INHABITANTS OF SYEDABAD KUPWARA vs UNION TERRITORY OF J AND K AND ORS. (HOUSING AND URBAN DEVELOPMENT)
- Court
- Jammu and Kashmir High Court
S. No.54
Regular List
,,,
IN THE HIGH COURT OF JAMMU & KASHMIR AND LADAKH
AT SRINAGAR
WP(C) No.2705/2025
CM No.(6367/2026)
CM No.(6368/2026)and
CMNo.(7165/2025)
INHABITANTS OF SYEDABAD KUPWARA
…..Petitioner(s)
Through: Mr.Shafqat Nazir, Advocate
Ms Heena Baqal, Advocate
V/s
UT OF J&K AND ORS
… ..Respondent(s)
Through :Mr. Faisal Qadiri, Sr.Advocate
with Mr. Noman, Advocate
Mr.Sheikh Manzoor, Advocate
Mr.Waseem Gul, GA
Mr.Ilyas Laway, GA
CORAM:
HON’BLE MR. JUSTICE SANJAY DHAR, JUDGE
ORDER
11.11.2026
1. The petitioners through the medium of present petition have
challenged order dated 08.09.2025 passed by J&K Special
Tribunal Srinagar, whereby a direction has been issued to the
official respondents to take a final call upon the impugned order
dated 08.10.2022 within a period of 30 days failing which the
said order shall be deemed to have been cancelled.
2. Heard learned counsel for the parties and perused the
record.
WP(C) 2705/2025 1 | P a g e
3. It appears that there is a long history of litigation between
the petitioners and respondent No.6 with regard to proposed
construction on the land belonging to Masjid situated at Mouza
Kupwara. It seems that respondent/Municipal authorities
granted permission in favour of respondent No.6 for construction
of commercial building vide order bearing
No.BP/ORDER/KUPWARA/2022/24 dated 22.08.2022. The
said order granting building permission was challenged by the
petitioners by way of a revision petition before J&K Special
Tribunal, Srinagar. The said revision petition came to be
dismissed by the Tribunal vide order date 20.10.2022.
Thereafter, the respondents Municipal Authorities passed
another order bearing No.MC/Kup/22-23/2100/2104 dated
08.10.2022, whereby the building permission order granted in
favour of respondent No.6 has been kept in abeyance. The said
order came to be challenged by respondent No.6 by way of
revision petition before the Jammu & Kashmir Special Tribunal
which came to be decided by the Tribunal in terms of impugned
order dated 08.09.2025.
4. As already stated, vide the impugned order the learned
Tribunal has directed the Municipal Authorities to take a
decision in the matter within 30 days and in default it has been
provided that the said order would be deemed to have been
WP(C) 2705/2025 2 | P a g e
cancelled and respondent No.6 would be at liberty to proceed
ahead with the construction as per the permission granted in its
favour.
5. It is not in dispute that order dated 08.10.2022 issued by the
Municipal Authorities keeping in abeyance the building
permission in favour of respondent No.6 is a temporary measure.
The said order cannot remain in force in perpetuity. The
Municipal Authorities have issued the said order with a view to
take a decision on the complaints/representations received by it
from the petitioner and other persons objecting to the raising of
construction on spot by respondent No.6. The validity of order
dated 08.10.2022 can be stretched only up to the time the
Municipal Authorities take a decision on the objections received
relating to grant of building permission in favour of respondent
No.6. Therefore, learned Tribunal has rightly directed the
respondents/Municipal Authorities to decide the issue within a
period of 30 days.
6. The petitioner is particularly aggrieved of the direction of
the Tribunal which provides for deemed permission in favour of
respondent No.6, if the respondent/Municipal Authorities fail to
decide the matter within a period of 30 days. To this limited
extent, impugned order dated 08.09.2025 deserves to be
modified so as to take care of the concerns of the petitioner.
WP(C) 2705/2025 3 | P a g e
7. Accordingly, the writ petition alongwith all connected
applications is disposed of by modifying the order of the learned
Tribunal passed on 08.09.2025 to the extent that default on the
part of the Municipal Authorities to decide the fate of order
dated 08.10.2022, whereby building permission of respondent
No.6 has been kept in abeyance, shall not lead to automatic
cancellation of said order. It is, however, made clear that the
respondent/Municipal Authorities shall decide the issue within
the time stipulated by the Tribunal which shall begin from today
itself. It shall be open to the petitioner as well as respondent
No.6 to make additional representations and produce documents
before the official respondents, which shall be considered while
taking the final decision in the matter.
(SANJAY DHAR)
JUDGE
SRINAGAR
11.11.2026
Sarveeda Nissar
1.
Whether the order is speaking: Yes/No
Whether the order is reportable: Yes/No
WP(C) 2705/2025 4 | P a g e
Sarveeda Nissar
I attest to the accuracy and
authenticity of this document
every page at bottom left side
13.11.2026 11:04