AL RAFIQ EDU. TECH PVT. LTD. AND OTHERS vs UNION TERRITORY OF J AND K AND OTHERS (RURAL DEVELOPMENT)

Court
Jammu and Kashmir High Court

HIGH COURT OF JAMMU &KASHMIR AND LADAKH AT
SRINAGAR
Reserved on: 18.11.2026
Pronounced on: 27.11.2026
Uploaded on: 27.11.2026
Whether the operative part or full
judgment is pronounced: Full
WP(C) No.2588/2026
AL RAFIQ EDU. TECH. PVT. LTD. & ORS.
...PETITIONER(S)
Through: - Mr. Mohammad Ibrahim Mehraj, Advocate.
Vs.
UT OF J&K & OTHERSS …RESPONDENT(S)
Through: - MS. Monika Kohli, Sr. AAG, with
Ms. Sagira, Advocate.
CORAM:
HON’BLE MR. JUSTICE SANJAY DHAR, JUDGE
JUDGMENT
1) The petitioners, who claim to be Project Implementing
Agencies (PIAs) engaged in the field of skill development,
training and placement, have filed the present writ petition
challenging minutes of meeting and recommendation dated
24.08.2026, whereby their applications have been rejected
and allocation of targets in their favour has been deferred. A
further direction commanding the respondents to allocate the
targets to the petitioners as per their eligibility and as per the
SOP of the Himayat Mission and guidelines of Phase II, has
also been sought.
WP(C) No.2588/2026 Page 1 of 12

2) According to the petitioners, they are Project
Implementing Agencies (PIAs) engaged in the field of skill
development, training and placement and that they possess
the requisite infrastructure, trained manpower and
operational capacity for implementation of skill development
programs within Union Territory of Jammu and Kashmir. It
has been submitted that the respondents issued Expression
of Interest (EOI) dated 16.05.2025, by virtue of which
proposals were invited for implementation of Deen Dayal
Upadhyaya Grameen Kaushalya Yojana (Himayat) in the
Union Territory of J&K. The said EOI was followed by a
corrigendum dated 09.07.2025 and an extension notice dated
16.07.2025.
3) The petitioners participated in the aforesaid process and
submitted their proposals in accordance with requirements
prescribed by the respondents. They also deposited appraisal
fees amounting to Rs.1,47,500 and paid an amount of
Rs.29,500 as application fees to the respondents. The
petitioners thereafter participated in the process of appraisal
and they were declared qualified, whereafter they were
directed to await allocation of training targets.
th
4) By virtue of 5 meeting of the Apex Committee for
Himayat, 2248 candidates were allocated to the Project
WP(C) No.2588/2026 Page 2 of 12

Implementing Agencies (PIAs) to the exclusion of the
petitioners, who were asked to wait till allocation of more
targets. However, the respondents issued another Expression
of Interest dated 16.05.2026 inviting project proposals from
eligible PIAs for implementation of Himayat (DDU-GKY 2.0)
for the financial years 2026-2028. The EOI contemplated
consideration of eligible PIAs in accordance with applicable
Himayat/DDU-GKY 2.0 guidelines and Standard Operating
Procedure. Since the petitioners had already been declared as
eligible in pursuance of the first pack, as such, scrutiny of
their proposals along with fresh bidders of second EOI was
made by the respondents and the assessment was placed
before the Apex Committee, but this time again the
applications of the petitioners were rejected.
5) According to the petitioners, they have established
operational presence and they possess the requisite
infrastructure, trained manpower, local understanding,
mobilization network and other resources necessary for
implementation of skill development programs in the Union
Territory of J&K and that they have always remained ready
and willing to undertake the program. The petitioners made a
representation dated 31.08.2026 with the respondents
specifically bringing to their notice that they fulfill all the
prescribed requirements and requested that appropriate
WP(C) No.2588/2026 Page 3 of 12

training targets be allocated in their favour in accordance
with the applicable framework.
6) It has been submitted that the petitioners have now
come to know that training targets/projects have been
allocated to various Project Implementing Agencies (PIAs)
falling in A and B categories only, whereas the petitioners fall
in category ‘C’. The petitioners sought clarification from the
respondents vide their legal notice dated 31.08.2026 and
subsequent communication dated 01.09.2026 as also the
details of the basis and criteria adopted for allocation of
targets, but the respondents have not responded to the same.
It has been contended that the petitioners have right to be
considered for allocation of targets in accordance with the
framework of the scheme, but their applications have been
rejected for an undisclosed criteria.
7)
The petitioners have challenged their exclusion from
allocation of training targets on the grounds that the same is
arbitrary and unexplained. It has been contended that the
respondents have not disclosed the criteria or basis on which
the petitioners have been excluded. It has been contended
that once the petitioners had qualified upon being assessed
and appraised, they were entitled to a fair and meaningful
consideration of their candidature in accordance with the
WP(C) No.2588/2026 Page 4 of 12

criteria governing the process. It has been submitted that
merely because the petitioners fall in ‘C’ category, the
respondents could not have excluded them from
consideration.
8) The respondents have contested the writ petition by
filing their reply to the same. In their reply, the respondents
have submitted that appraisal, evaluation, prioritization and
sanction of project proposals under Himayat (DDU-GKY 2.0)
are governed by the applicable guidelines, Standard
Operating Procedures and notifications issued by Ministry of
Rural Development from time to time. It has been submitted
that while inviting project proposals vide EOI dated
16.05.2025, it was made expressly clear to the applicants to
formulate and submit their proposals in strict compliance
with applicable SOPs and guidelines. In this regard, Clause
(5) of the EOI is being relied upon by the respondents.
9) It has been submitted that in the subsequent EOI dated
16.05.2026, compliance with the applicable guidelines and
SOPs was reiterated. It is being contended that the petitioners
also acknowledged the applicability of guidelines and SOPs
and, therefore, they were fully aware that consideration and
sanction of project proposals are governed by the prescribed
framework. It has been submitted that the petitioners
WP(C) No.2588/2026 Page 5 of 12

submitted their project proposals under category ‘C’ (priority
‘C’). According to the respondents, the categorization of PIAs
and corresponding project size and funding provisions
prescribed under Table 8, Section 7.2 of the guidelines read
with Standard Instruction 1.9 of the SOPs provide that
priority ‘A’ has to be assigned to captive employer, priority ‘B’
has to be assigned to existing skilling agencies having
experience of greater than 50% placement outcome
achievement, and priority ‘C’ is to be given to skilling agencies
that do not have any DDU-GKY experience, whereas priority
‘D’ is to be given to startups for skilling recognized by
Department of Industrial Policy and Promotion, Ministry of
Commerce and Industry, Government of India. It has been
submitted that Section 7.1 of DDU-GKY Guidelines 2.0
classifies all PIAs into four categories A, B, C and D, based on
their past experience and ability to deliver quality placements.
It has been submitted that further prioritization is carried out
within these categories. Thus, a PIA in category ‘A’ is
prioritized over those in category ‘B’, category ‘B’ PIA is
prioritized over category ‘C’ and so on, with category ‘D’ being
the least prioritized.
10) It has been submitted that the respondents have acted
in accordance with the aforesaid prescribed framework. It has
further been contented that the available project targets were
WP(C) No.2588/2026 Page 6 of 12

sanctioned to 52 category ‘B’ PIAs and no targets remained
available for allocation to category ‘C’ PIAs. It has been
submitted that because the petitioners fall in category ‘C’
PIAs, as such, they cannot claim an automatic or preferential
right to sanction merely on the basis of submission of their
proposals.

11) The respondents have further contended that the
petitioners have no vested or enforceable right to claim
sanction of their project proposals, as mere submission of a
proposal does not confer any right to sanction. It has been
submitted that every project is required to be considered in
accordance with the applicable SOPs, guidelines, prescribed
eligibility conditions, category wise prioritization and
availability of approved targets. It has further been contended
that there is no illegality in the action of the respondents
warranting interference from this Court. It has further been
submitted that interference with the execution of approved
projects at this stage would jeopardize the timely
commencement and completion of training and disrupt the
achievement of allocated targets. The respondents have
further contended that the petitioners have not impleaded the
affected PIAs as parties to the present writ petition and,
therefore, the writ petition suffers from non-joinder of
necessary parties. According to the respondents, any order
WP(C) No.2588/2026 Page 7 of 12

that may be passed by this Court is going to affect the rights
of PIAs in whose favour projects have been approved, as such,
they are necessary parties to the present writ petition.
12) I have heard learned counsel for the parties and perused
record of the case.
13) The dispute raised by the petitioners in the present writ
petition lies in a narrow compass. The petitioners, admittedly,
fall in category ‘C’ of PIAs. It is also not in dispute that
allocation of project targets is governed by the terms and
conditions laid down in applicable guidelines, SOPs and
notifications issued by the Ministry of Rural Development
Department from time to time. This is clearly spelled out in
Expression of Interest dated 16.05.2025 and 16.05.2026.
Standard Instruction No.1.9 categorizes the PIAs in four
categories. The relevant table is reproduced as under:
No. Category
Eligibility Criteria Project six & period
of PIA
1 Priority A
Captive Employer
-Maximum Project Target
5000 or 40% of Human
Resource of Captive
Employer registered with
ESIC or PF, whichever is
lower

-Project period of three
years
-Batch-wise funding
2 Priority B
Existing Agencies Skilling
having experience of
greater than 50%
placement outcome
achievement.
Maximum Project Target of
10,000 should not exceed at
any given point of time.

Individual Project Size
capped at 1200 target, with
WP(C) No.2588/2026 Page 8 of 12

the condition of continuous

top up sanction based on
outcome achievement or
based on capacity created by
performing DDU-GKY PIAs in
the State
-Project period of three years
-Batch-wise funding
3 Priority C
Skilling Agencies that do
not have any DDU-GKY
experience
-Maximum Project Target
3,000 should not exceed at
any given point of time.

-Individual Project Size
capped at 1200 target, with
the condition of continuous
top up sanction based on
outcome achievement.
-Project period of three years
- Batch wise funding.
4 Priority D
Start-ups for skilling
recognized by Dept of
Industrial Policy &
Promotion, Ministry of
Commerce & Industry.
Gol
-Maximum Project Size
capped at 1200 target, with
the condition of continuous
top up sanction based on
outcome achievement.

-Project period of three years

- Batch wise funding
14) Methodology for ascertaining ranking of project
proposals by PIAs is mentioned in Standard Instruction
No.1.14, which reads as under:
"Standard Instruction 1.14 Methodology for
ascertaining ranking of project proposals by PIAs.
Priority of PIAs: Section 7.1 of the DDU-GKY Guidelines
2.0 classifies all PIAs into four categories-A, B, C, and
D-based on their past experience and ability to deliver
quality placements. Further prioritization is carried out
within these categories (A, B, C, and D) based on the
DDU-GKY project proposal submitted. As a result, a PIA
in Category A is prioritized over those in Category B, a
Category B PIA is prioritized over those in Category C,
and so on, with Category D being the least prioritized."
15) From a perusal of the aforesaid instructions, it is clear
that PIAs are categorized into four groups. Priority ‘A’ is to be
WP(C) No.2588/2026 Page 9 of 12

given to the captive employer, priority ‘B’ is to be given to
category ‘B’ PIAs, priority ‘C’ is to be given to category ‘C’ PIAs
and priority ‘D’ is to be given to category ‘D’ PIAs. It is also
clear that maximum project targets, 5,000 or 40% of human
resource of captive employer registered with ESIC or PF, is to
be given to captive employer which falls in the category of
priority ‘A’. For priority ‘B’, maximum project target of 10,000
has to be given at any given point of time.
16) In the present case, as per the petitioners' own version,
in the year 2025, 2248 candidates were allocated and in the
year 2026, the number of candidates, who were allocated
training targets, was 24,228. As per Table 8 quoted above, in
category ‘B’, individual project size is capped at 1200 and 52
PIAs under category ‘B’ had qualified. A perusal of the
impugned minutes of the meeting would reveal that the
respondents have capped the individual project size
maximum at 510, amongst 52 qualified PIAs, as a result of
which all the 24,228 candidates stand allocated to PIAs falling
in category ‘B’, leaving behind no further candidate who could
be allocated to a PIA under category ‘C’.
17) As already stated, that, as per the guidelines, priority
has been fixed and it is only in case a PIA under categories ‘A’
and ‘B’ is not available that project targets can be allocated to
WP(C) No.2588/2026 Page 10 of 12

a PIA falling under category ‘C’. These guidelines and
instructions were well within the knowledge of the petitioners
and they took the risk and applied pursuant to the EOI. They
cannot now turn around and resile from the rigours of the
terms and conditions of EOI. The respondents have accorded
consideration and allocated the project targets strictly in
accordance with the SOPs on both occasions, i.e. in the
meeting held on 27.11.2025, when 2195 targets were
allocated to 13 category ‘B’ PIAs, and on 24.08.2026, when
24,228 targets were allocated to 52 category ‘B’ PIAs.
18) The petitioners, having participated in the process
governed by the guidelines and SOPs forming part of the
scheme, cannot selectively accept the framework for
establishing their eligibility and reject the same in so far as it
governs the prioritization and allocation of project targets.
Union of India and & Ors
The Supreme Court in the case of .
v. N. Murugesan Etc. (2022) 2 SCC 25 has clearly held that
a person cannot be allowed to have the benefit of an
instrument while questioning the same. It has been held that
a party either has to affirm or disaffirm a transaction and the
principle has to be applied with more vigor as a common law
principle if such a party actually enjoys the one part fully on
near completion of the said enjoyment, thereafter questions
the other part. Similar view has been taken by the Supreme
WP(C) No.2588/2026 Page 11 of 12

Court in the cases of Rajasthan State Industrial
Development and Investment Corporation & Anr . v.
Diamond and Gem Development Corporation Ltd. & Anr.
(2013) 5 SCC 470, and M/S Cauvery Coffee Traders,
Mangalore v . M/S Hornor Resources (Intern.) Co. Ltd. ,
( 2011) 10 SCC 420

19) As already stated, in the instant case the petitioners
have not been able to show any procedural irregularity or
non-adherence to the SOPs by the respondents while
allocating the project targets. Therefore, it is not open to this
Court to undertake a judicial review of the impugned action
of the respondents, particularly when the entities, to whom
the projects have been allocated, have not even been made
parties to the present writ petition.
20) For the foregoing reasons, I do not find any merit in this
writ petition. The same is dismissed accordingly along with
connected CM(s) .
(Sanjay Dhar)
Judge
SRINAGAR
27.11.2026