M/S AMMAPUR INFRASTRUCTURE PVT LIMITED vs UNION OF INDIA
- Court
- Karnataka High Court
- 1 -
HC-KAR
NC: 2026:KHC-D:17971
WP No. 108351 of 2025
CNR: KAHC020231002025
IN THE HIGH COURT OF KARNATAKA
AT DHARWAD
ND
DATED THIS THE 2 DAY OF NOVEMBER, 2026
BEFORE
THE HON'BLE MR. JUSTICE M.G.S. KAMAL
WRIT PETITION NO.108351 OF 2025 (GM-TEN)
BETWEEN:
M/S. AMMAPUR INFRASTRUCTURE PVT. LIMITED,
(REGISTERED UNDER COMPANIES ACT 2013),
H. NO. 2-8-197/112-115 SAPTHAGIRI NILAY,
BHAGEERATH COLONY, GUADANAL ROAD,
LINGASUGUR, TQ. LINGASUGUR,
DIST. RAICHUR - 548122.
(REP BY SRI SRINIVAS H AMMAPUR.)
…PETITIONER
(BY SRI. NAVEEN G.S, ADVOCATE)
AND:
1. UNION OF INDIA,
MINISTRY OF ROAD TRANSPORT AND HIGHWAYS,
OFFICE OF THE REGIONAL OFFICER (CIVIL),
ND
NO.32, 2 FLOOR, KSCFL BUILDING RACE COURSE
ROAD,
BENGALURU - 560 001.
(REP BY ITS REGIONAL OFFICER)
2. THE CHIEF ENGINEER,
NATIONAL HIGHWAYS, NORTH ZONE,
SUVARNA VIDHANA SOUDHA,
BELAGAVI - 580001.
3. THE EXECUTIVE ENGINEER,
NATIONAL HIGHWAYS DIVISION,
VIJAYAPURA - 586 101.
Digitally
signed by
SAROJA
HANGARAKI
Location:
High Court
of
Karnataka,
Dharwad
Bench
…RESPONDENTS
(BY SRI. ASHOK T. KATTIMANI, AGA FOR R2 AND R3;
SRI. SOMASHEKHAR B. ANCHATAGERI, ADVOCATE FOR R1)
- 2 -
HC-KAR
NC: 2026:KHC-D:17971
WP No. 108351 of 2025
CNR: KAHC020231002025
THIS WRIT PETITION IS FILED UNDER ARTICLES 226 OF THE
CONSTITUTION OF INDIA, PRAYING TO ISSUE A WRIT OR SUCH
OTHER ORDERS IN THE NATURE OF CERTIORARI TO SET ASIDE OR
QUASH THE ORDER PASSED BY RESPONDENT NO. 2, DATED
25.09.2025 BEARING NO.CE/NH(N) /TA-01/AE-04/NH-150A/ MASKI
AND SINDHANUR BYPASS / 2025-26/1159 AND PRODUCED AS
ANNEXURE-N AND ETC.
THIS WP COMING ON FOR ORDERS, THIS DAY, ORDER WAS
MADE THEREIN AS UNDER:
CORAM: HON'BLE MR. JUSTICE M.G.S. KAMAL
ORAL ORDER
1. Petitioner is before this Court being aggrieved by the
order dated 25.09.2025 passed by respondent
No.2/Chief Engineer, in terms of which, Engineering
Procurement and Construction Agreement (“Agreement”
for short) dated 20.07.2024, that had been entered into
between respondent No.2/Chief Engineer and the
petitioner herein for the purpose of construction of Maski
Bypass (starting at existing Km.144.220 and ends at
existing Km.151.760 and Sindhrur Bypass (starts at
existing Km.168.370 and ends at existing Km.180.800
on NH 150A of the State of Karnataka, has been
cancellation, which order has been communicated to the
petitioner as per Annexure-N.
- 3 -
HC-KAR
NC: 2026:KHC-D:17971
WP No. 108351 of 2025
CNR: KAHC020231002025
2. Consequent thereof respondent No.1 has issued fresh
Notice Inviting Tender (NIT) dated 03.10.2025 as per
Annexure-Q.
3. It is in this background the present petition is filed
seeking following relief.
i. Issue a Writ or such other orders in the nature of
Certiorari to set aside or quash the order passed by
respondent No.2, dated 25.09.2025 bearing
No.CE/NH(N)/TA-01/AE-04/NH-150A/Maski &
Sindhanur Bypass/2025-26/1159 and produced as
Annexure-N.
ii. Issue a writ or such other orders in the nature of
Certiorari to set aside or quash the fresh
Notification Inviting Tender (NIT) dated
03.10.2025, bearing Bid No.RW/BNG/NH-
nd
150A/Maski & Sindhanur Bypass/62/2023 (2 Call)
issued by Respondent No.1 and produced as
Annexure-Q.
iii. Pass such other or further orders as this Hon’ble
Court may deem fit, proper and expedient in the
facts and circumstances of the case, in the interest
of justice and equity.
4. Learned counsel for the petitioner taking this Court to
the records extensively and submits that the termination
of the Agreement is arbitrary, unilateral and the non
performance/breach, if any, is attributable only to the
respondents/authorities who though admitted non-
compliance of their obligation, have merely taken upon
- 4 -
HC-KAR
NC: 2026:KHC-D:17971
WP No. 108351 of 2025
CNR: KAHC020231002025
insignificant excuse of petitioner not furnishing the
Additional Performance Security to be the reason for
cancellation of the Agreement. While according to their
own admission in the correspondence produced at
Annexures-K and L, they had not even acquired 50% of
the land required for construction of the road even as on
28.08.2025, let alone handing over of the same to the
petitioner within 30 days from the date of Agreement as
contemplated under Article 3.1(iii)(a) of the Agreement.
5. He further submits that, though the ostensible reason
for cancellation of Agreement is non-furnishing of the
Additional Performance Security, the petitioner had
submitted the same on 05.02.2025, which have been
accepted and renewed by the respondents/authorities as
late as on 27.01.2026 and 24.07.2026 respectively.
Thus the respondents are not justified in terminating the
Agreement based on the reason for petitioner not
submitting the bank guarantee and Additional
Performance Security within the time stipulated under
- 5 -
HC-KAR
NC: 2026:KHC-D:17971
WP No. 108351 of 2025
CNR: KAHC020231002025
the Agreement resulting in cancellation of the
Agreement.
6. He further submits that the costs of the contract which
was awarded to the petitioner and the costs of the
contract which is now sought to be entered into
pursuant to the notification are one and the same.
Therefore in the absence of any significant change in the
costs of construction of the road and the petitioner being
ready and willing to perform his part of the contract the
respondent/authorities shall be directed to extend the
time for performance of the contract and the petitioner
is ready and willing to complete the construction if a
fixed period of time is given. He further submits that, if
the respondent/authorities hand over the land even
today the petitioner has all the necessary men and
material and would complete the construction within the
time stipulated. Hence seeks for allowing the petition.
7. Per contra learned Additional Government Advocate
appearing for respondents/authorities referring to the
- 6 -
HC-KAR
NC: 2026:KHC-D:17971
WP No. 108351 of 2025
CNR: KAHC020231002025
statement of objections submitted that the work
contract was required to be performed strictly in
accordance with the terms of the Agreement dated
20.07.2024. That there is a breach committed by the
petitioner in furnishing the Full Performance Security
and Additional Performance Security within the
stipulated time, including the permissible extension
period. That since no such performance security was
submitted, there was delay in acquiring the land, which
is attributable to the petitioner alone. Since, the contract
has been terminated by a speaking order dated
25.09.2025 and a fresh notice inviting tender has been
issued on 03.10.2025, the petitioner cannot seek grant
of relief as sought for in the writ petition.
8. Learned Additional Government Advocate further refers
to the Statement of objections filed on behalf of the
State to contend that the performance and Additional
Performance Security was to furnish within the time
stipulated under Clause 7.1(iv) and non-fulfillment of
- 7 -
HC-KAR
NC: 2026:KHC-D:17971
WP No. 108351 of 2025
CNR: KAHC020231002025
the period stipulated has been given effect resulting in
termination of the Agreement by a detailed order. He
submits that the acquisition and handing over the 90%
of the land is contingent upon petitioner furnishing the
performance security in 60 days. Since there was a
failure on his part, the petitioner has not taken further
action in the matter.
9. Referring to paragraph Nos.11 to 13 of the statement of
objections, he submitted that the Assistant Executive
Engineer vide letter dated 28.08.2025 as per Annexure-
L had called upon the petitioner to proceed with the pre-
construction activities with the available 50% of the land
to demonstrate his bona fide and good faith which has
been admitted by the petitioner yet the petitioner did
not perform his part of the contract constraining the
respondents/authorities to terminate the Agreement. He
hastened to add that in the light of the fresh tenders
being invited, petitioner is at liberty to participate in the
same. Hence seeks for dismissal of the petition.
- 8 -
HC-KAR
NC: 2026:KHC-D:17971
WP No. 108351 of 2025
CNR: KAHC020231002025
10. Heard. Perused the records.
11. There is no dispute that the respondent and the
petitioner herein had indeed entered into a construction
Agreement on 20.07.2024 as per Annexure-C for
purpose of construction of Maski-Sindanur Bypass as
noted above. In terms of Article 3.1(iii)(a), 90% of the
required right of way of the construction zone of total
length of the project highway shall be provided to the
contractor within 30 days from the date of the
Agreement, upon submission of the performance
security as per request for proposal by the contractor.
The said clause reads as under;
“3.1 Obligations of the Authority
(iii) The Authority shall, upon submission of the
Performance Security as per the RFP by the
Contractor, shall provide to the Contractor:
(a) No less than 90% (ninety per cent) of the
required Right of Way of the Construction
Zone of total length of the Project Highway
within a period of 30 (thirty) days from
the date of this Agreement, which shall be
in contiguous stretches of length not less
than 5 (five) kilometer.”
- 9 -
HC-KAR
NC: 2026:KHC-D:17971
WP No. 108351 of 2025
CNR: KAHC020231002025
12. Clause 3.4 of the Agreement, which is heavily relied
upon by the respondents/authorities in the statement of
objections read as under;
“3.4 Deemed termination upon delay
Without prejudice to the provisions of Clauses 8.3,
and subject to the provisions of Clause 7.3, the Parties
expressly agree that in the event the Appointed Date
does not occur, for any reason whatsoever, within 90
days of signing of the Agreement and submission of
the full Performance Security by the Contractor, the
Agreement shall be deemed to have been terminated.
The Authority shall pay damages to the Contractor
equivalent to 1% of the Contract Price (3% in case of
standalone bridge projects). All other rights,
privileges, claims and entitlements of the Contractor
under or arising out of this Agreement shall be
deemed to have been waived by, and to have ceased.
The Contractor shall hand over all information in
relation to the Highway, including but not limited to
any date, designs, drawings, structures, information,
plans, etc. prepared by them for Highway, to the
Authority.
13. Article 7 dealing with the performance security. Article
7.1(i)(a) of the Agreement reads as under;
“7.1 Performance Security
(i) Within 30 (thirty) days of receipt of Letter of
Acceptance, the selected Bidder shall furnish to the
Authority in the form of Insurance surety Bond in the
form set forth in Annex III of Schedule G, Account
payee Demand Draft, Banker’s Cheque or irrevocable
and unconditional c-Bank Guarantee from a Bank in the
form set forth in Annex-I of Schedule-G(the
“Performance Security”) for an amount equal to 3%
(three percent) as per Ministry circular No.NH-
37015/01/2022-H (Comp No.208778) Dtd: 18.05.2022
- 10 -
HC-KAR
NC: 2026:KHC-D:17971
WP No. 108351 of 2025
CNR: KAHC020231002025
of its Bid Price. In case of bids mentioned below, the
selected Bidder, along with the Performance Security,
shall also furnish to the Authority in the form of
Insurance surety Bond (in the same form given at
Annex III of Schedule G)”, Account payee Demand
Draft, Banker’s Cheque or irrevocable and unconditional
guarantee from a Bank in the same form given at
Annex-J of Schedule-G towards an Additional
Performance Security (the “Additional Performance
Security”) for an amount calculated as under:
(a) If the Bid Price offered by the Selected Bidder is
lower than 20% of the estimated Project Cost/cost put
to tender, then the Additional Performance Security
shall be calculated @ 20% of the difference in the
(i) Estimated project Cost (as mentioned in REF)-20%
of the Estimated project Cost and (ii) the Bid Price
offered by the selected Bidder.”
14. There is no dispute that there was delay in petitioner
submitting the Additional Performance Security.
However, the justification being offered to the petitioner
is non-performance of obligation by the
respondents/authorities in handing over 90% of the
right of way, which according to the respondents /
authorities contingent upon the reciprocal performance
by petitioner.
15. Be that as it is. The terms of the Agreement and the
extensive pleadings and the documents enclosed by the
parties in the writ petition, statement of objections,
- 11 -
HC-KAR
NC: 2026:KHC-D:17971
WP No. 108351 of 2025
CNR: KAHC020231002025
rejoinder and reply to the rejoinder indicate that both of
them have made averments and counter averments
alleging breach of performance, term of the contract and
failure in performing their respective parts of contract.
16. Article 26 of the Agreement provides for dispute
resolution, through conciliation and arbitration. It also
provides for the authority to adjudicate upon such
dispute.
17. Considering the petition averments, statement of
objection and the documents, this Court do not find it
appropriate to adjudicate upon these
controversial/complex disputed issues under Article 226
of the Constitution.
18. Reserving liberty to the parties to resolve their disputes
in terms of the dispute resolution mechanism provided
in the Agreement, petition is disposed of.
19. It is made clear that, this Court has not expressed any
view or opinion on the merits or otherwise of the case.
- 12 -
HC-KAR
NC: 2026:KHC-D:17971
WP No. 108351 of 2025
CNR: KAHC020231002025
The narration of the facts and submission is only for the
limited purpose of examining if this Court could
entertain this petition under Article 226 of the
Constitution, which now has held to be otherwise.
20. At this juncture, learned counsel for the petitioner
submits that, since the new tender, which is called for is
for a similar value of the Agreement which is now
terminated, respondents/authorities be directed to
provide an opportunity to the petitioner to perform its
obligation of putting up the construction by extending
the time.
21. Learned Additional Government Advocate submits that
notwithstanding that issuance of notice of terminate
without prejudice, petitioner may make a representation
and if it feasible and permissible under law same will be
considered.
22. In that view of the mater, petitioner is at liberty to
submit the representation within a period of 10 days
- 13 -
HC-KAR
NC: 2026:KHC-D:17971
WP No. 108351 of 2025
CNR: KAHC020231002025
from today and the respondents/authorities shall
consider the same and pass appropriate orders thereon,
within a period of 10 days thereafter.
23. The interim order granted, shall stand extended till 30
days from today.
24. It is made clear that liberty reserved shall not be
construed as recognition of any right of the petitioner for
extension or revival of the agreement.
Sd/-
(M.G.S. KAMAL)
JUDGE
EM
CT:SD
LIST NO.: 1 SL NO.: 85