.2016 in Para (f) avers that
only 5.63% work has been done since 2012.
12. He submitted that, in reply to the show-cause notice dated 18.01.2016,
the respondent attempted to justify its conduct by stating that work got
affected by various events, including:
a. Variation works to the extent of 14.1134% requiring more time;
b. Law and order problems resulting into delay of 570 days;
c. Bandh and strikes resulted into loss of 670 days;


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:18.06.2026
12:35:37
FAO (OS) (COMM) 206/2023 Page 13 of 93

d. Between 20.09.2010 to 31.03.2012, work stopped due to
deterioration of law and order and contractor had to demobilize;
e. Key managerial persons had to leave due to various problems such
as extortion, law and order etc.;
f. Out of 18 bridges, only 7 bridges completed. 2 major bridges
remain untouched;
g. Termination notice was issue dated 14.03.2016;
h. The Engineer vide letter dated 20.01.2016 in reply to the
contractor reply to the show-cause notice dated 20.01.2016 stated
that the contractor has not raised RFI (Request for work) since last
one year.
13. Mr. Mittal with regard to the finding of the Tribunal on the issues of
failing to carry out any obligation under the contract under Clause 63.1 (a),
submitted that, in the EOTs, the Engineer held that the contractor was not
available to work on the available work front, whereas, the Tribunal has
only taken into consideration the progress that too the financial progress
from March, 2010 to September, 2012 whereas there is close to nil progress
after April 2012.
14. With respect to preceding the work or any section thereof, within 28
days after receiving the notice pursuant to Sub-Clause 46.1, he submitted
that the Engineer has held that the contractor was not available to work on
the available work front and MOU dated 15.04.2015 could not be acted
upon due to the Bank Guarantee not being renewed. He also submitted that
the respondent’s action of abandoning the work plainly demonstrates the
intention not to continue performance of his obligations under the contract.
15. He submitted that, in a letter dated 26.03.2014, the Engineer stated


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:18.06.2026
12:35:37
FAO (OS) (COMM) 206/2023 Page 14 of 93

that the work is almost stand still for more than 1 year. In letter dated
26.03.2014, it was stated that, key personnel have not been mobilized. The
Engineer, vide letter dated 21.09.2015 asked the claimant to remobilize
those machines removed from the site without intimation to Engineer or the
appellant. Further, it stated that there are several machinery which are in
breakdown, rejected and under repair.
16. Mr. Mittal submitted that the Tribunal has stated that there is no
specific instance where EOTs recommended by the Engineer were not
granted by the appellant for more than 3.5 years. However, there are
numerous such instances recorded in the show-cause notice and termination.

17. According to him, the Tribunal observes that the respondent had
executed work worth about ₹ 60 crore between September 2010 and March
2012, which indicates that the contractor was capable of executing on an
average more than ₹ 3 crore per month. However, the respondent has
abandoned the site since 2012 and has only achieved a progress of hardly
5.63% between 2012-2016 when, even as per the case of the respondent, the
entire land (including forest land of 6 KM) was available to work upon. He
also submitted that, with regard to abandoning of the project, the manpower
status of the contractor’s part of the MPR as relied upon by the respondent
would show that it has completely abandoned the project between
31.01.2014 to 28.02.2015 and there was no key professional staff available
on the site. Again, the project manager was missing from February 2016.
18. Mr. Mittal has submitted that the challenge in this appeal to the claims
no. 3, 4, 17 and 18 allowed by the Tribunal are not pressed by the appellant
and the challenge is confined to claims no. 1, 6, 7, 8, 9 and 11.


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:18.06.2026
12:35:37
FAO (OS) (COMM) 206/2023 Page 15 of 93

CLAIM-WISE SUBMISSIONS OF THE APPELLANT
Claim No. 1- Towards unpaid work including escalation
a. The claim was filed seeking payment for the works done to the tune of
₹ 3,50,47,341.99/- and a further amount of ₹ 5,49,39,632/- for alleged
variations approved by the Engineer. The respondent relied upon
documents which were illegible. There is no basis for the figures, the
copy of which was not supplied anytime. Without admitting, even in
the statement, it comes out that the respondent has done no work after
May 2015. Moreover, no evidence was led by the claimant on this
claim.

b. In Claim No. 11, the respondent has made a specific averment that
balance work left to be executed is ₹ 51,51,93,861/-. The figure of ₹
51.5 crore was also quoted in the reply to the show-cause notice given
by the respondent on 18.01.2016. It is the respondent’s own case that it
had allegedly executed work to the extent of 74%. Despite that, the
claimant raised a specific claim of ₹ 8.99 crore as outstanding. Further,
the claimant at some other place stated that 30% of the work was yet to
be executed. On 24.08.2018, at the time of conclusion of arguments
before the Tribunal, the claimant moved an amendment application to
revise claim no. 1 from ₹ 8,99,86,974/- to ₹ 31,41,35,273 on the
following grounds:
i. Upon termination of the contract, the measurement of the
work is the responsibility of the appellant.
ii. The value of the work done and left to be done was not


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:18.06.2026
12:35:37
FAO (OS) (COMM) 206/2023 Page 16 of 93

within the knowledge of the respondent. This amounted to
introducing a completely new claim. The claimant alleged
that since the balance work is only ₹ 51,51,93,861 which is
equivalent to 23.59%, therefore, it must be assumed that it
has completed the remaining 76.41% of the work. Since
claimant was paid for only 68.97%, the difference of 7.44%
amounting to ₹ 31,41,35,273/- should be paid.
c. As per the finding of the Tribunal, since the balance work is ₹
51,51,93,861, which works out to be 23.59% of total work, it must be
assumed that the claimant would have completed 76.41% work. Since
claimant has been paid for 68.97%, it must be paid for 7.44% of the
contract price equivalent to ₹ 16,24,73,398 and also the price escalation
of ₹ 6,16,74,901.88, thus a total of ₹ 22,41,48,299/-. Additionally, the
Tribunal also awarded the originally amount claimed amounting to ₹ 8,
99, 86,974/- as well.
d. However, the Tribunal deducted an amount of ₹ 14,27,067/- claimed by
the claimant for providing and maintaining vehicles for the Employer,
including the driver. As such, the total amount awarded is (₹
22,41,48,299/- + ₹ 8,99,86,974/-) - ₹ 14,27,067/- = ₹ 31,27,08,206/-.
e. The Tribunal has not provided the opportunity of being heard to the
appellant on the amended Claim No.1 despite making a specific request
in this regard by the counsel for the appellant after allowing the
amendment application.
f. That apart, the amendment was allowed by the Tribunal on 03.12.2018


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:18.06.2026
12:35:37
FAO (OS) (COMM) 206/2023 Page 17 of 93

after the arguments by both sides were concluded on 12.11.2018. It is
to be noted that the parties had even filed the written arguments by the
time the said order was passed. The respondent/claimant had filed its
submissions on 30.08.2018, the appellant filed submissions on
29.10.2018. Before publication of the award, the counsel for the
appellant vide e-mail dated 07.02.2019 requested the Tribunal for the
hearing on the amended Claim No.1. The Tribunal’s reference to
“nothing more to say” is completely misconceived because of the
reason that the said statement was given by the parties with regarding
the argument for the amendment application not the arguments on
merits for the amended claim no.1.
g. Merely because the appellant chose not to file reply to amendment
application, it does not mean that the appellant has given up its right to
argue the amended claim on merits. The Tribunal declined the said
opportunity as noted in the impugned order, by alleging that the same is
with an intention to delay the award. The award has been passed
without even granting an opportunity to the appellant to argue on the
amended claim, thus in violation of the principles of natural justice.
h. The Tribunal adopted some random formula to arrive at the conclusion
that the unpaid work is 7.44% and awarded an amount of ₹
22,41,48,299/- in addition to ₹ 8,99,86,974/-. The document in support
of this claim was illegible. No legible copy was ever filed. No evidence
was also led.
i. The impugned award is in contravention of Clause 53.4 COPA; there is


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:18.06.2026
12:35:37
FAO (OS) (COMM) 206/2023 Page 18 of 93

no contemporaneous record that has been produced by the claimant to
support the claim. The entire award is based on assumption that since
the balance work shown in ₹ 51, 51, 93,861/- which is about 23.59%
therefore the work done would have been 76.41%. The claimant did not
produce any proof of work done in the form of IPC, bills raised by its
sub-contractor, proof of purchase of raw material, any request made by
the claimant for recording of measurement before termination of the
contract, which was allegedly not met by the Engineer or refused, or
any other document etc.
j. The claimant was executing work and raising IPCs from time to time.
The original claim was filed seeking payment of ₹ 8.99 crore which as
per the claimant was outstanding. This was based on some documents
filed in support of claim. No evidence was led on claim no. 1 and the
matter was argued. It is during arguments that the entire basis of this
claim was changed, and the amount was raised to almost 4 times the
original claim.
k. The award recorded that the claimant in Statement of Claim itself has
claimed that it has allegedly achieved 74% till 31.03.2026. However,
ignoring the respondent-claimant’s own pleading the Tribunal went on
to hold that it has achieved 76.41% based on surmises and conjectures.
No IPC, measurement book, invoices, vouchers etc. to prove that the
claimant has achieved 76.41% progress. No iota of evidence is on
record to show that the respondent has spent an amount of about ₹ 172
crore out of which only ₹ 150.61 crore has been paid.


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:18.06.2026
12:35:37
FAO (OS) (COMM) 206/2023 Page 19 of 93

l. There is no finding of the Tribunal on the originally claimed amount of
₹ 8,99,86,974/-, further, there is no record from the Tribunal could pick
up the unique figure of ₹ 14,27,067/- deducted in reference to the
alleged amount claimed by the claimant for providing and maintaining
vehicles for the Employer, including the driver. The Tribunal
completely ignored the material fact that no claims were made either in
any IPC or even in the final bill. Therefore, under Clause 60.13 COPA,
the appellant is not liable for any claims not raised in the final bill.
m. Admittedly, the appellant, vide letters dated 02.04.2016 and 22.04.2016
requested the Engineer to call upon the respondent to attend the site for
joint measurement of the work at the time of termination. Pursuant
thereto, the Engineer, vide letters dated 25.04.2016 and 11.05.2016
specifically called upon the respondent for a joint inspection and
measurement of work at the time of termination of the contract. Despite
the same, the respondent deliberately chose not to appear for the joint
measurement.
n. Clause 60.1 provides that the contractor shall submit a monthly
statement along with supporting documents by 7th day of each month
for the work executed up to the end of the previous month. This
statement reflects the work done in the previous month, with all
supporting documents and valuation thereof. The last IPC submitted
by the respondent was for the month of April 2014, and no further IPC
was submitted. Importantly, claim no. 1 has not been awarded on the
basis of any measurement made by the Engineer.


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:18.06.2026
12:35:37
FAO (OS) (COMM) 206/2023 Page 20 of 93

19. Mr. Mittal submitted that, it is a settled principle of law that the onus
lies upon the claimant to prove its claims. However, by its own conduct, the
respondent failed to adduce any evidence in respect of the balance work
allegedly executed. Consequently, there was no evidence whatsoever
regarding the balance work before the Tribunal. He also submitted that an
Award contrary to contractual provisions is patently illegal, as held by the
Supreme Court in ONGC v. Saw Pipes (2003) 5 SCC 705 and State of
Chhattisgarh v. SAL Udyog (P) Ltd., (2022) 2 SCC 275 .
20. He submitted that there is no proof of the work executed for which the
claim is awarded. The Tribunal awarded Claim No. 1 on the premise that the
contractor had executed 76.41% of the work. Clause 60.1 provides that the
contractor shall submit a monthly statement along with supporting
th
documents by 7 day of each month for the work executed up to the end of
the previous month. However, the contractor had submitted Interim Payment
Certificate (“IPC”) No. 73 only up to April 2014, reflecting execution of
merely 66.26% of the work.
21. He submitted that in the absence of any contemporaneous monthly
statements or IPCs substantiating execution of 76.41% work, the finding of
the Tribunal is unsupported by evidence and is therefore perverse. Post
termination of the contract agreement, the contract for the balance work has
been awarded for an amount ₹129.19 crore to Simplex Infrastructures
Limited, far more than the work claimed to be completed by the claimant.
22. Mr. Mittal submitted that post amendment application, the appellant
was not granted time to argue on the amended claim, the amendment
application was allowed by the Tribunal vide order dated 03.12.2018, after
the Award had been reserved and written submissions had been filed. The


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:18.06.2026
12:35:37
FAO (OS) (COMM) 206/2023 Page 21 of 93

claim was arbitrarily increased from ₹ 8,99,86,974/- to ₹31,41,35,273/-. He
submitted that claim no.1 was not legible and legible copy of the same was
never placed on record before the Tribunal. However, the list of variation
orders was on record. The claimant chose not to file a single document in
proof of having carried out any work but relied upon an illegible document
alleged to have been issued by the Engineer.
i. Claim No. 6 – Claim relating to Overheads
a. The claim was filed relating to overstay of the respondent on site
with all manpower, labour, equipment, and resources between the
extended period from April 2008 to December 2015 which comes
out to 95 months.
b. The claim was based on average overhead expenditure of 7% of the
estimated value of works based on Hudson Formula. The claimant
in the Statement of Claim stated that the date of handing over of the
balance 6 KM land may be construed as 12.12.2010 for all practical
purposes.
c. The Tribunal, despite holding that the appellant alone cannot be
held responsible for the delay, went on to award the entire
recommended EOT period i.e. 77 months less 8 months of
mitigation (all without any basis) i.e. 69 months as prolongation.
The Tribunal applied Hudson Formula to calculate damages and
awarded a sum of ₹35.15 crore towards overheads for a period of
69 months.
d. Despite the specific objection of the appellant that Hudson Formula


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:18.06.2026
12:35:37
FAO (OS) (COMM) 206/2023 Page 22 of 93

has no applicability in cases of concurrent delay, and is not
applicable at all, a huge amount of ₹ 35.15 crore was awarded
without any discussion or any basis whatsoever, which is in direct
contravention of law laid down in the cases of:
i. Nandi Infratech Pvt. Ltd. v. R. K. Bararia and Others,
2024 SCC OnLine Del 4287- Para 52-61;
ii. Batliboi Environmental Engineering Limited v.
Hindustan Petroleum Limited and Anr., 2023 SCC
OnLine 1366- Para 22,23, 26 and 46;
iii. Unibros v. All India Radio, 2023 SCC Online SC 1366-
Para 16-19;
iv. Edifice Developers and Project Engineers Ltd v. M/s.
Essar Projects (India) Ltd, 2013 SCC OnLine Bom 5-
Para 8-11, 12;
v. Essar Procurement Services Ltd. v. Paramount
Constructions, Arb. Pet. No. 470 of 2012 - Para
33,34,35,104;
vi. Campos Brothers Farms v. Matru Bhumi Supply Chain
Pvt. Limited and Others, 2019 SCC OnLine Del 8350 -
Para 55,56,77 and 81;
vii. Vijay Karia and Others v. Prysmian Cavi E Sistemi
SRL and others, (2020) 11 SCC 1- Para 75-81;
e. Clause 53.4 of the Contract Agreement categorically provides that
the jurisdiction of the Tribunal is confined to award damages based
on contemporaneous records. Thus, the contract itself excludes
applicability of any formula for calculation of losses. This was
completely ignored by the Tribunal. No contemporaneous


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:18.06.2026
12:35:37
FAO (OS) (COMM) 206/2023 Page 23 of 93

document was looked into by the Arbitral Tribunal to arrive at a
huge figure of ₹ 35.15 crore. On the contrary, the Tribunal
specifically arrived at a finding that it is not considering the revised
figure of ₹ 53,78,51,738 projected by the respondent in its evidence
affidavit. Prolongation costs were rejected throughout by the
Engineer while recommending the EOTs citing concurrent delays
on the part of contractor on critical path, including lack of
manpower, machinery, machinery not mobilized, no work/ slow
progress on available stretches also, slow progress on structures,
bridges etc.

f. There is no discussion in the entire award on the EOTs
recommended by the Engineer and how the rejection of
prolongation costs claimed by the Engineer in its recommendation
is not correct.
g. There is no discussion or finding by the Tribunal why the entire
EOT recommendation is synonymous with delay of the appellant.
EOTs themselves record that the contractor is to be majorly blamed
for delaying the project. Reliance is placed on NHAI v. IRB
Pathankot Amritsar Toll Road Ltd. 2023 SCC OnLine Del 3789 .
h. There is no discussion on the handing over of land. The last stretch
of 6 KM even as per the claimant was available with it on
22.12.2010. The Tribunal refused to consider the revised figure of
₹53,78,51,738/- projected by respondent in its Evidence Affidavit,
thus there being effectively no evidence on record to award


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:18.06.2026
12:35:37
FAO (OS) (COMM) 206/2023 Page 24 of 93

anything in favour of respondent.
i. The first three EOTs were duly approved by the appellant i.e. up to
06.03.2011. All these three EOTs were recommended with clear
finding of the Engineer that the respondent is concurrently liable
for delaying the project and is not entitled for any prolongation
costs at all. The approval of these 3 EOTs was well known to the
respondent who never protested or raised a claim despite specific
rejection of prolongation costs by the Engineer and the appellant.
j. The NHAI approved first EOT vide letter dated 16.06.2008 which
was intimated by the Engineer to the claimant vide letter dated
01.07.2008. The revised date of completion worked out as
10.05.2009 by the Engineer. The second approved EOT vide letter
dated 27.05.2009 was intimated by the Engineer to the claimant
vide letter dated 08.09.2009. The revised date of completion was
worked out as 10.05.2010 by the Engineer. The approved third
EOT vide letter dated 09.07.2010. The revised date of completion
was worked out as 06.03.2011 by the Engineer. The arbitration was
invoked only on 06.08.2016. Therefore, any claim which relates to
a period prior to 06.03.2011 was hopelessly time barred.
k. The Tribunal held that cause of action would arise only at the time
of submission of final bill which stage never arose in the Contract
and therefore, the claim is within limitation. This finding of
Tribunal is perverse. The cause of action towards prolongation for
the periods covered by three extensions recommended and granted


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:18.06.2026
12:35:37
FAO (OS) (COMM) 206/2023 Page 25 of 93

by NHAI arose when those recommendations were made and
eventually accepted by NHAI. A perusal of various Clauses of the
contract including Clauses 12, 41, 44 etc would reveal that the
while granting extension of time, any cost that the contractor is
entitled to is also required to be added to the contract price. The
cause of action crystallised on the date when EOTs
recommendation rejected prolongation costs and the same were
accepted by the NHAI. The cause of action does not get stretched to
the date of final bill as held in State of Gujarat v. Kothari and
Associates (2016) 14 SCC 761 . In support of his submission he has
relied on; NHAI v. M.G. Contractors P. Ltd.- Arvind Techno
Engineers P. Ltd. (JV) O.M.P. (COMM) 356/2023.
l. The respondent before this Court has argued that MoRTH specifies
certain overhead expenses, and there were key personnel were
deployed at site. In fact, the manpower status forming part of the
MPRs relied upon by the respondent itself shows that the contractor
had abandoned the project between 31.01.2014 and 28.02.2015,
with no key professional staff at site, and even the Project Manager
was missing from February 2016.
ii. Claim No. 7- Claim for increase in rate in executing the work due to
extra stay on work site
a. The claim for the period–April 2008 to IPC-72 is that the Engineer
while recommending EOT as per Clause 42.2 (a) of the contract did
not determine the extra cost incurred by the claimant. The claimant


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:18.06.2026
12:35:37
FAO (OS) (COMM) 206/2023 Page 26 of 93

is entitled to extra cost for executing the work as also claim no. 5,
6, 8 & 10. From April 2008 to IPC-72 the claimed amount comes
to ₹ 11,86,74,618/- The claim is made on the basis of alleged 10%
increase in rate, on an average over the agreement rates and price
adjustment given under the Contract. The Tribunal held that the
claim is without any basis or evidence. However, it went on to
award 5% of the alleged work done after April 2008 which was
never proved by the respondent. Amounts were awarded without
any basis whatsoever.
b. The award is in contravention of Clause 53.4 COPA. There was no
contemporaneous document to support the claim or award. The
Tribunal has completely ignored its own finding wherein it has
categorically held that it is not inclined to agree that the appellant
alone can be held responsible for the delay. The finding that the
respondent has carried out work of ₹ 11,86,74,618/- beyond
05.04.2008 is based on no evidence whatsoever. Nothing was
placed before the Tribunal to show that such amount of work
executed beyond 05.04.2008.
c. The Tribunal completely failed to consider that the respondent has
been given the benefit of price adjustment on the work executed in
terms of the contract, and as such, any amount awarded without
considering price adjustment paid to the respondent would amount
to duplication. It has categorically held that the respondent has
claimed 10% amount without any basis.


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:18.06.2026
12:35:37
FAO (OS) (COMM) 206/2023 Page 27 of 93

d. Prolongation costs were rejected throughout by the Engineer. The
same was not disputed by the respondent at the relevant time.
Therefore, the same is barred by limitation at least up to
06.03.2011.
iii. Claim No.8 - Towards Prolongation cost for idling and underutilization
of machinery.
a. The claim for a Period from May 2008 to December 2015-₹
102,82,21,205/- (old ₹ 63,37,75,828.80/-) was filed towards idling
and underutilization of machinery. The claimant did not mobilize
the entire machinery and was not able to work on the available
stretch. The claimant overstayed at the project site due to its own
defaults. Though the machinery is stated to be owned and hired, no
details were placed on record. Despite holding that the Tribunal is
not inclined to agree to the increased number of working hours
shown in the amended calculations, it went on to award the huge
amount of ₹ 77.11 crore based on the amended calculations only.
b. The Tribunal further held that there is no proof of each and every
machine being available at the time of completion of the work, but
made a vague assumption that the said machinery was available at
the site since the time of originally scheduled date of completion.
The Tribunal made a reference to RD-11 to hold that the machinery
was allegedly available.
c. CA-5 is a chart which avers certain machinery to be available and
uses certain “rates” per hour and use certain “number of working


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:18.06.2026
12:35:37
FAO (OS) (COMM) 206/2023 Page 28 of 93

hours” to arrive at an astronomical figure of ₹ 63,37,75,828,
without any proof, document or evidence whatsoever.
d. Arbitration was invoked only on 06.08.2016, thus the same is
barred by limitation to the extent that despite rejection of
prolongation costs, arbitration was not invoked within three years
of rejection of claim. The Tribunal has failed to give any finding as
to why the entire EOT period [less 9 months period towards
mitigation] has been attributed to NHAI default.
e. RD-7 relates to a list of plant and machinery prepared during a
surprise visit on 14.09.2015. The report shows that a number of
machinery was either under breakdown or under repair. RD-11 –
MPR of March 2016 and April 2016 refers to a number of
machinery under breakdown.
f. The respondent alleged in its written submissions that the
breakdown is only a minor problem. However, there is no
explanation why almost entire machinery continued to be under
breakdown/ under repair. The Tribunal did not deal with this
important aspect at all, and there is no finding of the following
issues:
i. What was the period during which various machineries
were under repair;
ii. What was the period during which the machineries were
under breakdown?
iii. Whether breakdown is a minor problem and can be
ignored for awarding prolongation costs?


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:18.06.2026
12:35:37
FAO (OS) (COMM) 206/2023 Page 29 of 93

g. The Tribunal went on to assume that the entire machinery was
available and would qualify for prolongation cost claim. RD-11
does not support case of claimant it reflects that most of the
machinery is not working. As per RD-11, 8 machines and in RD-7,
5 machines as claimed by the respondent were not found.
h. In case of idling, the party suffering would at best be entitled for
depreciation in cost of machinery (in case same is owned) and
interest on the cost of machinery during the period of prolongation
or alternatively, the lease rent and interest on lease rent, if the same
is hired.

i. In the present case the idling charges have been worked out way
more than the cost of the entire machinery itself. No invoice, lease
rent receipt etc. was produced by respondent. That, a machinery
which was purchased as per respondent, in 2007-08, the amount
claim towards prolongation is ranging from 4 -6 times and is more
than the cost of machinery itself, which is most perverse, arbitrary,
and illegal. The respondent has also claimed and awarded by the
Tribunal the cost of the machinery in claim no.9. Reliance is placed
on State of Orissa v. Samantary Construction 2015 SCC Online
SC 856 .
j. The claimant is claiming alleged loss of opportunity to use the
machinery elsewhere in other projects, while making a claim for
use of machinery based on working hours of 8 to 10 hours a day for
25 days in a month. The law in this aspect is settled that, for


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:18.06.2026
12:35:37
FAO (OS) (COMM) 206/2023 Page 30 of 93

claiming loss of opportunity, it must be show that: (a) there was a
delay in the completion of the project. (b) Delay is not attributable
to the claimant. (c) claimant status as an established contractor (d)
Credible evidence to substantiate the claim of loss of profitability.
k. In the evidence affidavit and in the oral arguments the claimant
makes reference to the MoRTH Standard Data Book. The said Data
Book would show that out of the 30 machineries for which the
idling is claimed, the rates of 12 machines are not mentioned. The
Tribunal has not considered this aspect. In the absence of actual
evidence, a claim cannot be awarded solely based on the MoRTH
Standard Data Book and has referred to Shivalaya Construction
Company Pvt. Ltd. v. Delhi Development Authority, 2021 SCC
OnLine 5303 .
l. The Tribunal has granted the claim taking the respondent as the
responsible for the whole delay for 69 months till the last EOT
dated 24.09.2014 recommended by Engineer.
m. In the Evidence Affidavit filed before the Tribunal with in
respect to Claims no. 6 and 8 stated that the machinery was
procured on 01.04.2007 and 01.04.2008. The respondent further
claimed depreciation at the rate of 13.91% per annum. On the
respondent’s own showing, the written-down value of the
machinery as on the date of termination, i.e. 14.03.2016, would be
nil .
iv. Claim No. 9- Claim for recovery of Rs. 13,61,08,604/- towards cost of


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:18.06.2026
12:35:37
FAO (OS) (COMM) 206/2023 Page 31 of 93

confiscated machinery, material, and other assets
a. Claim Period –On termination. The claim was filed towards
alleged confiscated machinery, material and other assets.
b. That the Tribunal allowed the claim amounting to ₹ 7,70,80,510/-
on guess work and arrived at a finding that there is no evidence
produced by the respondent and agrees that there has been
contradiction in CA-5 and CA-6 and therefore certain items in
CA-6 have not been considered by them. However, the Tribunal
failed to detail any such items. The Tribunal recorded that no
evidence has been furnished by respondent, despite that awarded ₹
7,70,80,510/.
c. That the respondent claimed that machines are owned as well as
hired. However, there is no detail separately produced by
respondent and claimed all the machinery as its own. The
machinery in CA-5 and CA-6 are different. Some parts supplied
by Kavuru Private Ltd., No details of any bill or payment made to
him are on the record. Without prejudice, the respondent in the
evidence affidavit has claimed depreciation @ 13.91% on the
plants and machinery. The respondent further states that the plants
and machineries mostly purchased in the year 2008.
d. That, the maximum value if any the machinery would have been
about 7 years. The present claim is based on the alleged
confiscation of the machinery pursuant to the termination of the
contract on 14.03.2016. The meaning thereby that the machinery


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:18.06.2026
12:35:37
FAO (OS) (COMM) 206/2023 Page 32 of 93

would have no value at the time of termination of the contract.
e. That the respondent before this Court has argued that the Tribunal
has awarded 15% as the salvage value as provided in the
Companies Act, 2013. This contention was neither pleaded nor
argued before the Tribunal, nor is there any finding to that effect
in the Award; any such conclusion, in the absence of pleadings or
proof of costs, it is perverse and violative of the principles of
natural justice. No case of salvage was ever set up anywhere at
any stage. On the contrary, the claim was towards the value of
plant and machinery. The unique amount awarded by the Tribunal
is arbitrary and not based on any pleadings or documents filed by
either side, and there is absolutely no explanation in the award as
to how that number was arrived at.
v. Claim No. 11- Claim for loss of profit- Rs. 5,15,00,000/-:
a. For Claim Period – April 2008 to 21.03.2016. The claimant is
entitled 10% profit on balance work of ₹ 51,51,93,861/-.
b. As per the submission of the NHAI, the claimant is only entitled to
cost in terms of Clause 42.2 of GCC and Clause 1.1 (g) (i). The
ample amount of material relating to the default of the claimant is
placed on record. The claimant could have terminated the contract
but abandoned the project, mis-utilized NHAI grant of capital
assistance of ₹ 10.91 crore.
c. The Tribunal allowed the claim since it had held termination illegal.


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:18.06.2026
12:35:37
FAO (OS) (COMM) 206/2023 Page 33 of 93

No quantification of claim at all was carried out by the Tribunal.
There was no material before the Tribunal by respondent to
substantiate that it would have made 10% of profit on the balance
work. No financial plan was produced by the respondent to show
as to how much profit it has anticipated to have made on the project
in question.
d. That, as per Clause 42.2 and 1.1 (g) (i), the respondent is only
entitled to the cost and not profit. Despite the finding that the
present case is a case of concurrent delay. The Tribunal has not
given any concession for the defaults of the respondent while
calculating the claim.
ADDITIONAL SUBMISSIONS
23. Mr. Mittal submitted that the EOTs cannot form the basis for award of
claims, for the following reasons:
a. The respondent before this Court has argued that the recommendation
letters issued by the Engineer were not marked to the respondent and
that it had no knowledge of the EOTs. However, the respondent itself,
in its Statement of Claim, expressly referred to and annexed various
recommendation letters of the Engineer, including letters dated
03.03.2011 and 14.12., thereby belying its own contention. More
importantly, the recommendations for grant of EOTs were treated as
the sole basis by the Tribunal for holding NHAI liable for the alleged
delay, notwithstanding the fact that the Engineer has recorded that the
respondent was largely responsible for the delay.


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:18.06.2026
12:35:37
FAO (OS) (COMM) 206/2023 Page 34 of 93

b. Without prejudice, once the respondent disputes the Engineer’s
recommendations regarding EOTs, the same could not have been relied
upon by the Tribunal for holding NHAI responsible for delay and the
basis for awarding any claims.
24. He submitted that the respondent did not renew the bank guarantee at
the time of termination the respondent argued that NHAI did not grant
extension till March 2016 pursuant to the Ministry’s meeting dated
16.12.2014. However, the respondent failed to show that MOU dated
15.04.2015 was executed in this regard, and despite mandatory requirement
under the said MOU to extend the bank guarantee, the respondent failed to
renew the bank guarantee, which had expired on 01.04.2015, in breach of
the said MOU.
25. Mr. Mittal submitted that the appellant cited many grounds for
terminating the Contract Agreement in its termination letter dated
14.03.2016. The Tribunal has dealt with those grounds extensively and as
such, the appellant cannot, under S. 37 of the Act seek re-appreciation of
those grounds.
26. However, the appellant only seeking to urge two grounds, which have
been completely perversely dealt with by the Tribunal, as under :-
i. One of the grounds raised by the appellant to terminate the contract
was that there was negligible progress between 2012 to 2016 and
the total progress during this period was only 5.63%.
ii. The Tribunal dealt with the issue of failure to carry out obligations.
However, the Tribunal recorded the progress made during


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:18.06.2026
12:35:37
FAO (OS) (COMM) 206/2023 Page 35 of 93

September 2010 to March 2012 and on this basis rejects this plea.
The stand of Appellant was, on the contrary, to the effect that there
was negligible progress from 2012 to 2016, which has not been
gone into at all by the Tribunal, thus ignoring material plea which
goes to the root of the matter.
iii. That the appellant filed multiple documents in this regard, which
were completely ignored by the Tribunal:
a) Last Interim Payment Certificate (IPC) was raised by
respondent was IPC-73 raised for the month of April 2014. No
further IPCs were ever raised by the respondent.

b) Manpower status from MPRs reflecting that Key
Professional staff was not available between 31.01.2014 – May
2015.
c) In the minutes of the meeting dated 16.12.2014, it is
noted that in last one year only 2% work has been done.
d) In Show Cause Notice dated 07.01.2016, it is asserted
that during 2012-13 only 2.05% work has been done, and during
2013-14 only 0.93% work has been done. It is further stated that
since January 2015 only 0.492% work has been done.
e) The Engineer’s letter dated 10.02.2016 states in para (a)
and (b) that in the last 4 years, only 5.63% work has been done.
f) Termination letter dated 14.03.2016 state that only
5.63% work has been done since 2012.
g) In reply to the show-cause notice dated 18.01.2016, the
respondent attempts to justify the less work by stating that work


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:18.06.2026
12:35:37
FAO (OS) (COMM) 206/2023 Page 36 of 93

got affected by various events, including:
i. Variation works to the extent of 14.1134% requiring
more time.
ii. law and order problem resulting into delay of 570 days
iii. Bandh and strikes resulting into loss of 670 days.
iv. Between period 20.09.2010 to 31.03.2012, work stopped
due to deterioration of law and order and contractor had
to demobilize.
v. Key managerial persons had to leave due to various
problems such as extortion, law and order etc.

vi. Out of 18 bridges, only 7 bridges completed. 2 major
bridges remain untouched. Termination notice dated
14.03.2016.
vii. The Engineer vide letter dated 20.01.2016 in reply to the
contractor reply to the show-cause notice dated
20.01.2016 stated that the contractor has not raised RFI
(Request for work) since last one year.

SUBMISSIONS ON BEHALF OF THE RESPONDENT
27. Mr. C. Mohan Rao, learned Senior Advocate for the respondent
submitted that the claimant had made claims 1 to 21 before the Tribunal
including interest and cost of arbitration. The claimant did not press for
claim No. 2. The Tribunal dismissed the claim Nos. 12, 13, 15, 16 & 21 and
allowed the claim Nos. 1, 3 to 11, 14, and 17 to 20. He also submitted that
the appellant had confined its arguments before the learned Single Judge for
the claim Nos. 5, 6, 8, 10, 14 & 19 and the learned Single Judge set aside the


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:18.06.2026
12:35:37
FAO (OS) (COMM) 206/2023 Page 37 of 93

award in respect of claim Nos. 5, 10, 14 & 19 and dismissed the challenge in
respect of claim Nos. 6 & 8.
28. He submitted that the appellant in the present appeal has contended
that the giving up of certain claims before learned Single Judge was without
any authority and that no such instructions were given by the appellant. The
appellant, as such sought to include those claims which were not decided by
the learned Single Judge in the present appeal. He submitted that this Court
has allowed the request of the appellant to include the claims which were not
decided by the learned Single Judge, subject to depositing ₹ 10 lakh as costs.
However, the appellant filed an affidavit giving up claims 3, 4, 17 and 18, in
the present appeal. Thus the present appeal is now confined to the Claim
Nos. 1, 6, 7, 8, 9 and 11.
29. Mr. Rao submitted that the findings in the impugned order of the
learned Single Judge as well as the Award are pure findings of fact and thus
are not amenable for interference under Section 34 or 37 of the Act. The
findings reflect no illegality, much less any perversity. A perusal of the
findings of the Tribunal would demonstrate that the Tribunal has considered
all the facts and circumstances relevant to the issues and the
contemporaneous correspondences exchanged between the parties and the
other evidence filed by the parties. It is a well-settled that courts while
exercising jurisdiction under section 34/37 of the Act do not to sit in appeal
over the findings of the Tribunal or re-appreciate evidence as an Appellate
Court. In support of this submission he has relied on the following
judgment. In support of his submission he has relied on MMTC Ltd. v.
Vedanta Ltd (SC; CA 1862 of 2014; 18.02.2019) & OPG Power


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:18.06.2026
12:35:37
FAO (OS) (COMM) 206/2023 Page 38 of 93

Generation Pvt. Ltd. v. ENEXIO Power Cooling Solutions India Pvt. Ltd .
30. Mr. Rao on the submission of the appellant on delay, EOT and
Termination of Contract submitted that, the stipulated dates of start and
completion are 06.10.2005 and 05.04.2008. The appellant illegally
terminated the contract on 31.03.2016, w.e.f. 29 .03.2016. The appellant had
commenced its arguments with a patently false statement that the entire land
for 30 Kms was handed over on 11.12.2005.
31. He submitted that, it is evident from the Monthly Progress Report
(MPR) of March 2016 that the appellant failed to remove encumbrances
such as trees, electric poles, transformers and 20 houses even as on the date
of termination of the contract in March 2016. This is also clear from the
balance work contract document in which removal of encumbrances like
tree cutting, utility shifting, relocation of religious places, wells tanks etc.
are included in the scope of the balance work, which clearly indicates that
the encumbrances were in existence even at the time of executing the
balance work.
32. He submitted that the Engineer categorically stated that the appellant
failed in handing over of possession as per the stipulation of the contract and
that the delay in handing over of the site was governing delay and that any
other delays whatsoever occurred would only overlap. This was emphasized
by the respondent/claimant during arguments and written arguments before
the Tribunal, which also form part of the award. The recommendation of the
Engineer was relied upon by this respondent in its arguments before the
Tribunal.


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:18.06.2026
12:35:37
FAO (OS) (COMM) 206/2023 Page 39 of 93

33. He submitted that the Tribunal after considering the material on
record held that the appellant is mainly responsible for the delay as held in
Paragraph No. 12.3.2.5 (ii) of the impugned award. He also submitted that,
as a result of abnormal delay in handing over the site, the Engineer
recommended EOTs seven times, the last being up to 24.09.2014. However,
the appellant had not granted any EOTs beyond 06.03.2011 till termination
of the contract on 31.03.2016. As a result of not granting any EOTs beyond
06.03.2011, the respondent had executed the work from 06.03.2011 to
31.03.2016 without there being any time granted by the appellant.
34. He submitted that the Tribunal after considering this aspect has in
Paragraph 12.3.2.3 of the Award held that the Employer also did not take
any further action at any stage for grant of extension of time to the
contractor till the process of termination was initiated. As no eligible EOT
was granted, time ceased to be the essence of the contract and time was set
at large.
35. According to him, the Tribunal has dealt with the aspect of EOTs and
termination of the contract elaborately and held that not approving EOTs
despite recommendation of the Engineer is illegal. The Tribunal also gave
elaborate reasons in support of its findings that the termination of contract is
illegal in paragraph No. 12.3.2. 7 of the impugned award. It is clear that the
findings of the Tribunal are based on the record and the same are neither
perverse nor illegal.
36. He submitted that under Clause 63.3 of COPA read with Clause 63.2
of GCC and Clause 1.5 of GCC, the Engineer is under obligation to


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:18.06.2026
12:35:37
FAO (OS) (COMM) 206/2023 Page 40 of 93

determine and certify the amount earned or accrued to the contractor as on
the date of termination, ex parte or by or after reference to parties, without
any undue delay. This obligation cast on the Engineer was not discharged.
37. As per Clause 63.2, the Engineer was under obligation to determine
the value of the work executed by the claimant ex-parte after investigation
or enquires. The appellant in its termination notice dated 14.03.2016 had
directed the Engineer to determine and certify the amount accrued to the
claimant, under Clause 63.2 of the contract. The appellant had also issued
reminders to the Engineer for determination of the amount vide letters dated
02.04.2016, 13.04.2016 & 22.04.2016. The Engineer vide letter dated
11.05.2016 had stated that the measurement and valuation of the terminated
contract is being done by them. However, no such certificate was issued and
no such valuation as contemplated under Clause 63.2/63.3 was placed on
record before the Tribunal by the appellant. Therefore, the objection of the
appellant that the claimant did not attend the joint inspection was not
correct, the claimant had attended the site for joint inspection; however, the
Engineer did not attend the site for joint inspection.
38. Mr. Rao submitted that the objection of the appellant that the claimant
did not file IPCs is also without any basis. Clause 63.2 empowers the
Engineer to take ex-parte measurements and not the respondent/claimant. It
was the duty of the Engineer to determine the value of work as on the date
of termination of the Contract. As such there is no such liability on the
respondent/claimant to file any IPCs or the contemporary documents under
Clause 53 .4 GCC by the claimant. He also submitted that the appellant had
contended before the Tribunal that the valuation under Clause 63.2 is under


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:18.06.2026
12:35:37
FAO (OS) (COMM) 206/2023 Page 41 of 93

progress, which is clear from the Award.
39. He submitted that, in absence of mandatory determination and
certificate by the Engineer as required under Clause 63.2 (GCC), the
respondent/claimant could not make any claim for the value of work
executed under BOQ items as on the date of termination. The
respondent/claimant has made original claim only for the extra work done
and variations which were approved by the Engineer. The appellant had
contended that page 187 of the Statement of Claim was not legible, it is
submitted that the said document was a letter issued by the Engineer
addressed to the appellant. The appellant itself has filed the list of variations
approved by it.
40. Mr. Rao submitted that the appellant filed certain documents before
the Tribunal during 2018, indicating the BOQ item wise balance quantities.
In the said document, the Engineer had determined the balance work
quantities for every BOQ item, precisely to two decimals and determined the
amount based on the quoted rates of the claimant. He also submitted that
there is no provision in the Contract Agreement for execution of the balance
work at the risk and cost of the respondent/claimant and the Engineer was
under obligation to determine the amount of work not completed by the
claimant at BOQ rates.
41. He submitted that, based on the documents filed by the appellant, the
respondent/claimant on 24.08.2018 filed an application for amendment of
the Claim No. 1 under Section 23(3) of the Act by including the value of the
work executed under BOQ items as on the date of termination. The claimant


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:18.06.2026
12:35:37
FAO (OS) (COMM) 206/2023 Page 42 of 93

had also filed amended Statement of Claim in respect of Claim No. 1 on
24.08.2018.
42. He submitted that the appellant was afforded sufficient opportunity by
the Tribunal to file amended Statement of Defence to the amended claim
No.1. The Tribunal allowed ten days’ time to the appellant for filing
amended Statement of Defence in respect of claim No. 1, further time up to
24.12.2018 was allowed (page 2159). On 07.01.2019, the Tribunal sent a
confirmation mail to the parties stating that no response is received from the
appellant. The amendment was made by the respondent/claimant on
24.08.2018, and till 07.01.2019, the appellant despite sufficient
opportunities did not file amended Statement of Defence in respect of one
Item i.e., Claim No. 1. He also submitted that, it is the obligation of the
Engineer to determine the value of the work done by the claimant as on the
date of termination, which the appellant did not place on record. The
amended claim was allowed after recording detailed reasons on amendment
of the claim and time given to the appellant for filing the amended Statement
of Defence.
43. Mr. Rao submitted that Claim No.6 was decided by the learned Single
Judge in favour of the respondent/claimant. The appellant instead of
showing how and why the findings of the learned Single Judge are incorrect,
made fresh objections raising disputed questions on merits for the first time,
which were not part of the Statement of Defence or the synopsis of oral
arguments filed nor the same were part of the challenge petition filed by the
appellant under Section 34 of the Act. The appellant has filed the particulars
of the availability of key personnel during the contract period from February


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:18.06.2026
12:35:37
FAO (OS) (COMM) 206/2023 Page 43 of 93

2006 to February 2016. In support of the claim, the respondent/claimant had
filed the books of accounts indicating the expenditure on overheads during
FY 2008-09 to FY 2015-16, duly certified by the Chartered Accountant. The
respondent/claimant had also relied on MoRTH Standard Data Book
indicating the overheads provision on highway works at 8% for roads and at
20% - 25% for bridges and the same was argued the respondent. Whereas,
the appellant for the first time before this Court in the present appeal
contended that the respondent has failed to comply with the conditions under
Clause 53.4 GCC. The appellant had also filed several documents indicating
existence of key personnel for 10 years from 2006 to 2016, as such the
objection is not tenable.
44. He submitted that the respondent/claimant had made a claim at 7% in
respect of road work as well as bridge works, which is much lower than
MoRTH provision and having maintained the establishment for 125 months
as against the stipulated time period of 30 months, the claimant has made a
claim for loss of overheads during the extended period of 95 months only
and no claim is made for the loss of overheads during the stipulated period
of contract (30 months). Once factual basis is made that a contractor is
entitled for overhead charges for the prolongation period Hudson Formula is
applicable.
45. He submitted that the delay in handing over of the site by the
appellant, was governing delay and hence the question of concurrent delay
does not arise. However, the Tribunal allowed the claim for loss of
overheads only for 69 months i.e. the EOT recommended by the Engineer,
as against 95 months claimed and proved by the claimant. In this regard the


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:18.06.2026
12:35:37
FAO (OS) (COMM) 206/2023 Page 44 of 93

Tribunal held that the appellant was responsible for prolongation cost to the
claimant for the above period of 77 months less 10% assessed as failure on
part of the claimant in mitigating losses, that is for the period of69.3 months,
say 69 months only. Although the appellant has objected to applicability of
the Hudson Formula, the Tribunal did not agree with the contention of the
respondent as the basis of Hudson Formula has been held to be good by
various courts of the country. Accordingly, the Tribunal found it fair and
reasonable to award a sum of ₹ 35.15 crore to the claimant for the above
claim.
46. Mr. Rao has contested the legal authorities cited by the appellant in
the following manner:
a. Batliboi Environmental Engineers Limited v. HPCL : In tcase, the
claim includes loss of profit due to prolongation of the contract. The
objection was mainly to grant of loss of profit for the prolongation
period by applying Hudson Formula. In the present case, there is no
claim for loss of profit due to prolongation of the contract. The only
evidence filed before the Tribunal was calculations in the form of a
chart. No other justification was produced before the Tribunal.
b. Unibros v. All India Radio : this judgment is not applicable to the
present case, since in Unibros the claim for loss of overheads due to
prolongation of the contract was rejected by the Tribunal itself. In
Unibros, the claim for loss of profit due to prolongation of the
contract was awarded. The Supreme Court observed that "Hudson's
formula, while attained acceptability and is well understood in trade,
does not, however, apply in a vacuum". In the present case, as pointed


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:18.06.2026
12:35:37
FAO (OS) (COMM) 206/2023 Page 45 of 93

out voluminous evidence is placed on record in support of the claim
for loss of overheads due to prolongation of contract.
c. Edifice Developers and Project Engineers Ltd. v. Essar Projects
(India) Ltd. (Bombay High Court; Appeal No. 11 of 2012; Arb. Pet.
313 of 2007; decided on 03.01.2013): Here, no evidence was filed
before Tribunal. The claim was allowed only on the basis of Hudson's
formula. The Supreme Court held that the award of the claim is on the
misconceived basis that the Hudson's Formula must be applied despite
the absence of evidence.
iv. Essar procurement Service Ltd. v. Paramount Constructions (Bombay
High Court; Section 34 petition): The Court held that the respondent
had not produced the books of account showing the expenditure
incurred on overhead. The respondent/ claimant in the present case had
filed the books of accounts duly certified by the Chartered Accountant;
the appellant itself has filed evidence of existence of establishment
from Feb 2006 to Feb 2016.
47. Mr Rao relied on the judgment of this Court, in the case of NHAI v.
Rayalaseema Expressway Pvt Ltd. (O.M.P. (COMM) 344/2019) ; decided
on 24.09.2019), to support the relevance of the Standard Data Book of
MoRTH. He has also relied on the judgment of this Court in the case of
NHAI v. BEL TBL JV., FAO(OS) 254/2016.
48. With regard to Claim No. 7, he stated that for increase in rate in
executing the work due to extra stay on work site. He submitted that this
claim is also on account of prolongation of the contract. The Engineer


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:18.06.2026
12:35:37
FAO (OS) (COMM) 206/2023 Page 46 of 93

recommended EOT under Clause 42.2 (a) due to default of the appellant in
handing over of the site for eight years. However, the Engineer did not
determine the cost payable to the claimant under Clause 42.2 (b), for which
the present claim is made under Clause 42.2 (b).
49. It is submitted that as a result of delay in handing over of the site that
too in bits and pieces, cost of execution of works increased and had made a
claim for 10% additional cost for the work executed during prolongation
period beyond the original date of completion. Detailed calculations based
on the IPC's in support of the claim. After considering the contentions raised
by the appellant, the Tribunal allowed the claim by awarding 5% additional
cost for the work executed during the prolongation period. He also
submitted that the appellant has awarded the balance work of ₹ 51.52 crore
to Simplex Infrastructure Limited for an amount of ₹ 129.18 crore i.e., more
than 150% above the estimated cost, which clearly shows that the 5%
additional cost allowed by the Tribunal on the amount of work executed
during the prolongation period of the contract is very much reasonable and
the same is neither perverse nor illegal and the objections are liable to be
dismissed.
50. With regard to Claim No. 8 for expenses incurred towards
prolongation cost as a result of working in the extended period of the
contract, Mr. Rao submitted that;-
i. This claim is decided by the learned Single Judge in favor of the
respondent/claimant. The appellant instead of showing how and
why the findings of the learned Single Judge are incorrect made
fresh objections raising disputed questions of facts for the first time.


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:18.06.2026
12:35:37
FAO (OS) (COMM) 206/2023 Page 47 of 93

He also submitted that the award has held that the contention of the
NHAI as regards the deployment of machinery does not stand in
view of the fact that the NHAI itself has filed the details of the
machinery at site vide its document No. RD-7. Thus the machinery
as required for the work was available till September 2015,
although, there is no specific proof of each and every machine
being available at the time of stipulated date of completion of work.
Therefore, the Tribunal was inclined to believe that the said
machinery was available at the site since the time originally
scheduled date of completion. Similarly, the availability of
machinery at site up to March 2016 and April 2016 has also been
evidenced by the appellant vide its document No. RD-11.
ii. The existence of plant, machinery and equipment was proved on the
basis of the documents filed by the appellant before the Tribunal,
viz; MPRs for the period March 2006 to April 2016. The
availability of equipment at site is also proved from the surprise
check conducted by the appellant itself on 14.09.2015 was filed by
the appellant before the Tribunal. The availability of equipment as
on the date of stipulated date of completion was also proved by the
claimant from the MPR for the month of March 2008. The
availability of equipment after termination of the contract
(31.03.2016) was also proved from the MPRs for the months of
March and April 2016 filed by the appellant. Therefore, the amount
initially claimed by the respondent/claimant was for
₹63,37,75,829/-. Subsequently a clerical error was noticed to the


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:18.06.2026
12:35:37
FAO (OS) (COMM) 206/2023 Page 48 of 93

effect that for calculating the total cost, initial period of
prolongation of 05.05.2008 to 02.06.2011 was found to be missed
out. This can be clearly seen from the document CA-5 and the
amended CA-5. The error was rectified by an amendment
application of Claim No. 8 by the claimant under Section 23(3) of
the Act. The amended claim amount was ₹ 102,82,31,205/- filed on
22.02.2018.
th
51. In the 44 hearing of the Tribunal held on 16.06.2018, the NHAI had
stated that it does not want to file any reply to the amendment application
and the amendment was allowed by the Tribunal on the same day i.e., on
16.06.2018.
52. He submitted that the claim is made based on the usage charges of
MoRTH Standard Data Book; the claim is made adopting 2001 usage rates
of MoRTH Standard Data Book. It did not apply any cost index on the 2001
rates to make the same applicable for the claim period of 2008-2016.
Further, it has claimed only 50% of the amount so arrived. He also
submitted that, based on the documents filed by the NHAI, the machinery as
required were available at site. However, by making reference to its finding
in respect of Claim No. 6, the Tribunal allowed this Claim also only for 69
months as against the actual claim for 92 months of prolongation period. In
support of the above claim, Mr. Rao placed reliance on the judgment of this
Court NHAI v. DIC NCC N; FAO(OS) (COMM) 20/2019 , wherein this
Court has upheld the similar claims based on the usage rates of the MoRTH.
53. He submitted that the NHAI had raised an objection for the first time
before this Court, alleging that the amount claimed is more than the cost of


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:18.06.2026
12:35:37
FAO (OS) (COMM) 206/2023 Page 49 of 93

the equipment by referring to a judgment of Supreme Court in Samantary
Construction Pvt Ltd (supra) . He also submitted that the claim in the said
judgment was due to seizure of the equipment after termination of the
contract.
54. According to Mr. Rao, in case of seizure (confiscation), depreciated
value should be the maximum claim as in case of Claim No. 9 in the present
case. He submitted that if equipment is returned within a short period, claim
for hire charges is permissible, limited to depreciated value as on the date of
seizure. There is no reference to cost of equipment in the above judgment,
only value of the equipment was referred. The NHAI’s contention that the
amount of hire charges should not be more than the original cost of the
equipment is without any basis, particularly when the claimant incurred
expenditure at site for 125 months as against the stipulated period of 30
months. In the present case, the claim itself is "Claim for expenses incurred
towards prolongation cost as a result of working in the extended period of
contract". The expenses incurred during the prolongation period are not
dependent on the cost of equipment alone. The equipment with 12 years life
was meant for execution of 4 such projects of 30 months each, whereas the
claimant could not even complete one project, further the equipment was
illegally confiscated.
55. He submitted the respondent suffered heavy losses on the account of
illegal confiscation. As the respondent has also paid huge interest on the
advances amounting to ₹ 43.64 crore to the appellant during the
prolongation period till the date of termination. This amount of interest was
enormous and is not dependent on the original cost of the equipment. He
also submitted that the respondent had incurred additional expenditure in


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:18.06.2026
12:35:37
FAO (OS) (COMM) 206/2023 Page 50 of 93

maintaining the machinery along with complete crew for operation and
maintenance for 125 months as against 30 months due to prolongation of the
contract, expenditure on spares and lubricants during the prolongation of the
contract which is clear from the material confiscated by the appellant after
termination of the contract. He contended that this is the first time the
appellant has alleged that the claim amount is more than the cost of
equipment.
56. Mr. Rao submitted that the appellant has raised another objection
before this Court for the first time that the MoRTH rates are not adopted by
the respondent for 12 out of 30 items. The said allegation is totally false and
misleading. These objections were not even raised in the present appeal and
are made for the first time in the written arguments. Neither such objection
was raised either before the Tribunal or before the learned Single Judge. He
also submitted that, except for one item i.e., PQC Paver which is German
made machinery; all other rates are taken from the MORTH Standard Data
Book. For PQC paver, the reasonable market rate for the relevant period has
been adopted. Where the capacity of the equipment did not match as in case
of generators of 7 different capacities, batching plant etc, the claimant had
adopted proportionate rates from the MORTH standard data book.
57. He submitted that the appellant had also taken another objection for
the first time in its written submissions i.e., the number of equipment
considered in CA-5 amended is more that the surprise checks document or
the March 2016 MPR, no such objection was raised. He submitted that at the
time of filing the claim, only the MPRs filed by the respondent were on
record. The NHAI filed the MPRs for the period February 2006 to April
2016 during the arbitration proceedings. Subsequent to filing of the MPRs


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:18.06.2026
12:35:37
FAO (OS) (COMM) 206/2023 Page 51 of 93

by the appellant, the respondent/claimant had filed quantification before the
Tribunal, by considering month wise availability the equipment for every
month, during the prolongation period which amounts to ₹ 141.7 Cr.
However, the respondent/claimant did not amend the Claim. This clearly
proves that the contention of the appellant raised for the first time in its
written submissions is contrary to the facts available on record. Even
though, respondent/claimant maintained the plant and equipment along with
complete establishment till the date of termination of the contract, the
Tribunal restricted the claim to 69 months.
58. With regard to Claim No.9: Claim for recovery of cost of confiscated
Machinery, Mr. Rao submitted that the appellant, in its Statement of
Defence and as in the petition under Section 34 of the Act, had stated that
confiscation of machinery is strictly in terms of the provisions of the
contract. However, there is no such provision for confiscation of plant,
machinery or material either in termination Clause 63 or otherwise
anywhere in the Contract Agreement.
59. As per Clause 63.l of COPA, the NHAI is under obligation to return
the plant, equipment etc. to the claimant. Despite being under the obligation
to return the plant, equipment etc., the NHAI did not even file the list of
inventory of the confiscated machinery, plant equipment and material before
the Tribunal. The appellant did not use any of the confiscated machinery for
execution of the balance work in sub-Clause 54.9 at page 138 of balance
work Contract document filed on 04. 10.2025.
60. Under the obligation to determine the value of the equipment,
material and temporary works as on the date of termination under Clause
63.2 of the Contract, the appellant in its termination notice dated 14.03.2016


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:18.06.2026
12:35:37
FAO (OS) (COMM) 206/2023 Page 52 of 93

directed the Engineer to determine the value of plant, equipment and
material at the time of termination of the contract. The appellant also issued
reminders to the Engineer for determination of the amount vide letters dated
02.04.2016, 13.04.2016 & 22.04.2016. The Engineer vide letter dated
11.05.2016 had stated that the measurement and valuation of the terminated
contract is being done by them. However, the appellant did not place on
record the Tribunal, any such valuation under Clause 63.2.
61. Mr. Rao submitted that, immediately after termination of the contract
on 31.03.2016, the claimant has made a claim for cost of confiscated
equipment vide letter dated 08.06.2016 addressed to the NHAI for
₹13,61,08,604/-. However, the NHAI neither denied nor disputed, having
confiscated the plant and equipment, the complete list of plant and
equipment was available with the NHAI. However, they had suppressed the
vital information required for deciding this claim.
62. He submitted that the appellant itself has filed list of major plant and
equipment as available at site after termination of the contract during March
and April 2016, including the details of invoices of the major plant and
equipment before the Tribunal. The Tribunal had taken into consideration all
the objections raised by the appellant held that, in light of the above it is
submitted that the award in respect of the Claim No. 9 is neither perverse
nor illegal and hence the objections of the appellant are liable to be
dismissed.
63. Mr. Rao submitted that, Claim No. 11; Claim for loss of profit on the
balance work due to illegal termination of the Contract by the appellant, the
claim is due to illegal termination of the contract and thereby preventing the
claimant from execution of the balance work and not due to prolongation of


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:18.06.2026
12:35:37
FAO (OS) (COMM) 206/2023 Page 53 of 93

the contract as sought to be contended by the appellant. Thus the references
to delay, prolongation period or Clause 42.2 are not relevant to this claim.
The Tribunal held that the termination is illegal hence the claimant is
entitled for claim for loss of profit for the balance work as on the date of
termination of the contract. In support of this, he has placed reliance on the
Supreme Court Judgment in Dwaraka Das v. State of M.P. [(1999) 3 SCC
500] & National Highways Authority of India v. BEL-ACC (JV) [2012
SCC OnLine Del 5530 .
64. He submitted that the standard data book of MoRTH indicates 10% as
contractor's profit, which substantiates the claim of the claimant for loss of
profit at the rate of 10%. The Tribunal had allowed the loss of profit after
deducting another 10% from the amount claimed on account of mitigation of
losses, i.e., the Tribunal has allowed only 9% as against 10% claimed, which
is neither perverse nor illegal and hence the objections in respect of this
claim are liable to be rejected.
65. Mr. Rao submitted that the Tribunal found that the appellant/Engineer
is guilty of not taking action/not discharging obligation in terms of the
contract. No effort was made by the appellant to bring the objections within
the scope of Section 34 and Section 37 of the Act. A mere perusal of the
award shows that the award is well reasoned and does not suffer from any
illegality or perversity, and is not maintainable. The present appeal is an
attempt to reopen issues of fact determined by the Tribunal.
66. He seek the present appeal under Section 37 of the Act needs to be
dismissed with costs.




Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:18.06.2026
12:35:37
FAO (OS) (COMM) 206/2023 Page 54 of 93

ANALYSIS AND CONCLUSION

67. Having heard the counsel for the parties, we note that in the impugned
order, the learned Single Judge states that the challenge in the petition under
Section 34 of the Act was confined to the conclusion drawn by the Tribunal
in respect of Claims No. 5, 6 and 8. The challenge to Claims No. 6 and 8
was rejected. Notice was only issued by the learned Single Judge with
regard to Claim No. 5. Later notice was also issued with regard to Claims
Nos. 10, 14 & 19. So, in effect, the learned Single Judge has decided the
petition with regard to Claims No. 5, 10, 14 & 19.
68. The conclusion drawn by learned Single Judge that the petition be
confined to Claims No. 5,10,14 & 19 was with the consent of the counsel for
the parties. The arbitral award dated 21.02.2019 was set aside in respect of
Claims No. 5, 10, 14 & 19.
69. This appeal under Section 37 of the Act has been filed with the
following prayers:-
“a) Allow the present appeal and set aside the arbitral
award dated 21.02.2019 passed by the Ld. AT in
respect of claims no. 6 and 8 and upheld by Impugned
judgment/Order dated 26.04.2023 passed by Ld. Single
Judge while exercising jurisdiction under Section 34 of
the Act.
b) Pass an order to set aside the claim nos. 1, 3, 4, 7,
9, 11, 17, 18, and 20 allowed by the Ld. AT in the
award dated 21.02.2019 and have not been
adjudicated on merits by the Ld. Single Judge while
exercising jurisdiction under Section 34 of the Act.
c) Pass such other order or orders as tis Hon'ble Court
may deem fit and proper in the facts and circumstances
of the present case;”



Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:18.06.2026
12:35:37
FAO (OS) (COMM) 206/2023 Page 55 of 93

70. However, during the course of arguments, the learned counsel for the
appellant stated that the appellant is confining its challenge in this appeal to
Claims No. 1, 6, 7, 8, 9 & 11. Accordingly, we have heard the counsel for
the parties on the said claims.
71. At the outset, we find it necessary to state the scope of judicial review
available to courts under Section 34 and Section 37 of the Act. In Somdatt
Builders NCC-NEC v. National Highways Authority of India; 2025 INSC
113 , the Supreme Court has held as under:
“36. In MMTC Ltd. Vs. Vedanta Ltd., this Court held that as far
as Section 34 is concerned, the position is well settled that the
court does not sit in appeal over an arbitral award and may
interfere on merits only on the limited ground provided under
Section 34(2)(b)(ii) i.e. if the award is against the public policy
of India. Even then, the interference would not entail a review
on the merits of the dispute but would be limited to situations
where the findings of the arbitrator are arbitrary, capricious or
perverse or when the conscience of the court is shocked or
when the illegality is not trivial but goes to the root of the
matter. An arbitral award may not be interfered with if the view
taken by the arbitrator is a possible view based on facts. As far
as interference with an order made under Section 34 by the
court under Section 37 is concerned, it has been held that such
interference under Section 37 cannot travel beyond the
restrictions laid down under Section 34. In other words, the
court cannot undertake an independent assessment of the
merits of the award and must only ascertain that the exercise of
power by the court under Section 34 has not exceeded the scope
of the provision.
…
39. In Reliance Infrastructure Ltd. (supra), this Court referring
to one of its earlier decisions in UHL Power Company Ltd. Vs.
State of Himachal Pradesh13, held that scope of interference
under Section 37 is all the more circumscribed keeping in view
the limited scope of interference with an arbitral award under
Section 34 of the 1996 Act. As it is, the jurisdiction conferred


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:18.06.2026
12:35:37
FAO (OS) (COMM) 206/2023 Page 56 of 93

on courts under Section 34 of the 1996 Act is fairly narrow.
Therefore, when it comes to scope of an appeal under Section
37 of the 1996 Act, jurisdiction of the appellate court in
examining an order passed under Section 34, either setting
aside or refusing to set aside an arbitral award, is all the more
circumscribed.
40. Again in M/s Larsen Air Conditioning and Refrigeration
Company (supra), this Court reiterated the position that
Section 37 of the 1996 Act grants narrower scope to the
appellate court to review the findings in an arbitral award if it
has been upheld or substantially upheld under Section 34.
42. As already discussed above, the Arbitral Tribunal had
interpreted Clause 51 in a reasonable manner based on the
evidence on record. This interpretation was affirmed by the
learned Single Judge exercising jurisdiction under Section 34
of the 1996 Act. Therefore, Division Bench of the High Court
was not at all justified in setting aside the arbitral award
exercising extremely limited jurisdiction under Section 37 of the
1996 Act by merely using expressions like ‘opposed to the
public policy of India’, ‘patent illegality’ and ‘shocking the
conscience of the court’. As reiterated by this Court in Reliance
Infrastructure Ltd. (supra), it is necessary to remind the courts
that a great deal of restraint is required to be shown while
examining the validity of an arbitral award when such an
award has been upheld, wholly or substantially, under Section
34 of the 1996 Act. Frequent interference with arbitral awards
would defeat the very purpose of the 1996 Act.”

72. As seen from the above, the scope for interference with an arbitral
award under both Section 34 and Section 37 of the Act is extremely narrow.
It is only if the findings of the arbitrator are arbitrary, capricious or perverse
or when the conscience of the court is shocked or when the illegality is not
trivial but goes to the root of the matter, that the Court shall choose to
interfere. We shall examine the contentions put forth by the parties within
the contours of the law as observed above.



Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:18.06.2026
12:35:37
FAO (OS) (COMM) 206/2023 Page 57 of 93

TERMINATION OF THE CONTRACT
73. First, we shall deal with the issue with regard to termination of the
contract. The appellant has challenged the finding of the Tribunal that the
termination of the contract is illegal, by stating that one of the grounds
raised by the appellant to terminate the contract was that there was
negligible progress in work between the years 2012 and 2016 inasmuch as
the total progress during this period was only 5.63%. Though the Tribunal
dealt with the issue of failure to carry out the obligations and recorded the
progress made during the period between September 2010 and March 2012,
it did not deal with the contention of the appellant that there was negligible
progress between the years 2012 and 2016. This, according to Mr Mittal, is a
material plea which goes to the root of the matter. He has submitted that the
following aspects were ignored by the Tribunal:
“1) Last Interim Payment Certificate (IPC) was raised by
respondent was IPC-73 raised for the month of April 2014.
No further IPCs were ever raised by the respondent., (Pg.
4867- 4868, pdf pg. 4875-4876 of pleading, vol-1).
2) Page 3642 – 3657, pdf pg. 3650-3665 of pleading, vol-1
– Manpower status from MPRs reflecting that Key
Professional staff was not available between 31.01.2014 –
May 2015.
3) Page 3045, pdf pg. 3053 of pleading, vol-1 - In MoM
dated 16.12.2014, it is noted that in last one year only 2%
work has been done.
4) Page 3173, pdf pg. 3181 of pleading, vol-1 - In Show
Cause Notice dated 07.01.2016, at para (d) page 3176, it
is asserted that during 2012- 13 only 2.05% work has been
done, and during 2013-14 only 0.93% work has been
done. It is further stated in para (m) on page 3178 that
since January 2015 only 0.492% work has been done.


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:18.06.2026
12:35:37
FAO (OS) (COMM) 206/2023 Page 58 of 93

5) Page 3224, pdf pg. 3232 of pleading, vol-1 – IE Letter
dated 10.02.2016 states in para (a) and (b) that in the last
4 years, only 5.63% work has been done.
6) Page 2623/ 2626, pdf pg. 2631/2634 of pleading, vol-1
– Termination letter dated 14.03.2016 in Para (f) avers
that only 5.63% work has been done since 2012.
7) Page 3189, pdf pg. 3197 of pleading, vol-1 – In reply to
SCN dated 18.01.2016, the respondent attempts to justify
the less work by stating that work got affected by various
events, including:
a) Para 10- page 3191, pdf pg. 3197 of pleading, vol-1-
variation works to the extent of 14.1134% requiring more
time.
b) Para 11 – page 3192, pdf pg. 3200 of pleading, vol-1 –
law and order problem resulting into delay of 570 days.
c) Bandh and strikes resulting into loss of 670 days – Para
12/ page 3194, pdf pg. 3202 of pleading, vol-1
d) Para 4- page 3197, pdf pg. 3205 of pleading, vol-1 –
period between 20.09.2010 to 31.03.2012 – work stopped
due to deterioration of law and order and contractor had
to demobilize. e) Para j -page 3198, pdf pg. 3206 of
pleading, vol-1- Key managerial persons had to leave due
to various problems such as extortion, law and order etc.
8) Out of 18 bridges, only 7 bridges completed. 2 major
bridges remain untouched. Termination notice dated
14.03.2016, Para (b), pg. 2623 @2626, pdf pg.
2631@2634 of pleading, vol-1.
9) The Engineer vide letter dated 20.01.2016 in reply to
the contractor reply to SCN dated 20.01.2016 stated that
the contractor has not raised RFI (Request for work) since
last one year. (Pg. 3205 @3207, pdf pg. 3217@3215 of
pleading, vol-1)”

74. The Tribunal had held that the termination of the contract by the
appellant is illegal, primarily for the reason that there was a considerable
delay on the part of the appellant in approving the EOTs. We note that the
appellant had approved EOTs no.1, 2 & 3 as recommended by the Engineer.


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:18.06.2026
12:35:37
FAO (OS) (COMM) 206/2023 Page 59 of 93

The Engineer vide letter dated 28.02.2008 had recommended EOT No.1, for
a time of 400 days, revising the completion date to 10.05.2009. The
Engineer again vide letter dated 06.05.2009 recommended EOT No.2, for a
time of 365 days, revising the completion date to 10.05.2010. Further, vide
letter dated 03.05.2010 the Engineer had recommended EOT No.3, for a
time of 300 days, revising the completion date to 06.03.2011. These three
EOTs were approved by the appellant, thereby bringing the approved
completion date to 06.03.2011.
75. Subsequently, the Engineer vide letter dated 03.03.2011 had
recommended extension for a period of 195 days, revising the completion
date as 17.09.2011. The Engineer vide letter dated 14.12.2012
recommended extension for a period of 14 months plus 25 days, changing
the date of completion to 15.01.2013. Subsequently, vide letter dated
14.05.2013, the Engineer recommended extension for 208 days revising the
date of completion as 11.08.2013. On 07.09.2013, the Engineer again
recommended an extension of 201 days, revising the completion date to
28.02.2014.
76. The Tribunal, noting the EOTs recommended by the Engineer, held as
under:-
“(iii) The contract stipulates under clause 2.1(v) of COPA
that the Engineer has to obtain prior approval of the
Employer before determining any Extension of Time under
Clause 44. When the Engineer makes a recommendation
for grant of EOTunder the above clause, the Employer has
only two options: (i) approve the proposal as
recommended or (ii) approve with changes giving reasons
for the same. As the Engineer is the entity specifically
appointed to be fully conversant with conditions al site and
administer the contract correctly, the question of the


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:18.06.2026
12:35:37
FAO (OS) (COMM) 206/2023 Page 60 of 93

Employer outrightly rejecting the recommendation of the
Engineer does not
arise. In any case, the decision of the Employer regarding
grant of EOT has to be conveyed to the Contractor within
a reasonable time so as to facilitate smooth
implementation and progress of the project. It is also
essential that when EOTis granted, a revised date of
completion is also fixed so that all parameters of the
contract can be adjusted accordingly.
(iv) It may be seen from the above table that the first three
EOTS amounting to 1065 days were granted by the
Employer based on the recommendation of the Engineer.
Thereafter the Engineer had recommended EOT for a
further period of 1292 days against the EOT applications
nos. 4, 5, 6 and 7, but there was no response from the
Employer. It is difficult to understand the inaction of the
Employer in this regard for a period of more than 32
years, which was in clear contravention of the provisions
of the contract. The Employer also did not take any further
action at any stage for grant of extension of time to the
Contractor till the process of termination was initiated. As
no eligible EOT was granted, time ceased to be the
essence of this contract and time was set at large.
(v) In para 3(iii) of the Minutes of the meeting with the
Minister of Road Transport & Highways held on
16.12.2014. (R-192, page 912 of RD-6) it is recorded as
follows: 'The contractor sought extension of time for
completion of the project upto March 2016. It was agreed
that the contractor should complete the project by
December 2015. Admissible extension of time as per-
recommendations of Engineer / RO may be granted with
escalation as per the contract. The Claimant requested for
further EOT up to 31.03.2016 for completing the work and
also submitted detailed programme for completion of
remaining work vide document No.C-64 dated 15.05.2015
(pages 518-560 of SOC). However, neither the Engineer
nor the Employer took any action for deciding and
granting the EOT as per clear directions given in the MoM
of the Minister's meeting, thus showing utter disregard and


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:18.06.2026
12:35:37
FAO (OS) (COMM) 206/2023 Page 61 of 93

dereliction of responsibility towards the interests of the
project. The Contractor was thus denied even the outside
chance of completing the project by December 2015.
(vi) The Respondent has argued that even though no
formal approval was given by the Employer, the EOT as
recommended by the Engineer should have been deemed
by the Contractor to have been granted. This is an entirely
fallacious and unacceptable argument. Without a properly
granted EOT in place, no contractor can proceed with the
work knowing that he is under constant threat of being
adversely affected by various punitive provisions of the
contract.
(vii) In view of the above, it is therefore evident that there
have been serious laxity and lapses on the part of the
Employer as well as the Engineer in the delays in
execution of the project and the Contractor alone is not to
blame for the ultimate fate of the project. Once it was
decided in December 2014 that the completion date of the
project should be extended to December 2015, and the
Contractor should be given admissible EOT, in all fairness
to the Contractor, he should have been intimated about the
EOT immediately. Thereafter, concerted efforts should
have been made by all the three parties concerned to
ensure substantial progress, if not completion of the
project in the remaining period of one year. This would
have yielded a far better result than that obtained by hasty
termination of the contract, which appears to have been
carried out without any such efforts being made.”

77. The Tribunal further examined the grounds raised by the appellant in
support of the termination of the contract, and held as under:
“12.3.2.4 The contract was terminated by the
Employer/Respondent vide letter dated 14.03.2016 (page
737, RD 5) stating that "the NHAI is satisfied that the
Contractor has committed breach of the contractual
provisions entitling the Employer/NHAI to terminate the
contract under Sub-Clause 63.1(a), (b) (ii), (d), (f) and (h)
of COPA"


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:18.06.2026
12:35:37
FAO (OS) (COMM) 206/2023 Page 62 of 93

The Clause 63.1 of COPA reads as follows:
63. Default of Contractor
The Employer shall be entitled to terminate the
contract if the Contractor:
(a) Fails to carry out any obligation under the
contract
(b) without reasonable excuse foils-
(ii) to proceed with the works, or any section thereof,
within 28 days after receiving notice pursuant to Sub-
Clause 46.1
(d) Abandons the work or otherwise plainly
demonstrates the intention not to continue
performance of his obligations under the contract
(f) Despite previous warning from Engineer, in
writing, is otherwise persistently or flagrantly
neglecting to comply with any of his obligations
under the contract.
(h) Has foiled to furnish the required securities or
extension thereof in terms of the contract.

12.3.2.5 In the light of all the material on record, each of
the five grounds which have been cited by the Employer
for terminating the contract are dealt with as follows:
A.63.1(a) Fails to carry out any obligation under the
contract
(1) It is not clearly specified as to which obligation under
the contract was not carried out by the Claimant. There is
no doubt that the main cause for the disruption of this
project was the refusal of the Employer to carry out its
obligation to grant EOTs as and when they became due.
Without these, the contractor was hamstrung in his efforts
to proceed with the works.
(ii) As regards slow progress, there were several reasons
for this which were clearly enumerated and recorded by
the Engineer while recommending the grant of EOTs. The
work under dispute involved 4-laning of the existing 2-lane
highway. Generally in a work of this nature, the new 2-
lanes are first built for the traffic to be diverted on them or
on the service road before strengthening of the existing 2-


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:18.06.2026
12:35:37
FAO (OS) (COMM) 206/2023 Page 63 of 93

lanes is undertaken. It is thus necessary that the land for
the new two lanes/service road is made available at the
appropriate stages. TheRespondent's statement that 45
meters width of Right of Way in the existing 2-lane road
was available at the start of work would not suffice. The
stipulated schedule for handing over of the site as given at
page 238 of Contract Agreement, was from 8 to 18 Kims at
the start, from 18 to 30 Kms during the next 6 months (for
main carriageway works) and from 0 to 8 Kms and from
18 to 30 Kins after 12 months. Thus the entire land in 30
Kms length was to be handed over on or before 12 months
after the date of commencement, whereas the process of
handing over of land to the Claimant continued upto 2013,
i.e. even after 8 years from date of commencement. Thus, it
is a fact that the main responsibility for delay in progress
of the work lay with the Respondent.
(iii) It is also pertinent to note that at the time of
termination, the Contractor had executed more than 70%
of the work. From document RD 20 filed by the
Respondent on 04.06.2018, giving value of work done
against various IPCs, it can be seen that between
September 2010 and March 2012 (IPCs 39 to 57), the
Contractor had executed work worth about 60 crores. This
indicates that given favourable circumstances the
Contractor was capable of executing on an average, more
than 3 crores of work per month.
(iv) Therefore, it cannot be stated with certainty that the
contractor failed to carry out any obligation under the
contract and hence this ground is not fully established.

B. 63.1 (b) without reasonable excuse fails-
to proceed with the works, or any section thereof, within
28 days after receiving notice pursuant 10 Sub-Clause
46.1
(i) In this connection, it is necessary to see the relevant
portion of Clause 46.1 ofGCC, which reads as follows:
If for any reason, which does not entitle the
Contractor to an extension of time, the rate of
progress of the works or any Section is at any tone, in


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:18.06.2026
12:35:37
FAO (OS) (COMM) 206/2023 Page 64 of 93

the opinion of the Engineer, too slow to comply with
the Time for Completion, the Engineer shall so notify
the Contractor who shall thereupon take such steps
as are necessary, subject to the consent of the
Engineer, to expedite progress, so as to comply with
the Time for Completion
(ii) From the above, it can be seen that any notice
pursuant to Clause46.1 can be issued to the Contractor
only if (a) he is not entitled to any extension of time and
(b) the Time for Completion is known against which the
slow rate of progress can be measured. As mentioned
earlier, in the present case, the Contractor was entitled to
large extensions of time which were recommended by the
Engineer but not granted by the Employer for more than
35 years. Because extensions of time were not being
granted, the revised Time for Completion was also not
fixed and hence, there was no way of measuring the rate of
progress to decide whether it was slow or not. As such,
notice pursuant to Sub-Clause 46.1 could not be issued to
the Corrector. Consequently Clause 63.1(b)(ii) is not
applicable at all and hence fails completely as a ground
for terminating the contract.
C. 63.1 (d) Abandons the work or otherwise plainly
demonstrates the intention not to continue performance of
his obligations under the contract
(1) The contention of the Respondent that the Claimant
had abandoned the site from 2012 and had demobilised its
resources, in not home cut by the scrutiny of the Monthly
Progress Reports (MPR) of September 2015 (R-295) page
1180 to 1190 (RD-7) and the MPRs of March 2015 and
April 2016 (Page 1642-1645, RD-11) These show that
substantial number of machines were available at site at
the time of termination of the contract taking into account
the balance work yet to be executed which was about 25%
of the current price. Similarly some key engineers and
other staff were available at site as can be seen from the
MPR of February, 2016 (Page 1364-1369, RD-9).
Therefore, the contention of the Respondent that the
Claimant had abandoned the site, is not factually correct.


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:18.06.2026
12:35:37
FAO (OS) (COMM) 206/2023 Page 65 of 93


(i) On the other hand, it is seen that the Engineer had
almost demobilised from the site. The Respondent itself
had requested to the Engineer to re-mobilise at the site
vide Minutes of Meeting dated 28.06.2015 (R-30), in pars
& of which it is recorded as follows:
“M/s Louis Burger Group Inc to mobile all key personnel
for supervision of the works in package AS-12 on priority.
Till then, on alternative arrangement may be made from
adjacent packages to supervise the works to avoid any
inconvenience for smoothexecution of work in Pkg No AS-
12. From this, it is clear that the Engineer had withdrawn
from the site and none of his personnel were available to
supervise the work.

(iii) The averment of the Claimant in Page 109 of the SoC
that the Engineer expressed his inability to supervise the
work vide letter dated 22.09.2014 is not specifically denied
by the Respondent, it appears that even the Respondent
was not giving serious attention to the administration of
the contract during this period.
(iv) As mentioned in para (ii) supra, after the Minister's
meeting in December 2014, the Contractor had shown
willingness to carry out the remainder of the work,
provided admissible EOT was granted to him and some
other conditions such as direct payment to suppliers and
release of pending payments were fulfilled by the MHAL
However, there was no response or any action from either
the Engineer or the Employer in this regard.
(v) in view of this, it would be incorrect to say that the
Claimant abandoned the work and showed intention to
continue performance of his obligations under the
contract. Therefore, this ground is also not tenable.
D. 63.1 (f)Despite previous warning from Engineer, in
writing, is otherwise persistently or flagrantly neglecting
to comply with any of his obligations under the contract.
(1) Against this Clause, the Respondent has failed to prove
what obligation under the contract was persistently or
flagrantly neglected by the Claimant. No specific instances


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:18.06.2026
12:35:37
FAO (OS) (COMM) 206/2023 Page 66 of 93

have been pointed out either in the Show Cause notice or
in the Letter of Termination regarding any persistent or
flagrant violation by the Claimant of any of the obligations
under the Contract. On the other hand, it is seen that it
was the Employer who persistently and flagrantly violated
the Conditions of Contract as laid down in the Contract
Agreement, by not granting legitimate EOT, as
recommended by the Engineer, to the Contractor over a
period of more than 35 years. This ground istherefore not
sustainable.
E. 63.1 (h) Has failed to furnish the required securities or
extension thereof in terms of the contract.
(1) Under this Clause, it is stated that the Bank Guarantee
for Performance Security submitted by the Claimant had
expired by 31.03.2015 and the Claimant did not furnish
required securities thereafter. The contention of the
Respondent is that it was the duty of the Claimant to
extend the bank guarantee for further period.

(ii) The Performance Security to be furnished by the
Contactor is stipulated in Clause 10.1 of COPA and the
amount is specified in Appendix to Bic as 10% of the
Contract Price. Further, Clause 102 of COPA states that
the Performance Security shall be valid for 365 days after
the expiry of the Defect Liability Period

(1) The Claimant's submission is that the Bank Guarantee
in question furnished by the Claimant could have been
encashed by the Respondent if the Claimant was not
willing to extend it. The

Respondent neither sought extension of Bank Guarantees
nor did it move to encash the BC. Also, the Claimant had
already kept the Bonk Guarantees alive for almost 10
years. The period up to which the Claimant could be asked
to extend the Performance Flack Guarantee, could have
been determined only after a future date of completion had
already been fixed.


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:18.06.2026
12:35:37
FAO (OS) (COMM) 206/2023 Page 67 of 93

(iv) It may be noted that since Extension of Time
applications were pending before the Employer and not
granted for many years and the question of DLP did not
arise, it was not possible to define the period up to which
the Bank Guarantees were to be extended In any event. nil
other Bark. Guarantees were encashed by the Employer in
January 2016 and hence, at the time of termination of the
contract in April, 2016, the question of renewal of Bark
Guarantee for Performance Security was of no relevance
at all. In view of the above, mis ground is non-existent.

12.3.2.6 (i) Apart from the above, the letter of Termination
suffers from the serious infirmity that it has not been
signed by the authorised signatory as required under the
contract. As pointed by the Claimant. The termination of
the contract under Clause 631 OCC can be done only by
the Employer, who is defined in the Contact Agreement is
the Chairman NHAI, for which the following two clauses
were cited: CT() () GCC-Employer" means the person
named as such in part 2 of these conditions and the legal
successors in title to such person, hot mot (except with the
content of the Contractor) any assignee of such person
page 42 of the Contract Agreement)
Cl. 1.1 (a) (1) COPA" The Employer is the Chairman
National Highways Authority of India or his successors in
office and assigns.(page 88 of the CA)
(ii) It is to be noted that the clause in COPA does not
replace the clause in GCC and hence both are applicable.
Taken together these clauses mean that in the present
contract, the Employer is the Chairman NHAI only, as no
consent of the Contractor has been taken for naming any
assigns. There is also nothing on record to show that any
official of the NHAT has been duly authorized to act as the
assignee of the Chairman.
(iii) The Show Cause Notice and Letter of Termination,
being most important documents having serious
implications on the fate of the contract, should have been
signed only by the Chairman or his assigns. However, they
have been signed by Shri R.K. Thakur, GM (Tech), NHAI,


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:18.06.2026
12:35:37
FAO (OS) (COMM) 206/2023 Page 68 of 93

who is not the authorized signatory and hence they are
invalid in terms of the contract.
(iv) The counter argument of the Respondent is that the
contract and other documents are being signed by various
officers of the NHAI with approval of the competent
authority. In fact, the Claimant himself has addressed
many letters to various officers of NHAI, other than the
Chairman and in one case even addressed the officer as
Employer. This implies that the Claimant has recognized
and accepted the fact without demur, that officers other
than the Chairman are also representatives and
signatories of NHAI who are fully authorized to sign
documents on behalf of the Employer. These arguments of
the Respondent do not carry much weight. The fact that the
Claimant has received letters from or addressed letters to
variousofficials of the NHAI does not change the
fundamental premise of the contract that the Employer is
the Chairman, NHAI or his assigns only. The Respondent
failed to produce any document to prove that Shri B.K.
Thakur GM (Tech), NHAI, has been made the assignee of
the Chairman. In any case, as per Cl. 1.1 (a) (i) GCC, this
could have been done only with the consent of the
Contractor, which has not been taken at any stage. The
letter of termination does not bear the signature of the
authorised signatory as required under the contract and
therefore has to be treated as invalid.
12.3.2.7- To view of what if stated above, the AT comes to
the conclusion that sufficient and inequitable grounds have
not been established by the Respondent for terminating the
contract and the Respondent itself cannot escape
responsibility for the abrupt closure of the project. The AT
therefore decides that the termination of the contract by
the Respondent vide its letter dated 24.03.2016 was illegal
and void.”

78. As seen from the above, the Tribunal after examining the aspect of
EOTs and the grounds of termination has held that the appellant cannot
escape the responsibility for the abrupt closure of the project and that it


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:18.06.2026
12:35:37
FAO (OS) (COMM) 206/2023 Page 69 of 93

failed to establish sufficient and irrefutable grounds to justify the
termination.
79. The Tribunal noted that as per the provisions of COPA, once the
Engineer makes a recommendation for grant of EOT, the employer, i.e. the
appellant, has only two choices – (i) to approve the proposal as
recommended; or (ii) to approve the proposal with changes giving reasons
for the same. In the present case, though the appellant approved the first
there EOTs, it failed to provide any response with regard to the EOTs
recommended after 06.03.2011. For more than 3.5 years, there was notable
inaction on the part of the appellant, till the termination of the contract. It
was observed that the appellant even failed to comply with the directions
given in the minutes of the meeting with the Minster of Road Transport and
Highways dated 16.12.2014, wherein the EOTs were directed to be granted
along with escalation. As such, the respondent was denied even an outside
chance of completing the project by December 2015.
80. Going by this, the Tribunal came to the conclusion that there has been
serious laxity and lapses on the part of the appellant as well as the Engineer,
and the respondent alone cannot be held liable for the ultimate fate of the
project. Once it was decided on 16.12.2024 that the completion of the
project should be extended to December 2015 and that the respondent
should be given all admissible EOTs, failure to do so, needs to be attributed
to the appellant.
81. Even the submission that has been raised before us on behalf of the
appellant that the respondent failed to renew its bank guarantee which had
expired on 01.04.2015, despite a mandatory requirement to extend the same
mentioned in the MOU dated 05.04.2015, has been dealt with by the


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:18.06.2026
12:35:37
FAO (OS) (COMM) 206/2023 Page 70 of 93

Tribunal in Ground E reproduced above. After noting that as per Clause 10.2
of COPA, the performance security shall be valid for 365 days after the
expiry of the DLP, the Tribunal held that since the EOTs were pending
before the appellant for years, the question of a DLP did not arise, and as
such it was not possible to define the period up to which the bank guarantees
were to be extended. Further, in any event, all the other bank guarantees
were encashed by the appellant in January 2016, and hence at the time of
termination of the contract in April 2016, the question of renewal of the
bank guarantee was of no relevance. Such being the conclusion of the
Tribunal based on a factual finding, we are not inclined to accept this
submission.

82. The Tribunal has dealt with in detail, the grounds raised by the
appellant for terminating the contract. That apart, it noted that the
termination suffers from an infirmity inasmuch as the letter of termination
was not signed by the authorised signatory as required under the contract,
i.e., the Chairman of the appellant-NHAI.
83. Upon a scrutiny of the above reasons recorded by the Tribunal, we
find no infirmity with the conclusion of the Tribunal. The appellant has
failed to put forth any justifiable reasons so as to warrant interference from
this Court, insofar as the issue of termination is concerned under Section 37
of the Act.
84. Now we shall examine the issues with regard to Claims no. 1, 6, 7, 8,
9 and 11 raised by the appellant.
CLAIM NO. 1
85. Claim No. 1 is relatable to unpaid work already executed including
escalation for an amount of ₹ 5,49,39,632/- and ₹ 3,50,47,342/-, totaling to


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:18.06.2026
12:35:37
FAO (OS) (COMM) 206/2023 Page 71 of 93

₹8,99,86,974/-, which was later amended to an amount of ₹ 31,41,35,273/-,
vide order of the Tribunal dated 03.12.2018.
86. The submission of Mr. Mittal can be summed up as under:-
a. The Tribunal has not provided opportunity of being heard to the
appellant on the amended claim no. 1 despite making specific request
in that regard.
b. He had relied upon an email dated 07.02.2019, which a is request
made by the counsel for the appellant to the Tribunal for hearing the
amended claim no. 1 on merits based on the documents available with
the Tribunal.

c. The observation of the Tribunal that the counsel for the appellant
stated there is “ nothing more to say ” is completely misconceived as
the said submission was made in respect of the amendment
application, and not on the merits of the amended claim no. 1.
d. Mere non-filing of reply by the appellant cannot be construed to mean
that the appellant has given up its right to argue the amended claim on
merits.
e. Even otherwise, the Tribunal erred in adopting a random formula to
arrive at the conclusion that unpaid work is 7.44%. Further, to award
an amount of ₹ 22,41,48,299/- and also an additional amount of
₹8,99,86,974/-, is nothing but duplication.
f. There is no evidence or proof in support of the amount claimed of
₹8,99,86,974/-.
g. The conclusion in the award is based on the assumption that since
balance work is shown as ₹ 51,51,93,861/-, which is about 23.59%,
therefore, the work done would have been 76.41%. However, as the


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:18.06.2026
12:35:37
FAO (OS) (COMM) 206/2023 Page 72 of 93

respondent had not produced any proof of work done in the form of
IPC, bills raised by it sub-contractor, proof of purchase of raw
material, the Tribunal could not have arrived at the conclusion.

87. First, we shall consider the submission of Mr. Mittal that the appellant
was not given any opportunity to make submissions on the merits of the
amended claim. The conclusion drawn by the Tribunal can be seen from
paragraphs A4, A5 and A6 at page no. 2150 of the paper-book, which we
reproduce as under:-
“A.4 The AT, after concluding its 76th meeting, beld
on 07.02.2019 at New Delhi, wrote to both the
Respondent and the Claimants, through its Presiding
Arbitrator, Sri Ravindra Kumar, vide e-Mail dated
07.02.2019, that the Award has been finalised.
A.5 After sending this e-mail, the AT received an e-
mail dated 07.02.2019 from Sri Rajiv Kapoor, counsel
for the Respondent on 08.02.2019, which stated that
the amended Claim no.1 had to be discussed again in
the light of amendments made. The Respondent also
admitted that, though time was given to him to file its
reply, however, he did not file any such reply, but
sought to argue the amended claim orally now, based
on the documents as available with the AT itself and
thus requested the AT to fix some date for the same. In
this connection, it is to mention that during the hearing
held on 12.11.2018 both the parties had concluded
arguments on the Amendment Application of the
Claimant and both the parties had declared that they
have nothing more to say. Even thereafter vide order
dated 03.12.2018 of the AT, the Respondent was
provided further opportunity to file amendments to its
Statement of Defence in view of application of
Claimant for amending Claim No. 1, if so considered
necessary by the Respondent, within 10 days from the
issue of the said order. No response, whatsoever, was


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:18.06.2026
12:35:37
FAO (OS) (COMM) 206/2023 Page 73 of 93

received from the Respondent. A further opportunity
was granted to the Respondent through the Minutes of
Internal Meeting dated 17.12.2018 to file the amended
SOD for which a further time of 7 days was allowed
and it was mentioned that in case no response was
received from the Respondent by 24.12.2018, it would
be presumed that the Respondent had nothing further
to say in this regard. No response was received from
the Respondent and this fact was made clear through
the minutes of internal meeting held on 07.01.2019.
A.6 In view of above, the said e-mail dated 07.02.2019
from the counsel of the Respondent cannot be
understood and appears to have been given with the
intention of delaying the Award. As such his request
cannot be allowed for a further hearing at this stage.
However, the AT has taken into consideration all the
facts before it and arguments made by both the parties
before publishing the Award.”

88. It is a matter of record that a reply to the application for amendment
was filed by the counsel for the appellant on 24.09.2018. Arguments were
advanced on 01.10.2018 and on 29.10.2018. The counsel for the appellant
commenced arguments against the amendment application on 31.10.2018,
followed by arguments on 10.11.2018. The application for amendment was
allowed vide order dated 03.12.2018. The conclusion drawn by the Tribunal
is the following:-
“Findings / Observations of the AT
The AT after considering all the written and oral
arguments put forward by both the parties, taking into
account various High Court and Supreme Court
Judgments cited and applying its mind to the matter,
observes as follows:
(i) Section 23(3) of the Act provides that either party
may amend or supplement his claim or defence during
the course of the arbitral proceedings, unless the


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:18.06.2026
12:35:37
FAO (OS) (COMM) 206/2023 Page 74 of 93

Arbitral Tribunal considers it inappropriate to allow
the amendment or supplement having regard to the
delay in making it.
(ii) Undoubtedly, the Amendment Application moved
by the Claimant has been delayed. However, it is seen
that, in general, Courts have been liberal in allowing
amendments during the course of proceedings provided
they do not cause injustice or prejudice to the other
side.
(iii) The Claimant is willing to accept the
quantification made by the Engineer of the work
carried out till termination of the contract. The
Claimant has taken a plea that it came to know about
the quantification of the work carried out by it till the
date of termination only on 04.06.2018, after receipt of
Document RD-20 from the Respondent. However, AT
notes from the document RD-4 dated 02.02.2018 filed
by the Respondent that the fact about work carried out
by it till the date of termination was already known to
him through the said document. However, the fact
remains that the Claimant failed to move this
application earlier which he could have done. Inspite
of the above position, the AT feels that it would not be
correct to deny the amendment application of the
Claimant in the interest of justice.
(iv) Considering all aspects, the AT comes to the
conclusion that the Amendment Application dated
24.08.2018 moved by the Claimant for amending
Claim No.1, under section 23(3) of the A&C Act needs
to be allowed.
(v) As the Claimant is responsible for delay in moving
the present Amendment Application, causing
inconvenience to AT as well as the Respondent, the AT
is constrained to impose costs of Rs. 30,000/- on the
Claimant
9 Decision of the AT
9.1 The Application for Amendment of Claim No.1
moved by the Claimant under Section 23(3) of the
Arbitration & Conciliation Act is hereby allowed.


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:18.06.2026
12:35:37
FAO (OS) (COMM) 206/2023 Page 75 of 93

9.2 The Respondent is directed to file amendments to
its Statement of Defence as may be considered
necessary by it within 10 days of the issue of this order.
The Claimant is also directed to file amendments to its
Rejoinder as may be considered necessary by it within
07 days of the receipt of amendments to its SOD by the
Respondent as referred to above. It may please be
noted that no extension of time whatsoever shall be
given to either party beyond the dates indicated
above.”

89. As seen from the above, the appellant was called upon to file an
amended Statement of Defence within 10 days, i.e., before 12.12.2018. It
appears that no such amended Statement of Defence was filed by the
appellant. A further opportunity was given to the appellant vide internal
minutes of the meeting dated 17.12.2018, whereby the counsel was granted
7 more days to file the amended Statement of Defence. It was mentioned
that if no response was received from the appellant by 24.12.2018, it would
be presumed that it had nothing further to add in this regard.
90. It appears that as there was no response from the appellant, on
07.02.2019, the Tribunal intimated the parties that it has finalised the award.
On 08.02.2019 the Tribunal received a request dated 07.02.2019 from the
counsel for the appellant to discuss the amended claim no. 1 afresh. We note
that no stand has been taken by the appellant as to why the amended
Statement of Defence was not filed between 03.12.2018 and 07.02.2019.
91. The case of the appellant is that despite receipt of the email dated
07.02.2019, the Tribunal did not grant the appellant an opportunity to argue
on the merits of the amended claim no. 1, which amounts to violation of the
principles of natural justice. The Tribunal in its award, stated that the
appellant was given enough opportunity for its response by way of the order


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:18.06.2026
12:35:37
FAO (OS) (COMM) 206/2023 Page 76 of 93

dated 03.12.2018, wherein it was stated that no extension of time
whatsoever will be provided to either of the parties. Still, an additional
opportunity was given to the vide minutes of the internal meeting dated
17.12.2018 to file a response by 24.12.2018. As the appellant failed to file
its amended Statement of Defence despite these opportunities, it cannot be
said there is a breach of the principles of natural justice, particularly, when
the appellant had almost two months to file its amended Statement of
Defence. Suffice it to state, paragraph A-5 of the arbitral award reproduced
above is self-speaking, and we agree with the same.
92. Now coming to the merits of the claim of the respondent for an
amount of ₹ 31,41,35,273/-, the Tribunal has awarded an amount of
₹31,27,08,206/-. The breakup of the same is:
1. ₹ 16,24,73,398/- under the head ‘for unpaid work already executed’;
2. ₹ 6,16,74,901.88 under the head ‘price adjustment’’ and
3. ₹ 8,99,86,974/-, for the extra work executed and on account of
variation as approved by the Engineer.
93. The plea of Mr. Mittal is primarily that no evidence was placed by the
respondent in respect of the amended claim for ₹ 31,41,35,273/-. Further, he
contended that awarding the amount of ₹ 8,99,86,974/-, is mere duplication
as the said amount is already part of ₹ 31,41,35,273/-.
94. The Tribunal has granted the amount on the premise that the total
value of work executed was 76.41%. This conclusion has been drawn
primarily based on the documents filed by the appellant herein, R-132 (RD-
4), R-134 and also RD-20.
95. Document R-132 ( at page 3167 of the appeal paperbook ) denotes that
the physical and financial progress till August 2015 is 69.976% and 71.33%,


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:18.06.2026
12:35:37
FAO (OS) (COMM) 206/2023 Page 77 of 93

respectively. Having taken such a position taken before the Tribunal by
filing the progress made in the work, the appellant cannot disown the same
to contend the completion of work was much less than 71.33%. Further, a
perusal of Document R-134 ( at page 3165 of the appeal paperbook ) filed by
the appellant, reveals that the total value of balance of work remaining was
₹51,51,93,861.11/-, which, as held by the Tribunal, works out in percentage
as 23.59%. If that be so, it follows logically that the amount of work actually
executed was 76.41%.
96. It has come on record as per paragraph A-2 of the award that the total
amount paid to the respondent up to April 2014 was ₹150,61,39,876/- as per
Document RD-20 filed by the appellant itself on 04.06.2018. Though we
could not find the said document on the record of this appeal, we note that it
is on a perusal of this document, that the Tribunal had held that the appellant
had paid a total amount of ₹150,61,39,876/- till IPC 73 for the period up to
April 2014, which according to the Tribunal works out as 68.97% of the
contract price. Hence, the Tribunal held that the value of the work executed
but not paid is 7.441% (76.41% - 68.97%) of the contract price of
₹218,37,82,239/- which comes to ₹16,24,73,398/-. The Tribunal further
worked out price adjustment as per Clause 70 of the contract to be 37.96%
relying upon the price adjustment for the previous year, and arrived at a
figure of ₹6,16,74,901.88/-. Therefore, it quantified the total balance amount
due for balance work done under BOQ items till termination of contract at
₹22,41,48,299/-. Further it allowed ₹8,99,86,974 on account of extra work
executed above BOQ rates, and on account of variations approved by the
Engineer.
97. Since Claim No.1 was not pressed during the hearing before the


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:18.06.2026
12:35:37
FAO (OS) (COMM) 206/2023 Page 78 of 93

learned Single Judge, it is only before this Court that the appellant had
effectively challenged the conclusion drawn by the Tribunal. As such, the
above averments made in the petition under Section 34 of the Act also
become relevant. We may reproduce the same as seen from paragraphs no.
56, 57, 58 and 59 of the petition before the learned Single Judge, as under:
“57. CLAIM N0.1: For unpaid work already executed
including escalation: Rs. 8,99,86,974/-. At the outset, it was
submitted that pursuant to termination Clause 63.2 of General
Conditions of Contact (GCC), valuation of executed works at
the date of Termination of the Contract is under process. The
unpaid amount, if any, would be considered pursuant to Sub-
Clause 63.3 of Condition of Particular Application (COPA).
58. The calculation as done by the Respondent were
emphatically denied and it was shown that there was no basis
shown of the figures as to where these figures have been taken
and no further document to establish that these figures are
correct, has been filed on record as shown on page 186. Thus,
these figures were disputed and the Respondent was put to
strict proof thereof. Page 187 was not legible at all and could
not be responded to. Thus, the claim being devoid of any basis
and evidence deserves to be dismissed on this count alone.
Therefore, the claim is not tenable.
59. Interestingly, it is to be noted that even this statement,
though it is denied, but an admission is carved out that the
Respondent has done no work after May 2015 as June is a
meagre work shown. However, this does not mean that the
Petitioner is admitting the figures in any case and neither can
the Petitioner be asked to verify the same nor to produce any
document to support the claim of the Respondent as it is for the
Respondent to build and prove its case and not the Petitioner.”

98. We must state here that in the appeal before us, the appellant has
contended that the finding of the Tribunal that the respondent/claimant has
completed 76.41% of the work is merely on surmises and conjectures,
inasmuch as there was no IPC, measurement book, invoices, vouchers etc. to


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:18.06.2026
12:35:37
FAO (OS) (COMM) 206/2023 Page 79 of 93

prove that the respondent had actually achieved 76.41% progress. It has also
been contended that there was no evidence on record to show that an amount
of ₹150.61 crore has been paid to the respondent. Further, it has been
submitted that the award is in contravention of Clause 63.4 of COPA which
inter alia contemplates that there should be contemporaneous record to
support any claim made.
99. Suffice it to state, the Tribunal has based its conclusion on the basis of
the documents filed by the appellant itself, i.e., R-132, R-134 and RD-20.
Though the appellant has raised a general contention that the award is not
based on any contemporaneous records, the existence of the said documents
has not been denied. In fact, no reference has been made to those documents
in the petition under Section 34 of the Act and also in the appeal under
consideration. We are of the view that the conclusion of the Tribunal based
on these three documents is a plausible one. Nothing has been placed by the
appellant before us to show that the conclusion drawn by the Tribunal is
patently illegal or against the public policy of India. Therefore, the challenge
to claim no. 1 is rejected.

CLAIM NO. 6
100. Claim No.6 is related to overheads due to overstay of the respondent
on site, including manpower, labour, equipment and resources for the
extended period from April 2008 to December 2015, which, according to the
respondent/claimant goes to 95 months. The said claim was made on
average overhead expenditure of 7% of the estimated value of work.
101. The Tribunal allowed the claim and awarded an amount of ₹35.15
crore in the following manner:


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:18.06.2026
12:35:37
FAO (OS) (COMM) 206/2023 Page 80 of 93

“F-1 The submissions made by the parties have already been
recorded hereinbefore and the same are not being repeated
here for the sake of brevity. Only salient issues are being
deliberated upon.
F-2 In the above claim, the Claimant has claimed overhead
charges during the prolongation period, considering that the
same were catered for by him @7% of estimated value of work.
Accordingly, he has claimed a sum of Rs. 48,40,71,752/- based
on Hudson formula, detailed as under:-
Loss due to overhead=0.07xRs. 218,37,82,339/30 months x 95
months = Rs. 48,40,71 ,752/-
F-3 The Respondent has denied the claim in its entirety.
F-4 In his Rejoinder, the Claimant has more or less reiterated
its contention as in its Statement of Claim.
F-5 The AT finds that the scheduled date of the completion of
work was 05.04.2005 and the work was terminated by the
Respondent on 29.03.2016. The Claimant appears to have
claimed prolongation for 95 months considering almost the
entire period between the scheduled date of completion and the
date of termination. The AT is not inclined to agree that the
Respondent alone can be held as responsible for the said delay.
However, the Respondent himself has mentioned in its
Statement of Defence on page 26 that the Engineer had
recommended consolidated extension up to 24.09.2014.
Although no decision was finally communicated by the
Respondent on the said recommendation of the Engineer, it
would be fair to consider that the Claimant was entitled for
extension at least up to 24.09.2014. The period between the
scheduled date of completion and 24.09.2014 works out to
approximately 77 months. AT holds that the Respondent was
responsible for the prolongation cost lo the Claimant for the
above period of 77 months less 10% assessed as failure on the
part of the Claimant in mitigating the losses, i.e. for a period of
69.3 months, say sixty nine months only. The rate of loss as
projected by the Claimant is considered reasonable. Although
the Respondent has objected to the applicability of the Hudson
formula, the AT did not agree with the contention of the
Respondent as the basis of Hudson formula has been held good
by various courts or the country. Accordingly, it would be fair


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:18.06.2026
12:35:37
FAO (OS) (COMM) 206/2023 Page 81 of 93

and reasonable to Award a sum of Rs. 35.15 crores to the
Claimant for the above claim, as worked out under:-
Loss due to overhead =0.07xRs.218,37,82,339/30 months x 69
months
= Rs.35,15,88,956/-
Say Rs. 35.15 crores
(Rupees Thirty Five Crores Fifteen Lakh only)
The revised figure of the claim for Rs. 53,78,51,738/- as
projected by the Claimant in its affidavit dated 07.02.2018 is
not being taken into consideration by the AT, while arriving at
the said figure of Rs.35.15 crores.”

102. The learned Single Judge has upheld the conclusion of the Tribunal,
as can be seen from paragraph 5 supra . The learned Single Judge was of the
view that the challenge made to the Award on Claim No.6 does not fall on
the limited grounds available to the appellant under Section 34 of the Act.
103. The challenge before us primarily rests on the following grounds:
“O. Ld. AT completely ignored the fact that the Engineer's
assessment of extension denied prolongation cost to the
contractor due to its concurrent delays on the part of the
contractor. The perusal of the award would show that there is
no discussion in respect of concurrent delays as stated by the
Engineer much less a finding on the same.
P. Ld. Single judge failed to appreciate that the award based on
Hudson Formula and no other evidence has been set aside for
lack of material on record, reliance is placed on:
- Edifice Developers and Project Engineers Ltd v. M/s.
Essar Projects (India) Ltd 2013 SCC Online Bom 5
[Para 8-11, 12(on profit)]
- Indo Nabin Projects Ltd v. Powergrid Corporation
2018 SCC Online Del 8405 [Para 11,12 &14]
Q. The entire period could not be claimed by the Respondent,
even if for the sake of arguments, it is taken that there were
defaults on the part of the Appellant in handing over the said
piece of site. Thus, the Hudson formula is not applicable at all,
which would cater for a situation where the entire delay is


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:18.06.2026
12:35:37
FAO (OS) (COMM) 206/2023 Page 82 of 93

attributable to one party alone.
R. The Respondent has simply applied the formula
mechanically without taking the realities into account. Besides,
it is a settled law that the formula cannot be applied
mechanically as it is and the person claiming must prove the
losses and breaches of the other parties before it can claim any
damages under the formula even.”

104. The learned counsel for the appellant has submitted that prolongation
costs were rejected throughout by the Engineer while recommending the
EOTs citing concurrent delays on the part of the contractor on critical part
including lack of manpower/machinery, machinery not mobilized, slow
progress on available stretches and on structures, bridges etc. There is no
discussion by the Tribunal as to why entire EOTs recommendation is
synonymous with the delay on part of the appellant. Further, it has been
contended that Hudson Formula is not applicable in cases of concurrent
delay and also that the amount of ₹35.15 crore has been granted without any
discussion or any basis, contrary to settled law.
105. The aforesaid being the submission of Mr. Mittal, it needs to be
decided whether the claim relating to overheads due to the
prolongation/extension is maintainable. Time to time, the Engineer had
recommended EOTs, which were approved by the appellant till 06.03.2011
but not thereafter. One common factor that binds all the EOTs is the
recommendation of the Engineer that the delay being concurrent, no
prolongation costs or overhead costs were payable during the period of
extended time. At no point of time did the respondent contest this conclusion
of the Engineer that no prolongation costs or overheads were payable. In
other words, the respondent had not contested that the delay in executing the
work was concurrent and as such it shall not be entitled to prolongation


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:18.06.2026
12:35:37
FAO (OS) (COMM) 206/2023 Page 83 of 93

costs/overheads. No communication in this respect has been placed before
us.
106. The respondent had continued executing the work during the
prolongation period till 24.09.2014 without any demur or protest. Though, it
is not urged by Mr. Mittal, we find that such an issue was not even raised
before the Dispute Resolution Board (DRB). The justification put forth by
the respondent is that the recommendations made by the Engineer are not
binding on respondent/claimant and under Clause 2.6 of the GCC, such a
determination is subject to challenge under Clause 67 which was done by
the respondent/claimant by referring the prolongation claims before the
Arbitral Tribunal. We are of the view that such challenge before the
Tribunal was not maintainable, when no such challenge was made
immediately after the issuance of the EOTs by the Engineer from time to
time. The Tribunal could not have allowed the claims without considering
and deciding the issue whether the Engineer was justified in holding that the
delay was concurrent and as such the respondent shall not be entitled to
prolongation cost.
107. This we say on the basis of the principles of acquiescence and waiver.
The respondent did not challenge the EOTs recommended by the Engineer
or seek a declaration that the Engineer could not have denied costs for the
prolongation period as the prolongation was because of reasons attributable
to the appellant. By knowingly sitting without any objection for years, the
respondent had, by its own conduct, accepted the recommendations of the
Engineer, including the rejection of prolongation/overhead costs.
108. Despite the appellant taking such a plea ( as seen from the Statement of
Defence, page 1064 of the appeal paper-book ), the Tribunal has not


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:18.06.2026
12:35:37
FAO (OS) (COMM) 206/2023 Page 84 of 93

considered or dealt with the same, which is clearly untenable as it is
expected of the Tribunal to deal with the submission advanced by a party
before allowing the claim of the opposite party. Such a conclusion made
without even considering the material submission made by the appellant
demonstrates patent illegality, which goes to the root of the matter.
Moreover, no prayer was made by the respondent challenging the EOTs to
set aside the rejection of prolongation and overhead costs. In fact, we find
that the learned Single Judge has also failed to address this issue in the
petition under Section 34 of the Act.
109. As such, the conclusion of the Tribunal with respect to Claim No. 6
needs to be set aside.

CLAIMS NO. 7 AND 8
110. Claim No.7 is for increase in rate due to the extra stay on the work
site, for an amount of Rs.11,86,74,618/-. Claim No.8 is for expenses
incurred towards the prolongation cost as a result of working in the extended
period of contract, quantified at Rs.63,37,75,829/-. In fact, the two claims
arise from the prolongation of work from 2008 to 2016 when the contract
was terminated. The learned counsel for the parties have put forth their
submissions in support of their respective cases, as noted by us above.
However, since both the claims arise from prolongation, our conclusion with
regard to Claim No. 6 would necessarily have an impact here as well. The
appellant while contesting Claims no. 7 and 8 had submitted before the
Tribunal that the Engineer while recommending the EOTs categorically
rejected all prolongation and overhead costs, as the delay is concurrent. As
such, going by the principles of acquiescence and estoppel, having accepted


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:18.06.2026
12:35:37
FAO (OS) (COMM) 206/2023 Page 85 of 93

such recommendations of the Engineer, the respondent could not have raised
the claims. The Tribunal has failed to even consider the submission of the
appellant while deciding these claims, making the conclusion so drawn
patently illegal and contrary to the public policy of India. The learned Single
Judge while considering the challenge to Claim No. 8 in the petition under
Section 34 of the Act has also failed to look into this issue. For this reason,
the decision of the Tribunal with regard to Claims no. 7 and 8 also need to
be set aside.
LIMITATION IN CLAIMS NO. 6 AND 8
111. At this stage, it is necessary to note that an issue of limitation has
been raised by the appellant with regard to Claims No. 6 and 8. The
contention of Mr. Mittal is that the cause of action for the respondent to raise
Claims no. 6 and 8 arose when the appellant approved the third EOT,
revising the date of completion to 06.03.2011. As the Engineer had rejected
prolongation costs while recommending the three EOTs, any claim which
relates back to a period prior to 06.03.2011 was time barred. However, we
note that the appellant, in its Statement of Defence ( paragraph 28 to 45 ),
had submitted before the Tribunal that the cause of action arose when
payment was deducted from the first IPC. Be that as it may, the conclusion
of the Tribunal with respect to the issue of limitation is reproduced
hereunder:
“12.4 LIMITATION:
12.4.1 The submissions made by the parties have
already been recorded hereinbefore and the same are not
being repeated here for the sake of brevity. Only salient
issues are being deliberated upon.
12.4.2 The Respondent is vague in Para 28 of SOD
while making his projection about the applicability of


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:18.06.2026
12:35:37
FAO (OS) (COMM) 206/2023 Page 86 of 93

Limitation. In the said Para he has denied the claims
also on the grounds, such as merit, non-adherence of
contractual clauses, law of waiver and estoppels etc. He
has contended that cause of action for the Claimant
accrued when the amount was deducted from the first
IPC. Further, Respondent has given reference of Section
43 of A&C Act, 1996 for applicability of the Limitation
Act.
12.4.3 The AT does not deny applicability of the
Limitation Act to arbitration proceedings also. However,
the main issue is as to what is to be considered as date of
cause of action. The contention of the Respondent that
cause of action arose at the time of first IPC is not
correct. It is an established law that any contractor can
make his clans arising out of a contract at the time of
submission of final bill, the stage for which did not come
in the present case because of illegal termination of the
contract by the Respondent. Further, the cause of action
for initiating arbitration arises only when the claim is
rejected by the concerned opposite party. There has been
no occasion in this case in the above context. The claims
in this case were projected by the Claimant under his
letter dated 08.06.2016 (С-72 of SOC) to which there
was no reply from the Respondent. Thereafter, the
Claimant invoked arbitration vide his letter dated
06.08.2016 (C-77 of SOC).
12.4.4 Even, referring to clause 43 of A&C Act, 1996, it
is provided therein that for the purpose of Limitation Act,
an arbitration shall be deemed to have commenced on
the date referred in Section 21 of the A&C Act.
12.4.5 Section 21 of the said Act states that date of cause
of action for arbitration is the date on which the disputes
are referred for arbitration to the opposite party, which
is 06-08-2016 in the present case.
12.4.6 Thurs it is therefore apparent that the claims of
the Claimant referred to this AT are well within the
period of three years provided in the limitation Act and
there is no violation of the same.”



Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:18.06.2026
12:35:37
FAO (OS) (COMM) 206/2023 Page 87 of 93

112. The Tribunal rejected the submission of the appellant that the cause of
action arose at the time of the first IPC. It observed that it is settled law that
a contractor can make its claims arising out of a contract at the time of
submission of the final bill. In the present matter, since the contract was
illegally terminated by the appellant, there was no occasion for raising the
final bill. Further, it was held that cause of action for initiating arbitration
arises only when the claim is rejected by the opposite party, which is not the
case here.
113. Mr Mittal has attempted to argue before us that since the Engineer had
rejected prolongation costs, Claims no. 6 and 8 are time-barred. However,
we are not inclined to accept this argument, for the reason that such a
submission was not raised either before the Tribunal or before the learned
Single Judge. In fact, there is nothing on record to show that the issue with
regard to limitation was raised at all in the petition before the learned Single
Judge. It has been raised for the first time in this appeal under Section 37 of
the Act. Be that as it may, even assuming that the claims were beyond the
period of limitation, in view of our clear finding in Claims No. 6 and 8 that
the respondent having accepted the rejection of prolongation costs, could not
have raised the claims later, we find no reason to interfere with the
conclusion of the Tribunal on the aspect of limitation. But we make it clear
that the findings on limitation has no bearing on the finding given by us on
the entitlement of the respondent to overheads and increase in the rate
because of the prolongation, in view of the stipulations in the EOTs.
CLAIM NO. 9
114. Insofar as Claim No.9 is concerned, the same is for recovery towards
the cost of confiscated machinery, material and other assets. The claim was


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:18.06.2026
12:35:37
FAO (OS) (COMM) 206/2023 Page 88 of 93

for ₹ 13,61,08,604/-. At the outset, it may be stated that the issue of
prolongation and decision of the Engineer granting EOT without
prolongation costs has no bearing insofar as this claim is concerned. The
Tribunal has awarded a sum of ₹7,70,80,510/- while referring to certain
judgments to hold that there is no wrong in accepting a formula based
approach for assessment of the quantum of claims.
115. The Tribunal by comparing the documents CA-5 and CA-6 held that
some of the items in CA-6 have not been considered, as there are some
variations. The Tribunal after noting the fact that no evidence has been
furnished by the claimant, on the basis of a fair assessment has awarded the
said amount.
116. The case of the appellant before the Tribunal is that the confiscation is
in terms of the contract and as such there is nothing illegal. This according
to the appellant, is because the respondent was contractually required to
complete the balance works and cannot seek refund of these goods under the
garb of this claim. It was also contended that the claimant has made the
claim in respect of machinery which also includes hired machinery from
other agencies, but without producing any record to differentiate the two
types of machinery. It is also stated that the respondent’s claim is
exaggerated by putting false and frivolous machinery to enrich itself. The
documents CA-5 and CA-6 which have been produced by the respondent are
different thereby belying the claim of the respondent as contradictory. That
apart, it was represented that the claim for hired machinery is also without
name of the suppliers and also without producing any bills of payment made
by the respondent, on record.
117. We find that though CA-5 and CA-6 are charts filed by the respondent


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:18.06.2026
12:35:37
FAO (OS) (COMM) 206/2023 Page 89 of 93

referring to the value of the machinery. However, the date of purchase of the
machinery and the bills in respect of said machinery and the bills of the
entity which had lent the hired material to the respondent have not been
placed on record. There is another aspect to this, which has been
highlighted by the appellant. Many of the machinery in terms of the
aforesaid documents were purchased in the year 2008 and the rate of
depreciation as per the respondent itself being 13.91% per annum, during the
time of termination of the contract in the year 2016, the value of the
machinery would have been depreciated to nil .
118. The issue is even if the value of the machinery has depreciated to nil ,
whether the same shall have scrap /salvage value, which can be translated to
monetary terms. The Tribunal, against the claim of ₹13,61,08,604/- has
granted an amount of ₹7,70,80,510/- terming it a fair assessment. The
Tribunal does not deal with the plea of the appellant that the depreciated
value of the machinery would be nil on the date of date of termination of the
contract. This itself is an infirmity in the award of the Tribunal. The
Tribunal was required to deal with the said submission of the appellant at the
first instance. It proceeds on the premise that the claim of ₹ 13,61,08,604/-
is the depreciated value of the machinery and on that basis granted an
amount of ₹7,70,80,510/-. Possibly, the appellant would be justified in
saying that between the years 2008 and 2016, the machinery would have
depreciated at the rate of 13.91% per annum, making it have nil value in
2016. In any case, the depreciated value of the goods cannot be
₹13,61,08,604/-, but the same shall surely have scrap/salvage value.
Unfortunately, the conclusion drawn by the Tribunal is not on that basis.
Even to conclude that the machinery has scrap/salvage value, which the


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:18.06.2026
12:35:37
FAO (OS) (COMM) 206/2023 Page 90 of 93

Tribunal has not done, there should be some basis.
119. The respondent failed to produce any evidence to show what the
actual/depreciated value of the machinery, material and other assets were at
the time of termination of the contract. In allowing the claim and awarding
the amount of ₹7,70,80,510/-, the Tribunal acted without evidence. The law
in this regard is quite well settled in terms of the decisions of the Supreme
Court in Associate Builders v. Delhi Development Authority: (2015) 3 SCC
49 , wherein, after taking note of the judgments in the cases of ONGC Ltd. v.
Saw Pipes Ltd.: (2003) 5 SCC 705, Hindustan Zinc Limited v. Friends
Coal Carbonisation: (2006) 4 SCC 445, McDermott International Inc. v.
Burn Standard Co. Ltd. & Ors.: (2006) 11 SCC 181, Centrotrade Minerals
& Metals Inc. v. Hindustan Copper Ltd.: (2006) 11 SCC 245, DDA v. R. S.
Sharma & Co.: (2008) 13 SCC 80, JG Engineers (P) Ltd. v. Union of
India: (2011) 5 SCC 758, Union of India v. Col. L.S. N. Murthy & Anr.:
(2012) 1 SCC 718 , and ONGC Ltd. v. Western Geco International Ltd.:
(2014) 9 SCC 263 , the Supreme Court held that when a Court is applying
the “public policy” test to an arbitral award, it does not act as a Court of
appeal and consequently, errors of facts cannot be corrected. A possible
view by the arbitrator on facts has necessarily to pass muster as the arbitrator
is the ultimate master of the quantity and quality of evidence to be relied
upon when he delivers any arbitral award. However, it was also held that
where-
(i) a finding is based on no evidence , or
(ii) an arbitral tribunal takes into account something irrelevant to the
decision which would necessarily be perverse, or
(iii) ignores vital evidence in arriving at a decision;


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:18.06.2026
12:35:37
FAO (OS) (COMM) 206/2023 Page 91 of 93

such a decision would necessarily be perverse.
120. We are of the view that the conclusion arrived at by the Tribunal with
respect to Claim No. 9 is perverse, as the same is without any basis or
evidence or for that matter not even a plausible view. The conclusion drawn
by the Tribunal is liable to be set aside.

CLAIM NO. 11
121. Claim No.11 is for the loss of profits that were to accrue to the
respondent. The Tribunal has allowed the claim, holding that the respondent
was deprived of earning profits on the execution of the balance work of
₹51,51,93,861/-, which it could not execute due to the illegal termination of
the contract by the appellant. The respondent quantified its loss to be 10%
of the aforesaid amount, which comes to ₹5,15,00,000/-. The Tribunal in
paragraph K(5), instead of granting the amount of ₹5,15,00,000/-, has
granted ₹4,63,50,000/-. As we have already upheld the conclusion drawn by
the Tribunal that the termination of the contract by the appellant is illegal,
the imperative consequence thereof would be that the respondent is liable to
be compensated for the loss of profit caused by the illegal termination. To
that extent, we agree with the conclusion drawn by the Tribunal. We do not
see any reason to interfere with the same.

CONCLUSION
122. In view of the discussion above, we set aside impugned judgment of
the learned Single Judge dated 26.04.2023. We also set aside the Award of
the Tribunal dated 21.02.2019 to the extent of Claims No.6, 7, 8 and 9. The


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:18.06.2026
12:35:37
FAO (OS) (COMM) 206/2023 Page 92 of 93

challenge made by the appellant to Claims no.1 and 11 of the Award is
rejected.



V. KAMESWAR RAO, J





VINOD KUMAR, J
JUNE 18, 2026
M/RT


Signature Not Verified
Signed By:PRADEEP
SHARMA
Signing Date:18.06.2026
12:35:37
FAO (OS) (COMM) 206/2023 Page 93 of 93