Steel Authorlty Of India Imited vs Primetals Technologies India Pvt. Ltd

Court
Delhi High Court

$~20
* IN THE HIGH COURT OF DELHI AT NEW DELHI
# CNR No. DLHC010236312026
+ FAO(OS) (COMM) 141/2026
STEEL AUTHORITY OF INDIA LIMITED .....Appellant
Through: Mr. Jayant Mehta, Senior Advocate
with Mr. Ashish Tiwari, Mr. Anurag Tiwari, Ms.
Mansvini Jain and Mr. Sahib Patel, Advs.
versus
PRIMETALS TECHNOLOGIES INDIA PVT. LTD .....Respondent
Through: Mr. Rajesh Markanda, Mr., Keshri
Kumar, Mr. Arshdeep Singh, Advs
CORAM:
HON'BLE MR. JUSTICE C. HARI SHANKAR
HON'BLE MS. JUSTICE MANMEET PRITAM SINGH ARORA
O R D E R
% 14.09.2026

This matter is being taken up today as 11.09.2026 was declared holiday
on account of BRICS Summit.

MANMEET PRITAM SINGH ARORA, J.
FAO(OS)(COMM)- 141/2026
1. The present appeal has been filed under Section 37 of the Arbitration
and Conciliation Act, 1996 [‘Act’], assailing the judgment dated 12.02.2026
passed by the learned Single Judge in OMP(COMM) No. 233/2025
[‘impugned judgment’], whereby the Appellant’s objections under Section 34
of the Act were dismissed and the arbitral award dated 28.08.2024, as
modified vide addendum dated 22.11.2024, was upheld.
FACTUAL MATRIX
2. The dispute arises out of Contract No. TC/M/AGT-964 dated
03.03.2008 entered into between Appellant and a consortium including the
Signature Not Verified
FAO(OS) (COMM) 141/2026 Page 1 of 26

Signed By:MAHIMA
SHARMA
Signing Date:01.10.2026
11:21

Respondent for setting up Unit-I, namely the Hot Dip Galvanising Line
(‘HDGL’), and Unit-II, namely the Electrolytic Cleaning Line (‘ECL’) in the
Bokaro Steel Plant (‘BSP’) of the Appellant (‘Project’).
3. The contract price, in terms of Clause 11 read with Appendix-1 of the
General Conditions of Contract (‘GCC’), for the Unit-I/HDGL was Euro
33,408,895/- and INR 223,78,09,443/-, and for the Unit-II/ECL was Euro
2,179,105/- and INR 21,79,105/-.
4. The dispute has arisen with respect to the Appellant’s claim for
1
recovery of shortfall in the minimum CENVAT credit guaranteed (‘MGCC’)
by Respondent for Unit-I/HDGL and Unit-II/ECL respectively, in terms of
Clause 11 read with Appendix-1 of the GCC. As per the Appellant, this
amount was INR 25,26,82,631/- for Unit-I/HDGL and INR 76,90,45,532/- for
Unit-II/ECL.
5. As per the Appellant, the obligation of the Respondent to pass on the
minimum CENVAT credit recorded in the GCC formed a material component
of the contractual bargain. It relies upon a Memorandum of Understanding
(‘MoU’) dated 04.03.2008 executed between the parties to clarify certain
issues, including the consequences arising out of a shortfall in CENVAT
credit.
6. The Project was commissioned in stages. The Unit-II/ECL was
commissioned on 20.02.2017 and the Unit-I/HDGL on 26.06.2018. The Final
Acceptance Certificate (‘FAC’) for the Unit-II/ECL was issued on
15.02.2019, whereas the FAC for the Unit-I/HDGL was issued on 05.05.2023.

1
Central Value Added Tax
Signature Not Verified
FAO(OS) (COMM) 141/2026 Page 2 of 26

Signed By:MAHIMA
SHARMA
Signing Date:01.10.2026
11:21

7. After completion of the relevant performance tests, the Respondent
raised three [3] invoices dated 03.04.2017, 10.09.2018 and 30.10.2018. The
aggregate value of the said invoices was INR 8,02,27,262.51/-.
8. The Appellant contended that, under Clause 14.5.6 of the GCC, it was
entitled to recover any shortfall in the minimum guaranteed CENVAT credit
[‘MGCC’]. It contended that the said Clause contemplated that the
Respondent (i.e. contractor) would indicate the MGCC that can be availed by
the Appellant (i.e. the employer) against the material supplied for the subject
work. The Appellant contended that the clause contemplates that, in the event
of a shortfall in the MGCC by the contractor, the shortfall amount shall be
deducted by the employer from the invoices. Whereas, in the event of excess
CENVAT credit, 50% of such ‘excess’ CENVAT amount would be payable
to the employer.
9. The Appellant contended that it was entitled to avail CENVAT credit
amounting to INR 32,95,87,163/-, whereas the CENVAT credit actually
availed by the Appellant was INR 27,42,86,238/-. Thus, there was a shortfall
of INR 5,53,00,925/- towards MGCC, and the Appellant was entitled to
deduct this amount from the invoices raised by the Respondent.
10. Accordingly, on 09.03.2019, the Appellant issued a recovery advice
letter informing the Respondent that the said shortfall amount would be
recovered from Respondent’s current or upcoming bills. This letter was duly
served on the Respondent. However, no response was received from the
Respondent to the said communication dated 09.03.2019. Therefore, on
11.03.2019, the Appellant, after deducting the MGCC shortfall of INR
5,53,00,925/- from the total invoice value of Rs.8,02,27,262.51/-, released a
sum of INR 2,29,76,392.43/- to the Respondent.
Signature Not Verified
FAO(OS) (COMM) 141/2026 Page 3 of 26

Signed By:MAHIMA
SHARMA
Signing Date:01.10.2026
11:21

11. The Respondent disputed the legality of the said deduction of INR
5,53,00,925/-. It denied that the Appellant was entitled to make a deduction
from the invoice value for the aforesaid shortfall.
12. The dispute remained unresolved and, on 21.10.2021, the Respondent
invoked conciliation under the Standing Conference of Public Enterprises
(‘SCOPE’) Rules. Since the parties were unable to arrive at a settlement, the
Respondent terminated the conciliation proceedings on 14.01.2022 and
thereafter initiated arbitration before the International Chamber of Commerce
(‘ICC’).
13. The arbitration was referred to an Arbitral Tribunal comprising three
[3] members. The Respondent nominated Justice V.K. Jhanji as its arbitrator
and the Appellant nominated Dr. Subir Bikas Mitra. Since the arbitration
agreement did not provide for appointment of the presiding arbitrator, the ICC
Court appointed Justice Madan B. Lokur as the President of the Arbitral
Tribunal in terms of Article 13(3) of the ICC Rules.
14. Before the Arbitral Tribunal, the Appellant raised a preliminary
objection to the maintainability of the claims on the ground of limitation. It
2
was contended that, under Clause 12.1.6 of the GCC, the invoices were
payable within 45 days of their respective dates and that limitation had to be
reckoned from the dates on which the payments fell due.
The Appellant contended that the relevant invoices had become due
between 2017 and 2018, whereas arbitration commenced only in March 2022.
The Appellant further contended that negotiations or conciliation proceedings
could not extend the period of limitation.

2
Refer to paragraph 7 of this order
Signature Not Verified
FAO(OS) (COMM) 141/2026 Page 4 of 26

Signed By:MAHIMA
SHARMA
Signing Date:01.10.2026
11:21

15. The Arbitral Tribunal, however, rejected the objection and held that in
terms of Clause 12.1.6 read with 12.1.7, all payments were regarded as
3
advance payments until the date of final payment . It held that the cause of
action arose only on 09.03.2019, when the Appellant issued the letter to the
Respondent to recover the shortfall amount, and since the
Respondent/Claimant had invoked arbitration on 02.03.2022, the same was
within the period of three [3] years from the date of cause of action.
4
16. With respect to the substantive claim raised by Respondent related to
recovery of INR 5,53,00,925/-, being the amount deducted by the Appellant
towards the alleged shortfall in MGCC, the same was allowed by the Arbitral
Tribunal in favour of the Respondent.

17. The Appellant had opposed the said claim and contended that the
Respondent had expressly guaranteed a minimum amount of CENVAT credit
and that the failure to provide such credit entitled the Appellant to recover the
shortfall. It contended that the Appellant is entitled to exercise the ‘guarantee’
and seek recovery of the shortfall either from the Gross Contract Price or the
Net Contract Price.
18. The Arbitral Tribunal rejected the submissions of the Appellant. The
Arbitral Tribunal, on a reading of Clause 14.5.6 of the GCC, Note to
Appendix 1 annexed to the contract and the contractual pricing mechanism,
held that, if at all, any withholding, deduction or adjustment is to be made, it
could only be from the Gross Contract Price and not from the Net Contract
Price. The Arbitral Tribunal allowed the claim in favour of the Respondent. It
placed reliance upon an earlier judgment of a Single Judge of this Court in

3
Refer to paragraph 55 of the Arbitral award
Signature Not Verified
FAO(OS) (COMM) 141/2026 Page 5 of 26

Signed By:MAHIMA
SHARMA
Signing Date:01.10.2026
11:21

5
SAIL v. Primetals Technologies India Pvt. Ltd. dated 12.03.2020 as
upheld by the Division Bench of this Court in FAO (OS)(COMM) 125/2020
titled Steel Authority of India Limited (SAIL) v Primetals Technologies
6
India Pvt. Ltd. vide judgment dated 03.11.2020, which dealt with
substantially similar contractual provisions and held that deduction could
have only been made from the Gross Contract Price and not the Net Contract
Price.
19. The Appellant contended that the decision rendered by the learned
Single Judge in SAIL v. Primetals (March 2020) (supra) arose from a
different contract; and reliance placed by the Arbitral Tribunal on the
aforementioned judgment is misplaced and without any independent
application of mind.
7
20. Another claim raised by the Respondent before the Arbitral Tribunal
was related to reimbursement of Excise duty of INR 1,08,26,859.36/-. The
Respondent initially claimed a sum of Rs.1,30,18,825/- towards Excise duty
allegedly paid in respect of Indigenous Plant and Equipment, which was not
reimbursed by the Appellant.
21. The Respondent relied upon Article 2.1 of the contract and Clauses
11.2.1 and 14.1 and Appendix-1 of the GCC and contended that the Appellant
is liable to reimburse the Respondent for all the taxes, duties and levies as
contemplated in the contract, on the production of the documentary evidence.
22. The Appellant opposed the said claim, inter alia, on the ground that the
underlying invoices ranged from 28.11.2009 to 07.12.2016 and were therefore

4
Claim 1
5
2020:DHC:1666
6
2020:DHC:3137-DB
7
Claim 2
Signature Not Verified
FAO(OS) (COMM) 141/2026 Page 6 of 26

Signed By:MAHIMA
SHARMA
Signing Date:01.10.2026
11:21

barred by limitation. It further contended that certain Excise-duty vouchers
had not been enclosed with the invoices, some Excise-duty vouchers were
more than one [1] year old, and some goods were not CENVATABLE.
23. Since the claim involved approximately 1,100 invoices, the Arbitral
Tribunal relied upon an Excel statement (i.e. spreadsheet) jointly prepared by
8
the parties. The disputes were considered under four [4] broad categories
whereafter a sum of INR 1,16,71,410.32/- was claimed by the Respondent.
After deducting a sum of Rs.8,44,550.96/-, which the Arbitral Tribunal found
had already been paid in excess by the Appellant, the Arbitral Tribunal
awarded INR 1,08,26,859.36/- in favour of the Respondent towards
reimbursement of the Excise duty.

24. While dealing with the said claim, the Arbitral Tribunal held that upon
production of the necessary documentary proof of payment of duty, the
Respondent was entitled to reimbursement in terms of the contract and
concluded that the relevant supporting documents had been supplied by the
Respondent with the invoices and rejected the Appellant’s objection in that
regard.
25. The Respondent had also claimed interest at the rate of 12% per annum
on the amounts found payable. The Appellant opposed the said claim on the
ground that the principal substantive claims were barred by limitation and
were otherwise without merit; therefore, the Respondent is not entitled to
claim interest. The Arbitral Tribunal awarded interest at the rate of 10% per
annum relying of the judgment of SAIL v. Primetals (March 2020) (supra).

8
Namely, goods allegedly not CENVATable amounting to Rs.33,82,057.33/-, documents allegedly not
received with the invoices amounting to Rs.23,30,783.39/-, documents allegedly received after one [1] year
amounting to Rs.59,24,328.60/-, and invoices allegedly not indicating the tariff or chapter heading amounting
to Rs.34,241/-
Signature Not Verified
FAO(OS) (COMM) 141/2026 Page 7 of 26

Signed By:MAHIMA
SHARMA
Signing Date:01.10.2026
11:21

26. The Respondent further claimed litigation and arbitration costs to the
tune of Rs.1,56,28,140/-, which claim was also allowed by the Arbitral
Tribunal.
27. After conclusion of the arguments, the Arbitral Tribunal passed the
award dated 28.08.2024, subsequently modified under Section 33 of the Act
by order dated 22.11.2024 (addendum).
28. Aggrieved by the said arbitral award, as modified, the Appellant filed a
petition under Section 34 of the Act. The challenge was principally founded
on the plea that the substantive Claims 1 and 2 were barred by limitation; that
the Arbitral Tribunal had erroneously interpreted Clause 14.5.6 of the GCC
and the contractual Price schedule; that the guaranteed CENVAT credit
constituted an independent contractual commitment, and that the Arbitral
Tribunal had mechanically relied upon the earlier judgment of the Single
Judge in SAIL v. Primetals (March 2020) (supra) without independently
addressing Appellant’s submissions. Appellant also challenged the findings
on reimbursement of Excise duty, interest and costs.
29. By judgment dated 18.02.2026 passed in OMP (COMM.) 233/2025, the
learned Single Judge dismissed the Section 34 petition and declined to
interfere with the arbitral award.
30. Mr. Jayant Mehta, learned senior counsel appearing for the Appellant
has pressed arguments on the bar of limitation and interpretation of Clause
14.5.6 of the GCC to the extent it pertains to Claim 1. No arguments have
been advanced qua award of Claim 2 or the award of interest or the award of
costs.

30.1. He stated that the phrase ‘minimum’ and ‘guaranteed’ in Clause 14.5.6
of the GCC entitles the Appellant to receive the MGCC from the Respondent.
Signature Not Verified
FAO(OS) (COMM) 141/2026 Page 8 of 26

Signed By:MAHIMA
SHARMA
Signing Date:01.10.2026
11:21

30.2. He stated on instructions that there is no dispute with respect to the fact
that the reason for the Respondent’s inability to pass on the shortfall of
MGCC of INR 5,53,00,925/- to the Appellant was on account of lowering of
duty post award of contract, and not due to any default on the part of the
Respondent in providing their relevant documents for enabling the Appellant
to avail the credit.
30.3. He stated that the shortfall caused in the CENVAT credit passed on to
the Appellant has to be made good by the Respondent from the invoiced
amounts. He stated that the deduction of the shortfall can either be made from
the Net Contract Price or from the Gross Contract Price.
31. Per contra, learned counsel for the Respondent submitted that no
ground is made out for interference with the arbitral award passed by the
Arbitral Tribunal, which has been affirmed by the learned Single Judge vide
the impugned judgment, particularly since the view taken by the Arbitral
Tribunal on Clause 14.5.6 of the GCC is a plausible view and a permissible
view based on the material on record. It is, therefore, submitted that the
present appeal is devoid of merit and is liable to be dismissed.
31.1. It is also contended that objections to Claim 2 were not pressed by the
Appellant before the learned Single Judge.
CASE ANALYSIS
32. The Court has heard the learned counsel for the parties and has perused
the record.
I. Scope of Interference
33. The jurisdiction of this Court under Section 37 of the Act, to interfere
with an arbitral award is as limited as the scope of interference permissible
under Section 34 of the Act and cannot exceed beyond it. Thus, if an award is
Signature Not Verified
FAO(OS) (COMM) 141/2026 Page 9 of 26

Signed By:MAHIMA
SHARMA
Signing Date:01.10.2026
11:21

not liable to be disturbed under Section 34 of the Act, the same cannot be
interfered with in exercise of powers under Section 37 of the Act. The Court
hearing an appeal under Section 37 of the Act cannot undertake an
independent assessment of the merits of the award and is only required to
ascertain that the Court under Section 34 of the Act has acted within its limit
as prescribed under the Act. The scope of jurisdiction under Section 37 of the
Act is not akin to normal appellate jurisdiction.
34. The limited scope of interference by the Court in Section 37 of the Act
has been recently reiterated by the Supreme Court in its recent judgment Jan
9
De Nul Dredging India Pvt Ltd. v. Tuticorin Port Trust . In this judgment
the Supreme Court has taken note of its earlier decisions in MMTC Limited
10
v. Vedanta Limited , Konkan Railway Corporation Ltd. v. Chenab
11
Bridge Project Undertaking , and UHL Power Company Ltd. v. State of
12
Himachal Pradesh . The relevant paragraphs read as under: -
29. That being the position, the award of the Arbitral Tribunal was not
liable to be disturbed under Section 34 of the Act and was rightly not
disturbed. It is settled in law that the appellate powers under Section 37
are limited to the scope of Section 34 and cannot exceed beyond it.
Certainly, therefore, if an award is not liable to be disturbed under
Section 34 of the Act, the same could not have been interfered with in
exercise of powers under Section 37 of the Act.
………..
35. The gist of the aforesaid decisions is that the jurisdiction of the
court under Section 37 of the Act is akin to the jurisdiction of the court
under Section 34 of the Act, and, therefore, the scope of interference by
the court in appeal under Section 37 cannot go beyond the grounds on
which challenge can be made to the award under Section 34 of the Act.
Moreover, the courts exercising powers under Sections 34 and 37, do

9
(2026) 3 SCC 186
10
(2019) 4 SCC 163
11
(2023) 10 SCC 228
12
(2022) 4 SCC 116
Signature Not Verified
FAO(OS) (COMM) 141/2026 Page 10 of 26

Signed By:MAHIMA
SHARMA
Signing Date:01.10.2026
11:21

not act as a normal court, and therefore, ought not to interfere with the
arbitral award on a mere possibility of an alternative view.
36. In other words, the scope of interference of the court with the
arbitral matters is virtually prohibited, if not absolutely barred. The
powers of the Appellate Court are even more restricted than the powers
conferred by Section 34 of the Act. The appellate power under
Section 37 of the Act is exercisable only to find out if the court
exercising power under Section 34 of the Act, has acted within its
limits as prescribed thereunder or has exceeded or failed to
exercise the power so conferred. The Appellate Court exercising
powers under Section 37 of the Act has no authority of law to consider
the matter in dispute before the Arbitral Tribunal on merits so as to
hold as to whether the award of the Arbitral Tribunal is right or wrong.
The Appellate Court in exercise of such power cannot sit as an ordinary
court of appeal and reappraise the evidence to record a contrary finding.
The award of the Arbitral Tribunal cannot be touched by the court
unless it is contrary to the substantive provision of law or any provision
of the Act or the terms of the agreement.
(Emphasis Supplied)
35. Thus, while examining the order passed by the Court under Section 34
of the Act, this Court while exercising jurisdiction under Section 37 of the Act
cannot interfere in the arbitral award on the mere possibility of an alternative
view on facts or interpretation of the contract to reverse the findings of the
arbitral tribunal. Where the view adopted by the arbitral tribunal is a possible
and plausible view of the contractual provisions and the learned Single Judge
has found no ground under Section 34 of the Act warranting interference, the
Appellate Court cannot substitute its own view for the view of the arbitral
tribunal, merely because a different interpretation may also be possible.
36. It is in the backdrop of the aforesaid limited scope of judicial
interference under Section 37 of the Act, the challenges raised by the
Appellant to the impugned judgment and impugned arbitral award have to be
examined in this judgment.
Signature Not Verified
FAO(OS) (COMM) 141/2026 Page 11 of 26

Signed By:MAHIMA
SHARMA
Signing Date:01.10.2026
11:21


II. Impugned Judgment
37. The learned Single Judge has dismissed the Appellant’s petition under
Section 34 of the Act and has upheld the arbitral award dated 28.08.2024, as
modified on 22.11.2024. The learned Single Judge has, inter alia, held that the
Respondent’s claim was within limitation, as the cause of action for Claim 1
arose only on 09.03.2019, when the Appellant deducted the shortfall amount
of INR 5,53,00,925/- from the Net Contract Price; and that Clause 14.5.6 of
the GCC read with the Note to Appendix-1 of the GCC provides that if at all,
any withholding, deduction or adjustment is to be made, it could only be from
the contract price mentioned at Serial no. 12 of the Summary Price
13
Schedule , i.e., the Gross Contact Price including the CENVAT credit and
not from the Net Contract Price as per the Note to the Appendix 1 of the
GCC.
38. The learned Single Judge has further held that, despite the shortfall in
MGCC passed on by the Appellant to the Respondent, the Net Contract Price
received by the Respondent remained unchanged, since the Appellant itself
retained the amount corresponding to the CENVAT shortfall by not
reimbursing it to the Respondent. Relying upon the principle that
interpretation of contractual terms falls primarily within the domain of the
Arbitral Tribunal, the learned Single Judge held that the interpretation
adopted by the Arbitral Tribunal was a plausible one and was not perverse,
patently illegal or contrary to the public policy of India.
39. The relevant Clause 12 of the GCC dealing with Terms of Payment and
Clause 14.5.6 of the GCC dealing with the Taxes and Duties, as well as the

13
At printed page 164 of the present appeal
Signature Not Verified
FAO(OS) (COMM) 141/2026 Page 12 of 26

Signed By:MAHIMA
SHARMA
Signing Date:01.10.2026
11:21

Note in the Appendix 1, relied upon by the Appellant in support of its
contentions, is set out hereunder:
“12. Terms of Payment
12.1.6. The Employer shall release the payment to the Contractor
within 45 days from the date of receipt of the complete and correct
invoices and relevant documents.
12.1.7. All interim/ progress payments shall be regarded as payment is
by way of advance against the final payment only and not as payment
for work completed and shall not preclude
defective/imperfect/incomplete facilities to be removed. It will not be
considered as an admission by the Employer of the due performance of
the contract, or any part thereof by the Contractor nor shall it preclude,
determine or affect in any way the powers of the Employer under these
conditions or in any way vary or affect the contract.
14. Taxes & Duties
14.5.6. Contractors to indicate Minimum Guaranteed CENVAT
Credit that can be availed by the Employer against materials supplies
for subject work. In case of any shortfall in CENVAT Credit from that
Guaranteed by the Contractor the shortfall shall be deducted by the
Employer from the Contractor. In case of excess of CENVAT, 50% of
the excess CENVAT amount will be paid
SUM OF SUMMARY PRICE SCHEDULES (for HDGL+ ECL)
…………
Note: All the necessary documents for availing the CENVAT credit
shall be furnished, else balance shortfall shall be deducted from the
contract price item serial no.12 above .”
(Emphasis supplied)
III. Plea of Limitation
40. The Arbitral Tribunal, on reading Clause 12.1.6 of the GCC in
conjunction with Clause 12.1.7 of the GCC, held that the crucial date for
reckoning the limitation is the date when final payment is made (or refused)
Signature Not Verified
FAO(OS) (COMM) 141/2026 Page 13 of 26

Signed By:MAHIMA
SHARMA
Signing Date:01.10.2026
11:21

to the contractor (i.e. the claimant). The Arbitral Tribunal held that this is the
date when the employer determines whether the claim of the contractor is
justified or not. The Arbitral Tribunal concluded that since the Appellant had
conveyed its decision to deduct the amount of INR 5,53,00,925/- on
09.03.2019 by issuing a recovery advice, the limitation period of three [3]
years commenced from the said date. The Arbitral Tribunal held that since the
Respondent took appropriate remedial steps within three [3] years, the said
Claim 1 was within limitation period. The relevant paragraphs of the arbitral
award read as under:
“ Conclusion
74. The conclusion of the Tribunal in respect of the objection of
limitation is that Clause 12.1.6 of the GCC must be read in conjunction
with clause 12.1.7 of the GCC. If both the clauses are read conjointly, it
is clear that the crucial date is the date when final payment is made (or
refused) to a contractor, such as the Claimant. On that date, it is finally
determined by the Employer such as the Respondent, whether a claim is
justified or not.
75. Even if clause 12.1.6 of the GCC is read as a stand-alone provision,
it is not possible to accept the ‘deemed rejection’ view canvassed by
learned counsel for the Respondent, namely, a ‘deemed rejection’ at the
end of 45 days after the invoices are submitted by the contractor/
Claimant. The language of clause 12.1.6 of the GCC does not warrant
such a reading —it only obliges the Respondent to release the payment
within 45 days and cannot be understood to mean that if the amount is
not so released by the Respondent, then the claim is deemed rejected.
This would be adding words to the Contract and even doing violence to
its terms.
76. The submission of learned counsel gives no importance to the
provision in the Contract and the GCC regarding negotiation and
conciliation proceedings. The submission ignores the terms of the
Contract which is not permissible as far as this Tribunal is concerned. If
the view canvassed by learned counsel for the Respondent is accepted,
it will place a contractor/ Claimant in a Catch-22 situation. In a given
case, the negotiations may be protracted and fail only after the
limitation period expires. On the other hand, if the contractor/ Claimant
Signature Not Verified
FAO(OS) (COMM) 141/2026 Page 14 of 26

Signed By:MAHIMA
SHARMA
Signing Date:01.10.2026
11:21

bypasses the negotiation process or invokes arbitration during the
prolonged negotiation process, it may be denied relief for not adhering
to the terms of the Contract. In the present arbitration, neither situation
arises, fortunately for the Claimant, but could arise in a given case. The
interpretation given by the Hon’ble Supreme Court to the expression
“cause of action” and a continuing cause of action, discussed above, is
therefore apposite and binds the parties and the Tribunal
77. The Tribunal finds no merit in the submissions of learned counsel
for the Respondent in denying the claim of the Claimant on the issue of
limitation.
78. Considering the sequence of events and the bundle of facts
mentioned above, it certainly cannot be said that the claim was made by
the Claimant beyond the period of three years of the cause of action that
th
occurred at the earliest on 9 March, 2019 or beyond the time limit
prescribed under the Limitation Act, 1963.”

41. Similarly, while adjudicating the objection of limitation qua Claim 2,
the Arbitral Tribunal held that on a perusal of the emails dated 02.11.2021
and 14.02.2022 it was evident that the Respondent’s claim for reimbursement
of Excise duty was alive and under active consideration by the Appellant, and
the claim was rejected only on 14.02.2022, and thus the right to sue accrued
to the Respondent on 14.02.2022. The Arbitral Tribunal concluded that since
the claim was filed immediately thereafter, the said Claim 2 was also within
the limitation period. The relevant paragraphs read as under:
“79. The objection of limitation with regard to this claim is stated by
the Respondent in the SOD in the following words:
That the Respondent states that Claim No. 1, as pleaded in the
SOC, is barred by limitation, stands extinguished accordingly,
and is therefore not admissible for adjudication thereon.
That the bar of limitation applies to Claim No. 2 in like manner
as aforesaid. The Invoices relevant to Claim No. 2, pertaining to
reimbursement sought in respect of Excise Duty amounting to
Rs. 1,30,18,825/- range from 28.11.2009 to 7.12.2016 in terms
of their date and are therefore barred by limitation in view of
Signature Not Verified
FAO(OS) (COMM) 141/2026 Page 15 of 26

Signed By:MAHIMA
SHARMA
Signing Date:01.10.2026
11:21

Clause 12.1.6 of the GCC when viewed in conjunction with the
applicable provisions of the Limitation Act, 1963.
80. … ….
Consequently, it is necessary, for the purposes of the preliminary
objection to refer to two communications sent by the Respondent to the
Claimant which make the cause of action a continuing cause of action
as far as the law is concerned. These two communications are an email
nd th
dated 2 November, 2021 and an email dated 14 February, 2022.
nd
81. The email dated 2 November, 2021 reads as follows:
Your notice [Conciliation Notice under Article 10 of the
Contract] was referred to our Project-finance. They are
reviewing the calculations and are in touch with your local
representative at Bokaro.
It is being expected that the matter will be resolved mutually
without intervention of 3rd agency. Conciliation process may be
initiated, if this effort for arriving at mutual agreement within a
reasonable time is failed
th
82. The email dated 14 February, 2022 reads as follows:
This is with reference to the meeting held on 08.02.2022
between Project Finance and representative of M/PFA the details
of Service tax and Excise duty.
After Reconciliation, the total amount Payable against Service
tax is Rs.11,88,937/-. (Details attached). Also, for Excise duty
details of Invoices which are not paid alongwith the reasons are
attached.
83. It is quite obvious from a plain reading of the aforesaid two emails
that the claim made by the Claimant was kept alive by the Respondent
and the right to sue accrued to the Claimant (as discussed above with
th
reference to Claim No. 1) only on 14 February, 2022. The arbitration
proceedings commenced well within three years thereafter.
84. There is no substance in the preliminary objection taken by the
Respondent with regard to Claim No. 2 and it is accordingly rejected.”
42. Learned Single Judge has upheld the findings of the Arbitral Tribunal
on the issue of limitation.
Signature Not Verified
FAO(OS) (COMM) 141/2026 Page 16 of 26

Signed By:MAHIMA
SHARMA
Signing Date:01.10.2026
11:21

43. The Appellant has contended that the cause of action for filing Claim 1
arose on expiry of 45 days after the invoices were raised by the Respondent
and the same remained unpaid. As per the Appellant, the limitation had
expired in October 2021, and since the Respondent failed to take steps for
referring the disputes to arbitration within the said period, the invocation of
arbitration on 02.03.2022 was barred by limitation.
44. We find no merit in the submission of the Appellant. The Arbitral
Tribunal has given detailed findings on the issue of limitation. The findings
on limitation returned by the Arbitral Tribunal qua Claim 1 on the basis of
recovery advise dated 09.03.2019 issued by the Appellant and qua Claim 2 on
the basis of Appellant’s emails dated 02.11.2021 and 14.02.2022 is correct
and merits no interference.
IV. Merits of Claim 1
45. The Arbitral Tribunal has allowed Claim 1 for sum of INR
5,53,00,925/- in favour of the Respondent.
46. The Appellant contended that the amount of INR 5,53,00,925/- was
guaranteed by the Respondent. It was an independent ‘item’ in the Summary
14
Price Schedule . It contended that since the Appellant received partial
amount and there was a shortfall of INR 5,53,00,925/- the Appellant was
entitled to recover the said shortfall from the Respondent, whether from the
Gross Contract Price or the Net Contract Price. It contended that the Arbitral
Tribunal ought to have adjudicated on these contentions but instead the
Tribunal merely applied the judgment of the Single Judge of this Court in
SAIL v. Primetals (March 2020) (supra), and there was no independent
application in mind.
Signature Not Verified
FAO(OS) (COMM) 141/2026 Page 17 of 26

Signed By:MAHIMA
SHARMA
Signing Date:01.10.2026
11:21

47. The Arbitral Tribunal noted that the Clause 14.5.6 of the GCC relied
upon by the Appellant for justifying the recovery of INR 5,53,00,925/- under
Claim 1 was para materia to the contractual clause, which was under
consideration in SAIL v. Primetals (March 2020) (supra). It also noted that
parties before the Arbitral Tribunal and before the High Court in SAIL v.
Primetals (March 2020) (supra) are same. The Arbitral Tribunal noted that
in the said judgment, the High Court had upheld the interpretation of Clause
14.5.6 of the GCC to mean that the deduction on account of shortfall viz the
guaranteed CENVAT credit has to be made from the Gross Contract Price and
not from the Net Contract Price. It noted that the High Court had specifically
rejected the contention of the Appellant herein that the shortfall can be
deducted from the Net Contract Price and opined that such of submission of
the Appellant is contrary to the plain language of the contractual clause. The
Arbitral Tribunal noted that the aforesaid judgment of the Single Judge was
challenged in appeal under Section 37 of the Act and was dismissed by the
Division Bench vide judgment dated 03.11.2020 reported in SAIL v.
Primetals (November 2020) (supra). The Arbitral Tribunal also noted that
15
the SLP filed by the Appellant against the judgment of the Division Bench
was also dismissed on 03.02.2021. It also referred to another judgment of the
Single Judge in Steel Authority of India Ltd. v, Larsen & Toubro
16
Limited (2021), which was also upheld by the Division Bench.
47.1. The Arbitral Tribunal held that in view of the judgments passed by the
High Court on this precise issue against the Appellant, there was no
justification for the Appellant to withhold or deduct or adjust any amount
from the dues of the Respondent. It held that deduction could have been made

14
At printed page 164 of the appeal
15
SLP No. 1567/2021
Signature Not Verified
FAO(OS) (COMM) 141/2026 Page 18 of 26

Signed By:MAHIMA
SHARMA
Signing Date:01.10.2026
11:21

only from the Gross Contract Price and not from the Net Contract Price.
Accordingly, the Arbitral Tribunal allowed Claim 1 in favour of the
Respondent.
48. The learned Single Judge after considering the submissions of the
Appellant, found no merit in the same and recorded following reasons for
upholding the award. The relevant paragraphs of the impugned judgment read
as under: -
“10. The contention that in case of a shortfall in MGCC the petitioner
was entitled to make a deduction from either the gross or the net
contract value is noted to be rejected. The language of the note in
Appendix-I clearly stipulates that deduction is to be made from the
gross contract value. The gross contract price pertains to the work
done and is inclusive of taxes and duties. The net contract price is
arrived at after deducting MGCC and remains unaffected in spite of
shortfall in MGCC. The non-reimbursed shortfall in MGCC remains
with the petitioner. If deduction were to be made from the net contract
value, the effect would be that on the one hand the shortfall in MGCC
would not be reimbursed and on the other hand the net contact value
would be reduced by deducting shortfall in MGCC which would not
be permissible in the absence of specific conditions in the contract.

10.1 The position can be demonstrated by way of an example. The
gross contract value inclusive of taxes and duties (as on the base date)
was Rs.1,50,000/-. The MGCC component was Rs.35,000/-. The net
contract value was Rs.1,15,000/-. In the event of a shortfall of
Rs.5,000/- in MGCC, the respondent will reimburse Rs.30,000/-
instead of Rs.35,000/-. The net contract value remains Rs.1,15,000/-
and the non-reimbursed amount of Rs.5,000/- will remain with the
petitioner.”

49. Mr. Jayant Mehta, learned Senior Counsel contended that the
interpretation of Clause 14.5.6 of the GCC as given by the Arbitral Tribunal
and accepted by learned Single Judge fails to give any meaning to the words
‘minimum guaranteed’ in the said clause. He stated that the action of the

16
2021 SCC OnLine Del 4065
Signature Not Verified
FAO(OS) (COMM) 141/2026 Page 19 of 26

Signed By:MAHIMA
SHARMA
Signing Date:01.10.2026
11:21

Appellant in recovering the shortfall of INR 5,53,00,925/- is justified as this
was part of the ‘minimum guaranteed’ amount assured by the Respondent. In
response to our query, he submitted that it is irrelevant that the duties actually
paid under the contract had reduced due to lowering of rate of duty, leading to
less CENVAT credit becoming available to the Respondent and not due to
any default of the Respondent.
49.1. He submitted that there was no allegation that Respondent had failed to
provide the requisite documents to the Appellant for availing the CENVAT
credit for the duty actually deposited or for any other default vis-à-vis
obligation of taxes.
49.2. He submitted that there is no dispute that the clause, which was the
subject matter in interpretation in SAIL v. Primetals (March 2020) (supra)
was identical. He however reiterates that the Arbitral Tribunal ought to have
independently adjudicated the claim and not merely followed the judgment of
the High Court.
50. In our considered opinion, the submission of the Appellant that the
Arbitral Tribunal erred in following the judgment of the Single Judge in SAIL
v. Primetals (March 2020) (supra) for adopting the interpretation of Clause
14.5.6 of the GCC is without any merits. The Appellate Tribunal was bound
by the said judgment of the High Court and more so, since it had been further
upheld in appeal.
51. In this regard, it would be relevant to refer to the judgment of Supreme
Court in OPG Power Generation (P) Ltd. v. Enexio Power Cooling
17
Solutions (India) (P) Ltd. holding that, after the 2015 amendments to the

17
(2025) 2 SCC 417
Signature Not Verified
FAO(OS) (COMM) 141/2026 Page 20 of 26

Signed By:MAHIMA
SHARMA
Signing Date:01.10.2026
11:21

Act, under Section 34(2)(b)(ii) of the Act, an arbitral award would be contrary
to the fundamental policy of Indian law where, inter alia, it disregards the
orders of superior courts in India or the binding effect of a judgment of a
superior court. The Supreme Court has explained that such disregard
constitutes a contravention of the fundamental principles which form the basis
for administration of justice and enforcement of law in the country. The
relevant paragraphs of the judgment read as under: -
“55. The legal position which emerges from the aforesaid discussion
is that after “the 2015 Amendments” in Section 34 (2)(b)(ii) and
Section 48(2)(b) of the 1996 Act, the phrase “in conflict with the
public policy of India” must be accorded a restricted meaning in terms
of Explanation 1. The expression in “contravention with the
fundamental policy of Indian law" bv use of the word “fundamental”
before the phrase “policy of Indian law” makes the expression
narrower in its application than the phrase “in contravention with the
policy of Indian law”, which means mere contravention of law is not
enough to make an award vulnerable. To bring the contravention
within the fold of fundamental policy of Indian law, the award must
contravene all or any of such fundamental principles that provide a
basis for administration of justice and enforcement of law in this
country.
56. Without intending to exhaustively enumerate instances of such
contravention, by way of illustration. it could be said that:
(a) violation of the principles of natural justice;
(b) disregarding orders of superior courts in India or the binding
effect of the judgment of a superior court ; and
(c) violating law of India linked to public good or public interest, are
considered contravention of the fundamental policy of Indian law.
However. while assessing whether there has been a contravention of
the fundamenta1 policy of Indian law, the extent of judicial scrutiny
must not exceed the limit as set out in Explanation 2 to Section
34(2)(b)(ii).”
(Emphasis supplied)
52. Accordingly, in view of the principle enunciated by the Supreme Court
in OPG Power (supra), disregarding the binding effect of a judgment of a
superior court falls within the illustrative instances of contravention of the
Signature Not Verified
FAO(OS) (COMM) 141/2026 Page 21 of 26

Signed By:MAHIMA
SHARMA
Signing Date:01.10.2026
11:21

fundamental policy of Indian law under Section 34(2)(b)(ii) of the Act
making the award vulnerable to interference. The law settled by Supreme
18
Court in National Highway Authority of India v Progressive- MVR (JV)
with respect to the duty of the Courts hearing Section 34 petition in
maintaining consistency of interpretation of identical contracts, more so,
where one of the parties is common would also be applicable and legally
justifies the decision of the Arbitral Tribunal to follow the interpretation of
Clause 14.5.6 of the GCC given by the Single Judge in SAIL v. Primetals
(March, 2020) (supra).
53. In the present case, the Arbitral Tribunal’s discretion to interpret Clause
14.5.6 of the GCC was circumscribed by the existence of judicial precedents
governing the same clause between same parties. The interpretation of the
said contractual provision had already fallen for consideration between the
same parties in SAIL v. Primetals (March 2020) (supra), which was
thereafter affirmed by the Division Bench of this Court in SAIL v. Primetals
(November 2020) (supra), and the SLP preferred was dismissed on
03.02.2021. The contractual provision considered in the aforesaid judgments
was pari materia with Clause 14.5.6 of the GCC which fell for consideration
in the present case before the Arbitral Tribunal. Since, the interpretation of the
contractual provision had already been authoritatively settled by this Court in
respect of the very same contractual stipulation, the Arbitral Tribunal was,
therefore, not at liberty to disregard the binding interpretation rendered by this
Court in proceedings arising from SAIL v. Primetals (March 2020) (supra)
and adopt an interpretation contrary thereto. Once this Court had interpreted
Clause 14.5.6 of the GCC, the Arbitral Tribunal was bound to give effect to
the said interpretation.

18
(2018) 14 SCC 688 at paragraph 40
Signed By:MAHIMA
SHARMA
Signing Date:01.10.2026
11:21
Signature Not Verified
FAO(OS) (COMM) 141/2026 Page 22 of 26

54. The Appellant has not been able to show any distinguishing fact which
would enable the Arbitral Tribunal to take a view different from the Court in
the cited precedents.
55. The Single Judge in SAIL v. Primetals (March 2020) (supra) had
independently interpreted the said Clause, considered the submissions of the
Appellant and had rejected the interpretation of the Appellant by observing
that the understanding of the Appellant was contrary to the plain language of
the Clause. There was therefore an affirmative determination by the Single
Judge in SAIL v. Primetals (March 2020) (supra) with respect to the nature
and scope of Clause 14.5.6 of the GCC and therefore the Arbitral Tribunal
rightly observed that the legal issue arising for determination under Claim 1 is
no longer res integra. In the said judgment it was not a case where the Single
Judge had upheld the award merely as a plausible view instead the award was
upheld on the finding that it was the correct interpretation of the Clause 14.5.6
of the GCC read with the Note to Appendix-1.
56. In these circumstances, the contention of the Appellant that the Arbitral
Tribunal ought to have independently interpreted Clause 14.5.6 of the GCC
cannot be accepted to the extent it suggests that the Arbitral Tribunal was free
to arrive at a conclusion contrary to the interpretation already rendered by this
Court. The Arbitral Tribunal could not, in the guise of independently
interpreting the contractual provision, disregard the binding effect of the
judgment of this Court between the same parties on the same contractual
clause. Therefore, the Arbitral Tribunal could not adopt any different
interpretation of the contractual stipulation which is no longer res integra.

57. The learned Single Judge has therefore rightly opined that the award in
regard to Claim 1 requires no interference.
Signature Not Verified
FAO(OS) (COMM) 141/2026 Page 23 of 26

Signed By:MAHIMA
SHARMA
Signing Date:01.10.2026
11:21

58. We find no merit in the interpretation contended by the Appellant as
the said submission ignores the words CENVAT credit in the clause. The
Appellant is selectively reading the word ‘minimum guaranteed’ where as the
relevant words are ‘minimum guaranteed CENVAT credit’. In the contract,
the parties had settled the Gross Contract Price for the Indian portion as INR
2,915,587,163/-, wherein the guaranteed amount of CENVAT credit was
estimated as INR 32,95,87,163/-. and the Net Contract Price for the Indian
portion, was therefore INR 2,586,000,000/-.
59. The parties had, at the time of the formation of the contract, expected
that during the course of the execution the amount of Excise duty and Counter
Veiling duty [‘duty’] payable to the Government would be INR
32,95,87,163/-. The Respondent agreed to pay the said estimated duty to the
Government and seek its reimbursement from the Appellant. Further
Respondent agreed to pass on the CENVAT credit equal to the said INR
32,95,87,163/- to the Appellant. This was the basis of the obligation of the
Respondent to pass on the minimum guaranteed CENVAT credit of INR
32,95,87,163/- to the Appellant.
60. However, during the course of the execution of the contract the rate of
duty was reduced by the Government and therefore the actual duty paid by the
Respondent and reimbursed by the Appellant was INR 27,42,86,238/-. There
is no dispute that the Respondent duly passed on the CENVAT credit equal to
INR 27,42,86,238/- to the Appellant.
61. Since, the duty reimbursed by the Appellant was only INR
27,42,86,238/-, Appellant saved INR 5,53,00,925/- and was never out of
pocket of the said amount, in the first place. The contention of shortfall in
receipt of CENVAT credit is therefore misconceived. The Appellant could
Signature Not Verified
FAO(OS) (COMM) 141/2026 Page 24 of 26

Signed By:MAHIMA
SHARMA
Signing Date:01.10.2026
11:21

have alleged that it suffered a shortfall if it had paid duty equal to the original
estimated INR 32,95,87,163/- and not received CENVAT credit equal to the
said amount. However, this is not the case, as Appellant only had to pay INR
27,42,86,238/- towards duty reimbursement to the Respondent and it has
received CENVAT credit equal to the said amount.
62. The emphasis of the Appellant on the words ‘minimum guaranteed’ by
ignoring the following words ‘CENVAT credit’ in the clause seeks to
consider the amount of INR 32,95,87,163/- as an assured sum or a cash
discount, which is not the intent of the contract. Infact, indeed if the Appellant
is permitted to deduct INR 5,53,00,925/- it would lead to unjust enrichment.
63. We therefore find no merit in the submissions of the Appellant vis-à-vis
of Clause 14.5.6 of the GCC.
V. Merits of Claim 2
64. The Appellant has not addressed any submissions on the merits of its
challenge to Claim 2. This claim pertains to reimbursement of Excise Duty of
INR 1,08,26,859.36/- in its written submissions, the Appellant contended that
since it could not avail CENVAT credit in respect of several invoices as the
goods supplied precluded Appellant from claiming CENVAT credit, therefore
the said amount has been rightly withheld by the Appellant. It is alleged that
the Arbitral Tribunal misinterpreted the terms of the contract while allowing
the said claim and rendered a view which was not plausible.
65. The relevant paras of the arbitral award which pertains to the aforesaid
submission of the Appellant is at paragraph nos. 107 to 113. The Arbitral
Tribunal has after considering Clause 11.2.1 and Clause 14.1 of the GCC
opined that when the Respondent or its sub-contractor produced documentary
Signature Not Verified
FAO(OS) (COMM) 141/2026 Page 25 of 26

Signed By:MAHIMA
SHARMA
Signing Date:01.10.2026
11:21

evidence to payments of duties such as Excise Duties, the Respondent or its
sub-contractor will be entitled to payment of the duty paid. The Arbitral
Tribunal held that there was no dispute that the Excise Duty was duly paid by
the Respondent or the sub-contractor and the relevant documents were
produced before the Appellant proving the payment, while seeking
reimbursement. The plea of deficiency of documents proving payment of
Excise Duty was expressly rejected. The Appellate Tribunal held that the
objection of the Appellant that it shall not make payment of the Excise Duty
on the plea that the said duty is non-CENVATable has no basis in the
contractual provisions agreed between the parties.
66. The Appellant has been unable to point out any error in the aforesaid
observations of the Arbitral Tribunal in its written submissions or in the
Ground (h) in the appeal. Challenge to the award of Claim 2 on merits also
appears to not have been pressed before the learned Single Judge. It appears
Claim 2 was challenged only on the ground of limitation.
67. Be that as it may, having perused the award of the Arbitral Tribunal, we
find no error in the said award requiring interference by this Court. The
interpretation of Clause 11.2.1 and 14.1 of GCC by the Arbitral Tribunal is
correct and does not merit any interference.
68. For aforesaid reasons, we find no merit in the present appeal, and is,
therefore, dismissed.
MANMEET PRITAM SINGH ARORA, J.


C.HARI SHANKAR, J.
SEPTEMBER 14, 2026/ dsn/AM/AJ