Union Of India Through Dy Chief Engineer Construction Moradabad vs Ms Pragati Construction Consultants
- Court
- Delhi High Court
* IN THE HIGH COURT OF DELHI AT NEW DELHI
% Judgment reserved on: 24.07.2026
Judgment pronounced on: 03.08.2026
+ O.M.P. (COMM) 153/2025 & I.A. 8609/2025
UNION OF INDIA THROUGH DY CHIEF ENGINEER
CONSTRUCTION MORADABAD ....Petitioner
Through: Ms. Rashmi Malhotra & Mr.
Arnab Chanda, Advs.
Versus
MS PRAGATI CONSTRUCTION
CONSULTANTS .....Respondent
Through: Mr. Utsav Garg, Mr. Pushkar
Khanna, Ms. Samvartika Pathak
& Mr. Tulha Rampal, Advs.
CORAM:
HON'BLE MR. JUSTICE AVNEESH JHINGAN
J U D G M E N T
1. This petition is filed under Section 34 of the Arbitration and
Conciliation Act, 1996 (for short „the Act‟) seeking setting aside of
arbitral award dated 04.12.2024.
2. The brief facts are that the petitioner/Northern Railway invited
tenders on 25.07.2019 for the work of earth filling, cutting of
embankment, supply and spreading of blanketing material, mechanical
compaction, construction of minor bridges, duty huts, trolley refuges,
service and residential buildings including electrical works at various
stations between Roza to Jahanikhera stations (Km 0.00 to 40.00 Km)
in connection with the doubling of Roza-Sitapur section of Moradabad
Signature Not Verified
O.M.P. (COMM) 153/2025
Page 1 of 13
Signed By:AWANISH
CHANDRA MISHRA
Signing Date:03.08.2026
16:57:04
Division. On 28.11.2019 the Award Letter was issued in favour of the
respondent at a value of Rs.42,46,24,036.66/-. The contract was
executed between the parties on 14.02.2020.
2.1 As per the contract, the respondent was required to complete the
work within eight months from the date of the letter of acceptance i.e.
by 27.07.2020. The work was not completed within the stipulated
time, the petitioner granted extensions on six occasions and the work
was ultimately completed on 15.12.2021. During the course of
nd
execution of work, the 2 Amendment and Correction (A&C) was
approved on 06.07.2021 for Rs.2,00,63,632.21/- and the cost of work
of was enhanced to Rs.4,81,19,255.36/-.
2.2 On 01.07.2023 as per Clause 64 of the General Conditions of
Contract (GCC) the respondent invoked arbitration claiming a total
amount of Rs.1,95,54,587/- under various heads along with interest at
14% p.a. On 12.09.2023 the arbitral tribunal (for short „the tribunal‟)
was constituted and the proceeding culminated in the impugned award
dated 04.12.2024. The claims were held to be arbitrable and not
falling under the category of „excepted matters‟. The respondent was
awarded Rs. 65,73,261/- with interest at 10.5% p.a. from the date of
receipt of the award, if the award is not satisfied within forty five days
of receipt. Aggrieved of the award, the petitioner has filed the present
petition.
2.3 The decision on claims and counter-claims in the award are
tabulated below:
Signature Not Verified
O.M.P. (COMM) 153/2025
Page 2 of 13
Signed By:AWANISH
CHANDRA MISHRA
Signing Date:03.08.2026
16:57:04
3. Learned counsel for the petitioner contends that the tribunal
erred in directing refund of the amount deducted consequent to
variation in quantities of items pertaining to Schedule „A‟. The
submission is that under Clause 63 of the GCC „excepted matters‟ are
not arbitrable. The tribunal held that claim for refund of deductions
made of items in Schedule „B‟ category was not arbitrable being an
„excepted matter‟ but proceeded to adjudicate the deductions made
under Schedule „A‟. It is emphasized that the respondent accepted the
Signature Not Verified
O.M.P. (COMM) 153/2025
Page 3 of 13
Signed By:AWANISH
CHANDRA MISHRA
Signing Date:03.08.2026
16:57:04
payments without raising objection and the matter falls within the
ambit of clause 63 of the GCC.
3.1 Vis-à-vis claim no.4, the submission is that the tribunal erred in
awarding damages for prolongation of work in absence of evidence of
actual loss suffered. The argument is that price variation compensation
(PVC) was paid to the respondent and the contract clauses barring
awarding of damages on account of prolongation of work were not
considered.
3.2 Lastly, it is argued that the tribunal after calculating the interest
held that the respondent was not entitled to pendente lite interest, yet
awarded the same amount as damages. The relief granted is beyond
the prayer and is contrary to the terms of the contract.
4. Per contra , the scope of interference under Section 34 of the
Act is limited. The view taken by the tribunal is a plausible one and
warrants no interference.
4.1 The direction to refund the amount deducted from the third and
final corrigendum is defended. It is stated that as per clause 42.2(i)
and 42.4(6) of the GCC the variation limit of 25 percent for Schedule
of Rates (SOR) items would apply to the value of SOR as a whole and
not to individual items. The argument is that the tribunal rightly held
that chapter-wise deductions made were contrary to the terms and
conditions agreed between the parties.
4.2 In respect of claim no. 4, the stand is that the tribunal did not
award damages but consequent to prolongation of the work allowed
the fixed cost component. Reliance is on clause 29.4 of the contract, to
fortify the submissions that fifteen per cent out of the total contract
Signature Not Verified
O.M.P. (COMM) 153/2025
Page 4 of 13
Signed By:AWANISH
CHANDRA MISHRA
Signing Date:03.08.2026
16:57:04
value was the fixed cost and on that basis claim no. 4 was quantified.
Reliance is upon the decision of this Court in NTPC Limited Vs.
Mudajaya Corporation, Malaysia Berhad 2026:DHC:3221 to content
that a reasonable yardstick can be applied by the tribunal for
quantifying the damages.
4.3 Lastly, learned counsel for the respondent fairly submits that the
damages awarded under claim no. 6 in lieu of pendent lite interest are
contrary to the contract and cannot be granted.
5. Heard the learned counsel for the parties at length. The relevant
record was perused with their able assistance. No other issue than
those noted above was pressed.
6. Before proceeding further it would be relevant to quote the
following clauses of the GCC:-
“ 42.(2) (i) Unless otherwise specified in the special
conditions of the contract, the accepted variation in
quantity of each individual item of the contract would
be upto 25% of the quantity originally contracted,
except in case of foundation work. The contractor shall
be bound to carry out the work at the agreed rates and
shall not be entitled to any claim or any compensation
whatsoever upto the limit of 25% variation in quantity
of individual item of works.
42.(4) (6) As far as SOR items are concerned, the limit
of 25% would apply to the value of SOR schedule as a
whole and not on individual SOR items. However, in
case of NS items, the limit of 25% would apply on the
individual items irrespective of the manner of quoting
the rate (single percentage rate or individual item
rate).”
7. The relevant clauses of the contract are reproduced below:-
Signature Not Verified
O.M.P. (COMM) 153/2025
Page 5 of 13
Signed By:AWANISH
CHANDRA MISHRA
Signing Date:03.08.2026
16:57:04
“ 2.2 COMPLETION OF TENDER DOCUMENTS
2.2.1 The tenderers shall quote the rates of one single %
age "Above/Below/At par" on the total amount
comprising basic value of entire Schedule-A of Chapters
of USSOR-2010 plus escalation and Scheduled of
Chapters of SOR of electrical one single age “Above /
Below / At par” over entire schedule of Non schedule
Items (Schedule B and Schedule-D) in the Schedule of
Items, Rates and Quantities. Every possible fluctuation
in the rate of labour, material and general commodities,
and other possibilities of each and every kind which
may affect the rates, should be considered and kept in
view before, quoting the rates and no claim on this
account shall be entertained by the Railway under any
circumstances except the price escalation payable, as
per price variation clause, if any, provided 'separately
in the tender documents.
2.2.2 The quantities shown, in the attached Schedule are
given as a guide and are approximate only and are
subject to variation according to the needs of the
Railway. The Railway does not guarantee work under
each item of the. Schedule. The tenderer(s) shall quote
rates/ rebates only at specified place in. Tender Form
supplied by Railway. Any revision of rates / rebates
submitted (quoted) through a separate letter whether
enclosed with the bid (Tender Form) or submitted
separately or mentioned elsewhere in the document
other than specified place shall be summarily ignored
and will not be considered. In case of tender other than
e tender, mode, Multiple Rates- in case tenderer/s quote
selective rebate on any individual item(s) of a USOR
Chapter of Schedule-A individual NS. Item of Schedule-
B, the same will be treated as multiple rate and their
offer will be summarily rejected.
29. Price Variation Clause-(applicable for contract
value Rs. 5 Cr and more)
Signature Not Verified
O.M.P. (COMM) 153/2025
Page 6 of 13
Signed By:AWANISH
CHANDRA MISHRA
Signing Date:03.08.2026
16:57:04
29.1 Price Variation Clause shall be applicable only
for tenders, of value (Contract Agreement value) Rs. 5
crore. and more, irrespective of the contract completion
period. Variation in quantities shall not be taken into
account for applicability of PVC in the contract.
Material supplied free of cost by Railway to the
contractors and any extra item(s) included in subsequent
variation, falling outside the purview of the Schedule of
items of tender shall fall outside the purview of. Price
Variation Clause, if in any case, accepted offer includes
some specific payment to be made to consultants or
some material Supplied by Railway free or at fixed rate;
such payments shall be excluded from the gross value of
the work for the purpose of payment/recovery of price
variation.
*
29.4 Adjustment for variation in prices of material,
labour, fuel, explosives, detonators, steel, concreting,
ferrous, non-ferrous, insulators, zinc and cement shall be
determined in the manner prescribed.”
8. In claim no. 1, the grievance raised before the tribunal pertained
to deductions made on account of variation in quantities of items
mentioned in Schedule „A‟ and „B‟. The claim relating to Schedule
„B‟ was rejected, held to be an „excepted matter‟ covered by clause 63
of the GCC and non-arbitrable. The grievance of the petitioner is
confined to the refund ordered qua the deductions made for items
falling under Schedule „A‟. The tribunal considered clause 2.2.1 and
2.2.2 of the contract and clause 42.2(i) and 42.4(6) of the GCC and
held that for SOR items the variation limit of 25 percent is to be
considered taking the whole value for SOR schedule whereas the
Signature Not Verified
O.M.P. (COMM) 153/2025
Page 7 of 13
Signed By:AWANISH
CHANDRA MISHRA
Signing Date:03.08.2026
16:57:04
petitioner contrary to the clause 42.4(6) of the GCC made deductions
of the items chapter-wise.
9. The plea raised by the petitioner that the deductions were made
chapter-wise as per the past practice was rightly held to be contrary to
the terms of the contract. The procedure adopted by the petitioner was
against the terms and conditions agreed between the parties and for
this reason, the contention that the disputes relates to „excepted
matter‟ was rejected. In other words the petitioner having violated the
terms and conditions of the contract cannot raise shield of clause 63 of
the GCC that violation of terms is an „excepted matter‟.
10. The contention of the learned counsel for the petitioner that the
tribunal has blown hot and cold in the same breath, having held issue
of deductions under Schedule „B‟ to be „excepted matter‟, yet
adjudicated deductions under Schedule „A‟, is ill-founded. The
deductions of Schedule „B‟ category items were made as per the
agreed procedure and the deductions under Schedule „A‟ were in
violation of the terms of the contract. Both the scenarios stand on a
different footing. The view of the tribunal is plausible and it is trite
law that under Section 34 of the Act Court does not sit in appeal and
possibility of another view is not a ground for interference.
11. The respondent under claim no. 4 sought a sum of
Rs.1,40,00,000/- (rupees one crore and forty lakhs) towards losses
suffered and expenses incurred due to prolongation of the contract, on
failure of the petitioner to make the work sites available in time.
Signature Not Verified
O.M.P. (COMM) 153/2025
Page 8 of 13
Signed By:AWANISH
CHANDRA MISHRA
Signing Date:03.08.2026
16:57:04
12. It would be relevant to quote the following decisions of the
Supreme Court dealing with the principles governing award of
liquidated damages (for short „LD‟):-
12.1 The Supreme Court in Kailash Nath Associatesv. DDA (2015)
4 SCC 136 held:
“43.1. Where a sum is named in a contract as a liquidated
amount payable by way of damages, the party complaining
of a breach can receive as reasonable compensation such
liquidated amount only if it is a genuine pre-estimate of
damages fixed by both parties and found to be such by the
court. In other cases, where a sum is named in a contract as
a liquidated amount payable by way of damages, only
reasonable compensation can be awarded not exceeding the
amount so stated. Similarly, in cases where the amount fixed
is in the nature of penalty, only reasonable compensation
can be awarded not exceeding the penalty so stated. In both
cases, the liquidated amount or penalty is the upper limit
beyond which the court cannot grant reasonable
compensation.
43.2. Reasonable compensation will be fixed on well-known
principles that are applicable to the law of contract, which
are to be found inter alia in Section 73 of the Contract Act.
43.3. Since Section 74 awards reasonable compensation for
damage or loss caused by a breach of contract, damage or
loss caused is a sine qua non for the applicability of the
section.
43.4. The section applies whether a person is a plaintiff or a
defendant in a suit.
43.5. The sum spoken of may already be paid or be payable
in future.
43.6. The expression “whether or not actual damage or loss
is proved to have been caused thereby” means that where it
is possible to prove actual damage or loss, such proof is not
Signature Not Verified
O.M.P. (COMM) 153/2025
Page 9 of 13
Signed By:AWANISH
CHANDRA MISHRA
Signing Date:03.08.2026
16:57:04
dispensed with. It is only in cases where damage or loss is
difficult or impossible to prove that the liquidated amount
named in the contract, if a genuine pre-estimate of damage
or loss, can be awarded.”
12.2 The Supreme Court in State of Rajasthan v. Ferro Concrete
Construction (P) Ltd. , (2009) 12 SCC 1 held:
“55.While the quantum of evidence required to accept a
claim may be a matter within the exclusive jurisdiction of
the arbitrator to decide, if there was no evidence at all and if
the arbitrator makes an award of the amount claimed in the
claim statement, merely on the basis of the claim statement
without anything more, it has to be held that the award on
that account would be invalid. Suffice it to say that the
entire award under this head is wholly illegal and beyond
the jurisdiction of the arbitrator, and wholly unsustainable.”
13. The tribunal held that the delay in completion of the work was
attributable to the petitioner. It was factored that the extension of time
without levy of penalty proved that the delay was not attributable to
the respondent. The law is well-settled that for awarding LD under
Section 73 of the Indian Contract Act, 1872 (for short „the Contract
Act‟) the twin conditions are required to be fulfilled. First, breach of
the contractual conditions and second, the actual loss or damage
suffered or the proof that it is not possible to prove the actual damage
suffered. In the present case, the second limb is missing. No evidence
was adduced by the respondent of actual loss suffered. It was not the
case set up that it was impossible or difficult to prove the actual loss.
The damages awarded are in violation of Section 73 of the Contract
Act and the settled position of law.
Signature Not Verified
O.M.P. (COMM) 153/2025
Page 10 of 13
Signed By:AWANISH
CHANDRA MISHRA
Signing Date:03.08.2026
16:57:04
14. The contention of the learned counsel for the respondent that
the tribunal awarded only the fixed cost component and not damages,
lacks merit. The claim made by the respondent was for the losses
incurred. The tribunal has specifically recorded that the respondent
was entitled to the compensation over and above the PVC.
15. Equally unpersuasive is the reliance of the respondent on clause
29.4 of the contract to support quantification of the damages. Clause
29 deals with price variation and has no application to a claim made
by the respondent for damages on account of prolongation of work.
16. The decision in NTPC Limited (supra) relied upon by the
learned counsel for the respondent is not applicable in the facts of the
present case. In that case, the arbitrator recorded a factual finding that
it would be difficult to assess the damage under each claim separately
and thereafter proceeded to award a reasonable compensation.
Whereas there is no finding by the tribunal in the case in hand that it
was difficult or impossible to prove the actual loss.
17. Under claim no. 6, the respondent prayed for grant of interest
from the date of completion of work. The tribunal quantifies the
interest, rejects the claim of the interest in view of the clauses of the
contract but proceeds to award the same amount as damages. The
relief granted is beyond the prayer and is vitiated by patent illegality
and is liable to be interfered with under Section 34(2)(a)(iv) of the
Act. The arbitral award cannot deal with matters beyond the scope of
the submission to arbitration.
18. Learned counsel for the respondent in all fairness conceded that
the damages could not have been granted.
Signature Not Verified
O.M.P. (COMM) 153/2025
Page 11 of 13
Signed By:AWANISH
CHANDRA MISHRA
Signing Date:03.08.2026
16:57:04
19. The impugned award attracts interference under Section 34 of
the Act being contrary to the public policy and vitiated by patent
illegality. The damages awarded under claim no. 4 were in
contravention to the Contract Act. Claim no.6 for interest was rejected
but the tribunal, beyond the prayer awarded the same amount as
damages rendering the award patently illegal.
20. The Supreme Court in Gayatri Balasamy v. ISG Novasoft
Technologies Ltd ., (2025) 7 SCC 1 held that while an arbitral award
cannot be modified under Section 34 of the Act, a severable part of the
award may be set aside. The relevant paragraphs are quoted below:
“32. In the present controversy, the proviso to Section
34(2)(a)(iv) is particularly relevant. It states that if the
decisions on matters submitted to arbitration can be
separated from those not submitted, only that part of the
arbitral award which contains decisions on matters non-
submitted may be set aside. The proviso, therefore,
permits courts to sever the non-arbitrable portions of an
award from arbitrable ones. This serves a twofold
purpose. First, it aligns with Section 16 of the 1996 Act,
which affirms the principle of kompetenz- kompetenz ,
that is, the arbitrators' competence to determine their
own jurisdiction. Secondly, it enables the Court to sever
and preserve the “valid” part(s) of the award while
27
setting aside the “invalid” ones. Indeed, before us,
none of the parties have argued that the Court is not
empowered to undertake such a segregation.
33. We hold that the power conferred under the proviso
to Section 34(2)(a)(iv) is clarificatory in nature. The
authority to sever the “invalid” portion of an arbitral
award from the “valid” portion, while remaining within
the narrow confines of Section 34, is inherent in the
Court's jurisdiction when setting aside an award.
Signature Not Verified
O.M.P. (COMM) 153/2025
Page 12 of 13
Signed By:AWANISH
CHANDRA MISHRA
Signing Date:03.08.2026
16:57:04
34. To this extent, the doctrine of omne majus continet
in se minus —the greater power includes the lesser—
applies squarely. The authority to set aside an arbitral
award necessarily encompasses the power to set it aside
in part, rather than in its entirety. This interpretation is
practical and pragmatic.It would be incongruous to hold
that power to set aside would only mean power to set
aside the award in its entirety and not in part. A contrary
interpretation would not only be inconsistent with the
statutory framework but may also result in valid
determinations being unnecessarily nullified.”
(emphasis supplied)
21. In view of the above discussions, challenge to the claim no. 1 of
the petitioner fails and the award is upheld. The claims nos. 4 and 6
awarded suffer from patent illegality and are set aside.
22. The claims nos. 4 and 6 are severable not intricately connected
to the other claims by the tribunal. Consequently, the award to the
extent of claims nos. 4 and 6 is set aside.
23. The petition is accordingly partly allowed. Pending application
stands disposed of.
AVNEESH JHINGAN, J
AUGUST 3, 2026
Pa
Reportable:- Yes
Signature Not Verified
O.M.P. (COMM) 153/2025
Page 13 of 13
Signed By:AWANISH
CHANDRA MISHRA
Signing Date:03.08.2026
16:57:04