* IN THE HIGH COURT OF DELHI AT NEW DELHI
% Date of Decision : 25.02.2026
+ W.P.(C) 2567/2026 & CM APPL. 12481/2026
SHIVA BUILDTECH PRIVATE LIMITED .....Petitioner
Through: Mr. Ramesh Kumar, Mr. Ashutosh
Prakash, Advs.
versus
NATIONAL HIGHWAYS AND INFRASTRUCTURE
DEVELOPMENT CORPORATION LTD. .....Respondent
Through: Mr. Deepak Thukral, Adv.
CORAM:
HON'BLE MR. JUSTICE V. KAMESWAR RAO
HON'BLE MS. JUSTICE MANMEET PRITAM SINGH ARORA
V. KAMESWAR RAO, J. (ORAL)
1. This petition has been filed seeking the following prayers: -
“(a) To issue a writ of mandamus or any other appropriate
writ, order or direction, to quash and set aside the Impugned
decision dated 17.02.2026 as illegal, arbitrary, unreasonable,
unfair, unconscionable, as also against the principles of fair-
play, equity and natural justice”
2. The challenge in this writ petition is primarily to a communication
dated 17.02.2026 of the respondent, whereby they have declared the
petitioner’s bid for work of NH-301 Kargil-Zanskar Road from Design km
6.000 to km 30.040 of 24.040 km length in the Union Territory of Ladakh
Signature Not Verified
W.P.(C) 2567/2026 Page 1 of 4
Signed By:MAHIMA
SHARMA
Signing Date:02.03.2026
16:34

on Engineering, Procurement & Construction [‘EPC’] mode, including the
additional perfection works for widening and upgradation of 2 lanes with
paved shoulder of Balance work of NH 301 Kargil-Zanskar Road from
Design km 30.040 to km 57.000 of 29.960 km length in the Union Territory
of Ladakh on EPC mode, as non responsive.
3. It is a conceded position that the petitioner and one M/s Haidary
Construction Pvt. Ltd., formed a joint venture, which was awarded the work
by the respondent vide letter of acceptance dated 31.03.2021.
4. The said work has resulted in a dispute inter se parties, which is
pending adjudication before the learned Arbitrator appointed by this Court.
5. As the contract has been terminated, it is for that balance work that
fresh tenders were invited by the Respondent vide NIT issued on
20.08.2025.
6. The case of the petitioner is that the respondent has issued
termination-cum-debarment order on 12.06.2025. It is also the considered
position that this debarment has been stayed by this Court vide order dated
04.10.2025.
7. The subject matter of this petition is primarily the rejection of the bid
of the petitioner by the respondent as being non-responsive.
8. The submission of Mr. Ramesh Kumar, learned counsel for the
petitioner, is that the respondents have now spelt out the reason that the bid
is non-responsive. In any case, the submission is that the respondent has
through portal sought information from the petitioner, on the information not
disclosed on the termination-cum-debarment order.
9. He submits that the information as sought by the respondent, has been
given vide letter dated 06.01.2026.
Signature Not Verified
W.P.(C) 2567/2026 Page 2 of 4
Signed By:MAHIMA
SHARMA
Signing Date:02.03.2026
16:34

10. He submits that even after giving such information, the impugned
communication dated 17.02.2026 has been passed, which, according to him,
is clearly illegal.
11. He states that the consequence of the same is that the financial bid
submitted by the petitioner is not being considered/opened.
12. On the other hand, learned counsel for the respondent submits that
even if the debarment order had been stayed by this Court, the petitioner was
required to disclose the same in his bid. Since the petitioner did not mention
the said fact in the bid the information was sought, and based on the reply
received, the impugned communication was issued, treating the bid as non-
responsive. It is thus contended that there is no illegality in that regard.
13. We have heard the submissions of learned counsel for the parties.
Though the petitioner has not referred to the fact that the debarment order
has been stayed, surely, the effect of the stay of the debarment order is that
prima facie the said order is not in existence against the petitioner herein.
14. The respondent herein having called for the information and the
petitioner having given the information to the respondent, prima facie, we
are of the view that the respondent could not have made the bid non-
responsive.
15. In these circumstances, and also the counsel for the respondent
intends to file a reply, we grant one week time to the counsel for the
respondent to file a reply to the petition.
16. As during the course of the hearing, we have been informed that the
financial bids are to be opened today, we grant liberty to the respondent to
open the financial bids, but shall not take further action thereon, till the next
date of hearing.
Signature Not Verified
W.P.(C) 2567/2026 Page 3 of 4
Signed By:MAHIMA
SHARMA
Signing Date:02.03.2026
16:34

17. Two days are granted to the petitioner to file the rejoinder thereafter.
18. List the petition on 09.03.2026.
V. KAMESWAR RAO, J
MANMEET PRITAM SINGH ARORA, J
FEBRUARY 25, 2026/ mt