Union Of India vs M/S G.D. Tewari & Co
- Court
- Delhi High Court
- Case type
- Original Misc Petition
- Decided on
- 17-03-2026
$~
* IN THE HIGH COURT OF DELHI AT NEW DELHI
% Judgment reserved on: 15.01.2026
Judgment pronounced on: 17.03.2026
+ O.M.P. 222/2009, I.A. 2019/2025 (Stay) & I.A. 15274/2025
(For the disposal of the IA NO. 2019/2025)
UNION OF INDIA .....Petitioner
Through: Mr. Kamal Kant Jha, CGSC
with Mr. Avinash Singh, Mr.
Aishwarya Deep Singh and Ms.
Aakriti, Advocates.
versus
M/S G.D. TEWARI & CO .....Respondent
Through: Mr. Shrey Chathly and Ms.
Vinita Sharma, Advocates.
CORAM:
HON'BLE MR. JUSTICE HARISH VAIDYANATHAN
SHANKAR
J U D G M E N T
HARISH VAIDYANATHAN SHANKAR, J.
1. The present Petition, under Section 34 of the Arbitration and
1
Conciliation Act, 1996 , has been filed assailing the Arbitral Award
dated 13.08.2008 read with the Modified Award dated
2
15.12.2008 , passed by the learned Sole Arbitrator.
2. By way of the Impugned Award, the learned Arbitrator has
allowed 6 out of the 7 claims of the Respondent herein arising out of
the disputes inter alia pertaining to the delay and hindrances caused to
1
A&C Act
2
Impugned Award
Signature Not Verified
O.M.P. 222/2009 Page 1 of 37
Digitally Signed
By:HARVINDER KAUR
BHATIA
Signing Date:18.03.2026
15:53:38
the Respondent herein during the pendency of the works to be carried
out by the Respondent, attributing such delays and hindrances to the
Petitioner herein.
3. At the outset, it is clarified that although the present petition
contains several averments challenging different aspects of the
Impugned Award, during the course of arguments the learned counsel
appearing on behalf of the Petitioner confined his submissions only to
Claims Nos. 1 to 3. In particular, the learned counsel emphasized that
the Petitioner’s strongest challenge in the present proceedings pertains
to Claim No. 3. In support of this contention, reliance was specifically
placed upon Annexure R-11 forming part of the Statement of Defence,
wherein it is recorded on behalf of the Claimant/Respondent that “we
will not claim any damages on account of delay”. According to the
learned counsel for the Petitioner, the aforesaid statement assumes
material significance in the context of the adjudication of Claim No. 3
and directly bears upon the sustainability of the findings returned by
the learned Arbitrator in respect thereof.
BRIEF FACTS:
4. Shorn of unnecessary details, the facts germane to the
institution of the present Petition are as follows:
I. The Petitioner herein invited tenders for the execution of the
work named and styled as “Providing Independent W.C. &
Bathroom (300 Nos.) to the Existing Type-I, General Pool
Quarters at Sector-2, R.K. Puram, New Delhi”.
II. The Respondent herein submitted its quotation/tender and the
same came to be accepted. Subsequent thereto, the work was
Signature Not Verified
O.M.P. 222/2009 Page 2 of 37
Digitally Signed
By:HARVINDER KAUR
BHATIA
Signing Date:18.03.2026
15:53:38
awarded to the Respondent herein vide letter dated 19.12.2001,
along with the Agreement containing the terms and
3
conditions dated 19.12.2001 .
III. The Award letter laid down the timeline that was to be followed
and stipulated that the work was to be completed within a
period of 12 months. The timeline so laid is reproduced below:
S.No. Particulars Date
1. Date of Tender 06.11.2001
2. Date of Award of Tender 19.12.2001
3. Date of start 03.01.2002
4. Stipulated Date of Completion 02.01.2003
5. Stipulated Time for Competition 12 months
6. Actual Date of Completion 20.01.2004
7. Estimated Cost Rs. 1,32,75,277/-
8. Tendered Amount Rs. 1,20,63,244/-
9. Percentage 9.13% below
10. Date of Final Bill 30.11.2005
IV. It is stated that various correspondences were exchanged
between the parties throughout the pendency of the Project.
However, due to certain hindrances faced by the Respondent,
the work on the Project got delayed. It was the case of the
Respondent herein that the hindrances that were faced by it
were not resolved in a timely manner by the Petitioner herein,
which ultimately caused the delay.
V. It was further the case of the Respondent that certain extra work
items cropped up during the pendency of the Project, which the
Petitioner needed the Respondent to resolve and execute, and
accordingly, the Respondent submitted its rate analysis in
3
Agreement
Signature Not Verified
O.M.P. 222/2009 Page 3 of 37
Digitally Signed
By:HARVINDER KAUR
BHATIA
Signing Date:18.03.2026
15:53:38
respect of the same. In addition to this, there were certain
deviations beyond the schedule of the quantities as mentioned
in the Agreement, as between the parties, the rate analysis of
which was also enclosed by the Respondent in its letter. More
particularly, the Respondent contends that the additional items
included a rate analysis for providing and laying cement
concrete in the ratio of 1:5:10 in the depressed portion of the
superstructure, along with an extra item pertaining to cutting
and making good holes in brickwork, which was also submitted
by the Respondent vide its letter dated 31.10.2002.
VI. It is stated that thereafter, the Executive Engineer of the
Petitioner reverted to the letter addressed by the Respondent
informing that the payment for extra items and deviation
quantities shall be made as envisaged in the terms of the
Agreement, and the extra items are under process.
VII. Further, as mentioned hereinabove, the stipulated time for
completion of the Project was 02.01.2003. However, the
Respondent was unable to finish and deliver the project in the
said stipulated time due to the hindrances faced by it, which it
alleged was caused by the Petitioner. Accordingly, the
Respondent, vide letter dated 02.01.2003 and 06.01.2003,
requested closing of the contract amicably.
VIII. It is stated that the Respondent could only execute the work of
the value of Rs, 43,28,952/- as on the dates due to the
hinderances and defaults stated to have been committed by the
Petitioner and the Respondent vide letter dated 06.01.2003
informed the Petitioner that they would be liable for the
Signature Not Verified
O.M.P. 222/2009 Page 4 of 37
Digitally Signed
By:HARVINDER KAUR
BHATIA
Signing Date:18.03.2026
15:53:38
payment of 20% increase over and above the tendered rates in
respect of the work executed after the stipulated date of
completion of the Project.
IX. It is stated that letters were written by the Respondent regarding
the work completed for the baths and WCs and for handing over
of the same, as also for the completion of work on 20.01.2004.
The Respondent, vide letter dated 25.06.2004 also requested for
payments and for the preparation of the final bill and for the
finalisation of the rate of extra, substituted and deviated items,
which were not finalised till that time. The Respondent also
claimed damages for the prolongation of work.
X. Thereafter, it is stated that, an undertaking came to be signed
that the Respondent will not claim any damages on account of
the delay; however, Respondent, vide letter dated 26.05.2005, to
the Petitioner stated that the said undertaking was given under
coercion and the same was not binding. It is stated that the
payment came to be made by the Petitioner only on 30.11.2005.
XI. Thereafter, various correspondences are stated to have been
addressed on behalf of the Respondent to the Petitioner, seeking
the release of the payments liable to be paid to the Respondent.
Consequently, the Respondent, vide letter dated 28.07.2006
addressed to the Chief Engineer of the Petitioner, sought the
appointment of an arbitrator, and upon the Petitioner’s failure to
do so, filed a Petition under Section 11 and this Court, vide
Order dated 22.02.2007, appointed the learned Arbitrator for the
adjudication of the disputes inter se the parties.
Signature Not Verified
O.M.P. 222/2009 Page 5 of 37
Digitally Signed
By:HARVINDER KAUR
BHATIA
Signing Date:18.03.2026
15:53:38
XII. The Statement of Claim on behalf of the Respondent herein was
filed before the learned Arbitrator on 01.05.2007, and the
counter statement of facts was filed on behalf of the Petitioner
herein on 12.09.2007. Both parties, with consent, stated that
they do not wish to file their evidence by way of affidavit and
that the arbitral proceedings can be decided on the basis of the
documents already on record.
XIII. Upon consideration of the pleadings and material placed on
record, and after hearing the parties, the learned Sole Arbitrator
rendered the Impugned Award dated 13.08.2008. Thereafter,
pursuant to an application filed by the Respondent herein
seeking correction of a minor typographical error, the learned
Arbitrator passed a modified/corrigendum award dated
15.12.2008, whereby the earlier award was corrected in a very
limited and narrow compass.
XIV. Brevitatis causa , the claims raised by the Respondent, before
the learned Arbitrator, are tabulated herein below:
S.NO. AMOUNT OF
PARTICULARS
CLAIMS
1. Rs. 3,71,466/- On account of less payment in the
alleged final bill under the head extra
and substituted items of work.
2. Rs . 8,48,081/- On account of additional pa y ment in
respect of agreement items that had
deviated beyond the deviation limit as
laid o ut in the agreement.
3. Rs . 15,21,994 / - On account of esca lation/ damages
suffered during the prolongation of the
Signature Not Verified
O.M.P. 222/2009 Page 6 of 37
Digitally Signed
By:HARVINDER KAUR
BHATIA
Signing Date:18.03.2026
15:53:38
contract beyond the s tipulated date of
completion.
4. Rs. 1 ,52,4 00 / - On account of es t abl ishment/overhead
charges for the extended period.
5. Rs . 15000 / - On account of refund of with held
amount lying in the form of FDR.
6. interest @ 18%
P.A
On the aforesaid amounts from due
date till the date of pay ment.
7. Rs . 1,50,000 On account of cost of arbitration
proceedings.
XV. Out of the aforesaid claims, the learned Arbitrator rejected
Claim No. 4, while allowing the remaining claims. In the
Impugned Award, the learned Arbitrator arrived at, inter alia ,
the following claim-wise conclusions:
S.
NO.
CLAIM AS MADE
BEFORE THE LD.
FINDINGS OF THE LD.
TRIBUNAL
TRIBUNAL
1. Claim No. 1: For Rs.
3,71,466/- on account of
less paid in the alleged
final bill under the head
extra and substituted
items of work.
The rates claimed by the
Claimant were refuted by the
Respondent [ The Petitioner
herein ]. The Respondent [ The
Petitioner herein ] did not fix
and convey any other rates.
As per Respondents own case,
the rates of the extra/
substituted items are yet to be
sanctioned by the competent
authority.
Thus, claim No. 1 - allowed.
2. Claim No 2: Rs.
8,48,081/- on account
Claimant has been
consistently writing to the
Signature Not Verified
O.M.P. 222/2009 Page 7 of 37
Digitally Signed
By:HARVINDER KAUR
BHATIA
Signing Date:18.03.2026
15:53:38
additional payment
respect of agreement
items that had deviated
beyond the deviation limit
Respondents [ The Petitioner
herein ] for payment at the
market rate for the deviated
items. The Respondents [ The
Petitioner herein ] had never
disputed the rates and
therefore, the department is
deemed to have accepted the
rates demanded by the
claimant from the time to
time.
Thus, claim 2 - allowed.
3. Claim No. 3: Rs.
15,21,994/- on account of
escalation/ damages
suffered during
prolongation of the
contract beyond stipulated
date of completion
The Claimant demanded 20%
increase over and above
tendered rates vide letter dated
06.01.2003.
The Claimant has been able to
prove the delay on the part of
the Respondent [ The
Petitioner herein ] in the
completion of work.
Thus, claim 3 - allowed.
4. Claim No. 4: Rs.
1,52,400/0 on account of
establishment/ overheard
charges for the extended
period
Claim rejected.
5. Claim No.5: Rs. 15,000/-
on account of refund of
withheld amount lying in
the form of FDR
Allowed, keeping in view of
the findings concerning
claims 1 to 3.
6. Claim No. 6: Interest @
18%
Awarded 12%
7. Claim No. 7: Cost Rs. 50,000/ - awarded.
Signature Not Verified
O.M.P. 222/2009 Page 8 of 37
Digitally Signed
By:HARVINDER KAUR
BHATIA
Signing Date:18.03.2026
15:53:38
5. Essentially, the findings in respect of Claims Nos. 1 to 3
constitute the principal determinations in the Impugned Award,
whereas Claims Nos. 5 to 6 are largely consequential in nature and
flow from the adjudication of Claims Nos. 1 to 3. As noted earlier,
Claim No. 4 was rejected by the learned Arbitrator.
6. Being aggrieved by the findings returned in respect of these
claims, primarily Claims Nos. 1 to 3, the Petitioner has instituted the
present Petition before this Court.
SUBMISSIONS OF THE PARTIES:
7. While raising contentions in respect of Claims Nos. 1 to 3,
learned counsel appearing for the Petitioner contended that the
findings returned by the learned Arbitrator are liable to be set aside as
being contrary to the public policy of India within the meaning of
Section 34(2)(b)(ii) of the A&C Act.
8. In relation to these claims, both parties advanced their
respective submissions before this Court. For the sake of clarity and
convenience, the claim-wise submissions made on behalf of the
parties are recorded hereinafter:
A. CLAIM 1
(a). The Petitioner herein would challenge the finding of the learned
Arbitrator wherein the entire amount so claimed by the
Respondent was awarded.
(b). Learned counsel would state that the learned Arbitrator has
failed to take into consideration Clause 12.1.2, wherein it is
stated that the rate of altered, additional or substituted item of
work cannot be determined in the manner specified in the
Signature Not Verified
O.M.P. 222/2009 Page 9 of 37
Digitally Signed
By:HARVINDER KAUR
BHATIA
Signing Date:18.03.2026
15:53:38
Agreement, then such item of works will have to be carried out
at the rate entered in Schedule of Rates mentioned in the
Schedule F, plus/minus the percentage by which the tendered
amount of the works actually awarded is higher or lower than
the corresponding estimated amount of the works actually
awarded.
(c). He would further argue that the learned Arbitrator has failed to
take into consideration that the rate analysis as submitted by the
Respondent herein was refuted by the Petitioner.
(d). He would also submit that the learned Arbitrator failed to
appreciate that the Respondent failed to place on record any
document/evidence to substantiate the rate analysis submitted
by it.
(e). Per Contra, learned counsel for the Respondent would support
the findings returned by the learned Arbitrator and submit that
the selective reliance placed by the learned counsel for the
Petitioner on Clause 12 is misconceived. It would be contended
that the learned Arbitrator had duly considered all the material
placed on record by the Petitioner, including the relevant
contractual arrangements as well as the admissions made by the
officials of the Petitioner during the course of the arbitral
proceedings, before arriving at the impugned findings.
B. CLAIM 2
(a). Learned counsel for the Petitioner would assail the finding of
the learned Arbitrator in the present claim on the ground that
the same has been allowed without giving any reasoning.
Signature Not Verified
O.M.P. 222/2009 Page 10 of 37
Digitally Signed
By:HARVINDER KAUR
BHATIA
Signing Date:18.03.2026
15:53:38
(b). He would also state that the Respondent herein had accepted the
amounts released by the Petitioner, without any challenge to the
same.
(c). He would also submit that the learned Arbitrator has erred in
not taking into consideration that for all items beyond the
deviation limit, payment had been paid, and since the
Respondent had accepted the payment, the claim as per the
market rates cannot be permissible.
(d). Learned counsel for the Petitioner would also contend that the
modification permitted through the correction/corrigendum
award dated 15.12.2008, which pertained to Claim No. 2, was
in violation of Section 33 of the A&C Act. It would be
submitted that the said modification travelled beyond the time
prescribed under the statutory framework and, therefore,
exceeded the bounds prescribed under Section 33 of the A&C
Act.
(e). Per Contra, learned counsel for the Respondent would rely
upon the various letters addressed from time to time to the
Petitioner, as well as the relevant contractual arrangements, to
contend that the learned Arbitrator was justified in awarding the
amount in favour of the Respondent.
(f). It would further be submitted that until the completion of the
work and the preparation of the final bill, the Engineer-in-
Charge of the Petitioner had not taken any definitive decision
regarding the applicable rates and had merely issued evasive or
non-committal responses. In these circumstances, the market
rates claimed by the Respondent were deemed to have been
Signature Not Verified
O.M.P. 222/2009 Page 11 of 37
Digitally Signed
By:HARVINDER KAUR
BHATIA
Signing Date:18.03.2026
15:53:38
accepted, and the learned Arbitrator was therefore correct in
granting the claim on that basis.
C. CLAIM 3
(a). Learned counsel for the Petitioner would submit that the
primary ground of challenge to the finding of the learned
Arbitrator in the present claim is that the Respondent had given
an undertaking, being Annexure R-11 forming part of the
Statement of Defence, that no damages would be claimed in
furtherance of the same.
(b). He would contend that upon the acceptance of the payment by
the Respondent and giving such an undertaking that no claims
will be raised by the Respondent, a challenge or claim to this
effect thereafter cannot be raised.
(c). Per Contra, learned counsel for the Respondent would draw the
attention of this Court to the letter dated 26.05.2005 issued by
the Respondent to the Petitioner, which was sent well prior to
the release of any payment by the Petitioner, which was made
only on 30.11.2005.
(d). It would be submitted that through the said communication, the
Respondent had expressly withdrawn the aforesaid undertaking,
contending that the same had been furnished under duress.
(e). Learned counsel for the Respondent would further rely on the
Hinderance Register as prepared by the Petitioner, which
formed part of the record before the learned Arbitrator, to show
that the Petitioner herein admitted to the delay on its part.
Signature Not Verified
O.M.P. 222/2009 Page 12 of 37
Digitally Signed
By:HARVINDER KAUR
BHATIA
Signing Date:18.03.2026
15:53:38
ANALYSIS:
9. This Court has heard the learned counsel appearing for the
parties and, with their able assistance, perused the paperbook and
other materials placed on record.
10. At the outset, it is apposite to note that this Court is conscious
of the limited scope of its jurisdiction while examining an objection
petition under Section 34 of the A&C Act. The contours of judicial
intervention in such proceedings have been authoritatively delineated
and settled by a consistent and evolving line of precedents of the
Hon’ble Supreme Court.
11. In this regard, a three-Judge Bench of the Hon’ble Supreme
Court, after an exhaustive consideration of a catena of earlier
decisions, in OPG Power Generation (P) Ltd. v. Enexio Power
4
Cooling Solutions (India) (P) Ltd. , while dealing with the grounds,
inter-alia , of conflict with the public policy of India, the ground which
has primarily been urged in the present case, made certain pertinent
observations, which are reproduced hereunder:
“ Relevant legal principles governing a challenge to an arbitral
award
30. Before we delve into the issue/sub-issues culled out above, it
would be useful to have a look at the relevant legal principles
governing a challenge to an arbitral award. Recourse to a court
against an arbitral award may be made through an application for
setting aside such award in accordance with sub-sections (2), (2-A)
and (3) of Section 34 of the 1996 Act. Sub-section (2) of Section
34 has two clauses, ( a ) and ( b ). Clause ( a ) has five sub-clauses
which are not relevant to the issues raised before us. Insofar as
clause ( b ) is concerned, it has two sub-clauses, namely, ( i ) and ( ii ).
Sub-clause ( i ) of clause ( b ) is not relevant to the controversy in
hand. Sub-clause ( ii ) of clause ( b ) provides that if the Court finds
that the arbitral award is in conflict with the public policy of India,
it may set aside the award.
4
(2025) 2 SCC 417
Signature Not Verified
O.M.P. 222/2009 Page 13 of 37
Digitally Signed
By:HARVINDER KAUR
BHATIA
Signing Date:18.03.2026
15:53:38
Public policy
31. “Public policy” is a concept not statutorily defined, though it
has been used in statutes, rules, notification, etc. since long, and is
also a part of common law. Section 23 of the Contract Act, 1872
uses the expression by stating that the consideration or object of an
agreement is lawful, unless, inter alia, opposed to public policy.
That is, a contract which is opposed to public policy is void.
*
35. In Renusagar Power Co. Ltd. v. General Electric Co. , 1994
Supp (1) SCC 644 , a three-Judge Bench of this Court observed
that the doctrine of public policy is somewhat open—textured and
flexible. By citing earlier decisions, it was observed that there are
two conflicting positions which are referred to as the “narrow
view” and the “broad view”. According to the narrow view, courts
cannot create new heads of public policy whereas the broad view
countenances judicial law making in these areas. In the field of
private international law, it was pointed out, courts refuse to apply
a rule of foreign law or recognise a foreign judgment or a foreign
arbitral award if it is found that the same is contrary to the public
policy of the country in which it is sought to be invoked or
enforced. However, it was clarified, a distinction is to be drawn
while applying the rule of public policy between a matter governed
by domestic law and a matter involving conflict of laws. It was
observed that the application of the doctrine of public policy in the
field of conflict of laws is more limited than that in the domestic
law and the courts are slower to invoke public policy in cases
involving a foreign element than when a purely municipal legal
issue is involved. It was held that contravention of law alone will
not attract the bar of public policy, and something more than
contravention of law is required.
*
37. What is clear from above is that for an award to be against
public policy of India a mere infraction of the municipal laws of
India is not enough. There must be, inter alia, infraction of
fundamental policy of Indian law including a law meant to serve
public interest or public good.
*
40. In ONGC Ltd. v. Western Geco International Ltd. , (2014) 9
SCC 263, paras 35, 38 & 39 , which also related to the period prior
to the 2015 Amendment of Section 34(2)( b )( ii ), a three-Judge
Bench of this Court, after considering the decision in ONGC
Ltd. v. Saw Pipes Ltd. , (2003) 5 SCC 705 , without exhaustively
enumerating the purport of the expression “fundamental policy of
Indian law”, observed that it would include all such fundamental
principles as providing a basis for administration of justice and
enforcement of law in this country. The Court thereafter
Signature Not Verified
O.M.P. 222/2009 Page 14 of 37
Digitally Signed
By:HARVINDER KAUR
BHATIA
Signing Date:18.03.2026
15:53:38
illustratively referred to three fundamental juristic principles,
namely:
( a ) that in every determination that affects the rights of a
citizen or leads to any civil consequences, the court or
authority or quasi-judicial body must adopt a judicial
approach, that is, it must act bona fide and deal with the
subject in a fair, reasonable and objective manner and not
actuated by any extraneous consideration;
( b ) that while determining the rights and obligations of
parties the court or Tribunal or authority must act in
accordance with the principles of natural justice and must
apply its mind to the attendant facts and circumstances
while taking a view one way or the other; and
( c ) that its decision must not be perverse or so irrational that
no reasonable person would have arrived at the same.
41. In Associate Builders v. DDA , (2015) 3 SCC 49 , a two-Judge
Bench of this Court, held that audi alteram partem principle is
undoubtedly a fundamental juristic principle in Indian law and is
enshrined in Sections 18 and 34(2)( a )( iii ) of the 1996 Act. In
addition to the earlier recognised principles forming fundamental
policy of Indian law, it was held that disregarding:
( a ) orders of superior courts in India; and
( b ) the binding effect of the judgment of a superior court
would also be regarded as being contrary to the
fundamental policy of Indian law.
Further, elaborating upon the third juristic principle (i.e. qua
perversity), as laid down in ONGC Ltd. v. Western Geco
International Ltd. , (2014) 9 SCC 263 , it was observed that where:
( i ) a finding is based on no evidence; or
(ii) an Arbitral Tribunal takes into account something
irrelevant to the decision which it arrives at; or
(iii) ignores vital evidence in arriving at its decision, such
decision would necessarily be perverse[ Associate Builders
case , (2015) 3 SCC 49, para 31 ].
To this a caveat was added by observing that when a court applies
the “public policy test” to an arbitration award, it does not act as a
court of appeal and, consequently, errors of fact cannot be
corrected; and a possible view by the arbitrator on facts has
necessarily to pass muster as the arbitrator is the ultimate master of
the quantity and quality of evidence to be relied upon when he
delivers his arbitral award. It was also observed that an award
based on little evidence or on evidence which does not measure up
in quality to a trained legal mind would not be held to be invalid on
that score. Thus, once it is found that the arbitrator's approach is
not arbitrary or capricious, it is to be taken as the last word on
facts.
The 2015 Amendment in Sections 34 and 48
Signature Not Verified
O.M.P. 222/2009 Page 15 of 37
Digitally Signed
By:HARVINDER KAUR
BHATIA
Signing Date:18.03.2026
15:53:38
42. The aforementioned judicial pronouncements were all prior to
the 2015 Amendment. Notably, prior to the 2015 Amendment the
expression “in contravention with the fundamental policy of Indian
law” was not used by the legislature in either Section 34(2)( b )( ii ) or
Section 48(2)( b ). The pre-amended Section 34(2)( b )( ii ) and its
Explanation read:
*
44. By the 2015 Amendment, in place of the old Explanation to
Section 34(2)( b )( ii ), Explanations 1 and 2 were added to remove
any doubt as to when an arbitral award is in conflict with the public
policy of India.
45. At this stage, it would be pertinent to note that we are dealing
with a case where the application under Section 34 of the 1996 Act
was filed after the 2015 Amendment, therefore the newly
substituted/added Explanations would apply [ Ssangyong Engg. &
Construction Co. Ltd. v. NHAI , (2019) 15 SCC 131 ].
46. The 2015 Amendment adds two Explanations to each of the
two sections, namely, Section 34(2)( b )( ii ) and Section 48(2)( b ), in
place of the earlier Explanation. The significance of the newly
inserted Explanation 1 in both the sections is two-fold. First, it does
away with the use of words : ( a ) “ without prejudice to the
generality of sub-clause (ii) ” in the opening part of the pre-
amended Explanation to Section 34(2)(b)(ii); and (b) “ without
prejudice to the generality of clause (b) of this section ” in the
opening part of the pre-amended Explanation to Section 48(2)( b );
secondly, it limits the expanse of public policy of India to the three
specified categories by using the words “ only if ”.
Whereas, Explanation 2 lays down the standard for adjudging
whether there is a contravention with the fundamental policy of
Indian law by providing that a review on merits of the dispute shall
not be done. This limits the scope of the enquiry on an application
under either Section 34(2)( b )( ii ) or Section 48(2)( b ) of the 1996
Act.
47. The 2015 Amendment by inserting sub-section (2-A) in Section
34, carves out an additional ground for annulment of an arbitral
award arising out of arbitrations other than international
commercial arbitrations. Sub-section (2-A) provides that the Court
may also set aside an award if that is vitiated by patent illegality
appearing on the face of the award. This power of the Court is,
however, circumscribed by the proviso, which states that an award
shall not be set aside merely on the ground of an erroneous
application of the law or by reappreciation of evidence.
48. Explanation 1 to Section 34(2)( b )( ii ), specifies that an arbitral
award is in conflict with the public policy of India, only if :
( i ) the making of the award was induced or affected by
fraud or corruption or was in violation of Section 75 or
Section 81; or
Signature Not Verified
O.M.P. 222/2009 Page 16 of 37
Digitally Signed
By:HARVINDER KAUR
BHATIA
Signing Date:18.03.2026
15:53:38
( ii ) it is in contravention with the fundamental policy of
Indian law; or
( iii ) it is in conflict with the most basic notions of morality
or justice.
49. In the instant case, there is no allegation that the making of the
award was induced or affected by fraud or corruption, or was in
violation of Section 75 or Section 81. Therefore, we shall confine
our exercise in assessing as to whether the arbitral award is in
contravention with the fundamental policy of Indian law, and/or
whether it conflicts with the most basic notions of morality or
justice. Additionally, in the light of the provisions of sub-section
(2-A) of Section 34, we shall examine whether there is any patent
illegality on the face of the award.
50. Before undertaking the aforesaid exercise, it would be apposite
to consider as to how the expressions:
( a ) “in contravention with the fundamental policy of
Indian law”;
( b ) “in conflict with the most basic notions of morality or
justice”; and
( c ) “patent illegality” have been construed.
In contravention with the fundamental policy of Indian law
51. As discussed above, till the 2015 Amendment the expression
“in contravention with the fundamental policy of Indian law” was
not found in the 1996 Act. Yet, in Renusagar Power Co.
Ltd. v. General Electric Co. , 1994 Supp (1) SCC 644 , in the
context of enforcement of a foreign award, while construing the
phrase “contrary to the public policy”, this Court held that for a
foreign award to be contrary to public policy mere contravention of
law would not be enough rather it should be contrary to:
( a ) the fundamental policy of Indian law; and/or
( b ) the interest of India; and/or
( c ) justice or morality.
*
55. The legal position which emerges from the aforesaid discussion
is that after “the 2015 Amendments” in Section 34(2)( b )( ii ) and
Section 48(2)( b ) of the 1996 Act, the phrase “in conflict with the
public policy of India” must be accorded a restricted meaning in
terms of Explanation 1 . The expression “in contravention with the
fundamental policy of Indian law” by use of the word
“fundamental” before the phrase “policy of Indian law” makes the
expression narrower in its application than the phrase “in
contravention with the policy of Indian law”, which means mere
contravention of law is not enough to make an award vulnerable.
To bring the contravention within the fold of fundamental policy of
Indian law, the award must contravene all or any of such
fundamental principles that provide a basis for administration of
justice and enforcement of law in this country.
Signature Not Verified
O.M.P. 222/2009 Page 17 of 37
Digitally Signed
By:HARVINDER KAUR
BHATIA
Signing Date:18.03.2026
15:53:38
56. Without intending to exhaustively enumerate instances of such
contravention, by way of illustration, it could be said that:
( a ) violation of the principles of natural justice;
( b ) disregarding orders of superior courts in India or the binding
effect of the judgment of a superior court; and
( c ) violating law of India linked to public good or public interest,
are considered contravention of the fundamental policy of
Indian law.
However, while assessing whether there has been a contravention
of the fundamental policy of Indian law, the extent of judicial
scrutiny must not exceed the limit as set out in Explanation 2 to
Section 34(2)( b )( ii ).
*
Patent illegality
65. Sub-section (2-A) of Section 34 of the 1996 Act, which was
inserted by the 2015 Amendment, provides that an arbitral award
not arising out of international commercial arbitrations, may also
be set aside by the Court, if the Court finds that the award is visited
by patent illegality appearing on the face of the award. The proviso
to sub-section (2-A) states that an award shall not be set aside
merely on the ground of an erroneous application of the law or by
reappreciation of evidence.
66. In ONGC Ltd. v. Saw Pipes Ltd. , (2003) 5 SCC 705 , while
dealing with the phrase “public policy of India” as used in Section
34, this Court took the view that the concept of public policy
connotes some matter which concerns public good and public
interest. If the award, on the face of it, patently violates statutory
provisions, it cannot be said to be in public interest. Thus, an award
could also be set aside if it is patently illegal. It was, however,
clarified that illegality must go to the root of the matter and if the
illegality is of trivial nature, it cannot be held that award is against
public policy.
67. In Associate Builders v. DDA , (2015) 3 SCC 49 , this Court
held that an award would be patently illegal, if it is contrary to:
( a ) substantive provisions of law of India;
( b ) provisions of the 1996 Act; and
( c ) terms of the contract [See also three-Judge Bench
decision of this Court in State of Chhattisgarh v. SAL
Udyog (P) Ltd. , (2022) 2 SCC 275 ].
The Court clarified that if an award is contrary to the substantive
provisions of law of India, in effect, it is in contravention of
Section 28(1)( a ) of the 1996 Act. Similarly, violating terms of the
contract, in effect, is in contravention of Section 28(3) of the 1996
Act.
68. In SsangyongEngg. & Construction Co. Ltd. v. NHAI , (2019)
15 SCC 131 this Court specifically dealt with the 2015
Amendment which inserted sub-section (2-A) in Section 34 of the
Signature Not Verified
O.M.P. 222/2009 Page 18 of 37
Digitally Signed
By:HARVINDER KAUR
BHATIA
Signing Date:18.03.2026
15:53:38
1996 Act. It was held that “patent illegality appearing on the face
of the award” refers to such illegality as goes to the root of matter,
but which does not amount to mere erroneous application of law. It
was also clarified that what is not subsumed within “the
fundamental policy of Indian law”, namely, the contravention of a
statute not linked to “public policy” or “public interest”, cannot be
brought in by the backdoor when it comes to setting aside an award
on the ground of patent illegality [ See Ssangyong Engg. &
Construction Co. Ltd. v. NHAI , (2019) 15 SCC 131 ]. Further, it
was observed, reappreciation of evidence is not permissible under
this category of challenge to an arbitral award [See Ssangyong
Engg. & Construction Co. Ltd. v. NHAI , (2019) 15 SCC 131 ].
Perversity as a ground of challenge
69. Perversity as a ground for setting aside an arbitral award was
recognised in ONGC Ltd. v. Western Geco International Ltd. ,
(2014) 9 SCC 263 . Therein it was observed that an arbitral
decision must not be perverse or so irrational that no reasonable
person would have arrived at the same. It was observed that if an
award is perverse, it would be against the public policy of India.
70. In Associate Builders v. DDA , (2015) 3 SCC 49 certain tests
were laid down to determine whether a decision of an Arbitral
Tribunal could be considered perverse. In this context, it was
observed that where:
( i ) a finding is based on no evidence; or
( ii ) an Arbitral Tribunal takes into account something
irrelevant to the decision which it arrives at; or
( iii ) ignores vital evidence in arriving at its decision, such
decision would necessarily be perverse.
However, by way of a note of caution, it was observed that when a
court applies these tests it does not act as a court of appeal and,
consequently, errors of fact cannot be corrected. Though, a possible
view by the arbitrator on facts has necessarily to pass muster as the
arbitrator is the ultimate master of the quantity and quality of
evidence to be relied upon. It was also observed that an award
based on little evidence or on evidence which does not measure up
in quality to a trained legal mind would not be held to be invalid on
that score.
71. In Ssangyong Engg. & Construction Co. Ltd. v. NHAI , (2019)
15 SCC 131 , which dealt with the legal position post the 2015
Amendment in Section 34 of the 1996 Act, it was observed that a
decision which is perverse, while no longer being a ground for
challenge under “public policy of India”, would certainly amount
to a patent illegality appearing on the face of the award. It was
pointed out that an award based on no evidence, or which ignores
vital evidence, would be perverse and thus patently illegal. It was
also observed that a finding based on documents taken behind the
back of the parties by the arbitrator would also qualify as a decision
Signature Not Verified
O.M.P. 222/2009 Page 19 of 37
Digitally Signed
By:HARVINDER KAUR
BHATIA
Signing Date:18.03.2026
15:53:38
based on no evidence inasmuch as such decision is not based on
evidence led by the parties, and therefore, would also have to be
characterised as perverse [ See Ssangyong Engg. & Construction
Co. Ltd. v. NHAI , (2019) 15 SCC 131 ].
72. The tests laid down in Associate Builders v. DDA , (2015) 3
SCC 49 to determine perversity were followed in Ssangyong
Engg. & Construction Co. Ltd. v. NHAI , (2019) 15 SCC 131 and
later approved by a three-Judge Bench of this Court in Patel Engg.
Ltd. v. North Eastern Electric Power Corpn. Ltd. , (2020) 7 SCC
167 .
73. In a recent three-Judge Bench decision of this Court in DMRC
Ltd. v. Delhi Airport Metro Express (P) Ltd. , (2024) 6 SCC 357 ,
the ground of patent illegality/perversity was delineated in the
following terms: (SCC p. 376, para 39)
“ 39 . In essence, the ground of patent illegality is available
for setting aside a domestic award, if the decision of the
arbitrator is found to be perverse, or so irrational that no
reasonable person would have arrived at it; or the
construction of the contract is such that no fair or
reasonable person would take; or, that the view of the
arbitrator is not even a possible view. A finding based on
no evidence at all or an award which ignores vital
evidence in arriving at its decision would be perverse and
liable to be set aside under the head of “patent illegality”.
An award without reasons would suffer from patent
illegality. The arbitrator commits a patent illegality by
deciding a matter not within its jurisdiction or violating a
fundamental principle of natural justice.”
Scope of interference with an arbitral award
74. The aforesaid judicial precedents make it clear that while
exercising power under Section 34 of the 1996 Act the Court does
not sit in appeal over the arbitral award. Interference with an
arbitral award is only on limited grounds as set out in Section 34 of
the 1996 Act. A possible view by the arbitrator on facts is to be
respected as the arbitrator is the ultimate master of the quantity and
quality of evidence to be relied upon. It is only when an arbitral
award could be categorised as perverse, that on an error of fact an
arbitral award may be set aside. Further, a mere erroneous
application of the law or wrong appreciation of evidence by itself is
not a ground to set aside an award as is clear from the provisions of
sub-section (2-A) of Section 34 of the 1996 Act.
75. In Dyna Technologies (P) Ltd. v. Crompton Greaves Ltd. ,
(2019) 20 SCC 1 , paras 27-43, a three-Judge Bench of this Court
held that courts need to be cognizant of the fact that arbitral awards
are not to be interfered with in a casual and cavalier manner, unless
the court concludes that the perversity of the award goes to the root
of the matter and there is no possibility of an alternative
Signature Not Verified
O.M.P. 222/2009 Page 20 of 37
Digitally Signed
By:HARVINDER KAUR
BHATIA
Signing Date:18.03.2026
15:53:38
interpretation that may sustain the arbitral award. It was observed
that jurisdiction under Section 34 cannot be equated with the
normal appellate jurisdiction. Rather, the approach ought to be to
respect the finality of the arbitral award as well as party's autonomy
to get their dispute adjudicated by an alternative forum as provided
under the law.
*
Scope of interference with the interpretation/construction of a
contract accorded in an arbitral award
84. An Arbitral Tribunal must decide in accordance with the terms
of the contract. In a case where an Arbitral Tribunal passes an
award against the terms of the contract, the award would be
patently illegal. However, an Arbitral Tribunal has jurisdiction to
interpret a contract having regard to terms and conditions of the
contract, conduct of the parties including correspondences
exchanged, circumstances of the case and pleadings of the parties.
If the conclusion of the arbitrator is based on a possible view of the
matter, the Court should not intefere [See: SAIL v. Gupta Brother
Steel Tubes Ltd. , (2009) 10 SCC 63; Pure Helium India (P)
Ltd. v. ONGC , (2003) 8 SCC 593; McDermott International
Inc. v. Burn Standard Co. Ltd. , (2006) 11 SCC 181; MMTC
Ltd. v. Vedanta Ltd. , (2019) 4 SCC 163 ]. But where, on a full
reading of the contract, the view of the Arbitral Tribunal on the
terms of a contract is not a possible view, the award would be
considered perverse and as such amenable to interference [ South
East Asia Marine Engg. & Constructions Ltd. v. Oil India Ltd. ,
(2020) 5 SCC 164 ].
Whether unexpressed term can be read into a contract as an
implied condition
85. Ordinarily, terms of the contract are to be understood in the
way the parties wanted and intended them to be. In agreements of
arbitration, where party autonomy is the grund norm , how the
parties worked out the agreement, is one of the indicators to
decipher the intention, apart from the plain or grammatical
meaning of the expressions used [ B ALCO v. Kaiser Aluminium
Technical Services Inc. , (2016) 4 SCC 126 ].
86. However, reading an unexpressed term in an agreement would
be justified on the basis that such a term was always and obviously
intended by the parties thereto. An unexpressed term can be
implied if, and only if, the court finds that the parties must have
intended that term to form part of their contract. It is not enough for
the court to find that such a term would have been adopted by the
parties as reasonable men if it had been suggested to them. Rather,
it must have been a term that went without saying, a term necessary
to give business efficacy to the contract, a term which, although
tacit, forms part of the contract [ Adani Power (Mundra)
Ltd. v. Gujarat ERC , (2019) 19 SCC 9 ].
Signature Not Verified
O.M.P. 222/2009 Page 21 of 37
Digitally Signed
By:HARVINDER KAUR
BHATIA
Signing Date:18.03.2026
15:53:38
87. But before an implied condition, not expressly found in the
contract, is read into a contract, by invoking the business efficacy
doctrine, it must satisfy the following five conditions:
( a ) it must be reasonable and equitable;
( b ) it must be necessary to give business efficacy to the
contract, that is, a term will not be implied if the contract
is effective without it;
( c ) it must be obvious that “it goes without saying”;
( d ) it must be capable of clear expression;
( e ) it must not contradict any terms of the contract [ Nabha
Power Ltd. v. Punjab SPCL , (2018) 11 SCC 508 ,
followed in Adani Power case , (2019) 19 SCC 9 ].”
(emphasis supplied)
12. A careful perusal of the Impugned Award demonstrates that the
learned Arbitrator has duly considered the relevant material, facts, and
circumstances placed on record while adjudicating upon the claims
raised by the Respondent herein. In particular, the findings recorded
by the learned Arbitrator in respect of those claims of the Impugned
Award, against which the learned counsel for the Petitioner has
specifically raised objections before this Court, are set out as follows:
“Claim No. 1
The rates claimed by the Claimant were refuted by the respondent.
The respondent did not fix and convey any other rates. As per the
respondent's own case, the rates of the extra/substituted items are
yet to be sanctioned by the competent authority. During arguments,
the counsel for the respondent conceded with the consent and in
the presence of the officers of the respondent, that till date no other
rates have been sanctioned by the competent authority. Mr. Sharma
had filed an extract from G.T. Gajaria's Book on page 419
"....under the variation clause in...... it is only the engineer-
in-charge or the Divisional Engineer who is mentioned as
the authority to determine or settle the rates and not any
other officer of competent authority. the rates fixed and
sanctioned by the s-called 'competent authority' will not be
binding upon the contractor as they will have no sanctity
according to the variation clause in the contract.
accordingly and a clear provision about the finality of the
rates sanctioned by the 'competent authority' should be
made"
Signature Not Verified
O.M.P. 222/2009 Page 22 of 37
Digitally Signed
By:HARVINDER KAUR
BHATIA
Signing Date:18.03.2026
15:53:38
Considering all the facts, I am therefore, of the opinion and hold
that the rates submitted by the claimant for extra and substituted
items based on the market rates have to be accepted. Even after
four years of completion of work, no other rates were sanctioned
by the competent authority of the respondent. The respondent
without any basis rejected the claim and delayed the payments to
the claimant of their justifiable dues. I, therefore, award a sum of
Rs. 3,71,466/- in favour of the Claimant and against the respondent
under this claim.
Claim No. 2
After perusal of the pleadings and documents on record it seems
that the claimant have been consistently writing to the respondent
for payment at the market rate for the deviated items. Out of the
many letters exchanged by the parties, I am referring to one
particular letter to reach my conclusion. The claimant in the letter
dated 10.01.2006 (Ex. C-43] addressed to Chief Engineer, CPWD
has clearly stated that the respondent department required them to
executed various extra and substitute items for which they had
demanded the payments at market rate duly supported by rate
analysis and quotations. That the respondent has never disputed the
rates and therefore, the department is deemed to have accepted the
rates demanded by the claimant from time to time.
In the said letter, it was alleged by the Claimant that despite this
while making payment in the final bill, the extra and substituted
items have been paid to the Claimant in a provisional manner as
per the rates given in the bill of quantities and not market rates as
recorded in terms of the clause/proviso at page 141 of the
agreement under the head Special Conditions. That against the
execution of work of extra and substituted items of the value of Rs.
7.17,954/-, the respondent had made payment of Rs. 3,46,488/-.
Therefore, the Claimant was claiming the balance sum of Rs.
3,71,466/-
In the said letter the claimant had also claimed a sum of Rs.
15,94,167/- It has been stated that beyond the stipulated date of
completion the claimant executed the work of the value of Rs.
97,13,1451- and the value of work included the stipulated materials
of the value of Rs. 17,42,312/-. So after deducting this value the
escalation is payable on the amount of Rs. 78,70,8331- at 20%. It
may also be stated that had clause 10 CC been there, have been
paid to the claimant whereas the claimant are demanding the
payment of Rs. 15,94,167 /- on the work executed beyond the
stipulated date of completion less the value of stipulated materials
Signature Not Verified
O.M.P. 222/2009 Page 23 of 37
Digitally Signed
By:HARVINDER KAUR
BHATIA
Signing Date:18.03.2026
15:53:38
supplied by the department. The claimant thus requested for
payment within three weeks with interest.
A perusal of the records shows that in the every letter written by
the Claimant, the claimant has prayed for payment, but the
respondent had always been evasive. The claimant had written
letter dated 10.10.2002 (C-13) to the respondent for been conveyed
the decision for the deviated quantities and finalization of their
rates as per the terms of the agreement i.e. at market rate. The
respondent remains silent without taking and conveying any
decision to the Claimant.
I have perused the provisions of the agreement at page 141
provides for payment of extra/substitute and deviated items at
market rate. A portion of it is extracted below for ready reference.
"The rate of extra items till now was being derived as per
Clause 12 of the agreement (general conditions of
contract, 2001). Hence forth the payment of extra item and
deviation item beyond the permissible limit as given in the
agreement will be worked out at market rates prevailing at
the time of Commencement of execution of these items"
The claimant has submitted the rate analysis as per Annexure-BB
to confront the Annexure-B submitted by the respondent. No
forceful reasons have been given by the respondent to negate the
claim of the Claimant. I have no hesitation in accepting the claim. I
am therefore, of the opinion and hold that the claimant is entitled to
the payment Rs. 8.48.811- as claimed under this head.
Claim No. 3
A perusal on the pleadings, documents on record and the
judgments cited and the oral and written submissions submitted by
the parties, I am of the opinion that the claimant has been able to
prove the delay on the part of the respondent in completion of the
work. The contents of the hindrance register submitted by the
respondent confirm the facts that the respondent took there own
sweat time to complete the various tasks which were attributable to
them. The respondent failed to fulfill their contractual obligations
under the contract. This is evident from hindrance register and also
from the fact that the extension of time granted to the claimant by
the respondent was without levy of any compensation. The
Claimant has explained why and how they were made to give
undertaking that they will not claim damages on any account of
delay (Ref. R-11). That they had subsequently withdrawn and
explained how the said undertaking was written.
Signature Not Verified
O.M.P. 222/2009 Page 24 of 37
Digitally Signed
By:HARVINDER KAUR
BHATIA
Signing Date:18.03.2026
15:53:38
The Claimant has calculated the escalation on the basis of cost
indices as circulated b CPWD from time to time after the stipulated
date of completion. Accordingly to the Claimant, their loss is
assessed on the basis of the difference between the cost indices at
the time of submission of tender and after stipulated date of
completion on the value of work of Rs. 93,52,283/- less the value
of stipulated material supplied by the respondent for execution of
this value of work. The Claimant cited the following judgments:
i. Metro Electirc Vs. DDA [ AIR 1980 Delhi 266J
ii. Rawala Construction V. Vs. UOI [1982 RLR 20]
iii. Ircon International Ltd. Vs. Shri Krishna Trading Co. [2007
X AD Delhi 309]
iv. Mecon Ltd. Vs. Pioneer Fabrications (P) Ltd. [2007 (4)
ALR 323 (Delhi)
v. Utam Singh Duggarl Vs. UOI [ 1988 (2) Arb. L.R. 225
vi. M/s. Salwan Construction Vs. UOI [AIL 1977) II DELHI
748
vii. P.M. Paul Vs. UOI [AIR 1989 SC 1034]
The judgment in the matter of General Manager, Northern
Railways Vs. Sarvesh Chopra 2002 (1) Arb. L.R. 506 cited by the
respondent's counsel is clearly distinguishable and not applicable
to the facts of the present case. I am, therefore, the opinion that the
claimant is entitled to the payment Rs. 15,21,994/ - as claimed
under this head.”
13. This Court now proceeds to examine the aforesaid findings
returned by the learned Arbitrator on the anvil of the limited and
circumscribed jurisdiction available under Section 34 of the A&C Act,
and in the light of the principles authoritatively laid down by the
Hon’ble Supreme Court in OPG Power Generation ( supra ).
14. Upon a careful consideration of the findings recorded in the
Impugned Award, as well as the rival submissions advanced by the
learned counsel appearing for the parties, this Court is of the
considered view that no infirmity can be discerned in the approach
adopted by the learned Arbitrator. Having due regard to the narrow
scope of judicial interference permissible under Section 34 of the
Signature Not Verified
O.M.P. 222/2009 Page 25 of 37
Digitally Signed
By:HARVINDER KAUR
BHATIA
Signing Date:18.03.2026
15:53:38
A&C Act, this Court finds no reason to depart from, or interfere with,
the conclusions arrived at by the learned Arbitrator and accordingly
concurs with the same.
15. A perusal of the present Petition and arguments made by the
learned counsel appearing for the Petitioner makes it abundantly clear
that the Petitioner is, in effect, seeking a re-appreciation and re-
evaluation of the evidence led by the parties before the learned
Arbitrator and is further inviting this Court to substitute its own
interpretation of the contractual terms governing the parties. Such an
exercise is wholly impermissible in proceedings under Section 34 of
the A&C Act, which does not confer appellate jurisdiction upon this
Court.
16. As regards Claim No. 1, a perusal of the Impugned Award
demonstrates that the learned Arbitrator has carefully examined the
pleadings, documents, and the relevant provisions governing the
dispute. The reasoning adopted by the learned Arbitrator clearly
reflects that the conclusions arrived at are rooted in the terms of the
Agreement and the material placed on record, and do not travel
beyond the jurisdiction vested in the learned Arbitrator under the
contract.
17. A closer examination of the contractual provisions would also
show that in circumstances where the Petitioner fails to specify or
determine the applicable rates for extra or substituted items, the rates
claimed by the Respondent herein, if supported by material, may
justifiably be accepted. In the present case, the learned Arbitrator has
specifically recorded that although the Petitioner disputed the rates
claimed by the Respondent for extra and substituted items, it failed to
Signature Not Verified
O.M.P. 222/2009 Page 26 of 37
Digitally Signed
By:HARVINDER KAUR
BHATIA
Signing Date:18.03.2026
15:53:38
determine, fix, or communicate any alternative rates.
18. In fact, it was the Petitioner’s own case that the rates for such
items were yet to be sanctioned by the competent authority. During
the course of the arbitral proceedings, it was candidly admitted by the
officials of the Petitioner that even after the lapse of nearly four years
from the completion of the work, no such rates had been sanctioned.
This admission has been specifically noted and recorded in the
Impugned Award.
19. Despite repeated communications and assertions by the
Respondent seeking finalization of the rates for extra and substituted
items, no decision was taken by the concerned authority for several
years. In such circumstances, the learned Arbitrator found that the
rejection of the Respondent’s claimed rates by the Petitioner lacked
any contractual or factual basis. Since no valid or duly sanctioned
rates were determined by the Petitioner, even long after completion of
the work, the market rates submitted by the Respondent, which were
supported by the material on record, were reasonably accepted by the
learned Arbitrator.
20. This Court finds that the aforesaid conclusions of the learned
Arbitrator are based on a proper appreciation of the contractual
provisions and the evidence on record. The Petitioner has failed to
demonstrate any error or violation of the limited grounds available
under Section 34 of the A&C Act that would warrant interference with
the findings so returned. The view taken by the learned Arbitrator is
clearly a plausible and reasoned view arising from the material on
record. Accordingly, the challenge raised by the Petitioner to the
findings of the learned Arbitrator in respect of Claim No. 1 is devoid
Signature Not Verified
O.M.P. 222/2009 Page 27 of 37
Digitally Signed
By:HARVINDER KAUR
BHATIA
Signing Date:18.03.2026
15:53:38
of merit and is therefore rejected, as this Court finds no infirmity in
the said findings.
21. With respect to the challenge raised by the Petitioner to the
findings pertaining to Claim No. 2, a careful perusal of the Impugned
Award reveals that the learned Arbitrator has allowed the said claim
on the basis of a proper appreciation of the material placed on record.
The learned Arbitrator took into account the contemporaneous
correspondence issued by the Respondent, wherein the Respondent
had specifically claimed payment at prevailing market rates for the
extra and substituted items and had supported the same with
quotations and detailed rate analysis.
22. Significantly, the rates so claimed were never disputed or
effectively challenged by the competent authority of the Petitioner at
the relevant time through any contemporaneous communication. In
these circumstances, the conclusion arrived at by the learned
Arbitrator cannot be said to suffer from perversity or arbitrariness.
This Court, therefore, finds no infirmity either in the reasoning
adopted or in the manner in which the learned Arbitrator has reached
the impugned finding.
23. From a perusal of the findings recorded by the learned
Arbitrator in respect of this claim, it is evident that the Respondent
herein had consistently addressed letters to the Petitioner seeking
payment for extra, substituted, and deviated items at prevailing market
rates. In particular, reliance was placed on the Respondent’s letter
dated 10.01.2006 addressed to the Chief Engineer, wherein it was
asserted that although the Respondent herein had executed various
extra and substituted items and had supported its demand with rate
Signature Not Verified
O.M.P. 222/2009 Page 28 of 37
Digitally Signed
By:HARVINDER KAUR
BHATIA
Signing Date:18.03.2026
15:53:38
analysis and quotations, the Petitioner had never disputed the claimed
rates. However, while preparing the final bill, the Petitioner made only
payments as per the rates contained in the Bill of Quantities rather
than the applicable market rates, resulting in a substantial balance
claimed by the Respondent herein.
24. The learned Arbitrator further observed that the record revealed
a consistent pattern wherein the Respondent herein repeatedly
requested the Petitioner to finalize and communicate the rates for
deviated quantities in accordance with the terms of the agreement.
Notwithstanding such requests, including the letter dated 10.10.2002,
the Petitioner failed to take any definitive decision and continued to
remain evasive. The contractual provisions, particularly those
contained in the Special Conditions of the Agreement, clearly
provided that payment for extra, substituted, and deviated items
beyond the permissible limits was to be determined on the basis of the
prevailing market rates at the time of execution.
25. In these circumstances, the learned Arbitrator concluded that
the Respondent herein had furnished detailed rate analysis in support
of its claim, whereas the Petitioner failed to provide any cogent or
persuasive material to rebut the same. In the absence of any
substantive challenge to the rates claimed and considering the
contractual framework mandating payment at market rates, the
Arbitrator found merit in the Respondent’s claim and held that the
Respondent was entitled to payment under the said head.
26. From the aforesaid findings, it is evident that the entire analysis
undertaken by the learned Arbitrator is based upon the documentary
evidence on record and the contemporaneous communications
Signature Not Verified
O.M.P. 222/2009 Page 29 of 37
Digitally Signed
By:HARVINDER KAUR
BHATIA
Signing Date:18.03.2026
15:53:38
exchanged between the parties. In proceedings under Section 34 of the
A&C Act, the scope of judicial interference is extremely limited and
this Court is not permitted to re-appreciate evidence or re-examine
factual determinations rendered by the arbitral tribunal. The Petitioner
has failed to demonstrate how the said findings suffer from perversity
or how they would amount to a violation of the public policy of India
within the meaning of Section 34 of the A&C Act. Consequently, the
challenge raised by the Petitioner on the merits of Claim No. 2 cannot
be sustained.
27. Insofar as the argument of the Petitioner with respect to the
correction award dated 15.12.2008 is concerned, whereby a clerical
change was made in the award pertaining to Claim No. 2, this Court
finds no merit in the said contention. The issue stands squarely
covered by the decision of the Division Bench of this Court in Human
Behaviour and Allied Sciences (IHBAS) vs. MI2C Securities and
5
Facilities Pvt Ltd. , wherein the scope and application of Section 33
of the A&C Act relating to correction of clerical, typographical, or
computational errors has been explained. The relevant observations of
the Division Bench in the said judgement are reproduced hereinbelow:
“ 9. From a perusal of the pleadings on record, it cannot be disputed
that the respondent had indeed filed its application on 02.04.2024
under Section 33(1)(a) of the Act, which is beyond a period of 30
days from the date of the award dated 26.02.2024. The arbitral
tribunal, relying upon the provisions of Section 33(1)(a) of the Act,
dismissed the said application on 13.05.2024. Though the
application was indeed filed beyond a period of 30 days as
prescribed in the said section, what we have to consider is whether
such an application would be completely barred in respect of the
relief sought by the respondent. In that context, it would be
apposite to extract Section 33(1)(a) of the Act hereunder:
“ 33. Correction and interpretation of award; additional
5
2025:DHC:9818:DB
Signature Not Verified
O.M.P. 222/2009 Page 30 of 37
Digitally Signed
By:HARVINDER KAUR
BHATIA
Signing Date:18.03.2026
15:53:38
award- (1) Within thirty days from the receipt of the
arbitral award, unless another period of time has been
agreed upon by the parties-
(a) A party, with notice to the other party, may request the
arbitral tribunal to correct any computation errors, any
clerical or typographical errors, or any other errors of a
similar nature occurring in the award;”
(emphasis supplied)
10. Having regard to the submissions made by learned counsel for
the appellant, and the narration of facts encapsulated by the learned
Single Judge in para 11 of the impugned order, we need to
appreciate this conundrum by considering whether the passing of
the award in the wrong name/title of the respondent would amount
to a typographical error in the award at all. In our considered
opinion, the said error occurred at the end of the arbitral tribunal,
and as such could not be deemed to be an error in the award in the
sense requiring correction by any of the parties. In fact, according
to us, correction of the said error would fall within the Latin maxim
“actus curiae neminem gravabit” which means an act of a Court
can prejudice no one. Undoubtedly, right from the time of
appointment of an arbitrator by this Court, as well as filing of the
statement of the claim, and other pleadings up till the culmination
of the arbitral proceedings, were in the name of M/s. MI2C
Security and Facilities Pvt. Ltd. Additionally, learned counsel for
the appellant fairly admitted that the contract, too, was awarded in
the name of M/s. MI2C Security and Facilities Pvt. Ltd. It is very
likely that all the payments before such disputes arose also must
have been tendered into the account of M/s. MI2C Security and
Facilities Pvt. Ltd.
11. In that view of the matter, in case while passing the final award,
the arbitral tribunal committed a mistake or a typographical error in
entering the correct name of the respondent, the said error would
clearly fall within the aforesaid maxim. Applied on all fours, it is
manifest that the respondent cannot be held responsible for the
error committed by the arbitral tribunal. Thus, the argument of
learned counsel for the appellant, to our mind, is hypertechnical
and is unmerited. Only to buttress and substantiate as to how
Courts have interpreted and applied the aforesaid maxim, we refer
to the judgment of the Hon’ble Supreme Court in Neeraj Kumar
Sainy & Ors. Vs. State of Uttar Pradesh & Ors., (2017) 14 SCC
135 and in particular to para 26, which is extracted hereunder:
“ 26. The seminal question that is required to be posed is
whether the maxim actus curiae neminem gravabit would
apply to such a case. In Jang Singh v. Brij Lal [Jang Singh
v. Brij Lal, AIR 1966 SC 1631], a three-Judge Bench
noted that there was error on the part of the court and the
officers of the court had contributed to the said error.
Signature Not Verified
O.M.P. 222/2009 Page 31 of 37
Digitally Signed
By:HARVINDER KAUR
BHATIA
Signing Date:18.03.2026
15:53:38
Appreciating the fact situation, the Court held: (AIR p.
1633, para 6)
“6. … It is no doubt true that a litigant must be vigilant
and take care but where a litigant goes to Court and asks
for the assistance of the Court so that his obligations
under a decree might be fulfilled by him strictly, it is
incumbent on the Court, if it does not leave the litigant to
his own devices, to ensure that the correct information is
furnished. If the Court in supplying the information makes
a mistake the responsibility of the litigant, though it does
not altogether cease, is at least shared by the Court. If the
litigant acts on the faith of that information the courts
cannot hold him responsible for a mistake which it itself
caused. There is no higher principle for the guidance of
the Court than the one that no act of courts should harm a
litigant and it is the bounden duty of courts to see that if a
person is harmed by a mistake of the court he should be
restored to the position he would have occupied but for
that mistake. This is aptly summed up in the maxim: Actus
curiae neminem gravabit.”
[emphasis supplied]
12. Predicated on the analysis, and the observations made above,
we are of the considered opinion that the emphasis of the learned
counsel for the appellant on the 30-day time period prescribed in
Section 33(1)(a) of the Act would not strictu senso bar the
respondent from filing and maintaining an application for
correction in the factual scenario noted by us. This is for the reason
that the error appears to be clearly on the part of the arbitral
tribunal and not attributable to any of the parties. It would be
onerous and absurd to deprive a party of a lawful decree, and an
entitlement to the benefits contained therein merely for the reason
that the court or the arbitral tribunal itself has committed an error of
such a nature. Even otherwise, the corrections sought have no
nexus or correlation to the merits of the case. We are not laying
down a proposition that in all cases the bar or limitation prescribed
in Section 33(1) of the Act is to be relaxed or diluted, but that it
may be only in exceptional circumstances like the one in the
present case, that the rigors may be relaxed. Clearly, it would
depend on a case to case basis.
13. Mr. Sannu, learned counsel for the appellant also argues that
the petition under Section 34 of the Act filed by the respondent
challenging the order of the tribunal on the application under
Section 33(1)(a) of the Act would not be maintainable, especially
in the absence of any challenge to the award dated 26.02.2024
itself. We fail to see how this argument is sustainable. Clearly, any
order passed under Section 33 of the Act is deemed to be an
additional award, and if so, the invocation of Section 34 of the Act
Signature Not Verified
O.M.P. 222/2009 Page 32 of 37
Digitally Signed
By:HARVINDER KAUR
BHATIA
Signing Date:18.03.2026
15:53:38
to challenge such additional award or refusal thereto would surely
fall within the ambit of challenge under Section 34 of the Act.
14. In view of the above, apart from the opinion rendered by the
learned Single Judge with which we concur, for the additional
reasons rendered above, we find no merit in the present appeal. In
fact, we are of the considered opinion that the present appeal is
misconceived and vexatious and could have been easily avoided by
an instrumentality of the State like the appellant. After all, the
appellant never filed any petition challenging the award dated
26.02.2024 on merits. In other words, no party can be deprived of
the benefits of an award passed by an arbitral tribunal, except in
accordance with law.”
(emphasis supplied)
28. This Court is of the considered opinion that the principle
governing Section 33 of the A&C Act, as elucidated in the aforesaid
judgment, would apply with equal force in the present case. The
Respondent cannot be deprived of the benefit flowing from the Award
merely on account of a minor clerical omission occurring in the
concluding line of the Award relating to Claim No. 2. It is pertinent to
note that under the head of “ Claim No. 2 ” in the Impugned Award, the
learned Arbitrator had clearly recorded the amount actually claimed
by the Respondent. However, while recording the operative
conclusion, the learned Arbitrator observed that “I am therefore, of
the opinion and hold that the claimant is entitled to the payment Rs.
8,48,81/- as claimed under this head.”
29. It is also significant that immediately following the numerical
figure, the expression “as claimed under this head” has been
expressly recorded, which clearly indicates that the amount awarded
corresponds to the amount claimed by the Respondent under the said
head and not otherwise. Thus, the context in which the operative line
was recorded makes it evident that the figure mentioned therein
contained a minor typographical or clerical omission and did not
Signature Not Verified
O.M.P. 222/2009 Page 33 of 37
Digitally Signed
By:HARVINDER KAUR
BHATIA
Signing Date:18.03.2026
15:53:38
reflect any alteration of the claim or the reasoning of the learned
Arbitrator. In such circumstances, the subsequent correction only
served to rectify the inadvertent clerical error in the numerical figure
and did not, in any manner, affect the substance, reasoning, or merits
of the Award.
30. The correction made is therefore purely ministerial in nature,
inconsequential to the adjudicatory reasoning of the Award, and
squarely falls within the scope of permissible corrections
contemplated under Section 33 of the A&C Act, particularly in light
of the law laid down in Human Behaviour and Allied Sciences
(supra) . Consequently, this Court finds no material error or illegality
in the learned Arbitrator permitting rectification of the said clerical
mistake, and the objection raised by the Petitioner in this regard is
therefore liable to be rejected.
31. Adverting now to Claim No. 3, the principal challenge raised by
the learned counsel for the Petitioner does not withstand scrutiny in
light of the material placed on record. The primary ground urged by
the Petitioner to assail the findings of the learned Arbitrator is that the
Respondent had furnished an undertaking, reflected in Annexure R-11
forming part of the Statement of Defence , to the effect that no
damages would be claimed.
32. On the basis of the said undertaking, it was contended by the
Petitioner that once the Respondent had accepted payment and had
given an assurance that no further claims would be raised, it was not
open for the Respondent thereafter to raise a claim for damages.
According to the Petitioner, the undertaking operated as a bar against
the Respondent seeking any additional amounts under this head.
Signature Not Verified
O.M.P. 222/2009 Page 34 of 37
Digitally Signed
By:HARVINDER KAUR
BHATIA
Signing Date:18.03.2026
15:53:38
33. However, the aforesaid contention stands completely negated
upon a perusal of the contemporaneous record, particularly the letter
dated 26.05.2005 addressed by the Respondent to the Petitioner. The
said letter assumes considerable significance as it was issued shortly
after the alleged undertaking relied upon by the Petitioner. A reading
of the said communication makes it evident that the Respondent had
expressly withdrawn or clarified the earlier undertaking and had
asserted that the same had been furnished under circumstances which
did not reflect the true intent of the Respondent. Thus, the very
foundation of the Petitioner’s argument, that the Respondent had
unequivocally waived its right to claim damages, stands seriously
undermined by the subsequent communication placed on record.
34. This Court also finds merit in the submission advanced by the
learned counsel for the Respondent that the letter dated 26.05.2005
was issued well prior to the release of any payment by the Petitioner.
The record indicates that the payment relied upon by the Petitioner
was in fact released much later, i.e., on 30.11.2005. Consequently, the
alleged undertaking contained in Annexure R-11 forming part of the
Statement of Defence , which is sought to be relied upon by the
Petitioner to contend that the Respondent had waived its claims, was
rendered inconsequential.
35. In other words, when the payment was eventually released by
the Petitioner, the Respondent had already placed on record its clear
position through the letter dated 26.05.2005. In these circumstances,
the Petitioner cannot legitimately rely upon the earlier undertaking to
defeat the Respondent’s claim, and the said argument is therefore
liable to be rejected.
Signature Not Verified
O.M.P. 222/2009 Page 35 of 37
Digitally Signed
By:HARVINDER KAUR
BHATIA
Signing Date:18.03.2026
15:53:38
36. Insofar as the issue of delay is concerned, the same has been
duly examined by the learned Arbitrator in the Impugned Award on
the basis of the material placed before the arbitral tribunal. The
findings recorded by the learned Arbitrator are supported by the
documentary record, including the Hindrance Register maintained by
the Petitioner itself, which formed part of the evidence before the
learned Arbitrator.
37. The said record reflects that the delays in execution of the work
were attributable to the Petitioner. In view of the aforesaid material
and the reasoning recorded in the Impugned Award, and in the
absence of any other substantive ground of challenge raised by the
Petitioner in respect of Claim No. 3, this Court finds no infirmity in
the findings returned by the learned Arbitrator. Accordingly, the
limited challenge raised by the Petitioner in respect of this claim does
not merit interference under Section 34 of the A&C Act.
CONCLUSION:
38. In view of the foregoing discussion and the reasons recorded
hereinabove, this Court finds no ground to interfere with the
Impugned Award passed by the learned Arbitrator insofar as it
pertains to Claims Nos. 1 to 3. Consequently, Claims Nos. 5 to 6,
which are purely consequential and flow from the findings returned in
respect of Claims Nos. 1 to 3, also do not warrant any interference.
Claim 7 relates to the Costs and this Court is of the opinion that the
same appears to be fairly reasonable and no interference is warranted.
39. The Petitioner has failed to demonstrate that the Impugned
Award suffers from any infirmity falling within the limited and well-
Signature Not Verified
O.M.P. 222/2009 Page 36 of 37
Digitally Signed
By:HARVINDER KAUR
BHATIA
Signing Date:18.03.2026
15:53:38
defined grounds for judicial interference under Section 34 of the A&C
Act. Accordingly, the present Petition stands dismissed.
40. The present Petition, along with pending application(s), if any,
stands disposed of in the above terms.
41. No Order as to Costs.
HARISH VAIDYANATHAN SHANKAR, J.
MARCH 17, 2026/sm/va
Signature Not Verified
O.M.P. 222/2009 Page 37 of 37