Oil And Natural Gas Corporation Limited vs Larsen And Toubro Limited

Court
Bombay High Court

2026:BHC-OS:11684
Neeta Sawant CARBP(L) 15345 OF 2026

IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ORDINARY ORIGINAL CIVIL JURISDICTION
COMMERCIAL ARBITRATION PETITION (L) NO. 15345 OF 2026
Oil and Natural Gas Corporation Limited …..PETITIONER
: VERSUS :
Larsen & Toubro Limited ….RESPONDENT
Mr. Zubin Behramkamdin, Senior Advocate with Ms. Shreya Gupta,
Ms. Prachi Gupta and Ms. Shradhha Kedia i/b M/s. Shardul Amarchand
Mangaldas & Co. for the Petitioner.
Mr. Vikram Nankani, Senior Advocate with Mr. Rohaan Cama, Mr.
Kyrus Modi, Mr. Mehul Talera, Mr. Indranil Deshmukh, Ms. Gathi
Prakash Karrah, Ms. Nidhi Asher, Ms. Arushi Poddar & Mr. Prakhar
Agarwal i/b M/s. Cyril Amarchand Mangaldas & Co. for the Respondent.
CORAM : SANDEEP V. MARNE, J.
RESD. ON: 30 APRIL 2026.
PRON. ON: 06 MAY 2026
JUDGMENT:
P REFACE
1) This is a post Award Petition filed under Section 9 of the
Arbitration and Conciliation Act, 1996 (Arbitration Act) seeking a
direction to the Respondent to extend and to keep alive the Bank
Guarantee provided by Respondent to the Petitioner towards liquidated
____________________________________________________________________________
PAGE NO. 1 of 33
06 MAY 2026
::: Uploaded on - 06/05/2026 ::: Downloaded on - 06/05/2026 21:03:00 :::

Neeta Sawant CARBP(L) 15345 OF 2026

damages as per clauses 6.3.2 and 6.3.4 of the General Conditions of
Contract. The Arbitral Tribunal has awarded in favour of Respondent an
aggregate sum of approximately INR 271,12,57,704.81 whereas the sum
awarded in favour of Petitioner is approximately INR 42,95,65,545.28.
Petitioner is aggrieved by the Award, which is challenged by it under
Section 34 of the Arbitration Act. In that sense, the Respondent is a
‘successful party’ in the arbitration whereas Petitioner is a ‘unsuccessful
party’. Though Petitioner is an unsuccessful party in the arbitral
proceedings, it has filed the present Petition under Section 9 of the
Arbitration Act seeking a direction for renewal of the bank guarantee on
the ground that it is entitled to recover from the Petitioner the entire or
at least the awarded amount of liquidated damages.
2) Though the issue of impermissibility for a losing party to
maintain application under Section 9 of the Arbitration Act was fairly
well settled by judgment of Division Bench of this Court in Dirk India
Pvt. Ltd. vs. Maharashtra State Electricity Generation Company
1
Limited , the law has undergone a change on account of Hon’ble
Supreme Court’s recent judgment dated 24 April 2026 in Home Care
2
Retail Marts Pvt. Ltd vs. Haresh N. Sanghavi , in which it is held that
the judgment of this Court in Dirk India Pvt. Ltd. (supra) does not lay
down a good law and that even an unsuccessful party to arbitration can
maintain application under Section 9 of the Arbitration Act.
1 2013 SCC OnLine Bom 481
2 2026 SCC OnLine SC 670
____________________________________________________________________________
PAGE NO. 2 of 33
06 MAY 2026
::: Uploaded on - 06/05/2026 ::: Downloaded on - 06/05/2026 21:03:00 :::

Neeta Sawant CARBP(L) 15345 OF 2026

3) The Petitioner has in fact applied for very same interim
relief under Section 36(3) of the Arbitration Act while challenging the
arbitral award under Section 34. However, after filing of Section 34
petition, since the legal position has undergone a change on account of
judgment in Home Care Retail Marts Pvt. Ltd. (supra) on 24 April 2026,
the Petitioner has chosen to file the present Petition under Section 9 of
the Arbitration Act rather than pressing for interim relief under Section
36(3). The Respondent questions (i) maintainability of the present
Petition, (ii) the propriety in filing of the present Petition despite
seeking similar relief in Section 36(3) Application and (iii) Petitioner’s
entitlement for interim measures on merits.
T HE I SSUE I NVOLVED
4) In the light of the above position, the issue that arises for
consideration is whether the Petitioner, who has been awarded claim in
the sum of Rs.42.95 crores as against award of claim of Rs.271.12 crores
in favour of the Respondent, can maintain a Petition under Section 9 of
the Arbitration Act for seeking interim measures for securing the
awarded and unawarded sum of liquidated damages by
extension/renewal of the bank guarantee by the Respondent. Also
involved is the issue whether Petitioner can maintain the present
Petition under Section 9 of the Arbitration Act after having exercised the
remedy under Section 36(3) of the Act by seeking interim stay in Section
34 petition.
____________________________________________________________________________
PAGE NO. 3 of 33
06 MAY 2026
::: Uploaded on - 06/05/2026 ::: Downloaded on - 06/05/2026 21:03:00 :::

Neeta Sawant CARBP(L) 15345 OF 2026

F ACTS
5) Since the issue involved in the petition is narrow and since
this Court is not dealing with the merits of the Award while execrcising
Section 9 jurisdiction, it is not necessary to narrate the factual
background in greater details. Petitioner ONGC is a Maharatna public
sector undertaking incorporated under the Companies Act, 1956 and is
engaged in the business inter alia of exploration and production of oil
and gas within the territory of India. Among others, it has large scale
petroleum operations in the Bombay High Oil and Natural Gas Field
offshore the Mumbai coast. Respondent is Larsen & Toubro Ltd.
(L&T)
engaged in the business inter alia of engineering, procurement and
construction in various sectors including hydrocarbon sector.
6) By and under the contract dated 3 July 2010 (Contract) ,
Petitioner engaged the Respondent for inter alia survey, design,
engineering, procurement, fabrication, load-out, transportation,
installation, hook-up, testing, pre-commissioning and commissioning of
four well-head platforms (N-14, N-17, N-18 and N-20) for Mumbai High
North Redevelopment Plan. The Contract was a Lump Sum Turn Key
(LSTK) basis for aggregate price of USD 97,104,900 plus EUR 5,293,700
plus INR 524,25,01,000 (Contract Price) . The scheduled date for
completion of all four platforms was 15 May 2011. Under the Contract,
Petitioner was entitled to recover liquidated damages (LD) from the
Respondent at the rate of ½ % of the Contract Price for each week of
delay subject to a maximum of 10% of the Contract Price. Under clause
6.3.4 of the GCC, it was permissible for L&T to furnish a bank guarantee
____________________________________________________________________________
PAGE NO. 4 of 33
06 MAY 2026
::: Uploaded on - 06/05/2026 ::: Downloaded on - 06/05/2026 21:03:00 :::

Neeta Sawant CARBP(L) 15345 OF 2026

for obtaining release of the amounts withheld by the Petitioner towards
LD.
7) According to the Petitioner, the project was delayed due to
factors attributable to the Respondent and three extensions of time
( EOT ) were granted to L&T subject to levy of liquidated damages (LD) .
The project was completed and handed over on 28 February 2012,
resulting in delay of 289 days beyond the scheduled completion date.
ONGC withheld and deducted amounts towards LD totally amounting to
Rs.122.73 crores. L&T submitted bank guarantee in the sum of Rs.150.34
crores representing 10% of the contract price and secured release of
withheld amount of LD of Rs.122.73 crores.

8) Disputes arose between ONGC and L&T out of performance
of the Contract and accordingly, a three-member Arbitral Tribunal was
constituted. The Arbitral Tribunal has made award dated 30 December
2024 and additional award dated 12 December 2025 granting EOT of 319
days to L&T out of alleged delay claimed of approximately 496 days. The
Award has limited Petitioner’s entitlement to liquidated damages to 35%
of the total amount of Rs.122.73 crores and has directed the Petitioner to
refund the balance 65% of the liquidated damages to L&T. The Award
grants claim Nos.2 to 7 in favour of L&T and has rejected Petitioner’s
counterclaim No.2. The Award has also granted Post Award interest at
the rate of 18% p.a. and 80% of costs of arbitration in favour of the
Respondent. According to the Petitioner, the Tribunal erroneously made
Additional Award on 12 December 2025 under Section 33 of the
____________________________________________________________________________
PAGE NO. 5 of 33
06 MAY 2026
::: Uploaded on - 06/05/2026 ::: Downloaded on - 06/05/2026 21:03:00 :::

Neeta Sawant CARBP(L) 15345 OF 2026

Arbitration Act thereby materially altering the original Award and
deleting condition for return of bank guarantee upon payment of 35% LD
amount and substituting it with a direction for mutual adjustment / set-
off of the amounts payable between the parties.
9) After making of the Additional Award directing mutual
adjustment of amounts payable to parties, Respondent has refused to
extend the bank guarantee beyond the present validity of 30 April 2026
vide letter dated 5 February 2026.
Petitioner has filed Commercial Arbitration Petition (L)
10)
No.9373 of 2026 on 12 March 2026 under Section 34 of the Arbitration
Act challenging Awards dated 30 December 2024 and 12 December 2025.
On 17 April 2026, Petitioner filed Interim Application under Section
36(3) of the Arbitration Act in Section 34 petition seeking unconditional
stay of the Awards and for a direction to the Respondent to extend and
keep alive the bank guarantee. By letters dated 13 April 2026 and 20
April 2026, Petitioner called upon Respondent to extend the bank
guarantee in view of the pending Section 34 petition and Section 36
application.
11) Under apprehension that the Petitioner may invoke and
encash the bank guarantee, Respondent filed Commercial Arbitration
Petition (L) 14555 of 2026 under Section 9 of the Arbitration Act. When
the petition came up for hearing on 23 April 2026, a statement was made
on behalf of the Petitioner that since Petitioner was seeking interim
____________________________________________________________________________
PAGE NO. 6 of 33
06 MAY 2026
::: Uploaded on - 06/05/2026 ::: Downloaded on - 06/05/2026 21:03:00 :::

Neeta Sawant CARBP(L) 15345 OF 2026

relief in Section 34 petition and in Section 36 application for renewal of
the bank guarantee, it was not proposing to invoke/encash the bank
guarantee. Accordingly, Commercial Arbitration Petition (L) No.14555
of 2026 was disposed of by order dated 23 April 2026.
Section 34 petition and Section 36 application filed by the
12)
Petitioner came up before this Court on 28 April 2026. Since the Hon’ble
Supreme Court pronounced the judgment in Home Care Retail Marts
Pvt. Ltd. (supra) on 24 April 2026, Petitioner decided not to press the
prayer in Section 36 application for renewal of bank guarantee and
sought liberty to move petition under Section 9 of the Arbitration Act.
Accordingly, the present Petition is filed by the Petitioner seeking post
award interim measures in terms of the following prayers:
(a) Direct the Respondent to extend (and keep extending from time to time, as
necessary) and keep alive the Bank Guarantee No. 00040100008747 dated 21
August 2015 issued by Axis Bank Limited, for the amount of USD 9,710,490
plus EUR 529,370 plus INR 52,42,50,100 (i.e., 10% of the Contract Price),
provided to the Petitioner towards liquidated damages as per Clauses 6.3.2 and
6.3.4 of the Contract dated 3 July 2010 between the Petitioner and the
Respondent, until the hearing and final disposal of Commercial Arbitration
Petition (L) No. 9373 of 2026 filed by the Petitioner under Section 34 of the
Arbitration and Conciliation Act, 1996;
(b) Alternatively, in the event the Respondent fails and/or neglects to extend
the said Bank Guarantee in terms of prayer clause (a) above and/or the said
Bank Guarantee lapses, direct the Respondent to forthwith furnish a fresh and
equivalent Bank Guarantee in favour of the Petitioner for an amount of USD
9,710,490 plus EUR 529,370 plus INR 52,42,50,100 (i.e., 10% of the Contract
Price),
(c) Grant ad-interim reliefs in terms of prayer clauses (a) and/or (b);
(d) Award costs of the present Petition; and
____________________________________________________________________________
PAGE NO. 7 of 33
06 MAY 2026
::: Uploaded on - 06/05/2026 ::: Downloaded on - 06/05/2026 21:03:00 :::

Neeta Sawant CARBP(L) 15345 OF 2026

13) The Bank Guarantee has two dates viz. 30 April 2026 (expiry
date) and 30 April 2027 (claim expiry date). Since a confusion prevailed
about validity of the bank guarantee beyond 30 April 2026, a statement is
made on behalf of the Respondent-L&T for renewal of the bank
guarantee in the event of Petitioner succeeding in the present petition,
which is recorded in the Order dated 30 April 2026 as under:
During the course of his submissions, Mr. Nankani, the learned Senior
Advocate appearing for Respondent has placed on record, copy of the
renewed Bank Guarantee (BG) dated 29 January 2026, which has two
dates. The BG expiry date is 30 April 2026. However, the claim expiry
date is up to 30 April 2027. This means that even though the BG may
expire on 30 April 2026, Petitioner can still make claim up to 30 April
2027. However, with a view to avoid any confusion about validity
and enforceability of the BG, Mr. Nankani has fairly made state-
ment that in the event of the Petitioner succeeding in the present
Petition, the Respondent shall either renew the BG or submit a
fresh one.
(emphasis added)
S UBMISSIONS
14) Mr. Behramkamdin, the learned Senior Advocate appearing
for the Petitioner has submitted that in view of the judgment of the Apex
Court in Home Care Retail Marts Pvt. Ltd. , the Petitioner is entitled to
seek interim measures under Section 9 of the Arbitration Act
notwithstanding the fact that a higher amount is awarded in favour of
the Respondent. He submits that mere award of claim in the sum of Rs.
271.12 crores in favour of the Respondent cannot be a reason for not
making interim measures in favour of the Petitioner to secure its claim
for the entire liquidated damages of Rs.122.73 crores. That the bank
____________________________________________________________________________
PAGE NO. 8 of 33
06 MAY 2026
::: Uploaded on - 06/05/2026 ::: Downloaded on - 06/05/2026 21:03:00 :::

Neeta Sawant CARBP(L) 15345 OF 2026

guarantee is submitted by the Respondent only for the purpose of release
of the deducted/withheld amounts towards liquidated damages. That the
Arbitral Tribunal has erroneously restricted the liquidated damages to
35%. That the methodology of apportionment of liquidated damages
applied by the Arbitral Tribunal is contrary to Clause 6.3.2 of the generla
Conditions of Contract. That Tribunal’s findings on delays caused in the
Project are patently illegal and perverse. That the findings of the
Tribunal that Respondent is entitled to approximately 319 days of
extension is incorrect and patently illegal as the extension granted by
the Tribunal exceeds the entire period by which completion of project
was delayed (289 days). That Tribunal granted extensions without
critical path analysis as required under the Contract and its findings on
delays are contrary to the contractual terms. That Additional Award
made by the Tribunal exceeds the limited jurisdiction under Section 33
of the Arbitration Act. That initially the Tribunal had directed Petitioner
to return the bank guarantee only upon payment of 35% of LD,
quantified at USD 2,825,336 + EUR 149,169 + INR 14,52,12,198 within 30
days. However, in the Additional Award, the Tribunal erroneously
directed “mutual adjustment” of party's monetary liabilities with only
net amount remaining payable.
15) Mr. Behramkamdin further submits that the specific awards
under Claim No.4 are independently vitiated by patent illegality. That
Tribunal’s award of post-award interest/service tax are unsustainable
and vitiated by patent illegality. That Tribunal reversed the burden of
____________________________________________________________________________
PAGE NO. 9 of 33
06 MAY 2026
::: Uploaded on - 06/05/2026 ::: Downloaded on - 06/05/2026 21:03:00 :::

Neeta Sawant CARBP(L) 15345 OF 2026

proof and impermissibly invoked Section 70 of the Indian Contract Act,
1872 in granting Change Order/Extra Work Claims.
16) Mr. Behramkamdin further submits that grant of interim
measures in the present Petition is necessary in view of strong prima
facie case and rare and compelling case made out by the Petitioner. That
Petitioner would suffer irreparable harm if the bank guarantee is allowed
to lapse as Petitioner would have no security against the Respondent’s
liability to LD. If Petitioner succeeds in Section 34 petition, absence of
bank guarantee would prejudice the Petitioner irreversibly. That balance
of convenience lies decisively in favour of the Petitioner. That grant of
interim measures does not materially prejudice the Respondent nor
comes in the way of enforceability of the Award. That Petitioner is a
Maharatna public sector undertaking and would remain compliant with
any directions of this Court. That all that is sought is to renew and keep
alive the bank guarantee, which the Petitioner is not going to invoke or
encash.
17) The Petition is opposed by Mr. Nankani, the learned Senior
Advocate appearing for the Respondent, who questions maintainability
of the Petition. He submits that since Respondent has higher monetary
claims against the Petitioner in the sum of Rs.271.12 crores, there is no
question of Petitioner filing Section 9 petition for securing its minuscule
claim of Rs.42.95 crores. That Petitioner has already filed Section 36
application and therefore is estopped from seeking interim measures
under Section 9 Petition. That Section 9 Petition is filed with a view to
____________________________________________________________________________
PAGE NO. 10 of 33
06 MAY 2026
::: Uploaded on - 06/05/2026 ::: Downloaded on - 06/05/2026 21:03:00 :::

Neeta Sawant CARBP(L) 15345 OF 2026

avoid pressing stay in Section 36 application which would require
deposit of awarded sum by the Petitioner. That a specific representation
was made before this Court on 23 April 2026 while opposing
Respondent’s Section 9 petition that relief of renewal of bank guarantee
would be sought in Section 36 application. However, when Section 36
application was heard on 28 April 2026, Petitioner took a volte face and
avoided seeking stay to the Award stating that it would file Section 9
Petition for renewal of bank guarantee.

18) Mr. Nankani further submits that there is gross delay in
filing the present Petition as Petitioner was put to notice on 5 February
2026 of not extending the bank guarantee. That present Petition is
however filed on 29 April 2026 i.e., a day before expiry of the bank
guarantee. That Petitioner has suppressed the position that the claim
expiry period is available upto 30 April 2027 and has made out a false
case of urgency before this Court. He submits that relief sought by the
Petitioner would amount to passing of an order contrary to the
enforcement of the Award which is impermissible even under the
judgment of the Apex Court in Home Care Retail Marts Pvt. Ltd.
(supra). That the Additional Award directs unconditional return of bank

guarantee and if an order is passed by this Court for extension/renewal
of bank guarantee, the same would come in the way of enforcement of
the Award. That under the garb of seeking interim measures under
Section 9, Petitioner is actually seeking modification of the Award which
only Section 34 Court can do. He relies on judgment of Delhi High Court
in M/s. Mukti Credits Pvt. Ltd. vs. Indraprastha Power Generation Co.
____________________________________________________________________________
PAGE NO. 11 of 33
06 MAY 2026
::: Uploaded on - 06/05/2026 ::: Downloaded on - 06/05/2026 21:03:00 :::

Neeta Sawant CARBP(L) 15345 OF 2026
3
Ltd. holding that Section 9 Court cannot enter into controversy of

correctness or otherwise of the Award as the same would encroach upon
jurisdiction of Section 34 / Section 36 Court.
19) Mr. Nankani further submits that similar requests for
extension of bank guarantee have been repeatedly rejected by this Court
in the case of the Petitioner/ONGC. He relies on order passed by this
4
Court in ONGC vs. Punj Lloyd Ltd. and ONGC vs. Consortium of Sime
Darby Engineering Sdn. Bhd. and Swiber Offshore Construction Pte.
5
Ltd. . He submits that in those decisions, this Court has taken a view
that when a net higher amount is owed to the award-holder and where
only relief available to ONGC is a Section 34 petition for setting aside the
Award, it would be improper and impermissible to direct extension of the
bank guarantee.

Lastly, Mr. Nankani submits that no rare or compelling case
20)
is made out as contemplated by the judgment in Home Care Retail Mart
Pvt. Ltd. (supra) as there is no apprehension of dissipation of assets or
impossibility to recover 35% LD under the Award or remaining 65% of LD
not awarded to the Petitioner. That judgment in Home Care Retail Mart
Pvt. Ltd. does not provide two mutually exclusive remedies to the
unsuccessful party viz. one under Section 9 and the other under Section
36(3) of the Arbitration Act. That remedy under Section 9 post award
subsists only until enforcement/execution of the Award. On the contrary,
3 OMP (I) (COMM) 113/2019 decided on 28 January 2020.
4 IA No. 2003 of 2019 in CARBP No. 36 of 2022 decided on 21 December 2022
5 2018 SCC OnLine Bom 6034
____________________________________________________________________________
PAGE NO. 12 of 33
06 MAY 2026
::: Uploaded on - 06/05/2026 ::: Downloaded on - 06/05/2026 21:03:00 :::

Neeta Sawant CARBP(L) 15345 OF 2026

Section 36(3) provides a mechanism to unsuccessful party to intercede
execution by obtaining a stay. That the provisions are complementary
and not competing. That therefore, interim measures in post Award
Section 9 petition cannot be understood to mean conferment of
protective powers until decision of Section 34 petition as such
interpretation would render provisions of Section 36(3) otiose. That
judgment in Home Care Retail Marts (supra) cannot be read in support
of proposition that Section 9 Petition furnishes a parallel and co-
extensive remedy subsisting until the final adjudication of Section 34
petition. Mr. Nankani would pray for dismissal of the Petition.
R EASONS AND A NALYSIS
21) The disputes and differences between Petitioner-ONGC and
Respondent-L&T have been arbitrated by a Three-Member Arbitral
Tribunal, which has made Award dated 30 December 2024 and Additional
Award under Section 33 of the Arbitration Act on 12 December 2025.
Under the Awards, the Tribunal has granted in favour of L&T, USD
2,62,09,133.42 plus EUR 4,893.28 plus INR 22,63,51,381.04 under Claim
Nos. 2 to 7. As against this, in respect of Claim No.1 raised by L&T for
EOT and consequential release of the bank guarantee, the Award directs
ONGC to return the bank guarantee to L&T. The bank guarantee was
submitted by L&T representing 10% of the contract price of
approximately INR 150.34 crores for the purpose of release of
deducted/withheld amount of LD. ONGC imposed total liquidated
damages of approximately INR 122.73 crores. However, the Arbitral
____________________________________________________________________________
PAGE NO. 13 of 33
06 MAY 2026
::: Uploaded on - 06/05/2026 ::: Downloaded on - 06/05/2026 21:03:00 :::

Neeta Sawant CARBP(L) 15345 OF 2026

Tribunal has held that ONGC was entitled to impose LD only to the
extent of 35%, quantified at USD 28,25,336.00 plus EURO 1,49,168.00
and INR 14,52,12,198.00.
22) The tabular statement of the claims awarded in favour of
L&T and ONGC is as under:
Heads of ClaimAmounts Awarded
Claims made by L&TUSDEURINR
Claim No.1: Claims For<br>Extension of Time and<br>Consequential Release of Bank<br>Guarantee in lieu of Liquidated<br>Damages(Award directs ONGC to return the bank<br>guarantee to L&T)
Claim No.2: Claim for<br>Compensation for De-<br>Mobilisation, Re-Mobilisation<br>of Marine Spread and<br>Transportation, Storage and<br>Re-Transportation of<br>Structures During and Post<br>Monsoon SeasonUSD<br>1,72,48,000.00INR<br>6,20,76,76,473.44
Claim No. 3: Claims for<br>Compensation on Account of<br>Standby of L&T’s Vessels/<br>BargesUSD<br>73,78,816.48
Claim No. 4: Claims For<br>Compensation on Account of<br>Change in Scope of Work/<br>Design Criteria and/or ONGC’s<br>InstructionsUSD<br>13,85,341.44INR<br>76,57,869.00
Claim No. 5: Claim for<br>reimbursement of service tax<br>on weight adjustmentINR 5,28,71,450.00
Claim No. 6: Claims forUSDINR

____________________________________________________________________________
PAGE NO. 14 of 33
06 MAY 2026
::: Uploaded on - 06/05/2026 ::: Downloaded on - 06/05/2026 21:03:00 :::

Neeta Sawant CARBP(L) 15345 OF 2026
Amounts Wrongfully Withheld<br>by ONGC386.5017,28,068.00
Claim No. 7: Miscellaneous<br>ClaimsUSD<br>1,96,589.00Euro<br>4,893.28INR<br>2,59,83,360.00
CostsINR<br>7,60,34,060.60
Total amounts awarded to<br>L&TUSD<br>2,62,09,133.4<br>2Euro<br>4,893.28INR<br>22,63,51,381.04
Total amounts awarded to<br>ONGC in its counterclaim<br>towardss refund of amounts<br>released by ONGC to L&T by<br>accepting Bank Guarantee in<br>lieu of liquidated damagesUSD<br>28,25,336.00Euro<br>1,49,168.00INR<br>14,52,12,198.00


23) Upon conversion of USD and EURO into INR by applying
conversion rate as on 29 April 2026, Respondent has presented following
figures of total value of claims in INR awarded in favour of L&T and
ONGC:
USDEURINRTOTAL IN INR
Total amounts<br>awarded to<br>L&TUSD<br>2,62,09,133.42Euro<br>4,893.28INR<br>22,63,51,381.04INR<br>271,12,57,704.81
Total amounts<br>awarded to<br>ONGC in its<br>counterclaimUSD<br>28,25,336.00Euro<br>1,49,168.00INR<br>14,52,12,198INR<br>42,95,65,545.28
NET AMOUNTINR<br>228,16,92,159.53

th
* Conversion rate for 1 USD is taken as 94.79 INR as on 29 April 2026
th
Conversion rate for 1 EUR is taken as 110.88 INR as on 29 April 2026
____________________________________________________________________________
PAGE NO. 15 of 33
06 MAY 2026
::: Uploaded on - 06/05/2026 ::: Downloaded on - 06/05/2026 21:03:00 :::

Neeta Sawant CARBP(L) 15345 OF 2026

24) Thus, the net result of the two Awards made by the Arbitral
Tribunal is that ONGC is liable to pay to L&T a sum of Rs. 271.12 crores
whereas L&T is liable to pay to ONGC a sum of Rs.42.95 crores. After
making mutual adjustments, the net sum payable by ONGC to L&T is
Rs.228.16 crores. Thus, Respondent-L&T is entitled to ultimately
recover amount from ONGC and in that sense, one may treat L&T as the
‘successful party’ and ONGC as ‘unsuccessful party’.
25) Division Bench of this Court in Dirk India Pvt. Ltd. (supra)
had taken a view that a party unsuccessful in arbitral proceedings cannot
maintain petition under Section 9 of the Arbitration Act. Similar view
was taken by Delhi, Madras and Karnataka High Courts. On the other
hand, the High Court at Telangana, Gujarat High Court and Punjab &
Haryana High Court had taken a contrary view that even unsuccessful
party in arbitral proceedings can maintain petition under Section 9 of
the Arbitration Act. The divergence of views expressed by various High
Courts attracted attention of the Hon’ble Supreme Court in Home Care
Retail Marts Pvt. Ltd. (supra) in which following substantial question of
law was framed in para-2 of the judgment:
2. The substantial question of law that arises for consideration in the present
batch of appeals is whether a petition under Section 9 of the Arbitration and
Conciliation Act, 1996 (hereinafter referred to as ‘the Act’) at the post-award
stage, by a party that has lost in the arbitral proceedings and has no
enforceable award in its favour, is maintainable in law?
26) Referring to plain language of Section 9 of the Arbitration
Act and taking into consideration the meaning of the expression ‘a party’
used therein, the Apex Court held that Section 9 of the Act does not draw
____________________________________________________________________________
PAGE NO. 16 of 33
06 MAY 2026
::: Uploaded on - 06/05/2026 ::: Downloaded on - 06/05/2026 21:03:00 :::

Neeta Sawant CARBP(L) 15345 OF 2026

any distinction between successful and unsuccessful parties in
arbitration proceedings. It further held that statutory framework does
not prescribe any qualification that would confine the availability of post
award relief under Section 9 solely to award holders. It is held that the
meaning of the expression ‘a party’ cannot be contextually modulated or
varied depending on the outcome of arbitral proceedings. The Apex
Court thus concluded that the interpretation adopted by this Court in
Dirk India (supra) is inconsistent with the statutory scheme. The Court
has held in paras-40 and 41 of the judgment as under:
40. The interpretation adopted in Dirk India (supra) appears inconsistent with
the statutory scheme. By restricting the availability of post-award interim
relief to a successful party, the judgment introduces a limitation unsupported
by the language of Section 9 of the Act. If the legislature, while consciously
deviating from the UNCITRAL Model Law, intended to impose such a
restriction, it would have done so expressly.
41. Consequently, this Court is of the considered view that the object and
purpose of Section 9 of the Act is to ensure that parties retain the right to
approach the Court for interim measures until the judicial process has reached
its culmination.
27) In Home Care Retail Marts Pvt. Ltd. , the Apex Court went
ahead to hold that Sections 34/36(2) and Section 9 of the Arbitration Act
apply in distinct spheres and that mere availability of recourse under
Section 34 of the Act or stay under Section 36(2) cannot operate as a bar
to seeking protection under Section 9. The Court has held in paras-42
and 43 of the judgment as under:
____________________________________________________________________________
PAGE NO. 17 of 33
06 MAY 2026
::: Uploaded on - 06/05/2026 ::: Downloaded on - 06/05/2026 21:03:00 :::

Neeta Sawant CARBP(L) 15345 OF 2026

42. The mere availability of recourse under Section 34 of the Act or of a stay
under Section 36(2) of the Act cannot operate as a bar to seeking protection
under Section 9.
43. Sections 34 as well as 36 provide remedies against an award or a stay
thereof, whereas Section 9 ensures protection of the subject matter or the
amount in dispute. An unsuccessful party cannot secure protection of its claim
under Section 34 or Section 36. To deny interim relief under Section 9 would
leave such a party remediless. In fact, if the Court declines to entertain an
application of a losing party for interim relief, there would be no forum
available for protection of the subject matter, even where the award under
challenge is stayed and potentially liable to be set aside. Moreover, the
ultimate outcome may alter the rights of parties and, therefore, distinction
between a ‘winning’ and a ‘losing’ party cannot govern access to the remedy
under Section 9 of the Act.
28) In Home Care Retail Marts Pvt. Ltd. (supra), the Apex
Court further held that Dirk India Pvt. Ltd. (supra) had proceeded on a
fundamentally erroneous premise that Section 34 Court can only dismiss
objections to the arbitral award or set it aside, which assumption was
erroneous in the light of judgment of the Constitution Bench in Gayatri
6
Balaswamy vs. ISG Novasoft Technologies Ltd. . The Apex Court has
held in paras-44, 45 and 47 of the judgment as under:
44.  The fundamental premise on which  Dirk India ,  Nussli Switzerland
Ltd. ,  Padma Mahadev  and  A. Chidambaram  (supra) held that an unsuccessful
party, post award, is disentitled to seek interim relief is that under Section 34
of the Act, the Court may either dismiss the objection to the arbitral award or
set it aside, therefore the interim measure of protection is intended to
safeguard the fruit of the proceedings until the eventual enforcement of the
award.
45.  This assumption is untenable in law, for it now stands conclusively settled
by the Constitution Bench Judgment in  Gayatri Balasamy  (supra) that Courts
exercising jurisdiction under Sections 34 and 37 of the Act possess the power
to modify an arbitral award where the award is severable, by excising the
invalid portion from the valid portion, and/or by correcting clerical,
6 (2025) 7 SCC 1
____________________________________________________________________________
PAGE NO. 18 of 33
06 MAY 2026
::: Uploaded on - 06/05/2026 ::: Downloaded on - 06/05/2026 21:03:00 :::

Neeta Sawant CARBP(L) 15345 OF 2026

computational, or typographical errors, and/or by modifying post-award
interest in appropriate circumstances. It has also been held that this Court, in
exercise of its powers under Article 142 of the Constitution, has the authority
to amend the award.
47.  Additionally, the expressions ‘ subject matter of arbitration ’ and ‘ amount in
dispute ’ used in Section 9(1)(ii) of the Act are broader in scope, width and
amplitude than the phrase ‘ fruits of arbitration ’. Where the Legislature has
expressly provided that measures under Section 9 of the Act may secure the
subject matter of arbitration or the amount in dispute, the Court in  Dirk India,
Nussli Switzerland Ltd., Padma Mahadev  and  A. Chidambaram  (supra) could not
have restricted its ambit to securing an enforceable claim of the successful
party. Such a restrictive interpretation is impermissible when the language of
the provision is plain and categorical.
The Apex Court thereafter went on to give purposive
29)
interpretation to the expression ‘ a party ’ and held that the Court can not
only stay the Award but also grant interim measures under Section 9 of
the Arbitration Act to balance the equities. Giving example of a bank
guarantee, the Court has held that in addition to stay of Award under
Section 36(3), the unsuccessful party is also entitled to seek interim
measures in relation to a bank guarantee. The Apex Court held in para-
49 of the judgment as under:
49. Even applying the test of purposive interpretation, ‘ a party ’ must mean any
party to the arbitration agreement. This Court can envisage situations where a
party that has lost in arbitration may nonetheless require interim protection.
For instance, where an arbitral award has been rendered without proper notice
to a party, or where a party is able to  prima facie  demonstrate that the award
has been induced or tainted by fraud or corruption. In such situations, the
Court may not only stay the award but also grant interim measures under
Section 9 of the Act to balance the equities. Similarly, in certain cases, an
unsuccessful party may have obtained interim protection during the arbitral
proceedings, such as an order restraining invocation of a bank guarantee. Upon
the rendering of the arbitral award, such interim protection ordinarily stands
vacated. However, the unsuccessful party may challenge the award under
Section 34 of the Act and obtain a stay on the enforcement of the arbitral
award under Section 36(3) of the Act. In such circumstances, immediate
removal of interim protection, for example, in relation to a bank guarantee,
____________________________________________________________________________
PAGE NO. 19 of 33
06 MAY 2026
::: Uploaded on - 06/05/2026 ::: Downloaded on - 06/05/2026 21:03:00 :::

Neeta Sawant CARBP(L) 15345 OF 2026

may result in irreversible prejudice to the unsuccessful party whose challenge
to the arbitral award is pending adjudication.
30) In Home Care Retail Marts Pvt. Ltd. , the Apex Court has
further held that courts are not disabled from granting ‘non prejudicial’
interim measures in favour of unsuccessful party where such relief does
not affect enforceability of Award. The Apex Court held in para-50 of the
judgment as under:
50. Further, the Courts are not disabled from granting ‘ non-prejudicial ’ interim
relief in favour of an unsuccessful party in arbitral proceedings, particularly
where such relief does not affect the enforceability of the award but merely
preserves ancillary rights pending adjudication under Section 34 of the Act as
was sought in the case of  Wind World (India) Ltd.  (supra).
31) The Apex Court in Home Care Retail Marts Pvt. Ltd. (supra)
has specifically dealt with the instance of ‘partially successful party’
against whom higher amount of counter claim is allowed and has held in
para-51 as under:
51. Another interesting conundrum may be where a party is partially
successful, inasmuch as, part of its claims are allowed but as a consequence of
a higher amount of counter-claim being allowed, it is branded as an
unsuccessful party in accordance with  Dirk India  (supra) and is not in a
position to prevent the other party from selling its assets after the award has
been rendered. It is possible that in Section 34 proceedings, the arbitral award
may be modified to the extent that the counter-claim is set aside and severed
from the award. However, without interim relief, assets may dissipate
rendering final success illusory.
32) However, the Hon’ble Apex Court has prescribed a caveat in
Home Care Retail Marts Pvt. Ltd. (supra) that interim measures under
Section 9 of the Arbitration Act in favour of unsuccessful party can only
be made in rare and compelling cases and that the threshold for grant of
____________________________________________________________________________
PAGE NO. 20 of 33
06 MAY 2026
::: Uploaded on - 06/05/2026 ::: Downloaded on - 06/05/2026 21:03:00 :::

Neeta Sawant CARBP(L) 15345 OF 2026

interim relief would be higher in the case of an unsuccessful party. The
Court has held in para-52 and 60 of the judgment as under:
52. Consequently, in rare and compelling cases, it may be necessary to permit
the unsuccessful party to invoke Section 9 of the Act to seek continuation of
the existing interim protection. This assumes greater significance, as noted
earlier, in light of the decision in  Gayatri Balasamy  (supra) which recognises
the Court's power under Section 34 of the Act to modify an arbitral award,
including the power to sever ‘ the “invalid” portion from the “valid” portion of the
award ’.
60. Undoubtedly, the threshold for grant of interim relief will be higher in the
case of an unsuccessful party in arbitration seeking such relief. In rare and
compelling cases, permitting the unsuccessful party to invoke Section 9 of the
Act would prevent irreparable prejudice and preserve the efficacy of the
challenge proceedings. However, the rights of such a party cannot be curtailed
merely on the apprehension of possible misuse of a statutory provision.
Thus, in Home Care Retail Marts Pvt. Ltd., the Apex Court
33)
has held that the judgment of Division Bench of this Court in Dirk India,
and other judgments of Delhi, Madras and Karnataka High Courts taking
similar view, do not lay down good law. The conclusions in the judgment
in para-61 and 62 are as under:
61.  For the aforesaid reasons, this Court holds that the judgments of the
Bombay, Delhi, Madras, and Karnataka High Courts insofar as they deny an
opportunity to unsuccessful parties in arbitration to apply for relief under
Section 9, do not lay down good law. The contrary views expressed by the
Telangana, Gujarat, and Punjab & Haryana High Courts correctly reflect the
statutory position.
62.  Consequently, this Court holds that any party to an arbitration agreement,
including an unsuccessful party in arbitration, may invoke Section 9 of the Act
at the post-award stage. However, the Courts would be well advised to exercise
care, caution and circumspection while dealing with a Section 9 application
filed by an unsuccessful party in arbitration.
____________________________________________________________________________
PAGE NO. 21 of 33
06 MAY 2026
::: Uploaded on - 06/05/2026 ::: Downloaded on - 06/05/2026 21:03:00 :::

Neeta Sawant CARBP(L) 15345 OF 2026

34) In the present case, Petitioner is largely unsuccessful in the
arbitral proceedings as it has the liability to pay higher amount to the
Respondent under the Award ( INR 271.12 crores) as compared to its
entitlement to receive amount of INR 42.95 crores. However, applying
the ratio of the judgment in Home Care Retail Marts Pvt. Ltd.,
Petitioner can still maintain application under Section 9 of the
Arbitration Act for seeking post-award interim measures. Petitioner is
hopeful of Section 34 Court setting aside part of the Award which seeks
to award a sum of INR 271.12 crores in favour of Respondent. This is why
Petitioner wants continuance of security in respect of sum of INR 42.95
crores awarded in its favour which represents 35% LD levied by it.
Petitioner thus claims post-award interim measures in its capacity as
‘partially successful party’. Additionally, the Petitioner believes that it is
would also receive from Section 34 Court balance 65% LD amount from
the Respondent and therefore wants the entire 100% LD amount of INR
122.73 crores being secured by the Respondent. Thus, even in capacity as
‘unsuccessful party’, Petitioner is seeking interim measures under
Section 9 of the Arbitration Act. The Petition is thus maintainable in
view of law enunciated in judgment in Home Care Retail Marts Pvt. Ltd.
and the objection of maintainability sought to be raised by Mr. Nankani
deserves to be repelled.
35) Petitioner’s insistence on renewal/extension of the bank
guarantee is otherwise not entirely misplaced since it got prevented from
deducting 100% LD amount of INR 122.73 crores on account of
Respondent securing the same by a bank guarantee. Under contractual
____________________________________________________________________________
PAGE NO. 22 of 33
06 MAY 2026
::: Uploaded on - 06/05/2026 ::: Downloaded on - 06/05/2026 21:03:00 :::

Neeta Sawant CARBP(L) 15345 OF 2026

clause 6.3.4, Respondent furnished bank guarantee of INR 150.35 crores
(representing 10% contract price) and asked for release of LD amount.
This is a reason why Petitioner-ONGC insists that till dispute over LD
amount is resolved by Section 34 Court, Respondent must keep the bank
guarantee renewed and extended. The issue for consideration is whether
this interim measure needs to be made under Section 9 of the Arbitration
Act, in the facts and circumstances of the present case?
36) As observed above, the Apex Court in Home Care Retail
Marts Pvt. Ltd., while recognising right of an unsuccessful party to seek
post-award interim measures under Section 9 of the Act, has prescribed a
caution that such interim measures can be made only in rare and
compelling cases and that the threshold for grant of such interim
measures needs to be higher in case of unsuccessful party. Thus, interim
measures under Section 9 of the Arbitration Act cannot be sought by an
unsuccessful party only on the strength of usual parameters of prima
facie case, balance of convenience and irreparable injury. Something
more needs to be demonstrated by unsuccessful party for seeking interim
measures under Section 9 in a post-award scenario.
37) Whether Petitioner has made out rare and compelling case
and whether it crosses the higher threshold is the issue for consideration
in the facts of the present case. Petitioner’s case is that the Arbitral
Tribunal has applied completely erroneous methodology while
restricting the LD to only 35%. According to the Petitioner, even going
by Tribunal’s erroneous computation of delay attributable to Respondent
____________________________________________________________________________
PAGE NO. 23 of 33
06 MAY 2026
::: Uploaded on - 06/05/2026 ::: Downloaded on - 06/05/2026 21:03:00 :::

Neeta Sawant CARBP(L) 15345 OF 2026

of 177 days, the LD at contractual weekly rate would translate to 13% of
contract price. However, since there is contractual cap of 10%, Petitioner
is entitled to levy liquidated damages upto the full cap of 10%.
Additionally, Petitioner has also sought to criticize the Tribunal while
computing the delay. However, even if the alleged error in computation
of delay is momentarily ignored, it prima facie appears that Petitioner
may be entitled to levy full 10% liquidated damages even for 177 days
( erroneously computed by the Tribunal as per Petitioner ). Thus, Petitioner
has made out a strong prima facie case of error in restricting the LD to
only 35% though it ought to be 13% (restrictable to contractual cap of
10%) even going by Tribunal’s own computation of delay days. Without
going into the evidentiary aspect of responsibility for delay and number
of delays attributable to the Respondents, Petitioner has set up a prima
facie case that the LD amount could not have been restricted to only
35%. This would be the first rare and compelling circumstance for
making interim measures in favour of Petitioner/ONGC.

38) There is yet another strong, rare and compelling
circumstance in favor of Petitioner-ONGC. As observed above, if
Respondent-L&T was not to submit the bank guarantee, ONGC would
have deducted the amount of liquidated damages from its running bills.
Thus, by submitting the bank guarantee, Respondent prevented ONGC
from deducting the LD. Thus, the bank guarantee was not submitted for
securing performance or for ensuring quality of work. It was submitted
by way of an assurance for Respondent refunding the amount of LD.
During arbitral proceedings, Respondent renewed and extended the bank
____________________________________________________________________________
PAGE NO. 24 of 33
06 MAY 2026
::: Uploaded on - 06/05/2026 ::: Downloaded on - 06/05/2026 21:03:00 :::

Neeta Sawant CARBP(L) 15345 OF 2026

guarantee rather than refunding the amount of LD to ONGC. Now, out
of the total LD levied of approximately INR 122.73 crores, the Tribunal
itself has awarded the Petitioner 35% LD amount of approximately INR
42.95 crores ( USD 28,25,336.00 + EURO 1,49,168.00 + INR 14,52,12,198) .
The Respondent-L&T has not challenged the Award and accordingly
Petitioner’s entitlement to secure sum of INR 42.95 crores is crystallised.
If Petitioner’s case is to be prima facie believed, it may be successful in
securing entire 100% LD amount of 122.73 crores also. In such
circumstances, a party, who prevents the other party from deducting the
amount of LD by giving assurance of bank guarantee, needs to continue
that assurance at least qua the amount awarded by the Arbitral Tribunal.
39) The claim awarded in favour of the Respondent of INR
271.12 crores cannot be confused with Petitioner’s entitlement to
receive LD amount of Rs.42.95 crores awarded by the Tribunal and its
claim for remaining 65% LD amount raised in Section 34 Petition. The
amount of INR 42.95 crores is actually Petitioner’s amount lying with the
Respondent for which security of bank guarantee is furnished by the
Respondent. Therefore the principle of set off cannot be applied in the
present case while determining the entitlement of ONGC to have a
continuing security in respect of its LD claim. What is awarded to L&T is
something recoverable towards alleged additional work. On the contrary,
what is awarded to ONGC is in the nature of directions for refund of
amount enjoyed by L&T by submitting the bank guarantee. Respondent
has not questioned its liability to refund INR 42.95 crores to the
Respondent. In such circumstances, if Respondent wants to avoid refund
____________________________________________________________________________
PAGE NO. 25 of 33
06 MAY 2026
::: Uploaded on - 06/05/2026 ::: Downloaded on - 06/05/2026 21:03:00 :::

Neeta Sawant CARBP(L) 15345 OF 2026

of 35% LD of INR 42.95 crores by relying on the figure of INR 271.12
crores awarded in its favour, it can be permitted to do so, but the least
that it needs to do is to extend and keep renewed the bank guarantee.
40) There is yet another factor which operates in favour of the
Petitioner for making interim measures of extension and renewal of the
bank guarantee. In the original Award dated 30 December 2024, the
Arbitral Tribunal had issued following directions:
321. For Claim No.1: Claims for extension of Time and Consequential Release
of Bank Guarantee in Lieu of Liquidated Damages + Related Compensation
Claims.
Counterclaim No.1: Refund of Amounts paid in return of Bank Guarantees in
lieu of Liquidated Damages
(i) Respondent is hereby directed to return to Claimant, the Bank
st
Guarantee No. 00040100008747 dated 21 August 2015 from Axis Bank
Limited, for the amount of USD 9,710,490 plus EURO 529,370 plus INR
52,42,50,100 which has been submitted to Respndent under clause 6.3.2
of the Contract by Claimant.
(ii) Respondent is entitled to levy LD on Claimant to the extent of 35%
of the LD imposed by it already which amounts to USD 2,825,336 + EUR
149,168 + INR 14,52,12,19. The above amount has to be paid by
Claimant to Respondent within 30 days from the date of this award.
(ii) the remaining amounts amounting to 65% of the LD imposed by
Respondent must be refunded to Claimant within 30 days from the date
of this award.
(iv) The return of the Bank Guarantee is subject to Claimant making the
above directed payment to Respondent.
41) Thus, as per the original Award, Respondent was to receive
back the bank guarantee only upon making payment of 35% LD of USD
28,25,336 + EURO 1,49,168 + INR 14,52,12,198 ( approximately INR 42.95
____________________________________________________________________________
PAGE NO. 26 of 33
06 MAY 2026
::: Uploaded on - 06/05/2026 ::: Downloaded on - 06/05/2026 21:03:00 :::

Neeta Sawant CARBP(L) 15345 OF 2026

crores) . This direction is altered in the Additional Award, made a year
later, by issuing following direction in para-61:
61. Upon consideration of the submissions and perusal of the Award, the
Tribunal deems it appropriate to allow the rectification sought by Claimant
and delete sub-paras (ii) and (iv) of paragraph 321 of the Award. Accordingly,
paragraph 321(ii) of the Operative Section of the Award shall stand substituted
as follows:
“ The respective amounts payable by Claimant and Respondent under
this Award shall be subject to mutual adjustment, and only the net
amount , after such adjustment, shall remain payable by the Party
against whom the balance is found due. The said adjustment shall be
effected wthin 30 days from the date of this Award. ”
Thus, what was originally granted in favour of the
42)
Petitioner-ONGC is taken away by making Additional Award and
correctness of this direction is questioned by the Petitioner submitting
that the same is beyond powers under Section 33 of the Arbitration Act.
If the Additional Award was not made, Respondent would have been
liable to pay the Petitioner amount of 35% LD as a precondition for
return of the bank guarantee.
43) In Home Care Retail Marts Pvt. Ltd. (supra), the Apex Court
has held in para-50 of the judgment that Section 9 Court can grant ‘non
prejudicial’ interim relief in favour of unsuccessful party, particularly
when such relief does not affect the enforceability of Award but merely
preserves ancillary rights pending adjudication under Section 34 of the
Arbitration Act. In my view, the present case perfectly meets the said
parameter set forth by the Hon’ble Apex Court in para-50 of the
judgment. Directing Respondent to extend and renew bank guarantee
____________________________________________________________________________
PAGE NO. 27 of 33
06 MAY 2026
::: Uploaded on - 06/05/2026 ::: Downloaded on - 06/05/2026 21:03:00 :::

Neeta Sawant CARBP(L) 15345 OF 2026

does not come in the way of enforceability of the Award. Even after
renewing the bank guarantee, Respondent can enforce the Award and
recover the awarded sum of INR 271.12 crores. Thus, directing interim
measures in Section 9 petition in favour of the Petitioner merely
preserves the ancillary rights of parties pending adjudication under
Section 34 of the Act.
44) In my view therefore, a rare and compelling case is made out
for grant of interim measures in favour of the Petitioner even though it is
largely an unsuccessful party in the arbitral proceedings. It has not
completely failed in the arbitration and is partly successful. It is just that
Respondent is awarded higher amount than the one awarded in favour of
the Petitioner. As observed above, part of the amount covered by the
bank guarantee is actually ONGC’s money, which is utilised by
Respondent-L&T. ONGC was entitled to deduct the same from bills of
L&T. However, L&T prevented ONGC from making such deductions by
furnishing a bank guarantee. Now that ONGC’s entitlement for such
deduction of LD is partially upheld, L&T cannot be heard to say that it
would neither refund LD amount nor even secure the same till ONGC
gets adjudicated the awarded claims of L&T as well as rejection of claim
for 65% LD. The consequences of ONGC succeeding in Section 34
petition would be that L&T’s claims of INR 271.12 crores would be set
aside and it would have the liability to pay at least INR 42.95 crores to
ONGC. If ONGC further succeeds in Section 34 petition in establishing
that it is entitled for levy of 100% LD of INR 122.73 crores, L&T will have
liability to pay amount of INR 122.73 crores to the Petitioner. Even if
____________________________________________________________________________
PAGE NO. 28 of 33
06 MAY 2026
::: Uploaded on - 06/05/2026 ::: Downloaded on - 06/05/2026 21:03:00 :::

Neeta Sawant CARBP(L) 15345 OF 2026

Section 34 Court stops at setting aside the Award, L&T’s claim of INR
271.12 crores would get nullified, Petitioner’s claim for refund of INR
42.95 crores would still survive and Petitioner would be entitled to
arbitrate again for recovery of balance 65% LD amount from L&T. Thus,
in both scenarios, L&T’s liability to secure 100% LD amount may
continue. In my view therefore, a very strong, rare and compelling case is
made out by Petitioner-ONGC for grant of interim measures.
45) Also, all that is sought by ONGC is mere extension and
renewal of bank guarantee which is continuing for last more than a
decade. It is not that ONGC would invoke or encash the renewed bank
guarantee. This would ensure that L&T can retain monies of ONGC at
least to the extent of INR 42.95 crores during pendency of Section 34
petition on the strength of award of claims to the tune of INR 271.12
crores in its favour. All that needs to be done for retaining in its pockets
the monies of ONGC, is to extend and renew the bank guarantee. This, in
my view, would be the bare minimum that L&T needs to do.
46) There is yet another angle from which the necessity for
extension and renewal of bank guarantee by L&T can be viewed. In the
event Section 34 Court directs ONGC to deposit the net awarded sum
with interest as a pre-condition for stay of execution of the Award,
L&T’s interests would get protected while leaving ONGC in lurch
without any security either in respect of 35% awarded LD or 100%
claimed LD. In the event of ONGC succeeding in the Section 34 Petition,
there would be no security left for ONGC for recovery of awarded 35% LD
____________________________________________________________________________
PAGE NO. 29 of 33
06 MAY 2026
::: Uploaded on - 06/05/2026 ::: Downloaded on - 06/05/2026 21:03:00 :::

Neeta Sawant CARBP(L) 15345 OF 2026

amount. Here it must be borne in mind that what is awarded by the
Tribunal is entitlement of Petitioner-ONGC to seek refund of 35% LD
amount, which could have been deducted by it while paying
Respondent’s bills, but not deducted on account of assurance in the form
of a bank guarantee In para-49 of the judgment in Home Care Retail
Marts Pvt. Ltd., the Apex Court has dealt with a situation where an
unsuccessful party who has obtained interim protection during arbitral
proceedings of stay on invocation of bank guarantee can pray for
continuation of the same during pendency of objections to the Award
under Section 34. Here the situation is converse where the Tribunal had
directed L&T to keep alive the bank guarantee to secure Petitioner’s
claim for refund of LD. Since LD claim is partially granted in ONGC’s
favour, I do not see any reason why the bank guarantee needs to be
returned to L&T during pendency of Section 34 petition.
47) The objection of Mr. Nankani about maintainability of the
present Petition in the light of filing of Section 34 Petition and pendency
of Section 36(3) Application is misplaced. The Apex Court has held, in no
uncertain terms, in paras-42 and 43 of the judgment in Home Care
Retail Marts Pvt. Ltd. that ‘ an unsuccessful party cannot secure protection
of its claim under Section 34 or Section 36’. Thus, Petitioner cannot expect
interim relief from Section 34 Court as that Court can merely stay
execution of the Award subject to deposit of the full or net awarded sum.
Therefore, Section 9 is the correct remedy available for the Petitioner for
the purpose of securing ancillary rights pending adjudication of Section
34 Petition.
____________________________________________________________________________
PAGE NO. 30 of 33
06 MAY 2026
::: Uploaded on - 06/05/2026 ::: Downloaded on - 06/05/2026 21:03:00 :::

Neeta Sawant CARBP(L) 15345 OF 2026

48) Reliance by Mr. Nankani on judgment of this Court in ONGC
vs Punj Lloyd (supra) is inapposite. The judgment is delivered squarely
by relying on the judgment in Dirk India, which is no longer a good law.
Also, in para-16 of the judgment, learned Single Judge of this Court has
held that Section 34 Court can only set aside the Award resulting in fresh
round of arbitration. In paras-44 and 45 of the judgment in Home Care
Retail Marts Pvt. Ltd. (supra), the Apex Court has held this premise to
be entirely erroneous on account of authoritative ruling by the
Constitution Bench in Gayatri Balasamy (supra). Thus, the very basis of
the judgment of this Court in is held to be
ONGC vs. Punj Lloyd
erroneous by the Apex Court in Home Care Retail Marts Pvt. Ltd.
Similar is the position in respect of the judgment of Division Bench of
this Court in ONGC vs. Consortium of Sime Darby Engineering (supra)
which squarely follows the judgment of this Court in Dirk India and of
Delhi High Court in Nussli Switzerland Ltd. v. Organising Committee
7
Commonwealth Games , both of which are held to be not laying down
good law by the Apex Court in Home Care Retail Marts Pvt. Ltd.. The
judgment of Delhi High Court in Mukti Credits Pvt. Ltd. (supra) is not of
much relevance for deciding the issue at hand. This Court has not gone
into the merits of the award while deciding the issue of grant of interim
measures in a post-Award scenario.
49) In view of the above discussion, Petitioner has clearly
crossed the higher threshold for making interim measures in the facts of
the present case. It has made out a very strong prima facie case for
7 (2014) 145 DRJ 399
____________________________________________________________________________
PAGE NO. 31 of 33
06 MAY 2026
::: Uploaded on - 06/05/2026 ::: Downloaded on - 06/05/2026 21:03:00 :::

Neeta Sawant CARBP(L) 15345 OF 2026

directing extension and renewal of the bank guarantee. Petitioner would
suffer irreparable injury if the security, which it holds for the last more
than a decade for the LD, is permitted to be terminated by not renewing
the bank guarantee. The balance of convenience is also in favour of the
Petitioner as the interim measures proposed to be granted are mere
protective measures which would preserve status quo until Section 34
Petition is adjudicated as opposed to severe consequences involved in
releasing the security against which public monies are parted with by
Petitioner in favour of Respondent. Respondent would only have an
obligation to extend the bank guarantee which has been in existence for
over a decade. Refusal of interim measures would result in a manifest
disproportion as the Petitioner would lose the security worth 10% of
contract price while Respondent’s only burden is the continued
existence of the bank guarantee. Petitioner has assured this Court that it
would not invoke or encash the bank guarantee and this balances out the
scale of equities. In my view therefore, higher threshold is clearly made
out by the Petitioner though it is not a fully successful party in arbitral
proceedings. In fact, denial of interim measures in the facts of this case
would cause violence to the ratio of judgment of the Apex Court in Home
Care Retail Marts Pvt. Ltd. The Respondent-L&T therefore needs to be
directed by way of interim measures to secure the subject matter of
arbitration, being LD claim of the Petitioner, during pendency of Section
34 Petition.
____________________________________________________________________________
PAGE NO. 32 of 33
06 MAY 2026
::: Uploaded on - 06/05/2026 ::: Downloaded on - 06/05/2026 21:03:00 :::

Neeta Sawant CARBP(L) 15345 OF 2026

O RDER
50) I accordingly proceed to pass the following Order:
Until the hearing and final disposal of Commercial
Arbitration Petition (L) No. 9373 of 2026 filed by the
Petitioner under Section 34 of the Arbitration Act, the
Respondent shall extend and keep alive the Bank Guarantee
No. 00040100008747 dated 21 August 2015 issued by Axis
Bank Limited, for the amount of USD 9,710,490/- plus EUR
529,370/- plus INR 52,42,50,100/- provided to the Petitioner
towards liquidated damages as per Clauses 6.3.2 and 6.3.4 of
the Contract dated 3 July 2010 and in the event the same has
expired for any reason, Respondent shall forthwith furnish a
fresh and equivalent bank guarantee in favour of the
Petitioner for an amount of USD 97,10,490/- plus EUR
5,29,370/- plus INR 52,42,50,100/-.
51) With the above directions, the Petition is allowed and
disposed of. There shall be no order as to costs.
[SANDEEP V. MARNE, J.]

____________________________________________________________________________
PAGE NO. 33 of 33
NEETA
SHAILESH
06 MAY 2026
SAWANT
Digitally
signed by
NEETA
SHAILESH
SAWANT
Date:
2026.05.06
20:47:25
+0530
::: Uploaded on - 06/05/2026 ::: Downloaded on - 06/05/2026 21:03:00 :::