M/S Kawatra Hospitality Pvt. Ltd. Through, Its Director/Authorized Representative vs The Director (R.P.Cell), Delhi Urban Shelter Improvement Board & Anr.
- Court
- Delhi High Court
$~
* IN THE HIGH COURT OF DELHI AT NEW DELHI
% Judgment reserved on: 22.07.2026
Judgment pronounced on: 03.08.2026
Judgment uploaded on: 03.08.2026
+ W.P.(C) 8508/2026 & CM APPL. 39547/2026
M/S KAWATRA HOSPITALITY PVT. LTD. THROUGH,
ITS
DIRECTOR/AUTHORIZED REPRESENTATIVE ..Petitioner
Through: Mr. Rakesh Tiku, Senior
Advocate with Mr. Mankan
Deep Singh and Ms. Nida
Akhtar, Advocates
versus
THE DIRECTOR (R.P.CELL), DELHI URBAN SHELTER
IMPROVEMENT BOARD & ANR. .....Respondents
Through: Mr. Rishikant Singh and Mr.
Manoj Jadly, Advocates for
DUSIB.
CORAM:
HON’BLE DR. JUSTICE SWARANA KANTA SHARMA
JUDGMENT
DR. SWARANA KANTA SHARMA, J
1. By way of the present writ petition, the petitioner – M/s
Kawatra Hospitality Pvt. Ltd. – seeks grant of following reliefs:
―a) Issue a writ of mandamus or any other appropriate writ
thereby directing respondents to issue fresh ―notice inviting
tender‖ for the subject land i.e. chunk-B at West Delhi District
Centre, Shivaji Place, Raja Garden, New Delhi and complete
W.P. (C) 8508/2026 Page 1 of 22
Signature Not Verified
Digitally Signed
By:ZEENAT PRAVEEN
Signing Date:03.08.2026
19:56:02
the fresh tender process within the reasonable time frame in a
fair and just manner for allotment of Subject land afresh;
and/or.
b) Issue a writ of prohibition or any other appropriate writ
thereby restraining the respondents no. 1 and from taking back
possession of subject land i.e. chunk-B at West Delhi District
Centre, Shivaji Place, Raja Garden, New Delhi till completion
of fresh tendering process and execution of fresh allotment of
subject land i.e., chunk-B at West Delhi District Centre, Shivaji
Place, Raja Garden, New Delhi in order to save government
ex-chequer as well as financial losses of petitioner…‖
FACTUAL BACKGROUND
2. The petitioner is a private limited company engaged in the
business of organizing marriages and other functions/events.
Respondent nos. 1 and 2 are the Director and Deputy Director, R.P.
Cell of the Delhi Urban Shelter Improvement Board [hereafter
‗ DUSIB ‘]. It is stated that they are the authorities responsible for
issuing tenders and allotting vacant/open lands belonging to DUSIB.
They are also stated to be responsible for the allotment and tendering
of vacant land parcels, designated as Chunks, situated at District
Centre, West Delhi, Shivaji Place, Raja Garden, New Delhi. The
petitioner is aggrieved by the action of the respondents in requiring it
to vacate the land designated as ‗Chunk-B‘ [hereafter ‗ subject land ‘]
pursuant to letters dated 10.06.2026 and 25.06.2026, whereby it was
directed to remove the pandals erected on the subject land and hand
over its vacant possession to the respondents.
3. The petitioner states that DUSIB had issued a Notice Inviting
Tender dated 05.10.2023 for allotment of eight land sites under its
W.P. (C) 8508/2026 Page 2 of 22
Signature Not Verified
Digitally Signed
By:ZEENAT PRAVEEN
Signing Date:03.08.2026
19:56:02
management, including the subject land, for a period of two years
commencing from 27.12.2023 and ending on 26.12.2025. The
petitioner participated in the tender process in accordance with the
terms and conditions stipulated therein and was declared the
successful bidder for allotment of the subject land. Consequently, a
Letter of Acceptance was issued on 15.11.2023, pursuant to which
the petitioner furnished the requisite documents and bank guarantees.
Thereafter, an Agreement dated 27.12.2023 [hereafter ‗ the
Agreement ‘] incorporating the terms and conditions contained in the
Notice Inviting Tender was executed between the petitioner and the
respondents through their authorized signatories. Prior thereto, a
letter of commencement dated 15.12.2023 was issued and thereafter
possession of the subject land was handed over to the petitioner vide
possession letter 26.12.2023.
4. It is stated that as the original tenure of allotment was to expire
on 26.12.2025 and no fresh tender process had been initiated by the
respondents for allotment of the subject land, the petitioner was
granted an extension of three months on 24.12.2025 on the same
terms and conditions as contained in the Agreement. Thereafter, upon
expiry of the said extended period and in the absence of any fresh
tender process, the respondents granted a further extension of three
months by way of letter dated 25.03.2026, again on the same terms
and conditions.
5. According to the petitioner, instead of initiating the process for
issuance of a fresh tender for the subject land, the respondents issued
W.P. (C) 8508/2026 Page 3 of 22
Signature Not Verified
Digitally Signed
By:ZEENAT PRAVEEN
Signing Date:03.08.2026
19:56:02
a communication dated 10.06.2026 directing the petitioner to vacate
the subject land and hand over its peaceful possession,
notwithstanding the substantial investments allegedly made by the
petitioner in developing and operating the site. The petitioner
contends that this action is contrary to the terms of the agreement,
under which the agreement was to continue until the execution of a
fresh agreement with the successful bidder pursuant to a fresh tender
process.
6. The grievance of the petitioner is essentially founded on the
contention that, under the terms of the Agreement, DUSIB was under
an obligation to initiate and complete the process of fresh tendering
before requiring the petitioner to vacate the subject land. Reliance has
been placed upon the following clause of the Agreement:
"If, the department could not finalize the auction process up to
the date of completion of agreement, the agreement period can
be further extended by DUSIB on quarterly basis up to a period
of six months on the same terms and conditions. During this
period the e-auction process for awarding new agreement shall
be completed by DUSIB. The old agreement will come an end
from the date of executing the new agreement of Chunk."
7. The petitioner further contends that upon receipt of the
communication dated 10.06.2026, its directors approached the
respondents requesting that the allotment be continued at least until
the fresh tender process was initiated and completed. It is stated that
the petitioner had, under the bona fide belief that the Agreement
would continue in the same manner as on the previous occasions,
accepted bookings for future functions at the subject land. According
W.P. (C) 8508/2026 Page 4 of 22
Signature Not Verified
Digitally Signed
By:ZEENAT PRAVEEN
Signing Date:03.08.2026
19:56:02
to the petitioner, the officials of the respondents assured it that
extension of the Agreement till completion of the fresh tender process
would be considered, particularly since the fresh tender process ought
to have been completed before expiry of the second extended period.
However, instead of considering the said request, the respondents
issued another communication dated 25.06.2026 directing the
petitioner to vacate the subject land and warning of financial
consequences in the event of non-compliance, thereby allegedly
causing the petitioner substantial financial loss.
SUBMISSIONS BEFORE THE COURT
8. The learned senior counsel appearing for the argues that it was
incumbent upon the respondents to complete the fresh tender process
before the expiry of the extended period of the Agreement. It is
argued that, instead of discharging their obligation to initiate and
complete the fresh tender process, DUSIB has adopted a practice of
directing the allottee to vacate the subject land, without due regard to
the interest of the Government exchequer as well as the financial
losses likely to be suffered by the petitioner on account of the
investments made by it in the subject land. It is submitted that the
respondents had adopted a similar course of action in the past,
compelling the petitioner to approach this Court by way of W.P.(C)
No. 2164/2018 and W.P.(C) No. 6784/2020 . It is stated that in the
said writ petitions, this Court had granted interim protection in
respect of possession of the subject land by directing maintenance of
W.P. (C) 8508/2026 Page 5 of 22
Signature Not Verified
Digitally Signed
By:ZEENAT PRAVEEN
Signing Date:03.08.2026
19:56:02
status quo till completion of the fresh tender process. In support of
the said contention, the learned senior counsel draws this Court's
attention to the orders dated 08.03.2018 and 28.09.2020, passed in
W.P.(C) No. 2164/2018 and W.P.(C) No. 6784/2020 respectively,
which read as under:
(i) Order dated 08.03.2018 in W.P.(C) No. 2164/2018
―4. It is the submission of the learned counsel for the petitioner
that the petitioner is, currently, in possession of the subject
property which was allotted in furtherance of a public auction.
It is averred, pursuant to the petitioner being declared a
successful bidder, an agreement dated 07.03.2016 was
executed between petitioner and respondents having a tenure of
2 years.
5. Concededly, the tenure of agreement dated 07.03.2016 has
ended on 28.02.2018. It is not disputed that thereafter the
respondents have once again held an auction, qua which, the
petitioner claims that it is the highest bidder.
6. Ms. Pushkarna, who appears on advance notice does not
dispute this position.
7. Counsel for the petitioner says that the fresh bid in terms of
value is (approximately) 20% more than the earlier bid and
therefore, the respondents stand to gain if they were to accept
the petitioner's bid.
8. The petitioner, in these circumstances, for the moment, prays
for maintenance of status quo as it has invested money in the
infrastructure which has been put up on the subject property,
which would, get disrupted if possession is taken, in the
interregnum, by the respondents.
9. Prima facie, there appears to be merit in the contention
advanced on behalf of the petitioner. In case petitioner is
declared a successful bidder, the possession of the subject
property would have to be returned to it. taking over possession
at this stage would cause undue disruption, expenses to the
petitioner and loss of revenue to the respondents.
10. Accordingly, the respondents are directed to maintain
status quo, qua possession of the subject property, till next date
W.P. (C) 8508/2026 Page 6 of 22
Signature Not Verified
Digitally Signed
By:ZEENAT PRAVEEN
Signing Date:03.08.2026
19:56:02
of hearing by which time, I am told, they will take a final
decision on the bid submitted by the petitioner.
11. To be noted, Mr. Rakesh Tiku, on instructions, offers to
pay the enhanced monthly licence fee as per the revised tender
bid. The said statement is taken on record. In the event
enhanced monthly license fee is not paid, the interim protection
granted by this Court will automatically dissolve.‖
(ii) Order dated 28.09.2020 in W.P.(C) No. 6784/2020
―3. Mr. Anil Sapra, learned Senior Advocate appearing for the
petitioner in WP(C) No. 6784/2020, Mr. Sudhir Nandrajog,
learned Sr. Advocate appearing for the petitioner in WP(C)
Nos. 6786/2020 & 6788/2020 and Mr. Pushkar Sood, learned
counsel appearing for the petitioner in WP(C) No. 7113/2020
state on instructions that their clients are proposing to submit
their bids in respect of the fresh NIT issued by the
respondent/DUSIB on 14.9.2020. They request that in the
event they are not declared as H-1 in the subject NIT issued on
14.9.2020, they be given a reasonable time to hand over vacant
peaceful possession of the chunks of land under their
occupation by removing the temporary structures raised
thereon.
4. Mr. Chauhan learned counsel for the respondent/DUSIB
states on instructions that if the petitioners are ready and
willing to file their affidavits in their respective petitions,
giving an undertaking to the court on the aforesaid lines then,
without prejudice to the right of the DUSIB to recover the
arrears of licence fee/occupation charges in respect of the
chunks of land under the occupation of the petitioners in
accordance with law, they will not take any coercive steps
against them for the period as may be ordered by the court.
5. In view of the submissions made hereinabove with the
consent of parties, the present petitions are disposed of with the
following directions:-
i) Each of the petitioners shall file an affidavit/undertaking
stating inter alia that in the event they are not declared as
the successful bidders in the subject tender floated by the
respondent/DUSIB on 14.9.2020, then they shall hand over
the vacant peaceful physical possession of the respective
chunks of land under their occupation to the
W.P. (C) 8508/2026 Page 7 of 22
Signature Not Verified
Digitally Signed
By:ZEENAT PRAVEEN
Signing Date:03.08.2026
19:56:02
respondent/DUSIB within 10 working days reckoned from
the date DUSIB finalises the highest bidder. The aforesaid
undertaking shall be filed on or before 03.10.2020, with
copies furnished to other side.
ii) Without prejudice to its right to recover the arrears of
licence fee and occupation charges from the petitioners, the
respondent/DUSIB shall not take any coercive steps against
the petitioners for a period of 10 days reckoned from the
date of declaration of the highest bidder in respect of the
chunk of land under their occupation…‖
9. It is further contended that, in terms of Clause 6 of the
Agreement, the respondents were under an obligation to issue a fresh
Notice Inviting Tender and commence the process of fresh allotment
of the subject land before requiring the petitioner to vacate the same.
It is, therefore, argued that the issuance of the impugned letters
without initiation of the fresh tender process is contrary to the express
terms of the contract.
10. The learned senior counsel further submits that the respondents
are fully aware that the petitioner has made substantial investments in
the subject land to render it suitable for the purpose for which it had
been allotted. It is argued that if the petitioner is compelled to vacate
the subject land before completion of the fresh tender process, it
would not only cause the petitioner substantial financial loss but
would also result in loss to the Government exchequer. He contends
that the action of the respondents is arbitrary and unreasonable. It is
also submitted that, as on the previous occasions, the petitioner is
willing to continue paying the licence fee, and even a higher amount
if so required, till the fresh tender process is concluded. It is stated
W.P. (C) 8508/2026 Page 8 of 22
Signature Not Verified
Digitally Signed
By:ZEENAT PRAVEEN
Signing Date:03.08.2026
19:56:02
that, in the event the petitioner is unsuccessful in the fresh tender
process, it shall hand over vacant possession of the subject land. On
these grounds, it is prayed that the present petition be allowed.
11. On the other hand , the learned counsel appearing for the
respondents/DUSIB opposes the present writ petition. The learned
counsel has also obtained instructions from DUSIB, which have been
placed on record. On the strength of the said instructions, he makes
the following submissions. It is submitted that the Agreement itself
does not contemplate grant of any extension beyond the cumulative
period of six months. Therefore, upon expiry of the extended period,
the contractual relationship between DUSIB and the petitioner came
to an end by efflux of time, and the petitioner has no contractual or
legal right to continue in possession of the subject land. It is further
contended that the petitioner‘s apprehension regarding loss to the
Government exchequer is misconceived, since DUSIB is presently in
the process of finalizing the fresh e-auction for allotment of the
marriage chunks, including the subject land, and the process is likely
to be completed within a short period. Thus, according to the
respondents, no loss to the Government exchequer is occasioned.
12. The learned counsel further submits that in order to ensure a
fair, transparent and competitive e-auction process, it is important
that vacant and unencumbered possession of the subject land is
available so that all prospective bidders are afforded an equal
opportunity to inspect the site and participate in the bidding process
on a level playing field. It is also argued that permitting the petitioner
W.P. (C) 8508/2026 Page 9 of 22
Signature Not Verified
Digitally Signed
By:ZEENAT PRAVEEN
Signing Date:03.08.2026
19:56:02
to continue in possession beyond the expiry of the contractual period,
in the absence of any contractual or statutory right, would be contrary
to the terms of the Agreement and would adversely affect the
transparency and fairness of the proposed e-auction process. Such
continuation, according to the respondents, would confer an undue
advantage upon the existing licensee to the prejudice of other
prospective bidders, who may be discouraged from participating in
the auction. It is further submitted that the continued existence of the
structures erected by the petitioner on the subject land would prevent
prospective bidders from making a proper assessment of the site.
13. The learned counsel also places reliance upon the decision of
this Court in W.P.(C) No. 12877/2023 along with CM APPL. Nos.
50706/2023 and 50707/2023 , wherein, it is stated that this Court had
observed that the petitioner therein had never been granted an
indefinite right to occupy the land and had been operating only under
a time-bound licence. It is submitted that the ratio of the said decision
squarely applies to the facts of the present case. Lastly, it is submitted
that DUSIB, being the owner of the subject land, is entitled to resume
possession upon expiry of the licence period and retains the
discretion to manage and deal with its property in accordance with
law. It is therefore prayed that the present petition be dismissed.
ANALYSIS & FINDINGS
14. The principal grievance of the petitioner is that despite the
respondents having failed to initiate and complete the process of fresh
W.P. (C) 8508/2026 Page 10 of 22
Signature Not Verified
Digitally Signed
By:ZEENAT PRAVEEN
Signing Date:03.08.2026
19:56:02
tender for allotment of the subject land within the period stipulated
under the Agreement executed between the parties, the respondents
have directed the petitioner to vacate the subject land upon expiry of
the extended contractual period. According to the petitioner , the
respondents were contractually bound to complete the fresh tender
process before requiring the petitioner to hand over possession, and
in the absence thereof, the petitioner is entitled to continue in
possession till the execution of a fresh agreement with the successful
bidder pursuant to the fresh tender process.
15. In view of the aforesaid, the foremost issue that falls for
consideration is the nature and extent of the petitioner‘s right under
the Agreement executed with DUSIB. The answer to this issue would
determine whether, upon expiry of the contractual tenure and the
maximum period of extension contemplated under the Agreement,
the petitioner possesses any enforceable right to continue in
occupation of the subject land merely because the respondents have
not completed the fresh tender process.
i. Nature of the Petitioner’s Right under the Agreement
16. The nature of the right created in favour of the petitioner under
the Agreement executed between the parties has to be ascertained
from the terms of the Agreement itself, which forms the foundation
of the relationship between the parties.
17. Some of the relevant terms of the Agreement, as incorporated
in the Notice Inviting Tender dated 05.10.2023, are set out below:
W.P. (C) 8508/2026 Page 11 of 22
Signature Not Verified
Digitally Signed
By:ZEENAT PRAVEEN
Signing Date:03.08.2026
19:56:02
―4. The bid is invited for a period of 02 (Two) years i.e. from
the date of taking over the possession. After expiry of the
agreement period, the Second party shall hand over the
particular chunk to the official of the First party in vacant,
clean, clear and original condition in peaceful manner.
x x x
39. The permission by DUSIB shall be for a limited period
only for use as per E-Auction terms and conditions and
agreement related thereto. This does not create any tenéncy
rights enjoyable by the selected bidder.
40. The land of such site shall always remain the property of
DUSIB and the bidder shall not claim any right/ title or interest
to any right or any nature of easement in relation to or in
respect thereto…‖
18. A plain reading of Clause 4 makes it clear that the allotment in
favour of the petitioner was for a fixed and definite period of two
years commencing from the date of handing over of possession. The
clause further stipulates that upon expiry of the agreement period, the
petitioner was required to hand over vacant, clean and peaceful
possession of the subject land to the officials of DUSIB. Thus, the
Agreement itself contemplated that the petitioner‘s right to remain in
occupation of the subject land was co-terminus with the contractual
period, unless extended in accordance with the terms of the
agreement.
19. Further, Clauses 39 and 40 expressly define the nature of the
interest created in favour of the petitioner. Clause 39 clarifies that the
permission granted by DUSIB is only for a limited period and solely
for the purposes contemplated under the e-auction terms and the
agreement. More importantly, it unequivocally provides that such
W.P. (C) 8508/2026 Page 12 of 22
Signature Not Verified
Digitally Signed
By:ZEENAT PRAVEEN
Signing Date:03.08.2026
19:56:02
permission does not create any tenancy rights in favour of the
successful bidder. Clause 40 further elaborates the same position by
declaring that the ownership of the subject land shall at all times
remain vested in DUSIB and that the successful bidder shall not
claim any right, title, interest or easement in respect of the subject
land.
20. In this Court‘s opinion, the aforesaid Clauses of the Agreement
make the intention of the parties abundantly clear – that the
Agreement does not confer upon the petitioner any proprietary or
possessory interest in the subject land, beyond what is expressly
permitted under the Agreement. The petitioner‘s occupation of the
subject land is purely contractual, limited in duration, and subject to
the terms and conditions governing the allotment. The petitioner,
therefore, cannot claim any independent or vested right in the subject
land dehors the Agreement itself.
21. Thus, the relationship between the parties has to be governed
entirely by the contractual terms agreed upon between them, and
consequently, the rights and obligations of both parties will have to
necessarily be determined with reference to those contractual
stipulations.
ii. Whether the Petitioner Acquired Any Right to Continue in
Possession Beyond the Maximum Contractual Period
22. In these petitions, the principal contention of the petitioner is
founded upon Clause 6 of the Agreement. According to the
W.P. (C) 8508/2026 Page 13 of 22
Signature Not Verified
Digitally Signed
By:ZEENAT PRAVEEN
Signing Date:03.08.2026
19:56:02
petitioner, once the Agreement casts an obligation upon DUSIB to
complete the fresh e-auction process during the extended period of
the Agreement, i.e. six month, the DUSIB cannot call upon the
petitioner to vacate the subject land until such fresh tender process is
completed and a new agreement is executed.
23. Insofar as this contention is concerned, there is no cavil that
the terms of a contract cannot be read in isolation. Every clause of an
agreement has to be construed harmoniously with the other clauses so
as to give effect to the intention of the parties as gathered from the
contract – as a whole. Any interpretation, which renders one or more
stipulations of a contract redundant or otiose, is to be avoided.
24. This Court notes that Clauses 4 and 5 of the Agreement,
discussed hereinabove, clearly stipulate that the contract is for a fixed
period of two years and that upon expiry of the Agreement period,
the petitioner is obliged to hand over vacant and peaceful possession
of the subject land to DUSIB. Thus, the Agreement itself
contemplates that the petitioner‘s right to occupy the subject land is
only for a fixed tenure. Furthermore, Clause 6 of the Agreement,
upon which the petitioner has placed considerable reliance, also
cannot be read in isolation from the other clauses of the Agreement.
It is pertinent to note that Clause 6 of the Agreement provides that if
DUSIB is unable to finalize the auction process by the date of
completion of the Agreement, the Agreement period ― can be further
extended ‖ by DUSIB on a quarterly basis up to a period of six
months on the same terms and conditions. The use of the expression
W.P. (C) 8508/2026 Page 14 of 22
Signature Not Verified
Digitally Signed
By:ZEENAT PRAVEEN
Signing Date:03.08.2026
19:56:02
― can be further extended ‖ is of significance, since the clause does not
provide that the Agreement ‗shall‘ stand extended in every case. It
rather only enables DUSIB to grant an extension, subject to the outer
limit expressly prescribed in the Agreement itself. Equally significant
is the fact that the extension itself is restricted up to a period of six
months . Therefore, in this Court‘s view, the parties consciously
agreed not only to the original contractual tenure of two years but
also to the maximum period for which the contractual relationship
could continue beyond the original term of two years.
25. The petitioner, however, seeks to rely upon the part of Clause 6
which provides that during the extended period, the e-auction process
for awarding the new agreement shall be completed by DUSIB.
According to the petitioner, the use of the expression shall makes it
obligatory upon DUSIB to complete the tender process before
requiring the petitioner to vacate the subject land. However, having
carefully perused the entire Agreement, this Court is unable to accede
to such an interpretation.
26. There is no dispute that Clause 6 of the Agreement puts an
obligation on DUSIB to undertake and complete the fresh tender
process during the extended period of six months. However, the said
clause cannot be construed in a manner so as to nullify the express
contractual limitation contained in the very same Agreement. If the
interpretation forwarded by the petitioner were to be accepted, the
consequence of the same would be that irrespective of the express
provisions in the Agreement – restricting the period of contract to
W.P. (C) 8508/2026 Page 15 of 22
Signature Not Verified
Digitally Signed
By:ZEENAT PRAVEEN
Signing Date:03.08.2026
19:56:02
two years and the extension to a maximum period of six months – the
petitioner would continue to remain in possession until such time as
DUSIB completes the fresh tender process. Accepting such an
interpretation would effectively convert a fixed-term licence for the
subject land into one of an indefinite duration, dependent entirely
upon the completion of a future tender process. Concededly, the
parties have consciously not provided for any such consequence in
the Agreement. The expression that the e-auction process shall be
completed during the extended period of six months cannot,
therefore, be read in isolation or read in a manner so as to render
other clauses of the same Agreement null and void.
27. It is also pertinent to note that, in the present case, the
respondents had, in fact, exercised the discretion available under
Clause 6 by granting two successive extensions of three months each.
Consequently, the petitioner has enjoyed the benefit of the entire six-
month extended period contemplated under the Agreement. Once the
maximum contractual period stands exhausted, no further right to
continue in possession can be claimed only because the fresh tender
process has not been concluded. Failure on the part of DUSIB to
complete the tender process within the contemplated period can
expose it to criticism for administrative delays on its part, but such
failure cannot have the effect of enlarging the petitioner‘s contractual
rights beyond what was consciously agreed between the parties.
28. The aforesaid interpretation also finds support from the
judgment of the Division Bench of this Court in Kawatra Tent and
W.P. (C) 8508/2026 Page 16 of 22
Signature Not Verified
Digitally Signed
By:ZEENAT PRAVEEN
Signing Date:03.08.2026
19:56:02
Caterers Private Limited v. The Director (R.P. Cell) Delhi Urban
Shelter Improvement Board & Anr.: W.P.(C) No. 12877/2023 ,
wherein the Court was considering substantially similar contractual
clauses. The Division Bench held that the contractual relationship
between the parties was solely that of a licensee and licensor; that the
licence created no proprietary or vested rights in favour of the
licensee; that the agreement contemplated a fixed tenure with an
extendable period only up to six months; and that upon expiry of the
maximum contractual period, the licensee had no legal or inherent
right to continue in occupation of the land. The Division Bench
further held that investments made by the licensee on the land did not
confer any special right to seek continuation of the licence and that
contractual stipulations could not be ignored merely because of the
commercial consequences flowing from the expiry of the licence. The
relevant observations of the Division Bench in decision dated
03.10.2023 are set out below:
―7. The contractual clauses that define the relationship between
the parties are unambiguous. Petitioner‘s relationship with the
land is solely as a licensee, without any supplementary rights.
Both the initial and extendable durations of the license have
elapsed — a fact which is uncontested. The land under
discussion is unequivocally owned by DUSIB, precluding the
Petitioner from asserting any proprietary rights, claims, or
interests. On this aspect, the salient terms of the contract,
stemming from the NIT dated 11th December, 2020, are as
follows:
“61. The permission by DUSIB shall be for a limited period
only for use as per E-Auction terms and conditions and
agreement related thereto. This does not create any tenancy
rights enjoyable by the selected bidder.
62. The land of such site shall always remain the property of
W.P. (C) 8508/2026 Page 17 of 22
Signature Not Verified
Digitally Signed
By:ZEENAT PRAVEEN
Signing Date:03.08.2026
19:56:02
DUSIB and the bidder shall not claim any right/ title or
interest to any right or any nature of easement in relation to
or in respect thereto.”
8. Moreover, Clause 26 of the aforesaid NIT denotes that the
term of the agreement was fixed for a period of two years. Post
this duration, onus was on the Petitioner to return the specified
land segment to DUSIB, ensuring it remained vacant and
unaltered. Clause 27 of the said NIT further stipulates that if
DUSIB was unable to finalize the subsequent auction process
by the end of the term of the original agreement, the duration of
original agreement could be extended on a monthly basis, but
only up to a maximum of six months. In the present scenario,
the initial term culminated on 31st January, 2023 – a fact which
is not in dispute. Acting upon Clause 27, DUSIB sanctioned a
six-month extension, from 31st January 2023 to 31st July 2023,
in monthly intervals. The subsequent e-tenders initiated by the
Respondents, in respect of the Land Parcel (Chunks A through
E in West District Shivaji Place, Raja Garden, New Delhi),
unfortunately yielded no effective response and were thus
deemed non-competitive. Given these developments and the
clear mandate that no provision allowed an extension beyond
31 st July, 2023, the Respondents‘ demand for the Petitioner to
relinquish control and deliver possession of the land stands on
firm ground and is wholly justified.
9. It is imperative to note that licenses, by their nature, do not
confer any proprietary rights to the licensee. The rights of a
licensee are circumscribed by the explicit terms and conditions
set forth in the agreement. The sanctity of these contractual
agreements is the cornerstone of commerce, ensuring
predictability in dealings. It is crucial that contracts are
honoured, and that parties operate within their defined
boundaries. When the terms of such agreements lapse, they
cannot be unilaterally extended, without mutual consent.
10. The Petitioner neither possesses a legal nor inherent right to
maintain their occupation of the Subject Land. Merely having
made investments to render the land suitable for its intended
use does not vest any special rights to seek extension of license
term. The Petitioner willingly entered into this commercial
agreement, fully cognizant of the duration of the terms of the
license. This Court is not bound to decide the issue merely on
the basis of economic implications faced by parties due to their
commercial decisions. The obligations set forth in contracts
W.P. (C) 8508/2026 Page 18 of 22
Signature Not Verified
Digitally Signed
By:ZEENAT PRAVEEN
Signing Date:03.08.2026
19:56:02
have to be given precedence. While the Petitioner's investment
decisions on the land are acknowledged, they were made
within a well-defined legal and contractual framework. Any
deviation from this arrangement especially when not supported
by mutual agreement, would be antithetical to the very
foundation of contractual obligations.
11. Given the absence of any legally-entrenched or intrinsic
right, and with the contractual term having reached its
conclusion, the Petitioner‘s plea for the writ of mandamus to
prolong its tenure stands on shaky ground. The Petitioner was
never provided with an indefinite right to the land but was,
instead, working within the defined confines of a time-limited
license. The right to possession by DUSIB, as the owner of the
land in-question, and their discretion in managing it, is a
significant counterweight.‖
29. The learned senior counsel for the petitioner has also placed
reliance upon the order dated 08.03.2018 passed by the Coordinate
Bench of this Court in W.P.(C) Nos. 2164/2018 and 2165/2018.
However, the said order is clearly distinguishable on facts. In the said
case, the fresh tender process had already been concluded and the
petitioner had emerged as the highest bidder. Thus, the possibility of
the petitioner continuing as the successful licensee had substantially
crystallized. It was in those peculiar facts and circumstances that the
Coordinate Bench had expressed that there was no purpose in first
directing the petitioner to vacate the subject land and thereafter
restoring possession to it upon execution of the fresh agreement, and
accordingly, interim protection was granted to the petitioner. In the
present case, admittedly, no fresh tender has yet been floated, much
less concluded.
30. Similarly, the reliance placed upon the order dated 28.09.2020
W.P. (C) 8508/2026 Page 19 of 22
Signature Not Verified
Digitally Signed
By:ZEENAT PRAVEEN
Signing Date:03.08.2026
19:56:02
passed by the Division Bench in W.P.(C) No. 6784/2020 is also
misconceived. A perusal of the said order itself reveals that it was
passed on the basis of the consent of the parties, with DUSIB
expressing its no objection to the petitioner continuing on the subject
land, subject to certain terms and conditions. The said order,
therefore, neither adjudicates the rights of the parties nor lays down
any principle of law governing the interpretation of the contractual
clauses in question. Pertinently, this distinction was also noticed by
the Division Bench in its subsequent decision in W.P.(C) No.
12877/2023 (discussed above), while considering a similar
contention founded upon the order dated 28.09.2020.
31. Accordingly, this Court is of the considered opinion that the
petitioner did not acquire any contractual or legal right to continue in
possession of the subject land – beyond the maximum contractual
period – only because the respondents did not complete the fresh
tender process within the extended period contemplated under Clause
6 of the Agreement.
iii. Conclusion
32. In view of the foregoing discussion, this Court is of the
considered opinion that the petitioner, being only a licensee under the
Agreement executed with DUSIB, does not possess any contractual,
statutory or vested right to continue in occupation of the subject land
beyond the maximum contractual period stipulated under the
Agreement. The Agreement itself envisages that upon expiry of the
W.P. (C) 8508/2026 Page 20 of 22
Signature Not Verified
Digitally Signed
By:ZEENAT PRAVEEN
Signing Date:03.08.2026
19:56:02
contractual tenure, the petitioner is obliged to hand over vacant and
peaceful possession of the subject land to DUSIB. Admittedly, apart
from the original contractual period of two years, the petitioner has
also availed the entire extended period of six months contemplated
under Clause 6 of the Agreement. Therefore, no direction, as prayed
for by the petitioner, can be issued permitting its continued
occupation of the subject land – till the completion of the fresh tender
process.
33. At the same time, this Court cannot overlook the fact that
Clause 6 of the Agreement obligated DUSIB to undertake and
complete the fresh tender process during the extended period of the
Agreement. Though the respondents‘ failure to do so cannot enlarge
the petitioner‘s contractual rights, it nevertheless casts an obligation
upon the respondents to ensure that the process is now completed
expeditiously. The learned counsel appearing for the DUSIB, on
instructions, has submitted before this Court that the process for
issuance of the fresh e-auction/tender is presently underway and is
likely to be completed within a period of six weeks. The said
statement is taken on record and the respondents shall remain bound
by the same.
34. Having regard to the fact that the petitioner has remained in
occupation of the subject land for a considerable period and that the
subject land presently contains pandals and other structures which
would require some time to be dismantled and removed, this Court is
of the opinion that the interests of justice would be served by
W.P. (C) 8508/2026 Page 21 of 22
Signature Not Verified
Digitally Signed
By:ZEENAT PRAVEEN
Signing Date:03.08.2026
19:56:02
granting the petitioner a period of one week from date, to hand over
vacant and peaceful possession of the subject land to DUSIB.
35. It is, however, made clear that for the aforesaid period during
which the petitioner continues to remain in occupation of the subject
land, the petitioner shall remain liable to pay the licence fee,
occupational charges and all other applicable charges, in accordance
with law and the applicable contractual terms, without prejudice to
the rights and contentions of the parties in that regard.
36. The respondents are further directed to place on record, within
a period of six weeks, a status report indicating the steps taken
towards initiation and completion of the fresh tender/e-auction
process in respect of the subject land.
37. The writ petition is, accordingly, dismissed in the aforesaid
terms. Pending application(s), if any, also stand disposed of.
38. The judgment be uploaded on the website forthwith.
DR. SWARANA KANTA SHARMA, J
AUGUST 03, 2026/A
T.D.
W.P. (C) 8508/2026 Page 22 of 22