MUNICIPAL CORPORATION OF GREATER MUMBAI vs MAHARASHTRA ELECTRICITY REGULATORY COMMISSION & Ors
- Court
- Appellate Tribunal For Electricity
- Case type
- APPEAL
- Decided on
- 11-03-2026
<div> <i> Judgement in Appeal Nos. 279 of 2017 </i><br /> <br /> <b>IN THE APPELLATE TRIBUNAL FOR ELECTRICITY </b><br /> <b>(Appellate Jurisdiction) </b><br /> <b>APPEAL No. 279 OF 2017 </b><br /> <b> </b><br /> <b>th</b><br /> <b>Dated: </b> <b>11</b> <b> March, 2026 </b><br /> <b>Present: Hon`ble Ms. Seema Gupta, Officiating Chairperson </b><br /> <b> </b> <b>Hon`ble Mr. Virender Bhat, Judicial Member </b><br /> <b> </b><br /> <b>In the matter of: </b><br /> MUNICIPAL CORPORATION OF GREATER MUMBAI, <br /> Brihanmumbai Electricity Supply <br /> And Transport Undertaking <br /> BEST Bhawan, BEST Marg <br /> Post Box No.192, Coloba, <br /> Mumbai-400 001. … Appellant(s) <br /> <br /> <b><i>VERSUS</i></b> <b><i> </i></b><br /> <br /> 1. MAHARASHTRA ELECTRICITY REGULATORY COMMISSION <i> </i><br /> <i>Through Secretary</i> , <br /> World Trade Centre No.1, <br /> th<br /> 13 floor, Cuffe Parade, Colaba, <br /> Mumbai – 400 001 <br /> <br /> 2. TATA POWER COMPANY LIMITED, <br /> <i>Through Managing Director </i><br /> Bombay House, 24, Homi Mody Street, <br /> Mumbai – 400 001 <br /> <br /> 3. ADANI ELECTRICITY MUMBAI LIMITED, <br /> <i>Through Managing Director </i><br /> CTS 407/A (New) 408 (Old), <br /> Village Eksar, Devidas Lane, <br /> Off SVP Road, Borovali (West), <br /> Mumbai – 400 103. …. Respondents <br /> <br /> Counsel on record for the Appellant(s) : Ms. Padma Priya <br /> Ms. Akanksha Das <br /> Ms. Aditi Sharma <br /> Page <b>1</b> of <b>28</b> <br /> <br /><br /> <i> Judgement in Appeal Nos. 279 of 2017 </i><br /> <br /> Mr. Kshitez Kaushik <br /> Mr. Dhruv Nayar <br /> Ms. Neetica Sharma <br /> Ms. Soumya Priyadarshini <br /> Ms. Shreya Sethi for App. 1 <br /> <br /> Counsel on record for the Respondent(s) : Ms. Pratiti Rungta for Res. 1 <br /> <br /> Mr. Amit Kapur <br /> Mr.Akshat Jain for Res. 2 <br /> <br /> Mr. Hemant Singh <br /> Mr. Ambuj Dixit <br /> Mr. Shariq Ahmed <br /> Mr. Lakshyajit Singh Bagdwal <br /> Mr. Tushar Srivastava <br /> Ms. Soumya Singh <br /> Mr. Karan Govel for Res. 3 <br /> <b>JUDGEMENT </b><br /> <b> </b><br /> <b>PER HON’BLE MRS. SEEMA GUPTA, OFFICIATING CHAIRPERSON </b><br /> <i> </i><br /> <b>1. </b> The captioned appeal No. 279 of 2017 has been filed by Municipal <br /> Corporation of Greater Mumbai <b>(herein referred as “Appellant”),</b> challenging <br /> the order dated 12.06.2017 in Case No. 182 of 2014 and Case No. 40 of 2015 <br /> <b>(</b> hereinafter referred as <b> Impugned Order”</b> ) passed by the Maharashtra <br /> Electricity Regulatory Commission. <b><i> </i></b><br /> <b><i> </i></b><br /> 2. The Appellant, Municipal Corporation of Greater Mumbai (MCGM), is a <br /> municipal corporation constituted under the Mumbai Municipal Corporation Act, <br /> 1888 and is a local authority under Part IX-A of the Constitution of India. Under <br /> the said Act, MCGM has an undertaking known as the Brihanmumbai Electric <br /> Supply and Transport Undertaking (BEST), which is a statutory undertaking of <br /> Page <b>2</b> of <b>28</b> <br /> <br /><br /> <i> Judgement in Appeal Nos. 279 of 2017 </i><br /> <br /> MCGM and accordingly, BEST falls within the definition of “local authority” under <br /> Section 2(41) of the Electricity Act, 2003. <br /> <br /> 3. The Respondent No.1 i.e. Maharashtra Electricity Regulatory Commission <br /> (herein referred as <b>“MERC/State Commission</b> ), is the Electricity Regulator for <br /> the State of Maharashtra. <br /> <br /> 4. The Respondent No. 2 i.e. Tata Power Company Limited (hereinafter <br /> referred to known as <b>“TPCL”</b> ) was earlier granted four distribution license in <br /> parts of Maharashtra before enactment of Electricity Act 2003, and the area under <br /> these licenses overlapped with the area of supply of BEST. Subsequently it has <br /> been granted distribution license by MERC (in suppression of the said four <br /> licenses) in its order dated 14.08.2014. The Respondent No.3, the Adani <br /> Electricity Mumbai Limited <b>(“AEML”)</b> is the power distribution company for <br /> Mumbai, <i> </i><br /> <b><i> </i></b><br /> <b><i>Factual matrix of the Case: </i></b> This case has a chequered history and facts <br /> relevant to deal with present Appeal are noted below: <br /> <br /> 5. Supreme Court in its judgment dated 08.07.2008, <b>“(2008) 10 SCC 321 </b><br /> <b>(Tata Power Co. Ltd. V/s Reliance Energy Limited)”</b> has held that TPCL under <br /> its four licenses was authorised to distribute electricity in retail directly to <br /> consumers, including those whose maximum demand is less than 1000 kVA, <br /> apart from its entitlement to supply electricity to other licensees. <i> </i><br /> <i> </i><br /> 6. On 20.08.2008 MERC issued Regulations, which classified TPCL as a <br /> distribution licensee under the Electricity Act, 2003, allowing it to supply electricity <br /> in its licensed area until 15.08.2014. <i> </i><br /> 7. In 2009, disputes emerged between TPCL and BEST with regard to TPCL's <br /> right to supply electricity in Mumbai, leading to several case proceedings under <br /> Page <b>3</b> of <b>28</b> <br /> <br /><br /> <i> Judgement in Appeal Nos. 279 of 2017 </i><br /> <br /> the MERC. These disputes culminated in Civil Appeal No. 4223 of 2012, where <br /> the Supreme Court of India ordered the parties to maintain the status quo as of <br /> May 10, 2012, pending the appeal's resolution. <i> </i><br /> <i> </i><br /> 8. On 01.01.2014 MERC issued an Invitation for Expression of Interest for the <br /> distribution of electricity in Mumbai City and parts of the Mumbai Suburban Area <br /> and cited Regulations 4 and 5 of the MERC (Specific Conditions of Distribution <br /> Licence applicable to Tata Power Company Ltd.) Regulations, 2008. Regulation <br /> 4 authorizes the Distribution Licensee to supply electricity within the areas <br /> defined by various historical licenses, and Regulation 5 stipulates that the <br /> Distribution License shall remain valid until August 15, 2014, marking the <br /> continuation of Tata Power Company as a Distribution Licensee till 15.08.2014. <i> </i><br /> <i> </i><br /> 9. On 30.01.2014, BEST filed Case No. 37 of 2014 with MERC to prevent <br /> other licensees from distributing electricity in its supply area. On 07.04.2014, <br /> TPCL filed Case (No. 90 of 2014) for grant of distribution license under the <br /> Section 15(2) of Electricity Act, which was admitted on 06.05.2014, requiring <br /> TPCL to issue a Public Notice. <i> </i><br /> <br /> 10. On 08.05.2014, the Supreme Court passed the order in Civil Appeal No. <br /> 4223 of 2012 and held that TPCL was a "deemed licensee" until 15.08.2014 and <br /> it could provide electricity to consumers in the shared supply area with its own <br /> network, without relying on BEST's infrastructure. <i> </i><br /> <br /> 11. On 14.08.2014, MERC granted TPCL a distribution license for 25 years, <br /> effective 16.08.2014 in case No 90 of 2014 filed by TPCL. On 03.09.2014, BEST <br /> filed Appeal No. 216 of 2014 before this Tribunal seeking to set aside the said <br /> order pertaining to grant of distribution license to TPCL in areas already served <br /> by them. <br /> <i> </i><br /> Page <b>4</b> of <b>28</b> <br /> <br /><br /> <i> Judgement in Appeal Nos. 279 of 2017 </i><br /> <br /> 12. On 26.09.2014, BEST preferred another Appeal, No. 243 of 2014, before <br /> this Tribunal against MERC and others to impugn and sought setting aside the <br /> Order dated 14.08.2014 passed by MERC in Case No. 37 of 2014 filed by BEST. <i> </i><br /> <i> </i><br /> 13. On 10.10.2014, TPCL filed Case No. 182 of 2014 before MERC seeking <br /> approval of its revised network rollout plan, as required under the Order dated <br /> 14.08.2014 and pursuant to Distribution License No. 1 of 2014 granted to it. <br /> <i> </i><br /> 14. This Tribunal vide its judgement dated 25.11.2014 in Appeal No 216 of 2014 <br /> held that Appeal 216 of 2014 was not maintainable and points raised to the merit <br /> in this appeal shall be considered in the Appeal No 243 of 2014, pending before <br /> this Tribunal <i> </i><br /> <br /> 15. This Tribunal vide its Judgment dated 28.11.2014, decided the cross-<br /> appeals, being Appeal No. 246 of 2012 filed by TPCL and Appeal No. 229 of 2012 <br /> filed by R-Infra, challenging the Order dated 22.08.2012 passed by the MERC in <br /> Case No. 151 of 2011, which imposed certain restrictions on TPCL with respect <br /> to category of consumers to which TPCL could supply electricity using R-Infra <br /> network and in respect of suburban Mumbai where TPCL was required to lay <br /> down its complete distribution network to meet its universal service Obligation ( <br /> USO). It has been submitted by BEST, that it was not party in the proceedings <br /> before State Commission as well as this Tribunal and the judgement relate to <br /> area common to TPCL and R-infra and accordingly this judgement is neither <br /> applicable nor relatable to BEST or its area of supply. <br /> <br /> 16. On 12.02.2015, TPCL filed a further revised network rollout plan before the <br /> MERC in pending Case No. 182 of 2014, in compliance with the Order dated <br /> 14.08.2014 passed in Case No. 90 of 2014 and the Judgment dated 28.11.2014 <br /> passed by the APTEL in Appeal Nos. 246 and 229 of 2012. <br /> <br /> Page <b>5</b> of <b>28</b> <br /> <br /><br /> <i> Judgement in Appeal Nos. 279 of 2017 </i><br /> <br /> 17. On 10.04.2015, BEST preferred Civil Appeals ( No 4074 of 2015 and 11771 <br /> of 2015 ) before the Hon’ble Supreme Court of India challenging the orders <br /> passed by the this Tribunal dated 25.11.2014 in Appeal No 216 of 2014 and <br /> 12.03.2015 vide which its review was dismissed; the said Civil Appeals were <br /> admitted on 15.05.2015. <br /> <br /> 18. On 09.11.2015, MERC passed an Interim Order in Case No. 182 of 2014, <br /> to constitute a committee to make recommendation on certain aspects in the <br /> rollout plan of TPCL, subsequent to the issue of notice on 16.07.2015 to BEST, <br /> R-Infra/AEML, TPCL and consumer representative in the case. <br /> <br /> 19. Being aggrieved by the said Interim Order dated 09.11.2015, BEST filed <br /> Appeal No. 21 of 2016 before this Tribunal to set aside the Impugned Order and <br /> dismissal of pending case 182 of 2014 filed by TPCL. Same is pending before <br /> this Tribunal for adjudication. <br /> <br /> 20. Meanwhile, in 2014, BEST had filed a Writ Petition No.2641 of 2014 <br /> (MCGM versus (i) MERC, (ii) TPCL and (iii) State of Maharashtra) before the <br /> Bombay High Court, to set aside Regulation 4.10 read with Regulations 4.1 and <br /> 4.7 of the MERC (Standards of Performance of Distribution Licensees, Period for <br /> Giving Supply and Determination of Compensation) Regulations 2014, which has <br /> been dismissed vide Bombay High Court by Judgement dated 02.03.2016. Being <br /> aggrieved by the same, BEST has filed SLP (Civil) No. 23470 of 2016 before the <br /> Supreme Court of India. Same is pending adjudication. <br /> <br /> 21. On 04.11.2016, this Tribunal dismissed the Appeal No. 243 of 2014 . <br /> Aggrieved thereby BEST has filed Civ il Appeal Nos. 3403-3404 of 2017 before <br /> the Supreme Court, which has been admitted and tagged along with Civil <br /> Appeal No. 4074 of 2015. <br /> <br /> Page <b>6</b> of <b>28</b> <br /> <br /><br /> <i> Judgement in Appeal Nos. 279 of 2017 </i><br /> <br /> 22. On 12.06.2017, the MERC has passed combined Order dated in Case <br /> N o . 182 of 2014 and Case No. 40 of 2015 allowing phased development <br /> of the Distribution network by TPCL. Being aggrieved thereby, BEST has <br /> preferred present Appeal with regard to phased development of network roll out <br /> plan of TPCL for common area of supply of BEST and TPCL <br /> <br /> <b>DISCUSSION AND ANALYSIS </b><br /> 23. Heard Mr. Harinder Toor, learned counsel on behalf of Appellant, <br /> Ms. Pratiti Rungta, learned counsel on behalf of State Commission and Mr. B.P <br /> Patil learned senior counsel on behalf of Respondent No 2-TPCL, pursued the <br /> written submissions filed by parties and relevant documents. Learned Counsel <br /> on behalf of BEST has raised contention with regard to approval of phased <br /> development of distribution network by TPCL over 7 years, mainly stating that it <br /> contravenes the universal service obligation under section 43 of Electricity Act, <br /> that it would result in cherry picking of customers by TPCL, non-level playing <br /> field, and about non addressing the concerns of BEST with regard to practical <br /> difficulty in migration protocol allowed by the State Commission. Per Contra, <br /> learned Counsel on behalf of MERC, at the outset, submitted that present Appeal <br /> is non maintainable and is an abuse of process of law and is barred by Principles <br /> of Res judicata as the issued involved in the present Appeal (i.e. phased <br /> development of distribution network by a parallel distribution licensee, grant of <br /> parallel license in the area where a local authority is licensed to supply electricity <br /> and switchover of consumers) has already been decided by the Hon’ble <br /> Supreme Court in its judgement dated 08.05.2014, in Civil Appeal No 4223 of <br /> 2012, and this Tribunal judgement dated 04.11.2016 in Appeal No 243 of 2014 <br /> Page <b>7</b> of <b>28</b> <br /> <br /><br /> <i> Judgement in Appeal Nos. 279 of 2017 </i><br /> <br /> and this Tribunal judgement dated 25.11.2014 in No 216 of 2014, both these <br /> judgements pending adjudication before the Hon’ble Supreme Court in the civil <br /> appeal filed by BEST but no stay is operating. In addition, learned Counsel for <br /> the MERC has elaborately argued each of the points and submitted that the <br /> Impugned Order is perfectly justified and it does not suffer from any infirmity <br /> warranting interference by this Tribunal. <br /> 24. The learned Senior Counsel appearing on behalf of TPCL, in justification <br /> of the Impugned Order has elaborately made submissions with regard to each <br /> of the contentions raised by the Appellant and also been submitted that the <br /> present Appeal has as such become infructuous due to passage of time and <br /> TPCL has complied with the Impugned Order and it is USO ready and has <br /> network to supply power to any applicant in the concerned area of supply. <br /> 25. With regard to submissions of TPCL that present Appeal has become, <br /> infructuous, this Tribunal vide its order dated 06.01.2026 has directed TPCL to <br /> furnish the progress of Network in terms of Network Layout mentioned in the <br /> Para 137.12 of the Impugned Order. In compliance thereof, TPCL vide its <br /> affidavit dated 05.02.2026 furnished the details. The information so provided is <br /> summarised hereinbelow. <br /> • TPCL has submitted its roll out plan to the State Commission in terms of <br /> para 137.12 of the Impugned Order. Further in terms of MERC’s <br /> Guidelines for in principle clearance of Capital Investment schemes 2005, <br /> TPCL is required to seek prior approval of MERC for capital expenditure <br /> above Rs. 10 Crore and accordingly, TPCL has submitted various Detailed <br /> Project Report (DPR) indicating network details and capital investment, <br /> which has been approved by MERC from time to time. <br /> Page <b>8</b> of <b>28</b> <br /> <br /><br /> <i> Judgement in Appeal Nos. 279 of 2017 </i><br /> <br /> • TPCL has fully completed Phase -I and has completed Phase II <br /></div><table><thead><tr><th>Sr.<br>No.</th><th>Particulars</th><th>Unit</th><th>As per Network Rollout<br>Plan</th><th></th><th></th><th>Actuals (As<br>of December<br>2025)</th><th>Status of<br>Implementation</th></tr></thead><tbody><tr><td></td><td></td><td></td><td>Phase I</td><td>Phase<br>II</td><td>Total</td><td></td><td></td></tr><tr><td>1</td><td>Consumer<br>Substation</td><td>Nos.</td><td>43</td><td>52</td><td>95</td><td>122</td><td>128.42%</td></tr><tr><td>2a</td><td>HT Cable<br>(33 KV to<br>11 KV)</td><td>KM</td><td>126</td><td>102</td><td>228</td><td>289</td><td>126.75%</td></tr><tr><td>2b</td><td>LT Cable</td><td>KM</td><td>102</td><td>312</td><td>414</td><td>215</td><td>51.75%</td></tr><tr><td>2</td><td>Total<br>HT+LT</td><td>Km.</td><td>228</td><td>414</td><td>642</td><td>504</td><td>78.50%</td></tr><tr><td>3</td><td>Feeder<br>Pillar, Sub-<br>feeder<br>pillar and<br>Mini Pillars</td><td>Nos.</td><td>129</td><td>156</td><td>285</td><td>610</td><td>214.03%</td></tr><tr><td>4</td><td>Distribution<br>Substation<br>Nos.</td><td>Nos.</td><td>4</td><td>6</td><td>10</td><td>4*</td><td>60%</td></tr></tbody></table><div><br /> *The figure would be 6 DSS by March 2026 <br /> <br /> • As DSS in South Mumbai is to be installed in the land allotted by developer <br /> in , its progress is affected due to non-availability of land by Developer. <br /> <br /> • Sufficient Network has been created by TPCL to power supply to the <br /> consumers and in the area overlapping with BEST and it is in position to <br /> supply power to any consumer as per stipulated timeline and MERC has <br /> not taken cognizance of any pending complaints regarding TPCL inability <br /> to effect supply. <br /> 26. It has been further submitted by TPCL, that BEST has raised objection with <br /> regard to non-laying of distribution network in accordance with Impugned Order <br /> in case no 237 of 2023, while truing up of ARR of FY 2022-23, Provisional True <br /> Page <b>9</b> of <b>28</b> <br /> <br /><br /> <i> Judgement in Appeal Nos. 279 of 2017 </i><br /> <br /> up of ARR of FY 2023-24 and Revised ARR for FY 2024-25 for TPCL, and such <br /> contentions has been dismissed by MERC in its Order dated 06.03.2024 and <br /> following observation has made <br /> <br /> <br /> <i>“…..2.3.4 The Commission has ben approving the DPR for network roll-out </i><br /> <i>to meet its obligation to supply using its own network as per principles laid </i><br /> <i>down in Case No.182 of 2014. Further, TPC-D has been updating the </i><br /> <i>Commission on the status of DPRs approved by the Commission. AEML-D </i><br /> <i>and BEST are free to approach Commission with specific instances/cases </i><br /> <i>to show selective network laying by TPC-D rather than making generic </i><br /> <i>comments…” </i><br /> 27. From the above details furnished by TPCL, it is evident that TPCL has <br /> substantially rolled out its network and the State Commission, has taken <br /> cognigence of the same and no deficiencies in roll out plan has been pointed out <br /> by the State Commission and AEML/R-Infra and BEST were free to approach <br /> State commission with specific instances. Before this Tribunal as well, the <br /> Appellant has not pointed out any specific instances of deficiencies / <br /> contravention in the Network roll out plan but has made general comments. <br /> Considering the fact that network roll out plan of TPCL has been substantially <br /> completed, the issues concerning phased network development raised in the <br /> present appeal have lost practical significance. Ordinarily, such matters would <br /> render the appeal infructuous. However, since the questions raised also involve <br /> interpretation of statutory obligations and regulatory principles of wider <br /> significance, we consider it appropriate to examine the issues on merits. <br /> Accordingly, based on deliberations held on contentions raised by BEST, the <br /> following issues emerges for Consideration: <br /> <b>ISSUE NO 1 : Is phased development of distribution network over a period </b><br /> <b>of seven years permitted to TPC contrary to Electricity act, 2003 and other </b><br /> <b>related issue </b><br /> Page <b>10</b> of <b>28</b> <br /> <br /><br /> <i> Judgement in Appeal Nos. 279 of 2017 </i><br /> <br /> <b>Submissions urged on behalf of Appellant - BEST </b><br /> 28. It is submitted that the phased development/rollout of the distribution <br /> network over a period of seven years by the second licensee (viz. TPCL) is <br /> contrary to the Universal Service Obligation under Section 43 of the Electricity <br /> Act, 2003 (i.e. duty to supply on request), and facilitates cherry-picking or luring <br /> away of consumers. Phased and selective network development is not conducive <br /> to a level playing field or genuine competition and does not provide equal access <br /> to all categories of consumers, particularly low-end/slum consumers with <br /> consumption between 0–300 units. In addition the limited and phased nature of <br /> TPCL’s network leads to lower maintenance costs, thereby enabling TPCL to <br /> offer lower tariffs, whereas BEST, being obligated to cater to all consumer <br /> categories and to maintain a comprehensive distribution network across its entire <br /> area of supply, necessarily incurs higher cost resulting in higher tariff. Further, <br /> the Sixth Proviso to Section 14 of the Electricity Act, 2003 mandates the <br /> requirement of an “own distribution system,” which necessarily entails adequate <br /> and timely development and rollout of the distribution network. <br /> 29. Such phased development besides not ensuring compliance by TPCL with <br /> its Universal Service Obligation to serve all classes and categories of consumers <br /> in the Island City of Mumbai, it proceeds on an erroneous premise that TPCL is <br /> entitled to selectively and progressively develop or rollout its distribution network <br /> in a phased manner within its area of supply and thus MERC has adopted a <br /> facilitative approach and MERC did not also accept the recommendation of <br /> Committee appointed by it, which has specially pointed out that TPCL’s Network <br /> Plan for the BEST Area should be such that it would be against selective targeting <br /> of consumers. <br /> <b> </b><br /> <b> </b><br /> Page <b>11</b> of <b>28</b> <br /> <br /><br /> <i> Judgement in Appeal Nos. 279 of 2017 </i><br /> <br /> <b>Submissions urged on behalf of State Commission </b><br /> 30. Without prejudice to the submissions made with regard to res-judicata, it is <br /> submitted that the State Commission in the impugned order has explained the <br /> rationale behind the directions given to TPCL for phased network development, <br /> inasmuch as the State Commission, has duly approved the principles and <br /> modalities for planning and development of TPCL network roll-out plan within the <br /> Appellant’s area and has also issued specific directions to ensure fulfilment of the <br /> Universal Service Obligation. The planned network development approach in <br /> phased manner has been considered to be the optimal approach considering its <br /> cost-effectiveness and to avoid selective bias in the coverage of areas or <br /> consumers. The contention of Appellant that that phased development of the <br /> distribution network would result in cherry-picking by TPCL, is misconceived as <br /> State Commission, in the Impugned Order, has duly examined the option of a <br /> planned, phased roll-out vis-à-vis development of the network solely on the basis <br /> of consumer demand and has categorically observed that permitting network <br /> expansion only upon demand would not be an optimal approach, as it would lead <br /> to scattered and unplanned development across various areas, thereby <br /> increasing the likelihood of selective laying of network and consequent cherry-<br /> picking. As such distribution of electricity is a licensed activity under the Electricity <br /> Act, 2003, and prior existence of a distribution network is not a precondition for <br /> the grant of a distribution licence. Section 43 of the Electricity Act prescribes <br /> timelines for supply of electricity, which itself contemplates staged development <br /> of infrastructure. <br /> <b>Submissions urged on behalf of TPCL </b><br /> 31. The Contention of BEST that phased development over a period of seven <br /> years is contrary to Section 43 of the Electricity Act is misplaced in law, since <br /> such an interpretation would illogically require the entire network to be laid within <br /> Page <b>12</b> of <b>28</b> <br /> <br /><br /> <i> Judgement in Appeal Nos. 279 of 2017 </i><br /> <br /> one year of grant of licence and reflects a misconstruction of the concept of <br /> network development vis-à-vis the Universal Service Obligation (USO); in fact, <br /> the statutory duty of a distribution licensee is governed by Section 42(1) of the <br /> Electricity Act, which mandates the licensee to develop and maintain an efficient, <br /> coordinated and economical distribution system in its area of supply and to supply <br /> electricity in accordance with the provisions of the Act, and does not prohibit <br /> phased development of the distribution network. With the conjoint reading of <br /> Sections 42(1) and 43 of the Electricity Act, 2003, it is evident that the obligation <br /> to develop and lay the distribution network is a continuous process, and no outer <br /> time limit for completion of network development by a distribution licensee in its <br /> entire area of supply has been specified. While, Section 43 stipulates a timeline, <br /> on request, considering the network which ought to be laid to connect the <br /> consumers. Keeping these principles in view, and considering the peculiar <br /> topography of the Island City of Mumbai as well as space constraints and right of <br /> way issues, the State Commission directed Tata Power to lay its distribution <br /> network in two phases so as to enable compliance with its Universal Service <br /> Obligation in overlapping areas with BEST, and further directed that Phase-I <br /> should ordinarily be completed prior to commencement of Phase-II so as to <br /> ensure that the network development remains economical, in terms of Section 42 <br /> of the Act. <br /> <b>CONSIDERATION AND OUR VIEW </b><br /> 32. We note that Section 14 of Electricity Act stipulates the conditions for Grant <br /> th<br /> of License, including license for Distribution of Electricity and as per 6 proviso, <br /> the State commission can grant two or more license for distribution of electricity <br /> through their own distribution system within the same area of supply, provided <br /> they comply with additional condition of capital adequacy, creditworthiness or <br /> code of conduct. Requirement of pre-owning of distribution network, has not been <br /> Page <b>13</b> of <b>28</b> <br /> <br /><br /> <i> Judgement in Appeal Nos. 279 of 2017 </i><br /> <br /> mandated in the Electricity Act to be eligible for Grant of license for distribution of <br /> electricity. In this context, it is also relevant to quote Section 42 and Section 43 <br /> of the Electricity Act, 2003. <br /> <i> </i><br /> <i>“Section 42 </i> <b><i>Duty of the Distribution licensee and Open Access</i></b> <i>: (1)It </i><br /> <i>shall be the duty of a distribution licensee to develop and maintain an </i><br /> <i>efficient, co-ordinated and economical distribution system in his area of </i><br /> <i>supply and to supply electricity in accordance with the provisions contained </i><br /> <i>in this Act…” </i><br /> <i> </i><br /> <i>Section 43. </i> <b><i>Duty to supply on request</i></b> <i>: (1) Save as otherwise provided </i><br /> <i>in this Act, every distribution licensee, shall, on an application by the owner </i><br /> <i>or occupier of any premises, give supply of electricity to such premises, </i><br /> <i>within one month after receipt of the application requiring such supply: </i><br /> <i> </i><br /> <i>Provided that where such supply requires extension of distribution mains, </i><br /> <i>or commissioning of new sub-stations, the distribution licensee shall </i><br /> <i>supply the electricity to such premises immediately after such extension or </i><br /> <i>commissioning or within such period as may be specified by the </i><br /> <i>Appropriate Commission....” </i><br /> <br /> 33. As per Section 42 of the Electricity Act, a distribution licensee is mandated <br /> to develop and maintain an efficient and economical distribution system within its <br /> area of supply, which would mean progressive expansion and improvement of <br /> the distribution system. In our view, it is not a one-time activity; instead, it means <br /> the licensee must continuously plan and invest in infrastructure to meet growing <br /> demand, and ensure reliability. Thus, in terms of Electricity Act, upon grant of <br /> distribution license, the Licensee cannot be expected to develop the entire <br /> distribution network at one go, and there would be phased development of <br /> network and furthermore no time line for such a network development has been <br /> mandated in the Act. Section 43 of the Act also acknowledges that in the course <br /> of providing supply to anew customer, there would be instances, where extension <br /> of substation and/ or distribution network would be required and same can be <br /> Page <b>14</b> of <b>28</b> <br /> <br /><br /> <i> Judgement in Appeal Nos. 279 of 2017 </i><br /> <br /> provided as per time lines specified by State Commission/ or upon such <br /> extension. Thus even for meeting the Universal Service Obligation, time line has <br /> to be specified by State Commission based on the requirement of extension of <br /> network if any. Thus, in our view, the phased development of the distribution <br /> Network under Distribution license over 7 years as permitted in Impugned Order, <br /> cannot be said to be in contravention of the provisions of the Electricity Act, 2003. <br /> It is of relevance to note that Appellant - BEST has challenged the State <br /> Commission order dated 14.08.2014 in Appeal No. 216 of 2014 before this <br /> Tribunal, challenging phased development of Tata Power’s distribution network <br /> allowed by MERC, being contrary to Law and relied to this Tribunal’s Judgment <br /> dated 06.04.2011 in “ <b><i>Noida Power Company Limited v. Paschimanchal </i></b><br /> <b><i>Vidyut Nigam Ltd. & Anr”.</i></b> This Tribunal, by Judgment dated 25.11.2014, <br /> dismissed BEST’s Appeal, holding that neither the Electricity Act nor the Noida <br /> Power judgment mandates that a distribution licensee must lay down the entire <br /> network prior to grant of licence, and that phased development of the network is <br /> permissible. BEST’s subsequent Review Petition No. 5 of 2015 against the <br /> Judgment dated 25.11.2014 was also dismissed by this Tribunal by Order dated <br /> 12.03.2015. Pursuant thereto, BEST filed Civil Appeal No. 4862 of 2015 and 4074 <br /> of 2015 before the Supreme Court against both these orders, mainly on the <br /> premise that the ratio of the Noida Power judgment purportedly prohibits phased <br /> development of a distribution network by a second licensee; same are pending <br /> adjudication, however, no interim relief has been granted in favour of BEST <br /> therein. <br /> 34. Therefore, in view of above deliberation and judicial pronouncement with <br /> no stay operating on the order, as far as broad issue of phased development of <br /> Distribution network is concerned, the principle of <i>res-judicata</i> shall be applicable <br /> to BEST, and same is also not in contravention of provisions of Electricity Act, <br /> 2003. However the other contentions raised about methodology of phased <br /> Page <b>15</b> of <b>28</b> <br /> <br /><br /> <i> Judgement in Appeal Nos. 279 of 2017 </i><br /> <br /> development allowed, cherry picking of customers, and issue of non-level playing <br /> fields etc. are deliberated in following paragraphs. <br /> 35. In the Impugned Order, the State Commission has analysed the three <br /> scenarios (Optimistic to pessimistic) of phased development of network in 7 years <br /> as proposed by TPCL and observed that though such a plan would cover entire <br /> license area (overlapping that of BEST in Mumbai District and with R-infra in Parts <br /> of Mumbai suburban District), no separate time line had been specified for area <br /> common to BEST has been indicated. With regard to proposed Municipal ward <br /> wise network roll out plan, the State Commission opined that this principle will <br /> have no relation with the geographical limits of Municipal ward and since a <br /> particular existing DSS /CSS may be able to cater to consumers more than one <br /> ward, and thus instead of approving addition of network ward wise basis, the <br /> State commission approved development of network in two distinct phases, and <br /> same is extracted hereunder: <b> </b> <br /> <i>“137.12 </i> <i>Accordingly, instead of approving the addition of network </i><br /> <i>elements Ward-wise, and in pursuance of its favoured approach set out </i><br /> <i>above, the Commission approves the following principles and modalities </i><br /> <i>for the planning and development of TPC-D's Network Roll-out in the </i><br /> <i>BEST area: </i><br /> <i>a. TPC-D is directed to roll out its network in the following two Phases, </i><br /> <i>which should be completed within 7 years of this Order. </i><br /> <i>Phase 1: Development/ augmentation/extension of existing </i><br /> <i>Distribution System </i><br /> <i>i. </i> <i>TPC-D already has some DSS (33/2211 kV sub-stations) and CSS </i><br /> <i>(22/11/0.415 kV or equivalent sub-stations) in certain areas. In these </i><br /> <i>areas, TPC-D shall develop its downstream distribution network </i><br /> <i>elements from the existing DSS and CSS, i.e. LT Mains and LT </i><br /> <i>feeder pillars/panels from the existing CSS. Where there is only a </i><br /> <i>DSS at present, TPC-D should develop the further 11 kV distribution </i><br /> <i>network, new CSS and LT network elements originating from the </i><br /> <i>CSS. </i><br /> <i>ii. </i> <i>Augmentation or extension of the existing network elements may </i><br /> <i>also be undertaken based on the requirements. </i><br /> Page <b>16</b> of <b>28</b> <br /> <br /><br /> <i> Judgement in Appeal Nos. 279 of 2017 </i><br /> <br /> <i>iii. </i> <i>TPC-D shall undertake these works in such a manner that it would </i><br /> <i>be in a position to comply with its USO towards all consumers in the </i><br /> <i>vicinity of its existing DSS and CSS upon completion of Phase I. </i><br /> <i>iv. </i> <i>Within Phase I, TPC-D shall prioritise the works required to meet </i><br /> <i>substantial existing or emergent consumer demand. </i><br /> <i>Phase II: Development of new DSS along with its downstream Distribution </i><br /> <i>System </i><br /> <i> </i><br /> <i>i. </i> <i>In the remaining areas where it does not have a distribution network </i><br /> <i>such as DSS, CSS, HT/LT lines, feeder pillars, etc. at present, TPC-D </i><br /> <i>shall establish such network in planned stages within the period </i><br /> <i>remaining after completing Phase I. </i><br /> <i>ii. Upon completion of this Phase, TPC-D must be in a position to comply </i><br /> <i>with its USO towards all consumers in the area common to BEST's </i><br /> <i>area of supply. </i><br /> <i>iii. While planning (or subsequently adjusting) the stages within Phase II, </i><br /> <i>TPC-D shall prioritise the works required to meet substantial existing </i><br /> <i>or emergent consumer demand. </i><br /> <i>b. While the maximum period envisaged for completing both Phases of this </i><br /> <i>roll-out is 7 years, the possibility of reducing this time-frame should be </i><br /> <i>reviewed by TPC-D from time to time, along with an evaluation of the </i><br /> <i>likely impact on consumer tariffs. The Commission may also do so. </i><br /> <i>c. In terms of the saving provisions of the SoP Regulations and by virtue of </i><br /> <i>the present Order, the period allowed for releasing supply upon demand </i><br /> <i>to applicants is relaxed till the scheduled or actual date of completing </i><br /> <i>works in each Phase or stage, whichever is earlier. </i><br /> <i>d. Within two months of this Order, TPC-D shall submit to the Commission </i><br /> <i>details of areas or locations covered under Phase-1, along with a </i><br /> <i>mapping of the components of its existing distribution network, and of </i><br /> <i>the planned stage-wise execution of Phase II, with the tentative time-</i><br /> <i>lines for completing network development in each of these Phases and </i><br /> <i>stages. TPC-D shall also provide these details on its website for the </i><br /> <i>information of consumers. These time-lines and stages may be adjusted </i><br /> <i>with the prior approval of the Commission. </i><br /> <i>e. TPC-D shall ordinarily release new connections only in accordance with </i><br /> <i>these Phases, i.e. new connections cannot be released in areas falling </i><br /> <i>in Phase II until Phase I is completed. However, if substantial demand </i><br /> <i>arises from an area to be covered in Phase II although Phase I is yet to </i><br /> <i>be completed, TPC-D may approach the Commission for its prior </i><br /> <i>approval for taking up that area also. </i><br /> Page <b>17</b> of <b>28</b> <br /> <br /><br /> <i> Judgement in Appeal Nos. 279 of 2017 </i><br /> <br /> <i>f. Based on the Phases and proposed stages of network development, </i><br /> <i>TPC-D shall furnish its capital expenditure proposals for in-principle </i><br /> <i>approval of the Commission, if applicable, in accordance with its </i><br /> <i>Guidelines of 2005. Relevant factors such as expected loading on the </i><br /> <i>network, impact on tariff, etc. should also be considered while doing so. </i><br /> <i>137.13 The Commission will review the execution of this Roll-out within 3 years </i><br /> <i>to ensure that it is being implemented in an effective and optimal </i><br /> <i>manner, and to address any issues that may arise. </i><br /> <i>137.14 The physical and other features and constraints acknowledged by the </i><br /> <i>ATE and the Commission in the area common to TPC-D and RInfra-D </i><br /> <i>also characterise the area of Mumbai common to BEST and TPC-D. </i><br /> <i>However, as mentioned earlier, since it is a Local Authority, BEST is not </i><br /> <i>required under the EA, 2003 to provide Open Access. The principles and </i><br /> <i>modalities of the Network Roll-out Plan approved for TPC-D in the BEST </i><br /> <i>area is predicated on this fact. The Commission is of the view that this </i><br /> <i>would not debar BEST from entering into a commercial arrangement for </i><br /> <i>the use of its network to provide electricity to TPC-D’s prospective </i><br /> <i>consumers. If such an arrangement is arrived at, the Network Roll-out </i><br /> <i>principles and modalities approved in this Order may require to be </i><br /> <i>reconsidered to that extent.” </i><br /> <b> </b><br /> 36. Thus, in terms of Impugned Order, first the downstream distribution network <br /> is to be developed from its existing DSS and CSS by TPCL and connections <br /> provided to consumers in vicinity of existing DSS/CSS and to comply with its USO <br /> and same were included under Phase I. In the Phase II, the rest of the network <br /> shall be developed. TPCL was further directed that new connections in Phase II <br /> to be released only after completion of Phase –I and for any deviation in this shall <br /> be subject to prior approval of State Commission. We find merit in this <br /> methodology of phase wise development allowed in the Impugned Order and are <br /> in agreement with the view of the State commission that it constitutes an optimal <br /> approach considering its cost-effectiveness and to avoid selective bias in the <br /> coverage of areas or consumers. In our considered view, adopting such an <br /> approach will enable faster coverage of the broader consumer base and foster a <br /> competitive market structure in line with the objectives of the Electricity Act. The <br /> Page <b>18</b> of <b>28</b> <br /> <br /><br /> <i> Judgement in Appeal Nos. 279 of 2017 </i><br /> <br /> same is preferable to sporadic network extensions to consumers located far from <br /> existing CSS/DSS, which typically involve longer lead times. <br /> <br /> 37. It has been also been contended on behalf of the Appellant, that State <br /> Commission has not considered the recommendation of Committee appointed by <br /> it to advise on the Network roll out plan. The Recommendation of the said <br /> Committee has been extracted below, as noted in paragraph 44.1 of the <br /> Impugned Order, are extracted hereinbelow. <br /> <br /> <i>“44. TPC-D NETWORK ROLL-OUT IN AREA OVERLAPPING WITH </i><br /> <i>BEST </i><br /> <i>44.1 The observations and recommendations of the Committee are </i><br /> <i>summarized below: </i><br /> <i> </i><br /> <i>a. </i> <i>The ATE Judgment is not applicable to the Licence area common </i><br /> <i>TPC-D BEST, as BEST has a special status under the EA, 2003 and is </i><br /> <i>not obliged to provide Open Access under Section 42(3) by virtue of being </i><br /> <i>a Local Authority Thus, network duplication by TPC-D is inevitable in the </i><br /> <i>BEST area. </i><br /> <i> </i><br /> <i>b. </i> <i>Therefore, in the area common to BEST, TPC-D needs to be given </i><br /> <i>some time for setting up its distribution system in a phased manner, and </i><br /> <i>hence the need for a Roll-out Plan for that area. </i><br /> <i> </i><br /> <i>c. </i> <i>TPC-D's Network Roll-out Plan for the BEST area should be such </i><br /> <i>as would ensure against selective targeting of consumers, as both </i><br /> <i>Licensees have a USO in that area. </i><br /> <i> </i><br /> <i>d. </i> <i>The appropriate solution would be for TPC-D to first develop its </i><br /> <i>distribution system at lower voltage levels in areas where the backbone </i><br /> <i>distribution system in the form of DSS and/or CSS is already available, </i><br /> <i>and then take up areas where it is yet to be set up. </i><br /> <i> </i><br /> <i>e. </i> <i>Study of the map of the distribution system submitted by TPC-D </i><br /> <i>shows that areas such as Dharavi, Carnac, Parel, Lower Parel, </i><br /> <i>Elphinstone, Mahalaxmi, Haji Ali, etc., already have DSS and/or CSS in </i><br /> Page <b>19</b> of <b>28</b> <br /> <br /><br /> <i> Judgement in Appeal Nos. 279 of 2017 </i><br /> <br /> <i>place and can be targeted first so that TPC-D can supply electricity to all </i><br /> <i>consumers, including LT consumers, in that area. </i><br /> <i> </i><br /> <i>f. </i> <i>TPC-D may target setting up the LT distribution system in areas </i><br /> <i>where the DSS/CSS already exist in a period of, say, 2 years. </i><br /> <i>44.2 In the light of the above, the Committee has recommended that </i><br /> <i>TPC-D be directed to re-submit its Network Roll-out Plan for its Licence </i><br /> <i>area overlapping that of BEST based on the above considerations.” </i><br /> <br /> 38. On perusal of the recommendations, it is observed that Committee has also <br /> recommended phased network roll out plan, and that TPCL should first develop <br /> its distribution system at lower voltage where its DSS and CSS is already existing. <br /> In our view, the network roll out methodology approved by the State Commission <br /> has broadly considered these recommendations. Moreover, it is a settled position <br /> that a State Commission is not legally bound by the recommendations of a <br /> committee it appoints. Such committees are generally set up to investigate, study, <br /> or advice on specific issues, and their role is recommendatory, not mandatory. <br /> The State Commission retains the authority to accept, reject, or modify those <br /> recommendations. Accordingly, the said contention is rejected. <br /> <br /> 39. With regard to specific contention of cherry picking, we have been informed <br /> by learned counsel of TPCL that on 29.02.2016, BEST filed Case No. 43 of 2016 <br /> before the MERC seeking to restrain Tata Power from laying its distribution <br /> network on the allegation of cherry-picking of high-end consumers, which was <br /> dismissed by MERC vide Order dated 22.01.2018 against which BEST had <br /> preferred Appeal No. 330 of 2018 which is pending adjudication before this <br /> Tribunal. As such, in the present appeal, no specific instances of Cherry picking <br /> has been indicated on behalf of BEST and only general reference has been made <br /> that such phased development shall lead to cherry picking. Having held above <br /> that permitted methodology of phased development is an optimal approach and <br /> would avoid selective bias in coverage of area, thus, avoid cherry picking, it is <br /> Page <b>20</b> of <b>28</b> <br /> <br /><br /> <i> Judgement in Appeal Nos. 279 of 2017 </i><br /> <br /> unnecessary for us to deliberate the issue of Cherry picking in the absence of <br /> specific details. The same shall be dealt in the Appeal No. 330 of 2018, pending <br /> adjudication before this Tribunal, on its own merits, <br /> 40. Accordingly, issue No 1 is decided against the Appellant on merits, and <br /> Impugned Order is upheld. <br /> <b>ISSUE NO 2 </b> <b>Is phased development of network permitted to TPCL in </b><br /> <b>contravention of specific conditions of Distribution License granted to it. </b><br /> <b>Submissions urged on behalf of BEST </b><br /> 41. It is submitted that permitted phased development of distribution network to <br /> TPCL is not in compliance with Distribution Licence No. 1 of 2014 (particularly <br /> Part II: Specific), granted by MERC on 14.08.2014 in Case No. 90 of 2014, which <br /> mandatorily required TPCL to submit a detailed Network Rollout Plan which was <br /> required to clearly demonstrate that it is cost-effective, provides equal access to <br /> all categories of consumers, creates a level playing field, and is optimal for the <br /> purpose of meeting the Universal Service Obligation in a time-bound manner; as <br /> well to be submitted for approval within six weeks from commencement of the <br /> licence. Further, MERC has gravely erred in failing to review and/or monitor the <br /> execution of the rollout of the distribution network by TPCL within the stipulated <br /> period of three years. <br /> <b>Submissions urged on behalf of State Commission </b><br /> 42. It is submitted that initially the Network roll out plan was submitted for <br /> approval by TPCL on 10.10.2014, however in view of the judgement dated <br /> 28.11.2014 of this Tribunal in Appeal Nos. 229 of 2012 and 246 of 2012, TPCL <br /> has to revise the plan and accordingly submitted the revised its Network Roll-out <br /> Plan to the State Commission on 12.02.2015. Further in compliance of the <br /> referred judgement of this Tribunal, an opportunity of hearing was provided to <br /> Page <b>21</b> of <b>28</b> <br /> <br /><br /> <i> Judgement in Appeal Nos. 279 of 2017 </i><br /> <br /> RInfra-D and the Appellant, and based on their comments, further refinements of <br /> the roll out Plan was necessitated. After inviting comments of the public and <br /> stakeholders, a public hearing was conducted on 21.06.2016 and vide Order <br /> dated 12.06.2017, the State Commission approved the Network Roll-out Plan of <br /> TPCL. <br /> <b>Submissions urged On behalf of TPCL </b><br /> 43. In addition to the submissions made on behalf of State Commission, it is <br /> submitted that Distribution Licence granted to TPCL was not a conditional <br /> licence, and MERC, vide its Order dated 14.08.2014 had directed TPCL to file a <br /> revised Network Rollout Plan, which, upon approval, would form part of the <br /> specific licence conditions under Section 16 of the Electricity Act, 2003, which <br /> provision contemplates specification of conditions applicable post facto grant of <br /> licence and not as a condition precedent to grant thereof, and hence, the grant of <br /> licence to Tata Power cannot be construed as being conditional upon prior <br /> approval of the Network Rollout Plan. Further, Network Roll out plan has been <br /> submitted in compliance with MERC’s directions and there is neither any wilful <br /> nor prolonged default on the part of Tata Power in discharge of its statutory <br /> obligations under the Electricity Act and the rules and regulations framed <br /> thereunder. <br /> <b>CONSIDERATION AND OUR VIEW </b><br /> 44. To deliberate this issue, it is of relevance to reproduce specific conditions <br /> of License: <b> </b><br /> <i> "Part II: Specific </i><br /> <i>1. </i> <i>The Distribution Licensee shall submit a detailed Network Rollout </i><br /> <i>Plan in accordance with the observations and directions of the Commission </i><br /> Page <b>22</b> of <b>28</b> <br /> <br /><br /> <i> Judgement in Appeal Nos. 279 of 2017 </i><br /> <br /> <i>in its Order dated 14 August,2014 in Case No. 90 of 2014 and the relevant </i><br /> <i>provisions of the Electricity Act, 2003, Rules and Regulations. </i><br /> <i>2. </i> <i>The plan should clearly bring out that it is cost effective; provides </i><br /> <i>equal access to all categories of consumers,· creates a level playing field; </i><br /> <i>and is optimal for the purpose of meeting the Universal Service Obligations </i><br /> <i>in a time bound manner. </i><br /> <i>3. </i> <i>The plan shall be submitted to the Commission for approval within a </i><br /> <i>period of 6 weeks from the date of commencement of this Distribution </i><br /> <i>Licence." </i><br /> 45. In terms of specific conditions of Distribution license granted to TPCL vide <br /> State Commission Order dated 14.08.2014, the Distribution licensee was to <br /> submit a detailed Network Roll out plan, which should be cost effective, creates <br /> a level playing field and optimal; for meeting Universal Service Obligation in a <br /> time bound manner. In this regard we note from the submissions made on behalf <br /> of State Commission that initially the plan was submitted by TPCL on 10.10.2014, <br /> which necessitated modifications in view of the Judgement of this Tribunal dated <br /> 28.11.2014 and in accordance with the directions in this judgement, both R-infra <br /> and the Appellant were provided opportunity to make their submissions and after <br /> conducting public hearing, the network roll out plan was approved by the <br /> Impugned Order. As already noted in preceding paragraphs, there has been <br /> multiple litigation with regard to grant of license to TPCL, development of network <br /> in the area common to R-Infra and the Appellant and few of such litigations are <br /> still pending adjudication in this Tribunal or at Supreme Court, and some <br /> directions have been passed from time to time in particular cases. In this present <br /> issue, the roll out plan submitted by TPCL needed to be modified in compliance <br /> with the direction of this Tribunal in the above referred judgement. It has been <br /> already held in the preceding paragraph that that suggested methodology is <br /> optimal from cost consideration and would lead to covering a larger area in short <br /> time. We are therefore of the view that permitted phased development of <br /> Page <b>23</b> of <b>28</b> <br /> <br /><br /> <i> Judgement in Appeal Nos. 279 of 2017 </i><br /> <br /> distribution network is not in contravention of License condition of TPCL. <br /> Accordingly, the issue is decided against the Appellant on merits. <br /> <b>ISSUE No 3: Non consideration of practical issues in approved Migration </b><br /> <b>plan </b><br /> <b>Submissions urged on behalf of BEST </b> <b> </b><br /> 46. It is submitted that, in providing for the process of switchover and/or <br /> migration, MERC failed to take into account critical practical difficulties and <br /> specific operational requirements, including that BEST has an elaborate <br /> distribution network across Mumbai City to meet its Universal Service Obligation <br /> and, upon switchover, infrastructure developed to meet the load of migrating <br /> consumers would become redundant and/or stranded, thereby causing financial <br /> loss to BEST. Further, the protocol envisaging a three-day timeline for scrutiny of <br /> applications and for sharing of information by the existing distribution licensee <br /> relating to arrears, disputes, court cases and other consumer-related issues is <br /> wholly inadequate, impractical, and incapable of ensuring due diligence and <br /> meticulous compliance, particularly in view of unforeseen operational difficulties. <br /> In addition, MERC failed to consider that defects and/or tampering may be <br /> detected during laboratory testing after removal of meters, in which event <br /> appropriate provisions are required for raising and recovering claims arising out <br /> of such defects or tampering, which have not been adequately provided for. <br /> 47. MERC gravely erred in relaxing and/or diluting the provisions of SoP <br /> Regulations in favour of TPCL by permitting relaxation of the obligation to supply <br /> on demand to applicants until the scheduled or actual date of completion of works <br /> in each phase or stage, whichever is earlier. While MERC has specified the <br /> applicability of the SoP Regulations for the process of switchover and for release <br /> of connections to new consumers as per the prescribed protocol. It clearly <br /> Page <b>24</b> of <b>28</b> <br /> <br /><br /> <i> Judgement in Appeal Nos. 279 of 2017 </i><br /> <br /> establish that MERC has relaxed and/or diluted the mandatory provisions of the <br /> Electricity Act, 2003 and the SoP Regulations so as to facilitate TPCL to develop <br /> its network as per its own convenience and suitability. <br /> <br /> <b>Submissions urged on behalf of State Commission </b><br /> <br /> 48. The issue regarding the inadequacy of the three-day period stipulated for <br /> sharing consumer details with the other distribution licensee was duly considered <br /> and addressed by the State Commission in the Impugned Order. The State <br /> Commission observed that the changeover protocol already in operation in Tata <br /> Power’s area of supply overlapping with that of RInfra-D in the suburban region <br /> of Mumbai, since 2009, prescribed the same period of three days for sharing <br /> consumer-related information, and that the said time frame has functioned <br /> effectively. The identical time period has been incorporated in the switchover <br /> protocol applicable to TPCL’s entire area of supply overlapping with that of both <br /> the Appellant and RInfra-D. The Appellant’s further contention concerning <br /> possible meter tampering and the need for provision for subsequent recovery of <br /> claims has also been specifically dealt with by the State Commission in the <br /> Impugned Order. <br /> <b> </b><br /> <b>Submissions urged on behalf of TPCL </b><br /> <b> </b><br /> 49. Supplementing the submissions made on behalf of State Commission it is <br /> submitted, that civil appeal filed by BEST before Supreme Court seeking <br /> directions against TPCL to supply electricity either through BEST’s network or by <br /> laying its own distribution network, was dismissed with costs in <b>“</b> <b><i>BEST v. MERC </i></b><br /> <b><i>& Ors.</i></b> <b> (2015) 2 SCC 438”.</b> Pursuant thereto, MERC suo motu listed Case No. <br /> 30 of 2011 and connected matters for monitoring switchover/migration of <br /> consumers from BEST to Tata Power and by Order dated 06.06.2016, MERC <br /> directed that until approval of the migration protocol, TPCL and BEST shall <br /> Page <b>25</b> of <b>28</b> <br /> <br /><br /> <i> Judgement in Appeal Nos. 279 of 2017 </i><br /> <br /> coordinate and disconnect consumers to minimise disruption of supply. This <br /> order attained finality, BEST having not challenged the same. <br /> <br /> 50. It is further submitted that BEST has approached this Tribunal with unclean <br /> hands and has suppressed material facts, inasmuch as switchover of consumers <br /> has been taking place both prior to and after the grant of Distribution Licence No. <br /> 1 of 2014, even in the absence of any approved migration protocol, with BEST <br /> duly effecting permanent disconnection of its supply to such consumers. Further, <br /> during the pendency of proceedings relating to approval of the Network Rollout <br /> Plan, the MERC, by Order dated 18.05.2016, approved a DPR amounting to Rs. <br /> 218.74 Crores for laying of network in areas where both BEST and TPCL are <br /> licensed to supply electricity, and all works undertaken by Tata Power to connect <br /> consumers have been carried out strictly in accordance with such DPRs. <br /> <b> </b><br /> <b>CONSIDERATION AND OUR VIEWS </b><br /> <b> </b><br /> 51. In the Impugned Order, the recommendations of the Committee with regard <br /> to migration protocol, as well as the concerns raised by stake holders, including <br /> that of Appellant has been deliberated in detail in Chapter 5. With regard to <br /> specific contention for period of 3 days for sharing information, the following <br /> observations have been recorded in the Impugned Order: <br /> <br /> <i>“n. Period of 3 days (Point 13 at para. 5.1 of the Report) may be extended to 7 days</i> <br /> <i> </i><br /> <i>135.25 The Commission notes that the period of 3 days for sharing information </i><br /> <i>regarding the consumer with the other Distribution Licensee is also stipulated in the </i><br /> <i>Change-over Protocol which is being followed since 2009. Hence, the Commission </i><br /> <i>does not consider a longer period to be necessary for the Switch-over Protocol.” </i> <br /> <br /> 52. The specific contention with regard to pending disputes, outstanding dues <br /> payable on account of meter tapering, ongoing court cases etc., has been dealt <br /> Page <b>26</b> of <b>28</b> <br /> <br /><br /> <i> Judgement in Appeal Nos. 279 of 2017 </i><br /> <br /> at Para 135.22 -135.24 of the Impugned Order. The relevant extracts thereof <br /> are reproduced herein below: <br /> <i>“m. Switch-over of consumers with pending dues/disputes should not be allowed, </i><br /> <i>or the arrears of existing Licensee may be recovered by the other Distribution </i><br /> <i>Licensee </i><br /> <i>135.22 As regards RInfra-D’s contention that consumers against whom the </i><br /> <i>existing Licensee has pending cases or dues should not be allowed to switch-</i><br /> <i>over, the Commission notes that in, the Change-over Protocol approved in Order </i><br /> <i>dated 15 October, 2009 in Case No. 50 of 2009, the restriction on change-over </i><br /> <i>is limited only to the payment defaults: </i><br /> <i>“iv. No consumer who has been disconnected for payment default shall be </i><br /> <i>allowed a Changeover without clearing dues of the Existing Distribution </i><br /> <i>Licensee.” </i><br /> <i>135.23 On the analogy of the Change-over Protocol, the same provision shall </i><br /> <i>apply to applications for switch-over. The Switch-over Protocol approved by the </i><br /> <i>Commission in the present Order also provides for recovery by the other </i><br /> <i>Licensee of any remaining net consumer dues intimated by the existing Licensee </i><br /> <i>after switch-over. </i><br /> <i>135.24 However, denying switch-over to a consumer because of court cases or </i><br /> <i>other pending legal disputes with the existing Distribution Licensee would not be </i><br /> <i>justified since the merits or otherwise of the respective claims are yet to be </i><br /> <i>decided by the concerned court or other forum. Any dues arising from the </i><br /> <i>outcome of such legal disputes after switch-over may be recovered by the </i><br /> <i>Licensee involved as in the case of any other such court dispensations.” </i><br /> 53. We are also of the view that the changeover protocol, which has been in <br /> operation since 2009 between area common to TPC and R-Infra/APEML, without <br /> any functional difficulty, is rightly made applicable in the present case. The <br /> contention of BEST that a different protocol involving its network ought to be <br /> adopted has no merit. With regard to changeover during pending litigation/ <br /> subsequent issues of meter tempering, we find no error in the Impugned Order, <br /> as the mere pendency of cases cannot justify denial of changeover, and any dues <br /> payable after switchover can be recovered in accordance with the prescribed <br /> dispensation. <br /> Page <b>27</b> of <b>28</b> <br /> <br /><br /> <i> Judgement in Appeal Nos. 279 of 2017 </i><br /> <br /> 54. The plea of stranded assets, due to changeover also has no merit. The <br /> provision of Electricity Act itself mandates the presence of more than one <br /> distribution licensee in the same area of supply and laying of network by each <br /> licensee is also permitted. Moreover, the Appellant, being a local authority, is <br /> exempt under Section 42(3) of the Act from the obligation to provide open access <br /> to its network and consequently if a consumer seek electricity from other <br /> distribution licensee, they are obligated to lay the network and supply electricity. <br /> Consequently, duplication of networks in overlapping areas is an inevitable <br /> statutory outcome. In view of the foregoing, we find no merit in the contention of <br /> BEST. <br /> <b>ORDER </b><br /> 55. In view of above deliberations, we do not find any error in the Impugned <br /> Order passed by the State Commission necessitating our interference and <br /> accordingly, Impugned Order dated 12.06.2017 is hereby upheld. <b> </b><br /> The Captioned Appeal and pending IAs, if any, stands dismissed. <br /> <br /> <b>th</b><br /> <b>PRONOUNCED IN THE OPEN COURT ON THIS 11</b> <b> DAY OF MARCH, 2026. </b><br /> <b> </b><br /> <b> </b><br /> <b> </b><br /> <b> </b><br /> <b>(Virender Bhat) </b><br /> <b>Judicial Member </b><br /> <b>(Seema Gupta) </b><br /> <b>Officiating Chairperson </b><br /> <b> </b><br /> <b>REPORTABLE / NON-REPORTABLE </b><br /> <i> </i><br /> <i>pr/dk/ag</i> <i> </i><br /> <b> </b><br /> <b> </b> <br /> Page <b>28</b> of <b>28</b> <br /> </div>