Wagad Infraprojects Pvt Ltd vs M/S Aryavart Projects Developers Pvt Ltd
- Court
- Madhya Pradesh High Court
1
IN THE HIGH COURT OF MADHYA PRADESH
AT JABALPUR
BEFORE
HON'BLE SHRI JUSTICE ALPESH Y. KOGJE,
CHIEF JUSTICE
&
HON'BLE SHRI JUSTICE VIVEK JAIN
ARBITRATION APPEAL No. 22 of 2025
CNR No.: MPHC010084232025
WAGAD INFRAPROJECTS PVT LTD
Versus
M/S ARYAVART PROJECTS DEVELOPERS PVT LTD
Appearance:
Shri Anshuman Singh and Sahil Sonkusale – Advocates for the appellant.
Shri Rahul Diwakar, Shri Aman Gupta, Shri Anukul Raj and Shri Naveen
Pandey – Advocates for the respondent.
ORDER
(Reserved on : 30.10.2026)
(Pronounced on : 25.11.2026)
Per: Justice Vivek Jain.
The present appeal under Section 37 of the Arbitration and
Conciliation Act 1996 (for short, “Act of 1996”) has been filed by the
appellant/claimant challenging the order dated 06.01.2025 passed by the
Commercial Court, Bhopal in MJC AV No.23 of 2021, whereby the
Signature Not Verified
Signed by: RAJESH KUMAR
JYOTISHI
Signing time: 11/27/2026
12:44:17 PM
2
application of the petitioner under Section 34 of Act of 1996 has been
rejected and the arbitral award passed by majority of the Arbitral Tribunal
dated 06.04.2021 has been confirmed.The Commercial Court has given
finding that no grounds as are laid down under Section 34 of Act of 1996
could be made out by the present appellant for setting aside the arbitral
award.
2. Learned counsel for the appellants has vehemently argued that the
appellant-claimant was the sub-contractor of the respondent for
construction of Guna-Ashoknagar-Isagarh Road. The client in the
construction of the road was M.P. Road Development Corporation
(MPRDC), which had entered into agreement with the concessionaire M/s
Aryavrat Tollways Private Limited Pvt. Ltd. and thereafter there was an
EPC agreement between Aryavrat Tollways Private Limited with the
present respondent, i.e. Aryavrat Projects and Developers Private Limited.
This present respondent-Aryavrat Projects and Developers Private Limited
had appointed the present appellant as sub-contractor for execution of the
work.
3. It is stated that the appellant worked until March, 2016 and the
respondent started collecting the toll and the contract between the
appellant and the respondent was never terminated. However, in view of
Signature Not Verified
Signed by: RAJESH KUMAR
JYOTISHI
Signing time: 11/27/2026
12:44:17 PM
3
the existing disputes, the appellant preferred claims aggregating Rs.106.85
crore and the respondent had submitted counter claims aggregating
Rs.115.54 crore. By majority of 2:1, the Tribunal not only allowed the
claim of the appellant to the tune of Rs.1.83 crore, but also allowed the
counter claim of the respondent to the tune of Rs.18.42 crore inclusive of
Rs.50 lakhs as costs, apart from interest.
4. Learned counsel for the appellant further submits that the award
was earlier put to challenge under Section 34 of Act of 1996 before the
District Judge/Commercial Court and in MJC AV No.30 of 2021, the
award was set aside by the District Judge/Commercial Court by order
dated 16.06.2022. This order was put to challenge before this Court in
Arbitration Appeal No.62/2022, which was allowed by a Coordinate
Division Bench of this Court vide order dated 10.07.2023. The Coordinate
Division Bench of this Court considered the position that the entire
consideration had been made by the Commercial Court only in one
paragraph of the order and the order was absolutely non-speaking in
nature. Therefore, it remanded the matter back to the Commercial Court to
re-decide the application under Section 34.
5. Learned counsel for the petitioner submitted that now in the
second round also, the Commercial Court has committed the same mistake
Signature Not Verified
Signed by: RAJESH KUMAR
JYOTISHI
Signing time: 11/27/2026
12:44:17 PM
4
and has passed such an order, which is non-speaking in nature, that too
without properly considering the grounds taken by the appellant. This time
it has confirmed the award.
6. Learned counsel for the appellant submits that the findings are
based on no evidence and ignoring vital evidence, that constitutes patent
illegality and therefore, on these grounds interference with the award can
be made in view of judgment of the Hon'ble Supreme Court in the case of
Delhi Airport Metro Express (P) Ltd. v. DMRC, (2022) 1 SCC 131 , so
also PSA Sical Terminals (P) Ltd. v. V.O. Chidambranar Port Trust,
(2023) 15 SCC 781.
7. It is further argued that the damages were awarded without proof
of loss, and compensation is not commensurate to the loss. The damages
have been awarded in a matter that has become a windfall for the
respondent. By relying on judgments in the case of Batliboi
Environmental Engineers Ltd. v. Hindustan Petroleum Corpn. Ltd.,
(2024) 2 SCC 375 , so also in the case of Maula Bux v. Union of India,
(1969) 2 SCC 554 , it is argued that valid grounds are made out to interfere
with the impugned award. It is further argued that express contractual
terms have been disregarded by the arbitrators, as well the Commercial
Court has failed to look into the matter.
Signature Not Verified
Signed by: RAJESH KUMAR
JYOTISHI
Signing time: 11/27/2026
12:44:17 PM
5
8. It is further argued that the agreed rate of interest has been
displaced by the arbitrator inasmuch as Clause 15.1.8 of the agreement
stipulated 14% interest, whereas the majority award has granted 18%
interest without containing any justification or basis for the same.
Therefore, it is argued that as per section 31(7)(a), the Arbitral Tribunal
cannot award interest more than the contractual rate of interest. The
contractual rate of interest being 14%, the Tribunal could not have granted
more than that.
9. It is further argued that every breach of contract alone does not
justify forfeiture of the security. For breach of security, forfeiture either
has to flow from conditions of the agreement or an ascertainable loss
caused to the other party must be proved, without which there cannot be
any justification for forfeiture of security amount.
10. It is further argued that counter claim requires an independent
adjudication and proof. Mere rejection of the claim of the claimant does
not supply any ground for acceptance of counter claim of the respondent to
the arbitration proceedings. The counter claim has to stand on its own legs
by a process of independent adjudication and independent proof, which
has not been done in the present case.
Signature Not Verified
Signed by: RAJESH KUMAR
JYOTISHI
Signing time: 11/27/2026
12:44:17 PM
6
11. Learned counsel for the appellant further argued that as per the
award, the claims of the claimant have been dealt with in the following
manner:-
Claimed Amount Claimed Finding
Claim No. 1:
Rs.5,25,86, 000/- Claim for
Rs.18305448/- allowed
Balance Labour Cess
and Royalty as per
(Issue) 3(a)
Payment of work done
by the Claimant up to
31/03/2016
Claim No. 2:
Rs 5,60,13,350/- +
Not entitled to release
of retention money
(Issue number 3(b))
Release of Retention
money withheld by the
Respondent
Rs. 4,41,05,000/- +
Rs. 1,19,08,350/- as
interest up to
21/03/2019
Claim No 3:
Rs 7,28,48,168/-
Not entitled
Performance security
in the form of Bank
Guarantee
Rs. 4,41,05,000/- +
Rs 1,68,34,818/- +
Issue number 3(b)
Interest from
24/12/2014
Rs 1,19,08,350/-
interest till date of
filing Claim
Claim No. 4:
Rs.14,70,00,000/- Not admissible under
clause 8.1.1
For idling of men &
machineries)
Signature Not Verified
Signed by: RAJESH KUMAR
JYOTISHI
Signing time: 11/27/2026
12:44:17 PM
7
Claim No. 5:
Rs.13,70,32,000/- Not entitled
Loss of bonus as per
clause 8.2.3 of the
agreement
Claim No. 6:
Rs. 15,40,00,000/- Under clause 8.1.1 not
admissible.
Loss of overheads and
profit due to
prolongation of
contract.
Claim No. 7:
Rs. 1,10,00,000/- with
the interest of Rs.
42,31,232/- (upto
31/03/2019).
Matter sub-judice and
not admissible.
Recovery of labor Cess
demanded by labor
commissioner.
Claim No. 8: Loss of
reputation, goodwill,
mental harassment.
Rs.10,00,00,000/- Not proved
Claim inadmissible.
Claim No. 9:
Rs. 1,00,00,000/- Not admissible.
Award of cost.
Claim No. 10:
Pendente lite or post
lite interest @ 18 %
from the date of
Completion of Work.
Rs.32,38,09,659/- Interest payable as per
Award @ 10 %, 90
days from date of
Award.
12. On the other hand, the counter claims of the respondent have
been dealt with by the Arbitral Tribunal in the following manner:-
Signature Not Verified
Signed by: RAJESH KUMAR
JYOTISHI
Signing time: 11/27/2026
12:44:17 PM
8
Claimed Amount Claimed Finding
Negative Variation
amount deducted by
MPRDC
Rs. 4,77,67,971/- Not proved.
Not admissible
Poor Quality of work
done
Rs.3,20,24,404/- Partially allowed
payable out of
Retention money
Less crust and DBM
thickness
Rs.9,32,40,000/- Not Admissible
Illegal Selling of
Aggregate by Claimant
Rs. 64,44,440/- Not proved
Claim for additional
overhead due to
machinery shifting
Rs.90,00,000/- Not proved
Claim for Defect
Liability period
Rs.11,00,90,229/- Payable limited to Rs
2,01,62,000/-
Claim for Liquidated
Damages
Rs.6,99,05,400/- Not admissible
Signature Not Verified
Signed by: RAJESH KUMAR
JYOTISHI
Signing time: 11/27/2026
12:44:17 PM
9
Completion of Punch
List Items
Rs.23,49,90,500/- Rs.4,41,05,000/-
Retained performance
Security amount
Defects in Construction
work:
Rs.15,63,59,000/- Retained Retention
Money.
Rs.4,41,05,000/-
Claim for Excess
payment made to the
Claimant
Rs.32,48,84,000/- Rs.7,09,00,000/- with
interest
Loss of interest on
O & M
Rs.36,75,000/- Not proved
Interest on Advance
payment
Rs.5,55,29,306/- Interest @18% from
20/04/2019 to
realization on
Rs.7,09,00,000/-
Mental Harassment and
Loss of Reputation:
Rs.15,00,000/- Not proved
Award of cost and
expenses
Rs. 1 Crore Allowed Rupees Fifty
Lakhs
Interest on the Claim
Amount
Rs.91,91,79,162/- Interest payable as per
Award @ 10%, if not
paid within 90 days
from date of Award
(excluding Excess
payment Award)
Signature Not Verified
Signed by: RAJESH KUMAR
JYOTISHI
Signing time: 11/27/2026
12:44:17 PM
10
13. While adjudicating the claims under various heads, the final
award is in the following terms:-
“1. a) Claimants claim for balance work
Rs.1,83,05,448/- (One Crore Eighty Three lakh Four
Hundred and Forty Eight.) allowed
b). Balance Labor cess Rs.1,52,000/- and Royalty
Rs.53.000/- allowed, if deducted and not deposited by
the Respondent to be paid to the Claimant.
2. Respondents Counter Claim for Defect Liability
period is partially allowed, limited to Rs.2,01,62,000/-.
3. Respondent Claim for Completion of Punch List
Items is partially allowed for Rs.4,41,05,000/-limited
to retained performance Security amount.
4. Claim for Respondents Claim for Excess payment
madeto the Claimant partially allowed for
Rs.7,09,00,000/- with 18% interest from 20/04/19 till
date of realization.
5. Defects in Construction work rectification limited to
Rs.4,41,05,000/- retained Retention money allowed.
6. Interest on Awarded amount if not paid within 90
daysof the publication of Award @ 10% from date of
Award till date of realization.
7. Fees paid to the Presiding Arbitrator and Arbitrator
appointed by Respondent, Sittings Fees,
Administrative fees and other expenses incurred by the
Parties before this Tribunal limited to Rs. Fifty lakhs
are to be borne by the Claimant and payable to the
Respondent.”
14. Learned counsel for the appellant has argued that for defect
liability, an amount of Rs.11.00 crores was claimed and against that,
performance security of Rs.4.41 crore was appropriated. The Tribunal
Signature Not Verified
Signed by: RAJESH KUMAR
JYOTISHI
Signing time: 11/27/2026
12:44:17 PM
11
found that no evidence was produced to prove that Rs.11.00 crores was
spent on maintenance during defect liability period, despite that it
proceeded to permit the respondent to retain and forfeit the performance
security to be used during defect liability period. The entire security was
appropriated without determination of proved expenditure or costs.
15. It is further argued that such a procedure is not permissible under
the contract, and the contract permits appropriation only of what is paid to
remedy the defect and only on failure to remedy the defects that are
notified. No determination process of any kind was undertaken to arrive at
the figure of Rs.4.41 crores.
16. It is further argued that in the punch list, an amount of Rs.23.49
crores was claimed against which Rs.2.01 crore has been awarded by the
Tribunal. However, the agreement permits recovery only of loss suffered
or incurred. The Tribunal held that it was for the respondent to prove that
they suffered loss, despite which it cast the burden on the appellant only
by relying on letter Annexure C-5/A by holding that mere denial by the
appellant is not enough. The figure has come from the respondent's own
demand, and not from any independent adjudicatory process of the
Arbitral Tribunal.
Signature Not Verified
Signed by: RAJESH KUMAR
JYOTISHI
Signing time: 11/27/2026
12:44:17 PM
12
17. Learned counsel for the appellant has also argued that against
defective construction, Rs.15.60 crores was claimed and retention money
of Rs.4.41 crores was appropriated against that. It is argued that in para
191, the Arbitral Tribunal has held that it is not proved that Rs.15 crores
was spent on rectifying faulty construction, but finding that there was
some faulty construction, still permitted retention of money of Rs.4.41
crores, which is without any basis.
18. It is further argued that against excess payment, amount of
Rs.32.48 crores was claimed against which Rs.7.09 crores has been
awarded by the Tribunal. However, there was no documentary evidence to
prove the excess payment for which the burden was on the respondent.
The Tribunal reversed the burden on the claimant to rebut the findings and
converted the appellant's own letter annexure C-5/A into proof for want of
specific denial.
19. Learned counsel for the appellant has also argued that the
Tribunal did not record any oral evidence and only on the basis of
affidavits and documents on record, it decided the matter, which cannot be
given stamp of approval by this Court. The claims and counter claims were
complex in nature, and the Tribunal ought to have recorded oral evidence,
which the Tribunal failed to do. After filing of the pleadings and affidavits,
Signature Not Verified
Signed by: RAJESH KUMAR
JYOTISHI
Signing time: 11/27/2026
12:44:17 PM
13
the matter was simply posted for final arguments, which is not a proper
procedure that was adopted by the Arbitral Tribunal.
20. The interest has also been awarded at exorbitant rate of 18% on
the excess payment of Rs.7.09 crore awarded by the Tribunal, which is
contrary to the contractual rate of interest, which as per Clause 5.1.8 is
14%. Though on the other heads, no interest has been awarded or the
interest of 10% has been awarded, however, under the head of excess
payment, interest of 18% per annum has been awarded without any basis
or justification.
21. Therefore, it is argued that the present appeal be allowed and the
order passed by the Commercial Court under Section 34 of Act of 1996 be
set aside, so also the award passed by the Tribunal be also set aside.
22. Per contra , learned counsel for the respondents have vehemently
supported the impugned award. It is argued that in an appeal under Section
37 of Act of 1996, the Appellate Court exercises the same scope of
jurisdiction as are available before the Commercial Court/District Court
under Section 34 of the Act of 1996. The Hon'ble Supreme Court in the
case of Punjab State Civil Supplies Corporation Ltd. v. M/s Sanman Rice
Mills, 2024 SCC Online SC 2632 , has held that arbitral award cannot be
interfered with on the ground of illegality or error, particularly through
Signature Not Verified
Signed by: RAJESH KUMAR
JYOTISHI
Signing time: 11/27/2026
12:44:17 PM
14
reappraisal of evidence and even if two views are possible, the High Court
should not substitute its view for that of the arbitrator. It is the view of the
arbitrator, which must ordinarily prevail. Therefore, it is argued that the
exercise which the appellant suggests this Court to undertake is the
exercise, which was to be undertaken by the arbitrator. The appellant is
challenging award of each and every item of claim as made by the
claimant, and as made by the respondent in counter claim on merits. Such
an exercise is impermissible in exercise of jurisdiction under section 37 of
Act of 1996. It is the view of the arbitrator, which should ordinarily prevail
unless the limited grounds as are made out under Section 34 of Act of
1996 are made out by the appellant. It is argued that none of the grounds
as are laid down under Section 34 of Act of 1996 are made out calling
interference of the Court with the award passed by the Arbitral Tribunal,
which is by majority of the arbitrators. Therefore, this Court may not make
any interference with the impugned award in the order of the District
Court/Commercial Court in confirming the award by rejecting application
under Section 34 of the Act of 1996.
23. It is further argued that no material illegality has been committed
by the Arbitral Tribunal in passing the impugned award. It cannot be said
that the findings are based on no evidence or ignoring vital evidence,
Signature Not Verified
Signed by: RAJESH KUMAR
JYOTISHI
Signing time: 11/27/2026
12:44:17 PM
15
which may constitute patent illegality. None of the grounds constituting
patent illegality are made out in the present case, so as to cause
interference with the impugned order under Section 34 so also with the
impugned award passed by the Arbitral Tribunal.
24. This Court has heard learned counsel for the rival parties at
length and perused the record.
25. The agreement in question between the appellant and the
respondent was agreement of sub-contract. MPRDC was the project
authority/client of the road which awarded the project to M/s Aryavrat
Tollways Private Limited as concessionaire which in turn entered into an
E.P.C agreement with the respondent, and the respondent in turn entered
into sub-contract with the present appellant. The appellant had submitted a
lump sum bid of Rs.96.71 crores for the project which was accepted by the
respondent and the sub-contract agreement dated 01.01.2013 was executed
between the parties. The date of commencement of work was 01.05.2013
and stipulated date of completion of work was 31.01.2015. The appellant
alleged various lapses on the part of respondent and claimed that the
appellant completed 90% of the work despite the lapses. The respondent
on his part made a claim of money against the appellant on the ground of
alleged delay in completion of the work and towards cost of the work not
Signature Not Verified
Signed by: RAJESH KUMAR
JYOTISHI
Signing time: 11/27/2026
12:44:17 PM
16
executed by the appellant. On account of such disputes between the parties
invoking arbitration clause in the agreement, the appellant nominated his
arbitrator and the respondent appointed his arbitrator and thereafter
Presiding Arbitrator was appointed, who was a retired District Judge. The
Arbitration Tribunal passed the award on 06.04.2021 by majority which
was challenged before the Commercial Court/District Court under Section
34 of the Act of 1996 and in the first instance, the same was set aside by
the said Court. The matter came up to this Court in Arbitration Appeal
No.62/2022 and finding the order under Section 34 to be an utterly non
speaking order containing reasons in only one paragraph therein, this
Court set aside the order passed by the Commercial Court/District Court
under Section 34 of Act of 1996 and remanded the matter back to the said
Court.
26. Upon remand, now the application under Section 34 has been
rejected by the Commercial Court, against which the appellant is before
this Court. The Arbitral Tribunal had allowed the claim of the appellant in
part only to the tune of Rs.1,83,05,448/- but allowed the counter claim of
the respondent substantially to the tune of Rs.18,42,72,000/-. The counsel
for the appellant had argued that against the defect liability, the claim of
the respondent was Rs.11.00 crores against which the performance
Signature Not Verified
Signed by: RAJESH KUMAR
JYOTISHI
Signing time: 11/27/2026
12:44:17 PM
17
security of Rs.4,41,05,000/- has been appropriated. Despite finding in para
182 of the award of the Tribunal that no evidence has been produced to
prove that Rs.11.00 crores was spent on maintenance during defect
liability period, appropriation of an amount of Rs.4,41,05,000/- has been
permitted.
27. For retention of the performance security, the Arbitral Tribunal
has assigned the reason that it is established that there were defects in
construction work and the same were not rectified by the claimant. The
maintenance not being done by the claimant is established and it fell upon
the respondent to attend to the defects and get the work completed which
cost money. The Tribunal held that the purpose of retaining the amount
was that if the work was defective or of poor quality then the said amount
can be utilized. The responsibilities of the contractor during the defect
liability period were detailed in Annexure–3 of the agreement. The
Tribunal in response to the issue No.3 (b) has considered the argument of
the appellant that he has executed all work except item of B.C.E. on about
5-6 KMs of Section II. The Tribunal in para 138 of the award after
considering the documents on record has given a categorical finding of
fact that from evidence it is proved that the appellant stopped the work and
did not perform any construction activity or maintenance activity after
Signature Not Verified
Signed by: RAJESH KUMAR
JYOTISHI
Signing time: 11/27/2026
12:44:17 PM
18
March, 2016 upto the defect liability period. As per clause 3 and other
provisions of the contract, it is provided that while calculating any monies
from the EPC contractor to the contractor, due account shall be taken of
any advance payment and retention amount. The statement of claim of the
appellant himself mentioned that the appellant has executed 90% work till
31.03.2016 whereas the stipulated period for completion of work was
31.01.2015. The defect liability period was upto 22.03.2019. From a
perusal of the pleadings of the appellant himself before the Arbitral
Tribunal, it is clear that the appellant did not perform any work after
31.03.2016 and as recorded in para 113 of the award by the Arbitral
Tribunal, during arguments the appellant himself contended before the
Tribunal that they have executed all work except item of BCE on about 5-
6 KMs of Section II. They contended that whatever else is left is not in the
scope of claimant’s work. Therefore, before the Tribunal also admission
was made that certain amount of work has been left out by the
claimant/appellant which was admittedly within the scope of work and for
the other work which was alleged to be left out to be executed by the
appellant, he was raising the dispute that it was not in the scope of work
awarded to him. The appellant could not establish before the Tribunal that
he was being asked to perform the work which was not in the scope of
Signature Not Verified
Signed by: RAJESH KUMAR
JYOTISHI
Signing time: 11/27/2026
12:44:17 PM
19
contract. In a table contained in para 115 of the award of the Tribunal, the
Tribunal has recorded that no additional work was done by the appellant.
The Tribunal held that the appellant/claimant could not establish that there
was any work which the appellant was being asked to perform and was not
in the scope of work. The claimant failed to establish before the Tribunal
that it has been asked to perform such work which was not in the scope of
contract.
28. In view of the aforesaid, it being clear that the appellant left the
work without it being completed and as per the own admission of the
appellant in para 10 of the statement of claim before the Arbitral Tribunal,
he completed 90% of the work under the contract, therefore it becomes
clear that as per his own admission he has not performed 10% of the work
which amounts to approximate value of Rs.9.6 crores and non-
performance of this 10% of the work is own admission of the claimant. He
did not also carry out any repairs and maintenance works in the defect
liability period which was upto March, 2019.
29. Therefore, the Tribunal having appropriated performance
security of Rs.4.41 crores towards defect liability period does not seem to
be something which has been ordered by the Tribunal without there being
any material evidence on record. Though exact amount of defect liability
Signature Not Verified
Signed by: RAJESH KUMAR
JYOTISHI
Signing time: 11/27/2026
12:44:17 PM
20
period has not been quantified, but the appellant not having performed any
defect within the entire period is not in dispute. The performance security
was towards defect liability period of 3 years. The performance security
was submitted against defect liability and no defect liability work was
done by the appellant. In such circumstances, the Tribunal ordering the
appropriation of performance security towards defect liability cannot be
stated to be something which is in conflict with the Public Policy of India.
30. So far as the amount of Rs.2,01,60,000/- awarded towards punch
list against which amount of Rs.23.49 crores was claimed, this was a list of
incomplete works and the respondent had pointed out vide letter dated
11.01.2016 to the appellant, the incomplete works as on that date which
have been quantified to the value of Rs.201.26 lakhs. The Tribunal has
considered the reply of the appellant vide Annexure 5-C/A whereby the
claimant stated that they have never denied executing the work but
requested for amount to be paid. The Tribunal found that the works
mentioned in the punch list was not performed and, therefore, found the
claim of Rs.2.01 crore to be substantiated against punch list items. This
reasoning of the Tribunal, which is as per the documents on record, also
cannot be said to be contrary to Public Policy of India.
Signature Not Verified
Signed by: RAJESH KUMAR
JYOTISHI
Signing time: 11/27/2026
12:44:17 PM
21
31. The claim of Rs.15.63 crores was made towards defects in
construction against which the Tribunal awarded appropriation of Rs.4.41
crores which was retention money. The respondent had submitted counter
claim stating that it had incurred expenditure of Rs.15.63 crores towards
defects in construction which was countered by the appellant by stating
that the amounts mentioned in R-75 are not in claimant’s scope such as
protection work, utility duct, RCC drain, toll plaza canopy, bus shelter,
restroom facilities, landscaping, plantation etc. The Tribunal has
considered in para 120 of the award that vide annexure R-69 & R-70, the
appellant was asked by the respondent to rectify major defects in the work.
Even the independent engineer from the firm Lion Engineering vide letters
R-34, R-35, R-36, R-37 & R-38 had pointed out the PQC work done at
Shadhora being very poor in quality and all the panels were cracking. The
Tribunal has also considered Annexure-63 which is the inspection note
dated 22.07.2016 wherein defects have been listed by the Engineer-in-
Chief of the M.P.R.D.C. This inspection was held immediately after
stoppage of work by the appellant. It was recorded that the existing road
surface is wearing off between Guna and Shadhora town. Ridge pavement
done at Shadhora town is having crocodile cracking and at many places
top surface in concrete is wearing off due to poor quality of construction
Signature Not Verified
Signed by: RAJESH KUMAR
JYOTISHI
Signing time: 11/27/2026
12:44:17 PM
22
and worksmanship, drain is partially complete. However, these defects
were not removed. Looking to these major defects in the construction
which were not completed, the Tribunal has ordered the amount to be
appropriated from retention money. The Tribunal has considered that 50%
of retention money was to be released/refunded after completion of road
and balance 50% after expiry of defect. However, neither the road was
completed nor the defects were rectified and therefore, the appropriation of
retention money has been ordered by the Tribunal. This also does not seem
to be something against Public Policy of India that has been ordered by the
Tribunal, so that this Court would interfere in exercise of its limited
jurisdiction under Section 37 of the Act of 1996.
32. The Tribunal has awarded an amount of Rs.7.09 crores to the
respondent towards excess payment with 18% interest. The Tribunal has
considered that there were item wise certification remarks sent by the I.E
Synergy Engineering Group on 13.06.2015 vide Annexure R-12. After
verification, the certified bill was of Rs.88.36 crores and upto that the over
payment of Rs.7.09 crores had been made to the appellant. Therefore,
against the claim of Rs.32.48 crores towards over payment, the Tribunal
awarded Rs.7.09 crores towards over payment. In para 150 of the award
the Tribunal has considered that the appellant could not rebut by way of
Signature Not Verified
Signed by: RAJESH KUMAR
JYOTISHI
Signing time: 11/27/2026
12:44:17 PM
23
evidence, the findings of R-12 were erroneous. The respondent had
contended that it had been paying for cube testing machine, material such
as bitumen, cement, LDO, EPO etc. Apart from that the respondent also
paid the appellant as per requirement for staff salaries, miscellaneous site
expenditure and other expenses as and when required by the appellant and
all those amounts have been debited to claimant as project payment. The
Tribunal has considered that vide Annexure C-5, the claimant denied the
claim and stated that from December 2014, instead of providing funds for
procurement of bitumen and diesel, the respondents started supply of
material but there is no specific denial regarding other items claimed by
the respondents for which funds were given to the appellant. The appellant
could not show that the given amount was adjusted later in the running
bills. On consideration of such evidence on record, the Tribunal held that
the respondent is entitled to recovery of excess payment of Rs.7.09 crores
made to the appellant. This Court does not find that the said finding is
without any evidence at all or that it is perverse. Therefore, this Court is
unable to hold that the aforesaid finding is something which is contrary to
the Public Policy of India. The Tribunal has also awarded interest on the
amounts and for the excess payment made to the claimant, the interest has
been awarded at the rate of 18% per annum from the date of submission of
Signature Not Verified
Signed by: RAJESH KUMAR
JYOTISHI
Signing time: 11/27/2026
12:44:17 PM
24
counter claim till actual realization and for other items interest has been
awarded at the rate of 10% from the date of award till the date of
realization.
33. So far as award of interest at the rate of 18% per annum on the
claim for excess payment to the tune of Rs.7.09 crores is concerned, the
Tribunal has awarded 18% interest from the date of submission of counter
claim till the date of realization. As per Section 31(7)(a) of the Act of
1996, the following provision has been made in the matter of payment of
interest :-
“(7) (a) Unless otherwise agreed by the parties, where
and in so far as an arbitral award is for the payment of
money, the arbitral tribunal may include in the sum for
which the award is made interest, at such rate as it
deems reasonable, on the whole or any part of the
money, for the whole or any part of the period between
the date on which the cause of action arose and the date
on which the award is made.”
(b) *
34. The Arbitral Tribunal, therefore has a jurisdiction to adjudicate
the appropriate rate of interest as it deems reasonable unless it has been
otherwise agreed by the parties. Therefore, it is required to be seen that
whether there is any contractual rate of interest or not.
Signature Not Verified
Signed by: RAJESH KUMAR
JYOTISHI
Signing time: 11/27/2026
12:44:17 PM
25
35. The contract which is on record in Clause 5.1.8 provides for rate
of interest for the payment made by the EPC contractor to the contractor.
The relevant clauses 5.1.6 & 5.1.8 are as under:-
“5.1.6 The EPC Contractor shall not be liable to
make any advance payment to the Contractor against
the Contract Price. However, the EPC Contractor may
at its sole discretion consider making of any adhoc
payments to the Contractor.
5.1.8 Any amount paid by the EPC Contractor under
the Sub-Clause 5.1.6 shall be immediately become due
as a debt from the Contractor to the EPC Contractor
until payment set off and shall carry interest @14% per
annum after one month of payment.”
36. The excess payment made by the respondent can be said to be a
payment made in terms of clause 5.1.6 for which the rate of interest would
be under clause 5.1.8 which is fixed rate of interest of 14% per annum.
Despite that, the arbitral Tribunal has awarded interest of 18% per annum
on the excess payment component of Rs.7.09 crores.
37. The excess payment by the respondent can be said to be a
payment made in terms of clause 5.1.6 for which the rate of interest would
be under clause 5.1.8 which is fixed @ 14% Per annum. Despite that the
Tribunal has awarded interest @ 18% per annum on the excess payment
amounting to Rs.7.09 crores.
Signature Not Verified
Signed by: RAJESH KUMAR
JYOTISHI
Signing time: 11/27/2026
12:44:17 PM
26
38. The aforesaid award on interest is contrary to statutory
provisions of Section 31(7) and therefore, the Tribunal passing an order
contrary to the mandatory provisions of Section 31(7)(a) of the Act, 1996
can be said to have acted in contravention of Public Policy of India which
includes compliance of statutes and judicial precedents, as held by the
Hon’ble Supreme Court in the case of Associate Developers vs. Delhi
Development Authority reported in 2015 (3) SCC 49 .
39. Therefore, we would reduce the rate of interest awarded on
excess payment of Rs.7.09 crores as awarded by the Tribunal to the tune of
18% per annum to 14% per annum in consonance with the terms of
contract.
40. Apart from that we do not find any fundamental breach of
principles of natural justice or that the award to be passed arbitrarily
ignoring vital evidence or having been passed with some patent illegality.
There is nothing in the award which has been found so perverse or
irrelevant nor construction of the contract in such a manner, which no fair
and reasonable person would take.
41. Even testing the award at the touchstone of the parameters led by
the Hon’ble Supreme Court in the case of Delhi Metro Rail Corporation
Limited vs. Delhi Airport Metro Express Private Limited reported in 2024
Signature Not Verified
Signed by: RAJESH KUMAR
JYOTISHI
Signing time: 11/27/2026
12:44:17 PM
27
(6) SCC 357 , we do not perceive any other ground of interference with the
impugned order passed by the Commercial Court rejecting application
under Section 34 of Act of 1996.
42. It has been held by the Hon’ble Supreme Court in the case of
Punjab State Civil Supplies Corporation Limited & Anr. Vs. Sanman
Rice Mills & Anr. reported in 2024 SCC Online 2632 that arbitral award
cannot be interfered with on the ground of illegality or error particularly
through reappreciation of evidence and even if two views are possible then
even the High Court should not substitute its view for that of the arbitrator,
and it is the view of the arbitrator which must ordinarily prevail. It has
been held therein as under:-
“12. It is pertinent to note that an arbitral award is not liable
to be interfered with only on the ground that the award is
illegal or is erroneous in law that too upon reappraisal of the
evidence adduced before the arbitral trial. Even an award
which may not be reasonable or is non-speaking to some
extent cannot ordinarily be interfered with by the courts. It is
also well settled that even if two views are possible there is no
scope for the court to reappraise the evidence and to take the
different view other than that has been taken by the
arbitrator. The view taken by the arbitrator is normally
acceptable and ought to be allowed to prevail.
20. In view of the above position in law on the subject, the
scope of the intervention of the court in arbitral matters is
virtually prohibited, if not absolutely barred and that the
interference is confined only to the extent envisaged under
Section 34 of the Act. The appellate power of Section 37 of the
Act is limited within the domain of Section 34 of the Act. It is
exercisable only to find out if the court, exercising power
Signature Not Verified
Signed by: RAJESH KUMAR
JYOTISHI
Signing time: 11/27/2026
12:44:17 PM
28
under Section 34 of the Act, has acted within its limits as
prescribed thereunder or has exceeded or failed to exercise
the power so conferred. The Appellate Court has no authority
of law to consider the matter in dispute before the arbitral
Tribunal on merits so as to find out as to whether the decision
of the arbitral Tribunal is right or wrong upon reappraisal of
evidence as if it is sitting in an ordinary court of appeal. It is
only where the court exercising power under Section 34 has
failed to exercise its jurisdiction vested in it by Section 34 or
has travelled beyond its jurisdiction that the appellate court
can step in and set aside the order passed under Section 34 of
the Act. Its power is more akin to that superintendence as is
vested in civil courts while exercising revisionary powers. The
arbitral award is not liable to be interfered unless a case for
interference as set out in the earlier part of the decision, is
made out. It cannot be disturbed only for the reason that
instead of the view taken by the arbitral Tribunal, the other
view which is also a possible view is a better view according
to the appellate court.
21. It must also be remembered that proceedings under
Section 34 of the Act are summary in nature and are not like a
full-fledged regular civil suit. Therefore, the scope of Section
37 of the Act is much more summary in nature and not like an
ordinary civil appeal. The award as such cannot be touched
unless it is contrary to the substantive provision of law; any
provision of the Act or the terms of the agreement.”
43. Recently, the Apex Court has again considered the scope of
limits of jurisdiction under Section 37 of Act of 1996 in Rajasthan Rajya
Vidyut Utpadan Nigam Ltd. vs. Parsa Kente Collieries Limited, SLP
(Civil) No.32968/2026 decided on 16.11.2026 as under:-
“49. The limits within which a court may examine an arbitral
award are well settled. The proviso to sub-section (2A) of
Section 34 of the Act provides that an award shall not be set
Signature Not Verified
Signed by: RAJESH KUMAR
JYOTISHI
Signing time: 11/27/2026
12:44:17 PM
29
aside merely on the ground of an erroneous application of the
law or by reappreciation of evidence. Patent illegality, on which
a domestic award may be set aside, is an illegality that goes to
the root of the matter and appears on the face of the award. It
does not extend to an error in appreciating evidence, or to a
construction of the contract merely because the court could have
construed it differently. An award is perverse only when a
finding is based on no evidence, or are based on irrelevant
material, or that the Tribunal ignored vital evidence. The Arbitral
Tribunal is the final arbiter of the facts, and the construction of
the contractual terms is primarily its domain. Where the
interpretation adopted is a possible and plausible one, the court
cannot substitute its own interpretation, however persuasive the
alternative reading may be. The Section 37 court is, moreover,
confined to the grounds available under Section 34 of the Act
and cannot undertake an independent assessment of the merits of
the award. Taking a holistic view, we find that both the Awards,
read as a whole, do not suffer from patent illegality, perversity or
any other ground that would justify these being set aside under
Section 34 of the Act. This accords with the consistent approach
of this Court, which has emphasised the restricted scope of
interference with arbitral awards, so that the autonomy and
finality of arbitration are respected, and the process of scrutiny is
not turned into an ordinary appeal on facts and law. Having
found that the Arbitral Tribunal has not deviated from the
established principles in a manner warranting interference, we
decline to interfere with the impugned Judgment of the High
Court which has upheld the Awards.”
44. The counsel for the appellant had also argued, though not with
much vehemence, that the Tribunal has not recorded any oral evidence.
However, upon perusal of the record, we do not find this ground to be
substantiated. This is because the Tribunal had framed the issues in
November 2019 and after framing of the issues, the matter was fixed on
Signature Not Verified
Signed by: RAJESH KUMAR
JYOTISHI
Signing time: 11/27/2026
12:44:17 PM
30
07.12.2019 on which date both the parties stated that there was no
necessity to decide the issues in dispute that they are relying on
documentary evidence. The parties were, therefore, directed to submit
their evidence affidavits by 10.01.2020 and the case was then fixed for
oral submissions for 19.01.2020. The Tribunal recorded the aforesaid
contention of the parties in the following manner :-
“Both the parties stated that there is no necessity of oral
evidence to decide the issues in dispute as they are based
on documentary evidence. The parties are directed to submit
their evidence on affidavit by 10/01/2020.”
Therefore, the Tribunal not having recorded oral evidence cannot be
said to be a material irregularity by the Tribunal and we are not inclined to
interfere with the award on that ground also.
45. Therefore, in totality, we do not find any good reason to interfere
with the well-reasoned award passed by the Arbitral Tribunal, except to
the extent of rate of interest on excess payment to the tune of Rs.7.09
crores allowed vide para 204 (4) of the award. The interest as contained in
the aforesaid para shall stand reduced to 14% per annum from 18% per
annum as already awarded by the Tribunal.
46. Except for the aforesaid modification which can duly be made in
view of the judgment of the Constitution Bench in the case of Gayatri
Signature Not Verified
Signed by: RAJESH KUMAR
JYOTISHI
Signing time: 11/27/2026
12:44:17 PM
31
Balasamy v. ISG Novasoft Technologies Ltd. , reported in (2025) 7 SCC
1 , the other part of the award is affirmed.
47. In terms of the above, the appeal stands partly allowed and
disposed of .
(ALPESH Y. KOGJE) (VIVEK JAIN)
CHIEF JUSTICE JUDGE