Delhi Jal Board vs Digvijay Sanitations

Court
Delhi High Court

* IN THE HIGH COURT OF DELHI AT NEW DELHI

% Reserved on : 07.07.2026
Pronounced on : 15.09.2026
Uploaded on : 16.09.2026

+ FAO 187/2019 & CM APPL. 20150/2019

DELHI JAL BOARD .....Appellant
Through: Mr. Tushar Sannu, SC for DJB
with Ms. Akansha Vidhyarthi,
and Ms. Pulak Gupta, Advocates
versus

DIGVIJAY SANITATIONS .....Respondent
Through: Mr. Vivekanand, Advocate

CORAM:
HON'BLE MR. JUSTICE MANOJ KUMAR OHRI

JUDGMENT
1. By way of the present appeal filed under Section 37 of the
Arbitration and Conciliation Act, 1996 (hereinafter the “Arbitration
Act”), the appellant has assailed the judgment dated 19.01.2019 passed
by the learned Additional District Judge-07 (Central), Tis Hazari
Courts, in Arbn. No. 11/2017, whereby the petition filed by the
appellant under Section 34 of the Arbitration Act seeking setting aside
of the arbitral award dated 29.12.2009 passed by the learned Sole
Arbitrator, was dismissed.
2. Pithily put, the facts of the case are that the appellant invited
tenders for the work of providing/laying/jointing internal sewer line in
the Naveen Shahdara Group of Colonies (Subhash Park Extension,
Signature Not Verified
Digitally SignedPREM
MOHAN CHOUDHARY
Signing Date:16.09.2026
23:34:40
FAO 187/2019 Page 1 of 13

East Subhash Park Extension, West Subhash Park, Panchsheel
Garden, Dwarkapuri and Uldan Park, Mohanpuri, Panchsheel Garden
Extension, West Gorakh Park and Krishna Puri) . The respondent
submitted its bid on 25.05.2001, which was accepted by the appellant
at 13% below the estimated cost of Rs.86,69,888/-, for an awarded
contract value of Rs.75,42,803/-. Work Order No. 19/2001-2002 dated
24.10.2001 was issued, and Agreement No. 18 (2001-2002) dated
28.12.2001 came to be executed between the parties. The stipulated
date of commencement of work was 01.11.2001, and the stipulated
period for completion was 15 months, expiring on 30.01.2003. The
work, however, could not be completed within the stipulated period
and came to be completed only on 26.12.2003, after a delay of nearly
11 months. Disputes arose between the parties regarding delays, non-
availability of hindrance-free sites, non-payment of running bills,
wrongful deductions, and claims towards losses suffered due to
prolongation as well as price escalation. This led to the respondent
invoking arbitration vide letter dated 07.04.2008. Thereupon, the
competent authority vide office order dated 12.05.2008 appointed the
learned Sole Arbitrator concerned to adjudicate the disputes.
3. Before the learned Arbitrator, the respondent preferred 6 claims.
While claim no. 1(a) pertaining to refund of Rs.72,534/- and claim no.
3 pertaining to reduced profitability of Rs.6,00,000/- were rejected, the
learned Arbitrator allowed the remaining claims in favour of the
respondent to the following extent:

a. Under claim no. 1(b), an amount of Rs.33,354/- was
Signature Not Verified
Digitally SignedPREM
MOHAN CHOUDHARY
Signing Date:16.09.2026
23:34:40
FAO 187/2019 Page 2 of 13

awarded towards refund of the sum withheld/recovered in
th
the 7 R.A. Bill on account of non-testing of joints of RCC
pipes.
b. Under claim no. 2(a), an amount of Rs.13,23,120/- was
awarded towards additional expenses and compensation for
prolonged retention of supervisory staff and hire charges of
Tools and Plants (T&P) for 264 days.
c. Under claim no. 2(b), an amount of Rs.2,29,008/- was
awarded towards damages on account of increase in the
rates of labour and materials during the prolonged period
for the work executed after January 2003.

d. Under claim no. 4(a), interest @ 7.5% per annum was
awarded on the delayed payment of the final bill amount of
Rs.2,34,595/- from 01.01.2004 till 19.09.2007.
e. Under claim no. 4(b), interest @ 7.5% per annum was
awarded on the delayed release of the security deposit
amount of Rs.7,12,068/- from 26.12.2004 till 16.10.2007.
f. Under claim no. 5, the learned Arbitrator awarded interest
@ 7.5% per annum on the awarded amounts under claims
1, 2, and 4 from the date of invocation of arbitration, i.e.
07.04.2008, till the date of the impugned award, i.e.
29.12.2009, with a further direction that if the total awarded
amount was not paid within 90 days of receipt of the copy
of the impugned award, the same would carry interest @
7.5% per annum from the date of the impugned award till
Signature Not Verified
Digitally SignedPREM
MOHAN CHOUDHARY
Signing Date:16.09.2026
23:34:40
FAO 187/2019 Page 3 of 13

the date of payment.
g. Under claim no. 6, an amount of Rs.1,00,000/- was
awarded towards costs of the arbitration proceedings.
4. Aggrieved by the impugned award, the appellant preferred
objections under Section 34 of the Arbitration Act. The learned ADJ
dismissed the objections vide the impugned judgment, holding that the
findings returned by the learned Arbitrator did not suffer from any
perversity or patent illegality within the parameters of Section 34(2) of
the Arbitration Act.
5. Assailing the impugned judgment, learned counsel for the
appellant contended that the learned Arbitrator as well as the learned
ADJ failed to appreciate that time was the essence of the contract and
that the delay in execution was attributable to the respondent. It was
submitted that the appellant, through various letters as well as remarks
in the Site Order Book, had pointed out deficiencies on the part of the
respondent in executing the work. It was further contended that the
claims for compensation and damages on account of prolongation and
price variation were strictly barred under Clause 24 of the General
Conditions of Contract and Special Condition No. 1. Learned counsel
further argued that claim no. 1(b) was awarded in direct contravention
of Special Condition Nos. 13 and 43, which mandated hydraulic
testing of pipe joints, whereas the respondent had only carried out
smoke testing. With respect to claim no. 2(a), it was submitted that the
respondent had failed to maintain wage registers or labour reports
under Clause 19-B of the contract, the salary vouchers placed on
Signature Not Verified
Digitally SignedPREM
MOHAN CHOUDHARY
Signing Date:16.09.2026
23:34:40
FAO 187/2019 Page 4 of 13

record were unverified, and there was no primary evidence to justify
the quantification arrived at by the learned Arbitrator. Insofar as claim
no. 2(b) is concerned, it was urged that Clause 10CC was not made
part of the contract and was inapplicable to works having a stipulated
period of less than 18 months, and therefore, granting escalation on the
analogy of Clause 10CC amounted to rewriting the contract. Lastly, it
was contended that the award of interest under Claims 4(a) and 4(b) as
well as pendente lite interest was impermissible since the respondent
had failed to submit the final bill in terms of Clause 8, the contract
contained no stipulation for interest, no notice under the Interest Act,
1978 was issued, and the direction amounted to awarding interest upon
interest.
6. Per contra , learned counsel for the respondent defended the
impugned judgment as well as the impugned award. He submitted that
the findings on delay were arrived at on the basis of undisputed
documents, primarily the Hindrance Register maintained by the
appellant itself. Learned counsel pointed out that out of the 334 days of
delay, the appellant’s own authority had found 312 days of delay
justified on account of departmental hindrances. Learned counsel
submitted that Clause 24 of the General Conditions and Special
Condition No. 1 only contemplated normal, phased handing over to
avoid public inconvenience and did not bar claims where work was
brought to a complete standstill time and again due to departmental
failures. In respect of claim no. 1(b), it was urged that smoke testing
was conducted on the specific written instructions of the Engineer-in-
Signature Not Verified
Digitally SignedPREM
MOHAN CHOUDHARY
Signing Date:16.09.2026
23:34:40
FAO 187/2019 Page 5 of 13

Charge in the Site Order Book, the testing was certified by third-party
inspection reports, and the appellant incurred no expenditure on further
testing. As regards claim no. 2(a), the learned Arbitrator acted
reasonably by excluding the 48 days falling within the stipulated
period, disallowing all unskilled labour, and confining the relief strictly
to deployed technical staff and bare minimum T&P at standard DSR
rates. For claim no. 2(b), learned counsel submitted that the impugned
award was not made under Clause 10CC, but as statutory damages
under Section 73 of the Indian Contract Act, 1872 for the prolonged
period, wherein the formula of Clause 10CC was merely used as an
objective computation mechanism, which approach has been squarely
upheld by the Division Bench of this Court in Delhi Development
1
Authority Vs. M/s Swastic Construction Co. . Lastly, it was submitted
that the learned Arbitrator possesses wide statutory discretion under
Section 31(7) of the Arbitration Act to award interest.
7. I have heard the learned counsels for the parties and perused the
material placed on record.
8. At this stage, it may be apposite to reiterate the well-settled
scope of interference under Section 37 of the Arbitration Act. It is trite
that the jurisdiction of this Court under Section 37 of the Arbitration
Act is supervisory and extremely restricted. The Court does not sit as a
Court of appeal over the arbitral award, nor can it embark upon a re-
assessment or re-appreciation of evidence. In MMTC Limited Vs.

1
2021:DHC:4409-DB
Signature Not Verified
Digitally SignedPREM
MOHAN CHOUDHARY
Signing Date:16.09.2026
23:34:40
FAO 187/2019 Page 6 of 13

2
Vedanta Limited , the Supreme Court delineated the scope of Section
37 in the following terms:
“ 14. As far as interference with an order made under Section
34, as per Section 37, is concerned, it cannot be disputed that such
interference under Section 37 cannot travel beyond the restrictions
laid down under Section 34. In other words, the court cannot
undertake an independent assessment of the merits of the award, and
must only ascertain that the exercise of power by the court under
Section 34 has not exceeded the scope of the provision. Thus, it is
evident that in case an arbitral award has been confirmed by the
court under Section 34 and by the court in an appeal under Section
37, this Court must be extremely cautious and slow to disturb such
concurrent findings. ”

9. A gainful reference may also be made to Haryana Tourism
3
Limited Vs. Kandhari Beverages Limited , wherein the Supreme Court
reiterated that an arbitral award can be set aside only if it is contrary to
the fundamental policy of Indian law, against basic notions of justice
or morality, or patently illegal, and held the following:
1
“ 8. So far as the impugned judgment and order passed by
the High Court quashing and setting aside the award and the order
passed by the Additional District Judge under Section 34 of the
Arbitration Act are concerned, it is required to be noted that in an
appeal under Section 37 of the Arbitration Act, the High Court has
entered into the merits of the claim, which is not permissible in
exercise of powers under Section 37 of the Arbitration Act.
9. As per settled position of law laid down by this Court in a
catena of decisions, an award can be set aside only if the award is
against the public policy of India. The award can be set aside under
Sections 34/37 of the Arbitration Act, if the award is found to be
contrary to, (a) fundamental policy of Indian Law; or (b) the interest
of India; or (c) justice or morality; or (d) if it is patently illegal.
None of the aforesaid exceptions shall be applicable to the facts of
the case on hand. The High Court has entered into the merits of the
claim and has decided the appeal under Section 37 of the Arbitration

2
(2019) 4 SCC 163
3
(2022) 3 SCC 237
Signature Not Verified
Digitally SignedPREM
MOHAN CHOUDHARY
Signing Date:16.09.2026
23:34:40
FAO 187/2019 Page 7 of 13

Act as if the High Court was deciding the appeal against the
judgment and decree passed by the learned trial court. Thus, the
High Court has exercised the jurisdiction not vested in it under
Section 37 of the Arbitration Act. The impugned judgment and order
passed by the High Court is hence not sustainable. ”

10. Adverting to the primary ground of challenge raised by the
appellant concerning the attribution of delay and the bar under Clause
24 of the General Conditions and Special Condition No. 1, a perusal of
the impugned award shows that the learned Arbitrator examined the
delay events extensively. The learned Arbitrator recorded that work
could not be started for 48 days from 01.11.2001 to 18.12.2001 for
want of road cutting permission from the MCD; execution was stopped
for 19 days in March 2002 due to Municipal elections; suspended for
30 days during October and November 2002 on account of festivals
and public resistance; halted for 95 days from 26.03.2003 to
28.06.2003 due to unremoved encroachments on the alignment; and
stalled from 01.09.2003 to December 2003 due to delay in shifting
existing water lines fouling the sewer alignment.
11. Significantly, the learned Arbitrator arrived at these findings
after examining the contemporaneous records, primarily the Hindrance
Register maintained by the appellant itself, wherein the department had
found 312 days of delay justified on grounds not attributable to the
respondent. The learned Arbitrator, having analysed the letters
exchanged between the parties in conjunction with the entries recorded
in the Hindrance Register, returned the finding that the delay was
attributable to acts of omission and commission on the part of the
appellant. This finding cannot be said to be perverse or without
Signature Not Verified
Digitally SignedPREM
MOHAN CHOUDHARY
Signing Date:16.09.2026
23:34:40
FAO 187/2019 Page 8 of 13

evidence.
12. Dealing with the exclusionary clauses, the learned Arbitrator
construed Clause 24 of the General Conditions and Special Condition
No. 1 and held as follows:
“… Thus the stipulations under clause 24 of general Conditions
read with special condition no.1 does not apply to the facts of the
case and as such cannot bar the claim for genuine compensation for
these periods. Further if one goes literally by the terms of these
clauses read together with the reasons for delay in handing over
alignments as envisaged in the clauses are different from the actual
reasons for delay. The respondent being maker and framer of the
contract would/could have included and covered specifically all
these reasons under those clauses. Having failed to do so, the
respondent cannot be allowed to read into it what is not specifically
provided for in the clauses to cover departmental casual attitude.
Further it is not the case of the respondent that these delays were
unavoidable and could not be removed within stipulated period by
30.1.2003 despite best efforts and due diligence. The respondent
knew that encroachment was on the alignment but nothing has been
shown as to what efforts were made from the award of the work till
March 2003 for removal of the encroachments and if no efforts were
made earlier, the reason for that are not disclosed or pleaded. The
clauses read together nowhere provide for or suggest that there
would/could be suspended/stopped time and again for considerable
months or days due to non availability of alignments at all. If this
meaning is given to the contract then not only the contract would
lose its efficacy but would also render meaningless the word
'progressively'. Progressively would not mean after gaps of more
than a month or so as and when available for indefinite period. Thus
the bar as provided under this clause is not attracted to the facts of
the case. ”

13. Seemingly, while holding that standard exclusionary clauses
governing phased site delivery cannot be interpreted to permit total,
intermittent cessations of work or to excuse fundamental defaults of
the department, the learned Arbitrator in fact, applied the principle of
contra proferentem . The learned Arbitrator also noted that the
Signature Not Verified
Digitally SignedPREM
MOHAN CHOUDHARY
Signing Date:16.09.2026
23:34:40
FAO 187/2019 Page 9 of 13

appellant did not rescind the contract but granted provisional
extensions without any contractual provision, thereby setting time at
large. The view taken by the learned Arbitrator is a plausible and
reasonable construction of the contract and was rightly affirmed by the
learned ADJ.
14. In respect of claim no. 1(b) relating to the refund of Rs.33,354/-,
the learned Arbitrator noted that although Special Condition Nos. 13
and 43 provided for hydraulic testing, the respondent was specifically
directed by the Engineer-in-Charge vide Site Order Book entry dated
23.09.2002 to carry out smoke testing. Smoke testing was duly carried
out and corroborated by third-party inspection reports. The appellant
neither directed hydraulic testing thereafter nor incurred any
expenditure in getting independent testing conducted. In the absence of
any defect or expenses incurred by the department, the learned
Arbitrator found the recovery to be arbitrary and unjustified. I find no
infirmity in the concurrent findings upholding the refund of this
amount.
15. With regard to claim no. 2(a), the learned Arbitrator awarded
compensation of Rs.13,23,120/- for additional expenses incurred on
supervisory staff and hire charges of tools and plants during the
prolonged period. The learned Arbitrator did not accept the
respondent’s claim in its entirety. Out of the 334 days of delay
claimed, the Arbitrator excluded 48 days that fell within the stipulated
period and confined compensation strictly to 264 days. The Arbitrator
specifically disallowed the claim for 16 unskilled helpers on the
Signature Not Verified
Digitally SignedPREM
MOHAN CHOUDHARY
Signing Date:16.09.2026
23:34:40
FAO 187/2019 Page 10 of 13

ground that daily labour could be engaged as and when work was
available. However, taking note that the site establishment had to be
maintained, the learned Arbitrator allowed expenses for bare minimum
supervisory staff (1 Engineer, 1 Supervisor, 3 Chowkidars , and plant
operators) and essential T&P (mixers, pumps, vibrators, and
tractor/loader) based on standard rates prescribed in the Delhi Schedule
of Rates (DSR) and construction handbooks. The contention of the
appellant that the quantification is arbitrary is without merit.
16. Insofar as claim no. 2(b) is concerned, the learned Arbitrator
awarded Rs.2,29,008/- on account of increase in material and labour
rates for the work executed after the expiry of the stipulated period.
The appellant’s objection that Clause 10CC was not part of the
contract and that Clause 22 prohibited price enhancement is
completely misplaced. The learned Arbitrator made it clear that the
amount was not awarded under Clause 10CC, but as damages under
Section 73 of the Indian Contract Act, 1872 for prolongation
attributable to the appellant, and that the formula under Clause 10CC
was merely adopted as an objective computation tool to assess the
quantum of damages.
17. In this regard, reference may be made to the decision of the
Coordinate Bench of this Court in Delhi Development Authority Vs.
4
Swastic Construction Company , wherein, while dealing with a
challenge to an award granting escalation for a prolonged period, it
was held that the formula under Clause 10CC can be legitimately

4
2021:DHC:2708
Signature Not Verified
Digitally SignedPREM
MOHAN CHOUDHARY
Signing Date:16.09.2026
23:34:40
FAO 187/2019 Page 11 of 13

relied upon by an arbitrator to compute damages under Section 73 of
the Indian Contract Act, 1872, even if the said clause is not specifically
incorporated in the contract. The said decision was upheld in appeal by
the Division Bench of this Court in Delhi Development Authority Vs.
5
M/s Swastic Construction Co. , observing as under:
“ 25. As regards the amount of damages awarded for Claim No. 1
is concerned, the learned Arbitrator has awarded damages by
relying on the formula provided under Clause 10C, 10CA and 10CC.
The learned Single Judge has correctly relied on Anurodh
Construction v. DDA [2005 SCC OnLine Del 867] and on DDA v.
N.N. Buildcon Pvt. Ltd., [2018 (246) DLT 314] to uphold the award
of damages for escalation of prolonged period based on the formula
provided under clause 10CC. We see no error in the approach of the
learned Arbitrator in relying on the formula for assisting in
calculation of damages. The respondent has to be compensated for
delays which are not attributable to the respondent. Hence, the
learned single judge correctly upheld the reliance on the formula
under Clause 10C, 10CA and 10CC for assessment of damages. ”

18. With respect to claim nos. 4(a) and 4(b), the learned Arbitrator
awarded interest @ 7.5% per annum on the delayed payment of the
final bill and security deposit. While the defect liability period ran till
26.12.2004, the final bill was paid only on 19.09.2007 and the security
deposit was released on 16.10.2007. Under Clause 8 of the contract,
the obligation to take measurements and prepare bills lay upon the
Engineer-in-Charge even if the respondent failed to submit a bill. The
learned Arbitrator acted prudently by awarding interest from
26.12.2004 till the respective dates of payment.
19. Under Section 31(7) of the Arbitration Act, the Arbitral Tribunal
possesses wide statutory discretion to award interest, unless there is an

5
2021:DHC:4409-DB
Signature Not Verified
Digitally SignedPREM
MOHAN CHOUDHARY
Signing Date:16.09.2026
23:34:40
FAO 187/2019 Page 12 of 13

express contractual bar. No such bar has been pointed out by the
appellant. The contention regarding lack of notice under the Interest
Act, 1978 was neither raised before the learned Arbitrator nor is it
sustainable at this stage, especially when the respondent had repeatedly
put the appellant on notice regarding interest on delayed payments.
The rate of interest awarded, being 7.5% per annum, is just, fair, and
reasonable. Similarly, the award of Rs.1,00,000/- towards arbitral costs
under claim no. 6 was within the statutory competence of the learned
Arbitrator.
20. In view of the above discussions, this Court finds that the
findings arrived at by the learned Arbitrator constitute a plausible view
of the material on record. The learned ADJ rightly dismissed the
objections preferred under Section 34 of the Arbitration Act. The
appellant has failed to show any illegality or perversity in the
impugned order or award to warrant interference by this Court under
Section 37 of the Arbitration Act.
21. Consequently, the present appeal is dismissed.
22. The pending application is also disposed of in the above terms.


(MANOJ KUMAR OHRI)
JUDGE
SEPTEMBER 15, 2026