Union Of India vs Janved

Court
Madhya Pradesh High Court

NEUTRAL CITATION NO. 2026:MPHC-GWL:22624
1 WP-12076-2020
IN THE HIGH COURT OF MADHYA PRADESH
AT GWALIOR

BEFORE
HON'BLE SHRI JUSTICE MILIND RAMESH PHADKE
th
ON THE 27 OF JULY, 2026
WRIT PETITION No. 12076 of 2020
UNION OF INDIA AND OTHERS
Versus
JANVED AND OTHERS


WRIT PETITION No. 11997 of 2020
UNION OF INDIA AND OTHERS
Versus
GAYAPRASAD (DELETED) S/O LATE SHRI RAMA TELI DIED
THROUGH LRS A) SMT. BINU SAHU AND OTHERS

WRIT PETITION No. 12131 of 2020
UNION OF INDIA THR. AND OTHERS
Versus
BALKRISHEN AND OTHERS

WRIT PETITION No. 12135 of 2020
UNION OF INDIA THR. AND OTHERS
Versus
HARIKISHOR AND OTHERS

WRIT PETITION No. 12142 of 2020
UNION OF INDIA AND OTHERS
Versus
RAM KUMAR AND OTHERS

WRIT PETITION No. 12143 of 2020
UNION OF INDIA AND OTHERS
Versus
MUKESH KUMAR AND OTHERS
Signature Not Verified
Signed by: ASHISH PAWAR
Signing time: 30-07-2026
15:43:28

NEUTRAL CITATION NO. 2026:MPHC-GWL:22624
2 WP-12076-2020

WRIT PETITION No. 12148 of 2020

UNION OF INDIA AND OTHERS
Versus
BADRIPRASAD AND OTHERS

WRIT PETITION No. 12152 of 2020
UNION OF INDIA AND OTHERS
Versus
SHIV CHARAN AND OTHERS

WRIT PETITION No. 12171 of 2020
UNION OF INDIA AND OTHERS
Versus
SATYAPRAKASH AND OTHERS

Appearance:
Shri Praveen Kumar Newaskar - Deputy Solicitor General for the
petitioners/UOI.
Shri Koushlendra Singh Tomar - GA for the State.
Shri Sunil Kumar Jain - Advocate f or the respondent No.1/respondents.
ORDER
Since all the above petitions arise out of the same cause of action,
therefore all the petitions are being decided by this common order. For the
sake of convenience, facts necessary for adjudication are taken from Writ
Petition No. 12076/2020.
All the petitions under Article 226 of the Constitution of India have
been filed by the petitioners calling in question the legality, validity and
propriety of the order/award dated 31.01.2020 passed by the Sub-Divisional
Officer and Land Acquisition Officer, Karera, District Shivpuri, whereby the
application preferred under Section 28-A of the Land Acquisition Act, 1894
for re-determination of compensation came to be decided.
Signature Not Verified
Signed by: ASHISH PAWAR
Signing time: 30-07-2026
15:43:28

NEUTRAL CITATION NO. 2026:MPHC-GWL:22624
3 WP-12076-2020
Briefly stated, the land ad-measuring 209.80 hectares situated at

Village Kalothra, Tehsil Karera, District Shivpuri, was acquired pursuant to
the notifications issued under Sections 4 and 6 of the Land Acquisition Act,
1894 for a public purpose. The Land Acquisition Officer passed the original
award on 30.03.1996 under Section 11 of the Act of 1894. It is the case of
the petitioners that certain landholders had sought reference under Section 18
of the Act and, on the basis of the award passed by the Reference Court, the
respondent preferred an application under Section 28-A of the Act seeking
re-determination of compensation. The said application remained pending for
considerable time and, pursuant to the directions issued by this Court in W.P.
No.2706/2019, the Sub-Divisional Officer and Land Acquisition Officer
decided the application by the impugned order dated 31.01.2020.
Assailing the aforesaid order, learned counsel for the petitioners
submits that the impugned order has been passed without granting adequate
opportunity of hearing to the petitioners and without properly considering
their objections, particularly on the issue of limitation under Section 28-A of
the Act. It is further submitted that the authority has failed to assign cogent
reasons while recording its conclusions and, therefore, the impugned order is
liable to be set aside. In support of his arguments, learned counsel, while
placing reliance on the order dated 21.04.2026 passed by this Court in W.P.
No. 29708/2022, submitted that in similar circumstances, this Court had
passed the aforesaid order in the said writ petition, which is reproduced as
under:-
"The present petition under Article 226 of the Constitution of India has been filed by the
petitioners challenging the legality, validity, and propriety of the impugned order/award dated
Signature Not Verified
Signed by: ASHISH PAWAR
Signing time: 30-07-2026
15:43:28

NEUTRAL CITATION NO. 2026:MPHC-GWL:22624
4 WP-12076-2020
16.08.2021 passed by the Sub-Divisional Officer and Land Acquisition Officer, Karera, District
Shivpuri.
Briefly stated, the land ad-measuring 209.80 hectares situated at Village Kalothra, Tehsil
Karera, District Shivpuri, including the land bearing Survey No. 897/1046, ad-measuring 3.01
hectares belonging to the respondent No.1, was acquired by the Government of India through the
Ministry of Home Affairs for the purpose of construction of an arms and ammunition depot for
the Indo-Tibetan Border Police. The acquisition proceedings were initiated by issuance of
notification under Section 4(1) of the Land Acquisition Act, 1894 dated 21.02.1994, published on
18.03.1994, followed by declaration under Section 6 dated 06.04.1994, published on 10.06.1994.
Possession of the acquired land was taken on 28.02.1995, and thereafter the Land Acquisition
Officer i.e. the Collector passed an award on 30.03.1996 in Case No. 1/93-94/A-82 under Section
11 of the Act. It is an admitted position that the respondent accepted the compensation awarded
by the Collector under protest on 26.08.2000 and did not seek reference under Section 18 of the
Act against the award dated 30.03.1996. However, certain other landholders, whose lands were
acquired under the same notification, had sought reference under Section 18, which came to be
decided by the Court of Second Additional District Judge, Shivpuri in Reference Case Nos.
10/1998, 11/1998 and 15/1998. By award dated 01.05.2000, the Reference Court enhanced the
compensation amount. The said award was further carried in first appeal before this Court
wherein by judgment dated 25.10.2017, the compensation was further enhanced and the rate for
interior land was fixed at Rs.1,28,000 per hectare along with statutory benefits including solatium
and interest. On the basis of the award passed by the Reference Court dated 01.05.2000, the
respondent submitted an application under Section 28-A of the Act seeking re-determination of
compensation. As per the statutory scheme of Section 28-A, such an application is required to be
filed within a period of three months from the date of the award of the Reference Court.
However, the application of the respondent was not decided for a considerable period.
Subsequently, the respondent approached this Court by filing Writ Petition No. 20374/2019
seeking a direction to the Collector to decide the application under Section 28-A. The said writ
petition was disposed of on 26.06.2021 with a direction to the Collector, Land Acquisition
Officer, District Shivpuri to decide the pending application expeditiously. Pursuant to the
directions issued by this Court, the Sub-Divisional Officer and Land Acquisition Officer, Karera,
proceeded to consider the application under Section 28-A and, by the impugned order dated
16.08.2021, held that the respondent fulfilled all the requirements under Section 28-A of the Act.
The authority recorded findings that the land of the respondent was acquired under the same
notification as the lands involved in the reference cases and the respondent had accepted the
compensation under protest and was therefore an aggrieved person as well as the application
under Section 28-A had been filed within the prescribed period of limitation. On the basis of such
findings, the authority re-determined the compensation payable to the respondent No.1 in terms of
the judgment of this Court dated 25.10.2017 and awarded a total sum of Rs.20,35,024/- after
adjusting the amount already paid, along with statutory benefits including solatium and
interest. Assailing the impugned order on the ground that the same has been passed without
proper appreciation of the settled legal position and without due consideration of the objections
raised by the petitioners particularly with regard to the bar of limitation prescribed under Section
28-A of the Act, the petitioners have preferred the present petition before this Court seeking
following reliefs:-

"(i) That the impugned order/award dt. 16.08.2021 (Annexure P/1) passed by the SDO
and Land Acquisition Officer Karera District Shivpuri may kindly be set aside.
(ii) That, ultimately this Hon'ble Court has found that the application was well within
limitation and award has rightly been passed then looking to the delay made by
respondents the interest as well as additional compensation which is directed to be paid
may be recovered from the then land acquisition officer who has not decided the
application within time and unnecessarily delayed the matter. It is also important to note
Signature Not Verified
Signed by: ASHISH PAWAR
Signing time: 30-07-2026
15:43:28

NEUTRAL CITATION NO. 2026:MPHC-GWL:22624
5 WP-12076-2020
that, the respondent no. 2 also approach before the court belatedly first time in the year
2019 therefore, he is not entitle any interest as has been awarded by the land acquisition
officer and this award is liable to be modify accordingly.
(iii) That any other relief to which this Hon'ble Court may deem fit may also be directed
to be extended in favour of the petitioners in the interest of justice.
Costs of this petition be also awarded in favour of the petitioners."
Learned counsel for the petitioners submits that the impugned order dated 16.08.2021 passed
by the Sub-Divisional Officer and Land Acquisition Officer, Karera, District Shivpuri is ex facie
illegal, arbitrary and contrary to the settled provisions of the Land Acquisition Act, 1894, and
therefore deserves to be quashed, as it has been passed in complete disregard of the mandatory
provisions contained in Section 28-A of the Act of 1894. The statutory scheme clearly provides
that an application for re-determination of compensation is required to be filed within a period of
three months from the date of the award passed by the Reference Court. In the present case, the
award by the competent Reference Court was admittedly passed on 01.05.2000, whereas the
application under Section 28-A is shown to have been filed on 26.08.2000. Thus, the application
was clearly beyond the prescribed period of limitation and was not maintainable in law. The Act
of 1894 does not provide for any condonation of delay, and therefore, the Land Acquisition
Officer had no jurisdiction to entertain such a time-barred application. The impugned order,
having been passed on a non-maintainable application, is liable to be set aside on this ground
alone.
Learned counsel further submits that while passing the impugned order, the Land Acquisition
Officer has failed to properly appreciate the definition of the term “Court” as provided under
Section 3(d) of the Act of 1894. The expression “Court” refers to the principal Civil Court of
original jurisdiction, which in the present case is the Reference Court that passed the award dated
01.05.2000. The subsequent orders passed in appeal under Section 54 of the Act cannot be treated
as the “award of the Court” for the purpose of computing limitation under Section 28-A. This
settled legal position has been consistently affirmed by the Hon’ble Supreme Court.
In this regard, reliance is placed on the judgment of the Hon’ble Supreme Court in State of A.P.
vs. Marri Venkaiah and others, reported in (2003) 7 SCC 280, wherein it has been categorically
held that the limitation period under Section 28-A is to be strictly computed from the date of the
award of the Reference Court, excluding only the time requisite for obtaining a certified copy,
and no further extension on the ground of knowledge or otherwise is permissible. Similarly, in
Jose Antonio Cruz Dos R. Rodrigues vs. Land Acquisition Collector reported in (1996) 6 SCC
746, a three-Judge Bench of the Hon’ble Supreme Court has clearly held that the period of
limitation is to be reckoned from the date of the award of the Reference Court and not from any
appellate order. The same principle has also been reiterated in Tota Ram vs. State of U.P.
reported in (1997) 6 SCC 280 and State of Tripura vs. Roopchand Das reported in (2003) 1 SCC
421. In light of these authoritative pronouncements, the contrary view taken by the Land
Acquisition Officer is wholly unsustainable.
It is further submitted that the impugned order has also been passed without affording a proper
and effective opportunity of hearing to the petitioners and the principles of natural justice have
been violated inasmuch as the objections raised by the petitioners, particularly on the issue of
limitation, have not been duly considered or adjudicated. The order has been passed in a
mechanical and cursory manner, without recording any cogent reasons for rejecting the objections
of the petitioners.
Learned counsel also submits that the conduct of the Land Acquisition Officer in the present
case reflects gross negligence and inaction, as the application under Section 28-A, even if
assumed to have been filed, remained pending for an inordinate period of more than two decades
and was taken up for consideration only after the directions issued by this Court in the year 2021.
Thereafter, the impugned award came to be passed in undue haste within a short span, without
proper application of mind. Such arbitrary exercise of power has resulted in imposing an

Signature Not Verified
Signed by: ASHISH PAWAR
Signing time: 30-07-2026
15:43:28

NEUTRAL CITATION NO. 2026:MPHC-GWL:22624
6 WP-12076-2020
unjustified financial burden upon the petitioners, particularly in the form of interest for a
prolonged period extending from the year 2000 to 2022.
It is further submitted that if at all any liability towards payment of interest arises, the same
cannot be saddled upon the State exchequer in the facts of the present case, as the delay is
entirely attributable to the inaction and negligence of the concerned Land Acquisition Officer.
The petitioners cannot be penalized for administrative lapses beyond their control, and therefore,
it would be just and proper that the liability, if any, be recovered from the concerned officer
personally.
Learned counsel further submits that the impugned award is otherwise contrary to the
provisions of the Act of 1894 and the law laid down by the Hon’ble Supreme Court as the Land
Acquisition Officer has exercised jurisdiction not vested in him by law by entertaining and
allowing a time-barred application under Section 28-A. Such an order is without jurisdiction and
is liable to be declared null and void.
In view of the aforesaid submissions, it is prayed that this Court may be pleased to allow the
present petition by setting aside the impugned order/Award dated 16.08.2021.
Per contra, learned counsel for the respondents submits that the present writ petition under
Article 226 of the Constitution of India is misconceived and lacks merit, as the impugned order
dated 16.08.2021 has been passed strictly in accordance with law by the competent authority
exercising jurisdiction under Section 28-A of the Land Acquisition Act, 1894. The said provision
is a beneficial one intended to extend the benefit of enhanced compensation to similarly situated
landowners, and therefore deserves liberal interpretation. The respondent fulfilels all statutory
requirements, as the land was acquired under the same notification, compensation was accepted
under protest, and the respondent qualifies as an aggrieved person.
It is further submitted that the application under Section 28-A was filed within limitation after
excluding the time requisite for obtaining the certified copy of the Reference Court award dated
01.05.2000. The authority has recorded a categorical finding to this effect upon due verification
of records, which is a finding of fact not liable to be interfered with in writ jurisdiction. The
contention of the petitioners regarding delay is based on an incorrect computation, and the
authority’s conclusion is both plausible and legally sustainable.
It is also submitted that the respondent cannot be denied enhanced compensation and statutory
benefits on account of administrative delay attributable to the State. Interest and solatium are
statutory entitlements that flow from re-determination of compensation, and the respondent
cannot be penalized for inaction of authorities. The impugned order is reasoned, passed after
affording opportunity to all parties, and does not suffer from any illegality or jurisdictional error.
Hence, the writ petition deserves to be dismissed and the impugned award/order is required to be
upheld.
After hearing the rival contentions and perusing the record, this Court finds that the
controversy involved in the present petition primarily revolves around the exercise of jurisdiction
by the competent authority under Section 28-A of the Land Acquisition Act, 1894, particularly in
relation to the determination of limitation, which is a jurisdictional prerequisite for entertaining
an application for re-determination of compensation. The issue of limitation under Section 28-A
is not merely procedural in nature but goes to the very root of the competence of the authority,
and therefore requires strict scrutiny and a clear, reasoned determination based on the material
available on record.
On perusal of the impugned order dated 16.08.2021, this Court finds that although the
authority has recorded a conclusion that the application filed by respondent No. 2 was within the
prescribed period of limitation, the order does not disclose any cogent reasoning or proper
analysis of the relevant dates and statutory requirements for arriving at such a conclusion. In
particular, the objections raised by the petitioners with regard to the computation of limitation,
including the applicability of exclusion of time for obtaining the certified copy of the Reference
Court award, have not been adequately considered or adjudicated. The absence of a reasoned

Signature Not Verified
Signed by: ASHISH PAWAR
Signing time: 30-07-2026
15:43:28

NEUTRAL CITATION NO. 2026:MPHC-GWL:22624
7 WP-12076-2020
finding on such a vital and jurisdictional issue reflects non-application of mind and renders the
decision-making process flawed.
It is well settled that when a quasi-judicial authority exercises statutory powers affecting
valuable rights of parties, it is under an obligation to pass a reasoned and speaking order dealing
with all material issues raised before it. Failure to do so not only violates principles of natural
justice but also vitiates the order on the ground of arbitrariness. In the present case, the impugned
order falls short of these requirements, as it neither addresses the objections in a meaningful
manner nor provides a clear basis for the conclusions drawn therein.
In such circumstances, this Court is of the considered view that the impugned order dated
16.08.2021 cannot be sustained in law and deserves to be set aside. However, having regard to
the nature of the controversy and the fact that the matter involves determination of factual aspects
as well as application of statutory provisions, this Court does not deem it appropriate to
adjudicate the issue on merits in exercise of its writ jurisdiction under Article 226 of the
Constitution of India. Accordingly, the impugned order dated 16.08.2021 is hereby set aside, and
the matter is remanded to the Sub-Divisional Officer and Land Acquisition Officer, Karera,
District Shivpuri for fresh consideration. The competent authority shall reconsider the application
filed by respondent No. 2 under Section 28-A of the Act afresh, strictly in accordance with law,
and shall specifically deal with and adjudicate upon all objections raised by the petitioners,
including the issue of limitation, by passing a detailed, reasoned and speaking order.
The authority shall afford full and effective opportunity of hearing to all concerned parties and
permit them to place such documents and material on record as may be necessary for proper
adjudication of the matter. It is further directed that the entire exercise shall be completed
expeditiously and in any case within a period of three months from the date of receipt of a
certified copy of this order. It is made clear that all questions of fact and law are left open for
determination by the competent authority, which shall decide the matter independently and
uninfluenced by any observations made by this Court in the present order.
With the aforesaid observations and directions, the present writ petition stands disposed of."

Per contra, learned counsel appearing for the respondents supports the
impugned order and submits that the same has been passed in accordance
with law after considering the relevant material available on record. It is
contended that the respondent fulfills the statutory requirements for seeking
re-determination of compensation under Section 28-A of the Act and no
interference is warranted in exercise of extraordinary jurisdiction under
Article 226 of the Constitution of India.
Heard learned counsel for the parties and perused the record.
The controversy involved in the present petition essentially pertains to
the exercise of jurisdiction by the competent authority under Section 28-A of
the Land Acquisition Act, 1894. The issue of limitation under Section 28-A
Signature Not Verified
Signed by: ASHISH PAWAR
Signing time: 30-07-2026
15:43:28

NEUTRAL CITATION NO. 2026:MPHC-GWL:22624
8 WP-12076-2020
goes to the very root of the jurisdiction of the authority and, therefore,

requires a proper, reasoned and independent consideration.
On perusal of the impugned order dated 31.01.2020, this Court finds
that although the authority has recorded its conclusions while deciding the
application under Section 28-A, the objections raised by the petitioners,
particularly with regard to limitation and other jurisdictional issues, have not
been dealt with in a comprehensive and reasoned manner. The impugned
order does not disclose adequate reasons for rejecting the objections raised
by the petitioners, nor does it demonstrate proper application of mind to the
material questions arising for determination.
It is trite law that every quasi-judicial authority exercising statutory
powers affecting valuable rights of parties is required to pass a reasoned and
speaking order dealing with all material objections. Recording of reasons is
an indispensable component of the principles of natural justice and ensures
transparency and fairness in the decision-making process.
In view of the aforesaid, this Court is of the considered opinion that
the impugned order dated 31.01.2020 cannot be sustained in its present form.
Accordingly, the impugned order dated 31.01.2020 passed by the Sub-
Divisional Officer and Land Acquisition Officer, Karera, District Shivpuri is
hereby set aside.
The matter is remanded to the Sub-Divisional Officer and Land
Acquisition Officer, Karera, District Shivpuri for fresh consideration of the
application under Section 28-A of the Land Acquisition Act, 1894. The
competent authority shall afford due and effective opportunity of hearing to
Signature Not Verified
Signed by: ASHISH PAWAR
Signing time: 30-07-2026
15:43:28

NEUTRAL CITATION NO. 2026:MPHC-GWL:22624
9 WP-12076-2020
all concerned parties, permit them to place such documents and material as

may be considered necessary, and thereafter pass a detailed, reasoned and
speaking order dealing specifically with all objections, including the issue of
limitation, strictly in accordance with law.
The aforesaid exercise shall be completed as expeditiously as possible,
preferably within a period of three months from the date of receipt of a
certified copy of this order.
It is made clear that this Court has not expressed any opinion on the
merits of the controversy.
With the aforesaid direction, aforesaid writ petitions stand disposed
of.
(MILIND RAMESH PHADKE)
JUDGE
(aspr)

Signature Not Verified
Signed by: ASHISH PAWAR
Signing time: 30-07-2026
15:43:28