Ministry Of Health & Family Welfare vs Nagarjuna Construction Ltd.
- Court
- Delhi High Court
- Case type
- Original Misc Petition Commercial
- Decided on
- 09-04-2026
<div> <br /> $~J <br /> * <b>IN THE HIGH COURT OF DELHI AT NEW DELHI </b><br /> <i>Judgment reserved on: 16.12.2025 </i><br /> <i>Judgment pronounced on: 09.04.2026 </i><br /> <b>+ O.M.P. (COMM) 337/2017 </b><br /> MINISTRY OF HEALTH & FAMILY WELFARE <br /> ...Petitioner <br /> <br /> Through: Ms. Pratima N Lakra(CGSC), <br /> Ms. Kanchan Shakya, Mr. Shailendra <br /> kumar Mishra, Mr. Chanakya Kene, <br /> Ms. Mansi, Advs. <br /> <br /> versus <br /> NAGARJUNA CONSTRUCTION LTD. ...Respondent <br /> <br /> Through: Dr. Amit George, Ms. <br /> Rupam Jha, Mr. Adhishwar Suri, Ms. <br /> Ibansara Syiemlieh, Mr. Dushyant <br /> Kishan Kaul, Mr. Vaibhav Gandhi, <br /> Ms. Medhavi Bhatia, Mr. Kartikay <br /> Puneesh, Mr. Bhrighu Pamidighantam, <br /> Advs. <br /> <br /> <br /> <b> CORAM:</b> <br /> <b> HON'BLE MR. JUSTICE JASMEET SINGH </b><br /> <b> </b><br /> <b>J U D G M E N T </b><br /> <b> </b><br /> <b>1.</b> <b> </b> This is a petition filed under Section 34 of the Arbitration and <br /> Conciliation Act, 1996, ( <b><i>“the Act”</i></b> ) seeking to challenge the Arbitral <br /> Award dated 08.05.2017 <b><i>(“Award”)</i></b> passed by the learned Sole <br /> Arbitrator in the matter of <i>“M/s Nagarjuna Construction Ltd. v. Ministry </i><br /> <i>Of Health & Family Welfare”.</i> <b><i> </i></b><br /> Digitally Signed<br /> By:MAYANK<br /> Signing Date:09.04.2026<br /> 18:31:43<br /> <b>O.M.P. (COMM) 337/2017</b> <b>Page 1 of 82</b> <br /><br /> <br /> <b>FACTUAL BACKGROUND </b><br /> <b> </b><br /> <b>2.</b> The petitioner, namely Ministry of Health & Family Welfare (respondent <br /> in the Arbitral Proceedings) invited bids for the execution of the works <br /> of construction of medical college and hostel complex at AIIMS, <br /> Bhopal. <br /> <b>3.</b> <b> </b> The contract was awarded <i>vide </i> a letter of notification dated 13.04.2010, <br /> to the respondent company namely NCC Limited, formerly known as <br /> M/s Nagarjuna Construction Co. Ltd. (Claimant in the Arbitral <br /> Proceedings) for the works including preparing designs and construction <br /> of Medical College & Hostel Complex at AIIMS, Bhopal, Package-I. <br /> <b>4.</b> <b> </b> Pursuant thereto, a contract with value of Rs. 147,89,73,233/- was <br /> executed between the parties on 21.05.2010 <b><i>(“Contract”), </i></b> with <br /> scheduled completion period of project being 15 months i.e., from <br /> 27.05.2010 to 26.08.2011. <br /> <b>5.</b> <b> </b> During the execution of works under the Contract, some disputes arose <br /> between the parties and the respondent company <i>vide </i> its letters dated <br /> 07.11.2014 and 13.12.2014 requested for appointment of Arbitrator by <br /> invoking arbitration Clause and also filed a petition under Section 11 of <br /> the Act on 07.04.2015 before this Court. However, during the pendency <br /> of the proceedings, the Director (PMSSY), Ministry of Health and <br /> Family Welfare PMSSY Division vide its order dated 29.05.2015 <br /> appointed Dr. Y.P.C. Dangay as the Sole Arbitrator to adjudicate <br /> disputes between the parties. <br /> <b>6.</b> <b> </b> The respondent filed its Statement of Claim <b><i>(“SOC”) </i></b> before the <br /> Arbitrator on 06.07.2015, to which the petitioner filed its written <br /> statement along with counter claim on 18.02.2016. Thereafter, on <br /> 04.04.2016, the respondent filed rejoinder to the written statement and <br /> counter claim. <br /> Digitally Signed<br /> By:MAYANK<br /> Signing Date:09.04.2026<br /> 18:31:43<br /> <b>O.M.P. (COMM) 337/2017</b> <b>Page 2 of 82</b> <br /><br /> <br /> <b>7.</b> <b> </b> During the Arbitral proceedings, the Arbitrator also visited the site for <br /> assessment of the status of work on 27.08.2016, 28.08.2016, 26.11.2016, <br /> 27.11.2016 and 16.04.2017. <br /> <b>8.</b> <b> </b> The Arbitrator passed an interim award dated 30.12.2016, directing the <br /> release of amount of Rs. 2,95,79,465/- for the Claim No. 1 in favour of <br /> the respondent and also, directing the respondent to complete the <br /> remaining works by the end of the year. <br /> <b>9.</b> <b> </b> Thereafter, the Arbitrator passed a final Award dated 08.05.2017, <br /> allowing most of the claims as raised by the respondent except Claim No. <br /> 11, and rejecting all the counter claims filed by the petitioner. The <br /> petitioner being aggrieved by the Award has filed the present petition. <br /> <b>SUBMISSIONS ON BEHALF OF THE PETITIONER </b><br /> <b><i>General Contentions </i></b><br /> <b>10.</b> <b> </b> Ms. Lakra, learned CGSC for the petitioner, submits that the Award is in <br /> violation of the public policy of India and is patently illegal for reasons <br /> apparent on the face of record. The scope of public policy is wide in <br /> nature and cannot be restricted in its interpretation. Reliance is placed on <br /> 1<br /> <i>DDA v. Manohar Lal</i> <i> </i> and <i>Oil & Natural Gas Corporation Ltd. v. SAW </i><br /> 2<br /> <i>pipes Ltd.</i> <br /> <b>11.</b> <b> </b> It is submitted by the learned counsel that the Arbitrator has failed to take <br /> into consideration, the deficiency/delays on part of the respondent by <br /> failing to comply with the directions issued by the Arbitrator during <br /> hearings. Despite this non-compliance by the respondent, the Arbitrator <br /> failed to observe this fact in his Award that there existed wilful delays on <br /> part of the respondent. These kinds of awards are not only perverse but <br /> also against the public policy of India, and against the interest of <br /> <br /> 1<br /> 2006 SCC OnLine Del 46. <br /> 2<br /> AIR 2003 SC 2629. <br /> Digitally Signed<br /> By:MAYANK<br /> Signing Date:09.04.2026<br /> 18:31:43<br /> <b>O.M.P. (COMM) 337/2017</b> <b>Page 3 of 82</b> <br /><br /> <br /> Government of India as they will encourage contractors to raise fake <br /> claims by quoting extremely low rates for getting government projects <br /> and then attempt to get unfair advantage by placing reliance on such <br /> awards. <br /> <b>12.</b> <b> </b> The Arbitrator has exceeded the jurisdiction conferred to it, has acted in <br /> violation of the terms of the Contract, and has not taken into <br /> consideration vital evidence and contentions. Thus, it is liable to be set <br /> aside under Section 34(2)(a)(iv) and Section 34(2)(b)(ii). <br /> <b><i>Attribution of Delays and associated claims for prolongation. </i></b><br /> <b>13.</b> <b> </b> The Arbitrator has failed to correctly appreciate the issue of delay <br /> attribution as it has not taken into consideration a vital report dated <br /> 21.04.2017 prepared by the superintending engineer, wherein the <br /> incomplete status of work was clearly stated. The respondent was bound <br /> by Section 37 of the Indian Contract Act, 1872 <b><i>(“Contract Act”)</i></b> , to <br /> perform its promise or to offer to perform the same, however in the view <br /> of this report it is clear that the respondent violated section 37 of the <br /> Contract act and the Arbitrator has failed to take into consideration this <br /> material evidence. Reliance is placed on <i>Aboobker Latif v. Reception </i><br /> <i>th</i> <i>3</i><br /> <i>Committee of the 48</i> <i> INC</i> <i>. </i><br /> <b>14.</b> <b> </b> It is also submitted that the Arbitrator failed to read the contract as a <br /> whole, leading to an erroneous interpretation of the relationship between <br /> the parties to the contract and the non-application of principle laid down <br /> 4<br /> in <i>Ramnath International Construction Pvt. Ltd. v. Union of India</i> <i> </i><br /> concerning employer-contractor agreements, wherein it was held that if <br /> the contractor sought and obtained extensions for delay attributable to <br /> either party, he would not be entitled to claim any compensation for such <br /> <br /> 3<br /> AIR 1937 BOM 410. <br /> 4<br /> (2007) 2 SCC 453. <br /> Digitally Signed<br /> By:MAYANK<br /> Signing Date:09.04.2026<br /> 18:31:43<br /> <b>O.M.P. (COMM) 337/2017</b> <b>Page 4 of 82</b> <br /><br /> <br /> delay. Reliance is also placed on <i>Unity Realty and Developers Ltd. v. BW </i><br /> <i>5</i><br /> <i>Highway Star Pvt. Ltd.</i> <br /> <b>15.</b> <b> </b> The Arbitrator had awarded the claim Nos. 6, 7, 8, and 9 by exceeding <br /> his jurisdiction and in ignorance of the terms of the Contract, which <br /> clearly stipulated that compensation is not payable on account of delay. <br /> Reliance is placed on <i>Ramnath International Construction Pvt. </i><br /> <i>Ltd.(Supra). </i> It is also submitted that the respondent filed inflated claims <br /> as the respondent claimed Rs. 35.09 crores under this head, but only Rs. <br /> 3.2 crores were held admissible by the Arbitrator. Additionally, the delay <br /> in project was attributable to the respondent only. <b> </b><br /> <b>16.</b> <b> </b> The Arbitrator awarded compensation under Claim Nos. 5, 6, 7, 8, 9, and <br /> 12 in ignorance of the terms of the Contract, i.e. Clause No. 6(a), 6(b), <br /> 40(h), 40(p)(ix) of the special conditions of the contract. Thus, the Award <br /> is in clear violation of the statutory mandate as encapsulated under <br /> Section 28(3) of the Act, whereby the Arbitrator is required to take into <br /> consideration the terms of the contract and trade usages as well. The <br /> Arbitrator has clearly acted beyond its jurisdiction conferred by the terms <br /> of the Contract. Reliance is placed on <i>Associated Engineering Co. vs. </i><br /> 6<br /> <i>Govt. of Andhra Pradesh</i> <i>.</i> <br /> <b><i>Claim No. 1: Release of wrongfully withheld amount from RA Bill-33 </i></b><br /> <b><i>& 34. </i></b><br /> <b>17.</b> <b> </b> Ms. Lakra, further states that the Arbitrator did not properly distinguish <br /> between regular extension of time <b><i>(“EOT”)</i></b> and provisional EOT. In <br /> construction contracts, as a regular trade practice provisional extensions <br /> are given to keep the contract running and avoid major disruptions. <br /> However these provisional EOT‟s do not imply that the delay is <br /> <br /> 5<br /> 2009 SCC Online Bom 1509. <br /> 6<br /> (1991) 4 SCC 93. <br /> Digitally Signed<br /> By:MAYANK<br /> Signing Date:09.04.2026<br /> 18:31:43<br /> <b>O.M.P. (COMM) 337/2017</b> <b>Page 5 of 82</b> <br /><br /> <br /> condoned/admitted. In the instant case, even after regular extensions up <br /> to 12.10.2012, the petitioner issued provisional extensions to keep the <br /> contract alive and explicitly reserved the petitioner‟s right to claim <br /> compensation under Clause No. 2 of the GCC for the respondent‟s <br /> delays. The Arbitrator while awarding this Claim No. 1 in the interim <br /> Award ignored this standard practice of granting provisional EOT‟s and <br /> acted in non-compliance of Section 28(3) of the Act. <br /> <b>18.</b> <b> </b> Additionally, the rescheduling of milestones were not required as <br /> rescheduling is only required up to the regular extension period i.e. <br /> ending on 12.10.2012. However, the recovery of withheld amount was <br /> made in March 2013 because the respondent defaulted in achieving <br /> milestone Nos. 4 and 5. The Arbitrator substantiated his Award on the <br /> ground that milestones were not rescheduled in accordance with the new <br /> timeline after grating of EOT‟s, and overlooked the fact that delays <br /> beyond 12.10.2012 were attributable to the respondent only. <br /> <b><i>Claim No. 2: Reimbursement of increase in taxes and duties under </i></b><br /> <b><i>Clause 38 of GCC of contract (VAT, Entry Tax and Central Excise). </i></b><br /> <b>19.</b> <b> </b> With respect to Claim No. 2, it is submitted that the finding of the <br /> Arbitrator is based on wrong interpretation of Clause No. 38 of the <br /> General Conditions of Contract <b><i>(“GCC”)</i></b> . The reasoning of the <br /> Arbitrator is patently illegal as the Arbitrator held that non-compliance <br /> with the provision for notice does not mean that the statutory increase in <br /> taxes duly paid by the petitioner will not be reimbursed. When a <br /> contractual term stipulated that a claim needed to be lodged within a <br /> specific time, non-compliance should lead to an adverse inference. Thus, <br /> the Arbitrator by allowing this claim despite non-compliance by the <br /> respondent has favoured the respondent in an unjust manner. <b> </b><br /> <b><i>Claim No. 3: Reimbursement of increase in taxes and duties under </i></b><br /> Digitally Signed<br /> By:MAYANK<br /> Signing Date:09.04.2026<br /> 18:31:43<br /> <b>O.M.P. (COMM) 337/2017</b> <b>Page 6 of 82</b> <br /><br /> <br /> <b><i>Clause 20 and 19B iv (b) of GCC of contract (Minimum Wages Act). </i></b><br /> <b> </b><br /> <b>20.</b> It is submitted that the Arbitrator erred in applying the provision <br /> contained in Clause No. 38 of the GCC while adjudicating the Claim No. <br /> 3, as the respondent itself has not substantiated this claim under Clause <br /> No. 38 of the GCC. <br /> <b>21.</b> <b> </b> Further, the Arbitrator has erred in holding that the present contract is <br /> similar to the CPWD contracts and that the respondent has rightly <br /> quantified its claim as per Clause No. 10 CC of the CPWD contract in <br /> which labour component for escalation is fixed at 25%. However, in the <br /> present case Clause No. 10CC of the CPWD was inapplicable as the <br /> stipulated completion period for the project was 15 months only, and <br /> Schedule F provided that Clause No. 10CC is only applicable when the <br /> stipulated period extends beyond 24 months. <br /> <b><i>Claim No. 4: Extra items of work claimed under Clause 12 of GCC </i></b><br /> <b><i>and Clause 22, 23 of SCC. </i></b><br /> <b>22.</b> <b> </b> Learned Counsel, apropos the Claim No. 4 submits, that the Arbitrator <br /> has not considered the contention of the petitioner that the dispute <i>qua </i><br /> Claim No. 4 i.e. extra items, survives only for ready mix concrete (RMC) <br /> item, as the issue concerning grit plaster was already discussed during the <br /> site visit on 26.11.2016 and was duly approved by the petitioner. Thus, <br /> the Arbitrator has erred in again awarding the claimed amount without <br /> discussing the detailed breakup and the basis of the rates claimed by the <br /> petitioner. <br /> <b>23.</b> <b> </b> She further submits that the Arbitrator has wrongly interpreted agreement <br /> item No. 3.8 and DSR Item No. 5.33, wherein it was clear that the cost of <br /> making and placing concrete were included in the quoted rates. The extra <br /> claim raised by the respondent was false because in this project, the <br /> concrete was made directly at the site and this fact was admitted by the <br /> Digitally Signed<br /> By:MAYANK<br /> Signing Date:09.04.2026<br /> 18:31:43<br /> <b>O.M.P. (COMM) 337/2017</b> <b>Page 7 of 82</b> <br /><br /> <br /> respondent during arbitral proceedings. The Arbitrator still compared and <br /> relied upon DSR Item No. 5.37 on the ground that the respondent also <br /> executed the work having scope similar to DSR Item No. 5.37, which is <br /> item for ready-mix concrete made in fully automatic plant somewhere <br /> else and then transported to the site in transit mixture for a lead of about <br /> 10 kms. This “upto 10 km lead” is a substantial cost factor, it assumes <br /> extra cost for making and transportation to the site. The same was not <br /> applicable in the present case, as the concrete was made on site. Thus, the <br /> finding of the Arbitrator had allowed undue benefits to the respondent on <br /> the basis of this misinterpretation and has disregarded the scope of <br /> agreement item No. 3.8 and DSR item No. 5.33. <b> </b><br /> <b>24.</b> <b> </b> Additionally, the Arbitrator has ignored the contention of the petitioner <br /> that these specific claims for extra items were not raised in terms and <br /> compliance of Clause No. 12 of the GCC during the execution of those <br /> items. <b> </b><br /> <b><i>Claim No. 5: Revised rates for individual items of work the quantities </i></b><br /> <b><i>of which had exceeded beyond limit. </i></b><br /> <b>25.</b> <b> </b> She further contends that with respect to the Claim No. 5, the Arbitrator <br /> has misinterpreted the terms of the contract and in an unjustified manner <br /> awarded market rates for items deviating more than 30% of the BOQ <br /> quantity because the respondent was well aware of the fact that Clause <br /> Nos. 12.2 and 12.3 applies only after deviation exceeds the threshold of <br /> 30% of trade work or 100% of foundation work as the case may be, and <br /> still the respondent did not claim this amount under Clause No. 12.4. <br /> Thus, directly raising this claim before the Arbitrator is unjustified. Also, <br /> there are inherent inconsistencies in findings of the Arbitrator as at one <br /> specific section of the Award, the Arbitrator used the word “Trade” to <br /> mean “building trade” and while allowing claim No. 5 he stated the same <br /> Digitally Signed<br /> By:MAYANK<br /> Signing Date:09.04.2026<br /> 18:31:43<br /> <b>O.M.P. (COMM) 337/2017</b> <b>Page 8 of 82</b> <br /><br /> <br /> word to be vague and proceeded to award rates applicable to individual <br /> BOQ items instead of BOQ subheads as contended by the petitioner <br /> during the arbitral proceedings. <b> </b><br /> <b>26.</b> <b> </b> Schedule F (Package-I), provides for deviation limit of 30% of the trade <br /> upto which the BOQ rates were payable and were already paid with <br /> respect to several deviated items, yet the Arbitrator failed to consider <br /> these contractual provisions and the petitioner‟s specific submissions. <br /> The petitioner further submits that the respondent‟s quantification was <br /> erroneous and unsupported by proper justification and did not even take <br /> into consideration the Bhopal cost index. For the sake of argument, even <br /> if any claim was maintainable, the Arbitrator did not scrutinise itemwise <br /> rates or the petitioner‟s objections, thereby vitiating the entire <br /> quantification process. In these circumstances, by effectively <br /> disregarding and rewriting the terms of the contract beyond the scope of <br /> reference, the Award is liable to be set aside in the interest of justice. <b> </b><br /> <b><i>Claim No. 10: Loss on locked up deposits Bank Guarantees due to </i></b><br /> <b><i>Prolongation of Contract. </i></b><br /> <b>27.</b> <b> </b> Ms. Lakra, submits that with respect to Claim No. 10, the Arbitrator has <br /> acted in violation of Clause No. 1(ii) of the GCC which provides that the <br /> petitioner is not liable to pay any interest/charge on account of the <br /> performance guarantee. <b> </b><br /> <b><i>Claim No. 12: Escalation Amount on material payable due to </i></b><br /> <b><i>prolongation ofcontract. </i></b><br /> <b>28.</b> <b> </b> The Arbitrator with respect to Claim No. 12 has acted in violation of the <br /> terms of the Contract as the respondent has preferred the claim because <br /> of escalation of materials, being fully aware of the fact that contract does <br /> not allow such escalation claims. <b> </b><br /> Digitally Signed<br /> By:MAYANK<br /> Signing Date:09.04.2026<br /> 18:31:43<br /> <b>O.M.P. (COMM) 337/2017</b> <b>Page 9 of 82</b> <br /><br /> <br /> <b>29.</b> <b> </b> It is also submitted that the Arbitrator in the Claim Nos. 13 and 14 <br /> awarded loss of interest on the amounts claimed under Claim Nos. 2, 3, <br /> 4, 5, 10 & 12 at the rate of 10% per annum, the same is in violation of <br /> law as settled by the Hon‟ble Supreme Court in the case of <i>Union of </i><br /> 7<br /> <i>India v. M/s Krafters Engineering & Leasing Pvt Ltd.</i> <i>, </i> and the terms of <br /> the contract as the contract does not provide for grant of interest. <b> </b><br /> <b>SUBMISSIONS ON BEHALF OF THE RESPONDENT </b><br /> <b>30.</b> <b> </b> Dr. George, learned counsel for the respondent, submits that the delays in <br /> execution of the Contract are not attributable to the respondent as the <br /> Arbitrator has returned categorical findings by placing reliance on the <br /> records i.e. hindrance register maintained and signed by the petitioner <br /> itself. Reliance is placed on <i>Delhi Agricultural Marketing Board v. HR </i><br /> 8<br /> <i>Builders.</i> <b> </b><br /> <b>31.</b> <b> </b> It is also submitted that the contents of the hindrance register were <br /> neither challenged by the petitioner in the present petition nor in the <br /> defence before the Arbitrator. It was only at the stage of oral arguments <br /> that this objection was raised by the petitioner. <b> </b><br /> <b>32.</b> <b> </b> He further submits that the Claim No. 2 concerning the reimbursement of <br /> Rs. 38,10,057/- towards increase in taxes and duties under Clause No. 38 <br /> of the GCC was rightly adjudicated by the Arbitrator. The petitioner <br /> raised the identical contention of absence of notice in terms of Clause <br /> No. 38 (iii) of the GCC before the Arbitrator as well and the same was <br /> rejected by the Arbitrator on the ground that the clause provided for the <br /> notice to be given but default of such notice is not in itself a ground to <br /> attract adverse consequences so as to reject a claim otherwise due. <br /> <br /> 7<br /> (2011) 7 SCC 279. <br /> 8<br /> 2019 SCC Online Del 8538. <br /> Digitally Signed<br /> By:MAYANK<br /> Signing Date:09.04.2026<br /> 18:31:43<br /> <b>O.M.P. (COMM) 337/2017</b> <b>Page 10 of 82</b> <br /><br /> <br /> 9<br /> Reliance is placed on <i>Mahesh Bansal v. Executive Engineer</i> and <i>Union </i><br /> <i>10</i><br /> <i>of India v. Associated Construction Co.</i> <i> </i> to state that the decision of the <br /> Arbitrator is in consonance with the settled position of law. <b> </b><br /> <b>33.</b> <b> </b> With respect to Claim No. 3, it is submitted that the challenge of the <br /> petitioner is baseless as the Arbitrator had adjudicated the claim in <br /> consonance with Clause Nos. 20 and 38 of the GCC. Clause No. 20 of <br /> the GCC provided that the respondent was bound to comply with the <br /> Minimum Wages Act, 1948 and Clause No. 38 states that any further tax <br /> or levy imposed by the statute and duly paid by the respondent shall be <br /> reimbursed to it. The Arbitrator rightly allowed this claim of the <br /> respondent with respect to the additional expenditure towards payment of <br /> minimum wages as amended from time to time. Reliance is placed on <br /> <i>11</i><br /> <i>Union of India v. Saraswat Trading Agency and Ors.</i> <i> </i> and <i>Associated </i><br /> <i>Construction Co. (Supra) </i> to submit that the stand of the Arbitrator is in <br /> consonance with the settled position of law. <b> </b><br /> <b>34.</b> <b> </b> Apropos the Claim Nos. 6, 7, 8, and 9, it is submitted that the Arbitrator <br /> has awarded these claims with detailed reasoning on fact and law. The <br /> petitioner has challenged these claims on the ground that the terms of the <br /> contract does not provide for compensation, in fact the special conditions <br /> of contract specifically preclude grant of compensation. However, as per <br /> the provisions of the Contract Act more particularly Section 53, 54, 55 <br /> and 73, in case of failure of performance, promises, and breach, the party <br /> at fault is liable for compensation for the losses suffered by the other <br /> party. In a judgment of this Court titled <i>Union of India v. Vishva Shanti </i><br /> <i>12</i><br /> <i>Builders (India) Pvt. Ltd.</i> <i>, </i> it was held that despite a clear condition <br /> <br /> 9<br /> 1995 SCC Online Del 333. <br /> 10<br /> 2016 SCC Online Del 4679. <br /> 11<br /> (2009) 16 SCC 504. <br /> 12<br /> (2024) SCC Online Del 5018. <br /> Digitally Signed<br /> By:MAYANK<br /> Signing Date:09.04.2026<br /> 18:31:43<br /> <b>O.M.P. (COMM) 337/2017</b> <b>Page 11 of 82</b> <br /><br /> <br /> under the contract barring compensation, the compensation cannot be <br /> said to be barred when the extensions were granted due to fault of the <br /> other party. Reliance is also placed on <i>K.N. Sathyapalan v. State Of </i><br /> <i>13</i><br /> <i>Kerala & Anr.</i> <b> </b><br /> <b>ANALYSIS AND FINDINGS </b><br /> <b>35.</b> <b> </b> I have heard the learned counsels for the parties and perused the material <br /> and documents placed on record. <b> </b><br /> <b><i>Scope of Interference Under Section 34 Of The Act</i></b> <b> </b><br /> <b>36.</b> <b> </b> The scope of interference under Section 34 of the Act is now clearly <br /> established. The Court is not required to sit in appeal as an Appellate <br /> Court over the Award, and it can neither reappreciate the evidence nor <br /> reinterpret the terms of the contract, when the view already taken by the <br /> Arbitrator is a probable and possible one. Judicial intervention with the <br /> Award is permissible only on limited and specific grounds, as <br /> encapsulated under Section 34 of the Act. The Court is not <br /> required/empowered to reappreciate evidence or substitute its own view <br /> with that of the Arbitral Tribunal. It is a settled position of law that <br /> Section 34 of the Act, embodies the principle of minimal judicial <br /> interference, thereby preserving the foundational precept of the Act, the <br /> finality and efficacy of Arbitral Awards. The Hon‟ble Supreme Court has <br /> recently observed this scope of interference in the judgment of <br /> <b><i>Consolidated Construction Consortium Ltd. v. Software Technology </i></b><br /> 14<br /> <b><i>Parks of India</i></b> , the relevant paragraphs of which reads as under: <b> </b><br /> <i>“46. Scope of Section 34 of the 1996 Act is now well </i><br /> <i>crystallised by a plethora of judgments of this Court. </i><br /> <i>Section 34 is not in the nature of an appellate provision. It </i><br /> <br /> 13<br /> (2007) 13 SCC 43. <br /> 14<br /> (2025) 7 SCC 757. <br /> Digitally Signed<br /> By:MAYANK<br /> Signing Date:09.04.2026<br /> 18:31:43<br /> <b>O.M.P. (COMM) 337/2017</b> <b>Page 12 of 82</b> <br /><br /> <br /> <i>provides for setting aside an arbitral award that too only on </i><br /> <i>very limited grounds i.e. as those contained in sub-sections </i><br /> <i>(2) and (2-A) of Section 34. It is the only remedy for setting </i><br /> <i>aside an arbitral award. An arbitral award is not liable to </i><br /> <i>be interfered with only on the ground that the award is </i><br /> <i>illegal or is erroneous in law which would require re-</i><br /> <i>appraisal of the evidence adduced before the Arbitral </i><br /> <i>Tribunal. If two views are possible, there is no scope for the </i><br /> <i>court to re-appraise the evidence and to take the view other </i><br /> <i>than the one taken by the Arbitrator. The view taken by the </i><br /> <i>Arbitral Tribunal is ordinarily to be accepted and allowed </i><br /> <i>to prevail. Thus, the scope of interference in arbitral </i><br /> <i>matters is only confined to the extent envisaged under </i><br /> <i>Section 34 of the Act. The court exercising powers under </i><br /> <i>Section 34 has per force to limit its jurisdiction within the </i><br /> <i>four corners of Section 34. It cannot travel beyond Section </i><br /> <i>34. Thus, proceedings under Section 34 are summary in </i><br /> <i>nature and not like a full-fledged civil suit or a civil appeal. </i><br /> <i>The award as such cannot be touched unless it is contrary </i><br /> <i>to the substantive provisions of law or Section 34 of the </i><br /> <i>1996 Act or the terms of the agreement.</i> ” <i> </i><br /> <b>37.</b> <b> </b> At the outset, Dr. George, learned counsel for the respondent, states that <br /> the present petition is <i>sans merit</i> as the petitioner has failed to plead or <br /> establish any specific permissible ground under Section 34 of the Act. <br /> The Award is a detailed Award substantiated by the evidence available <br /> on record and the same does not suffer from any vices as enumerated <br /> under Section 34 of the Act warranting interference by this Court. The <br /> findings of the Arbitrator are plausible and therefore cannot be interfered <br /> Digitally Signed<br /> By:MAYANK<br /> Signing Date:09.04.2026<br /> 18:31:43<br /> <b>O.M.P. (COMM) 337/2017</b> <b>Page 13 of 82</b> <br /><br /> <br /> with under the Section 34 jurisdiction. Reliance is placed on <b><i>Associate </i></b><br /> <b><i>15</i></b> <b><i>16</i></b><br /> <b><i>Builders v. DDA</i></b> <i>and </i> <b><i>Delhi Airport Metro Express (P) Ltd. v. DMRC</i></b> <i>.</i> <b> </b><br /> <b>38.</b> <b> </b> With the above scope of Section 34 of the Act in mind, I shall now deal <br /> with the rival contentions. <b> </b><br /> <b><i>Attribution of Delays </i></b><br /> <b>39.</b> <b> </b> The petitioner‟s challenge to the Award with regards to several claims <br /> can be distilled into one core controversy i.e. the findings on attribution <br /> of delays and prolongation of contract, which are pertinent for the entire <br /> Award and especially for decisions on Claim Nos. 6, 7, 8, and 9. <b> </b><br /> <b>40.</b> <b> </b> It is the case of the petitioner that the Arbitrator has erred in attributing <br /> the delays in execution of works under the contract to the petitioner. The <br /> Arbitrator has failed to take into consideration the pertinent facts and <br /> evidence which show that in fact the delays were attributable to the <br /> respondent. <b> </b><br /> <b>41.</b> <b> </b> It is contended by the petitioner that despite recording the objection of <br /> the petitioner in page No. 13 of the Award that the respondent had not <br /> completed the work by December 2016 as directed by the interim Award, <br /> the Arbitrator has ignored this contention and also a vital report dated <br /> 21.04.2017 of the superintending engineer, wherein the status of work <br /> was shown as incomplete. The Arbitrator also visited the site on many <br /> instances and directed the respondent to complete certain works before <br /> 31.12.2016. Despite, all these contentions and evidence pertaining to the <br /> attribution of the delay on part of the respondent, the Arbitrator did not <br /> give any findings on these arguments in the Award. It is also stated that <br /> the Award is passed without taking terms of the contract into <br /> consideration and these kind of awards confer undue benefits on <br /> <br /> 15<br /> (2015) 3 SCC 49. <br /> 16<br /> (2022) 1 SCC 131. <br /> Digitally Signed<br /> By:MAYANK<br /> Signing Date:09.04.2026<br /> 18:31:43<br /> <b>O.M.P. (COMM) 337/2017</b> <b>Page 14 of 82</b> <br /><br /> <br /> contractors from government department and consequently the Award is <br /> against public policy and the interest of the Country. <b> </b><br /> <b>42.</b> <b> </b> <i>Per contra</i> , the respondent contends that the Arbitrator has correctly <br /> relied on hindrance registers in giving his findings on the issue of delay. <br /> The specific delays mentioned in the hindrance register are attributable to <br /> the petitioner for several reasons as stated therein including the delays <br /> duly noted at Serial Nos. 20 and 21 of the Hindrance register on the <br /> ground of delay in receipt of drawing for stone flooring over terrace and <br /> works being carried out by other agencies engaged by the petitioner. The <br /> respondent has also drawn my attention to the paragraph Nos. 17 and 18 <br /> of the judgment of the Hon‟ble Division Bench of this court in the case <br /> of <b><i>Delhi Agricultural Marketing Board (Supra)</i></b> , which read as under: <b> </b><br /> <i>“17. The Hindrance Register is a document which is </i><br /> <i>maintained at the work site and is signed by the officers of </i><br /> <i>the employer and the contractor. It records the events which </i><br /> <i>occur contemporaneously in relation to the hindrances that </i><br /> <i>may be faced by the contractor from time to time in the </i><br /> <i>execution of the work. It is a document which is a log of the </i><br /> <i>communications which take place between the employer and </i><br /> <i>the contractor in relation to the events leading to hindrance </i><br /> <i>in the execution of the work. </i><br /> <i>18. The extension of time that may be considered by the </i><br /> <i>Engineer-in-Charge necessarily would have to rely upon </i><br /> <i>records, such as the hindrance register: In the present case, </i><br /> <i>the Arbitrator has found that the Hindrance Register </i><br /> <i>recorded hindrances for as many as 563 days, whereas the </i><br /> <i>actual delay in completion of the work was only 502 days. </i><br /> <i>That being the position, the finding returned by the learned </i><br /> Digitally Signed<br /> By:MAYANK<br /> Signing Date:09.04.2026<br /> 18:31:43<br /> <b>O.M.P. (COMM) 337/2017</b> <b>Page 15 of 82</b> <br /><br /> <br /> <i>Arbitrator fixing the responsibility for delay in completion </i><br /> <i>of work, in our view, is completely justified.” </i><br /> <b><i>(Emphasis Supplied) </i></b><br /> <b>43.</b> <b> </b> The Arbitrator apropos this issue has critically examined the multiple <br /> EOT‟s duly approved by the petitioner and also noted that many extra <br /> items pending since 2013 were only settled after directions from the <br /> Arbitrator, and because of many pending issues the time for contract was <br /> delayed by almost three times of the scheduled completion time. The <br /> Arbitrator duly considered the submissions of the petitioner and observed <br /> that the petitioner was directed to produce the hindrance register despite <br /> which the petitioner never disputed the entries in this register. The <br /> Arbitrator went on to observe that the hindrance register is maintained at <br /> site by the petitioner, duly signed by the engineers of the petitioner and <br /> by the consultants engaged by the petitioner only. The relevant portions <br /> of the Award reads as under: <b> </b><br /> <i>“14.3.2 Many pending extra items were pending since 2013 </i><br /> <i>which were settled and paid on the directions of this Tribunal </i><br /> <i>during the proceedings. As is ascertained barring two extra items </i><br /> <i>for rest of the items the rates were settled during the Arbitration </i><br /> <i>proceedings. Because of many pending issues, the project </i><br /> <i>execution, as it appears had lost the track for long. Though the </i><br /> <i>time stipulation of 15 months was made, with the prolongation of </i><br /> <i>the Contract by more than three times of the stipulated period, </i><br /> <i>the time has been set at large by various defaults of the </i><br /> <i>Respondent. </i><br /> <i>14.3.3 The written submissions made by the Respondent latest on </i><br /> <i>10-4-2017 were carefully examined. The Charts produced do not </i><br /> <i>have any material significance to the issue on delays since both </i><br /> Digitally Signed<br /> By:MAYANK<br /> Signing Date:09.04.2026<br /> 18:31:43<br /> <b>O.M.P. (COMM) 337/2017</b> <b>Page 16 of 82</b> <br /><br /> <br /> <i>the parties have argued and admitted that there are delays and </i><br /> <i>when the work is incomplete the value executed on comparison </i><br /> <i>with the original period will be less. </i><br /> <i>14.3.4 The Tribunal has asked the Respondent to produce the </i><br /> <i>hindrance register maintained at the site by the Respondent </i><br /> <i>which has been relied by the parties. The Respondent has not </i><br /> <i>made any allegation either in arguments or written submissions </i><br /> <i>of possibility of forging of the register which itself is produced by </i><br /> <i>Respondent during the proceedings. </i><br /> <i>14.3.5 The Respondent pointed out few discrepancies in the </i><br /> <i>written submissions made dt: 21.4.2017 in the hindrance </i><br /> <i>register. As can be seen the hindrance register is the record </i><br /> <i>maintained by the Respondent signed by the Respondent </i><br /> <i>Engineers and the Consultants engaged by the Respondent. </i><br /> <i>Neither during the pleadings nor during the arguments, the </i><br /> <i>discrepancies alleged are pointed out which appear an </i><br /> <i>afterthought. Moreover, the hindrance register is Respondent's </i><br /> <i>document which is admitted by them. </i><br /> <i>14.3.6 The Claimant had in fact pointed out few factual </i><br /> <i>discrepancies in actual dates of removal of hindrances as </i><br /> <i>recorded in the Hindrance register produced by the Respondent </i><br /> <i>during the proceedings. This was by way of filing a written </i><br /> <i>statement submitted by the Claimant which was not challenged </i><br /> <i>by the Respondent. </i><br /> <i>14.3.7 Considering the material evidence on record, the Tribunal </i><br /> <i>is of the opinion that the delays are not attributable to the </i><br /> <i>Claimant and the reasons mentioned in various EOT </i><br /> <i>applications are legitimate as found from records.” </i><br /> Digitally Signed<br /> By:MAYANK<br /> Signing Date:09.04.2026<br /> 18:31:43<br /> <b>O.M.P. (COMM) 337/2017</b> <b>Page 17 of 82</b> <br /><br /> <br /> <b><i> (Emphasis Supplied) </i></b><br /> <b> </b><br /> <b>44.</b> I am of the view that the reliance placed by the Arbitrator on hindrance <br /> register is well founded, and reasoned, as the petitioner has never <br /> disputed the contents of the hindrance register before the Arbitrator or <br /> even before this court until the stage of oral arguments. The petitioner <br /> only pointed out few discrepancies before the Arbitrator which were <br /> categorically dismissed by the Arbitrator by terming them as an <br /> afterthought. Again raising such crucial objection at such a belated stage <br /> of oral arguments of Section 34 proceedings is nothing but an <br /> afterthought. A perusal of the hindrance register shows that it is a <br /> contemporaneous record maintained at site and duly signed by the <br /> representatives of the petitioner and the consultant engaged by them, thus <br /> it can be said that the petitioner had knowledge of the delays, and its <br /> causes and the same cannot be attributed to the respondent for no <br /> reason/fault on its part. The relevant portions of the hindrance register <br /> (Typed Copy) showing signature of consultant and engineers are <br /> reproduced as under:- <b> </b><br /> <b> </b><br /> <b> </b><br /> <b> </b><br /> <b> </b><br /> <b> </b><br /> <b> </b><br /> <b> </b><br /> <b> </b><br /> <b> </b><br /> <b> </b><br /> <b> </b><br /> <b> </b><br /> Digitally Signed<br /> By:MAYANK<br /> Signing Date:09.04.2026<br /> 18:31:43<br /> <b>O.M.P. (COMM) 337/2017</b> <b>Page 18 of 82</b> <br /><br /> <br /> <b> </b><br /> <b> </b><br /> <b> </b><br /> <b> </b><br /> <b> </b><br /> <b> </b><br /> <b> </b><br /> <b> </b><br /> <b> </b><br /> <b> </b><br /> Digitally Signed<br /> By:MAYANK<br /> Signing Date:09.04.2026<br /> 18:31:43<br /> <b>O.M.P. (COMM) 337/2017</b> <b>Page 19 of 82</b> <br /><br /> <br /></div><table><thead><tr><th>S.<br>No.</th><th>Nature of<br>hindrance</th><th>Item of work<br>which could not<br>be executed due<br>to this hindrance</th><th>Date of start<br>of hindrance</th><th>Date of<br>removal of<br>hindrance</th><th>Overlapping if<br>any</th><th>Net<br>hindrance<br>in days</th><th>Sign of<br>A.E.</th><th>Weightage<br>of this<br>hindrance</th><th>Net<br>affected<br>days</th><th>Sign of<br>PM/EE</th><th>Remarks<br>of<br>residing<br>officer</th></tr></thead><tbody><tr><td>18</td><td>Details of cold<br>rooms and<br>kitchens in<br>hostels</td><td>Due to non-<br>availability of<br>the details of<br>provisions to be<br>left in the dining<br>halls and<br>kitchens for the<br>services and<br>equipments,<br>these portions<br>cannot be<br>finished and so<br>the completion<br>of hostels is<br>affected<br>Affected areas –<br>all hostels</td><td>07.12.2011</td><td>31.03.2012<br>and cont.</td><td>114 days</td><td>114 days</td><td></td><td></td><td>Nil</td><td></td><td></td></tr><tr><td>19<br>igned</td><td>Extended<br>development</td><td>Due to existence<br>of sewer pond</td><td>07.12.2011</td><td>31.03.2012<br>and cont.</td><td>114 days</td><td>114 days</td><td></td><td></td><td>Nil</td><td></td><td></td></tr></tbody></table><div><br /> <b>O.M.P. (COMM) 337/2017</b> <b>Page 20 of 82</b> <br /><br /> <br /></div><table><thead><tr><th></th><th>and work of<br>services around<br>the building</th><th>and non<br>channelization of<br>nallas passing<br>around the<br>building, the<br>work of<br>sewer/water<br>supply and other<br>services were in<br>the limits and<br>scope of<br>package-1<br>cannot be<br>completed and so<br>the progress is<br>affected.<br>Affected areas –<br>Medical college<br>and college of<br>Nursing</th><th></th><th></th><th></th><th></th><th></th><th></th><th></th><th></th><th></th></tr></thead><tbody><tr><td>20<br>igned</td><td>Delay in receipt<br>of drawing for<br>kota stone</td><td>Delay in water<br>proofing work.</td><td>23.11.2011</td><td>04.05.2012</td><td>163 days</td><td>163 days</td><td></td><td></td><td>Nil</td><td></td><td></td></tr><tr><td>NK</td><td></td><td></td><td></td><td></td><td></td><td></td><td></td><td></td><td></td><td></td><td></td></tr></tbody></table><div><br /> <b>O.M.P. (COMM) 337/2017</b> <b>Page 21 of 82</b> <br /><br /> <br /></div><table><thead><tr><th></th><th>flooring and<br>terrace water<br>proofing</th><th>Affected area<br>Medical College,<br>College of<br>Nursing Ayush<br>block and<br>Library Building</th><th></th><th></th><th></th><th></th><th></th><th></th><th></th><th></th><th></th></tr></thead><tbody><tr><td>21</td><td>Delay of civil<br>work due to<br>work of other<br>agencies in main<br>service building<br>& library.</td><td>Delay in<br>complete work<br>of block „A‟ of<br>service building<br>as well as<br>Ground floor and<br>terrace of library<br>Affected area :<br>Service building<br>and library<br>building</td><td>27.01.2012</td><td>30.09.2011<br>and cont.</td><td></td><td>613 days</td><td></td><td></td><td>613 days</td><td></td><td></td></tr><tr><td>22<br>igned</td><td>Delay of civil<br>work due to<br>work of other<br>agencies near<br>hostels and</td><td>Delay in civil<br>work and<br>finishing work<br>near hostel and<br>other buildings.</td><td>14.03.2012</td><td>30.09.2013<br>and cont.</td><td>565 days</td><td>565 days</td><td></td><td></td><td>Nil</td><td></td><td></td></tr></tbody></table><div><br /> <b>O.M.P. (COMM) 337/2017</b> <b>Page 22 of 82</b> <br /><br /> <br /></div><table><thead><tr><th></th><th>other buildings</th><th>Affected area: -<br>Hostel and other<br>building</th><th></th><th></th><th></th><th></th><th></th><th></th><th></th><th></th><th></th></tr></thead><tbody><tr><td>23</td><td>Details of cold<br>rooms and<br>kitchen in<br>hostels</td><td>Due to non<br>availability of<br>the details of<br>provisions to be<br>left in the dining<br>halls and<br>kitchens for the<br>services and<br>equipments,<br>these portions<br>cannot be<br>finished and so<br>the completion<br>of hostels is<br>affected.<br>Affected area: all<br>hostels</td><td>24.05.2012</td><td>30.09.2013<br>and cont.</td><td>494 days</td><td>494 days</td><td></td><td></td><td>Nil</td><td></td><td></td></tr><tr><td>24<br>igned</td><td>Heavy rains</td><td>Delay in civil</td><td>06.06.2012</td><td>24.09.12</td><td>88 days</td><td>88 days</td><td></td><td></td><td>Nil</td><td></td><td></td></tr></tbody></table><div><br /> <b>O.M.P. (COMM) 337/2017</b> <b>Page 23 of 82</b> <br /><br /> <br /></div><table><thead><tr><th></th><th>during 2012</th><th>work and<br>finishing was<br>due to the heavy<br>rains<br>Affected area:<br>hostels and other<br>buildings</th><th></th><th></th><th></th><th>(Rain<br>effected<br>days only)</th><th></th><th></th><th></th><th></th><th></th></tr></thead><tbody><tr><td>25</td><td>Modifications<br>desired by the<br>Director in O.T<br>room Autoclave<br>room and<br>flooring in<br>Ayush building.</td><td>Delay in final<br>finishing work<br>in Ayush block<br>Affected area:<br>Ayush block.</td><td>01.07.2012</td><td>30.09.2013<br>and cont.</td><td>456 days</td><td>456 days</td><td></td><td></td><td>Nil</td><td></td><td></td></tr><tr><td>26</td><td>Delay in receipt<br>GFC drawings<br>for work of<br>atrium and<br>mumty in<br>nursing college</td><td>Finishing work<br>of first floor<br>elevation on<br>atrium side<br>Affected area:<br>Nursing college.</td><td>01.07.2012</td><td>30.09.2013<br>and cont.</td><td>456 days</td><td>456 days</td><td></td><td></td><td>Nil</td><td></td><td></td></tr></tbody></table><div><br /> Digitally Signed<br /> By:MAYANK<br /> Signing Date:09.04.2026<br /> 18:31:43<br /> <b> </b> <b> </b><br /> <b>O.M.P. (COMM) 337/2017</b> <b>Page 24 of 82</b> <br /><br /> <br /> <b> </b><br /> <b> </b><br /> <b>45.</b> <b> </b> The objections of the petitioner <i>qua </i> the non-consideration of report of <br /> superintending engineer dated 21.04.2017, site visits and status of <br /> incomplete work, were considered by the Arbitrator and were found <br /> irrelevant in view of better evidence in the form of hindrance register. <br /> The same is evident from the paragraph Nos. 14.3.2, 14.3.3 and 14.3.4 as <br /> reproduced above. <b> </b><br /> <b>46.</b> <b> </b> The respondent has correctly relied on <b><i>Delhi Agricultural Marketing </i></b><br /> <b><i>Board (Supra) </i></b> highlighting the significance of hindrance registers. Also, <br /> a Coordinate Bench of this Court in a recent judgment titled as <b><i>Airport </i></b><br /> <b><i>17</i></b><br /> <b><i>Authority of India v. URC Construction</i></b> <b><i>, </i></b> reiterated the position that <br /> hindrance registers hold substantial evidentiary value in construction <br /> contract disputes. The relevant paragraph No. 89 of the aforesaid <br /> judgment reads as under: <b> </b><br /> <i>“89. It is a settled principle that site records i.e. Hindrance </i><br /> <i>Registers often hold greater evidentiary value regarding the </i><br /> <i>actual impact of weather on specific construction activities </i><br /> <i>like concreting or earthwork than general meteorological </i><br /> <i>data.” </i><br /> <b><i>(Emphasis Supplied) </i></b><br /> <b>47.</b> <b> </b> Additionally, the Arbitrator is the master of quality and quantity of <br /> evidence and his reasoning when substantiated by the material evidence <br /> cannot be said to be perverse, patently illegal or against public policy, <br /> just because another view is plausible. <b> </b><br /> <b>48.</b> <b> </b> Therefore, on the issue of attribution of delays, the reasoning and <br /> findings of the Arbitrator rests on legitimate contemporaneous evidence <br /> <br /> 17<br /> 2026 SCC OnLine Del 534. <br /> Digitally Signed<br /> By:MAYANK<br /> Signing Date:09.04.2026<br /> 18:31:43<br /> <b>O.M.P. (COMM) 337/2017</b> <b>Page 25 of 82</b> <br /><br /> <br /> and the said Award cannot be said to be vitiated on the grounds under <br /> Section 34 of the act merely because a report or some contentions of the <br /> petitioner are not discussed in detail in the Award. This court under <br /> Section 34 of the act cannot weigh evidence or reappreciate the same. <b> </b><br /> <b><i>Claim Nos. 6, 7, 8, AND 9: Additional expenses due to prolongation of </i></b><br /> <b><i>contract for various reasons.</i></b> <b> </b><br /> <b>49.</b> <b> </b> Claim Nos. 6, 7, 8, and 9 pertain to the claims raised by the respondent <br /> before the Arbitrator for compensation arising from prolongation of the <br /> Contract period, covering idling of resources such as plant, machinery, <br /> labour, etc. These claims collectively forms a substantial portion of the <br /> relief sought by the respondent i.e. an amount of about Rs. 35.08 crore, <br /> out of which an amount of about Rs. 3.2 crores was awarded <i>vide </i> the <br /> Award. These claims are predicated on the arbitral finding that the delays <br /> are primarily attributable to the petitioner, justifying damages. <b> </b><br /> <b>50.</b> <b> </b> The primary contention raised by the petitioner, apropos these claims is <br /> that the Arbitrator exceeded its jurisdiction by granting compensation <br /> despite clear bar contained in the terms and conditions of the Contract. It <br /> is contended by the petitioner that the respondent in terms and conditions <br /> of the Contract is only entitled to extensions and not compensation. The <br /> petitioner has relied on <b><i>Ramnath International Construction Pvt. Ltd. </i></b><br /> <b><i>(Supra) </i></b> to support its contention that when there is a contractual <br /> stipulation prohibiting compensation in case of extension of time, the <br /> same cannot be awarded by the Arbitrator. <b> </b><br /> <b>51.</b> <b> </b> The Award of these claims is contended by the petitioner to be in <br /> violation of Clause Nos. 6(a), (b) and 40(h), (p)(ix) of the Special <br /> Conditions of the Contract, as they bar any claims for delays and only <br /> allows remedy of extension of time. The relevant clauses read as under: <b> </b><br /> <i>“Clause 6: Disruption of Progress </i><br /> Digitally Signed<br /> By:MAYANK<br /> Signing Date:09.04.2026<br /> 18:31:43<br /> <b>O.M.P. (COMM) 337/2017</b> <b>Page 26 of 82</b> <br /><br /> <br /> <i>(a) The Contractor shall give adequate but not less than 4 </i><br /> <i>weeks written notice to the PC whenever planning or </i><br /> <i>progress of the works is likely to be delayed or disrupted </i><br /> <i>unless any further drawing or order, including a direction, </i><br /> <i>instruction or approval, is required to be issued by the PC. </i><br /> <i>The notice shall include details of the drawing or order </i><br /> <i>required explaining why and by when it is required and of </i><br /> <i>any delay or disruption likely to be suffered if it is late . </i><br /> <i>(b) If by any reason of any failure or inability of the PC to </i><br /> <i>issue within 4 weeks any drawing or instruction for which </i><br /> <i>notice has been given by the Contractor in accordance with </i><br /> <i>Sub-clause 1 and the Contractor suffers delay when the PC </i><br /> <i>shall after due consultation with the Contractor recommend </i><br /> <i>to the Client any extension of time under respective clause. </i><br /> <i>Notwithstanding anything stated above, the Contractor shall </i><br /> <i>not be eligible for any financial compensation arising out of </i><br /> <i>the above. </i><br /> <i>Clause 40 Miscellaneous </i><br /> <i>(h) Delay in starting the work </i><br /> <i>No compensation shall be allowed for any delay caused in </i><br /> <i>the starting of the work on account of acquisition of land, </i><br /> <i>encroachment or in the case of clearance of works, on </i><br /> <i>account of any delay in according sanction to estimates in </i><br /> <i>issue of drawings, decisions etc. however, the extension of </i><br /> <i>time shall be granted as per relevant conditions of Contract. </i><br /> <i>…. </i><br /> <i>(p) Miscellaneous </i><br /> Digitally Signed<br /> By:MAYANK<br /> Signing Date:09.04.2026<br /> 18:31:43<br /> <b>O.M.P. (COMM) 337/2017</b> <b>Page 27 of 82</b> <br /><br /> <br /> <i>(ix) No idling charges or compensation shall be paid for </i><br /> <i>idling of the Contractor's labour, staff or P&M etc. on any </i><br /> <i>ground or due to any reason whatsoever.” </i><br /> <b>52.</b> <b> </b> The respondent contends that these claims awarded under several heads <br /> for additional expenses during the period of prolongation, are based on <br /> detailed reasoning and despite presence of the aforesaid clauses, where <br /> the delays are attributable to one party i.e. the petitioner, the respondent <br /> is entitled to compensation/damages under Section 53, 54, 55 and 73 of <br /> the Contract Act. The respondent to support his contention has placed <br /> reliance on <b><i>Vishwa Shanti Builders (India) Pvt. Ltd. (Supra) </i></b> and <b><i> K.N. </i></b><br /> <b><i>Sathyapalan (Supra). </i></b><br /> <b>53.</b> <b> </b> The Arbitrator in the Award has categorically observed that the <br /> principles of compensation apply in case of prolongation of Contract <br /> arising due to breach as the delays were attributable to the petitioner <br /> only. The relevant portions of the Award read as under: <b><i> </i></b><br /> <i>“6.1.6 The Claimant submitted that, as per section 53,54,55 </i><br /> <i>and 73 of the Indian Contract Act, 1872, under </i><br /> <i>circumstances of failure in performance, promises and </i><br /> <i>breach on part of the Respondent, the Respondent is liable </i><br /> <i>for compensation for the losses suffered by Claimant as a </i><br /> <i>consequence of the said lapses of the Respondent. The </i><br /> <i>Claimant argued that as per sections of Indian Contract </i><br /> <i>Act, 1872 which clearly provides that when one party who </i><br /> <i>has been compelled to incur loss due to the failure of the </i><br /> <i>other party, such party is entitled for compensation. </i><br /> <i>6.1.7 The Claimant cited following case laws in support of </i><br /> <i>this claim: </i><br /> Digitally Signed<br /> By:MAYANK<br /> Signing Date:09.04.2026<br /> 18:31:43<br /> <b>O.M.P. (COMM) 337/2017</b> <b>Page 28 of 82</b> <br /><br /> <br /> <i>i. The Hon'ble Supreme Court in the case of K.N. </i><br /> <i>Sathyapalan (Dead) by LRs. Vs. State of Kerala and </i><br /> <i>Anr. (2007) 13 SCC 43 </i><br /> <i>ii. The Hon'ble High Court of Delhi in National </i><br /> <i>Highways </i> <i>Authority </i> <i>of </i> <i>India </i> <i>Vs. </i> <i>Hindustan </i><br /> <i>Construction Company Ltd. 2016 (2) Arb. LR 1 (Delhi) </i><br /> <i>(DB). </i><br /> <i>6.1.8 The Claimant submitted that ordinarily parties would </i><br /> <i>be bound by the terms agreed upon in the Contract but in </i><br /> <i>the event of one of the parties is unable to fulfill its </i><br /> <i>obligations under the Contract which has direct bearing, </i><br /> <i>the Arbitrator is vested with the authority to compensate the </i><br /> <i>injured party for the extra cost incurred by him as a result </i><br /> <i>of failure of the other party. The Claimant has also </i><br /> <i>submitted that in the light of various Court Judgments, the </i><br /> <i>aggrieved party needs to be compensated on account of </i><br /> <i>delay in completion of work due to breaches committed by </i><br /> <i>the other party. </i><br /> <i>…. </i><br /> <i>6.2.1 The Respondent referred Contract Clauses 6 of SCC, </i><br /> <i>Clause 40(a),(b),(h),(p) of SCC and submitted that various </i><br /> <i>reasons like delays due to rainfall, cold weather etc. for </i><br /> <i>which holding Respondent liable is beyond any logical </i><br /> <i>sense. The Respondent had argued that despite clearance of </i><br /> <i>the said hindrances, the Claimant has miserably failed to </i><br /> <i>complete the works within the justified extension granted to </i><br /> <i>it. This irresponsible act of the Claimant has resulted in </i><br /> <i>delay in creation of required infrastructure for this </i><br /> Digitally Signed<br /> By:MAYANK<br /> Signing Date:09.04.2026<br /> 18:31:43<br /> <b>O.M.P. (COMM) 337/2017</b> <b>Page 29 of 82</b> <br /><br /> <br /> <i>prestigious institute, as argued by Respondent. It is clarified </i><br /> <i>also that after considering all hindrances the competent </i><br /> <i>authority has decided to grant interim regular extension of </i><br /> <i>th</i><br /> <i>time for completion of work up to 18</i> <i> July 2012 only. The </i><br /> <i>Respondent argued that as the rest of the delay up to point </i><br /> <i>of consideration lies on part of the Claimant, the burden of </i><br /> <i>delay should also be borne by the Claimant only. </i><br /> <i>…. </i><br /> <i>6.3.2 The Claimant has worked out the expenses on actual </i><br /> <i>audited account basis for showing the costs incurred as per </i><br /> <i>their books of accounts on machinery, manpower and </i><br /> <i>various overheads. These costs were claimed in the </i><br /> <i>prolonged period extending from contractual completion </i><br /> <i>from August 2011 to till May 2015 for nearly 60 months. </i><br /> <i>6.3.3 In Construction Contracts, the Courts have also </i><br /> <i>upheld the principles of compensation in case of </i><br /> <i>prolongation of contracts arising due to breach. For </i><br /> <i>quantification of overheads application of formula is also </i><br /> <i>recognized by Indian courts and Hudson's formula is more </i><br /> <i>popular having judicial acceptability. This formula is based </i><br /> <i>on the practice that contractors do add the overheads as </i><br /> <i>percentage loaded to the direct costs to arrive at bid costs. </i><br /> <i>As per CPWD standard practice, 15% is allowed towards </i><br /> <i>Contractor's profit & overheads on the analysis of rates for </i><br /> <i>the items. In building trade, the site, general office & other </i><br /> <i>overheads may be to the tune of at least 5 to 8% even as per </i><br /> <i>the CPWD practice. Generally the contractor recovers the </i><br /> Digitally Signed<br /> By:MAYANK<br /> Signing Date:09.04.2026<br /> 18:31:43<br /> <b>O.M.P. (COMM) 337/2017</b> <b>Page 30 of 82</b> <br /><br /> <br /> <i>costs incurred on resources deployed including overhead </i><br /> <i>costs from the turn over achieved. </i><br /> <i>Award: </i><br /> <i>Towards Claims No. 6, 7, 8 and 9, the claimant has totally </i><br /> <i>claimed of Rs. 35,08,71,374/- under various heads of </i><br /> <i>machinery hire charges, manpower costs, site overheads & </i><br /> <i>establishment costs and head office, regional office </i><br /> <i>expenses in the prolongation period. </i><br /> <i>The average monthly turnover which is lost due to </i><br /> <i>prolongation of work is assessed as Rs. 7.5 Cr. in above. An </i><br /> <i>under recovery of 1% expenses per month on lost turnover </i><br /> <i>summing up all types of overheads and expenses claimed </i><br /> <i>under Claims number 6,7,8 and 9 is judged genuine and </i><br /> <i>reasonable. Thus for 43 months prolongation from </i><br /> <i>Sept.2011 to up to March2015, a compensation of Rs. 7.5 </i><br /> <i>Lakhs per month that is 1% of Rs. 7.5 Crores is awarded. </i><br /> <i>Thus a total of Rs. 3,22,50,000/-, is awarded towards claim </i><br /> <i>numbers 6, 7, 8 and 9.” </i><br /> <b><i>(Emphasis Supplied) </i></b><br /> <b>54.</b> <b> </b> A perusal of the arbitral Award and written statement dated 18.02.2016 <br /> filed by the petitioner before the Arbitrator, makes it clear that the <br /> petitioner raised this identical contention even before the Arbitrator as <br /> well. Raising this contention again in a Section 34 jurisdiction is nothing <br /> but reiteration of the same pleadings before this Court. The Award is well <br /> reasoned, based on correct application of principle of law, and passed <br /> after taking into consideration all the material evidence placed on record. <br /> Thus, the Arbitrator has rightly adopted a plausible view by making a <br /> categorical finding that in construction contracts the courts have applied <br /> Digitally Signed<br /> By:MAYANK<br /> Signing Date:09.04.2026<br /> 18:31:43<br /> <b>O.M.P. (COMM) 337/2017</b> <b>Page 31 of 82</b> <br /><br /> <br /> principles of compensation in cases of breach of contract. The Arbitrator <br /> has not awarded these claims in lump sum rather the Arbitrator has also <br /> made categorical formula based technical finding. <b><i> </i></b><br /> <b>55.</b> <b> </b> The reliance placed by the petitioner on <b><i>Ramnath International </i></b><br /> <b><i>Construction Pvt. Ltd. (Supra)</i></b> is misconceived and unfounded, as that <br /> decision was based on a very widely worded condition of the contract, <br /> namely Clause No. 11, which reads as under: <b><i> </i></b><br /> <i>“11. Clause 11 of the General Conditions of Contract </i><br /> <i>relates to time, delay and extension. We extract below the </i><br /> <i>portions of clause 11 relevant for our purpose: </i><br /> <i>11. Time, delay and extension.—(A) Time is of the essence </i><br /> <i>of the contract and is specified in the contract documents or </i><br /> <i>in each individual works order. </i><br /> <i>As soon as possible, after contract is let or any substantial </i><br /> <i>work order is placed and before work under it is begun, the </i><br /> <i>GE and the contractor shall agree upon the time and </i><br /> <i>progress chart. The chart shall be prepared in direct </i><br /> <i>relation to the time stated in the contract documents or the </i><br /> <i>works order for completion of the individual items thereof </i><br /> <i>and/or the contract or works order as a whole. It shall </i><br /> <i>include the forecast of the dates for commencement and </i><br /> <i>completion of the various trades, processes or sections of </i><br /> <i>the work, and shall be amended as may be required by </i><br /> <i>agreement between the GE and the contractor within the </i><br /> <i>limitation of time imposed in the contract documents or </i><br /> <i>works order. If the work be delayed: </i><br /> <i>(i) by force majeure, or </i><br /> Digitally Signed<br /> By:MAYANK<br /> Signing Date:09.04.2026<br /> 18:31:43<br /> <b>O.M.P. (COMM) 337/2017</b> <b>Page 32 of 82</b> <br /><br /> <br /> <i>(ii) by reason of abnormally bad weather, or </i><br /> <i>(iii) by reason of serious loss or damage by fire, or </i><br /> <i>(iv) by reason of civil commotion, local combination of </i><br /> <i>workmen, strike or lockout, affecting any of the tradesmen </i><br /> <i>employed on the work, or </i><br /> <i>(v) by reason of delay on part of nominated sub-contractors, </i><br /> <i>or nominated suppliers which the contractor has, in the </i><br /> <i>opinion of GE, taken all practicable steps to avoid, or </i><br /> <i>reduce, or </i><br /> <i>(vi) by reason of delay on the part of contractors or </i><br /> <i>tradesmen engaged by the Government in executing work </i><br /> <i>not forming part of the contract, or </i><br /> <b></b> *<br /> <i>(viii) by reason of any other cause, which in the absolute </i><br /> <i>discretion of the accepting officer is beyond the contractor's </i><br /> <i>control; </i><br /> <i>then in any such case the officer hereinafter mentioned may </i><br /> <i>make fair and reasonable extension in the completion dates </i><br /> <i>of individual items or groups of items of works for which </i><br /> <i>separate periods of completion are mentioned in the </i><br /> <i>contract documents or works order, as applicable. </i><br /> <b></b> *<br /> <i>(B) If the works be delayed: </i><br /> <i>(a) by reason of non-availability of government stores in </i><br /> <i>Schedule B or </i><br /> Digitally Signed<br /> By:MAYANK<br /> Signing Date:09.04.2026<br /> 18:31:43<br /> <b>O.M.P. (COMM) 337/2017</b> <b>Page 33 of 82</b> <br /><br /> <br /> <i>(b) by reason of non-availability or breakdown of </i><br /> <i>government tools and plant listed in Schedule C; </i><br /> <i>then, in any such event, notwithstanding the provisions </i><br /> <i>hereinbefore contained, the accepting officer may in his </i><br /> <i>discretion, grant such extension of time as may appear </i><br /> <i>reasonable to him and the same shall be communicated to </i><br /> <i>the contractor by the GE in writing. The decision so </i><br /> <i>communicated shall be final and binding and the contractor </i><br /> <i>shall be bound to complete the works within such extended </i><br /> <i>time. </i><br /> <i>(C) No claim in respect of compensation or otherwise, </i><br /> <i>howsoever arising, as a result of extensions granted under </i><br /> <i>Conditions (A) and (B) above shall be admitted.” </i><br /> <b><i>(Emphasis Supplied) </i></b><br /> <b><i> </i></b><br /> <b>56.</b> <b> </b> The Hon‟ble Supreme Court treated the above stated Clause as a specific <br /> consent by the contractor to accept only extension of time in full <br /> satisfaction of any delay claims. The relevant paragraph of the judgment <br /> reads as under: <b><i> </i></b><br /> <i>“18. In spite of having held that both were responsible for </i><br /> <i>the delay and having noticed the arguments based on clause </i><br /> <i>11(C) of the General Conditions of Contract, the Arbitrator </i><br /> <i>proceeded to award damages on the ground of delay on the </i><br /> <i>reasoning that the contractor is entitled to compensation, </i><br /> <i>unless the employer establishes that the contractor has </i><br /> <i>consented to accept the extension of time alone in </i><br /> <i>satisfaction of his claim for delay. As rightly held by the </i><br /> Digitally Signed<br /> By:MAYANK<br /> Signing Date:09.04.2026<br /> 18:31:43<br /> <b>O.M.P. (COMM) 337/2017</b> <b>Page 34 of 82</b> <br /><br /> <br /> <i>High Court, which decision we have affirmed while </i><br /> <i>considering Question (i), clause 11(C) of the General </i><br /> <i>Conditions of Contract is a clear bar to any claim for </i><br /> <i>compensation for delays, in respect of which extensions </i><br /> <i>have been sought and obtained. Clause 11(C) amounts to a </i><br /> <i>specific consent by the contractor to accept extension of </i><br /> <i>time alone in satisfaction of his claims for delay and not </i><br /> <i>claim any compensation. In view of the clear bar against </i><br /> <i>award of damages on account of delay, the Arbitrator </i><br /> <i>clearly exceeded his jurisdiction, in awarding damages, </i><br /> <i>ignoring clause 11(C).” </i><br /> <b><i>(Emphasis Supplied) </i></b><br /> <b>57.</b> <b> </b> However, in the present case, the Clause Nos. 6(a), (b), 40(h) and <br /> 40(p)(ix) are narrow in nature and are not structured as comprehensive <br /> clauses covering all prolongations caused by breach of the either party <br /> i.e. the petitioner or respondent, the Arbitrator here has found the delays <br /> to be attributable to the petitioner alone on the basis of hindrance <br /> registers, and has not disregarded the contractual clauses but has <br /> consciously reconciled them with Sections 53, 55 and 73 of the Contract <br /> Act while awarding damages. <b><i> </i></b><br /> <b>58.</b> <b> </b> Additionally, the judgment of <b><i>Ramnath International Construction Pvt. </i></b><br /> <b><i>Ltd. (Supra) </i></b> is distinguishable from the factual backdrop of the present <br /> case as from a perusal of the paragraph No. 18 of the judgment as <br /> reproduced above, the delays were attributable to both the parties, which <br /> was not the case in the instant petition. A Coordinate Bench of this Court <br /> Digitally Signed<br /> By:MAYANK<br /> Signing Date:09.04.2026<br /> 18:31:43<br /> <b>O.M.P. (COMM) 337/2017</b> <b>Page 35 of 82</b> <br /><br /> <br /> <b><i>18</i></b><br /> in <b><i>Simplex Concrete Piles (India) Ltd. v. Union of India</i></b> <b><i>, </i></b> also made <br /> the following observations: <b><i> </i></b><br /> <i>“19. In my opinion, if I look at the issue from both the micro </i><br /> <i>and macro positions, keeping in focus the intendment of </i><br /> <i>legislation called the Contract Act, then, the judgment in the </i><br /> <i>case of Asian Techs Ltd. can be said to laying down a law </i><br /> <i>which would further the object and purpose of the Contract </i><br /> <i>Act. I must hasten to add that I am still doubtful whether I </i><br /> <i>am entitled to decide the aspect that out of two decisions of </i><br /> <i>Supreme Court, which one is to prevail, therefore, my </i><br /> <i>observations are strictly in terms of the limited parameters </i><br /> <i>of the facts of the present case required to decide the aspect </i><br /> <i>of the entitlement or the disentitlement to damages in view </i><br /> <i>of the provisions of Section 55 and 73 of the Contract Act. I </i><br /> <i>would with all due respect to the learned senior counsel for </i><br /> <i>the petitioner, would not venture further and would leave it </i><br /> <i>finally for a larger Bench of this court or the Supreme Court </i><br /> <i>itself to consider whether at all there is any conflict between </i><br /> <i>the judgments of Ram Nath International and Asian Techs </i><br /> <i>Ltd and if there is a conflict, the ratio of which of the two </i><br /> <i>judgments ought to prevail. I am therefore, deciding this </i><br /> <i>case, to make things very clear, only on the basis of the </i><br /> <i>decision that contractual clauses which prohibit the </i><br /> <i>entitlement to rightful damages of a person is clearly hit and </i><br /> <i>are void by virtue of Section 23 of the Contract Act.”</i> <b><i> </i></b><br /> <br /> 18<br /> 2010 SCC OnLine Del 821. <br /> Digitally Signed<br /> By:MAYANK<br /> Signing Date:09.04.2026<br /> 18:31:43<br /> <b>O.M.P. (COMM) 337/2017</b> <b>Page 36 of 82</b> <br /><br /> <br /> <b>59.</b> <b> </b> For the said reasons, the findings of the Arbitrator are sound, reasonable <br /> and based on a plausible view. Hence, no interference with the same is <br /> warranted under Section 34 of the Act. <b> </b><br /> <b><i>Claim No. 1: Release of wrongfully withheld amount from RA Bill-33 </i></b><br /> <b><i>& 34. </i></b><br /> <b>60.</b> <b> </b> The Arbitrator <i>vide</i> interim award dated 30.12.2016 has awarded Rs. <br /> 2,95,79,465/- apropos the Claim No. 1 towards the amount withheld <br /> from the respondent‟s running account bills, without interest which was <br /> decided later by the Arbitrator at the time of final Award. The Award is <br /> based on the finding that the withholding of amount for non-achievement <br /> of milestone Nos. 4 and 5, was wrong as pursuant to the EOT‟S <br /> milestone Nos. 4 and 5 also needed to be rescheduled. It was further held <br /> by the Arbitrator that milestone Nos. 1, 2, and 3 were rescheduled <br /> pursuant to the EOT‟s and hence there was no reason for not <br /> rescheduling milestone Nos. 4 and 5. <br /> <b>61.</b> <b> </b> Notably, the findings of the Arbitrator in award of Claim No. 1 in the <br /> final Award is a reproduction of the findings made in the interim award <br /> dated 30.12.2016 wherein the claim was adjudicated except the interest <br /> component which was adjudicated to be paid in the final Award. <br /> <b>62.</b> <b> </b> The petitioner raises two fold contentions with respect to Claim No. 1, <br /> firstly that the Arbitrator failed to distinguish between a regular <br /> extension and a provisional extension. In construction contracts, <br /> provisional extensions, are granted merely to keep the contract alive and <br /> does not mean that the delay of the contractor is condoned or admitted. <br /> In the present case despite regular extensions, provisional extensions <br /> were granted while explicitly reserving the right to levy compensation <br /> for delays under Clause No. 2 of the GCC. Secondly, rescheduling of <br /> milestone applied only upto regular EOT i.e. granted upto 12.10.2012 <br /> Digitally Signed<br /> By:MAYANK<br /> Signing Date:09.04.2026<br /> 18:31:43<br /> <b>O.M.P. (COMM) 337/2017</b> <b>Page 37 of 82</b> <br /><br /> <br /> and recovery in March 2013 for persistent non-achievement of milestone <br /> Nos. 4 and 5 was valid, rendering this claim of the Award violative of <br /> Section 28(3) of the Act. <br /> <b>63.</b> <b> </b> The Arbitrator apropos this Claim observed that as per Clause No. 5 of <br /> the GCC, Schedule F, the original milestones in the Contract were meant <br /> to be mutually decided between the parties and as per Clause No. 5.4 of <br /> the GCC, the milestones were required to be adjusted by the Engineer in <br /> Charge when extensions of time were granted. However, in the instant <br /> factual matrix, the petitioner granted several EOT‟s but never <br /> rescheduled milestone Nos. 4 and 5 in accordance with the new <br /> timelines. The Arbitrator categorically went on to hold that the amount <br /> was withheld by the petitioner based on the originally agreed milestones, <br /> which are irrelevant in light of the several EOT‟s granted by the <br /> petitioner without rescheduling the said milestones. Additionally, the <br /> Arbitrator held that the delays were attributable to the petitioner even <br /> beyond the period of regular EOT. The relevant portions of the Award <br /> read as under: <br /> <i>“Finding of the Tribunal:</i> <br /> <i>1.6 I have carefully considered the above arguments of both </i><br /> <i>the parties, the documents and evidence produced before </i><br /> <i>me. </i> <br /> <i>1.7 In clause 5 of GCC, Schedule 'F' Page 107 of the </i><br /> <i>Contract, (Page 85 of CV -1) it is stipulated that Mile </i><br /> <i>stone(s) will be mutually decided on award of work. Also as </i><br /> <i>per clause 5.4 of GCC Engineer-in-charge has to determine </i><br /> <i>the EOT and reschedule the Milestones for completion of </i><br /> <i>work. In the instant case though the Engineer-in-charge </i><br /> Digitally Signed<br /> By:MAYANK<br /> Signing Date:09.04.2026<br /> 18:31:43<br /> <b>O.M.P. (COMM) 337/2017</b> <b>Page 38 of 82</b> <br /><br /> <br /> <i>granted EOT but had not rescheduled the milestones. From </i><br /> <i>the records placed before me it is seen that the Respondents </i><br /> <i>had withheld sum of amount Rs.2,95,79,465/- from the RA </i><br /> <i>Bills of 33 & 34 of the Claimants. Also it is evident from the </i><br /> <i>hindrance register filed by the Respondents that some of the </i><br /> <i>hindrances which were persisting beyond the period of </i><br /> <i>regular EOT i.e. 18.07.2012. Such hindrances were </i><br /> <i>continuing all along. </i><br /> <i>1.8 As can be seen from the records, withholding of above </i><br /> <i>referred amount was initiated based on originally agreed </i><br /> <i>mile stones stipulated in the agreement well before the </i><br /> <i>determination of EOT. It was imperative upon the parties to </i><br /> <i>agree on rescheduling the milestones on granting of EOT. </i><br /> <i>Because of this the original agreed schedule for milestones </i><br /> <i>have lost their relevance. Furthermore the dispute between </i><br /> <i>th</i> <i>th</i><br /> <i>the parties is only regarding non achievement of 4</i> <i>, 5</i> <i> </i><br /> <i>st</i> <i>nd</i> <i>rd</i><br /> <i>milestones. Since milestones 1</i> <i> , 2</i> <i>, 3</i> <i> were achieved </i><br /> <i>within the extended period, which is not denied by the </i><br /> <i>Respondents. Hence, there is no dispute between the parties </i><br /> <i>on achieving the first three milestones. </i><br /> <i>AWARD:- </i><br /> <i>After deliberating in detail and considering all the </i><br /> <i>submissions of parties, documents and evidence filed, the </i><br /> <i>Tribunal awards that the withheld amount of Rs. </i><br /> <i>2,95,79,465/- on account of non achievement of milestones </i><br /> <i>from the Claimants bill shall be refunded to the Claimants. </i><br /> Digitally Signed<br /> By:MAYANK<br /> Signing Date:09.04.2026<br /> 18:31:43<br /> <b>O.M.P. (COMM) 337/2017</b> <b>Page 39 of 82</b> <br /><br /> <br /> <i>The Claimants have claimed interest @ 15 % P A for the </i><br /> <i>above claim amount separately under Claim no.13. From </i><br /> <i>the records placed before me I find that the amount was </i><br /> <i>th</i><br /> <i>withheld while releasing payments for 33,34</i> <i> RA bills on </i><br /> <i>18-2-2014. </i><br /> <i>The Tribunal Awards the simple interest at a rate 12% per </i><br /> <i>annum on the above amount to be refunded from the date of </i><br /> <i>recovery i.e.l8.2.2014 to the date of the award.” </i><br /> <b>64.</b> <b> </b> The relevant Clause No. 5 of the GCC reads as under: <br /> <i>“Clause No. 5.1 of GCC </i> <br /> <i>As soon as possible after the contract is concluded, the </i><br /> <i>contractor shall submit a Time and Progress Chart for each </i><br /> <i>mile stone and get it approved by the Department. The </i><br /> <i>Chart shall be prepared in direct relation to the time stated </i><br /> <i>in the contract documents for completion of items of the </i><br /> <i>works. It shall indicate the forecast of the dates of </i><br /> <i>commencement and completion of agreement between the </i><br /> <i>Engineer-in-Charge </i> <i>and </i> <i>the </i> <i>Contractor within </i> <i>the </i><br /> <i>limitations of time imposed in the Contract documents, and </i><br /> <i>further to ensure good progress during the execution of the </i><br /> <i>work, the contract shall in all cases in which the time </i><br /> <i>allowed for any work, exceeds one month (Save for special </i><br /> <i>jobs for which a separate programme has been agreed </i><br /> <i>upon) complete the work as per mile stones given in </i><br /> <i>Schedule 'F'. </i><br /> Digitally Signed<br /> By:MAYANK<br /> Signing Date:09.04.2026<br /> 18:31:43<br /> <b>O.M.P. (COMM) 337/2017</b> <b>Page 40 of 82</b> <br /><br /> <br /> <i>Sl. No. 13 amendment no 1 to tender document: </i><br /> <i>Five (5) Mile Stone(s) will be mutually decided on award of </i><br /> <i>work based on the work programme submitted by </i><br /> <i>contractor. The amount to be withheld for non-achievement </i><br /> <i>of each mile stone· will be 1% of the tendered value. </i><br /> <i>Clause No. 5.4 of GCC </i><br /> <i>In any such case the Engineer-In-charge may give a fair </i><br /> <i>and reasonable extension of time and reschedule the </i><br /> <i>milestones for completion of work. Such extension shall be </i><br /> <i>communicated to the Contractor by the Engineer-in-charge </i><br /> <i>in writing within 3 months of the date of receipt of such </i><br /> <i>request. Non application by the Contractor for Extension of </i><br /> <i>time shall not be a bar for giving a fair and reasonable </i><br /> <i>extension by the Engineer-in-charge and this shall be </i><br /> <i>binding on the contractor.” </i><br /> <b>65.</b> <b> </b> I am in full agreement with the view of the Arbitrator that once extension <br /> is granted in view of Clause No. 5, the originally fixed milestone <br /> becomes irrelevant and any withholding cannot be allowed on the basis <br /> of not achieving the earlier fixed milestones. The reasoning adopted by <br /> the Arbitrator is cogent, correct and based on interpretation of Clause <br /> No. 5 of the GCC, which mandates rescheduling of the milestones in <br /> cases of grant of EOT. The view taken by the Arbitrator is not only a <br /> plausible view but also a reasonable one which is substantiated by <br /> contractual terms and evidence available on record. <br /> <b>66.</b> <b> </b> The findings of the Arbitrator are based on plausible interpretation of <br /> Digitally Signed<br /> By:MAYANK<br /> Signing Date:09.04.2026<br /> 18:31:43<br /> <b>O.M.P. (COMM) 337/2017</b> <b>Page 41 of 82</b> <br /><br /> <br /> Clause No. 5 of the GCC, which cannot be reinterpreted/reappreciated <br /> by this Court under Section 34 of the Act. Thus, no ground warranting <br /> interference by this Court is established. <br /> <b><i>Claim No. 2: Reimbursement of increase in taxes and duties under </i></b><br /> <b><i>Clause 38 of GCC of contract (VAT, Entry Tax and Central Excise). </i></b><br /> <b>67.</b> <b> </b> Claim No. 2 pertains to reimbursement of a sum of Rs. 38,10,057/‑ <br /> towards increase in taxes and duties during the currency of the Contract, <br /> claimed by the respondent under Clause No. 38 of the GCC. The <br /> Arbitrator has allowed this claim, holding that once the statutory levies <br /> were in fact increased and duly paid by the respondent (contractor) in <br /> relation to the works, the petitioner (employer) was bound, under the <br /> Contract, to reimburse the same. <b> </b><br /> <b>68.</b> <b> </b> The petitioner has challenged the findings of the Arbitrator apropos the <br /> Claim No. 2 only on the ground that the respondent failed to lodge the <br /> claim within 30 days time period as stipulated under Clause No. 38 of the <br /> GCC. The same contention was also raised by the petitioner before the <br /> Arbitrator. The findings of the Arbitrator in favour of the respondent on <br /> this contention are stated to be patently illegal, perverse and unjust. <br /> Clause No. 38 of the GCC reads as under: <b> </b><br /> <i> “Clause 38: Conditions for reimbursement of levy/taxes if </i><br /> <i>levied after receipt of tenders </i><br /> <i>i. All tendered rate shall be inclusive of all taxes and levies </i><br /> <i>payable under respective statutes. However, pursuant to the </i><br /> <i>constitution (46th amendment Act, 1982), if any further tax </i><br /> <i>or levy is imposed by statute, after the last stipulated date </i><br /> <i>for the receipt of tender including extensions if any and the </i><br /> <i>contractor thereupon necessarily and properly pays such </i><br /> <i>taxes/levies, the contractor shall be reimbursed the amount </i><br /> Digitally Signed<br /> By:MAYANK<br /> Signing Date:09.04.2026<br /> 18:31:43<br /> <b>O.M.P. (COMM) 337/2017</b> <b>Page 42 of 82</b> <br /><br /> <br /> <i>so paid, provided such payments, if any, is not, in the </i><br /> <i>opinion of the superintending engineer (whose decision </i><br /> <i>shall be final and binding on the contractor) attributable to </i><br /> <i>delay in execution of work within the control of the </i><br /> <i>contractor. </i><br /> <i>ii. The contractor shall keep necessary books of accounts </i><br /> <i>and other documents for the purpose of this condition as </i><br /> <i>may be necessary and shall allow inspection of the same by </i><br /> <i>a duly authorized representative of the Government and/or </i><br /> <i>the Engineer-in-charge and further shall furnish such other </i><br /> <i>information/document as the Engineer-in-charge may </i><br /> <i>require from time to time. </i><br /> <i>iii. The contractor shall, within a period of 30 days of the </i><br /> <i>imposition of any such further tax or levy, pursuant to the </i><br /> <i>constitution (Forty Sixth Amendment) Act 1982, give a </i><br /> <i>written notice thereof to the Engineer-in-charge that the </i><br /> <i>same is given pursuant to this condition, together with all </i><br /> <i>necessary information relating thereto.” </i><br /> <b><i>(Emphasis Supplied) </i></b><br /> <b>69.</b> <b> </b> <i>Per contra, </i> the respondent argues that the petitioner has only reiterated <br /> the same contentions as raised before the Arbitrator, and the Arbitrator <br /> has already in a detailed and reasoned manner adjudicated these <br /> contentions of the petitioner. The respondent to substantiate the decision <br /> of the Arbitrator has placed reliance on <b><i>Mahesh Bansal (Supra) </i></b> and <br /> <b><i>Associated Construction Co. (Supra),</i></b> where courts have upheld <br /> reimbursement of statutory levies despite procedural lapse of furnishing <br /> notice, so long as the substantive liability under the contract stood <br /> established. <b> </b><br /> Digitally Signed<br /> By:MAYANK<br /> Signing Date:09.04.2026<br /> 18:31:43<br /> <b>O.M.P. (COMM) 337/2017</b> <b>Page 43 of 82</b> <br /><br /> <br /> <b>70.</b> <b> </b> The Arbitrator with regards to the Claim No. 2 has noted that the <br /> petitioner has neither disputed the admissibility of the claim nor the <br /> quantification of it, but has only raised a defence limited to the ground <br /> that the claim was not lodged within 30 days. The Arbitrator referred to <br /> the Clause No. 38 of the GCC to hold that the said Clause provides for <br /> the notice to be given, but it does not stipulate that if notice is not given, <br /> the otherwise legitimate dues will not be reimbursed. Thus, in absence of <br /> any specific bar, the amounts paid in accordance with revised taxes are <br /> bound to be reimbursed. The relevant operative portions of the Award <br /> read as under: <b> </b><br /> <i>“2.3.1 In Clause 38 of GCC it is stipulated that pursuant to </i><br /> <i>the Constitution (46th Amendment Act, 1982), if any further </i><br /> <i>tax or levy is imposed by Statute, after the last stipulated </i><br /> <i>date of receipt of tender including extensions if any and the </i><br /> <i>contractor thereupon necessarily and properly pays such </i><br /> <i>taxes/levies, the contractor shall be reimbursed the amount </i><br /> <i>so paid. Further the contractor is required to keep the </i><br /> <i>necessary </i> <i>records </i> <i>for </i> <i>the </i> <i>purpose </i> <i>of </i> <i>seeking </i><br /> <i>reimbursement. </i><br /> <i>…. </i><br /> <i>2.3.3 From the records placed before me it is seen that the </i><br /> <i>Claimant had paid such increase in taxes time to time </i><br /> <i>during execution of work and requested the Respondent for </i><br /> <i>reimbursement of the same as per the provisions of the </i><br /> <i>Contract and based on the supporting documents provided </i><br /> <i>to it. </i><br /> <i>2.3.4 As can be seen from the record, the Respondent </i><br /> <i>neither disputed the admissibility of claim under this clause </i><br /> Digitally Signed<br /> By:MAYANK<br /> Signing Date:09.04.2026<br /> 18:31:43<br /> <b>O.M.P. (COMM) 337/2017</b> <b>Page 44 of 82</b> <br /><br /> <br /> <i>nor the quantification of the reimbursement of the taxes </i><br /> <i>filed by the Claimant. But only submitted and argued in </i><br /> <i>their submissions that the claim was not lodged within 30 </i><br /> <i>days. Furthermore, the dispute between the parties is only </i><br /> <i>regarding limitation of claim and the only objection taken </i><br /> <i>by the Respondent is that notice as required under Clause </i><br /> <i>38 of GCC had not been served on the Respondent before </i><br /> <i>making this claim. As can be seen the above Clause </i><br /> <i>provides that notice had to be given but that by itself is no </i><br /> <i>ground to reject the claim if otherwise found due. Clause 38 </i><br /> <i>of GCC does not stipulate that if notice is not given then </i><br /> <i>statutory increase in taxes paid by the contractor would not </i><br /> <i>be reimbursed. However, the work is in progress and the </i><br /> <i>Claim is of progressive in nature. In the absence of any bar </i><br /> <i>that the Claimant having paid the revised taxes which is </i><br /> <i>calculated based on the actual paid challans, this claim </i><br /> <i>appears justified. </i><br /> <i>Award: An amount of Rs. 38,10,057/- is awarded to the </i><br /> <i>Claimant against this Claim towards reimbursement of </i><br /> <i>taxes and duties paid.” </i><br /> <b><i>(Emphasis Supplied) </i></b><br /> <b>71.</b> <b> </b> In this view of the matter, the line of reasoning followed by the <br /> Arbitrator cannot be characterised as perverse or patently illegal. Clause <br /> No. 38 (iii) of the GCC as reproduced undoubtedly embodies a <br /> stipulation regarding notice within a certain period, but the same Clause <br /> does not in any possible way provide that failure to comply with the <br /> provision concerning notice within 30 days shall result in nullifying that <br /> right of reimbursement or the same will render the claim for otherwise <br /> Digitally Signed<br /> By:MAYANK<br /> Signing Date:09.04.2026<br /> 18:31:43<br /> <b>O.M.P. (COMM) 337/2017</b> <b>Page 45 of 82</b> <br /><br /> <br /> legitimate dues as non-maintainable. Treating such a stipulation of notice <br /> as directory rather than mandatory and in the absence of an express <br /> stipulation, the interpretation of the Arbitrator is a plausible construction <br /> of the Contract. It cannot, therefore, be said that the Arbitrator has <br /> ignored the terms of the Contract or exceeded the jurisdiction. The <br /> Arbitrator has interpreted Clause No. 38 and has made a finding which is <br /> also in consonance of the judgments of this Court. <br /> <b>72.</b> <b> </b> The respondent to substantiate the decision of the Arbitrator has correctly <br /> placed reliance on <b><i>Associated Construction Co. (Supra), </i></b> wherein a <br /> Coordinate Bench of this Court relied on <b><i>Mahesh Bansal (Supra),</i></b> to <br /> hold that mere non-compliance with provision for notice is not in itself a <br /> ground to invalidate a claim otherwise valid and when the Arbitrator <br /> bases his decision on evidence based formula/methodology/admitted <br /> amount, the same should not be interfered under Section 34 jurisdiction. <br /> The relevant paragraphs of <b><i>Associated Construction Co. (Supra) </i></b> read as <br /> under: <br /> <i>“31. It is not disputed by the petitioner that almost a similar </i><br /> <i>controversy has already been adjudicated upon by this </i><br /> <i>Court in the case titled as Mahesh Bansal v. Executive </i><br /> <i>Engineer (FCD. 1) (1995) 34 DRJ 249. Single Judge of this </i><br /> <i>Court in the said case was concerned with a similar claim </i><br /> <i>for labour escalation under a similar clause as in the </i><br /> <i>present case, and proceeded to deal with the objections to </i><br /> <i>the arbitral award in the said case as under: </i><br /> <i>“8. So far as Claim No. 3 is concerned, the claimant had </i><br /> <i>claimed increase in the cost of labor due to increase in </i><br /> <i>labor </i> <i>wages </i> <i>on </i> <i>account </i> <i>of </i> <i>Delhi </i> <i>Administration </i><br /> Digitally Signed<br /> By:MAYANK<br /> Signing Date:09.04.2026<br /> 18:31:43<br /> <b>O.M.P. (COMM) 337/2017</b> <b>Page 46 of 82</b> <br /><br /> <br /> <i>Notification. Minimum labor rates were quoted at the time </i><br /> <i>the lenders were submitted. These rates were revised w.e.f. </i><br /> <i>st</i><br /> <i>1</i> <i> June, 1984 by Delhi Administration. Hence the petitioner </i><br /> <i>was duly bound to pay the revised wages to his labor. The </i><br /> <i>only objection taken by the respondent is that notice as </i><br /> <i>required under Clause 10(c) had not been served on the </i><br /> <i>respondent before making this claim. Secondly record had </i><br /> <i>not been produced to substantiate the same. Both these </i><br /> <i>objections have been turned down by the Arbitrator </i><br /> <i>primarily on the ground that the respondent submitted a </i><br /> <i>st</i><br /> <i>statement showing the amount of work done after 1</i> <i> June </i><br /> <i>1984 i.e. exhibit „R-11‟. He also look into consideration the </i><br /> <i>labor component from exhibit „R11‟ which worked out to be </i><br /> <i>23.5% as per the norms of C.P.W.D. Therefore, he </i><br /> <i>concluded that the petitioner would be justified to claim </i><br /> <i>escalation as worked out on the basis of exhibit „R-11‟ while </i><br /> <i>absorbing 10% and, therefore, concluded that award of Rs. </i><br /> <i>3,620.00 would be just as against the claim of Rs. </i><br /> <i>20,700.00. So far as serving of notice is concerned, </i><br /> <i>admittedly Clause 10(c) provides that notice had to be given </i><br /> <i>but that by itself is no ground to reject the claim if otherwise </i><br /> <i>found due. Clause 10(c) does not stipulate that if notice is </i><br /> <i>not given than statutory increase in labor wages paid by the </i><br /> <i>contractor would not be given. In the absence of any bar, </i><br /> <i>the Arbitrator was within his right to conclude that the </i><br /> <i>contractor having paid the revised wages which he </i><br /> <i>calculated on the assumed labor component of 23.5%; as </i><br /> <i>per the norms of the C.P.W.D. and therefore, relying on the </i><br /> Digitally Signed<br /> By:MAYANK<br /> Signing Date:09.04.2026<br /> 18:31:43<br /> <b>O.M.P. (COMM) 337/2017</b> <b>Page 47 of 82</b> <br /><br /> <br /> <i>document filed by the respondent exhibit „R-11” he </i><br /> <i>calculated the escalation of the labor component and </i><br /> <i>awarded the amount. I see no reason to interfere in the </i><br /> <i>same.” </i><br /> <i>32. A reading of the aforesaid judgment would show that </i><br /> <i>similar objections to the award have been raised by the </i><br /> <i>petitioner in the present case have been repelled. The </i><br /> <i>approach taken by the Arbitrator in the present case is </i><br /> <i>similar to the approach that has been upheld by this Court </i><br /> <i>in the aforesaid case. </i><br /> <i>33. It appears from the record that the Arbitrator has </i><br /> <i>gone strictly by the admitted amount of work done in the </i><br /> <i>present contract by the petitioner and extracted the labor </i><br /> <i>component from the same. As already noted hereinabove, </i><br /> <i>the Arbitrator has thus based his formula/methodology only </i><br /> <i>on the relevant statutory notifications evidencing the </i><br /> <i>increase in minimum wages and RAR bills, to evidence the </i><br /> <i>work actually executed, which have admittedly been </i><br /> <i>certified by the petitioner itself at different stages of the </i><br /> <i>work. </i><br /> <i>34. It is not the case of the petitioner that the subject </i><br /> <i>contract provide for a different formula to be applied in </i><br /> <i>order to arrive at the quantification of the escalation due. It </i><br /> <i>is the petitioner who had appointed the Arbitrator, who is </i><br /> <i>not only a technical person but is also incidentally a serving </i><br /> <i>officer of the petitioner. The very purpose behind the </i><br /> <i>appointment of technical persons as Arbitrators is that they </i><br /> Digitally Signed<br /> By:MAYANK<br /> Signing Date:09.04.2026<br /> 18:31:43<br /> <b>O.M.P. (COMM) 337/2017</b> <b>Page 48 of 82</b> <br /><br /> <br /> <i>may use their expertise and experience in the field to be able </i><br /> <i>to resolve technical and trade-specific disputes between the </i><br /> <i>parties. Once such a technical and factual determination </i><br /> <i>has been carried out, it is not open to the petitioner to make </i><br /> <i>a grievance about the same merely because the said </i><br /> <i>determination was not to its liking. Single Judge of this </i><br /> <i>Court in the case of P.C. Sharma and Co. v. Delhi </i><br /> <i>Development Authority in CS(OS) No. 2057A/1996 decided </i><br /> <i>nd</i><br /> <i>on 2</i> <i> July, 2010 in this regard has opined as under: </i><br /> <i>“…The respondent DDA had the choice to appoint an </i><br /> <i>Arbitrator and appointed a technical person rather than a </i><br /> <i>legal person. The sole purpose of appointment of a technical </i><br /> <i>rather than a legal person as an Arbitrator is to take benefit </i><br /> <i>of the special knowledge of the Arbitrator relating to the </i><br /> <i>matters in dispute.” </i><br /> <i>35. In light of the above, the challenge by the petitioner </i><br /> <i>to the findings of the Arbitrator under Claim No. 5 has no </i><br /> <i>force and this Court is not inclined to interfere with the said </i><br /> <i>findings.” </i><br /> <b><i>(Emphasis Supplied) </i></b><br /> <b>73.</b> <b> </b> The Arbitrator‟s view is both possible and reasonable and interference is <br /> unwarranted. Accordingly, the award on Claim No. 2, granting <br /> reimbursement of increased taxes and duties under Clause No. 38 of the <br /> GCC, rests on a tenable interpretation of the Contract. <br /> <b><i>Claim No. 3: Reimbursement of increase in taxes and duties under </i></b><br /> <b><i>Clause 20 and 19B iv (b) of GCC of Contract (Minimum Wages Act). </i></b><br /> <b>74.</b> <b> </b> The Claim No. 3 pertains to reimbursement of additional expenditure <br /> Digitally Signed<br /> By:MAYANK<br /> Signing Date:09.04.2026<br /> 18:31:43<br /> <b>O.M.P. (COMM) 337/2017</b> <b>Page 49 of 82</b> <br /><br /> <br /> incurred by the respondent on account of increases in statutory payments <br /> of minimum wages and other statutory obligations. The respondent has <br /> substantiated this claim by relying on Clause No. 20 of the GCC, which <br /> obliges the respondent to comply with the Minimum Wages Act, 1948, <br /> and other labour laws, read with Clause No. 19B(iv)(b) of the GCC. The <br /> Arbitrator accepted the contentions of the respondent and allowed the <br /> claim. <br /> <b>75.</b> <b> </b> Apropos this Claim, the petitioner has raised two-fold contentions. <br /> Firstly, the Arbitrator has committed grave error by basing his decision <br /> on Clause No. 38 of the GCC, despite the fact that the respondent itself <br /> has not claimed the amount under Clause No. 38 of the GCC. Secondly, <br /> the respondent relied on Clause 10CC of CPWD contracts for <br /> quantification and the same was treated as correct by the Arbitrator. <br /> <b>76.</b> <b> </b> Additionally, the petitioner also relies upon paragraph No. 3, Volume IV <br /> of “Preamble to Bill of Quantities” to contend that the rates quoted are <br /> not amenable to change for any reason, the paragraph No. 3 reads as <br /> under: <br /> <i>“3. Rates quoted shall be firm and shall not be subject to </i><br /> <i>any price variation due to increase in labour wages, cost of </i><br /> <i>material etc., or any other price variations due to any </i><br /> <i>reason whatsoever whether during the stipulated period of </i><br /> <i>execution or during the extended period of completion if </i><br /> <i>any.” </i><br /> <b>77.</b> <b> </b> At this stage, it is pertinent to see Clause No. 20 and 19B(iv)(b) of the <br /> GCC and the same read as under: <br /> <i>“ Clause 19B Payment of wages: </i><br /> <i>Payment of wages: </i><br /> <i>… </i><br /> Digitally Signed<br /> By:MAYANK<br /> Signing Date:09.04.2026<br /> 18:31:43<br /> <b>O.M.P. (COMM) 337/2017</b> <b>Page 50 of 82</b> <br /><br /> <br /> <i>(iv.)... </i><br /> <i>(b). Under the provision of Minimum Wages (Central) </i><br /> <i>Rules, 1950, the contractor is bound to allow to the labours </i><br /> <i>directly or indirectly employed in the works one day rest for </i><br /> <i>6 days continuous work and pay wages at the same rate as </i><br /> <i>for duty. In the event of default, the Engineer-in-Charge </i><br /> <i>shall have the right to deduct the sum or sums not paid on </i><br /> <i>account of wages for weekly holidays to any labours and </i><br /> <i>pay the same to the persons entitled thereto from any money </i><br /> <i>due </i> <i>to the </i> <i>contractor by </i> <i>the </i> <i>Engineer-in-Charge </i><br /> <i>Concerned. </i><br /> <i>In the case of Union Territory of Delhi, however, as the all </i><br /> <i>inclusive minimum daily wages fixed under Notification of </i><br /> <i>the </i> <i>Delhi </i> <i>Administration </i> <i>No. </i> <i>F. </i> <i>12(162) </i> <i>MWO/ </i><br /> <i>DAB/43884-91, dated 31.12.1979 as amended from time to </i><br /> <i>time are inclusive of wages for the weekly day of rest, the </i><br /> <i>question of extra payment for weekly holiday would not </i><br /> <i>arise. </i><br /> <i>…. </i><br /> <i>CLAUSE 20 Minimum Wages Act to be complied with </i><br /> <i>The Contractor Shall comply with all the provisions of the </i><br /> <i>Minimum Wages Act, 1948 and Contract Labour </i><br /> <i>(Regulation and Abolition) Act, 1970, amended from time to </i><br /> <i>time and rules framed thereunder and other labour laws </i><br /> <i>affecting contract labour that may be brought into force </i><br /> <i>from time to time.” </i><br /> <b><i>(Emphasis Supplied) </i></b><br /> Digitally Signed<br /> By:MAYANK<br /> Signing Date:09.04.2026<br /> 18:31:43<br /> <b>O.M.P. (COMM) 337/2017</b> <b>Page 51 of 82</b> <br /><br /> <br /> <b>78.</b> <b> </b> From a perusal of the Clause Nos. 19B(iv)(b) and 20 of the GCC, it is <br /> clear that together both of these clauses cast a mandatory and a <br /> continuing obligation on the respondent to comply with the payment of <br /> statutory wages as revised from time to time. <b> </b><br /> <b>79.</b> <b> </b> The Arbitrator while dealing with this claim has relied on the Clause No. <br /> 38 of the GCC, which provides that if any tax or levy is imposed after the <br /> last stipulated date of receipt of tenders, and the respondent has duly paid <br /> the same, the respondent shall be reimbursed the amount so paid. <b> </b><br /> <b>80.</b> <b> </b> The Arbitrator in this regard made a factual observation that the claimant <br /> had in fact paid minimum wages increased from time to time to the <br /> labour engaged, and had claimed reimbursement from the petitioner. The <br /> respondent had produced supporting documents evidencing such <br /> payments. He further noted that the claimant had quantified its claim by <br /> adopting the labour component and formula analogous to Clause No. <br /> 10CC of the CPWD contract, treating the present Contract as similar in <br /> structure. The Arbitrator granted actual expenditure incurred/actual <br /> payments made to labour in this Claim <i>.</i> The relevant portions of the <br /> Award read as under: <br /> <i>“3.3.1 In Clause 38 of GCC it is stipulated that pursuant to </i><br /> <i>the Constitution (46th amendment Act, 1982), if any further </i><br /> <i>tax or levy is imposed by Statute, after the last stipulated </i><br /> <i>date of receipt of tender including extensions if any and the </i><br /> <i>contractor thereupon necessarily and properly pays such </i><br /> <i>tax/levies, the contractor shall be reimbursed the amount so </i><br /> <i>paid. From the records placed before me it is seen that the </i><br /> <i>Claimant had paid properly such increase in Minimum </i><br /> <i>Wages to labour engaged from time to time during </i><br /> <i>execution of work and requested the Respondent for </i><br /> Digitally Signed<br /> By:MAYANK<br /> Signing Date:09.04.2026<br /> 18:31:43<br /> <b>O.M.P. (COMM) 337/2017</b> <b>Page 52 of 82</b> <br /><br /> <br /> <i>reimbursement of the same as per the provisions of the </i><br /> <i>Contract and based on the supporting documents provided </i><br /> <i>to it. </i><br /> <i>3.3.2 As can be seen from the record, the Claimant had </i><br /> <i>quantified its claim as per Clause 10 CC of the CPWD </i><br /> <i>contract as the present contract is also similar to CPWD </i><br /> <i>contracts in which the labour component for escalation is </i><br /> <i>adopted as 25%. The Claimant has submitted the actual </i><br /> <i>expenditure incurred/ actual payments made to labours in </i><br /> <i>support of above claim. These are the records maintained </i><br /> <i>during execution and certified. Further the subject contract </i><br /> <i>was also prolonged for reasons not attributable to the </i><br /> <i>Claimant and grant of extension of time by the Respondent </i><br /> <i>to this effect was also in place. In the light of above </i><br /> <i>judgments cited the court held that when the state has </i><br /> <i>agreed to reimburse the increased wages than those </i><br /> <i>prescribed or notified at the time of inviting tenders, it is </i><br /> <i>obligatory to reimburse such costs. </i><br /> <i>Award: </i><br /> <i>In view of the above findings, an amount of Rs. </i><br /> <i>1,44,71,999/- as against the claim of Rs. 6,98,63,141/- is </i><br /> <i>awarded on this Claim towards reimbursement of minimum </i><br /> <i>wages of labour, based on records produced .” </i><br /> <b><i>(Emphasis Supplied) </i></b><br /> <b>81.</b> <b> </b> The first objection of the petitioner that the Arbitrator has substantiated <br /> the Award on Clause No. 38 without jurisdiction is misconceived and <br /> unfounded. The fact that the respondent, in its SOC, stressed on Clause <br /> Nos. 20 and 19B(iv)(b) rather than Clause No. 38 does not mean that the <br /> Digitally Signed<br /> By:MAYANK<br /> Signing Date:09.04.2026<br /> 18:31:43<br /> <b>O.M.P. (COMM) 337/2017</b> <b>Page 53 of 82</b> <br /><br /> <br /> Arbitrator was barred from referring to Clause No. 38 as the more <br /> specific reimbursement provision while giving its findings. The <br /> Arbitrator has not granted the claim by relying on something alien to the <br /> Contract, it has merely located the correct clause that gives effect to the <br /> same substantive right as the respondent claimed. Moreover, the <br /> Arbitrator while noting the submissions of the respondent has also noted <br /> a reference to Clause No. 38 of the GCC, the relevant portion of the <br /> Award reads as under: <b> </b><br /> <i>“3.1 Claimant's Submissions: </i><br /> <i>3.1.1 The Claimant submitted that as per Clause 20 of GCC, </i><br /> <i>the Claimant should comply with all the provisions of the </i><br /> <i>Minimum Wages Act, 1948 and the Contract Labour Act, </i><br /> <i>1970 during execution of contract. </i><br /> <i>3.1.2 The Claimant submitted that as per Clause 38 (iii) of </i><br /> <i>GCC if any further tax or levy is imposed by statute after the </i><br /> <i>last stipulated date of receipt of tender including extensions </i><br /> <i>if any, and the Contractor thereupon necessarily and </i><br /> <i>properly pays such taxes/levies, the Contractor shall be </i><br /> <i>reimbursed the amount so paid.” </i><br /> <b><i>(Emphasis Supplied) </i></b><br /> <b>82.</b> <b> </b> Be that as it may, the Arbitrator being the master of the quality and <br /> quantity of the evidence, the appreciation of the terms of the contract is <br /> the sole prerogative of the Arbitrator. <b> </b><br /> <b>83.</b> <b> </b> The second objection raised by the petitioner <i>qua </i> this claim is the <br /> quantification of claim as per Clause No. 10CC of CPWD despite the <br /> subject Contract not being same as CPWD contract. This objection is a <br /> mere reiteration of the objection already raised before the Arbitrator and <br /> duly adjudicated by him. The Arbitrator in the present case has only <br /> Digitally Signed<br /> By:MAYANK<br /> Signing Date:09.04.2026<br /> 18:31:43<br /> <b>O.M.P. (COMM) 337/2017</b> <b>Page 54 of 82</b> <br /><br /> <br /> made a reference to the Clause 10CC of CPWD but has not relied on it, <br /> the Arbitrator relied on the actual records for the purpose of allowing and <br /> awarding the claim. <b> </b><br /> <b>84.</b> <b> </b> Third objection as regards to amenability of quoted rates to change in <br /> view of paragraph 3 of the Preamble to BOQ, this particular objection <br /> was also raised before the Arbitrator. I am of the view that this Clause <br /> cannot be read in isolation and the same requires a comprehensive <br /> reading along with other provisions of the Contract. Merely because <br /> Arbitrator did not refer this particular Clause of the Contract in his <br /> Award, the same cannot be used as a ground to assail the Award, when <br /> the view taken by the Arbitrator is plausible view and based on cogent <br /> reasons and evidence. <b> </b><br /> <b>85.</b> <b> </b> Moreover, the reliance placed by the respondent on the judgment of <br /> <b><i>Associated Construction Co. (Supra) </i></b> is also well founded, as the dispute <br /> adjudicated in that matter squarely substantiates the decision of the <br /> Arbitrator in the present matter. The findings of the Arbitrator with <br /> respect to quantum of the Claim are based on actual expenditure <br /> incurred. Thus, the same does not warrant any interference by this Court. <br /> The relevant paragraphs of the aforesaid judgment are already <br /> reproduced in the paragraph No. 72 of this judgment. <b> </b><br /> <b>86.</b> <b> </b> To my mind, the view taken by the Arbitrator is a correct view based on <br /> appreciation facts, which cannot be reappreciated by this Court under <br /> Section 34 of the Act. Thus, there is no ground established by the <br /> petitioner for warranting interference with the Award. <b> </b><br /> <b><i>Claim No. 4: Extra items of work claimed under Clause 12 of GCC and </i></b><br /> <b><i>Clause 22, 23 of SCC. </i></b><br /> <b>87.</b> <b> </b> The Claim No. 4 pertains to the additional items/substituted items <br /> executed during the execution of works by the respondent, in accordance <br /> Digitally Signed<br /> By:MAYANK<br /> Signing Date:09.04.2026<br /> 18:31:43<br /> <b>O.M.P. (COMM) 337/2017</b> <b>Page 55 of 82</b> <br /><br /> <br /> with the instructions of the petitioner. These extra items of work were <br /> claimed under Clause No. 12 of the GCC and Clause Nos. 22 and 23 of <br /> the Special Conditions of the Contract. <b> </b><br /> <b>88.</b> <b> </b> The Claim No. 4 majorly relates to the payment for two extra executed <br /> items, the first one being washed stone grit plaster with marble chips and <br /> the second one being laying in position the ready-mix concrete (RMC), <br /> and the petitioner has assailed the Award on three broad grounds: <b> </b><br /> i. That the extra items must be claimed in strict compliance of <br /> Clause 12, more specifically Clause No. 12.2 of the GCC. <b> </b><br /> ii. That the dispute survived only with respect to the RMC as the grit <br /> plaster issue had already been approved during the site visit on <br /> 26.11.2016 and paid. The same fact had already been conveyed to <br /> the Arbitrator <i>vide </i> petitioner‟s written arguments submitted during <br /> the arbitral proceedings. <b> </b><br /> iii. That the RMC was already covered by agreement item No. <br /> 3.8/DSR item No. 5.33, and the Arbitrator has erred in relying <br /> upon item No. 5.37 of the DSR. <b> </b><br /> <b>89.</b> <b> </b> From a bare perusal of the submissions and findings recorded by the <br /> Arbitrator, it is clear that the petitioner has only reiterated its arguments <br /> which were contended before the Arbitrator. The relevant portions of the <br /> Award read as under: <b> </b><br /> <i>“4.1 Claimant's Submissions: </i><br /> <i>4.1.1 The Claimant submitted that during the execution of </i><br /> <i>works there were additional items/ substituted items which </i><br /> <i>were executed as per the directions/Instructions of the </i><br /> <i>Respondent. The Claimant submitted that for these extra </i><br /> <i>items of works it had submitted its rates along with detailed </i><br /> <i>rate analysis in accordance to contract clause 12 of GCC. </i><br /> Digitally Signed<br /> By:MAYANK<br /> Signing Date:09.04.2026<br /> 18:31:43<br /> <b>O.M.P. (COMM) 337/2017</b> <b>Page 56 of 82</b> <br /><br /> <br /> <i>The list of extra item for which the rates are not finalized by </i><br /> <i>the Respondent are listed at page 93 of SOC. </i><br /> <i>4.1.2 The Claimant submitted that during the proceedings </i><br /> <i>as per the directions of AT, the Respondent finalized the </i><br /> <i>rates for almost all aforesaid extra items except for only two </i><br /> <i>items pending/disputed. One such item is Washed stone grit </i><br /> <i>plaster at sl.no.6 of the list of extra items at page 93 of SOC </i><br /> <i>and the other is Providing and laying in position Ready Mix </i><br /> <i>Concrete (RMC) at Sl.no.7 of the list of extra items at same </i><br /> <i>page. </i><br /> <i>4.1.3 The Claimant submitted that the external plaster is to </i><br /> <i>be washed stone grit plaster with ordinary stone chips of 10 </i><br /> <i>mm nominal size. But the Claimant has executed the work </i><br /> <i>as per the drawings/ details for finishing works issued by </i><br /> <i>the Respondent at a later date during execution of work, </i><br /> <i>which envisages that the grit plaster with marble chips </i><br /> <i>instead of ordinary stone chips. As the marble chips are </i><br /> <i>much costlier in comparison to ordinary stone chips the </i><br /> <i>Claimant has submitted the extra item along with rate </i><br /> <i>analysis for extra costs towards costlier marble chips, </i><br /> <i>which is a substituted item. </i><br /> <i>4.1.4 The Claimant pleaded that the difference in market </i><br /> <i>rates for ordinary-stone and marble is huge. The Claimant </i><br /> <i>also argued that the rate quoted at the time of submission of </i><br /> <i>bid was based on stone chips only as per item nomenclature </i><br /> <i>intender. The Claimant argued that during execution the </i><br /> <i>claimant was asked to execute the item with marble chips </i><br /> Digitally Signed<br /> By:MAYANK<br /> Signing Date:09.04.2026<br /> 18:31:43<br /> <b>O.M.P. (COMM) 337/2017</b> <b>Page 57 of 82</b> <br /><br /> <br /> <i>and hence it is legitimately entitled for above claim of extra </i><br /> <i>item of grit plastering using marble chips. </i><br /> <i>4.1.5 The Claimant during arguments on 21.11.2016 </i><br /> <i>submitted a revised rate analysis as per then prevailing </i><br /> <i>market rate for the above extra item along with copy of </i><br /> <i>invoices to support the actual procurement rate of marble </i><br /> <i>chips and other materials for finalization of rates. The </i><br /> <i>Claimant submitted that the revised rate is Rs. 398.81 per </i><br /> <i>sqm. whereas it is being paid a rate of Rs. 266.66 per sqm. </i><br /> <i>And it is entitled for difference of rate of Rs.l32.15. </i><br /> <i>4.1.6 The Claimant submitted that another extra item </i><br /> <i>beyond the scope of work executed was of Ready Mixed </i><br /> <i>Concrete (RMC) which was not covered under BOQ item </i><br /> <i>provided in the contract. The Claimant argued that the </i><br /> <i>Respondent had wrongly incorporated the item from DSR </i><br /> <i>(Delhi Schedule of Rates) which does not cover the scope of </i><br /> <i>RMC. The DSR item under which the scope of work </i><br /> <i>executed for RMC is covered under DSR item no. 5.37. </i><br /> <i>4.1.7 The Claimant submitted that the Claimant has used </i><br /> <i>Ready Mixed Concrete manufactured in fully automatic </i><br /> <i>Batching plant and transported the same to job site by </i><br /> <i>transit mixers in accordance to contract clause 40, para </i><br /> <i>P(ii) of Special conditions of contract (SCC). For such an </i><br /> <i>item the rate is catered against item no.5.37 of DSR. The </i><br /> <i>Claimant argued that the item in BOQ under which this was </i><br /> <i>being paid which does not cover the scope of RMC. </i><br /> <i>4.1.8 The Claimant submitted that the scope of work for </i><br /> <i>RMC also includes transit mixer for transporting RMC to </i><br /> Digitally Signed<br /> By:MAYANK<br /> Signing Date:09.04.2026<br /> 18:31:43<br /> <b>O.M.P. (COMM) 337/2017</b> <b>Page 58 of 82</b> <br /><br /> <br /> <i>site of work, having continuous agitated mixer which was </i><br /> <i>not covered under the scope of BOQ item 3.8. The Claimant </i><br /> <i>submitted that as the work was executed by the Claimant in </i><br /> <i>accordance to contract clause 40(P)(ii) of SCC and with </i><br /> <i>similar description of work as per DSR item 5.37, the </i><br /> <i>Claimant has claimed the RMC as substituted item. Hence </i><br /> <i>the Claimant as rightly claimed the aforesaid substituted </i><br /> <i>item as per the terms of the agreement as pleaded by </i><br /> <i>Claimant. The Claimant has submitted the photographs as </i><br /> <i>evidence of deploying RMC plant and Transit mixers for </i><br /> <i>executing concrete by RMC against the Respondent's </i><br /> <i>arguments that no RMC plant was deployed. The Claimant </i><br /> <i>submitted that it submitted a rate analysis for substituted </i><br /> <i>item of RMC for Rs. 4932.69 per Cu.m. and the payment </i><br /> <i>with BOQ rate of Rs. 4695.94 per Cu.m is being paid by the </i><br /> <i>Respondent. The Claimant argued that it is entitled for the </i><br /> <i>difference of these rates. </i><br /> <i>4.2 Respondent's submissions: </i><br /> <i>4.2.1 The Respondent submitted that as per Clause 12 of </i><br /> <i>GCC the Contractor may seek extra rate within fifteen days </i><br /> <i>of receipt of order or occurrence of items claim rates, </i><br /> <i>supported by proper analysis for the work. But the Claimant </i><br /> <i>was neither serious in raising the claims or submitting the </i><br /> <i>required details within 15 days of occurrence as per </i><br /> <i>contract clause and taken his own arbitrary time in </i><br /> <i>submitting the claims in the arbitrary format. </i><br /> <i>4.2.2 The Respondent submitted that the valid claims are </i><br /> <i>being scrutinized and processed soon after receiving the </i><br /> Digitally Signed<br /> By:MAYANK<br /> Signing Date:09.04.2026<br /> 18:31:43<br /> <b>O.M.P. (COMM) 337/2017</b> <b>Page 59 of 82</b> <br /><br /> <br /> <i>desired supporting details from the Claimants and valid </i><br /> <i>claims are approved by the competent authority. But the </i><br /> <i>Claimant has unnecessarily pressurizing the Respondents by </i><br /> <i>claiming arbitrary claims in terms of extra items like using </i><br /> <i>RMC plants instead of BMC plants and extra payments of </i><br /> <i>sand stone cladding on DSR items against BOQ rates etc. </i><br /> <i>4.2.3 The Respondent submitted that the major part of the </i><br /> <i>claimed extra item consists of use of marble chips in Grit </i><br /> <i>plaster amounting to Rs.62.17 lac and use of RMC plants in </i><br /> <i>RCC work amounting to Rs. 84.17 lac. It is mentioned that </i><br /> <i>these claims were raised much after the occurrence of these </i><br /> <i>items at site and also without any supporting base. </i><br /> <i>4.2.4 The Respondent submitted that the item of grit plaster </i><br /> <i>is always done in a particular combination using various </i><br /> <i>type and colour of stone chippings in particular grading. </i><br /> <i>The work is being executed based on approved design and </i><br /> <i>colour combination of stone chippings which includes </i><br /> <i>marble chips also. The Claimants claim for additional </i><br /> <i>amount for using marble chips is denied as the same is also </i><br /> <i>covered under broad category of stone chips as per </i><br /> <i>agreement item no 11.13 which states "top layer 15mm </i><br /> <i>cement plaster 1:0.5:2 (1 cement : 0.5 coarse sand : 2 stone </i><br /> <i>chipping 10 mm nominal size)". </i><br /> <i>4.2.5 On the extra rate for RMC, the Respondent submitted </i><br /> <i>that the concrete was actually prepared using automatic </i><br /> <i>Batch Mix Concrete Plants and shifted to various location </i><br /> <i>of work sites using transit mixers in lieu of direct pumping </i><br /> <i>as specified in agreement item. The Respondent argued that </i><br /> Digitally Signed<br /> By:MAYANK<br /> Signing Date:09.04.2026<br /> 18:31:43<br /> <b>O.M.P. (COMM) 337/2017</b> <b>Page 60 of 82</b> <br /><br /> <br /> <i>the Claimant used the transit mixer for his own convenience </i><br /> <i>and that was neither forced by the Respondents nor </i><br /> <i>beneficial for the progress of work. Also the Respondent </i><br /> <i>argued that the Claimant executed the RCC work using this </i><br /> <i>system and the Respondent allowed this to avoid any </i><br /> <i>hindrance in work. The extra claim is based on another </i><br /> <i>DSR item in which concrete is brought from fully automatic </i><br /> <i>RMC plants being owned by third party and approved for </i><br /> <i>construction by the Client. </i><br /> <i>4.2.6 The Respondent vide its written submissions of </i><br /> <i>arguments dt: 10-4-2017 sent few invoice copies of which </i><br /> <i>are already submitted by Claimant and on record. </i><br /> <i>4.2.7 The Respondent submitted that as there is no deviation </i><br /> <i>from agreement items there should not be any extra claim </i><br /> <i>permitted and hence the claim of the claimant is denied. </i><br /> <i>4.3 Findings of the AT: </i><br /> <i>4.3.1 This Arbitral Tribunal observes that the BOQ item </i><br /> <i>no.13. 72 for "washed stone grit plaster" consist of ordinary </i><br /> <i>stone chips of 10 mm nominal size and not with marble </i><br /> <i>stone chips. On being questioned it is ascertained that </i><br /> <i>nowhere in the tender documents usage of marble chips in </i><br /> <i>the grit plaster was mentioned. Obviously the bidders do </i><br /> <i>quote for this BOQ item is considering stone chips only. The </i><br /> <i>Respondent's instruction to use marble chips in place of </i><br /> <i>stone chips on the later date of execution of work is a </i><br /> <i>deviation to this BOQ item and hence a new rate to be </i><br /> <i>decided as per the terms of the contract. The Claimant is </i><br /> <i>entitled for above claim of extra item of grit plastering using </i><br /> Digitally Signed<br /> By:MAYANK<br /> Signing Date:09.04.2026<br /> 18:31:43<br /> <b>O.M.P. (COMM) 337/2017</b> <b>Page 61 of 82</b> <br /><br /> <br /> <i>marble chips. The Claimant on 21.11.2016 submitted a </i><br /> <i>revised rate analysis based on the actual procurement of </i><br /> <i>marble chips and other materials. The copy of the same has </i><br /> <i>been received by the Respondent. The quantity is not </i><br /> <i>disputed as it is being paid under BOQ item. </i><br /> <i>4.3.2 With regards to other item of Ready Mix Concrete, the </i><br /> <i>Tribunal observers that in the given BOQ item of contract </i><br /> <i>the nomenclature of BOQ does not includes transit mixer </i><br /> <i>for transporting concrete to site of work, having continuous </i><br /> <i>agitated mixer. The Contract BOQ item stipulates as </i><br /> <i>follows: </i><br /> <i>"Providing and laying in position machine hatched, </i><br /> <i>machine mixed and machine vibrated design mix cement </i><br /> <i>concrete of specified grade for reinforced cement concrete </i><br /> <i>work including pumping of concrete to site of laying but </i><br /> <i>excluding the cost of centering...... as per IS: 9103 ....... as </i><br /> <i>per direction of Engineer-in-charge". </i><br /> <i>4.3.3 The DSR item under which the scope of work executed </i><br /> <i>for RMC is covered under DSR item no. 5.37 which </i><br /> <i>stipulates as follows: </i><br /> <i>"DSR item no. 5.37 Providing and laying in position ready </i><br /> <i>mixed M-25 grade concrete for reinforced cement concrete </i><br /> <i>work, using cement content as per approved design mix, </i><br /> <i>manufactured in fully automatic hatching plant and </i><br /> <i>transported to site of work in transit mixer for all leads, </i><br /> <i>having continuous agitated mixer, manufactured as per mix </i><br /> <i>design of specified grade for reinforced cement concrete </i><br /> <i>work including pumping of R.MC. from transit mixer to site </i><br /> Digitally Signed<br /> By:MAYANK<br /> Signing Date:09.04.2026<br /> 18:31:43<br /> <b>O.M.P. (COMM) 337/2017</b> <b>Page 62 of 82</b> <br /><br /> <br /> <i>of laying, excluding the cost of centering........ as per IS: </i><br /> <i>9103 ...... . as per direction of Engineer-in-charge. " </i><br /> <i>4.3.4 Since the Claimant executed the work of scope similar </i><br /> <i>to DSR item no. 5.37 using automatic batching plant and </i><br /> <i>transit mixer having continuous agitated mixer for </i><br /> <i>transporting the RMC to site , the Claimant is entitled for </i><br /> <i>the rate as per DSR item no. 5.37 as claimed . The quantity </i><br /> <i>is not disputed as it is being paid under BOQ item. </i><br /> <i>4.3.5 The quantification based on the revised rates is </i><br /> <i>presented in pages 9109 and 9110 of Claimant's </i><br /> <i>submissions. This is amounting to total of Rs.1,18,89,226/-. </i><br /> <i>Award: </i><br /> <i>In the light of above findings the Claimant is entitled to </i><br /> <i>payment for these extra items. In the considered opinion of </i><br /> <i>Tribunal the Claim of the Claimant for payment ofthese </i><br /> <i>extra </i> <i>items </i> <i>is </i> <i>justified. </i> <i>Accordingly </i> <i>I </i> <i>award </i><br /> <i>Rs.1,18,89,226/- on this claim.” </i><br /> <b><i>(Emphasis Supplied) </i></b><br /> <b>90.</b> <b> </b> The petitioner‟s challenge on the ground of non-compliance of Clause <br /> No. 12.2 of the GCC stating the claims as “afterthought” is misplaced. <br /> Most of the extra items were finalised during the proceedings, and that <br /> only these two items were pending. For approval of grit plaster, the <br /> respondent submitted revised analysis with invoices dated 21.11.2016. <br /> For RMC, a detailed rate analysis for the substituted item was submitted <br /> and considered but the same was disputed. Clause No. 12.2 of the GCC <br /> prescribes that, for substituted/extra items exceeding the specified limits, <br /> the contractor “may within fifteen days” claim revision of rates supported <br /> Digitally Signed<br /> By:MAYANK<br /> Signing Date:09.04.2026<br /> 18:31:43<br /> <b>O.M.P. (COMM) 337/2017</b> <b>Page 63 of 82</b> <br /><br /> <br /> by proper analysis, whereafter the Engineer‑in‑Charge is to fix rates on <br /> the basis of market rates. Clause No. 12.2 of the GCC reads as under: <b> </b><br /> <i>“12.2 Deviation, Extra Items and Pricing </i><br /> <i>In the case of extra item (s), the contractor may within </i><br /> <i>fifteen days of receipt of order or occurrence of the item(s) </i><br /> <i>claim rates, supported by proper analysis, for the work and </i><br /> <i>the Engineer-in-Charge shall within one month of the </i><br /> <i>receipt of the claims supported by analysis, after giving </i><br /> <i>consideration to the analysis of the rates submitted by the </i><br /> <i>contractor, determine the rates on the basis of the market </i><br /> <i>rates and the contractor shall be paid in accordance with </i><br /> <i>the rates so determined…” </i><br /> <b>91.</b> <b> </b> The Arbitrator has considered similar Clause of the Contract namely <br /> Clause No. 38 of the GCC and held that these kind of Clauses are <br /> directory as no consequences for non-compliance are prescribed. <br /> Additionally, the invoices, were duly submitted by the respondent and <br /> there were no dispute to their authenticity. Thus, such non-compliance of <br /> a procedural requirement cannot render a valid claim wrong. <b> </b><br /> <b>92.</b> <b> </b> Apropos the second ground i.e. the issue with regards to the grit plaster <br /> component already being approved and paid, is misconceived and cannot <br /> be used to assail the Award. <b> </b><br /> <b>93.</b> <b> </b> The Arbitrator‟s reasoning <i>qua </i> the issue of grit plaster is that the <br /> Contract rate for “washed stone grit plaster” covered plaster using <br /> ordinary stone chips, and everyone bid on that basis, but later the <br /> department asked the respondent to use much costlier marble chips <br /> instead, which changed the item into a different, higher specification job. <br /> Since this was a deviation ordered by the petitioner, the Contract required <br /> a fresh rate to be fixed, and the respondent did submit a revised rate <br /> Digitally Signed<br /> By:MAYANK<br /> Signing Date:09.04.2026<br /> 18:31:43<br /> <b>O.M.P. (COMM) 337/2017</b> <b>Page 64 of 82</b> <br /><br /> <br /> analysis on 21.11.2016 with invoices for marble chips, which the <br /> department received, while the quantity of work itself was never <br /> disputed, so the Arbitrator treated the marble chip work as an extra item <br /> and granted the claim accordingly. <b> </b><br /> <b>94.</b> <b> </b> Therefore, the challenge of the petitioner does not shake the reasoning of <br /> the Arbitrator, because what the Award has approved is the existence and <br /> quantum of a substituted item (marble chips) with a documented rate <br /> analysis, and not a second payment for work already compensated at <br /> BOQ. Moreover, the petitioner failed to place on record any evidence <br /> that the payment for the said item has been made twice. Hence, this Court <br /> cannot reappreciate the cogent quantification and analysis which is <br /> undertaken by the Arbitrator. <b> </b><br /> <b>95.</b> <b> </b> The petitioner‟s challenge with respect to the RMC is also unfounded, <br /> misconceived and a mere reiteration of the contentions as raised before <br /> the Arbitrator, the Arbitrator followed a clear, stepwise analysis for <br /> adjudication, he first looked at the BOQ concrete item, which only covers <br /> normal machine mixed concrete pumped to the site and says nothing <br /> about using transit mixers. He then compared this with DSR 5.37, which <br /> specifically covers ready mix concrete made in an automatic plant and <br /> brought to site in transit mixers. Based on evidence such as photos and <br /> the respondent‟s explanation, he held that the respondent had actually <br /> used an RMC plant and transit mixers, so the work matched DSR 5.37 <br /> rather than the simpler BOQ item. On that basis, he applied the DSR 5.37 <br /> rate as a substituted rate but kept the quantity the same, as it was not in <br /> dispute. Thus, the Arbitrator has relied on evidence placed on record to <br /> conclude that the scope of work executed by the respondent is that which <br /> is covered by DSR 5.37. The view of the Arbitrator is plausible and <br /> based on reasons. <b> </b><br /> Digitally Signed<br /> By:MAYANK<br /> Signing Date:09.04.2026<br /> 18:31:43<br /> <b>O.M.P. (COMM) 337/2017</b> <b>Page 65 of 82</b> <br /><br /> <br /> <b>96.</b> <b> </b> In these circumstances, the Award on Claim No. 4 is reasoned and <br /> evidence based. It does not disclose any perversity, patent illegality or <br /> disregard of the contractual terms, and accordingly, no interference is <br /> warranted under Section 34 of the Act. <br /> <b><i>Claim No. 5: Revised rates for individual items of work the quantities </i></b><br /> <b><i>of which had exceeded beyond limit. </i></b><br /> <b>97.</b> <b> </b> The Claim No. 5 pertains to the payment at revised rates for certain items <br /> where the executed quantities exceeded the contractual deviation limits <br /> prescribed under Clause No. 12 of GCC, which is 30% of the trade, and <br /> beyond this limit the respondent is entitled to seek revision of rates for <br /> particular trade/items i.e. the prevailing market rates. Under this <br /> mechanism, the original BOQ rate ceases to apply and the respondent can <br /> seek revision of the rates (market rates) for that particular item/trade. <br /> <b>98.</b> <b> </b> In this backdrop, the petitioner has challenged the Award of the <br /> Arbitrator apropos this claim on the ground that revised rates apply only <br /> for deviation of quantities beyond the deviation limit and the same needs <br /> to be claimed strictly as per the Clause No. 12.4, which was not claimed <br /> by the respondent despite being fully aware of the scheme of clause 12. <br /> Further, the Award apropos this claim is also assailed on the ground that <br /> the Arbitrator has inconsistently first used the word “trade” to mean <br /> “building trade” and then stated the word to be vague, to proceed to <br /> award the claim on flawed quantification without scrutinizing each item <br /> or applying the Bhopal Cost Index. The petitioner has relied upon a <br /> similar arbitral proceeding <i>qua </i> Package-1 of AIIMS Rishikesh to buttress <br /> its submission that the term “trade” refers to the subhead for allowing the <br /> market rate under clause 12 of the agreement. The relevant Clause No. <br /> 12.4 reads as under: <br /> Digitally Signed<br /> By:MAYANK<br /> Signing Date:09.04.2026<br /> 18:31:43<br /> <b>O.M.P. (COMM) 337/2017</b> <b>Page 66 of 82</b> <br /><br /> <br /> <i>“12.4 GCC: The Contractor shall send to the Engineer-in-</i><br /> <i>Charge once in every three months, an upto date account </i><br /> <i>giving complete details of all claims for additional payments </i><br /> <i>to which the contractor may consider himself entitled and of </i><br /> <i>all additional work ordered by the Engineer in Charge </i><br /> <i>which he has executed during the preceding quarter failing </i><br /> <i>which the contractor shall be deemed to have waived his </i><br /> <i>right. However, the Superintending Engineer may authorize </i><br /> <i>consideration of such claims on merits. " </i><br /> <b>99.</b> <b> </b> At this stage it is important to peruse the relevant portions of the Award <br /> and findings, which read as under: <br /> <i>“5.3 Findings of the AT: </i><br /> <i>5.3.1 </i> <i>In </i> <i>the </i> <i>contract </i> <i>the </i> <i>Clause-12 </i> <i>is </i> <i>on </i><br /> <i>"Deviations/Variations Extent and Pricing ".Under this sub </i><br /> <i>Clause 12.2 is on "Deviation, Extra items and Pricing ". In </i><br /> <i>this the terms and conditions are stipulated in subhead </i><br /> <i>clause "Deviation, Deviated Quantities, Pricing". This </i><br /> <i>clause stipulates that in case the contract items exceed the </i><br /> <i>limits laid down in Schedule - F, the contractor can claim </i><br /> <i>revision of rates supported by the proper analysis of rates </i><br /> <i>for the work in excess of the above mentioned limits. 5.3.2 </i><br /> <i>The Arbitral Tribunal observers that the provisions in the </i><br /> <i>contract agreement for deviation limit under Clause -12 of </i><br /> <i>Schedule F which reads as below: Clause 12: </i><br /> <i>12.2 & 12.3 </i><br /> <i>Deviation Limit beyond which clauses </i><br /> <i>12.2 & 12.3 shall apply for building work. </i> <i>30% </i> <i>of </i><br /> <i>trade </i><br /> Digitally Signed<br /> By:MAYANK<br /> Signing Date:09.04.2026<br /> 18:31:43<br /> <b>O.M.P. (COMM) 337/2017</b> <b>Page 67 of 82</b> <br /><br /> <br /> <i>5.3.3 The word trade has a meaning based on the context of </i><br /> <i>usage. The Dictionary meaning of trade refers to </i><br /> <i>commercial activity. In general practice it relates to the </i><br /> <i>business. For instance, when a phrase like "trade practice" </i><br /> <i>is used, it refers to the practice prevailing in a particular </i><br /> <i>kind of industry or trade. </i><br /> <i>5.3.4 Looking from the said angle, the reference to "Trade" </i><br /> <i>can only be construed as a reference to the construction </i><br /> <i>work as a whole that is involved in the subject contract. </i><br /> <i>What it matters most is how the parties understood and </i><br /> <i>meant by the word "Trade" while entering in to contract </i><br /> <i>with respect to deviation limits specified in schedule-F for </i><br /> <i>operation of Clause -12. There is no definition of the word </i><br /> <i>'Trade' in the contract agreement or how it is structured for </i><br /> <i>deviation in quantities. The Claimant's arguments are that </i><br /> <i>the deviation limit is on individual item quantities while the </i><br /> <i>Respondent during arguments stated that the limit is </i><br /> <i>applicable for group of subhead items in BOQ. It is clear </i><br /> <i>that the issue is of interpretation. When any word/phrase </i><br /> <i>built in any clause gives scope for multiple interpretations </i><br /> <i>there seems to be an ambiguity which needs to be </i><br /> <i>interpreted. </i><br /> <i>Award: </i><br /> <i>After carefully considering the facts, contractual provisions, </i><br /> <i>evidence on record and the legal principles, the Arbitral </i><br /> <i>Tribunal is of the view that deviation limit needs to be </i><br /> <i>applied on item quantities individually. Hence this Claim is </i><br /> <i>awarded in favour of the Claimant. </i><br /> Digitally Signed<br /> By:MAYANK<br /> Signing Date:09.04.2026<br /> 18:31:43<br /> <b>O.M.P. (COMM) 337/2017</b> <b>Page 68 of 82</b> <br /><br /> <br /> <i>The abstract quantification of claim presented is for Rs. </i><br /> <i>4,23,76,331/-in pages 863 to 875 of Claimant's submissions </i><br /> <i>CV-6 . The item quantities are not disputed. As can be seen </i><br /> <i>from quantification details presented, for most of the </i><br /> <i>deviated items beyond the limits, the rates are claimed </i><br /> <i>based on DSR schedule rates pertaining to 2012, the period </i><br /> <i>of execution of work. For some items of deviated quantities, </i><br /> <i>market rates claimed for deviated quantities. Since there is </i><br /> <i>no evidence submitted for market rates (MR), the revised </i><br /> <i>rates cannot be considered for such items. Deleting such </i><br /> <i>MR items, the quantification works out to Rs.4,10,11,761 /-. </i><br /> <i>Hence an amount ofRs.4,10,11,761/- is awarded on this </i><br /> <i>Claim.” </i><br /> <b><i>(Emphasis Supplied) </i></b><br /> <b>100.</b> <b> </b> The first ground to assail this claim of the Award i.e. non-compliance of <br /> the Clause No. 12.4 of the GCC, is misconceived as the Arbitrator has <br /> already held similar Clause No. 38 of the GCC to be directory, the Clause <br /> No. 12.4 being similar in nature is also directory. Hence, the same cannot <br /> be used as a ground to defeat an otherwise substantive and legitimate <br /> claim. <br /> <b>101.</b> <b> </b> In the second ground regarding the interpretation of the term “trade”, the <br /> respondent argued that the term should be interpreted to mean individual <br /> BOQ items, while the petitioner wanted it to be interpreted as broader <br /> BOQ sub-heads. The Arbitrator categorically observed that the term is <br /> not defined in the contract and is ambiguous and both interpretations are <br /> tenable. However, the Arbitrator proceeded to apply it to individual item <br /> quantities by relying on facts, contractual provisions, evidence on record <br /> and the legal principles. The Arbitrator deduced this interpretation by <br /> Digitally Signed<br /> By:MAYANK<br /> Signing Date:09.04.2026<br /> 18:31:43<br /> <b>O.M.P. (COMM) 337/2017</b> <b>Page 69 of 82</b> <br /><br /> <br /> relying on evidence and making a finding as to how the parties <br /> understood the term before and during the execution of the Contract. <br /> <b>102.</b> <b> </b> To my mind, this reasoning of the Arbitrator strongly rooted in <br /> appreciation of evidence by the Arbitrator himself. The view of the <br /> Arbitrator is a plausible one supported by evidence and the same cannot <br /> be reappreciated by this court under Section 34 of the Act. <br /> <b>103.</b> <b> </b> The findings of the Arbitrator <i>qua</i> the quantification of the Claim are also <br /> cogent and reasonable. The respondent‟s computation was of Rs. <br /> 4,23,76,331/‑, supported by detailed tables, and importantly the item <br /> quantities themselves were not disputed by the petitioner. For most of the <br /> excess quantities beyond the 30% limit, the respondent had based its <br /> revised rates on the DSR schedule for 2012. For some items it had <br /> claimed market rates without submitting corroborating evidence. The <br /> Arbitrator expressly refused to accept these unsupported market rates, <br /> and removed those items from the computation and arrived at Rs. <br /> 4,10,11,761/‑, which it awarded. <br /> <b>104.</b> <b> </b> In this view of the matter, the quantification of claim by the Arbitrator by <br /> applying DSR 2012, is not merely approval of the claim as filed by the <br /> petitioner but there is proper application of mind on part of the Arbitrator <br /> thereby, rejecting the unsubstantiated market rates. The Arbitrator has <br /> made categorical cogent findings and the petitioner by way of raising this <br /> challenge to the Award more particularly this claim is trying to persuade <br /> this court for reappreciation of its evidence, which is not permissible <br /> under Section 34 of the Act. <br /> <b><i>Claim No. 10: Loss on locked up deposits Bank Guarantees due to </i></b><br /> <b><i>Prolongation of Contract. </i></b><br /> <b>105.</b> <b> </b> Claim No. 10 pertains to the loss caused due to locked up performance <br /> bank guarantee due to the prolongation of the Contract. The respondent <br /> Digitally Signed<br /> By:MAYANK<br /> Signing Date:09.04.2026<br /> 18:31:43<br /> <b>O.M.P. (COMM) 337/2017</b> <b>Page 70 of 82</b> <br /><br /> <br /> claimed that since the delay in execution is not attributable to it, the loss <br /> sustained by it like loss of interest, cost incurred on extension, etc. was <br /> payable. <br /> <b>106.</b> <b> </b> The petitioner‟s objection is that the Clause No. 1, specifically Clause <br /> No. 1(ii) of the GCC provides that the performance bank guarantee <br /> needed to be kept valid up to the stipulated date of completion plus 60 <br /> days and thereafter the same needed to be returned without any interest. <br /> Thus, the petitioner is not liable to pay any interest/charges. The Clause <br /> No. 1(ii) of the GCC reads as under: <br /> <i>“The Performance Guarantee shall be initially valid up to </i><br /> <i>the stipulated date of completion plus 60 days beyond that. </i><br /> <i>In case the time for completion of work gets enlarged the </i><br /> <i>contractor shall get the validity of Performance Guarantee </i><br /> <i>extended to cover such enlarged time for completion of </i><br /> <i>work. After recording of the completion certificate for the </i><br /> <i>work by the client, the Performance guarantee shall be </i><br /> <i>returned to the contractor, without any interest.” </i><br /> <b>107.</b> <b> </b> The operative portions of the Award with respect to Claim No. 10 reads <br /> as under: <br /> <i>“10.3 Findings of the AT </i><br /> <i>10.3.1 …. </i><br /> <i>10.3.2 As per the above provision in the contract the </i><br /> <i>Claimant has to keep the Performance Guarantee valid till </i><br /> <i>the completion of work plus 60days beyond that. </i><br /> <i>I0.3.3 Since the contract period got prolonged due to </i><br /> <i>reasons not attributable to Claimant against stipulated </i><br /> <i>period of 15months,the Claimant is to be compensated for </i><br /> Digitally Signed<br /> By:MAYANK<br /> Signing Date:09.04.2026<br /> 18:31:43<br /> <b>O.M.P. (COMM) 337/2017</b> <b>Page 71 of 82</b> <br /><br /> <br /> <i>the additional expenditure incurred on account of extension </i><br /> <i>of BG in the extended period of contract as claimed. </i><br /> <i>Award: </i><br /> <i>After deliberating in detail and considering all the </i><br /> <i>submissions of the parties, I am of the view that the </i><br /> <i>Claimant is entitled for reimbursement of additional </i><br /> <i>expenditure incurred on account of commission charges for </i><br /> <i>extension of Performance BG in the extended period of </i><br /> <i>contract.” </i><br /> <b>108.</b> <b> </b> The Award, notes that the bank guarantee was in fact kept alive beyond <br /> the contractually contemplated period solely because of prolongation not <br /> attributable to the respondent. In treating those additional charges as a <br /> compensable component for the delay in execution, the Arbitrator has <br /> only made a logical/reasonable/lawful conclusion. The same is supported <br /> by the observations made in the above sections of this judgment that <br /> compensation is not barred unless clearly prohibited by the contractual <br /> term. Therefore, the reasoning of the Arbitrator is well founded and does <br /> not disclose any patent illegality or any other ground warranting <br /> interference under Section 34 of the Act. <br /> <b><i>Claim No. 12: Escalation Amount on material payable due to </i></b><br /> <b><i>prolongation of Contract. </i></b><br /> <b>109.</b> <b> </b> This claim pertains to price escalation due to the prolonged period of the <br /> Contract. The respondent claimed that it is entitled to such price <br /> escalation because there is substantial increase in burden due to the <br /> increased cost of construction material. <br /> <b>110.</b> <b> </b> The petitioner assails the Award of this claim on the ground that the <br /> claim is in violation of the terms of the Contract. Paragraph No. 3 of <br /> “preamble to the bill of quantities” stipulates that the quoted rates shall <br /> Digitally Signed<br /> By:MAYANK<br /> Signing Date:09.04.2026<br /> 18:31:43<br /> <b>O.M.P. (COMM) 337/2017</b> <b>Page 72 of 82</b> <br /><br /> <br /> not be subject to any variation whatsoever including the extended period, <br /> the relevant paragraph reads as under: <br /> <i>“Rates quoted shall be firm and shall not be subject to any </i><br /> <i>price variation due to increase in labour wages, cost of </i><br /> <i>materials, etc., or any other price variations due to any </i><br /> <i>reason whatsoever whether during the stipulated period of </i><br /> <i>execution or during the extended period of completion if </i><br /> <i>any.” </i><br /> <b>111.</b> <b> </b> The relevant portions of the Award with respect to Claim No. 12, read as <br /> under: <br /> <i>“12.3 Findings of the AT : </i><br /> <i>12.3.1 I have carefully considered the above arguments of </i><br /> <i>both the parties, the documents and evidence produced </i><br /> <i>before me. </i><br /> <i>12.3.2 The date of commencement of the work was on </i><br /> <i>27.05.2010. The time for completion was 15months and the </i><br /> <i>schedule date of completion was 26.08.2011. In the Award </i><br /> <i>against Claim no. 1, it has been held that the delay causes </i><br /> <i>are not attributable to Claimant. </i><br /> <i>12.3.3 This claim is for escalation amount on material due </i><br /> <i>to prolongation of contract worked out in the prolonged </i><br /> <i>period up to 42nd RA bill submitted (March 2015). The </i><br /> <i>detail of claim has been given by the Claimant in CV -27 of </i><br /> <i>the Statement of Claims. </i><br /> <i>12.3.4 As can be seen from the records, as per terms of the </i><br /> <i>contract Schedule F Clause 10CC is not applicable since </i><br /> <i>the contract stipulated duration is 15 months. The Hon'ble </i><br /> <i>Supreme Court in the case of Union of India Vs. Saraswat </i><br /> Digitally Signed<br /> By:MAYANK<br /> Signing Date:09.04.2026<br /> 18:31:43<br /> <b>O.M.P. (COMM) 337/2017</b> <b>Page 73 of 82</b> <br /><br /> <br /> <i>Trading Agency and Ors. (2009) 16 SCC 504 has </i><br /> <i>categorically held that escalation is a normal incidence in a </i><br /> <i>prolonged contract and even in the absence of an escalation </i><br /> <i>clause, such escalation is payable. The Claimant has </i><br /> <i>worked out price escalation for materials following the </i><br /> <i>formulae based methodology as per Clause 10(CC) of </i><br /> <i>CPWD with base price and current indices of whole sale </i><br /> <i>price indices published. </i><br /> <i>12.3.5 It is a general industry practice that formula based </i><br /> <i>price escalation provisions are commonly adopted in </i><br /> <i>construction contracts to compensate for increase for rise in </i><br /> <i>prices in materials. Generally for building contracts CPWD </i><br /> <i>and such public departments provide formulae based price </i><br /> <i>adjustment provisions popularly referred as escalation </i><br /> <i>clauses. The formula based methodology do consist of </i><br /> <i>component wise weightage for materials, labour based on </i><br /> <i>the type of construction. For building works for the cement , </i><br /> <i>steel the escalation is considered separately and for rest of </i><br /> <i>the construction materials under the head 'other materials' </i><br /> <i>a component of 30% to 40% provided for and around 25% </i><br /> <i>considered as labour component. </i><br /> <i>But the Claimant has claimed 75% component stating that </i><br /> <i>for cement, steel he did not claim such escalation separately </i><br /> <i>and included in this weightage component. Considering the </i><br /> <i>facts on record 40% component for all materials portion put </i><br /> <i>together is found genuine and justified. The quantification </i><br /> <i>of formulae based escalation with 75% component </i><br /> <i>weightage is not disputed. Thus the amount payable with </i><br /> Digitally Signed<br /> By:MAYANK<br /> Signing Date:09.04.2026<br /> 18:31:43<br /> <b>O.M.P. (COMM) 337/2017</b> <b>Page 74 of 82</b> <br /><br /> <br /> <i>40% component weightage for materials can be calculated </i><br /> <i>proportionately. </i><br /> <i>Award: </i><br /> <i>After deliberating in detail and considering all the </i><br /> <i>submissions of the parties, I am of the view that the </i><br /> <i>Claimant is entitled for price escalation on materials due to </i><br /> <i>prolongation of contract. The Claim on escalation of </i><br /> <i>materials is awarded with a component of 40% weightage </i><br /> <i>in the formula exhibited. Thus the amount payable to </i><br /> <i>Claimant towards price escalation on materials works out </i><br /> <i>to Rs.6,21,69,860/-.” </i><br /> <b>112.</b> <b> </b> The Arbitrator recorded that the causes of delay were not attributable to <br /> the respondent, and that Claim No. 12 is confined to escalation in <br /> nd <br /> material costs during the prolonged period up to the 42 RA bill i.e. <br /> March 2015. Thereafter, relying on the Hon‟ble Supreme Court‟s <br /> decision in <b><i>Saraswat Trading Agency (Supra)</i></b> , the Arbitrator noted that <br /> escalation is a normal incident of a prolonged contract and that, even in <br /> the absence of a formal escalation Clause, a respondent can in principle <br /> be compensated where the contract period stands substantially extended <br /> for reasons not attributable to it. <br /> <b>113.</b> <b> </b> The petitioner‟s challenge to the quantification of claim by application of <br /> 10CC of CPWD, is also misconceived. Despite, the scheduled timeline <br /> for execution of the Contract i.e. 15 months rendering Clause 10CC of <br /> CPWD inapplicable, the Arbitrator used this relevant formula based <br /> methodology as a fair quantification method for escalation for materials <br /> during the prolonged period, wherein delays were not attributable to the <br /> respondent. Additionally, the reduction of claimed 75% component to <br /> 40% reflects reasoned approach which is based on industry practice. <br /> Digitally Signed<br /> By:MAYANK<br /> Signing Date:09.04.2026<br /> 18:31:43<br /> <b>O.M.P. (COMM) 337/2017</b> <b>Page 75 of 82</b> <br /><br /> <br /> Thus, no interference is warranted with this cogent reasoning of the <br /> Arbitrator. <br /> <b>114.</b> <b> </b> The reasoning of the Arbitrator is not in violation of the terms of the <br /> Contract and is supported by law. The Award of this claim is not <br /> suffering from any vice enumerated under Section 34 of the Act, thereby <br /> warranting interference. <br /> <b><i>Claim No. 13 and 14: Interest on delay in payment of RA bills and </i></b><br /> <b><i>Claim Nos. 2 to 12. </i></b><br /> <b>115.</b> <b> </b> The Claim No. 13 pertains to the interest on delayed payments of RA <br /> bills and the same was adjudicated by the Arbitrator with Claim No. 1 in <br /> the final Award. The relevant findings of the Arbitrator read as under: <br /> <i>“AWARD:- </i><br /> <i>After deliberating in detail and considering all the </i><br /> <i>submissions of parties, documents and evidence filed, the </i><br /> <i>Tribunal awards that the withheld amount of Rs. </i><br /> <i>2,95,79,465/- on account of non achievement of milestones </i><br /> <i>from the Claimants bill shall be refunded to the Claimants. </i><br /> <i>The Claimants have claimed interest @ 15 % P A for the </i><br /> <i>above claim amount separately under Claim no.13. From </i><br /> <i>the records placed before me I find that the amount was </i><br /> <i>withheld while releasing payments for 33,34 th RA bills on </i><br /> <i>18-2-2014. The Tribunal Awards the simple interest at a </i><br /> <i>rate 12% per annum on the above amount to be refunded </i><br /> <i>from the date of recovery i.e.l8.2.20 14 to the date of the </i><br /> <i>award.”</i> <br /> <b>116.</b> <b> </b> The Claim No. 14 pertains to the payment of <i>pendente lite</i> interest on <br /> the claims raised by the claimant and adjudicated in the final Award <br /> Digitally Signed<br /> By:MAYANK<br /> Signing Date:09.04.2026<br /> 18:31:43<br /> <b>O.M.P. (COMM) 337/2017</b> <b>Page 76 of 82</b> <br /><br /> <br /> i.e., from Claim Nos. 2 to 12 at the rate of 10% per annum. In this <br /> regard the relevant portions of the Award read as under: <br /> <i>“Claim No. 14: </i><br /> <i>Loss of Interest on the Claimed amounts for Claims no.2 </i><br /> <i>to 12@ 10% per annum: </i><br /> <i>14.1 Claimant's Submissions: The Claimant submitted </i><br /> <i>that it had been deprived of legitimate entitlements which </i><br /> <i>were due to it at appropriate time. According to the law, </i><br /> <i>any party which is deprived of the use of money has a </i><br /> <i>right to be compensated for deprivation. The Claimant </i><br /> <i>submitted that the Section 31 (7) of the Arbitration act </i><br /> <i>empowers the Arbitrator to award past , pendent-lite and </i><br /> <i>future interest also. The Claimant cited the case law of </i><br /> <i>Indian Hume Pipe Co. Ltd Vs State of Rajasthan (2009), </i><br /> <i>10 SCC 187 on the issue. The Claimant submitted that it </i><br /> <i>claimed 10% interest on Claims no. 2 to I2 @ 10% PA </i><br /> <i>from cause of action and future interest 18% P A. </i><br /> <i>14.2 Respondent's Submissions: </i><br /> <i>The Respondent submitted that this claim is not </i><br /> <i>admissible in view of the specific reference to the terms </i><br /> <i>and conditions of the contract which have been referred </i><br /> <i>by Respondent in refuting the Claims in SOD. Further the </i><br /> <i>Respondent submitted that the interest claim is not </i><br /> <i>justified and not agreed to. </i><br /> <i>Award: </i><br /> <i>I. A simple interest of 10% per annum, pendent-lite i.e. </i><br /> <i>from date of invocation of arbitration, 13.I2.20I4 to the </i><br /> Digitally Signed<br /> By:MAYANK<br /> Signing Date:09.04.2026<br /> 18:31:43<br /> <b>O.M.P. (COMM) 337/2017</b> <b>Page 77 of 82</b> <br /><br /> <br /> <i>date of the Award is awarded on the awarded amounts for </i><br /> <i>Claims no. 2, 3,4,5, 10 and I2.” </i><br /> <b><i>(Emphasis Supplied) </i></b><br /> <b>117.</b> <b> </b> The petitioner assails the award of <i>pendente lite</i> interest for Claim No. 2, <br /> 3, 4, 5, 10, and 12 under Claim No. 14 and interest awarded on delay in <br /> payments of RA bills adjudicated under Claim No. 13, on the ground that <br /> the same is in violation of the judgment delivered by the Hon‟ble <br /> Supreme Court in the case of <b><i>M/S Krafters Engineering & Leasing Pvt. </i></b><br /> <b><i>Ltd. (Supra)</i></b> , and also in violation of the conditions of the Contract. The <br /> Contract does not contemplate award of interest and the same is liable to <br /> be set aside. <br /> <b>118.</b> <b> </b> It is pertinent to note that Section 31(7)(a) of the Act empowers an <br /> arbitral tribunal, unless otherwise agreed by the parties, to award interest <br /> at such rate as it deems reasonable, on the whole or any part of the <br /> amounts due, for the whole or any part of the period between the date on <br /> which the cause of action arose and the date of the award. Section <br /> 31(7)(b) then provides that, unless the award otherwise directs, the sum <br /> directed to be paid by the award shall carry interest from the date of the <br /> Award to the date of payment. The relevant portions of Section 31(7) of <br /> the Act read as under: <br /> <i>“(7) (a) Unless otherwise agreed by the parties, where and </i><br /> <i>in so far as an arbitral award is for the payment of money, </i><br /> <i>the arbitral tribunal may include in the sum for which the </i><br /> <i>award is made interest, at such rate as it deems reasonable, </i><br /> <i>on the whole or any part of the money, for the whole or any </i><br /> <i>part of the period between the date on which the cause of </i><br /> <i>action arose and the date on which the award is made. </i><br /> Digitally Signed<br /> By:MAYANK<br /> Signing Date:09.04.2026<br /> 18:31:43<br /> <b>O.M.P. (COMM) 337/2017</b> <b>Page 78 of 82</b> <br /><br /> <br /> <i>(b) A sum directed to be paid by an arbitral award shall, </i><br /> <i>unless the award otherwise directs, carry interest at the </i><br /> <i>rate of two per cent. higher than the current rate of interest </i><br /> <i>prevalent on the date of award, from the date of award to </i><br /> <i>the date of payment. </i><br /> <i>Explanation.—The expression “current rate of interest </i><br /> <i>shall have the same meaning as assigned to it under clause </i><br /> <i>(b) of section 2 of the Interest Act, 1978 (14 of 1978).” </i><br /> <b>119.</b> <b> </b> The decision of the Hon‟ble Supreme Court in <b><i>UHL Power Company </i></b><br /> 19<br /> <b><i>Ltd. v. State of Himachal Pradesh</i></b> reinforces the scope of arbitral <br /> discretion on interest and the limited scope for judicial interference. The <br /> arbitral tribunal there had granted pre-claim compound interest and future <br /> interest on the awarded amount, which the Division Bench of the High <br /> <b><i>20</i></b><br /> Court modified relying on <b><i>State of Haryana v. S.L. Arora & Co</i></b> <b><i>.</i></b> , the <br /> Hon‟ble Supreme Court relied on <b><i>Hyder Consulting (UK) Ltd. v. State of </i></b><br /> <b><i>21</i></b><br /> <b><i>Orissa</i></b> <b><i>, </i></b> to hold that the High Court‟s approach was erroneous and then <br /> restored the Arbitrator‟s award on interest expressly recognising that, <br /> unless prohibited by contract, an arbitral tribunal may grant compound <br /> interest. It is a settled position of law that a court cannot substitute its <br /> own view for that of the Arbitrator, so long as the Arbitrator‟s view is a <br /> plausible one. Also, the Hon‟ble Supreme Court in the case of <b><i>Ferro </i></b><br /> 22<br /> <b><i>Concrete Construction (India) (P) Ltd. v. State of Rajasthan</i></b> , traced <br /> down the changes in the power of the Arbitrator to award interest from <br /> the 1940 act and went on to summarise the current position of this power <br /> in the following words: <br /> <br /> 19<br /> (2022) 4 SCC 116. <br /> 20<br /> (2010) 3 SCC 690. <br /> 21<br /> (2015) 2 SCC 189. <br /> 22<br /> 2025 SCC OnLine SC 708. <br /> Digitally Signed<br /> By:MAYANK<br /> Signing Date:09.04.2026<br /> 18:31:43<br /> <b>O.M.P. (COMM) 337/2017</b> <b>Page 79 of 82</b> <br /><br /> <br /> <i>“13. From the above extracted paragraphs, the decision of </i><br /> <i>the 3-judge bench in the First Ambica case (supra) can be </i><br /> <i>stated as follows. The Arbitrator's power to grant interest </i><br /> <i>would depend on the contractual clause in each case, and </i><br /> <i>whether it expressly takes away the Arbitrator's power to </i><br /> <i>grant pendente lite interest. This would have to be </i><br /> <i>determined based on the phraseology of the agreement, </i><br /> <i>clauses conferring powers relating to arbitration, the nature </i><br /> <i>of claim and dispute referred to the Arbitrator, and on what </i><br /> <i>items the power to award interest is contractually barred </i><br /> <i>and for which period. Further, a bar on award of interest for </i><br /> <i>delayed payment would not be readily inferred as an express </i><br /> <i>bar to the award of pendente lite interest by the Arbitrator. </i><br /> <i>14. We find that the position of law laid down in paragraph </i><br /> <i>24 of Reliance Cellulose (supra) is in line with the position </i><br /> <i>of law laid down in the First Ambica case. Both decisions </i><br /> <i>emphasise the need for an express contractual bar on the </i><br /> <i>payment of pendente lite interest to create a bar on the </i><br /> <i>Arbitrator from awarding interest. They also emphasise that </i><br /> <i>a bar on the Arbitrator's power would depend on the </i><br /> <i>phraseology of the contractual clause in that case….” </i><br /> <b>120.</b> <b> </b> It is a settled position of law that the Arbitrator being a creation of an <br /> agreement cannot exceed the limits of the agreement. Thus, if there is <br /> any provision contained in the contract which prohibits the award of <br /> interest then the Arbitrator cannot exceed its jurisdiction and go beyond <br /> the terms of the contract to award interest. <br /> Digitally Signed<br /> By:MAYANK<br /> Signing Date:09.04.2026<br /> 18:31:43<br /> <b>O.M.P. (COMM) 337/2017</b> <b>Page 80 of 82</b> <br /><br /> <br /> <b>121.</b> <b> </b> The petitioner however in the present case has challenged the Award of <br /> this claim without specifying any contractual Clause which specifically <br /> prohibits the award of interest by the Arbitrator. <br /> <b>122.</b> <b> </b> Therefore, the award of interest by the Arbitrator under this claim is well <br /> founded and in exercise of the statutory powers conferred upon the <br /> Arbitrator by the Act itself. <br /> <b><i>Counter Claim Nos. 1 to 4 </i></b><br /> <b>123.</b> <b> </b> The petitioner‟s challenge to the adjudication of its counter claims by the <br /> Arbitrator is bereft of reasoning and unsubstantiated by cogent evidence. <br /> The petitioner has not made any submissions before this Court so as to <br /> warrant interference on the limited grounds enumerated under Section 34 <br /> of the Act and has merely made a fleeting contention that the counter <br /> claims were erroneously rejected by the Arbitrator. At this stage, it is <br /> pertinent to note that the counter claims raised by the petitioner are of the <br /> following description: <br /></div><table><thead><tr><th>Counter Claim<br>No. 1</th><th>Establishment cost for prolonged execution of works:<br>Rs. 19.32 Cr.</th></tr></thead><tbody><tr><td>Counter Claim<br>No. 2</td><td>Cost due to Alternate accommodation for Nursing<br>students due to non-completion of Nursing Hostel: Rs.<br>0.32 Cr.</td></tr><tr><td>Counter Claim<br>No. 3</td><td>Establishment cost for HVAC commissioning due to<br>delay in Package-I works: Rs. 1.40 Cr.</td></tr><tr><td>Counter Claim<br>No. 4</td><td>Escalation being paid to other agencies due to delay in<br>completion of Buildings Rs. 2.47 Cr.</td></tr></tbody></table><div><br /> <br /> <b>124.</b> <b> </b> Since, the delays leading to the prolongation of Contract were clearly <br /> held attributable to the petitioner, these co-related counter claims flowing <br /> from the same cause were rejected by the Arbitrator. This Court finds no <br /> Digitally Signed<br /> By:MAYANK<br /> Signing Date:09.04.2026<br /> 18:31:43<br /> <b>O.M.P. (COMM) 337/2017</b> <b>Page 81 of 82</b> <br /><br /> <br /> reason to interfere with the findings of the Arbitrator regarding <br /> attribution of delays in execution of works under the Contract and <br /> consequently, the findings of the Arbitrator <i>qua </i> the aforesaid <br /> counterclaims also deserves to be upheld. Moreover, the Arbitrator in its <br /> Award has recorded the submissions of both the parties with respect to <br /> counter claims and then made relevant findings. Additionally the <br /> Arbitrator also held that none of the counter claims were supported by <br /> any documentary evidence. Thus, no interference by this court is <br /> warranted. <br /> <b>CONCLUSION </b><br /> <b>125.</b> <b> </b> For all the aforesaid reasons, and having found no ground within the <br /> confines of Section 34 of the Act to set aside the reasoned findings of the <br /> Learned Sole Arbitrator, I hold that the impugned Award does not suffer <br /> from perversity, patent illegality or any other recognised vice warranting <br /> interference. <br /> <b>126.</b> <b> </b> The petition is dismissed in the aforesaid terms, along with pending <br /> applications, if any. <br /> <br /> <br /> <b>JASMEET SINGH, J</b> <br /> <b>th</b><br /> <b>APRIL 09</b> <b>, 2026/SS </b><br /> <br /> <br /> Digitally Signed<br /> By:MAYANK<br /> Signing Date:09.04.2026<br /> 18:31:43<br /> <b>O.M.P. (COMM) 337/2017</b> <b>Page 82 of 82</b> </div>