Sanyogita Gupta & Ors. vs Ashok Kumar Gupta

Court
Delhi High Court
Case type
Criminal Revision Petition
Decided on
27-02-2026

$~
* IN THE HIGH COURT OF DELHI AT NEW DELHI
% Judgment reserved on: 09.01.2026
Judgment pronounced on: 27.02.2026
Judgment uploaded on: 27.02.2026
+ CRL.REV.P. 520/2024 & CRL.M.A. 17787/2023
SANYOGITA GUPTA & ORS. ....Petitioners
Through: Mr. S. D. Windlesh, Adv.

versus

ASHOK KUMAR GUPTA .....Respondent
Through: Mr. Nitin Saluja and Ms. Ishita
Soni, Advs.

CORAM:
HON’BLE DR. JUSTICE SWARANA KANTA SHARMA
JUDGMENT

DR. SWARANA KANTA SHARMA, J
1. By way of the present petition, the petitioners are challenging
the order dated 25.09.2019 [hereafter „ impugned order ‟], passed by
the learned Family Court, East District, Karkardooma Courts, Delhi
[hereafter „ Family Court ‟] in CC No. 389/2017, filed under Section
125 of the Code of Criminal Procedure, 1973 [hereafter „Cr.P.C.‟], by
the petitioners, claiming maintenance from the respondent.
2. Briefly stated, the facts of the present case are that the
petitioner no. 1 is the legally wedded wife of the respondent no. 1.
They were engaged to each other on 01.01.1999 and were married on
CRL.REV.P. 520/2024 Page 1 of 14


Signature Not Verified
Digitally Signed
By:ZEENAT PRAVEEN
Signing Date:27.02.2026
19:53:14

27.05.2001 in Delhi as per Hindu rites and ceremonies. Out of the
said wedlock, two daughters, i.e., petitioner no. 2 and petitioner no. 3,
were born on 30.03.2002 and 29.08.2005 respectively. Due to
matrimonial discord between the parties, the relationship between
them deteriorated and they started living separately. Thereafter, the
petitioner, in the year 2016, had filed a petition under Section 125 of
the Code of Criminal Procedure, 1973 [hereafter „ Cr.P.C. ‟], inter alia
alleging that she and her minor daughters had been neglected and
refused maintenance by the respondent, despite his having sufficient
means to maintain them. It was averred that she was a housewife and
had no independent source of income to sustain herself or to provide
for the education and daily needs of the children. It was further stated
that none of the petitioners were earning any income and were
dependent upon financial assistance and loans received from friends
and relatives for their survival and the educational expenses of the
children. It was stated that the respondent was gainfully employed
and earning a regular income sufficient to maintain the petitioners but
had failed to discharge his legal and moral obligations towards them.
3. By way of the impugned order dated 25.09.2019, the learned
Family Court has awarded interim maintenance at the rate of Rs.
5,500/- in favour of each of the petitioners, i.e. Rs. 16,500/-, however ,
only with effect from 01.01.2019. The relevant observations are as
under:
“...11. The present petition has remained pending since
05.03.2016. I am of the opinion that in the peculiar facts of
CRL.REV.P. 520/2024 Page 2 of 14


Signature Not Verified
Digitally Signed
By:ZEENAT PRAVEEN
Signing Date:27.02.2026
19:53:14

this case and for the purpose of the present Order, the interim
maintenance be awarded to the petitioners with effect from
01.01.2019 and not from the date of filing of this petition as
is the normal rule. The respondent is thus directed to pay
Rs.5500/- per month as interim maintenance to each of the
petitioners (total Rs.16,500/- per month) with effect from
01.01.2019 till the disposal of the present petition.
12. It is also made clear that the observations made in the
present order are for the purpose of disposal of the present
interim· maintenance application. The directions issued under
this order would be subject to the further directions as may be
passed at the time of disposal of this petition. It is also
clarified that any amount received by the petitioners towards
maintenance from the respondent in any other proceedings or
in the present proceedings shall be adjusted against the
amount payable under this order.
13. The application for grant of interim maintenance stands
disposed off accordingly...”

4. The petitioners are aggrieved only by the limited aspect of the
impugned order – directing payment of interim maintenance with
effect from 01.01.2019, and not from the date of filing of the petition
under Section 125 of Cr.P.C., i.e. 03.03.2016.
5. The learned counsel appearing on behalf of the petitioners
submits that the learned Family Court has erred in directing that
interim maintenance shall be payable only with effect from
01.01.2019 instead of from the date of filing of the petition, i.e.,
05.03.2016, without recording any cogent or special reasons for
departing from the normal rule. It is argued that the petition under
Section 125 of Cr.P.C. had remained pending for several years for no
fault of the petitioners, and they had been compelled to survive on
financial assistance from friends and relatives during this period. The
CRL.REV.P. 520/2024 Page 3 of 14


Signature Not Verified
Digitally Signed
By:ZEENAT PRAVEEN
Signing Date:27.02.2026
19:53:14

respondent, despite being gainfully employed and earning
approximately ₹48,000–50,000 per month at the relevant time, had
neither voluntarily maintained the wife and minor daughters nor
complied with the interim maintenance order in its true spirit, having
paid only a negligible amount and accumulated substantial arrears. It
is further contended that the respondent has repeatedly attempted to
avoid his statutory obligation by filing multiple applications for
reduction or modification, all of which have failed, and has taken
inconsistent pleas regarding his financial incapacity, including
voluntary retirement and alleged loans, which stand unsupported by
any credible material. The petitioners submit that the Family Court,
having accepted their entitlement to maintenance and having found
no independent source of income in their favour, ought to have
granted maintenance from the date of application, and the failure to
do so has resulted in grave financial prejudice to the wife and the two
daughters, who have been left without lawful support for the
prolonged pendency of the proceedings. It is therefore prayed that the
impugned order be modified to the limited extent of directing that
interim maintenance be payable from the date of filing of the petition.
6. The learned counsel appearing on behalf of the respondent
submits that the present petition is wholly misconceived and liable to
be dismissed, inasmuch as the learned Family Court has exercised its
discretion judiciously and for recorded reasons while directing that
interim maintenance be payable with effect from 01.01.2019, having
regard to the peculiar facts of the case. It is argued that the law does
CRL.REV.P. 520/2024 Page 4 of 14


Signature Not Verified
Digitally Signed
By:ZEENAT PRAVEEN
Signing Date:27.02.2026
19:53:14

not mandatorily require that maintenance must, in every case, be
granted from the date of filing of the application, and the discretion
vested in the Court to determine the effective date continues to
subsist depending upon the facts and equities of each case. It is
further contended that the respondent has undergone a substantial
change in financial circumstances, having been retrenched from
service in January 2020 and remaining without regular income
thereafter; he has even suffered imprisonment on account of inability
to clear arrears. The respondent submits that the petitioners have,
over time, encashed multiple FDRs amounting to substantial sums,
withdrawn monies from his account, received compensation under
statutory schemes, and are in possession of other financial resources
including matured LIC proceeds and interest-bearing deposits. It is
also contended that petitioner no. 1 is an educated individual who has
concealed bank accounts and is earning through private tuitions, and
that the petitioners are residing in accommodation belonging to the
respondent‟s family without paying rent. The respondent further
points out his medical condition, including treatment for depression,
financial liabilities towards his aged parents, and outstanding loan
repayments, which materially affect his capacity to pay. It is thus
submitted that there exists no justification either to enhance the
maintenance amount to an exorbitant figure or to direct payment
retrospectively from 2016, particularly when the Family Court has
already assessed the material on record and balanced the competing
equities. The respondent accordingly prays that the present revision
CRL.REV.P. 520/2024 Page 5 of 14


Signature Not Verified
Digitally Signed
By:ZEENAT PRAVEEN
Signing Date:27.02.2026
19:53:14

petition be dismissed.
7. This Court has heard arguments addressed on behalf of the
petitioner as well as the respondent, and has perused the material
available on record.
8. This Court notes that the present revision petition has been
preferred by the wife and her two daughters, assailing the impugned
order on the ground that the learned Family Court, while granting
interim maintenance, erred in directing that the same shall be payable
with effect from 01.01.2019 instead of from the date of filing of the
petition under Section 125 of Cr.P.C., i.e., 05.03.2016, and further
failed to award an appropriate and commensurate amount having
regard to the respondent‟s income and the needs of the petitioners.
9. Therefore, the principal issue which arises for consideration is
whether the learned Family Court was justified in directing that
interim maintenance shall be payable from 01.01.2019, or whether, in
the facts and circumstances of the case, the petitioners are entitled to
interim maintenance from the date of filing of the petition under
Section 125 of Cr.P.C. The ancillary issue, as urged by the
petitioners, also concerns the adequacy of the quantum of
maintenance awarded in their favour.
10. As regards the issue of date from which maintenance is to be
granted, the Hon‟ble Supreme Court in Rajnesh v. Neha: (2021) 2
SCC 324 has held and directed as under:
“ 109 . The judgments hereinabove reveal the divergent views of
CRL.REV.P. 520/2024 Page 6 of 14


Signature Not Verified
Digitally Signed
By:ZEENAT PRAVEEN
Signing Date:27.02.2026
19:53:14

different High Courts on the date from which maintenance
must be awarded. Even though a judicial discretion is conferred
upon the Court to grant maintenance either from the date of
application or from the date of the order in Section 125(2)
Code of Criminal Procedure, it would be appropriate to grant
maintenance from the date of application in all cases, including
Section 125 Code of Criminal Procedure In the practical
working of the provisions relating to maintenance, we find that
there is significant delay in disposal of the applications for
interim maintenance for years on end. It would therefore be in
the interests of justice and fair play that maintenance is
awarded from the date of the application.
110 . In Shail Kumari Devi and Ors. v. Krishnan Bhagwan
Pathak , this Court held that the entitlement of maintenance
should not be left to the uncertain date of disposal of the case.
The enormous delay in disposal of proceedings justifies the
award of maintenance from the date of application. In Bhuwan
Mohan Singh v. Meena , this Court held that repetitive
adjournments sought by the husband in that case resulted in
delay of 9 years in the adjudication of the case. The delay in
adjudication was not only against human rights, but also
against the basic embodiment of dignity of an individual. The
delay in the conduct of the proceedings would require grant of
maintenance to date back to the date of application.
*
VI. Final Directions
(a) ... …
(b) ... …
(c) ... …
(d) Date from which maintenance is to be awarded
131. We make it clear that maintenance in all cases will be
awarded from the date of filing the application for
maintenance, as held in Part B - IV above.”

11. In Shahjahan v. State of Uttar Pradesh & Anr.: 2025 INSC
528 , the Hon‟ble Supreme Court considered the issue regarding the
date from which maintenance under Section 125 of Cr.P.C. ought to
be made payable. The relevant observations are extracted herein
CRL.REV.P. 520/2024 Page 7 of 14


Signature Not Verified
Digitally Signed
By:ZEENAT PRAVEEN
Signing Date:27.02.2026
19:53:14

below:
“17. This brings us to the next question, i.e., from which date
will the maintenance be payable – the date of the application or
the date of the Order? The appellant has contested the direction
of the Family Court wherein it has made the maintenance
payable from the date of the order instead of the date of
application. Of course, Section 125(2) of the Code empowers
the Court to award maintenance from the date of the order but
the same has to be justified in the background of the attendant
facts and circumstances and should not cause unnecessary
hardship to the applicant. In our view, Section 125 of the Code
is a beneficial piece of legislation which has been enacted to
protect the wife and children from destitution and vagrancy
and, in the usual course, it would not be appropriate to
disadvantage the applicant for the delay in the disposal of the
application by the judicial system. It would be beneficial to
reproduce the relevant discussion in Rajnesh v Neha, (2021) 2
SCC 324 , which is extracted hereunder:
„109. The judgments hereinabove reveal the divergent
views of different High Courts on the date from which
maintenance must be awarded. Even though a judicial
discretion is conferred upon the court to grant maintenance
either from the date of application or from the date of the
order in Section 125(2) CrPC, it would be appropriate to
grant maintenance from the date of application in all cases,
including Section 125 CrPC. In the practical working of
the provisions relating to maintenance, we find that there
is significant delay in disposal of the applications for
interim maintenance for years on end. It would therefore
be in the interests of justice and fair play that maintenance
is awarded from the date of the application.
110. In Shail Kumari Devi v. Krishan Bhagwan Pathak
[Shail Kumari Devi v. Krishan Bhagwan Pathak, (2008) 9
SCC 632: (2008) 3 SCC (Cri) 839], this Court held that
the entitlement of maintenance should not be left to the
uncertain date of disposal of the case. The enormous delay
in disposal of proceedings justifies the award of
maintenance from the date of application. In Bhuwan
Mohan Singh v. Meena [Bhuwan Mohan Singh v. Meena,
(2015) 6 SCC 353: (2015) 3 SCC (Civ) 321: (2015) 4 SCC
(Cri) 200], this Court held that repetitive adjournments
sought by the husband in that case resulted in delay of 9
CRL.REV.P. 520/2024 Page 8 of 14


Signature Not Verified
Digitally Signed
By:ZEENAT PRAVEEN
Signing Date:27.02.2026
19:53:14

years in the adjudication of the case. The delay in
adjudication was not only against human rights, but also
against the basic embodiment of dignity of an individual.
The delay in the conduct of the proceedings would require
grant of maintenance to date back to the date of
application.
111. The rationale of granting maintenance from the date
of application finds its roots in the object of enacting
maintenance legislations, so as to enable the wife to
overcome the financial crunch which occurs on separation
from the husband. Financial constraints of a dependent
spouse hamper their capacity to be effectively represented
before the court. In order to prevent a dependant from
being reduced to destitution, it is necessary that
maintenance is awarded from the date on which the
application for maintenance is filed before the court
concerned.
112. In Badshah v. Urmila Badshah Godse [Badshah v.
Urmila Badshah Godse, (2014) 1 SCC 188: (2014) 1 SCC
(Civ) 51], the Supreme Court was considering the
interpretation of Section 125 CrPC. The Court held: (SCC
p. 196, para 13) “13.3. … purposive interpretation needs to
be given to the provisions of Section 125 CrPC. While
dealing with the application of a destitute wife or hapless
children or parents under this provision, the Court is
dealing with the marginalised sections of the society. The
purpose is to achieve “social justice” which is the
constitutional vision, enshrined in the Preamble of the
Constitution of India. The Preamble to the Constitution of
India clearly signals that we have chosen the democratic
path under the rule of law to achieve the goal of securing
for all its citizens, justice, liberty, equality and fraternity. It
specifically highlights achieving their social justice.
Therefore, it becomes the bounden duty of the courts to
advance the cause of social justice. While giving
interpretation to a particular provision, the court is
supposed to bridge the gap between the law and society.”
(emphasis supplied)
113. It has therefore become necessary to issue directions
to bring about uniformity and consistency in the orders
passed by all courts, by directing that maintenance be
awarded from the date on which the application was made
before the court concerned. The right to claim
CRL.REV.P. 520/2024 Page 9 of 14


Signature Not Verified
Digitally Signed
By:ZEENAT PRAVEEN
Signing Date:27.02.2026
19:53:14

maintenance must date back to the date of filing the
application, since the period during which the maintenance
proceedings remained pending is not within the control of
the applicant.‟ (emphasis supplied by bolding; underlining
reflects emphasis supplied in original)‟
18. No doubt, Rajnesh (supra) was pronounced after the
Family Court’s Order and Impugned Order were passed,
but its enunciation of the law would entail that maintenance
should be reckoned as awarded from the date of filing of
the application in this behalf. Having regard to the totality
of the facts and circumstances, we direct the respondent
no.2 to pay Rs.4,000/- (Rupees Four Thousand) per month
as maintenance to the appellant, from the date of filing of
the maintenance petition before the Family Court. The
maintenance awarded to the children will also be payable from
the date of filing of the maintenance petition before the Family
Court. We take judicial notice that during the pendency of the
appeal before this Court, the daughter Aatika has attained
majority. Having due regard to the scheme of Section 125 of
the Code, it is clarified that the maintenance awarded in her
favour will only be payable up to the date of her attaining
majority. The entire amount of arrears shall be deposited by the
respondent no.2 in the Family Court within four months from
today, after adjustment of amount(s), if any, already
paid/deposited by him. ”
(Emphasis Supplied)

12. This Court notes that in Shahjahan v. State of Uttar Pradesh
(supra) , the Hon‟ble Supreme Court has reaffirmed that although
Section 125(2) of Cr.P.C. confers discretion upon the Court to award
maintenance either from the date of the order or from the date of the
application, such discretion must be exercised in a manner consistent
with the beneficial object of the provision. The Hon‟ble Supreme
Court emphasized that Section 125 of Cr.P.C. is a social welfare
legislation intended to protect wives and children from destitution,
and that delays in judicial proceedings should not operate to the
CRL.REV.P. 520/2024 Page 10 of 14


Signature Not Verified
Digitally Signed
By:ZEENAT PRAVEEN
Signing Date:27.02.2026
19:53:14

disadvantage of the claimant. Relying upon the principles earlier laid
down in Rajnesh v. Neha (supra) , the Court held that, in the usual
course, maintenance ought to be awarded from the date of filing of
the application so as to prevent financial hardship caused by
protracted litigation. It was observed that the right to claim
maintenance must relate back to the date of institution of
proceedings, since the pendency of the case is beyond the control of
the applicant. Consequently, it was directed that maintenance be
made payable from the date of filing of the petition, including for the
children, subject to statutory limitations such as attainment of
majority.
13. It is noted by this Court that the petition under Section 125 of
Cr.P.C. was instituted by the petitioners on 05.03.2016. The learned
Family Court, while allowing interim maintenance, had directed that
the same shall be payable with effect from 01.01.2019, observing that
the direction was being passed in view of the “peculiar facts” of the
case. However, this Court finds that the impugned order does not
disclose any clear or cogent reason for postponing the
commencement of maintenance by nearly three years from the date of
filing of the petition. A discretionary power, though wide, must be
exercised on discernible principles and supported by reasons; in the
absence of such reasons, the exercise of discretion becomes
vulnerable to interference.
14. This Court further observes that Section 125 of Cr.P.C. is a
measure of social justice intended to prevent destitution and
CRL.REV.P. 520/2024 Page 11 of 14


Signature Not Verified
Digitally Signed
By:ZEENAT PRAVEEN
Signing Date:27.02.2026
19:53:14

vagrancy. The object of the provision is not punitive but protective.
Where a wife and minor children approach the Court alleging neglect
and refusal to maintain, and the Court ultimately finds them entitled
to maintenance, the normal rule – now consistently affirmed by the
Hon‟ble Supreme Court – is that such maintenance should relate back
to the date of the application. The delay in adjudication of
maintenance proceedings is ordinarily systemic and cannot be
attributed to the dependent spouse or children. To deprive them of
maintenance for the interregnum period, without adequate
justification, would defeat the very purpose of the legislation.
15. It is though correct that the decision in Rajnesh v. Neha
(supra) was rendered after the passing of the Family Court‟s order in
the present case, however, as subsequently clarified in Shahjahan v.
State of Uttar Pradesh (supra) , the principles laid down in Rajnesh
v. Neha (supra) are declaratory of the legal position and intended to
bring uniformity and consistency in maintenance jurisprudence. The
Hon‟ble Supreme Court has categorically observed that maintenance
should ordinarily be awarded from the date of filing of the
application, since the pendency of proceedings is not within the
control of the claimant.
16. In the facts of the present case, the petitioners – being the wife
and two daughters – had asserted that they had no independent source
of income and were dependent upon assistance from relatives and
friends. The respondent, at the relevant time, was gainfully employed
and earning a regular income. Even as per the material before the
CRL.REV.P. 520/2024 Page 12 of 14


Signature Not Verified
Digitally Signed
By:ZEENAT PRAVEEN
Signing Date:27.02.2026
19:53:14

Family Court, his net income was assessed at about ₹35,000/- per
month, and there is nothing to suggest that during the initial
pendency of the petition, he was incapable of contributing towards
the maintenance of his family. The record also reflects prolonged
litigation between the parties; however, there is no finding that the
petitioners were responsible for any deliberate delay so as to
disentitle them from maintenance for the earlier period.
17. The contention of the respondent regarding subsequent change
in circumstances, including cessation of employment, medical issues,
loans, or other liabilities, may be relevant for proceedings under
Section 127 of Cr.P.C. for modification of maintenance, but cannot
retrospectively justify denial of maintenance for the period during
which he admittedly had sufficient earning capacity. Similarly,
disputes regarding encashment of FDRs or other financial
transactions do not absolve the statutory obligation to maintain the
wife and minor children.
18. As regards the quantum of maintenance, this Court notes that
the learned Family Court awarded ₹5,500/- per month to each of the
three petitioners, aggregating to ₹16,500/- per month. Having regard
to the respondent‟s assessed income at the relevant time and the
needs of two growing daughters pursuing education, the said amount
cannot be said to be excessive. At the same time, the prayer for
substantial enhancement to ₹80,000/- per month appears
disproportionate to the income assessed by the Family Court,
particularly in the absence of clear material demonstrating
CRL.REV.P. 520/2024 Page 13 of 14


Signature Not Verified
Digitally Signed
By:ZEENAT PRAVEEN
Signing Date:27.02.2026
19:53:14

significantly higher earnings. The quantum awarded by the Family
Court appears to have been determined on a prima facie assessment
of income and liabilities and does not call for interference at this
stage, save and except in relation to the effective date from which
payment of interim maintenance is to be made. Needless to say, the
petitioner would be at liberty to file an application under Section 127
of Cr.P.C. before the Family Court, if so advised.
19. In view of the aforesaid discussion, this Court is of the opinion
that the learned Family Court erred in directing that interim
maintenance shall be payable only with effect from 01.01.2019
without assigning adequate reasons. The petitioners herein are held
entitled to interim maintenance from the date of filing of the petition,
i.e., 05.03.2016. The impugned order dated 25.09.2019 is accordingly
modified to this extent, subject to adjustment of any amounts already
paid.
20. In view of the above, the present petition stands disposed of.
21. Nothing expressed hereinunder shall tantamount to an
expression on the merits of the case.
22. The judgment be uploaded on the website forthwith.


DR. SWARANA KANTA SHARMA, J
FEBRUARY 27, 2026/
T.S.
CRL.REV.P. 520/2024 Page 14 of 14


Signature Not Verified
Digitally Signed
By:ZEENAT PRAVEEN
Signing Date:27.02.2026
19:53:14