M/S Gyan Chand vs Government Of Nct Of Delhi
- Court
- Delhi High Court
$~49
* IN THE HIGH COURT OF DELHI AT NEW DELHI
Date of decision: 23.04.2026
+ ARB.P. 697/2026
M/S GYAN CHAND .....Petitioner
Through: Mr. Abhishek Pandey and Mr.
Ramesh Pandey, Advocates.
versus
GOVERNMENT OF NCT OF DELHI .....Respondent
Through: Mr. Pramod Kumar, Panel
Counsel for PWD (GNCTD).
CORAM:
HON'BLE MR. JUSTICE HARISH VAIDYANATHAN
SHANKAR
% JUDGEMENT (ORAL)
1. The present Petition has been filed under Section 11 of the
Arbitration and Conciliation Act, 1996 [“ Act ”], seeking appointment
of a Sole Arbitrator for adjudication of disputes inter se the parties
arising out of the Agreement bearing No. 57/EE/SRDProject-
1/PWD/2024-2025 dated 19.12.2024 [ “Agreement” ], as executed
between the parties.
2. The material on record reflects that the Agreement stipulates a
dispute resolution mechanism, which contemplates reference of
disputes thereunder, inter se the parties, to Arbitration. The relevant
stipulation is contained in Clause 25 of the Agreement [ “Arbitration
Clause” ]. The relevant portion of the same reads as follows:-
Signature Not Verified
Digitally Signed
By:VARNIKA
Signing Date:28.04.2026
11:21:17
ARB.P. 697/2026 Page 1 of 11
“ Clause 25
Settlement of Conciliation and Arbitration.
Except where otherwise provided in the contract, all questions and
disputes relating to the meaning of the specifications, designs,
drawings and instructions hereinbefore mentioned and as to the
quality of workmanship or materials used in the work or as to any
other question, claim, right, matter or thing whatsoever in any way
arising out of or relating to the contract, designs, drawings,
specifications, estimates, instructions, orders or otherwise
concerning the works or the execution or failure to execute the
same whether arising during the progress of the work or after the
cancellation, termination, completion or abandonment thereof shall
be dealt with as mentioned hereinafter.
25.1 Conciliation: If the contractor considers any work demanded
of him to be outside the requirements of the contract, or disputes
any drawing, record or decision given in writing by the Engineer-
in-Charge; or if the Engineer-in-Charge considers any act or
decision of the contractor on any matter in connection with or
arising out of contract or carrying out of the work to be
unacceptable and disputed; such party may promptly refer such
disputes and amount claimed for each dispute to the conciliator
Conciliator (Special Director General or the Additional Director
General concerned with the work, as applicable) in the performa
prescribed in Appendix XVII mentioned in Schedule F, under
intimation to the other party. The Conciliator may then request
each party to submit to him a brief written statement describing the
disputes and the points at issue. Each party shall send a copy of
such statement to the other party. At any stage of the conciliation
proceedings, the Conciliator may request a party to submit to him
such additional information as he deems appropriate. When it
appears to the conciliator that there exists elements of settlement
which may be acceptable to the parties, he shall formulate the
terms of a possible settlement and submit them to the parties for
their observations. After receiving the observations of the parties,
he may re-formulate the terms of a possible settlement in the light
of such observations. If the parties reach agreement on a settlement
of the disputes, they may draw up and sign a written settlement
agreement on non-judicial stamp paper as per Stamp Act. The
Conciliator shall authenticate the settlement agreement and furnish
a copy thereof to each party. The termination of conciliation
proceedings shall be in accordance with Section 76 of The
Arbitration and Conciliation Act, 1996. No party shall be
represented before the said Conciliator by an advocate or legal
counsel. The conciliation proceedings shall be completed within 45
days from the receipt of reference. This time may be enlarged by
Signature Not Verified
Digitally Signed
By:VARNIKA
Signing Date:28.04.2026
11:21:17
ARB.P. 697/2026 Page 2 of 11
15 days by the Conciliator. The conciliation proceedings shall be
deemed to have been terminated at the end of 60 days from the
receipt of reference.
25.2 Arbitration:
If the aforesaid conciliation proceedings fail or the Conciliator fails
to give proposal for settlement within the aforesaid period, either
party may promptly give notice in the proforma prescribed in
Appendix-XVIII, under intimation to the other party, to the Chief
Engineer or the Superintending Engineer concerned with the work
(as applicable), hereinafter referred to as the Arbitrator Appointing
Authority as indicated in Schedule F, for appointment of
Arbitrator.
However, a party may seek appointment of Arbitrator without
taking recourse to the process of conciliation mentioned in
subclause 25.1 above.
In the event of either party giving a notice to the Arbitrator
Appointing Authority for appointment of Arbitrator, the said
Authority shall appoint Arbitrator as per the procedure given below
and refer such disputes to arbitration.
(a) Number of Arbitrators: If the contract amount is less than
Rs.100 crore, the disputes may be referred for adjudication by a
sole Arbitrator. If the contract amount is Rs. 100 crore or more, the
disputes may be referred to an Arbitral Tribunal of three
Arbitrators.
(b) Qualification of Arbitrators: It is a term of this contract that
each member of the Arbitral Tribunal shall be Graduate Engineer
with experience in execution of public works engineering
contracts, and he should have worked earlier at a level not lower
than the Chief Engineer (equivalent to level of Joint Secretary to
the Government of India).
The aforesaid educational qualification and work experience shall
be mandatory for appointment as Arbitrator. The age of Arbitrator
at the time of appointment shall not exceed 75 years, An Arbitrator
may be appointed notwithstanding the total number of active
arbitration cases with him.
(c) Parties to select Arbitrator: Based on the criteria specified
above, a list of empanelled Arbitrators has been prepared in PWD
and the parties shall have option to select an Arbitrator from the list
sent to them.
25.3 Appointment of Sole Arbitrator: The parties may opt for
Signature Not Verified
Digitally Signed
By:VARNIKA
Signing Date:28.04.2026
11:21:17
ARB.P. 697/2026 Page 3 of 11
appointment of the Arbitrator of the Ministry of Housing and
Urban Affairs. In such cases, the party seeking arbitration has to
submit an agreement in writing as per Appendix XIX towards
waiver of Section 12(5) of the Arbitration and Conciliation Act,
1996 along with the notice for appointment of Arbitrator in the
proforma prescribed in Appendix XVIII, under intimation to the
other party. The Arbitrator Appointing Authority shall, within 30
days of receipt of the said notice, appoint Arbitrator of the Ministry
of Housing and Urban Affairs as Arbitrator in the matter, provided
the other party also submits waiver of Section 12(5), ibid in
Appendix XIX within 7 days of the receipt of the said notice.
Where any one of the parties does not opt for the Arbitrator of the
Ministry of Housing and Urban Affairs, or does not submit the
waiver agreement, the Arbitrator Appointing Authority shall
propose five Arbitrators from the list of PWD Empanelled
Arbitrators to the party seeking arbitration under intimation to the
other party within 15 days of receiving the notice. The party
seeking arbitration shall give his choice for one of them within 15
days of receiving the list, and the Arbitrator Appointing Authority
shall appoint the chosen personas the Sole Arbitrator within 15
days of the receipt of choice.
It is a term of this arbitration agreement that if the parties fail to
select, within the period prescribed above, an Arbitrator of their
choice from the list of PWD Empanelled Arbitrators forwarded to
them, the Arbitrator Appointing Authority shall himself select and
appoint Arbitrator from the said list.
25.4 Appointment of Arbitral Tribunal of three Arbitrators:
The Arbitrator Appointing Authority shall prepare two separate
lists of five Arbitrators each from the list of PWD Empanelled
Arbitrators, and send one to the party seeking arbitration and other
to the responding party, within 15 days of the receipt of notice. The
parties will then choose any one Arbitrator from the list provided to
them within 15 days of receipt of the list, The Arbitrator
Appointing Authority shall then appoint those chosen by the
respective parties as Arbitrators and also a third Arbitrator from the
list of PWD Empanelled Arbitrators to act as presiding Arbitrator
within 15 days of receipt of choice from both the parties.
It is a term of this arbitration agreement that if the parties fail to
select, within the period prescribed above, an Arbitrator of their
choice from the list of PWD Empanelled Arbitrators forwarded to
them, the Arbitrator Appointing Authority shall himself select and
appoint Arbitrator from the said list.
25.5 Applicable Law: The provisions of the Arbitration and
Signature Not Verified
Digitally Signed
By:VARNIKA
Signing Date:28.04.2026
11:21:17
ARB.P. 697/2026 Page 4 of 11
Conciliation Act, 1996 (Act 26 of 1996) and any further statutory
modification or re-enactment thereof shall be applicable. Further,
the fast-track procedure for arbitration contained in Section 29B of
the said Act shall apply.
25.6 Fee payable to Arbitrator(s): The fee payable to the arbitral
tribunal shall be as-per CPWD OM No.2/2006/SE[TLC/CSO/137
dated 19.11.2019 (or latest amendment),decided by the Competent
Authority and shall be shared equally by both the parties.
25.7 Place of Arbitration: The place of arbitration shall preferably
be as mentioned in Schedule F.
However, the Arbitral Tribunal may decide the place in
consultation with both the parties.
25.8 Terms of reference: The Arbitral Tribunal shall adjudicate
on only such disputes as are referred to it by the Arbitrator
Appointing Authority and give separate award against each dispute
referred to him and shall give reasons for the award in all cases
where the total amount of the claim by any party exceeds
Rs.1,00,000/-.
25.9 Interest on Arbitration award: It is also a term of this
arbitration agreement that where the Arbitral award against any
dispute is for the payment of money, no pre-suit and pendent-elite
interest shall be payable on any part of the Arbitral award.”
3. The material on record further reflects that the statutory
requirement of issuing a Legal Notice under Section 21 of the Act,
invoking the aforestated Arbitration Clause, stands duly complied vide
Legal Notice dated 17.03.2026.
4. At the outset, learned counsel for the parties submit that they
are ad idem that the disputes, inter se the parties, may be referred for
adjudication by a Sole Arbitrator.
5. Learned counsel appearing on behalf of the parties would
submit that the qualification of the Arbitrator as prescribed in Clause
25.2(b) of the Agreement shall be a Graduate Engineer with
experience in execution of public works engineering contracts, and he
Signature Not Verified
Digitally Signed
By:VARNIKA
Signing Date:28.04.2026
11:21:17
ARB.P. 697/2026 Page 5 of 11
should have worked earlier at a level not lower than the Chief
Engineer (equivalent to level of Joint Secretary to the Government of
India) and pray that a learned Sole Arbitrator may be appointed who
has qualifications corresponding to the conditions as set out in the
Agreement.
6. At this juncture, it is apposite to note that the legal position
governing the scope and standard of judicial scrutiny under Section
11(6) of the Act is no longe r res integra . A three-Judge Bench of the
Hon’ble Supreme Court in SBI General Insurance Co. Ltd. v. Krish
1
Spinning , after taking into consideration the authoritative
pronouncement of the seven-Judge Bench in Interplay Between
Arbitration Agreements under Arbitration Act, 1996 & Stamp
2
Act, 1899, In re , comprehensively delineated the contours of judicial
intervention at the stage of Section 11 of the Act. The excerpt of Krish
Spg (supra ) reads as under:-
“ (c) Judicial interference under the 1996 Act
110 . The parties have been conferred with the power to decide and
agree on the procedure to be adopted for appointing arbitrators. In
cases where the agreed upon procedure fails, the courts have been
vested with the power to appoint arbitrators upon the request of a
party, to resolve the deadlock between the parties in appointing the
arbitrators.
111 . Section 11 of the 1996 Act is provided to give effect to the
mutual intention of the parties to settle their disputes by arbitration
in situations where the parties fail to appoint an arbitrator(s). The
parameters of judicial review laid down for Section 8 differ from
those prescribed for Section 11. The view taken in SBP &
Co. v. Patel Engg. Ltd., (2005) 8 SCC 618 and affirmed in Vidya
Drolia v. Durga Trading Corpn., (2021) 2 SCC 1 that Sections 8
and 11, respectively, of the 1996 Act are complementary in nature
was legislatively overruled by the introduction of Section 11(6-A)
in 2015. Thus, although both these provisions intend to compel
parties to abide by their mutual intention to arbitrate, yet the scope
1
(2024) 12 SCC 1
2
(2024) 6 SCC 1
Signature Not Verified
Digitally Signed
By:VARNIKA
Signing Date:28.04.2026
11:21:17
ARB.P. 697/2026 Page 6 of 11
of powers conferred upon the courts under both the sections are
different.
112 . The difference between Sections 8 and 11, respectively, of the
1996 Act is also evident from the scope of these provisions. Some
of these differences are:
112.1 . While Section 8 empowers any “judicial authority” to refer
the parties to arbitration, under Section 11, the power to refer has
been exclusively conferred upon the High Court and the Supreme
Court.
112.2 . Under Section 37, an appeal lies against the refusal of the
judicial authority to refer the parties to arbitration, whereas no such
provision for appeal exists for a refusal under Section 11.
112.3 . The standard of scrutiny provided under Section 8 is that of
prima facie examination of the validity and existence of an
arbitration agreement. Whereas, the standard of scrutiny under
Section 11 is confined to the examination of the existence of the
arbitration agreement.
112.4 . During the pendency of an application under Section 8,
arbitration may commence or continue and an award can be passed.
On the other hand, under Section 11, once there is failure on the
part of the parties in appointing the arbitrator as per the agreed
procedure and an application is preferred, no arbitration
proceedings can commence or continue.
113 . The scope of examination under Section 11(6-A) is confined
to the existence of an arbitration agreement on the basis of Section
7. The examination of validity of the arbitration agreement is also
limited to the requirement of formal validity such as the
requirement that the agreement should be in writing.
114 . The use of the term “examination” under Section 11(6-A) as
distinguished from the use of the term “rule” under Section 16
implies that the scope of enquiry under Section 11(6-A) is limited
to a prima facie scrutiny of the existence of the arbitration
agreement, and does not include a contested or laborious enquiry,
which is left for the Arbitral Tribunal to “rule” under Section 16.
The prima facie view on existence of the arbitration agreement
taken by the Referral Court does not bind either the Arbitral
Tribunal or the Court enforcing the arbitral award.
115 . The aforesaid approach serves a twofold purpose — firstly, it
allows the Referral Court to weed out non-existent arbitration
agreements, and secondly, it protects the jurisdictional competence
of the Arbitral Tribunal to rule on the issue of existence of the
arbitration agreement in depth.
117 . In view of the observations made by this Court in Interplay
Between Arbitration Agreements under the Arbitration Act, 1996
& the Stamp Act, 1899, In re, (2024) 6 SCC 1 , it is clear that the
scope of enquiry at the stage of appointment of arbitrator is limited
Signature Not Verified
Digitally Signed
By:VARNIKA
Signing Date:28.04.2026
11:21:17
ARB.P. 697/2026 Page 7 of 11
to the scrutiny of prima facie existence of the arbitration
agreement, and nothing else. For this reason, we find it difficult to
hold that the observations made in Vidya Drolia v. Durga Trading
Corpn., (2021) 2 SCC 1 and adopted in NTPC Ltd. v. SPML Infra
Ltd. , (2023) 9 SCC 385 that the jurisdiction of the Referral Court
when dealing with the issue of “accord and satisfaction” under
Section 11 extends to weeding out ex facie non-arbitrable and
frivolous disputes would continue to apply despite the subsequent
decision in Interplay Between Arbitration Agreements under the
Arbitration Act, 1996 & the Stamp Act, 1899, In re, (2024) 6 SCC
1.
119 . The question of “accord and satisfaction”, being a mixed
question of law and fact, comes within the exclusive jurisdiction of
the Arbitral Tribunal, if not otherwise agreed upon between the
parties. Thus, the negative effect of competence-competence would
require that the matter falling within the exclusive domain of the
Arbitral Tribunal, should not be looked into by the Referral Court,
even for a prima facie determination, before the Arbitral Tribunal
first has had the opportunity of looking into it.
120 . By referring disputes to arbitration and appointing an
arbitrator by exercise of the powers under Section 11, the Referral
Court upholds and gives effect to the original understanding of the
contracting parties that the specified disputes shall be resolved by
arbitration. Mere appointment of the Arbitral Tribunal does not in
any way mean that the Referral Court is diluting the sanctity of
“accord and satisfaction” or is allowing the claimant to walk back
on its contractual undertaking. On the contrary, it ensures that the
principle of arbitral autonomy is upheld and the legislative intent of
minimum judicial interference in arbitral proceedings is given full
effect. Once the Arbitral Tribunal is constituted, it is always open
for the defendant to raise the issue of “accord and satisfaction”
before it, and only after such an objection is rejected by the
Arbitral Tribunal, that the claims raised by the claimant can be
adjudicated.
121 . Tests like the “eye of the needle” and “ex facie meritless”,
although try to minimise the extent of judicial interference, yet they
require the Referral Court to examine contested facts and
appreciate prima facie evidence (however limited the scope of
enquiry may be) and thus are not in conformity with the
principles of modern arbitration which place arbitral autonomy and
judicial non-interference on the highest pedestal.
122 . Appointment of an Arbitral Tribunal at the stage of Section 11
petition also does not mean that the Referral Courts forego any
scope of judicial review of the adjudication done by the Arbitral
Tribunal. The 1996 Act clearly vests the national courts with the
power of subsequent review by which the award passed by an
Signature Not Verified
Digitally Signed
By:VARNIKA
Signing Date:28.04.2026
11:21:17
ARB.P. 697/2026 Page 8 of 11
arbitrator may be subjected to challenge by any of the parties to the
arbitration.
*
126 . The power available to the Referral Courts has to be construed
in the light of the fact that no right to appeal is available against
any order passed by the Referral Court under Section 11 for either
appointing or refusing to appoint an arbitrator. Thus, by delving
into the domain of the Arbitral Tribunal at the nascent stage of
Section 11, the Referral Courts also run the risk of leaving the
claimant in a situation wherein it does not have any forum to
approach for the adjudication of its claims, if its Section 11
application is rejected.
127 . Section 11 also envisages a time-bound and expeditious
disposal of the application for appointment of arbitrator. One of the
reasons for this is also the fact that unlike Section 8, once an
application under Section 11 is filed, arbitration cannot commence
until the Arbitral Tribunal is constituted by the Referral Court. This
Court, on various occasions, has given directions to the High
Courts for expeditious disposal of pending Section 11 applications.
It has also directed the litigating parties to refrain from filing bulky
pleadings in matters pertaining to Section 11. Seen thus, if the
Referral Courts go into the details of issues pertaining to “accord
and satisfaction” and the like, then it would become rather difficult
to achieve the objective of expediency and simplification of
pleadings.
128 . We are also of the view that ex facie frivolity and dishonesty
in litigation is an aspect which the Arbitral Tribunal is equally, if
not more, capable to decide upon the appreciation of the evidence
adduced by the parties. We say so because the Arbitral Tribunal
has the benefit of going through all the relevant evidence and
pleadings in much more detail than the Referral Court. If the
Referral Court is able to see the frivolity in the litigation on the
basis of bare minimum pleadings, then it would be incorrect to
doubt that the Arbitral Tribunal would not be able to arrive at the
same inference, most likely in the first few hearings itself, with the
benefit of extensive pleadings and evidentiary material.”
(emphasis supplied)
7. The decision in Krish Spinning (supra) thus unequivocally
reiterates that the Referral Court, while exercising jurisdiction under
Section 11 of the Act, is required to confine itself to a prima facie
examination of the existence of a valid Arbitration Agreement and
nothing beyond. The Court’s role is facilitative and
Signature Not Verified
Digitally Signed
By:VARNIKA
Signing Date:28.04.2026
11:21:17
ARB.P. 697/2026 Page 9 of 11
procedural, namely , to give effect to the parties’ agreed mechanism of
dispute resolution when it has failed, without embarking upon an
adjudication of contentious factual or legal issues, which are reserved
for the Arbitral Tribunal.
8. In view of the law as laid down by the Hon’ble Supreme Court
in Krish Spinning (supra) , the scope of this Court’s jurisdiction under
Section 11 of the Act is extremely circumscribed. All the contentions
sought to be raised herein are matters that can appropriately be urged
before the learned Arbitrator, who is legally empowered and
competent to adjudicate upon the same.
9. At this stage, having considered the submissions advanced, the
material placed on record and the consent accorded by both the
parties, this Court is of the view that the disputes between the parties
warrant reference to arbitration, and that it would be appropriate to
appoint a Sole Arbitrator for adjudication of the disputes inter se the
parties.
10. Material on record indicates that the valuation of the subject
matter of the disputes is stated to be approximately Rs. 50,00,000/-.
11. Accordingly, this Court hereby requests Mr. Anand Kumar,
Chief Engineer, (e-mail : [email protected] and Mobile
No. 9716753377), to enter upon the reference and adjudicate the
disputes inter se the parties.
12. The learned Arbitrator may proceed with the arbitration
proceedings, subject to furnishing to the parties the requisite
disclosures as required under Section 12(2) of the A&C Act.
13. The learned Arbitrator shall be entitled to a fee in accordance
with the Fourth Schedule of the A&C Act or as may otherwise be
Signature Not Verified
Digitally Signed
By:VARNIKA
Signing Date:28.04.2026
11:21:17
ARB.P. 697/2026 Page 10 of 11
agreed to between the parties and the learned Arbitrator.
14. The parties shall share the learned Arbitrator’s fee and arbitral
costs equally.
15. All rights and contentions of the parties in relation to the
claims/counter claims are kept open, to be decided by the learned
Arbitrator on their merits, in accordance with law.
16. Needless to state, nothing in this order shall be construed as an
expression of opinion of this Court on the merits of the controversy.
17. Let the copy of the said order be sent to the learned Arbitrator
through all permissible modes, including electronic mode as well.
18. Accordingly, the present Petition stands disposed of in the
aforesaid terms.
HARISH VAIDYANATHAN SHANKAR, J.
APRIL 23, 2026/tk/va