The State of Bihar vs M/s. Balaji Enterprises
- Court
- Patna High Court
IN THE HIGH COURT OF JUDICATURE AT PATNA
Letters Patent Appeal No.865 of 2024
In
Civil Writ Jurisdiction Case No.11678 of 2023
======================================================
1. The State of Bihar through the Chief Secretary, Government of Bihar, Old
Secretariat Building, Patna.
2. The Additional Chief Secretary-cum- Commissioner Mines, Department of
Mines and Geology, Government of Bihar, Vikas Bhawan, Bailey Road,
Patna.
3. The District Magistrate, Sheikhpura.
4. The Mineral Development Officer, Sheikhpura.
... ... Appellant/s
Versus
M/s. Balaji Enterprises a Proprietorship Firm having its Registered Office at
Babu Bazar, Ara, Bhojpur through its Signing Authority Sri. Chandan Kumar,
aged about 35 years, Gender- Male, Son of Sri Ashok Kumar, resident of
Village and Post- Pareo, P.S.- Bihita, District- Patna- 802160.
... ... Respondent/s
======================================================
Appearance :
For the Appellant/s : Mr. S.D. Sanjay, Advocate General
Mr. Prakash Chandra Agrawal, GA-5
Ms. Surbhi Agrawal, JC to GA-5
For the Respondent/s : Mr. Suraj Samdarshi, Advocate
Mr. Avinash Shekhar, Advocate
Ms. Simran Kumari, Advocate
Ms. Abhilasha Jha, Advocate
======================================================
CORAM: HONOURABLE MR. JUSTICE BIBEK CHAUDHURI
and
HONOURABLE MR. JUSTICE RANA VIKRAM SINGH
C.A.V. JUDGMENT
(Per: HONOURABLE MR. JUSTICE BIBEK CHAUDHURI)
Date : 01-10-2026
1. An application for stay in connection with the
instant appeal and application dated 02.09.2026 filed by the
respondent/ writ-petitioner with a prayer to direct the appellants
not to proceed with the auction and settlement of Stone Block
No.27 situated at Mauza-Hazratpur Mandro Chandi, Area-5
Patna High Court L.P.A No.865 of 2024 dt.01-10-2026
2/32
hectares at District-Shaikhpura, mentioned at Serial No.11 in the
notice inviting tender dated 13.08.2026 were fixed for hearing
on 25.09.2026.
2. At the time of hearing of the applications above-
named, we were of the view that the instant appeal can be
disposed of on the basis of the submission made by the learned
Counsels for the parties.
3. Therefore, we proposed to take up the hearing of
the appeal in presence of the learned Counsel for the appellants
and the respondent.
4. The instant appeal under Clause-10 of the Letters
Patent Act is directed against the judgment dated 02.05.2026
passed by the learned Single Judge in C.W.J.C. No. 11678 of
2023.
5. By the impugned judgment, the writ petition was
allowed. The appellants herein were directed to finalize the
D.S.R. (District Survey Report) of mining lease with the
respondent; extend the time of lease and issue work order
followed by final settlement of contract of lease with the
respondent within a period of six weeks from the date of passing
of the order.
6. In order to ascertain the issue, the following facts
Patna High Court L.P.A No.865 of 2024 dt.01-10-2026
3/32
are required to be recorded which are as follows:-
“In connection with grant of mining lease
on settlement of nine stone blocks, a notice inviting
tender was published by the District Magistrate,
Shaikhpura. The petitioner participated in the auction
and being the highest bidder, a letters of intent was
issued on 21.09.2017 in favour of the writ-petitioner.
The stone block was settled in favour of the petitioner
for five years from the date of execution of the lease
deed. Further the petitioner was required to make
payment of 10% of deed amount as security deposit,
submission of Form-B within 120 days from the date
of issuance of LOI, mining plan, environment
clearance and other payments as per the LOI.
However, environmental clearance could not be
granted due to non-submission of D.S.R. (District
Survey Report). On 23.01.2023, the District
Magistrate approved emolument of letter of intent
granted in favour of the petitioner for stone block
No.27 and also directed forfeiture of the earnest
money on the ground that there was delay of five
years and three months on the part of the petitioner to
Patna High Court L.P.A No.865 of 2024 dt.01-10-2026
4/32
execute the lease deed. The said order passed by the
District Magistrate, Shaikhpura dated 23.01.2023 was
challenged in appeal by the petitioner before the
Commissioner of Mines, Bihar and vide order dated
14.07.2023 passed in Appeal No.01 of 2022, the
Commissioner of Mines dismissed the said appeal
filed by the petitioner affirming the order passed by
the District Magistrate, Shaikhpura. Hence, the writ
petition.”
7. We have already stated in a nutshell the order
passed by the writ-Court.
8. Mr. Samdarshi, learned Advocate for the
respondent/writ petitioner submits that the writ-court in
Paragraph No.30 of its judgment recorded the observation of the
Hon’ble Supreme Court of India in State of Bihar and Ors. Vs.
Pawan Kumar and Ors. etc. (Civil Appeal No.3661-3662 of
2020) decided on 10.11.2021 . Paragraph No.11 of the said
judgment records the guidelines of possible sand mining sources
and preparation of D.S.R. in the following words:-
“11. Chapter 4 of the 2020 Guidelines
deals with identification of possible sand mining
sources and preparation of DSR. It will be relevant to
refer to Clauses 4.1.1(a), (o) and (p) of the 2020
Patna High Court L.P.A No.865 of 2024 dt.01-10-2026
5/32
Guidelines:
“4.1. Identification of possible sand mining
sources and preparation of District Survey Report
(DSR)
4.1.1. Preparation of District Survey
Report.
(a) District Survey Report for sand mining
shall be prepared before the auction/e-auction/grant
of the mining lease/Letter of Intent (“LoI”) by
Mining Department or department dealing the
mining activity in respective states.
(o) Potential site for mining having its
impact on the forest, protected area, habitation,
bridges, etc. shall be avoided. For this, a Sub-
Divisional Committee may be formed which after the
site visit shall decide its suitability for mining. The
list of mining lease after the recommendation of the
Committee needs to be defined in the following
format given in as Annexure II. The Sub-Divisional
Committee after the site visit shall make a
recommendation on the site for its suitability of
mining and also records the reason for selecting the
mining lease in the Patta land. The details regarding
cluster and contiguous cluster needs to be provided
as in Annexure III. The details of the transportation
need to be provided as in Annexure IV.
(p) Public consultation—The comments of
the various stakeholders may be sought on the list of
mining lease to be auctioned. The State Government
shall give an advertisement in the local and national
Patna High Court L.P.A No.865 of 2024 dt.01-10-2026
6/32
newspaper for seeking comments of the general
public on the list of mining lease included in the
DSR. The DSR should be placed in the public
domain for at least one month from the date of
publication of the advertisement for obtaining
comments of the general public. The comments so
received shall be placed before the Sub-Divisional
Committee for active consideration. The final list of
sand mining areas [leases to be granted on riverbed
& patta land/khatedari land, de-siltation location
(ponds/lakes/dams), M-Sand Plants (alternate source
of sand)] after the public hearing needs to be defined
in the final DSR in the format as per Annexure V.
The details regarding cluster and contiguous cluster
needs to be provided in Annexure VI. The details of
the transportation need to be provided in Annexure
VII.”
9. It is submitted by the learned Advocate on behalf of
the respondent/writ-petitioner that on the basis of D.S.R.
(District Survey Report), auction is to be made, letter of intent
will be issued. The successful bidder will submit mining plan
which shall be approved by the Competent Authority.
Thereafter, the successful bidder is required to file application
before SEIAA for environmental clearance and only then the
lease deed is to be executed under Rule-28 of Bihar Minerals
(Concession, Prevention of Illegal Mining, Transportation &
Patna High Court L.P.A No.865 of 2024 dt.01-10-2026
7/32
Storage) Rules, 2019.
10. Mr. Samdarshi after elaborating briefly different
stages till the execution of lease deed in connection with this
matter draws our attention to Page No.148 of the list of letter of
intent holder in the district of Shaikhpura alongwith its validity.
11. It is pointed out by the learned Advocate on behalf
of the respondent/writ petitioner that location of the mining
lease with reference to latitude and longitude was not stated in
respect of the petitioner's block by the District Mining Office,
Shaikhpura. Therefore, the respondent/writ-petitioner did not
get environmental clearance within the stipulated period of time.
The writ-petitioner was not in fault for non-execution of the
deed of lease within the stipulated period of time. However,
without admitting the inaction on the part of the State Authority,
the Collector cancelled the letter of intent, which was approved
by the Commissioner.
12. The learned Advocate on behalf of the respondent/
writ-petitioner next draws our attention to paragraph Nos.5, 7 &
11 of the order passed in appeal by the Commissioner of Mines
on 14.07.2023. The above-mentioned paragraphs are quoted
below:-
“ 5- vihydrkZ ds fo}ku vf/koDrk dk dguk gS fd
Patna High Court L.P.A No.865 of 2024 dt.01-10-2026
8/32
muds }kjk SEIAA, fcgkj ds le{k i;kZoj.kh; Lohd`fr vkosnu
lefiZr fd;k tk pqdk gS ,oa Lohd`r izkIr djus ds fy, lHkh laHko
vkSj vko”;d dne mBk, x, gSA f;k }kjk ;g vkifRr dh x;h gS fd
“ks[kiqjk ftyk ds ftyk losZ{k.k izfrosnu esa Geo-Coordinate vkSj
mRiknu fooj.k dk mYys[k ugha gS rFkk PFR, EIA vkSj [kuu ;kstuk
esa of.kZr mRiknu fooj.k ds chp folaxfr;kWa gSA vihydrkZ }kjk lnL;
lfpo] fl;k dks “kh?kz i;kZoj.kh; Lohd`fr fuxZu djus ds fy, iqu%
vkosnu fnukad 21-11-2022 dks fn;k x;kA SEIAA, fcgkj us
fnukad25-11-2022 ds ek/;e ls vihydrkZ dks funs”k fn;k fd
i=kad&193] fnukad& 07-09-20 dk vuwikyu ugha fd;k x;k gS vkSj
la”kksf/kr ftyk losZ{k.k izfrosnu ,oa [kuu ;kstuk izLrqr ugha fd;k
x;k gSA blfy,] tc rd mUgsa la”kksf/kr ftyk losZ{k.k izfrosnu izkIr
ugha gksrk gS] rc rd Ik;kZoj.kh; Lohd`fr izkIr djuk vkSj iêk fu’iknu
djkuk laHko ugha gks ldsxkA
7- orZeku vihy esa i{kksa dh vksj ls nh xbZ nyhyksa ij
fopkj djus ls igys] dqN izklafxd frfFk;ksa] tks vfHkys[k ij ifjyf{kr
gks jgk gS] dk lanHkZ fuEu izdkj gS%&
18-03-17% lekgŸkkZ] “ks[kiqjk }kjk iRFkj Hkw[k.M dh uhykehA
21-09-2017% lS)kafrd Lohd`Rokns”k fuxZrA
13-09-2018 % [kuu iêk ds 500 ehVj dh ifjf/k ds laca/k esa ,oa
vapykf/kdkjh dk izfrosnu miyC/k djkus gsrq mPpre] “ks[kiqjk dks
vkosnu lefiZr fd;k x;kA
25-01-2020 % [kfut fodkl inkf/kdkjh] “ks[kiqjk }kjk vapykf/kdkjh]
vfj;kjh ls izkIr izfrosnu mPpre MkdoDrk dks miyC/k djk;k x;kA
Patna High Court L.P.A No.865 of 2024 dt.01-10-2026
9/32
28-01-2020% mPpre MkdoDrk }kjk jkT; Ik;kZoj.k lek?kkr fu/kkZj.k
izkf/kdkj (SEIAA) dks vkosnu lefiZr fd;k x;kA
28-02-2020 % lnL; lfpo] SEIAA dks vihydŸkkZ }kjk vkosnu lefiZr
fd;k x;k] ftlesa cslykbu MkVk vuqJo.k ekpZ 2020 ls izkjaHk djus dh
vuqefr dh ek¡x dh x;hA
07-03-2020% [kfut fodkl inkf/kdkjh] “ks[kiqjk dks 500 ehVj dh ifjf/k
ls lacaf/kr dyLVj izek.k i= miyC/k djkus dk vuqjks/k fd;k x;kA
16-03-2020% [kfut fodkl inkf/kdkjh] “ks[kiqjk }kjk lwpuk vihydŸkkZ
dks miyC/k djk;h x;hA
29-01-2021% vihydŸkkZ }kjk fcgkj jkT; iznw’k.k fu;a=.k Ik’kZn dks yksd
lquokbZ ds fy, vkosnu lefiZr fd;k x;kA
17-12-2021% yksd lquokbZ lEiUu dh xbZA
30-06-2022% mPpre MkdoDrk }kjk [kfut fodkl inkf/kdkjh] “ks[kiqjk
dks ftyk losZ{k.k izfrosnu ds laca/k esa vkosnu f n;k x;kA
11-10-2022% vihydŸkkZ us funs”kd] [kku ,oa HkwrRo foHkx dks ftyk
losZ{k.k ,oa [kuu ;kstuk ds laca/k esa vkosnu l efiZr fd;k x;kA
- SEIAA
21-11-2022% lnL; lfpo] fcgkj ls “kh?kz Ik;kZoj.kh; Lohd`fr
fuxZr djus gsrq vkosnu lefiZr fd;k x;kA
25-11-2022% SEIAA fcgkj }kjk ftyk losZ{k.k izfrosnu ,oa [kuu
;kstukds laca/k esa i`PNk dh x;hA
23-01-2023% lekgŸkkZ] “ks[kiqjk }kjk fnukad& 23-01-3023 dk vkns”k
ikfjr fd;k x;kA
7- fcgkj y?kq [kfut lekuqnku fu;ekoyh] 1972 ds
fu;e 52 ds igr lekgŸkkZ] “ks[kiqjk }kjk iRFkj Hkq[k.M la[;k 27
Patna High Court L.P.A No.865 of 2024 dt.01-10-2026
10/32
dh cankscLrh ds fy, uhykeh djkbZ xbZ FkhA fcgkj y?kq [kfut
lekuqnku fu;ekoyh] 1972 ds fu;e 25¼1½ ds vuqlk lekgŸkkZ }
kjk [kuu iêk Lohd`r djus ds vkns”k ds 120 fnuksa ds Hkhrj
vkSipkfjd iêk izi= fM esa fu’ikfnr fd;s tkus dk izko/kku gSA
mDr fu;e ds ijarqd esa izko/kku gS fd [kuu ;kstuk vuqeksnu
vkSj Ik;kZoj.kh; Lohd`r izkIr djus ds ckn gh iêk fu’iknu fd;k
tk ldrk gSA mijksDr izko/kkuks dks fcgkj [kfut ¼lekuqnku]
voS/k [kuu] ifjogu ,oa HkaMkj.k fuokj.k½ fu;ekoyh] 2019 ds
fu;e 28 }kjk izfrLFkkfir fd;k x;k gS] tgka iêk lfork
fu’iknu ds fy, 180 fnu fu/kkZfjr fd;k x;k gSA fcgkj [kfut
¼lekuqnku] voS/k [kuu] ifjogu ,oa HkaMkj.k fuokj.k½ u;ekoyh]
2019 ds rgr Hkh [kuu ;kstuk vkSj Ik;kZoj.k Lohd`fr izkIr djuk
vfuok;Z gSA
11- ekuuh; mPpre U;k;ky; }kjk flfoy vihy
la[;k&3661&3662@2020 esa fnukad& 10-11-2021 dks ikfjr
vkns”k ds vkyksd esa ftyk losZ{k.k izfrosnu vuqe.My jŸkjh;
lfefr }kjk rS;kj fd;k tkuk gS] ftldh leh{kk jkT; fo”ks’kK
vkadyu lfefr (SEAC) }kjk fd;s tkus ds mijkar vuqeksnu dh
dkjZokbZ jkT; Ik;kZoj.k lek?kkr fu/kkZj.k izkf/kdkj (SEIAA) }kjk
dh tkuh gSA vihydrkZ }kjk okafNr ftyk losZ{k.k izfrosnu iqu%
rS;kj djus esa mDr izfdz;k dk ikyu djuk gksxk] ftlesa djhc
N% ls 12 ekg dk le; yx ldrk gS vFkkZr vihydrkZ dks vkSj
le; fn;k Hkh tkrk gS] rks og okLrfod [kuu dk;Z yxHkx ,d
o’kZ ckn gh izkjaHk dj ldsaxsA ”
Patna High Court L.P.A No.865 of 2024 dt.01-10-2026
11/32
13. Learned Advocate for the respondent/writ-
petitioner next draws our attention to Rule-28 of Bihar Minerals
(Concession, Prevention of Illegal Mining, Transportation &
Storage) Rules, 2019, which deals with execution of lease. Rule-
28 runs thus:-
" 28. Execution of lease .-(1) Where a
mineral concession is granted under the rules the
formal lease deed shall be executed by the Collector
in Form "B" within 180 days of the order sanctioning
the lease and if the person to whom such mineral
concession has been granted fails to submit the
required documents for execution within the
aforesaid period the order sanctioning the lease shall
be deemed to have been revoked, and in that event
the application fee and the security deposit shall be
forfeited.
Provided that no lease shall be executed
unless the person to whom such lease has been
granted submits the mining plan and environment
clearances as required under these rules.
Provided further that where the Collector is
satisfied that the person to whom such lease has been
granted is not responsible for the delay in execution
of the formal lease, he may permit the execution of
the formal lease even after the expiry of the aforesaid
period of 180 days.
(2) The date of the commencement of the
period for which a mineral concession is granted
Patna High Court L.P.A No.865 of 2024 dt.01-10-2026
12/32
shall be the date on which the mining lease deed is
executed under sub-rule (1) and the lessee shall be
liable to pay rent/royalty from the date of the
execution of the mining lease.
(3) The lease dead has to be duly registered
by paying proper stamp duty and registration fees.
(4) No claim for extension of lease period
shall be entertained for any delay."
14. Referring to the above provisions, it is contended
by Mr. Samdarshi that duty of supplying D.S.R. with Geo-
coordinates for issuance of environmental clearance lies upon
the State-Respondents. If the D.S.R. and environment clearance
were supplied by the Mining Authority and in spite of receipt of
such documents, there was delay on the part of the
respondent/writ-petitioner to execute the deed of lease within
180 days of the order sanctioning the list than the respondent
might have been held to be responsible.
15. Mr. Samdarshi also refers to the second proviso of
the aforesaid Rules of 2019 which gives power to the Collector
to permit the execution of formal lease even after the expiry of
the said period of 180 days, where the Collector is satisfied that
the person to whom such lease has been granted is not
responsible for delay in execution of formal lease.
16. The learned Advocate for the respondent/writ-
Patna High Court L.P.A No.865 of 2024 dt.01-10-2026
13/32
petitioner refers to a very recent decision in the case of The
Director of Mines and Geology Vs. M/s. BMM Ispat Ltd. &
Anr. , reported in 2026 INSC 627 . In the aforesaid decision an
order of Karnataka High Court in Writ Petition No.6979 of
2017, whereby the Court allowed the respondent's petition
directed against an order passed by the appellant herein,
rejecting the respondent's representation made against the
charge of higher royalty than what was stipulated in the tender
agreement, which in itself was a consequence of an earlier
round of litigation, was challenged. The Hon'ble Supreme Court
in Paragraph Nos.12 & 13 held as hereunder:-
"12. This Court in its order fixing the rate of
royalty at 10% use the word 'applicable', which
denotes, in our understanding, applicability at the
relevant time, of removing the tendered goods which
already stood extracted, and does not intend to freeze
the rate of royalty. We are supported in our conclusion
by the understanding of a 9-Judge Bench in Mineral
Area Development Authority (supra) wherein the
payment of royalty is linked with dispatch. D.Y.
Chandrachud, CJI writing for majority held as under:
"92... The expression "dispatch" has
been defined to mean the removal of
minerals or mineral products from the
leased area and to include the
consumption of minerals and mineral
Patna High Court L.P.A No.865 of 2024 dt.01-10-2026
14/32
products within such area. [MMDR Act,
Section 3(aa).] It is worth noting that
royalty is payable under Section 9 on the
removal or consumption of minerals by
the lessee in the leased area. Thus,
essentially royalty is payable on the
dispatch of minerals from the leased
area."
(emphasis supplied)
13. In that view of the matter, the payment
is to be made on the date of the movement of the
minerals. If the date of the movement is after the
enhancement in royalty, a contract entered into prior
to the statutory change cannot be limiting its impact.
In other words, the appellant was correct in
deducting the additional 5% royalty from the security
deposit of the respondent. It would have been
entirely open to the respondents to remove the iron
ore from the site at one go or at any date prior to the
amendment, which they chose not to do. It is they
who either adopted the piecemeal approach in
moving the mineral or moved the entire quantity
after the date of the amendment. As such, they
cannot escape payment of enhanced royalty."
17. Mr. Samdarshi also refers to a three Judges Bench
decision of the Hon'ble Supreme Court in Goa State
Cooperative Bank Ltd. Vs. Krishna Nath A. (Dead) through
Legal Representatives & Ors. , reported in (2019) 20 SCC 38 .
Patna High Court L.P.A No.865 of 2024 dt.01-10-2026
15/32
Paragraph No.23 of the said judgment states as follows:-
"23. The principle of restitution enjoins a
duty upon the courts to do complete justice to the
party at the time of final decision, and to do away
with the effect of interim order in the fact situation of
the case. In South Eastern Coalfields Ltd. Vs. State
of M.P., (2003) 8 SCC 648 , it was observed that no
party can take advantage of litigation, it has to
disgorge the advantage gained due to delay, in case
lis is lost."
18. The learned Advocate General, on the other hand,
refers to certain dates which are relevant for the purpose of this
case from the record. In respect of the mining lease in question,
auction was conducted by the District Magistrate, Shaikhpura
on 18.03.2017. Letter of intent was issued on 21.09.2017. On
10.08.2018, the petitioner requested the respondent, Mineral
Development Officer that for environmental clearance the
petitioner seeks information which were to be provided by the
Circle Officer, Ariari. On 13.09.2018 Mining Plan was
submitted by the appellant. Subsequently, during the year 2018
and 2019, the writ-petitioner submitted representation to the
Mineral Development Officer for providing information through
the Circle Officer for submitting the said before SEIAA. On
28.01.2019, the petitioner submitted pre-feasibility report and
Patna High Court L.P.A No.865 of 2024 dt.01-10-2026
16/32
Proposed Terms of Reference before the SEIAA. Since March,
2020 to July, 2020 normal work of all Departments was
suspended due to COVID Pandemic. On 07.09.2020 the SEIAA
recommended to issue the terms of reference on the basis of
recommendation of SEAC and SEIAA pointed out the
discrepancies, such as approval of mining plan by the
Department of Mines and Geology, D.S.R. lacking latitude and
longitude etc. However, considering the COVID Pandemic, the
SEIAA resolved to issue the term of reference subject to
submission of certain documents and complying with the
necessary directions dated 07.09.2020. On 29.01.2021, the
petitioner deposited demand draft for conducting public hearing
before the Bihar State Pollution Control Board. On 16.03.2021,
the Mineral Development Officer communicated the Bihar State
Pollution Control Board that on 24.04.2021 is the date fixed for
public hearing. However, public hearing was conducted on
17.12.2021. On 30.06.2022, the petitioner again requested the
Mineral Development Officer to provide approved D.S.R. with
Geo-coordinates, without which SEIAA was not considering
grant of environment clearance. Subsequently, a series of
explanations was submitted before the District Magistrate and
the Competent Authority in the Mining Department explaining
Patna High Court L.P.A No.865 of 2024 dt.01-10-2026
17/32
the petitioner's stands as to why the delay in issuing the sanction
order was not attributable to the petitioner. However, on
23.01.2023 the Collector, Shaikhpura cancelled the sanction
letter and forfeited the security deposit.
19. Referring to the above list of dates, it is submitted
by Mr. S.D. Sanjay, the learned Advocate General that as per
Rule-28(1) of 2019 Rules, the formal lease deed shall be
executed by the Collector in Form 'B' within 180 days of the
order sanctioning the lease and if the person to whom such
mineral concession has been granted fails to submit the required
documents for execution within the aforesaid period, the order
sanctioning the lease shall be deemed to have been revoked, and
in that event the application fee and the security deposit shall be
forfeited.
20. If a person in favour of whom the sanction order is
issued fails to produce necessary documents within 180 days for
execution of the lease deed, the lease will automatically be
revoked.
21. In the instant case, the letter of intent was issued
on 21.09.2017, from the list of dates it appears that the
petitioner for the first time took step on 10.08.2018 requesting
the Mineral Development Officer to produce certain
Patna High Court L.P.A No.865 of 2024 dt.01-10-2026
18/32
information/ documents for obtaining environmental clearance.
Thus, the petitioner for the first time took step to discharge his
liability after the expiry of 180 days.
22. The learned Advocate General next draws our
attention to paragraph No.33 of the impugned judgment, where
the learned Single Judge observed as follows:-
“33. One cannot lose sight of the fact that
despite there being delay and latches on part of the
petitioner, the respondents too erred in not issuing
the geo coordinates of the concerned Stone Block in
the DSR, which also added to the duration of delay
in obtaining environmental clearance.”
23. A bare perusal of the above quoted observation
clearly suggests that there was delay and laches on the part of
the writ-petitioner. Therefore, when the learned Single Judge
found that the respondent/writ-petitioner was guilty by delay
and laches, it was not proper for the learned Single Judge to
extend equitable relief under Article 226 of the Constitution of
India.
24. It is submitted by the learned Advocate General on
behalf of the appellants that the equity cannot override the
statutory principle.
25. The learned Advocate General next refers to
Patna High Court L.P.A No.865 of 2024 dt.01-10-2026
19/32
paragraph Nos.52, 53 & 54 of the impugned judgment. In
paragraph No.52, the learned Single Judge directed the
Competent Authority-cum-District Magistrate to finalize D.S.R.
and thereafter, extend the time and issue work order followed by
final settlement of contract of lease within a period of six weeks
from the date of passing of this order. In paragraph No.53, the
learned Single Judge observed that already more than six years
have lapsed and no third party right is created, therefore, the
Competent Authority-cum-District Magistrate and the
Additional Chief Secretary considering that proposal has been
submitted by the Proponent of Project before the SEIAA and
considering the said proposal in detail as would appear from the
letter dated 09.07.2020 for considering the ‘Term of Reference’
herein-above, petitioner having satisfied, the Competent
Authority is required to take decision for issuing modified
D.S.R. giving the Geo-coordinate expeditiously without further
delay. In paragraph No.54, the SEIAA was directed not to cause
any delay in taking decision to issue Environmental Clearance
Certificate forthwith.
26. It is contended by the learned Advocate General
that SEIAA was not even a party to the writ petition then how
could the learned Single Judge pass a direction upon a State
Patna High Court L.P.A No.865 of 2024 dt.01-10-2026
20/32
Authority who is not a party to the writ petition.
27. Under the above stated premises, it is submitted
by the learned Advocate General that till date the writ-petitioner
failed to produce requisite documents for execution of the lease
deed.
28. Rule-25 of Bihar Minor Mineral Concession
Rules, 1972 clearly stipulates that the mining lease shall be
executed by the Collector in Form 'D' within 120 days of the
order sanctioning the lease and if the person to whom such lease
has been granted fails to submit the required documents for
execution within the aforesaid period, the order sanctioning the
lease shall be deemed to have been revoked and in that event the
application fee and the security deposit shall be forfeited. Thus,
revocation of the lease deed is automatic. After the expiry of
120 days from the date of sanction, no formal order is also
necessary. Section 25(1) is a deeming provision.
29. Having heard the learned Advocate for the
respondent/writ-petitioner and the learned Advocate General on
behalf of the appellants, the moot question that is required to be
adjudicated is the scope of judicial review of the action of the
State in matters relating to contract/tender under writ-
jurisdiction.
Patna High Court L.P.A No.865 of 2024 dt.01-10-2026
21/32
30. It is needless to say that tender operates in the
realm of the law of contract. Floating a tender by any
organization is an invitation to offer. When the offer is accepted
as per the terms of tender. The offers are examined and the
person or company or firm who offers the highest bid is
accepted. After acceptance under various rules created under the
statute like Bihar Minerals (Concession, Prevention of Illegal
Mining, Transportation & Storage) Rules, 2019, Bihar Minor
Mineral Concession Rules, 1972 as well as under different
Rules on various matters.
31. The parties are directed to execute various
documents and only on satisfactory execution of documents, a
contract is entered into. A lease for quarrying sand or extracting
stones for a particular period of time is basically a contract of
lease.
32. The issue relating to the scope of judicial review
of State action in matters relating to contract/tender under writ
jurisdiction was elaborately dealt with in a three Judges Bench
decision of the Hon'ble Supreme Court in Subodh Kumar
Singh Rathore Vs. Chief Executive Officer & Ors. , reported
(2024) 15 SCC 461 . The Hon'ble Supreme Court was pleased to
consider its earlier view and the present changes in judicial
Patna High Court L.P.A No.865 of 2024 dt.01-10-2026
22/32
review.
33. Over the years, the scope of judicial review and
the extent to which a Court can interfere in disputes arising out
of contracts or tenders has seen a significant development,
marked by a nuanced understanding of the critical role of
administrative discretion. The judicial quest in administrative
matters has always been to find a right balance between: ( i )
allowing leeway to the States in deciding the exercise of their
administrative discretion in matters pertaining to policy; and ( ii )
the need to ensure fairness and propriety in such administrative
actions.
34. Earlier, the position of law was that any dispute
arising out of a contract entered into with the State or its
instrumentalities could not be adjudicated by the Court under its
writ jurisdiction, as in all such cases, it could be said that the
“real grievance” was essentially only one being that of breach of
a contract for which the appropriate remedy would be an
ordinary suit and not a writ petition.
35. Thus, for a period of time the courts recognised
that there was a clear brightline distinction between when a
State or its instrumentalities could be said to be acting in its
executive capacity and when it could be said to be acting in its
Patna High Court L.P.A No.865 of 2024 dt.01-10-2026
23/32
private capacity, with the existence of a “contractual relation”
inter se the parties being the determinative factor. Wherever,
there was a contract, the State's relations and all its actions were
said to be within the field of a contract i.e. within the realm of
private law, and the courts would resile from interfering with the
same under their writ jurisdiction or embarking upon a judicial
review of such actions.
36. Such reluctance on the part of the courts stemmed
from its understanding that the State or any of its
instrumentalities must have the flexibility or the discretion to
take decisions that are in the best interest of the public and
efficient governance. The Government being the decision-maker
of the State is said to be the best judge of when a contract or an
agreement is in its interest and by its extension in the interest of
the public, and as such the courts should not interfere in the
State's discretion to award or terminate contracts. Another
reason why contractual disputes were precluded from being
espoused under the writ jurisdiction of the courts was due to the
summary nature of such proceedings, which do not allow for an
exhaustive review unlike civil suits.
37. This simplistic approach of the courts in deeming
every act and action of the State which was complained of as
Patna High Court L.P.A No.865 of 2024 dt.01-10-2026
24/32
nothing more than a “contractual dispute” or a case of “breach
of contract” often led to the State abusing its position and acting
unfairly under the misconceived notion, that all its actions such
as award of contracts or tenders were nothing but a “largesse”
— a generosity bestowed upon its citizens, which it can at its
own whims choose to deny, alter, modify, or take away without
any consequences. This often led to a conflation of power with
duty, and resulted in every arbitrary exercise of power by the
State under the guise of a “contractual dispute” to remain
unchecked and undisputable before the courts and out of the
reach of judicial review, undermining the rights of the citizen to
have their interests safeguarded and protected.
38. Over a period of time the courts recognised the
crucial role of judicial oversight in preventing the abuse of
power and maintaining public confidence in the administrative
process. Courts developed various doctrines and principles to
guide their review, such as the principles of natural justice,
reasonableness and proportionality. These principles ensured
that the administrative actions are not arbitrary, discriminatory
or capricious. By enforcing such standards, the courts also
ensured that the rule of law was maintained and the individual
rights were protected.
Patna High Court L.P.A No.865 of 2024 dt.01-10-2026
25/32
39. The interplay between judicial review and
administrative discretion has been a dynamic process. As new
challenges and complexities kept on arising before the courts as
regards the State's actions and governance, it continued to refine
its approach. This ongoing dialogue between the courts and the
executive branch contributed to the development of a more
accountable and transparent administrative framework, paving
the way for the exercise of judicial review even in the realm of
contractual disputes to achieve a fine balance between
efficiency and fairness in policy decisions on the one hand and
the rights of individuals and overall public interest on the other.
40. In Mahabir Auto Stores v. Indian Oil Corpn.
[ Mahabir Auto Stores v. Indian Oil Corpn. , reported in (1990)
3 SCC 752 : (1990) 69 Comp Cas 746] , this Court expressed
doubts over the correctness of the earlier position of law, that
actions of the State in the private contractual field cannot be
questioned in writ jurisdiction. This Court further held that even
if the inter se relation of parties with the State is governed
purely by a contract, the method, motive and decision of the
State would be subject to judicial review on the grounds of
relevance and reasonableness, fair play, natural justice, equality
and non-discrimination. This view was reiterated in subsequent
Patna High Court L.P.A No.865 of 2024 dt.01-10-2026
26/32
decisions.
41. The decision of the Hon'ble Supreme Court in
A.B.L. International Ltd. Vs. Export Credit Guarantee Corpn. of
India Ltd., reported in (2004) 3 SCC 553 is significant and was
the turning point in the scope of judicial review in contractual
matters. In this landmark ruling, the Court decisively laid down
and approved that a relief against the State or its
instrumentalities in matters related to contractual obligation can
be sought under the writ jurisdiction.
42. It is needless to state that in matters concerning
specific modalities of the such as required work, execution
methods, material quality, time frame, contract the supervision
standards, and other aspects impacting the tender's purpose
court usually refrains from interference. State authorities, like
private individuals, have a consensual element in contract
formation. The stipulations or terms in the underlying contract
purpose are part of the consensual aspect, which need not be
entertained by the courts in writ jurisdiction and the parties may
be relegated to ordinary private law remedy. Judicial review
does not extend to fixing contract stipulations but ensures that
the public authorities act within their authority to prevent
arbitrariness.
Patna High Court L.P.A No.865 of 2024 dt.01-10-2026
27/32
43. Thus, the demarcation between a private law
element and public law element in the context of contractual
disputes if any, may be assessed by ascertaining whether the
dispute or the controversy pertains to the consensual aspect of
the contract or tender in question or not. Judicial review is
permissible to prevent arbitrariness of public authorities and to
ensure that they do not exceed or abuse their powers in
contractual transactions and requires overseeing the
administrative power of public authorities to award or cancel
contracts or any of its stipulations. (emphasis supplied)
(Paragraph Nos.33 to 43 are reproduced from head notes in
Subodh Kumar Singh Rathore (supra ).
44. Factual aspects of the instant appeal are not in
dispute that the letter of intent was issued on 21.09.2017. The
statutory rule provides that from the date of issuance of letter of
intent, the lease is required to be executed within 120 days
under 2019 Rules or within 180 days under 1972 Rules, as the
case may be. Admittedly the respondent/writ-petitioner took
step to obtain environmental clearance on 10.08.2018, i.e. after
a lapse of about 11 months. There is no explanation as to the
delay committed by the writ-petitioner to obtain environmental
clearance. Subsequent to 10.08.2018, the State Government also
Patna High Court L.P.A No.865 of 2024 dt.01-10-2026
28/32
delayed supplying necessary document and according to the
writ-petitioner environmental clearance was not issued by the
concerned department because the respondents failed to produce
geo-coordinate mentioning latitude and longitude of the stone
block. In the meantime about nine years have elapsed.
45. Under such backdrop if we consider the factual
circumstances of the case this appears to us that both the parties
are responsible for contributory negligence in the matter of
timely execution of the lease deed for quarrying stone from
Block No.27.
46. We are in agreement with the learned Advocate
General that due to non-execution of the deed of lease and
failure on the part of the writ-petitioner from extracting stone
from the stone mines, the appellant has lost revenue and
financial gain.
47. It is, however, contended by Mr. Samdarshi that as
per the terms of agreement, the writ-petitioner was obliged to
pay the price of stone prevailing on the date of actual extraction
of stones. Therefore, the State Government will not loose any
revenue, royalty or any other financial benefit.
48. However, it is obvious that the rate of revenue has
ofcourse been enhanced within 9-10 years. The royalty depends
Patna High Court L.P.A No.865 of 2024 dt.01-10-2026
29/32
upon determination of revenue and charges of royalty over a
particular block. Therefore, the royalty that was fixed in the year
2017 must not be the same as on this date.
49. The learned Single Judge failed to consider this
aspect of contributory negligence and consequent loss incurred
by the State Government for non-execution of lease deed.
50. Since the State Government failed to comply with
the part of their promise by providing necessary documents for
environmental clearance within the stipulated period of time, the
State Government/appellants were negligent in the same manner
as that of the writ-petitioner who initiated the process of having
D.S.R. and environmental clearance after about one year of
issuance of letter of intent. On due recognition of appellants'
negligence, we set aside the portion of the order passed by the
Collector and affirmed by the Appellate Tribunal of forfeiture of
the initial bid amount paid by the respondent/writ-petitioner to
the tune of Rs.2,90,00,000/- (Rupees Two Crore Ninety Lakhs
only).
51. At the same time, we impose interest over the said
amount at the rate of 12% per annum from the date of
depositing the amount till the date of payment. Such amount
shall be paid by the appellant before initiation of new tender
Patna High Court L.P.A No.865 of 2024 dt.01-10-2026
30/32
process in respect of Block No.27. It is also made clear that the
writ-petitioner shall be given an opportunity to participate in the
new tender process and its past conduct cannot be considered by
the State Authority to reject his claim. If the writ-petitioner
becomes L-1, he will be entitled to get the order of intent.
52. In the instant case as well as in many other cases
of similar type we have noticed that execution of lease deed is
being delayed because of the failure on the part of the State
Government in its various departments to produce necessary
documents immediately after the letter of intent. Therefore, we
propose to formulate the following guidelines so that mining
lease may not be revoked for want of necessary documents like
environmental clearance etc. before execution of lease deed:-
(i) henceforth, District Survey Report
(DSR) in respect of the tender shall be produced
alongwith the notice of tender in respect of mining
blocks;
(ii) the D.S.R. must contain geo-coordinate
mentioning latitude and longitude and all other
information of each block separately;
(iii) within 15 days from the date of
auction, the letter of intent shall be published;
Patna High Court L.P.A No.865 of 2024 dt.01-10-2026
31/32
(iv) within 15 days from the date of receipt
of the letter of intent, the successful bidder shall
deposit the mining plan;
(v) mining plan shall be approved within
15 days from the date of submission of the plan;
(vi) within 7 days thereafter the successful
bidder shall make requisite application before SEIAA
for environmental clearance, on receipt of
environmental clearance from the Central
Government, the deed of lease shall be executed
within the statutory period of time as contemplated in
the Rules.
(vii) failure to provide the information by
executing appropriate documents shall be considered
as non-performance of promise by the concerned
department of the State Government and the State
Government shall be under obligation to pay
damages for non-performance of their part of
performance."
53. Since we have come to a decision that the deed of
lease was revoked by the State Government, as a result of
contributory negligence by both the parties, we have no other
Patna High Court L.P.A No.865 of 2024 dt.01-10-2026
32/32
alternative but to set aside the order passed by the learned
Single Judge.
54. For the reasons stated above, the instant appeal is
allowed.
55. The District Magistrate, Shaikhpura is directed to
comply with the order regarding payment of initial deposit with
interest within the stipulated period of time to the writ-
petitioner.
56. Let a copy of this order be sent to the Chief
Secretary, Government of Bihar, Patna for information and
issuance of appropriate direction to maintain the guidelines
described herein-above, in the matter of execution of the deed of
lease in connection with mines and minerals.
(Bibek Chaudhuri, J)
Rana Vikram Singh, J: I Agree.
(Rana Vikram Singh, J)
mdrashid/-
AFR/NAFR NAFR
CAV DATE 25.09.2026
Uploading Date 01.10.2026
Transmission Date 01.10.2026