M/S Ircon International Limited vs Kanchanjunga Construction Co Pv Ltd
- Court
- Delhi High Court
* IN THE HIGH COURT OF DELHI AT NEW DELHI
th
Date of decision: 29 SEPTEMBER, 2026
IN THE MATTER OF:
# CNR No. DLHC010365972023
+ O.M.P. (COMM) 132/2020
M/S IRCON INTERNATIONAL LIMITED .....Petitioner
Through: Mr. K. R. Gupta, Advocate.
versus
KANCHANJUNGA CONSTRUCTION CO PV LTD
.....Respondent
Through: Mr. Animesh Kumar, Mr. Murari
Kumar, Mr. Nishant Kumar, Dr.
Sumit Kumar, Ms. Aprajita, Mr.
Murari Kumar & Mr. Shiv Shankar,
Mr. Yashwardhan Singh, Advocates.
CORAM:
HON'BLE MR. JUSTICE SUBRAMONIUM PRASAD
JUDGMENT
1. The present petition has been filed under Section 34 of the Arbitration
and Conciliation Act, 1996, (herein referred to as the “Act” ) for setting aside
of the for an Arbitral Award dated25.08.2013 (herein referred to as the
“Impugned Award” ) passed by the Learned Sole Arbitrator.
2. Shorn of unnecessary details, facts leading to the filing of the present
petition are enumerated below:
a. The Petitioner herein is a government-owned enterprise and a
public sector undertaking incorporated under the laws of India,
having its Corporate Office at New Delhi. The Respondent,
Kanchanjunga Construction Co. Pvt. Ltd. is a private limited
construction company organised and existing under the statutory
Signature Not Verified
O.M.P. (COMM) 132/2020 Page 1 of 28
Signed By:RAHUL
SINGH
Signing Date:01.10.2026
18:03:20
laws of Nepal, with its registered office in Tinkune, Kathmandu,
Nepal.
b. On 30.03.2005, the Government of Nepal, Department of Roads
(hereinafter referred to as “GON”) entered into a Contract
(Contract No. RNDP/ICB/BC) with the Petitioner for the
execution of the Strengthening of East-West Highway (Belbari-
Chauharwa) Project in Nepal, covering a total road length of 140
Km, with a strictly mandated completion period of 728 days.
c. Following a competitive bidding process, the Petitioner herein sub-
contracted the execution of 50% of the project length to the extend
of 70 Km to the Respondent. In furtherance of the same, the parties
formally executed a Sub-Contract Agreement on 14.03.2006 vide
Agreement No. IRCON/EWH-NEPAL/WORKS/AGREEMENT
NO 3 OF 2006.
d. The initial sub-contract value was Nepalese Rupees (NRs.)
14,10,94,109.90, which was subsequently revised and escalated via
a Variation Order (VO) dated 19.12.2006 to NRs. 20,15,61,285.25.
The works were to commence on 07.03.2006, and the Respondent
was contractually obligated to complete the entire stretch of 70 Km
within periodof 12 months i.e. on or before 06.03.2007.
e. The sub-contract agreement required the Respondent to execute
three primary activities: (a) asphalt concrete overlay on 67 Kms
with varying thicknesses; (b) complete reconstruction from
subgrade to bituminous layers on 3 Kms; and (c) hard shoulder
construction on both sides for the entire 70 Km stretch.
f. Initially under the Contract, the Petitioner was contractually
obligated to supply material including bitumen, base course, and
Signature Not Verified
O.M.P. (COMM) 132/2020 Page 2 of 28
Signed By:RAHUL
SINGH
Signing Date:01.10.2026
18:03:20
aggregates, free of cost to the Respondent, which accounted for
approximately 90% of the raw materials.
g. However, during the first nine months of the contract, the
Petitioner failed to fulfil its obligations and no aggregates or base
course were timely made available. On this account, the
Respondent requested to take over the supply of material which
culminated in a Variation Order signed on 19.12.2006, which
officially shifted the aggregate supply scope onto the Respondent
and led to an adjustment in the contract price accordingly.
h. It is stated that the Respondent experienced critical delays during
the working season due to the Petitioner‟s failure to timeously
erect a contractually required 80 TPH Hot Mix Plant (HMP),
supplying a lower-capacity 60 TPH unit only in late September
2007.
i. Following the commencement of works, the Terai region of Nepal
became highly volatile, experiencing massive civil commotions,
strikes, and political blockades (referred to as “Nepal Bandhs”)
j. From 02.01.2007, the project site was paralyzed by violent
agitations and the Respondent‟s operations were severely disrupted
by systematic extortion of money, forced donations by local armed
gangs and political factions, violent abduction of the Respondent‟s
administrative staff and machine operators, who were held captive
for 28 days, an armed attempt to kidnap the Respondent‟s Project
Representative, which left him with severe head injuries etc.
k. Confronted with this collapse of security, the Petitioner formally
instructed the Respondent to temporarily evacuate its personnel
and attempt to supervise the construction works remotely from
Signature Not Verified
O.M.P. (COMM) 132/2020 Page 3 of 28
Signed By:RAHUL
SINGH
Signing Date:01.10.2026
18:03:20
Itahari, which was located approximately 100 Kilometres away
from the construction site. Due to these events, the original sub-
contract timeline of 12 months was ultimately extended by 3.33
years or 1,215 days i.e. up to the date of contract closure on
30.06.2009.
l. It is stated that the site was closed for a total of 702 days
specifically due to Bandhs and diesel crises. Other reasons
included flooding due to the monsoons that submerged the site for
60 days annually, Local festivals accounting for another 30 days
annually and consequently, out of the 1,215 days and the
Respondent had only 243 workable days. Recognizing these severe
disruptions as entirely beyond the Respondent‟s control, the
Petitioner granted multiple extensions of time without imposing
any liquidated damages or penalties.
m. As the security situation remained unfeasible, the Respondent was
forced to demobilise its equipment and personnel before June
2008. Ultimately, towards the final stages of the Contract, the
Petitioner unilaterally withdrew the Respondent‟s remaining scope
and completed the last leg of works.
n. On 17.07.2008, the Petitioner approached the main Employer, i.e.
GON to foreclose the main contract on an “as is where is” basis,
citing massive idling costs and force majeure. The GON accepted
the foreclosure on 06.08.2008. Following this, the sub-contract
between the Petitioner and the Respondent was formally closed on
30.06.2009.
o. Following the foreclosure of the Contract, two arbitration
proceedings commenced with directly overlapping claims. Under
Signature Not Verified
O.M.P. (COMM) 132/2020 Page 4 of 28
Signed By:RAHUL
SINGH
Signing Date:01.10.2026
18:03:20
the Primary Contract between the Petitioner and the GON, the
Petitioner referred its disputes with the GON to a three-member
UNCITRAL Arbitral Tribunal in Nepal. On 07.05.2013, the three
member Tribunal issued an award in favour of the Petitioner for
NRs. 161,325,119.00. What is relevant to note is that the Tribunal
awarded the Petitioner NRs. 118,075,272.00 as idling
compensation for 315 days due to idling of resources of the
Petitioner.
p. Consequently, disputes arose under the sub-contract between the
Petitioner and the Respondent herein. The Respondent invoked
Clause 72 of the GCC and approached the Managing Director of
the Petitioner for the appointment of an arbitrator. On 07.03.2012
Shri B.K. Makhija was appointed as the Sole Arbitrator
3. The Respondent submitted 11 claims totalling NRs. 22,73,85,115.67,
while the Petitioner raised 4 counterclaims totalling NRs. 15,00,61,966.70
4. On 25.08.201, the Sole Arbitrator issued an award, wherein Claim No.
1 with respect to idling of resources were awarded to the extent of 248 days
in favour of the Respondent. The Arbitrator noted that Clause 71.1 which
was the Force Majeure clause and Clause 19.3 of the SCC strictly barred
claims for damages due to Bandhs or strikes. However, the Arbitrator
observed that the Petitioner had utilized the Respondent‟s idling data to
secure its own award from the Government of Nepal. Furthermore, the
Petitioner‟s representative conceded during hearings that the Petitioner
would accept KCCPL's claim on the same basis as awarded by the Nepal
Tribunal. Grounded in this and the Petitioner‟s own written admission of
248 Bandh days, the Arbitrator accepted Claim No. 1 in principle and
awarded idling compensation for 248 days. Further, the Arbitrator allowed
Signature Not Verified
O.M.P. (COMM) 132/2020 Page 5 of 28
Signed By:RAHUL
SINGH
Signing Date:01.10.2026
18:03:20
Claim No. 4 with respect to Price Adjustment and awarded the Respondent,
NRs. 3,555,133.60 on the ground that the Variation Order un-balanced the
fuel weightage. In addition, the learned arbitrator had also allowed Claim
No. 11 with respect to Interest and awarded compound interest @ 10% per
annum on Claims 1 and 4 from the date of contract closure (June 30, 2009)
to the date of the award (August 25, 2013) and rejected all of the Petitioner‟s
counterclaims.
5. Aggrieved by the award passed by the sole arbitrator, the Petitioner
has preferred the present petition challenging the impugned award passed by
the Learned Arbitrator.
6. The challenge in the present petition pertains to mainly two claims,
i.e. the award of idling/ underutilization cost and (ii) grant of compound
interest on claim 1 and claim 5 by the Learned Arbitrator.
7. At this juncture, it is quintessential to state that the impugned award
being dealt with by this Court was passed prior to the 2015 amendment to
the Act, which means that the scope of interference by this Court would be
judged by the yardstick of the Arbitration regime prior to the 2015
amendment.
8. The appointment in the present case was before the 2015 amendment.
The extension of judicial intervention by a Court under Section 34 of the
Arbitration Act was laid down by the Apex Court in ONGC Ltd. v. Saw
Pipes Ltd., (2003) 5 SCC 705 , wherein the Apex Court has held as under:
“ 74. In the result, it is held that:
(A) (1) The court can set aside the arbitral award under Section
34(2) of the Act if the party making the application furnishes
proof that:
Signature Not Verified
O.M.P. (COMM) 132/2020 Page 6 of 28
Signed By:RAHUL
SINGH
Signing Date:01.10.2026
18:03:20
(i) a party was under some incapacity, or
(ii) the arbitration agreement is not valid under the law to
which the parties have subjected it or, failing any
indication thereon, under the law for the time being in
force; or
(iii) the party making the application was not given proper
notice of the appointment of an arbitrator or of the
arbitral proceedings or was otherwise unable to present
his case; or
(iv) the arbitral award deals with a dispute not
contemplated by or not falling within the terms of the
submission to arbitration, or it contains decisions on
matters beyond the scope of the submission to arbitration.
(2) The court may set aside the award:
(i)
(a) if the composition of the Arbitral Tribunal was not in
accordance with the agreement of the parties,
(b) failing such agreement, the composition of the Arbitral
Tribunal was not in accordance with Part I of the Act.
(ii) if the arbitral procedure was not in accordance with:
(a) the agreement of the parties, or
(b) failing such agreement, the arbitral procedure was not
in accordance with Part I of the Act.
However, exception for setting aside the award on the ground
of composition of Arbitral Tribunal or illegality of arbitral
procedure is that the agreement should not be in conflict with
the provisions of Part I of the Act from which parties cannot
derogate.
(c) If the award passed by the Arbitral Tribunal is in
contravention of the provisions of the Act or any other
substantive law governing the parties or is against the
terms of the contract.
(3) The award could be set aside if it is against the public
policy of India, that is to say, if it is contrary to:
(a) fundamental policy of Indian law; or
Signature Not Verified
O.M.P. (COMM) 132/2020 Page 7 of 28
Signed By:RAHUL
SINGH
Signing Date:01.10.2026
18:03:20
(b) the interest of India; or
(c) justice or morality; or
(d) if it is patently illegal.
(4) It could be challenged:
(a) as provided under Section 13(5); and
(b) Section 16(6) of the Act.
(B)(1) The impugned award requires to be set aside mainly on
the grounds:
(i) there is specific stipulation in the agreement that the
time and date of delivery of the goods was of the essence
of the contract;
(ii) in case of failure to deliver the goods within the period
fixed for such delivery in the schedule, ONGC was entitled
to recover from the contractor liquidated damages as
agreed;
(iii) it was also explicitly understood that the agreed
liquidated damages were genuine pre-estimate of
damages;
(iv) on the request of the respondent to extend the time-
limit for supply of goods, ONGC informed specifically that
time was extended but stipulated liquidated damages as
agreed would be recovered;
(v) liquidated damages for delay in supply of goods were
to be recovered by paying authorities from the bills for
payment of cost of material supplied by the contractor;
(vi) there is nothing on record to suggest that stipulation
for recovering liquidated damages was by way of penalty
or that the said sum was in any way unreasonable.
(vii) In certain contracts, it is impossible to assess the
damages or prove the same. Such situation is taken care of
by Sections 73 and 74 of the Contract Act and in the
present case by specific terms of the contract.”
9. The judgment of the Apex Court in ONGC Ltd. (supra) was
considered in a number of Judgments and was explained in Hindustan Zinc
Ltd. v. Friends Coal Carbonisation, (2006) 4 SCC 445 , wherein the Apex
Signature Not Verified
O.M.P. (COMM) 132/2020 Page 8 of 28
Signed By:RAHUL
SINGH
Signing Date:01.10.2026
18:03:20
Court held that it is open to the court to consider whether the award is
against the specific terms of contract and if so, interfere with it on the
ground that it is patently illegal and opposed to the public policy of India.
10. In McDermott International Inc. v. Burn Standard Co. Ltd., (2006) 11
SCC 181 , the Apex Court dilated on the expression „public policy‟ by
relying on its Judgment in Renusagar Power Co. Ltd. v. General Electric
Co., 1994 Supp (1) SCC 644 , by holding that an arbitral award can be set
aside if it is contrary to (a) fundamental policy of Indian law; (b) the
interests of India; or (c) justice or morality. In McDermott (supra) the Apex
Court has explained the Judgment rendered in Renusagar (supra) by
observing that a narrower meaning to the expression „public policy‟ was
given therein by confining judicial review of the arbitral award only on the
aforementioned three grounds. In McDermott (supra) the Apex Court has
further explained the said principle by placing reliance on the Judgment of
ONGC Ltd. (supra) by adding one more ground to the grounds enumerated
in Renusagar (supra) and has held that Awards can be set aside if they are
patently arbitrary. In McDermott (supra) the Apex Court further went on to
say that patent illegality must go to the root of the matter and that the public
policy violation should be so unfair and unreasonable as to shock the
conscience of the court or where the arbitrator has gone contrary to or
beyond the expressed law of the contract or granted relief in the matter not
in dispute. The same principle was adopted by the Apex Court in
Centrotrade Minerals & Metals Inc. v. Hindustan Copper Ltd., (2006) 11
SCC 245 , wherein the Apex Court while holding that patent illegality must
go to the root of the matter has also held that what would be a public policy
would be a matter which would depend upon the nature of transaction and
Signature Not Verified
O.M.P. (COMM) 132/2020 Page 9 of 28
Signed By:RAHUL
SINGH
Signing Date:01.10.2026
18:03:20
the nature of statute, the pleadings of the parties and the materials brought
on record.
11. In DDA v. R.S. Sharma and Co., (2008) 13 SCC 80 , the Apex Court,
after analysing all the aforementioned decisions, has held as under:
“ 21. From the above decisions, the following principles
emerge:
(a) An award, which is
(i) contrary to substantive provisions of law; or
(ii) the provisions of the Arbitration and
Conciliation Act, 1996; or
(iii) against the terms of the respective contract;
or
(iv) patently illegal; or
(v) prejudicial to the rights of the parties;
is open to interference by the court under Section 34(2)
of the Act.
(b) The award could be set aside if it is contrary to:
(a) fundamental policy of Indian law; or
(b) the interest of India; or
(c) justice or morality.
(c) The award could also be set aside if it is so unfair
and unreasonable that it shocks the conscience of the
court.
(d) It is open to the court to consider whether the
award is against the specific terms of contract and if
Signature Not Verified
O.M.P. (COMM) 132/2020 Page 10 of 28
Signed By:RAHUL
SINGH
Signing Date:01.10.2026
18:03:20
so, interfere with it on the ground that it is patently
illegal and opposed to the public policy of India.”
12. The Apex Court in Associate Builders v. DDA , (2015) 3 SCC 49 , has
further explained the expression „ fundamental policy of Indian law ‟ by
holding that since awards affect the rights of the citizen or leads to any civil
consequences, it is the duty of the Court to adopt „judicial approach‟ in the
matter. The Apex Court has further held that judicial approach ensures that
the authority acts bona fide and deals with the subject in a fair, reasonable
and objective manner and that its decision is not actuated by any extraneous
consideration and that the principle of audi alteram partem has been properly
followed and that the decision must not be so perverse or irrational that no
reasonable persons would have arrived at the same, i.e. the decision must be
based on some evidence and should not ignore vital evidence. In the said
Judgment, the Apex Court has further explained the principle of „ patent
illegality ‟ by observing as under:
“42. In the 1996 Act, this principle is substituted by
the “patent illegality” principle which, in turn, contains
three subheads:
42.1. (a) A contravention of the substantive law of
India would result in the death knell of an arbitral award.
This must be understood in the sense that such illegality
must go to the root of the matter and cannot be of a
trivial nature. This again is really a contravention of
Section 28(1)(a) of the Act, which reads as under:
“28.Rules applicable to substance of dispute.—(1)
Where the place of arbitration is situated in India—
(a) in an arbitration other than an international
commercial arbitration, the Arbitral Tribunal shall
decide the dispute submitted to arbitration in accordance
with the substantive law for the time being in force in
India;”
Signature Not Verified
O.M.P. (COMM) 132/2020 Page 11 of 28
Signed By:RAHUL
SINGH
Signing Date:01.10.2026
18:03:20
42.2. (b) A contravention of the Arbitration Act itself
would be regarded as a patent illegality — for example if
an arbitrator gives no reasons for an award in
contravention of Section 31(3) of the Act, such award will
be liable to be set aside.
42.3. (c) Equally, the third subhead of patent illegality
is really a contravention of Section 28(3) of the
Arbitration Act, which reads as under:
“28.Rules applicable to substance of dispute.—(1)-
(2) *
(3) In all cases, the Arbitral Tribunal shall decide in
accordance with the terms of the contract and shall take
into account the usages of the trade applicable to the
transaction.”
This last contravention must be understood with a caveat.
An Arbitral Tribunal must decide in accordance with the
terms of the contract, but if an arbitrator construes a
term of the contract in a reasonable manner, it will not
mean that the award can be set aside on this ground.
Construction of the terms of a contract is primarily for an
arbitrator to decide unless the arbitrator construes the
contract in such a way that it could be said to be
something that no fair-minded or reasonable person
could do.
”
13. In view of the above parameters, this Court will now proceed to
analyse the grounds taken by the Petitioner assailing the validity of the
Impugned Award.
14. The first challenge to the Impugned Award is against claim 1 awarded
by the Learned Arbitrator with respect to the idling of resources. The
Learned Arbitrator, while allowing the claim partially, observed that during
the initial period of the contract when there was no socio-political
Signature Not Verified
O.M.P. (COMM) 132/2020 Page 12 of 28
Signed By:RAHUL
SINGH
Signing Date:01.10.2026
18:03:20
disturbance, the Respondent did not execute much work and various excuses
were provided by the Respondent for these initial delays which were not
supported by adequate or proper documentation. The only reason furthered
by the Respondent is the delay on account of the Petitioner‟s delay in
installing the Hot Mix Plant. It was observed that the Petitioner proved
through correspondences that the Respondent failed to arrange sufficient
aggregate supplies early on, and that the Variation Order transferring
aggregate supply to the Respondent‟s scope was issued at the Respondent‟s
own specific request, not on account of failure by the Petitioner.
15. It is recorded by the Learned Arbitrator that despite delays in the
completion, the Petitioner ultimately granted extension of time without
imposing any liquidated damages.
16. With respect to the determination of the number of idling days, the
Respondent claimed idling compensation for 702 days. The Learned
Arbitrator observed that the Respondent failed to produce any reliable
documentation during the hearings to support this number stating that their
records were destroyed in riots.
17. A perusal of the Impugned Award discloses that before the Learned
Arbitrator, the Petitioner conceded that the project was affected by 248
bandh days, but argued that under Special Provision Clause 120, 164 days
should be deducted, leaving only 84 days. The Learned Arbitrator rejected
this deduction, observing that Clause 120 strictly governs extensions of time
due to abnormal rainfall and has nothing to do with the stoppages on account
of bandhs. He added that this conclusion was strengthened by the fact that
the Petitioner had granted extensions for periods much longer than 248 days
without liquidated damages. Hence, in the absence of primary records from
the Respondent, the Learned Arbitrator relied on the Petitioner‟s own written
Signature Not Verified
O.M.P. (COMM) 132/2020 Page 13 of 28
Signed By:RAHUL
SINGH
Signing Date:01.10.2026
18:03:20
admissions and calculations to formally assess the number of compensable
idle days at 248 days.
18. The arbitrator noted that the sub-contract lacked any Special Risk or
adverse physical obstruction clauses similar to that in the PrimaryContract
between the Petitioner and the GON. The only applicable clause was the
standard Force Majeure clause, which barred both parties from claiming
damages for non-performance or delay. Hence on the basis of the COC, the
claim of the Respondent was not sustainable.
19. Despite this contractual bar, the Learned Arbitrator proceeded on the
basis of equity and held that the Respondent‟s argument deserved
consideration as its claim was not for extra payment on account of time
extensions, but rather to cover the cost of idle resources that they were
contractually forced to maintain at the site under the Petitioner‟s
instructions, when no work could be performed. The arbitrator observed that
this required consideration because both the Primary contract between the
Petitioner and GON and the Sub-Contract were being executed under
identical, highly volatile regional circumstances.
20. The Learned Arbitrator observed that the Petitioner‟s conduct during
the project aligned with the Respondent‟s logic. During the execution of the
project, the Petitioner had actively directed the Respondent to submit its
idling details, and the Petitioner had subsequently used those very details to
secure its own Arbitral Award for idle resources from the GON. On a
specific query raised by the Learned Arbitrator, the Petitioner‟s
representative formally admitted that the Petitioner will have no issue in
accepting the claim of the Respondent on the same basis as awarded to them
by the Arbitral Tribunal and accepted by GON under the Primary Contract,
provided the Respondent could produce the required documentation.
Signature Not Verified
O.M.P. (COMM) 132/2020 Page 14 of 28
Signed By:RAHUL
SINGH
Signing Date:01.10.2026
18:03:20
21. Relying on the equity of the situation and the Petitioner‟s own
admission, the Learned Arbitrator accepted Claim No. 1 in principle for 248
days. He directed the Petitioner to calculate the final payable amount using
the documentation already in its possession and any additional papers the
Respondent could provide.
22. With respect to this claim, there are three primary arguments taken by
the Petitioner.
23. Firstly, it is the submitted by the Learned Counsel for the Petitioner
that the claim is barred by Clause 19.3 of the SCC as this clause explicitly
stipulates that any extension of time granted on account of Bandhs in Nepal
is an extension of time only, and no claim for any form of extra payment
shall accrue by reason of such extension being granted.
24. Secondly, it is submitted by the Learned Counsel for the Petitioner
that the Learned Arbitrator himself recorded a categorical finding in the
Impugned award that “strictly on the basis of COC [Conditions of
Contract], the claim of KCCPL is not sustainable”. In terms of this finding
returned by the Learned Arbitrator, it is submitted by the learned Counsel for
the Petitioner that as per the unamended Section 28(3) of the Act, the
Arbitral Tribunal must strictly decide in accordance with the terms of the
contract. By departing from the contract to award compensation to the
Respondent on extraneous, equitable considerations, the Learned Arbitrator
acted in clear violation of this statutory mandate.
25. Reliance has been placed on ONGC v. Saw Pipes Ltd., (2003) 5 SCC
705 , to submit that the learned Arbitrator had no power to act in breach of
substantive law or the contract, and any award made outside the contractual
terms is, on the face of it, patently illegal.
Signature Not Verified
O.M.P. (COMM) 132/2020 Page 15 of 28
Signed By:RAHUL
SINGH
Signing Date:01.10.2026
18:03:20
26. Thirdly, it is submitted by the learned Counsel for the Petitioner that
the Learned Arbitrator had partially justified the award by pointing to the
Petitioner‟s conduct during execution, such as requesting the Respondent‟s
idling log books, using those details to secure its own award from GON and
making a conditional admission during hearings. However, it is submitted by
the Learned Counsel for the Petitioner that the terms of a written contract
cannot be varied or changed by the conduct of a party‟s officers. Reliance
has been placed on Tamil Nadu Electricity Board v. N. Raju Reddiar, (1996)
4 SCC 551 , to assert that when a written contract contains all its terms, any
subsequent conduct or concession by officers that detracts from those
written terms is legally inadmissible and not binding on the company.
27. This Court has perused the submissions made by the Petitioner and
the findings of the Learned Arbitrator.
28. The specific contention of the Petitioner is that the Contract
contemplated for extension of time on account of Bandhs in Nepal but did
not provide for any monetary compensation or claims towards idling cost. It
is therefore contended that the learned Arbitrator, while allowing the claim,
the Learned Arbitrator has acted contrary to the mandate of the unamended
Section 28(3) of the Act, as per which, the Learned Arbitrator is strictly
bound by the terms of the Contract while adjudicating the disputes between
the parties, and cannot take into consideration extraneous factors, if the
relief is not specifically provided for in the contract between the parties.
29. Since the Impugned Award was rendered prior to the coming into
force of the 2015 amendment to the Act, it is apposite at this stage to
bifurcate the distinction between the unamended and the amended scope of
Section 28(3) of the Act. The same is reproduced hereunder:
Signature Not Verified
O.M.P. (COMM) 132/2020 Page 16 of 28
Signed By:RAHUL
SINGH
Signing Date:01.10.2026
18:03:20
PRE-AMENDMENT
In all cases, the arbitral tribunal
shall decide in accordance with
the terms of the contract and
shall take into account the usages
of the trade applicable to the
transaction.
POST-AMENDMENT
While deciding and making an
award, the arbitral tribunal
shall, in all cases, take into
account the terms of the
contract and trade usages
applicable to the transaction.
30. This distinction is material in the facts of the present case. A perusal
of both the sections clearly reflects that the scope prior to the amendment
was confined to the scrutiny strictly as per the terms of the contract. This
scope was relaxed post 2015 amendment wherein, the term “shall decide”
has been replaced by “take into account”.
31. In the opinion of this Court, this cannot, on any account, mean that,
even under the unamended Section 28(3), the terms of a contract could not
be construed taking into account the conduct, representations and
admissions of the parties.
32. A perusal of the Impugned Award indicates that the Learned
Arbitrator has proceeded on the premise that the Petitioner‟s representative
had expressly represented that the Petitioner would have no objection in
accepting the Respondent‟s claim on the same basis on which the Petitioner
itself had been awarded the corresponding amount by the tribunal in its
dispute with the Government of Nepal (GON), subject to the Respondent
producing the requisite supporting documentation. In fact, the Learned
Arbitrator noted that the Petitioner had itself asserted and pursued a claim
for idling costs against the GON in the arbitration arising out of the Main
Contract and had relied upon the very documentation furnished by the
Respondent for establishing the consequences of the Nepal Bandhs. Having
itself relied upon such material for securing an award of idling costs from
Signature Not Verified
O.M.P. (COMM) 132/2020 Page 17 of 28
Signed By:RAHUL
SINGH
Signing Date:01.10.2026
18:03:20
the GON, the Petitioner represented before the Learned Arbitrator that it
would not deny the Respondent a corresponding amount, provided the
requisite documentation was produced.
33. In these circumstances, the Learned Arbitrator was justified in
treating the aforesaid representation as an admission made by the Petitioner
in the course of the arbitral proceedings. Significantly, the making of this
representation is not disputed by the Petitioner. The Petitioner‟s objection is
mainly that such an admission or conduct cannot be permitted to operate
contrary to the express terms of the Contract.
34. This submission, in the facts of the present case, cannot be accepted.
This Court is of the opinion that the principle that an arbitral tribunal must
give effect to the terms of the Contract cannot be converted into a licence for
a party to resile from an admission made voluntarily by it during the course
of the arbitral proceedings, particularly where such representation was
founded upon its own conduct under the Main Contract and upon the very
claim which it had itself successfully pursued against the GON.
35. What is even more relevant to note is that the Petitioner had itself
suffered the consequences of the Nepal Bandhs, had itself pursued a claim
for idling costs before the tribunal constituted in the Main Contract
proceedings, and had relied upon the Respondent‟s documentation in
substantiating that claim.
36. This being the case, this Court is of the opinion that the Learned
Arbitrator has proceeded to award cost of idling based on an assurance/
verbal undertaking given by the Petitioner.
37. While terms of the Contract are to be given full effect, the same
cannot be a defence in a case where there is waiver by conduct. As the
Petitioner had succeeded in its claim for idling cost with the GON under the
Signature Not Verified
O.M.P. (COMM) 132/2020 Page 18 of 28
Signed By:RAHUL
SINGH
Signing Date:01.10.2026
18:03:20
main Contact, it cannot now shy away from adhering to a verbal undertaking
made during the course of proceedings before the Learned Arbitrator.
38. Hence, in the opinion of this Court, no interference is warranted as far
as Claim no. 1 is concerned.
39. The next challenge to the impugned award deals with claim 11 with
respect to award of Compound Interest the Learned Arbitrator awarded 10%
compound interest on Claim No. 1 and Claim No. 5 from the date of closure
of contract on 30.06.2009 to the date of the award i.e. 25.08.2013. While
awarding the same, the Learned Arbitrator has observed that although the
contract does not contain an express provision with respect to interest, but
neither was there any stipulation in the Contract which excluded the
payment of interest. Proceeding on this premise, the Learned Arbitrator has
granted Compound Interest on Claim 1 and Claim 5.
40. It is submitted by the Learned Counsel for the Petitioner that
Compound Interest can only be awarded if there is a specific contractual
clause permitting it. In the absence of a contractual agreement with respect
to award of compound interest, the Arbitral tribunal have no general
discretion to award „interest upon interest‟. It is submitted that under Section
3 of the Interest Act, 1978, pre-reference interest can only be allowed if the
claimant had served a formal written notice demanding interest from a
specific date. As the Respondent never served such a notice, the award of
pre-reference interest is legally unsustainable.
41. In addition, it is the specific contention of the learned counsel for the
Petitioner that there is no provision in the Act, specifically Section 31 for
granting compound interest. It is contended that even if the Learned
Arbitrator possessed the power to award interest, such power could only be
to the extend of granting simple interest and not compound interest.
Signature Not Verified
O.M.P. (COMM) 132/2020 Page 19 of 28
Signed By:RAHUL
SINGH
Signing Date:01.10.2026
18:03:20
42. In view of the aforesaid submissions, the question which arises for
consideration before this Court is whether, in the absence of a contractual
prohibition against interest, an arbitral tribunal exercising jurisdiction under
Section 31(7) of the Act possesses the power to award compound interest for
the period between the accrual of the cause of action and the date of the
award.
43. At the outset, it is apposite to delineate the power of the Arbitral
Tribunal to award interest. The Arbitral tribunal under Section 31(7) is
bestowed with the power to award interest. For the sake of reference, the
same is reproduced hereunder:
“31(7) (a) Unless otherwise agreed by the parties, where
and in so far as an arbitral award is for the payment of
money, the arbitral tribunal may include in the sum for
which the award is made interest, at such rate as it deems
reasonable, on the whole or any part of the money, for the
whole or any part of the period between the date on
which the cause of action arose and the date on which the
award is made.
[(b) A sum directed to be paid by an arbitral award shall,
unless the award otherwise directs, carry interest at the
rate of two per cent higher than the current rate of
interest prevalent on the date of award, from the date of
award to the date of payment.
Explanation.—The expression “current rate of interest”
shall have the same meaning as assigned to it under
clause (b) of section 2 of the Interest Act, 1978 (14 of
1978).]”
44. As the Learned Arbitrator has awarded 10% compound interest for the
pendente lite period i.e. from the date of cause of action till the date of the
award, this Court is primarily concerned with Section 31(7)(a) of the Act.
Signature Not Verified
O.M.P. (COMM) 132/2020 Page 20 of 28
Signed By:RAHUL
SINGH
Signing Date:01.10.2026
18:03:20
45. Sub clause (a) of Section 31(7) begins with the proviso “unless
otherwise agreed between the parties ”. This is to say, that unless parties by
contract have excluded the entitlement of either of the parties to grant of
interest, the Arbitral Tribunal has the discretion to award the same on the
principal amount.
46. It is the case of the Petitioner that Interest could not have been
granted by the Learned Arbitrator as there was no clause in the Contract
between the parties for grant of interest. This submission of the Learned
Counsel for the Petitioner cannot be accepted by this Court. While it is true
that there was no clause in the Contact entitling either parties to award of
interest, the expression “unless otherwise agreed by the parties” does not
contemplate that an express contractual provision conferring a right to
interest must necessarily exist before the tribunal can exercise its statutory
power. In fact, where the Contract is silent, the statutory discretion under
Section 31(7)(a) remains available to the arbitral tribunal. Thus, there is a
material distinction between a Contract which prohibits or excludes interest
and a Contract which is merely silent as to interest. Silence cannot, by itself,
be elevated to an express contractual prohibition. If the parties intended to
exclude the statutory power of the tribunal to award interest, they were at
liberty to so stipulate. In the absence of such exclusion, the jurisdiction
conferred by Section 31(7)(a) remains available to the tribunal.
47. The aforesaid interpretation of the section is in consonance with the
judgement of the Apex Court in Delhi Airport Metro Express (P) Ltd. v.
DMRC , (2022) 9 SCC 286 , wherein it has observed as under:
“17. It could thus be seen that the part which deals
with the power of the Arbitral Tribunal to award interest,
would operate if it is not otherwise agreed by the parties.
If there is an agreement between the parties to the
Signature Not Verified
O.M.P. (COMM) 132/2020 Page 21 of 28
Signed By:RAHUL
SINGH
Signing Date:01.10.2026
18:03:20
contrary, the Arbitral Tribunal would lose its discretion
to award interest and will have to be guided by the
agreement between the parties. The provision is clear
that the Arbitral Tribunal is not bound to award interest.
It has a discretion to award the interest or not to award.
It further has a discretion to award interest at such rate
as it deems reasonable. It further has a discretion to
award interest on the whole or any part of the money. It
is also not necessary for the Arbitral Tribunal to award
interest for the entire period between the date on which
the cause of action arose and the date on which the
award is made. It can grant interest for the entire period
or any part thereof or no interest at all.
18. We find that in the present case, the words “unless
otherwise agreed by the parties” would assume
significance. The said words fell for consideration before
this Court in N.S. Nayak & Sons v. State of Goa [N.S.
Nayak & Sons v. State of Goa, (2003) 6 SCC 56] . This
Court in the said case had an occasion to consider the
scope of the phrase “unless otherwise agreed by the
parties” in various provisions of the 1996 Act. This Court
observed thus : (SCC p. 63, para 14)
“14. … The phrase „unless otherwise agreed by the
parties‟ used in various sections, namely, 17, 21, 23(3),
24(1), 25, 26, 29, 31, 85(2)(a), etc. indicates that it is
open to the parties to agree otherwise. During the
arbitral proceedings, right is given to the parties to
decide their own procedure. So if there is an agreement
between the parties with regard to the procedure to be
followed by the arbitrator, the arbitrator is required to
follow the said procedure. Reason being, the arbitrator is
appointed on the basis of the contract between the parties
and is required to act as per the contract. However, this
would not mean that in appeal parties can contend that
the appellate procedure should be as per their
agreement.”
Signature Not Verified
O.M.P. (COMM) 132/2020 Page 22 of 28
Signed By:RAHUL
SINGH
Signing Date:01.10.2026
18:03:20
19. This Court in Sree Kamatchi Amman
Constructions v. Railways [Sree Kamatchi Amman
Constructions v. Railways, (2010) 8 SCC 767 : (2010) 3
SCC (Civ) 575] had an occasion to directly consider the
aforesaid phrase as employed by the legislature in sub-
section (7) of Section 31 of the 1996 Act. R.V.
Raveendran, J. in the said case observed thus : (SCC p.
774, para 19)
“19. Section 31(7) of the new Act by using the words
„unless otherwise agreed by the parties' categorically
clarifies that the arbitrator is bound by the terms of the
contract insofar as the award of interest from the date of
cause of action to the date of award. Therefore, where the
parties had agreed that no interest shall be payable, the
Arbitral Tribunal cannot award interest between the date
when the cause of action arose to the date of award.”
(emphasis in original)
20. If clause (a) of sub-section (7) of Section 31 of the
1996 Act is given a plain and literal meaning, the
legislative intent would be clear that the discretion with
regard to grant of interest would be available to the
Arbitral Tribunal only when there is no agreement to the
contrary between the parties. The phrase “unless
otherwise agreed by the parties” clearly emphasises that
when the parties have agreed with regard to any of the
aspects covered under clause (a) of sub-section (7) of
Section 31 of the 1996 Act, the Arbitral Tribunal would
cease to have any discretion with regard to the aspects
mentioned in the said provision. Only in the absence of
such an agreement, the Arbitral Tribunal would have a
discretion to exercise its powers under clause (a) of sub-
section (7) of Section 31 of the 1996 Act. The discretion is
wide enough. It may grant or may not grant interest. It
may grant interest for the entire period or any part
thereof. It may also grant interest on the whole or any
part of the money.”
Signature Not Verified
O.M.P. (COMM) 132/2020 Page 23 of 28
Signed By:RAHUL
SINGH
Signing Date:01.10.2026
18:03:20
48. Consequently, the Learned Arbitrator cannot be faulted merely for
having proceeded on the basis that the absence of an interest clause did not,
by itself, constitute a prohibition against the grant of interest. The relevant
enquiry is whether the parties had agreed otherwise so as to exclude or
regulate the statutory power under Section 31(7)(a). The same has not been
demonstrated.
49. The second limb of the argument of the Learned Counsel for the
Petitioner was thatif interest, at all could be granted, it could have only been
done at the rate of simple interest and not compound interest.
50. The Learned Counsel for the Petitioner has placed reliance on the
judgement of State of Haryana v. S.L. Arora & Co., (2010) 3 SCC 690 to
substantiate its argument that compound interest cannot be granted by an
arbitrator in absence of a contractual stipulation.
51. The Court has perused the judgement of S.L. Arora & Co. (supra).
While reliance has been placed by the Petitioner on this judgement,
however, the same has been overruled by the subsequent judgement of the
Apex Court in Hyder Consulting (UK) Ltd. v. State of Orissa, (2015) 2 SCC
189 . Relevant paragraphs of the said judgment are reproduced hereunder:
PARA 15-21
“15. In such a situation one is reminded of the
decision in Ganga Prasad Verma v. State of Bihar [1995
Supp (1) SCC 192 : 1995 SCC (L&S) 383 : (1995) 29
ATC 154] , wherein this Court held that : (SCC p. 195,
para 5)
“5. Where the language of the Act is clear and
explicit, the court must give effect to it, whatever may be
the consequences, for in that case the words of the statute
speak the intention of the legislature.”
Similarly, in Keshavji Ravji & Co. v. CIT [(1990) 2 SCC
231 : 1990 SCC (Tax) 268] , a three-Judge Bench of this
Signature Not Verified
O.M.P. (COMM) 132/2020 Page 24 of 28
Signed By:RAHUL
SINGH
Signing Date:01.10.2026
18:03:20
Court explained the rule of literal interpretation as under
: (SCC p. 242, para 11)
“11. … If the intendment is not in the words used it is
nowhere else. The need for interpretation arises when the
words used in the statute are, on their own terms,
ambivalent and do not manifest the intention of the
legislature.”
16. We may also refer to the decision of the Privy
Council in Pakala Narayana Swami v. King
Emperor [(1938-39) 66 IA 66 : (1939) 49 LW 349 : AIR
1939 PC 47] , wherein Lord Atkin observed that : (IA p.
78)
“… when the meaning of words is plain, it is not the
duty of courts to busy themselves with supposed
intentions.”
This view was upheld recently by this Court in T.N.
SEB v. Central Electricity Regulatory
Commission [(2007) 7 SCC 636] .
17. In fact the settled view on this subject has been to
admit results of construction even if they be strange or
surprising [London Brick Co. Ltd. v. Robinson, 1943 AC
341 : (1943) 1 All ER 23, p. 26 (HL)] , unreasonable or
unjust or oppressive [IRC v. Hinchy, 1960 AC 748 :
(1960) 2 WLR 448 : (1960) 1 All ER 505, pp. 508 & 512
(HL)] . The Privy Council in King Emperor v. Benoari
Lal Sarma [(1944-45) 72 IA 57 : (1945) 58 LW 64 : AIR
1945 PC 48] , (AIR p. 53), emphasised : (IA p. 71)
“… Again and again, this Board has insisted that in
construing enacted words we are not concerned with the
policy involved or with the results, injurious or otherwise,
which may follow from giving effect to the language
used.”
18. In Nasiruddin v. Sita Ram Agarwal [(2003) 2 SCC
577] , SCC para 37, a three-Judge Bench of this Court,
made it clear that the Court's jurisdiction cannot be
invoked to interpret a statute so as to add or subtract
Signature Not Verified
O.M.P. (COMM) 132/2020 Page 25 of 28
Signed By:RAHUL
SINGH
Signing Date:01.10.2026
18:03:20
words or read something into a provision which is not
there.
19. In fact, Maxwell on the Interpretation of Statutes,
states:
“Where the language is plain and admits of but one
meaning, the task of interpretation can hardly be said to
arise. „The decision in this case‟, said Lord Morris of
Borth-y-Gest in a revenue case, „calls for a full and fair
application of particular statutory language to particular
facts as found. The desirability or the undesirability of
one conclusion as compared with another cannot furnish
a guide in reaching a decision.‟ [Shop and Store
Developments Ltd. v. IRC, (1967) 1 AC 472 at p. 493 :
(1967) 2 WLR 35 : (1967) 1 All ER 42 (HL), per Lord
Morris of Borth-y-Gest. But see IRC v. Bates, (1965) 1
WLR 1133 : (1965) 3 All ER 64 (CA), per Lord Denning
M.R., affirmed in Bates v. IRC, 1968 AC 483 : (1967) 2
WLR 60 : (1967) 1 All ER 84 (HL); Luke v. IRC, 1963 AC
557 : (1963) 2 WLR 559 : (1963) 1 All ER 655 (HL), per
Lord Reid.] Where, by the use of clear and unequivocal
language capable of only one meaning, anything is
enacted by the legislature, it must be enforced however
harsh or absurd or contrary to common sense the result
may be. [Cartledge v. E. Jopling & Sons Ltd., 1963 AC
758 : (1963) 2 WLR 210 : (1963) 1 All ER 341 (HL).
Cf. Miller v. Salomons, (1852) 7 Ex 475 : 155 ER 1036,
per Pollock C.B.; British Farmers Pure Linseed Cake
Co., In re, (1878) LR 7 Ch D 533 : (1878) 48 LJ Ch 56
(CA), per Jessel M.R.; Magor and St. Mellons
RDC v. Newport Corpn., 1952 AC 189 : (1951) 2 All ER
839 (HL)] The interpretation of a statute is not to be
collected from any notions which may be entertained by
the court as to what is just and expedient :
[Gwynne v. Burnell, (1840) 7 Cl & Fin 572 : 7 ER 1188
(HL) per Coleridge, J.] words are not to be construed,
contrary to their meaning, as embracing or excluding
cases merely because no good reason appears why they
Signature Not Verified
O.M.P. (COMM) 132/2020 Page 26 of 28
Signed By:RAHUL
SINGH
Signing Date:01.10.2026
18:03:20
should not be embraced or excluded.
[Whitehead v. James Stott & Co., (1949) 1 KB 358 :
(1949) 1 All ER 245 (CA); Galashiels Gas Co.
Ltd. v. O'Donnell, 1949 AC 275 : (1949) 1 All ER 319
(HL)] ”
20. Tindal, C.J. in Sussex Peerage case [(1844) 11 Cl
& Fin 85, p. 143 : (1843-60) All ER Rep 55 : 8 ER 1034
(HL)] , summarised this principle as follows : (ER p.
1057)
“… If the words of the statute are in themselves
precise and unambiguous, then no more can be necessary
than to expound those words in their natural and
ordinary sense. The words themselves alone do, in such
case, best declare the intention of the lawgiver.”
This cardinal principle of construction was first stated by
the United States Supreme Court in its landmark decision
of Caminetti v. United States [61 L Ed 442 : 242 US 470
(1917)] , US p. 485, whereby Day, J. observed : (L Ed p.
453)
“Where the language is plain and admits of no more
than one meaning, the duty of interpretation does not
arise….”
21. In the result, I am of the view that S.L. Arora
case [State of Haryana v. S.L. Arora and Co., (2010) 3
SCC 690 : (2010) 1 SCC (Civ) 823] is wrongly decided
in that it holds that a sum directed to be paid by an
Arbitral Tribunal and the reference to the award on the
substantive claim does not refer to interest pendente lite
awarded on the “sum directed to be paid upon award”
and that in the absence of any provision of interest upon
interest in the contract, the Arbitral Tribunal does not
have the power to award interest upon interest, or
compound interest either for the pre-award period or for
the post-award period. Parliament has the undoubted
power to legislate on the subject and provide that the
Arbitral Tribunal may award interest on the sum
directed to be paid by the award, meaning a sum
Signature Not Verified
O.M.P. (COMM) 132/2020 Page 27 of 28
Signed By:RAHUL
SINGH
Signing Date:01.10.2026
18:03:20
inclusive of principal sum adjudged and the interest,
and this has been done by Parliament in plain
language .” (emphasis supplied)
52. A perusal of the judgement of Hyder Consulting (UK) Ltd, ( supra ),
indicates that the Learned Arbitrator has the power to grant compound
interest for the pre-award as well as the post award period.
53. Further, Section 31(7)(a) of the Act states “at such rate as it deems
reasonable ”. In fact, the provision does not contain any statutory
classification between “simple” and “compound” There is no classification
of interest provided in the statute. In such a case, interest may be at a simple
or a compounded rate, whatever the Learned Arbitrator deems reasonable.
54. In the present case, the Learned Arbitrator has exercised the
discretion conferred by Section 31(7)(a), has awarded interest at 10% per
annum for a defined period, and there is no demonstrated contractual
prohibition against the grant of such interest. The award of compound
interest, considered in the light of the law laid down in Hyder Consulting
(UK) Ltd, ( supra ) cannot therefore be said to be without jurisdiction.
55. In light of the same, no interference is warranted with respect to
Claim No. 11.
56. Accordingly, the present petition is dismissed, with pending
applications, if any.
SUBRAMONIUM PRASAD, J
SEPTEMBER 29, 2026