Navin Kumar vs The State Of Bihar and Ors

Court
Patna High Court

IN THE HIGH COURT OF JUDICATURE AT PATNA
Civil Writ Jurisdiction Case No.9839 of 2018
======================================================
Navin Kumar Son of Rameshwar Prasad Yadav, Resident of Village- Bari
Aighu, Police Station- Muffassil, District- BegusaraiBihar.
... ... Petitioner/s
Versus
1. The State Of Bihar
2. The Principal Secretary, Urban Development and Housing Department,
Government of Bihar, Vikas Bhawan, Bailey Road, Patna - 800015
3. The Secretary, Bihar Rural Road Development Agency, 5th Floor,
Vishveshwarya Bhawan, Bailey Road, Patna
4. The Engineer-in-Chief, Rural Road Development Agency, 5th Floor,
Vishveshwarya Bhawan, Bailey Road, Patna
5. The Commissioner, Munger Division, District- Munger Bihar.
6. The District Magistrate-cum-Chairman, District Urban Development
Agency, Khagaria Bihar.
7. The Chief Engineer-2, Rural Works Department, Bhagalpur Camp,
Vishveshwarya Bhawan, Bailey Road, Patna
8. The Deputy Development Commissioner, Khagaria, District- Khagaria
Bihar.
9. The Superintending Engineer, Rural Works Department, Works Circle-2,
Saharsa, District- Saharsa Bihar
10. The Executive Engineer, Rural Works Department, Works Division-2,
Newly Constituted Work Division- Gogri, DIstrict Khagaria, Bihar
11. The Executive Engineer, Rural Development, Special Division, Khagaria,
District Khagaria Bihar.
12. The Executive Engineer, Road Construction Department, Road Division,
Khagaria, District- Khagaria Bihar
13. The Sub-Divisional Officer-cum-Assistant Engineer, Rural Works
Department, Works Division-2, Newly Constituted Work Division- Gogri,
DIstrict Khagaria, Bihar
14. The Junior Engineer, Rural Works Department, Works Division-2, Now
Newly Constituted Work Division- Gogri, DIstrict Khagaria, Bihar
... ... Respondent/s
======================================================
Appearance :
For the Petitioner/s : M/s Yogesh Chandra Verma, Sr. Advocate
Om Prakash
Uday Shankar Pandey, Advocates
For the Respondent/s : Mr. Avdhesh Kumar Singh, AAG 6
Arvind Kumar, AC to AAG 6

Patna High Court CWJC No.9839 of 2018 dt.21-09-2026
2/14
======================================================
CORAM: HONOURABLE JUSTICE SMT. G. ANUPAMA CHAKRAVARTHY
ORAL JUDGMENT
Date : 21-09-2026
1. The petitioner has filed the instant
application for the following reliefs:
“(A) For issuance of a Writ in the nature of
Certiorari or any other appropriate
Writ/Writs quashing the order dated
15.12.2017 contained in Memo No. 1792
dated 31.12.2017 passed by the District
Magistrate Khagaria (Respondent No. 6
Annexure-18) in view/compliance of the
order dated 22.09.2017 passed in C.W.J.C.
No. 14256 of 2015 by the Hon'ble Bench of
the Patna High Court (Annexure-15)
whereby and where under he has rejected
the petitioner's claim of payment of
outstanding admitted due amount of Rs.
13,67,134/ against Last/Final Bill contained
in Measurement Book at Pg. No. 25 and
also payment of refund of Security Deposit
of Rupees 6,14,451 i.e. total amounting to
Rs. 19,81,585/- with 5% simple interest per
annum upon the same in view of the
aforesaid order passed by the Hon'ble
Patna High Court, purely/arbitrarily on
Legal/Administrative and technical
grounds, committed by the respondents
concerned, not by the petitioner as same
was beyond the control of him. The

Patna High Court CWJC No.9839 of 2018 dt.21-09-2026
3/14
aforesaid payment is to be made
for/against satisfactorily completion of 2.70
K.M. By-Pass road from Bakhari Bus-Stand
to Baluahi Bapu Park under "Mukhya Mantri
Sahari Vikas Yojana" in Khagaria District
within stipulated period of 12 months,
done by the petitioner under jurisdiction of
Executive Engineer (Respondent No. 10).
(B) A Writ in the nature of Mandamus or
any other appropriate Writ or Writs/order,
direction/directions commanding
Respondent for the following:-the
(i) To make the payment outstanding
admitted due amount of Rs. 13,67,134/-to
the petitioner against the Last/Final Bill as
contained in Measurement Book at Page
No. 25 relates to satisfactorily completion
of construction of "2.70 K.M. By-Pass Road"
from Bakhari Bus Stand to Baluahi Bapu
Park under "Mukhya Manti Sahari Vikas
Yojana" in Khagaria District, done by him
under Respondent No. 10.
(ii) To direct the respondent to pay interest
at the @ 18% per annum to the petitioner
upon the aforesaid admitted due amount
i.e. Rs. 13,67134/- from the date of Bill till
the date of final payment.
(iii) And further for commanding and
directing the concerned Respondent to
make refund of security deposit i.e. Rs.
6,14,451/- with interest at the rate of 18
percent per annum from the date of its

Patna High Court CWJC No.9839 of 2018 dt.21-09-2026
4/14
entitlement till payment to the petitioner.
(C) For passing such other order or orders
for which the petitioner is found entitled
under the law, in the facts and
circumstances of the case."
2. The brief facts culled out of the Writ
petition are that the petitioner is a Class-II
registered contractor with the Rural Works
Department, Government of Bihar, bearing
Registration No. 1689/10. Pursuant to a tender
notice published in August, 2010, the petitioner
was awarded the work of construction of a 2.70
K.M. bypass Road from Bakhari Bus Stand to
Baluahi Bapu Park in Khagaria District under the
Mukhya Mantri Sahari Vikas Yojana, for an
agreement value of Rs.1,37,40,647/-. An
agreement was executed on 02.02.2011 and, on
the same date work order was issued o,
prescribing a period of twelve months for
completion of the work.
3. The petitioner claims to have completed
the work, within the stipulated period and,
pursuant thereto, measurements were recorded in

Patna High Court CWJC No.9839 of 2018 dt.21-09-2026
5/14
the Measurement Book and a final bill of
Rs.13,67,134/- was prepared. Out of the
agreement amount, Rs.1,22,89,020/- had already
been paid to the petitioner after deduction of
Rs.6,14,451/- towards security deposit. The
concerned authorities also issued certificates
regarding completion of the work and an
experience certificate in favour of the petitioner.
The petitioner thereafter repeatedly requested
payment of the final bill and for refund of the
security deposit, but the same was not paid.
4. The petitioner earlier approached this
Court in C.W.J.C. No.14256 of 2015. The Writ
petition was disposed of on 22.09.2017 directing
the District Magistrate, Khagaria to examine the
petitioner's claim and make payment of the
admitted dues within three months. In case of
disagreement, the District Magistrate was directed
to pass a reasoned order after giving notice to and
an opportunity of hearing to the petitioner. It was
further directed that the admitted amount would
carry simple interest at the rate of 5% per annum.

Patna High Court CWJC No.9839 of 2018 dt.21-09-2026
6/14
5. Pursuant to the said order, the petitioner
was heard by the District Magistrate, Khagaria on
15.12.2017. By order dated 15.12.2017, the claim
of the petitioner was rejected principally on the
grounds of alleged deficiencies in the estimate,
Measurement Book and technical approval as well
as alleged lapses on the part of the departmental
officials.
6. The grievance of the petitioner is that
the work had admittedly been completed, the
measurements had been recorded, the final bill
had been prepared and substantial payment had
already been made, while the grounds assigned for
withholding the remaining amount pertained to
alleged lapses on the part of departmental
authorities and not to any default on the part of
the petitioner.
7. Mr. Yogesh Chandra Verma, the Learned
Senior counsel for the petitioner submits that the
petitioner duly completed the work under a valid
agreement and within the stipulated period, as is
supported by the departmental measurement

Patna High Court CWJC No.9839 of 2018 dt.21-09-2026
7/14
records, completion certificates and experience
certificate. It is submitted that the final bill for
Rs.13,67,134/- was prepared after measurement of
the work, and a sum of Rs.6,14,451/- was deducted
and retained towards security deposit.
8. The Learned Senior counsel further
submits that the earlier order of this Court dated
22.09.2017 required the District Magistrate to
examine the claim and pay the admitted dues, or,
if the claim was disputed, to pass a reasoned order
after hearing the petitioner. However, instead of
identifying any default or deficiency attributable to
the petitioner, the impugned order relies upon
alleged deficiencies or omissions on the part of the
departmental authorities.
9. It is, therefore, submitted by the
Learned Senior Counsel for the petitioner that the
petitioner cannot be deprived of payment for work
admittedly executed merely on account of alleged
procedural or technical lapses on the part of the
respondents' officials. Learned counsel accordingly
prayed to quash of the impugned order and

Patna High Court CWJC No.9839 of 2018 dt.21-09-2026
8/14
sought for a direction to the respondents to release
the final bill amount of Rs.13,67,134/- along with
the security deposit of Rs.6,14,451/- with an
appropriate interest.
10. Counter affidavits and supplementary
counter affidavit have been filed on behalf of the
State respondents. The Learned counsel for the
respondents submits that pursuant to the order
dated 22.09.2017 passed in C.W.J.C. No.14256 of
2015, notice was duly issued to the petitioner and
having heard by the District Magistrate, Khagaria,
after examining the relevant records, the claim of
the petitioner was rejected by order dated
15.12.2017, communicated vide Memo No.1792
dated 31.12.2017.
11. The Learned counsel for the
respondents submits that the petitioner's claim for
Rs.13,67,134/- towards the final bill and
Rs.6,14,451/- towards security deposit could not be
accepted, as the departmental examination
disclosed deficiencies in the execution and
documentation of the work. The project, being

Patna High Court CWJC No.9839 of 2018 dt.21-09-2026
9/14
above Rs.50 lakhs, was required to be supervised
by the Superintending Engineer in terms of
Notification No.5343 dated 22.10.2008, however,
such supervision and verification of the
Measurement Book at the prescribed level were
not undertaken.
12. It is further submitted by the Learned
counsel for the respondents that the reports of the
Executive Engineer, Road Construction
Department, Khagaria raised concerns regarding
the condition and thickness of the road and its
suitability for heavy vehicles. Deficiencies were
also noticed in the preparation of the estimate and
in the relevant entries in the Measurement Book,
and, therefore, payment of Government money
could not be made contrary to the prescribed
departmental norms.
13. The Learned counsel for the
respondents further submits that the District
Magistrate, Khagaria was the fund-sanctioning
authority, whereas the concerned department was
only the executing agency. Since the claim had

Patna High Court CWJC No.9839 of 2018 dt.21-09-2026
10/14
already been examined and rejected by the District
Magistrate by a reasoned order, the executing
department has no further role in the matter.
Further, the impugned order does not call for
interference and prayed to dismiss the Writ
petition as devoid of merits.
14. Heard the Learned Senior counsel for
the petitioner as well as the Learned counsel for
the respondents.
15. Having considered the rival
submissions and the materials available on record,
this Court finds that the petitioner was awarded
the work in question, under a duly executed
agreement and the work was completed within the
stipulated period. The records placed before the
Court also show that substantial payment had
already been made to the petitioner and a final bill
for Rs.13,67,134/- was prepared after
measurement of the work. An amount of
Rs.6,14,451/- had also been retained towards
security deposit.
16. It is not in dispute that the petitioner

Patna High Court CWJC No.9839 of 2018 dt.21-09-2026
11/14
had earlier approached this Court in C.W.J.C.
No.14256 of 2015 seeking for payment of the
aforesaid dues. The said Writ petition was disposed
of on 22.09.2017 with a specific direction to the
District Magistrate, Khagaria to examine the
petitioner's claim and to make payment of the
admitted dues within three months. It was further
directed that, if the District Magistrate was not
agreeable to the claim, he was required to give
notice to the petitioner, afford him an opportunity
of hearing and thereafter pass a reasoned order.
The admitted amount was also directed to carry
simple interest at the rate of 5% per annum.
17. In compliance thereof, the petitioner
was noticed and heard. However, the claim has
been rejected principally on the ground that the
requisite supervision by the Superintending
Engineer was not undertaken, the Measurement
Book was not duly verified, and certain deficiencies
were noticed in the estimate and in the condition
of the road.
18. In the considered view of this Court,

Patna High Court CWJC No.9839 of 2018 dt.21-09-2026
12/14
the reasons assigned in the impugned order do not
disclose any specific finding, that the petitioner
had failed to execute the work, in terms of the
agreement or that the final measurement and final
bill prepared by the departmental authorities were
incorrect. The alleged deficiencies relied upon by
the District Magistrate substantially relate to
procedural, technical or administrative lapses on
the part of the departmental authorities.
19. It is also significant that the
respondents do not dispute that about the
allotment of work its execution and substantial
payment against the work and further about the
preparation of final bill. No material has been
brought on record to establish that any quantified
amount paid or claimed by the petitioner was in
respect of work not executed by him or that the
petitioner had committed any specific breach of
the agreement warranting withholding of the
admitted dues.
20. The earlier order of the Court dated
22.09.2017, required the District Magistrate to

Patna High Court CWJC No.9839 of 2018 dt.21-09-2026
13/14
determine the petitioner's entitlement to the
admitted dues. The impugned order, however,
proceeds mainly on departmental lapses and
deficiencies in supervision and record-keeping,
without recording any specific finding of liability or
default on the part of the petitioner. Such
departmental omissions cannot, in the facts of the
present case, by themselves constitute a valid
ground for denying payment for the work executed
by the petitioner under the agreement.
21. In view of the aforesaid facts and
circumstances, this Court finds that the impugned
order dated 15.12.2017, contained in Memo
No.1792 dated 31.12.2017, cannot be sustained
and is accordingly liable to be quashed. The
petitioner would consequently be entitled to
consideration and release of the amount found due
towards the final bill and security deposit, in
accordance with the departmental records and the
terms of the agreement. So far as interest is
concerned, in view of the earlier order of this Court
dated 22.09.2017, the admitted amount shall carry

Patna High Court CWJC No.9839 of 2018 dt.21-09-2026
14/14
simple interest at the rate of 5% per annum, as
directed therein.
22. The Writ petition is, accordingly,
allowed.
23. Interlocutory Application(s), if any,
shall stand disposed of.


(G. Anupama Chakravarthy, J)
Spd/-
AFR/NAFR NAFR
CAV DATE NA